CAPITAL IMPROVEMENT PROGRAM

Size: px
Start display at page:

Download "CAPITAL IMPROVEMENT PROGRAM"

Transcription

1 CAPITAL IMPROVEMENT PROGRAM Public Work Session No. 2 Project Narrative Submittal December 18, 2017 Prepared for: HALLSVILLE R-IV SCHOOL DISTRICT 421 East Highway 124 Hallsville, MO Prepared by: KLINGNER & ASSOCIATES, P.C. 907 E. Ash Street Columbia, MO Project No Quincy, IL Galesburg, IL Burlington, IA Pella, IA Columbia, MO Hannibal, MO

2 Capital Improvement Program Hallsville R-IV School District Project No CAPITAL IMPROVEMENT PROGRAM BACKGROUND On November 27, 2017 Klingner & Associates, P.C. (Klingner) participated in the First Public Work Session hosted by the Hallsville R-IV School District (District) for the District s capital improvement program. Klingner provided a brief overview followed by breakout discussion session of the initially identified projects for the capital improvement program including: Construction of a wing at the Hallsville Primary School Construction of a gymnasium at the Hallsville Primary School Construction of an athletic track at the Hallsville football stadium Renovations to the Hallsville Middle School, including potential demolition and reconstruction of a wing Following the First Public Work Session, Superintendent John Downs provided Klingner with direction on how to proceed with project development based on public and school board member feedback. The feedback provided my Mr. Downs to Klingner is summarized as follows: Athletic Track No further consideration is necessary for relocating or reconditioning the track at this point in time.

3 Capital Improvement Program Hallsville R-IV School District Project No Primary School The primary school is most likely going to be the focus area of the current bond issue Include an eight-classroom addition on the northwest corner of the building Include a two-classroom addition on the west end of the first-grade wing Include a two-classroom addition on the southwest corner of the kindergarten wing Include a gym on the east side of the building including: o Seating for spectators o Exterior entry from parking area o Modest concession area o Public restrooms o Four locker rooms o Wrestling practice room. Mr. Downs noted that the wrestling room would only be used for practice and to stick with basic construction and features Mr. Downs requested additional information on the cost differences between standard construction methods and storm-resistant construction Mr. Downs requested that the cost of the locker rooms and the wrestling room be broken out separately. Mr. Downs requested a detailed building cost breakdown including design and bonding fees Middle School Although sufficient bond funds are not available within the current bond issue to address both the primary school and middle school, Mr. Downs requested that Klingner develop a master plan to address the issues with the middle school. Mr. Downs indicated that the District might not ever have or may not want to spend the estimated $12 million dollars necessary to build a completely new middle school and asked that Klingner develop a phased approach to addressing the middle school issues via a series of smaller projects.

4 Capital Improvement Program Hallsville R-IV School District Project No PRIMARY SCHOOL Appendix 1 contains two different concepts for the Primary School. A brief summary of the various project areas and the similarities and differences between the two concepts is presented below: Eight-Classroom Addition on North West Corner The major difference between the two concepts is the location of the restrooms. Concept A places the restrooms on the end of the corridor while Concept B places them in the middle of the corridor. Both concepts are configured to allow additional expansion to the west if necessary in the future. The estimated cost for this wing is $2,620,000 for both Concept A and Concept B. Two-Classroom Expansion on the End of First-Grade Wing The major difference between the two concepts is that Concept B is configured to support future expansion to the west while Concept A is not. As Concept A does not incorporate corridor space, the amount of usable classroom space is larger for Concept B. The estimated costs for Concept A is $500,000 and Concept B is $575,000. Two-Classroom Expansion on the West Side of the Kindergarten Wing The proposed Kindergarten Wing expansion is the same for both Concept A and Concept B and the estimated cost for this expansion is $691,000.

5 Capital Improvement Program Hallsville R-IV School District Project No Gymnasium Addition Both gymnasium concepts incorporate a mezzanine constructed above the ancillary gymnasium support rooms. The mezzanine provides space for additional bleacher seating and also provides a wrestling practice area in Concept B. The concrete floor of the mezzanine also serves as the roof structure for the lobby, restrooms, etc located adjacent to the gymnasium. The use of a concrete roof combined with other appropriate construction techniques will allow this space to serve as a severe weather shelter area. The major differences between the two concepts include: Concept B incorporates a wrestling practice area Concept B incorporates four locker rooms Concept B has the potential of serving as a severe weather shelter for a greater number of people. Concept B has a larger overall building footprint to incorporate the above listed features and its estimate of cost of $3,417,000 is higher than the Concept A estimate of cost of $2,634,000. As the mezzanine concept was developed to address several different design goals including: additional spectator seating, wrestling practice area, and a storm shelter, it is difficult to quantify the amount of cost directly attributed to the inclusion any one of these features. However, the difference in cost between Concept A and Concept B ($783,000) can be considered a general indication of the total additional cost for these features. Primary School Cost Summary Concept A Concept B 8-Classroom Wing (2 nd Grade): $2,620,000 $2,620,000 2-Classroom Addition (1 st Grade): $500,000 $575,000 8-Classroom Addition (Kindergarten): $500,000 $575,000 Gymnasium Addition: $2,634,000 $3,417,000 Total $6,445,000 $7,303,000

6 Capital Improvement Program Hallsville R-IV School District Project No MIDDLE SCHOOL A multi-phase development option for the middle school is presented in Appendix 2. A brief description of the construction phases is presented below: Phase 1 In the initial phase, the current administration office area would be demolished allowing for the construction of a new classroom wing and central office area. This phase also includes the construction of a corridor connection to the science wing and intermediate school to improve building connectivity and campus security. The entrance next to the administration office would become the main entry point for visitors to the school and can be easily monitored by school administration to improve campus security. The front façade of the new addition will become the focal point for those entering the school and various aesthetic enhancements are possible to add prominence and instill school pride to students and visitors entering the campus through this entrance. A media center is planned for the new wing to facilitate moving of the media center from its current location to allow for band room relocation and kitchen expansion in subsequent phases. Once the proposed construction is complete, existing middle school classrooms can be relocated to the new classroom space to facilitate future middle school phases. The anticipated cost of Phase 1 work including demolition and proposed construction is $3,822,000. Phase 2 In this phase the current kitchen and cafeteria will be expanded to address current capacity constraints within the kitchen/cafeteria. Currently five lunch shifts are used to serve the high school and middle school students. This many lunch shifts causes some students to eat much earlier/later than normal lunch times. Increasing the size of the kitchen/cafeteria will allow a greater number of students to eat within a lunch shift to reduce the amount of lunch shifts required. The anticipated cost of Phase 2 work including demolition and proposed construction is $1,135,0000. It is important to note that although this is listed as Phase 2, the only prerequisite to allow proceeding with this work is the relocation of the band room and no subsequent work is dependent on this phase. Therefore, moving this phase up or back based on District priorities can be achieved with relative ease. As the kitchen is critical to the operation of the school, kitchen expansion work would have to occur during summer recess.

7 Capital Improvement Program Hallsville R-IV School District Project No Phase 3 In this phase the existing southern wing of the middle school will be demolished and a new middle school wing constructed. The new middle school wing will incorporate larger classrooms, larger corridors, and modern classroom amenities as compared to the current middle school. The classroom wing will be moved north to allow for more parking on the south side of the wing. The classrooms housed in this wing will have been previously relocated following Phase 1 and temporary classrooms are not anticipated to be needed to facilitate this work. The south elevation of this wing would be designed to compliment the campus entry constructed in Phase 1 and further increase the visual impact of the school from the south parking/entry area. The anticipated cost of Phase 3 work including demolition and proposed construction is $3,566,000. Phase 4 In this phase the existing northern wing of the middle school will be demolished and new middle school classrooms constructed. Five classrooms are shown within the attached exhibit but various other classroom quantities, sizes and configurations could be developed based on the needs of the District at that point in time. Based on the exact configuration of the classrooms constructed and the phasing of demolition/construction, temporary classrooms may or may not be necessary with this phase of work. The anticipated cost of Phase 4 work including demolition and proposed construction is $1,720,000. Middle School Cost Summary Phase 1: $3,822,000 Phase 2: $1,135,000 Phase 3: $3,566,000 Phase 4: $1,720,000 Total: $10,243,000 It should be noted that the estimated costs for the Middle School work is less than the $11-$12 million estimate presented at the First Public Meeting. The reason for this discrepancy is that the Middle School concept presented at the First Public Meeting represented a larger building area than the current Middle School area to account for future District growth. The phased approach presented within this document represents replacement of current facilities and does not account for future growth. If the District experiences significant growth, the development plan would have to be adjusted to account for this growth.

8 Capital Improvement Program Hallsville R-IV School District Project No PROJECT SEQUENCING As discussed during the First Public Meeting, the most pressing need is additional classroom and gym space at the Primary School. Both Concept A and Concept B can be completed within the $8 million bond limit and proceeding with the work at the Primary School appears to be the most logical choice. As additional bond capacity becomes available, proceeding with the middle school according to the phases presented in this report is recommend. Timing of the phases will have to be coordinated with school schedules and bond capacity but it would be possible to combine phases into a common phase to speed up overall project delivery if desired. 5.0 COST ESTIMATES Klingner utilized an estimate of $235 per square foot for the cost of the various campus improvements. This estimate is inclusive of anticipated bond origination fees, design fees, and construction costs. Appendix 3 includes a detailed description of the various cost components included within the $235/SF estimate. Movable furniture, fixtures, and other equipment (FF&E) are not included within the cost estimate as these items are not typically included within construction contracts. The one exception to the $235/SF estimate is the kitchen which is estimated at $245/SF to account for the cost of kitchen equipment. The estimated costs are representative for a project constructed in It is not known with certainty when the various work items will be constructed but construction prices generally increase over time and the associated costs of this work are expected to increase for work completed following

9 Capital Improvement Program Hallsville R-IV School District Project No Appendix 1

10 6" 6" 4"PVC 4"PVC 8"CPP 6"PVC CPP 8" Quincy, IL Galesburg, IL Hannibal, MO Burlington, IA Pella, IA 4"PVC Columbia, Missouri 907 East Ash Street ' KLINGNER S GYMNASIUM PRIMARY SCHOOL PRIMARY SCHOOL CONCEPTS 30' SCALE: 1" = 30' 0 S S

11 KITCHEN COMMONS SAFEROOM CAPACITY: 220 STANDING AND 2 WHEELCHAIR SPACES BUILDING POPULATION: SF 777 SF 777 SF 783 SF 242 SF GIRL'S 232 SF BOY'S 244 SF BOY'S GIRL'S DRY AGE 26 SF 26 SF 26 SF 26 SF GEN. 54 SF MECH. 121 SF AGE AGE 242 SF 783 SF 777 SF 777 SF 783 SF RESOURCE 495 SF MUSIC COMPUTER LOUNGE BOYS 241 SF GIRLS 241 SF KITCHEN AGE 200 SEATS GYMNASIUM 8,369 SF LOBBY 1,011 SF AT-RISK 906 SF JANITOR 1ST GRADE 1ST GRADE 1ST GRADE RESOURCE JANITOR MEDIA CENTER CONFERENCE CONCESS. 92 SF CONCESS.. 42 SF 200 SEATS 28 SF 28 SF. 153 SF AGE 906 SF GIRL'S BOY'S 1ST GRADE 1ST GRADE 1ST GRADE AGE ART GIRL'S BOY'S TITLE I SPECIAL EDUCATION DOWN ADDITION LEGEND KINDERGARTEN KINDERGARTEN EIGHT 2ND GRADE ADDITION - $2,620,000 TWO 1ST GRADE ADDITION - $500, SEATS TWO KINDERGARTEN ADDITION - $691,000 GYMNASIUM ADDITION - $2,634,000 KINDERGARTEN KINDERGARTEN MEZZANINE 2,421 SF GYMNASIUM (OPEN TO BELOW) 200 SEATS KINDERGARTEN KINDERGARTEN 895 SF 150 SF DOWN TLT 53 SF MEZZANINE PLAN TLT 53 SF 895 SF 150 SF PRE-KINDERGARTEN OFFICE PRE-KINDERGARTEN PRIMARY SCHOOL FLOOR PLAN: CONCEPT 'A' KLINGNER Columbia, Missouri 907 East Ash Street Quincy, IL Galesburg, IL Hannibal, MO Burlington, IA Pella, IA

12 KITCHEN COMMONS SAFEROOM CAPACITY: 590 STANDING AND 3 WHEELCHAIR SPACES 783 SF 783 SF GIRL'S 235 SF BOY'S 240 SF 783 SF 783 SF 242 SF BOY'S GIRL'S DRY AGE BUILDING POPULATION: SF 26 SF 26 SF 26 SF AGE LOCKER ROOM 460 SF LOCKER ROOM 460 SF 783 SF 783 SF INTERVENTION 584 SF 783 SF 783 SF RESOURCE 427 SF MUSIC COMPUTER LOUNGE KITCHEN AGE LOCKER ROOM 460 SF LOCKER ROOM 460 SF 200 SEATS JAN. 117 SF OFFICE 119 SF OFFICE 119 SF TRAINING 117 SF AT-RISK CONCESS. 96 SF GYMNASIUM 7,989 SF 787 SF 26 SF 158 SF 1ST GRADE 1ST GRADE 1ST GRADE RESOURCE AGE JANITOR MEDIA CENTER CONFERENCE GEN. RM. 91 SF GIRL'S 257 SF BOY'S 257 SF MECH. 210 SF CONCESS.. 59 SF LOBBY 1,809 SF. 208 SF 200 SEATS 787 SF GIRL'S BOY'S 234 SF 234 SF 1ST GRADE 1ST GRADE 1ST GRADE AGE ART GIRL'S BOY'S TITLE I SPECIAL EDUCATION DOWN KINDERGARTEN KINDERGARTEN ADDITION LEGEND EIGHT 2ND GRADE ADDITION - $2,620, SEATS TWO 1ST GRADE ADDITION TWO KINDERGARTEN ADDITION GYMNASIUM ADDITION - $575,000 - $690,000 - $3,417,000 KINDERGARTEN KINDERGARTEN WRESTLING MEZZANINE 6,069 SF GYMNASIUM (OPEN TO BELOW) KINDERGARTEN KINDERGARTEN 895 SF 150 SF TLT 53 SF 200 SEATS: IN. STACKED POSITION DOWN TLT 53 SF MEZZANINE PLAN - WRESTLING ROOM 895 SF 150 SF PRE-KINDERGARTEN OFFICE PRE-KINDERGARTEN PRIMARY SCHOOL FLOOR PLAN: CONCEPT 'B' KLINGNER Columbia, Missouri 907 East Ash Street Quincy, IL Galesburg, IL Hannibal, MO Burlington, IA Pella, IA

13 Capital Improvement Program Hallsville R-IV School District Project No Appendix 2

14 NORTH RICKETTS ROAD MIDDLE SCHOOL RENOVATION/ADDITION MAIN ENTRANCE NOTE: NEW ADDITIONS MOVED NORTH TO ALLOW FOR ADDITIONAL PARKING MIDDLE SCHOOL CONCEPTS KLINGNER 0 30' SCALE: 1" = 30' 60' Columbia, Missouri 907 East Ash Street Quincy, IL Galesburg, IL Hannibal, MO Burlington, IA Pella, IA

15

16

17

18

19

20

21

22

23 Capital Improvement Program Hallsville R-IV School District Project No Appendix 3

24 Opinion of Project/Construction Costs Date 12/18/17 Eng Proj # Estimate by JJN Checked by HALLSVILLE R-IV SCHOOL DIST. Project: CAPITAL IMPROVEMENT NO ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL COST SUBSTRUCTURE FOUNDATION 1 SF $ 5.00 $ 5.00 SLAB ON GRADE 1 SF $ 6.75 $ 6.75 EXCAVATION 1 SF $ 1.00 $ 1.00 BASEMENT WALLS 1 SF $ 3.85 $ 3.85 SUPERSTRUCTURE FLOOR CONSTRUCTION 1 SF $ 2.33 $ 2.33 ROOF CONSTRUCTION 1 SF $ $ EXTERIOR ENCLOSURE EXTERIOR WALLS 1 SF $ $ EXTERIOR WINDOWS 1 SF $ 8.62 $ 8.62 EXTERIOR DOORS 1 SF $ 2.68 $ 2.68 ROOFING ROOF COVERINGS 1 SF $ 7.00 $ 7.00 ROOF OPENINGS 1 SF $ 0.25 $ 0.25 INTERIORS PARTITIONS 1 SF $ 6.00 $ 6.00 INTERIOR DOORS 1 SF $ 1.67 $ 1.67 FITTINGS 1 SF $ 6.42 $ 6.42 WALL FINISHES 1 SF $ 3.75 $ 3.75 FLOOR FINISHES 1 SF $ 9.56 $ 9.56 CEILING FINISHES 1 SF $ 7.22 $ 7.22 CASEWORK 1 SF $ 9.50 $ 9.50 PLUMBING PLUMBING FIXTURES 1 SF $ 8.00 $ 8.00 DOMESTIC WATER DISTRIBUTION 1 SF $ 1.00 $ 1.00 ROOF DRAINS 1 SF $ 1.00 $ 1.00 HVAC HVAC SYSTEM AND EQUIPMENT 1 SF $ $ FIRE SUPRRESSION WET PIPE FIRE SPRINKLER SYSTEM 1 SF $ 3.00 $ 3.00 ELECTRICAL ELECTRIC DISTRIBUTION 1 SF $ 3.00 $ 3.00 LIGHTING AND BRANCH CIRCUITS 1 SF $ $ COMMUNICATIONS AND SECURITY 1 SF $ 4.00 $ 4.00 OTHER SQUARE FOOT COSTS BONDING FEES 1 SF $ 4.07 $ 4.07 CONTRACTOR FEES 1 SF $ $ ARCHITECT/ENGINEERING FEES 1 SF $ $ CONTINGENCY 1 SF $ $ BUILDING COST PER SQUARE FOOT $ Sheet 1 of 1 Form 450 Updated 08/30/12

OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN

OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN KBE APPROVAL DATE: APRIL 2013 including Finding #1 g g OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN PLAN OF SCHOOL ORGANIZATION 1. Current Plan PS, K-5, 6-8, 9-12 2. Long Range Plan PS, K-5, 6-8, 9-12

More information

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic GENERAL SITE PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS Scope of work narrative Building code review Description of construction Documentation on drawings as List of applicable

More information

1001 Feehanville Drive Phone Mt. Prospect, IL Fax

1001 Feehanville Drive Phone Mt. Prospect, IL Fax NICHOLAS & ASSOCIATES, INC. 1001 Feehanville Drive Phone 847.394.6200 Mt. Prospect, IL 60056 Fax 847.394.6205 November 29, 2016 Community Unit School District 200 130 West Park Avenue Wheaton, IL 60189

More information

Continuing Education Credit

Continuing Education Credit BIM + CM-at-RISK = Saves You Time & $$$ Especially on Renovation Projects PeterMcElwain,AIA ArtCampbell,AIA Facilities/Planning RickScott,LEEDAP,CPC JohnCook.CPC CM-at-Risk/Construction JenniferS.Henrikson,AIA,LEEDAP

More information

Central High School. 275 Lexington Parkway North. Project Summary: Issues Identified By School Community In 2015

Central High School. 275 Lexington Parkway North. Project Summary: Issues Identified By School Community In 2015 275 Lexington Parkway North Project Summary: Central is the oldest high school in the state of Minnesota, beginning its 150th year. Its rich traditions, including academic excellence, are widely celebrated.

More information

ouglas Intermediate School

ouglas Intermediate School ouglas Intermediate School DOUGLAS INTERMEDIATE/ELEMENTARY SCHOOL Board of Selectmen / Finance Committee February 15, 2011 DiNisco Design www.dinisco.com Site Discussion Site Discussion Site Discussion

More information

COMPONENT FLOW CHART & SEQUENCING DIAGRAMS

COMPONENT FLOW CHART & SEQUENCING DIAGRAMS Oak Park and River Forest High School Master Facilities Plan COMPONENT FLOW CHART & SEQUENCING DIAGRAMS The following is a narrative intended to accompany the component flow chart and sequencing diagrams

More information

Harding Senior High School

Harding Senior High School 1540 Sixth Street East Project Summary:, located in the Eastview area of St. Paul, offers students in grades 9 through 12 a wide range of curriculum options ranging from International Baccalaureate to

More information

Horace Mann Elementary

Horace Mann Elementary 2001 Eleanor Avenue Project Summary: Horace Mann is a neighborhood school filled with students who are excited to be here taught by teachers who transform excitement into achievement. Expectations are

More information

Mahalia Jackson Elementary School 917 W 88th St Chicago, IL 60620

Mahalia Jackson Elementary School 917 W 88th St Chicago, IL 60620 W 88th St Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

11/29/12. Des Moines Social Club Urban Design Review Project Narrative

11/29/12. Des Moines Social Club Urban Design Review Project Narrative 11/9/1 Des Moines Social Club Urban Design Review Project Narrative Strategically located at 9th and Walnut, the Des Moines Social Club (DMSC) will become a critical link between the Court Avenue Entertainment

More information

AUBURN VILLAGE SCHOOL ADDITION & RENOVATION Executive Team Meeting Minutes

AUBURN VILLAGE SCHOOL ADDITION & RENOVATION Executive Team Meeting Minutes AUBURN VILLAGE SCHOOL ADDITION & RENOVATION Executive Team Meeting Minutes Meeting No. 4 Date: 5/12/2018 Job No. Meeting Location: AVS Conference Room The following notes were taken during a meeting on

More information

Exhibit A Project Identification. Exhibit B Project Charter / Project Intent. Exhibit C Project Scope. Exhibit C Project Schedule

Exhibit A Project Identification. Exhibit B Project Charter / Project Intent. Exhibit C Project Scope. Exhibit C Project Schedule Exhibit A Project Identification Exhibit B Project Charter / Project Intent Exhibit C Project Scope Exhibit C Project Schedule Exhibit D Project Budget Exhibit E Owner Supplied Documents Exhibit F Sample

More information

Huntington Beach City School District. M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y

Huntington Beach City School District. M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y Huntington Beach City School District M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y 0 1 7 Agenda 1. Where are we in the process?. Measure Q Bond Program

More information

CS2.0 COVER SHEET VOL. 2

CS2.0 COVER SHEET VOL. 2 ARCHITECT GEORGE CROMWELL ELEMENTARY SCHOOL REVITALIZATION 525 Wellham Avenue Glen Burnie, Maryland 21061 OWNER ANNE ARUNDEL COUNTY PUBLIC SCHOOLS 9034 FT. SMALLWOOD ROAD PASADENA, MARYLAND 21122 tel:

More information

Wendell Smith Elementary School

Wendell Smith Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Wendell E Green Elementary School 1150 W 96th St Chicago, IL 60643

Wendell E Green Elementary School 1150 W 96th St Chicago, IL 60643 11 W 9th St Chicago, IL 3 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

STEM Magnet Academy. Definitions EXTERIOR W Fillmore St Chicago, IL 60607

STEM Magnet Academy. Definitions EXTERIOR W Fillmore St Chicago, IL 60607 Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

SCARSDALE PUBLIC SCHOOLS

SCARSDALE PUBLIC SCHOOLS SCARSDALE PUBLIC SCHOOLS GREENACRES FEASIBILITY STUDY PROGRESS REPORT BOARD OF EDUCATION Mary Beth Gose Leila Shames Maude Lewis Leone, Jr. Christopher Morin William Natbony Suzanne Seiden Scott E. Silberfein

More information

Marcus Moziah Garvey Elementary School S Morgan St Chicago, IL 60643

Marcus Moziah Garvey Elementary School S Morgan St Chicago, IL 60643 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item

More information

Langston Hughes Elementary School

Langston Hughes Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

State College Area School District

State College Area School District State College Area School District The following is a guideline for project design submittals to the Facility Committee of the State College Area School District. During the design process the committee

More information

FAYETTE COUNTY SCHOOLS DISTRICT FACILITY PLAN

FAYETTE COUNTY SCHOOLS DISTRICT FACILITY PLAN KBE APPROVAL DATE: APRIL 2017 FAYETTE COUNTY SCHOOLS DISTRICT FACILITY PLAN DFP REVISIONS FINDING. NO. 1: APRIL 2018 BOLD NEXT DFP DUE: APRIL 2021 PLAN OF SCHOOL ORGANIZATION 1. Current Plan P, P-5, K-5,

More information

March 23, 2015 Total Project Cost 18,553,027

March 23, 2015 Total Project Cost 18,553,027 Executive Summary Charles City CSD Middle School Addition 25% CD Up April 3, 205 Project Approach This up to be considered recap of changes since March 23, 205 budget. It is intended to reflect significant

More information

John Milton Gregory Elementary School

John Milton Gregory Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Jackie Robinson Elementary School

Jackie Robinson Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Everett McKinley Dirksen Elementary School

Everett McKinley Dirksen Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Josefa Ortiz De Dominguez Elementary School 3000 S Lawndale Ave Chicago, IL 60623

Josefa Ortiz De Dominguez Elementary School 3000 S Lawndale Ave Chicago, IL 60623 3000 S Lawndale Ave Chicago, IL 023 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This

More information

DRAFT FOR INTERNAL DISCUSSION ONLY

DRAFT FOR INTERNAL DISCUSSION ONLY Jameson St. 2 Riser Room Cistern Base Men's Locker Room Women's Locker Room Mud Room Stair Elev. Entry Lobby Shipping and Receiving Stair EO/IO Breakdown A40 Shop / Warehouse Alley Gilman Pl. Storage Room

More information

ADDENDUM #2 September 12, 2018

ADDENDUM #2 September 12, 2018 Physical Plant Services Project Management 1000 Rim Drive Phone: (970) 247-7523 Fax: (970) 247-7555 Project No. 2007-130P18 Whalen Gymnasium Expansion and Renovation for Exercise Science Request for Qualifications

More information

Amos Alonzo Stagg Elementary School

Amos Alonzo Stagg Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

BASEBALL PLAYER FACILITIES CLEMSON, SOUTH CAROLINA

BASEBALL PLAYER FACILITIES CLEMSON, SOUTH CAROLINA THROUGH THE YEARS THROUGH THE YEARS VIEW FROM RIGHT FIELD VIEW FROM DUGOUT VIEW FROM NEW GRANDSTAND EXISTING CONDITIONS EXTERIOR PHOTOS PLAYER S LOUNGE LOCKER ROOM TRAINING AREA COACH S OFFICE CORRIDOR

More information

Marcus Moziah Garvey Elementary School

Marcus Moziah Garvey Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

MODEL SETUP FOR RENOVATION PROJECTS INSTRUCTIONS AND TUTORIALS

MODEL SETUP FOR RENOVATION PROJECTS INSTRUCTIONS AND TUTORIALS MODEL SETUP FOR RENOVATION PROJECTS INSTRUCTIONS AND TUTORIALS WHAT S INSIDE INTRODUCTION 1 PART ONE LAYERS AND CLASSES FOR RENOVATION PROJECT 1 OVERVIEW 1 SETTING UP LAYERS AND CLASSES 1 CREATING OBJECT

More information

ADDENDUM #1. April 29, 2009

ADDENDUM #1. April 29, 2009 April 29, 2009 Re: HACC, Central Pennsylvania s Community College Midtown 1 CCTA Phase 2 Solicitation # 09-17 From: Eastern pcm, LLC Construction Manager HACC 212 Locust Street, Suite 604 Harrisburg, PA

More information

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO PAGE PROJECT NO. 0-0 0 0 0 0 0 DATE: PROJECT: GATEWAY STEM ATHLETICE FIELD ALTERATIONS GATEWAY STEM HIGH SCHOOL - ST. LOUIS PUBLIC SCHOOLS 0 MCRTEE AVENUE ST. LOUIS, MISSOURI 0 TO BID DOCUMENTS DATED DECEMBER,

More information

Adams Spanish Immersion 615 Chatsworth Street South

Adams Spanish Immersion 615 Chatsworth Street South Project Summary: Adams Spanish Immersion is an international education without the travel expense. Our school is a place where families and staff value the opportunities gained from learning a second language.

More information

Joseph E Gary Elementary School 3740 W 31st St Chicago, IL 60623

Joseph E Gary Elementary School 3740 W 31st St Chicago, IL 60623 3 W 3st St Chicago, IL 3 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Charles N Holden Elementary School

Charles N Holden Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

AMES COMMUNITY SCHOOL DISTRICT SAWYER ELEMENTARY

AMES COMMUNITY SCHOOL DISTRICT SAWYER ELEMENTARY Exhibit D-4 AMES COMMUNIY SCHOOL DISRIC SAWYER ELEMENARY Schematic Development Project Manual June 25th 2014 RDG Planning & Design 301 Grand Avenue Des Moines, Iowa 50309 architectural narrative Summarized

More information

Nathanael Greene Elementary School 3525 S Honore St Chicago, IL 60609

Nathanael Greene Elementary School 3525 S Honore St Chicago, IL 60609 athanael Greene Elementary School 32 S Honore St Chicago, IL 009 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the

More information

Thomas A Edison Regional Gifted Center ES 4929 N Sawyer Ave Chicago, IL Co-locating on this campus are EDISON and ALBANY PARK

Thomas A Edison Regional Gifted Center ES 4929 N Sawyer Ave Chicago, IL Co-locating on this campus are EDISON and ALBANY PARK Facility Assessment Report 4929 Sawyer Ave Chicago, IL 025 Co-locating on this campus are EDISO and ALBA PARK This report contains a summary of the results from the facility assessment completed on the

More information

Dimension Below are the critical settings in AutoCAD. Other software should follow the same settings.

Dimension Below are the critical settings in AutoCAD. Other software should follow the same settings. 8.1 Drawing Standard 8.1.1 Introduction This drawing standard applies to all building drawings being prepared for the University of Calgary (UCalgary) by external consultants or vendors and internal staff

More information

George Washington Elementary School 3611 E 114th St Chicago, IL 60617

George Washington Elementary School 3611 E 114th St Chicago, IL 60617 3 E th St Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up

More information

PRESENT: Dr. George Mannon TUSD Superintendent Dr. Donald Stabler TUSD Deputy Superintendent. Marybeth Spadafino Committee Member: Admin.

PRESENT: Dr. George Mannon TUSD Superintendent Dr. Donald Stabler TUSD Deputy Superintendent. Marybeth Spadafino Committee Member: Admin. MEETING DATE: March 22, 2010 PROJECT: Bert Lynn Middle School Modernization Site Committee Meeting #5 HMC PROJECT #: 3203-037-000 PRESENT: Dr. George Mannon TUSD Superintendent Dr. Donald Stabler TUSD

More information

MODEL SETUP FOR RENOVATION PROJECTS: INSTRUCTIONS AND TUTORIALS

MODEL SETUP FOR RENOVATION PROJECTS: INSTRUCTIONS AND TUTORIALS MODEL SETUP FOR RENOVATION PROJECTS: INSTRUCTIONS AND TUTORIALS TABLE OF CONTENTS INTRODUCTION 1 PART ONE LAYERS AND CLASSES FOR RENOVATION PROJECT 2 OVERVIEW 2 SETTING UP LAYERS AND CLASSES 2 CREATING

More information

DESIGN-BUILD CONSTRUCTION SERVICES OCEAN VIEW ELEMENTARY SCHOOL RE-BUILD

DESIGN-BUILD CONSTRUCTION SERVICES OCEAN VIEW ELEMENTARY SCHOOL RE-BUILD ALBANY UNIFIED SCHOOL DISTRICT DESIGN-BUILD CONSTRUCTION SERVICES OCEAN VIEW ELEMENTARY SCHOOL RE-BUILD BOARD OF EDUCATION PRESENTATION JANUARY 22, 2019 DOUG ESPLAND Sr. Precon Manager & Project Director

More information

Richard J Oglesby Elementary School

Richard J Oglesby Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

BRYANT HERITAGE PLAZA 5301 Magasin Avenue Beaumont, AB

BRYANT HERITAGE PLAZA 5301 Magasin Avenue Beaumont, AB BRYANT HERITAGE PLAZA, AB RE-ISSUED FOR BUILDING PERMIT May 9, 206 L I S T O F D R A W I N G S HD ENGINEERING SERVICES LTD. D.B.K. ENGINEERING LTD. D.B.K. ENGINEERING LTD. JUBILEE ENGINEERING CONSULTANTS

More information

Chuck Caesar. VIA: /Webposting April 27, 2017

Chuck Caesar. VIA:  /Webposting April 27, 2017 VIA: Email/Webposting April 27, 2017 O Haver Contractors 12831 O Connor Road San Antonio, TX 78233 Telephone 210-590-2889 Fax 210/657-5888 Attn: John Zamoyski, Project Manager Email johnz@ohcltd.net John

More information

1.01 NOTICE TO BIDDERS

1.01 NOTICE TO BIDDERS ADDENDUM NO. 1 1.01 NOTICE TO BIDDERS A. Date: 15 March 2013 B. From: Bahr Vermeer and Haecker Architects, Ltd. C. To: Prospective Bidders. D. Project: Lexington Public Schools Lexington Middle School

More information

Buildings and Grounds Supervisor, EASD. CG Schmidt, Sr. Project Manager

Buildings and Grounds Supervisor, EASD. CG Schmidt, Sr. Project Manager MEETING MINUTES August 25, 2015 Colleen O'Meara EUA, Project Manager Bill Trewyn Mike Datza Jason Tadlock Dave Stebnitz Ross Eggert Bob Vajgrt Business Manager, EAST Buildings and Grounds Supervisor, EASD

More information

John Spry Elementary Community School

John Spry Elementary Community School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

CHAPTER 5 ARCHITECTURE

CHAPTER 5 ARCHITECTURE CHAPTER 5 ARCHITECTURE 5.1 GENERAL... 4 5.2 CONCEPT/PROJECT DEFINITION DESIGN (30%) SUBMITTAL REQUIREMENTS... 4 5.2.1 DESIGN ANALYSIS... 4 5.2.1.1 Design Criteria... 4 5.2.1.2 Narratives... 4 5.2.1.2.1

More information

Charles G Hammond Elementary School 2819 W 21st Pl Chicago, IL 60623

Charles G Hammond Elementary School 2819 W 21st Pl Chicago, IL 60623 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item

More information

Hall of Waters List of Historic Drawings

Hall of Waters List of Historic Drawings List of Historic Drawings The following represents the historic drawings of the PROJECT PWA PROJECT NUMBER JOB NUMBER SHEET NUMBER SHEET TITLE DATE NOTES 1935 Drawing Piping Layout at Tank Room for Mineral

More information

EPIC Academy High School

EPIC Academy High School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

DOCUMENT LIST OF DRAWINGS, TABLES AND SCHEDULES

DOCUMENT LIST OF DRAWINGS, TABLES AND SCHEDULES DOCUMENT 00 0115 LIST OF DRAWINGS, TABLES AND SCHEDULES DRAWINGS GENERAL A0.0 COVER SHEET ADDENDUM #2 revised A0.01 TITLE SHEET ADDENDUM #2 revised CIVIL C1.0 TOPO C2.0 DEMOLITION C3.0 TEMPORARY STREET

More information

Morton School of Excellence

Morton School of Excellence Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: 08012.00 SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA ADDENDUM NUMBER 1 to the BID SET August 10, 2009 General This Addendum will become part

More information

University of Chicago - North Kenwood/Oakland 1119 E 46th St Chicago, IL Co-locating on this campus are U OF C - NKO and ARIEL

University of Chicago - North Kenwood/Oakland 1119 E 46th St Chicago, IL Co-locating on this campus are U OF C - NKO and ARIEL Facility Assessment Report 9 E 4th St Chicago, IL 03 This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Johann W von Goethe Elementary School 2236 N Rockwell St Chicago, IL 60647

Johann W von Goethe Elementary School 2236 N Rockwell St Chicago, IL 60647 3 Rockwell St Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Ellen Mitchell Elementary School 2233 W Ohio St Chicago, IL 60612

Ellen Mitchell Elementary School 2233 W Ohio St Chicago, IL 60612 33 W Ohio St Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

St. John Paul II Catholic Parish

St. John Paul II Catholic Parish St. John Paul II Catholic Parish 167th & Ridgeview Road Olathe, Kansas Master Plan Town Hall October 30, 2018 Purpose [ The Church s ] mission consists essentially in offering people an opportunity not

More information

James Shields Middle School 2611 W 48th St Chicago, IL 60632

James Shields Middle School 2611 W 48th St Chicago, IL 60632 2 W 48th St Chicago, IL 02 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Paul Cuffe Math-Science Technology Academy ES 8324 S Racine Ave Chicago, IL 60620

Paul Cuffe Math-Science Technology Academy ES 8324 S Racine Ave Chicago, IL 60620 82 S Racine Ave Chicago, IL 020 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

Cherokee Heights Elementary School

Cherokee Heights Elementary School 694 Charlton Street Project Summary: Cherokee Heights Elementary is about to start its exciting transition to a Montessori learning model. The school is connected to the Baker Center which is currently

More information

MEETING MINUTES. SPS SWS at TT Minor TCF Architecture Project Number: Seattle World School SWS SDAT Workshop 3 2 December 2013

MEETING MINUTES. SPS SWS at TT Minor TCF Architecture Project Number: Seattle World School SWS SDAT Workshop 3 2 December 2013 Seattle World School SWS SDAT Workshop 3 2 December 203 SPS SWS at TT Minor TCF Architecture Project Number: 203 002 MEETING MINUTES Attendance: Name Representing Role Paul Wight Seattle Public Schools

More information

William H Seward Communication Arts Academy ES 4600 S Hermitage Ave Chicago, IL 60609

William H Seward Communication Arts Academy ES 4600 S Hermitage Ave Chicago, IL 60609 S Hermitage Ave Chicago, IL 9 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

SPRINKLER SF. Stair 190 SF WOMEN SF LOBBY SF MECH/ELEC CONCESSIONS SF 225 SF STORAGE SF

SPRINKLER SF. Stair 190 SF WOMEN SF LOBBY SF MECH/ELEC CONCESSIONS SF 225 SF STORAGE SF 1JACKSON MSC TEMPSTAR W/DT-3-LR TABLE PACKAGE WAREWASHER, DOOR TYPE W/ DISHTABLES ARCHITECTURE & INTERIOR DESIGN Montgomery Dothan WWW.SSLARCH.COM (M) 334. 263. 5162 (D) 334. 791. 5248 No. Revision Date

More information

TRIBAL BUILDING AND DEVELOPMENT Plan Check Submittal

TRIBAL BUILDING AND DEVELOPMENT Plan Check Submittal TRIBAL BUILDING AND DEVELOPMENT Plan Check Submittal Complete sets of plans are required. Plans shall be stamped and wet signed by the architect or engineer. (signed and accompanied with letter from Homeowners

More information

Allan Hancock College

Allan Hancock College Allan Hancock College Project Planning Board Workshop February 17, 2009 Agenda Objective Funding Allocation Space Demand Analysis Project Overview Bond Measure I Program Schedule Charge: To review funding

More information

KIPP Charter Bloom. Definitions EXTERIOR S Lowe Ave Chicago, IL Co-locating on This Campus: Hope HS and Kipp Chtr Bloom

KIPP Charter Bloom. Definitions EXTERIOR S Lowe Ave Chicago, IL Co-locating on This Campus: Hope HS and Kipp Chtr Bloom Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

COMPILATION OF TENDER DOCUMENTS

COMPILATION OF TENDER DOCUMENTS COMPILATION OF TENDER DOCUMENTS Arc. Ibrahim A. Haruna, FNIA, PNIA, mni. -the familiar question!- Mr. Architect, after these your beautiful drawings, what next? ARCHITECT S PROCEDURE: -drawing board to

More information

Jonathan Burr Elementary School

Jonathan Burr Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

ADDENDUM THREE SPECIFICATIONS. Vincennes University Renovations of the Curtis G. Shake Learning Resources Center

ADDENDUM THREE SPECIFICATIONS. Vincennes University Renovations of the Curtis G. Shake Learning Resources Center ADDENDUM THREE Addendum Three (AD.03) to the drawings and specifications prepared by Gibraltar Design for Curtis G. Shake Learning Resources Center for Vincennes University, Vincennes, Indiana. All Contractors

More information

ARCHITECTURE CADD Course Syllabus

ARCHITECTURE CADD Course Syllabus 6111 E. Skelly Drive P. O. Box 477200 Tulsa, OK 74147-7200 ARCHITECTURE CADD Course Syllabus Course Number: TTC-0880 OHLAP Credit: Yes OCAS Code: 8903 Course Length: 120 Hours Career Cluster: Manufacturing

More information

Idaho State Historical Museum Renovation and Addition

Idaho State Historical Museum Renovation and Addition Idaho State Historical Museum Renovation and Addition History is essential to understanding America. Lessons from the past enhance historical literacy, create an informed citizenry, deepen our connections

More information

Design Deliverables. Summary. A. Expectations for Design Deliverables:

Design Deliverables. Summary. A. Expectations for Design Deliverables: Design Deliverables Summary A. Expectations for Design Deliverables: The Design Team is obligated to advance and deliver the project with a professional manner and standard of care that meets the expectations

More information

To the Drawings and/or Specifications for. Board of Education of Harford County Lancaster, PA 17603

To the Drawings and/or Specifications for. Board of Education of Harford County Lancaster, PA 17603 ENDUM NO. 2 To the Drawings and/or Specifications for Gilbert Architects Youth s Benefit Elementary School - #0729 626 N. Charlotte St. Board of Education of Harford County Lancaster, PA 17603 June 2,

More information

Southern Oregon University

Southern Oregon University Southern Oregon University Public Meeting Notice August 5, 05 TO: FROM: RE: Southern Oregon University Board of Trustees, Finance Committee Sabrina Prud homme, University Board Secretary Notice of special

More information

GREENWICH PUBLIC SCHOOLS. Greenwich, Connecticut REQUEST FOR BOARD ACTION OR PRESENTATION OF INFORMATIONAL ITEM

GREENWICH PUBLIC SCHOOLS. Greenwich, Connecticut REQUEST FOR BOARD ACTION OR PRESENTATION OF INFORMATIONAL ITEM Date of Meeting: March 20, 2014 GREENWICH PUBLIC SCHOOLS Greenwich, Connecticut Title of Item: New Lebanon School Pre-Feasibility Study Policy Reference: E - 051 REQUEST FOR BOARD ACTION OR PRESENTATION

More information

THE FOLLOWING ITEMS WERE DISCUSSED: 1. HVAC SYSTEM:

THE FOLLOWING ITEMS WERE DISCUSSED: 1. HVAC SYSTEM: 4900 Lang Ave NE Albuquerque, NM 87109 505-348-4000 phone 505-348-4055 fax Meeting Minutes Project: Valley View Elementary School Owner: Valley View Public Schools / PSFA Albuquerque Colorado Springs Denver

More information

Proximity to Employee Housing and Centers of commerce. 2 Minutes to Georgetown. 3 Minutes to The Pentagon

Proximity to Employee Housing and Centers of commerce. 2 Minutes to Georgetown. 3 Minutes to The Pentagon Proximity to Employee Housing and Centers of commerce 270 95 2 Minutes to Georgetown 3 Minutes to The Pentagon 4 Minutes to K Street 8 Minutes to Reagan National 9 Minutes to The White House 11 Minutes

More information

Ashby, Pepperell, Townsend North Middlesex Regional High School. Feasibility Study Update

Ashby, Pepperell, Townsend North Middlesex Regional High School. Feasibility Study Update Ashby, Pepperell, Townsend North Middlesex Regional High School Feasibility Study Update June 6, 2013 AGENDA Preliminary Design Program (PDP) District Capacity Analysis Preferred Schematic Report (PSR)

More information

RFQ Question and Answer List State of Ohio Standard Forms and Documents

RFQ Question and Answer List State of Ohio Standard Forms and Documents RFQ Question and Answer List State of Ohio Standard Forms and Documents Project Name University Hall Renovation Project Number BGU-565 Project Location Bowling Green State University Date posted: June

More information

James Otis Elementary School 525 N Armour St Chicago, IL 60642

James Otis Elementary School 525 N Armour St Chicago, IL 60642 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item

More information

RECORD GROUP NUMBER 156

RECORD GROUP NUMBER 156 DEPARTMENT OF MENTAL HEALTH AND MENTAL RETARDATION HOSPITAL AND SCHOOL FOR THE RETARDED ARLINGTON, TENN. BLUEPRINTS, 1965 RECORD GROUP NUMBER 156 Processed by: David R. Sowell Archival Technical Services

More information

CAC MEETING, FEB. 28 TH, 2017 NADAAA

CAC MEETING, FEB. 28 TH, 2017 NADAAA ADAMS STREET BRANCH LIBRARY PROGRAMMING STUDY FOR CITY OF BOSTON BOSTON PUBLIC LIBRARY AND PUBLIC FACILITY DEPARTMENT CAC MEETING, FEB. 28 TH, 2017 NADAAA 1 AGENDA 1.0 SCHEDULE 2.0 SUMMARY OF PROJECT GOAL

More information

Architecture, Construction, and Engineering Technical Charter

Architecture, Construction, and Engineering Technical Charter Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Charles P Caldwell Academy of Math & Science ES 8546 S Cregier Ave Chicago, IL 60617

Charles P Caldwell Academy of Math & Science ES 8546 S Cregier Ave Chicago, IL 60617 S Cregier Ave Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Robert Fulton Elementary School

Robert Fulton Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Andrew Carnegie Elementary School

Andrew Carnegie Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Friedrich Ludwig Jahn Elementary School 3149 N Wolcott Ave Chicago, IL 60657

Friedrich Ludwig Jahn Elementary School 3149 N Wolcott Ave Chicago, IL 60657 39 Wolcott Ave Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

214 Wilshire Blvd., Suite 102 Santa Monica California 90401

214 Wilshire Blvd., Suite 102 Santa Monica California 90401 Wilshire Blvd., Suite 0 Santa Monica California 900 7 W a l l a c e P l. C a l i f o r n i a 9 8 t e l : 0 7 7 N ND COURT PROPERTY LINE 0.00' THE RENOVATION AND CHANGE OF USE OF AN EXISTING BOOK STORE

More information

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118 PART 1: GENERAL This section of the design standard outlines general requirements for electrical and telecommunications designs to be performed for the University of Texas at Austin. This standard is intended

More information

John Barry Elementary School 2828 N Kilbourn Ave Chicago, IL 60641

John Barry Elementary School 2828 N Kilbourn Ave Chicago, IL 60641 Kilbourn Ave Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

GREENWICH PUBLIC SCHOOLS New Lebanon ES Feasibility Expansion Study

GREENWICH PUBLIC SCHOOLS New Lebanon ES Feasibility Expansion Study GREENWICH PUBLIC SCHOOLS New Lebanon ES Feasibility Expansion Study New Lebanon School (K-5) 25 Mead Avenue, Greenwich, CT 20 March 2014 KSQ Architects PC 20 March 2014 GREENWICH PUBLIC SCHOOLS NEW LEBANON

More information

San Francisco Unified School District Beyond the Talk: Modernizing our Schools to Inspire Learning. September 27, Raoul Wallenberg High School

San Francisco Unified School District Beyond the Talk: Modernizing our Schools to Inspire Learning. September 27, Raoul Wallenberg High School San Francisco Unified School District Beyond the Talk: Modernizing our Schools to Inspire Learning September 27, 2011 Raoul Wallenberg High School Summer of 2011 Continuing the task to fix, repair, make

More information

ROBERT TURNER COLLEGE AND CAREER HIGH SCHOOL

ROBERT TURNER COLLEGE AND CAREER HIGH SCHOOL ROBERT TURER COLLEGE AD CAREER HIGH SCHOOL SCHEMATIC DESIG PRESETATIO 23 MAY 2017 Project Milestones Schematic Design..... March May 2017 SD Presentation to Board of Trustees...... 23 May, 2017 Design

More information