1 275 Lexington Parkway North Project Summary: Central is the oldest high school in the state of Minnesota, beginning its 150th year. Its rich traditions, including academic excellence, are widely celebrated. Families prize the high value we place on academics; the varied extracurricular opportunities; our culture of constant innovation; and our focus on relationships as the center for learning. It was originally constructed in 1912 at 188,000 square feet. A later addition was completed in 1925 and a major renovation was completed in It is now 340,641 square feet. Issues Identified By School Community In Safety and security 2. Indoor air quality unhealthy 3. Update of camera system 4. Furniture - fixtures and equipment 5. Improve all learning spaces 6. Bathroom improvements 7. True study hall space with desks and good lighting 8. Community and shared - open social space 9. Welcoming entrance and identity Grade Levels: 9-12 SY 2014/15 Enrollment: 1858 Design Enrollment: 2160 General Notes: Existing utilization shown is for School Year The Conceptual Utilization Plans are exploratory rather than actual construction plans and represent the design at one moment in time, which will change as the design and funding process progress. The Conceptual Plans are included as a way to organize scopes of work into logical, efficient and meaningful projects. There is no prioritization implied in a work scope title (e.g. Work Scope A is not necessarily the most critical work to be done). The plans in this document are not comprehensive of the entire building s needs as maintenance and replacement of existing building systems such as roofs and mechanical systems are omitted to maintain graphic clarity of the overall vision generated during the Facilities Master Plan Process. Formal zoning reviews have not been undertaken for the proposed work shown in these plans. A review with zoning and building code authorities will occur once the funding is secured. 1

2 Legend: S1. New main entry, lobby, commons, and Instructional Space additions Site Concept (9,230 SF) S2. Incorporate Plaza retrofit (by others) into new landscape construction at Main Entry (12,000 SF) S3. Relocate outdoor Instructional Space (1,600 SF) MATCH-LINE Property Line Main Entry Secondary Entry Service Entry Alterations New Landscape Construction New Building Construction 2

3 Existing Utilization BASEMENT FLOOR 3.1

4 Existing Utilization FIRST FLOOR 3.2

5 Existing Utilization SECOND FLOOR 3.3

6 Existing Utilization THIRD FLOOR 3.4

7 Existing Utilization FOURTH FLOOR 3.5

8 Conceptual Utilization Plan Legend: C1. New Instructional Space (1,194 SF) C2. Refurbish Instructional Space - furniture, lighting, equipment, aesthetics (5,330 SF) C3. Restroom upgrades (270 SF) BASEMENT 4.1

9 Conceptual Utilization Plan Legend: C2. Refurbish Instructional Space - furniture, lighting, equipment, aesthetics (16,974 SF) C3. Restroom upgrades (2,286 SF) FIRST FLOOR Property Line Main Entry Secondary Entry Service Entry 4.2A

10 Conceptual Utilization Plan Legend: C1. New Instructional Space (6,110 SF) C2. Refurbish Instructional Space - furniture, lighting, equipment, aesthetics (3,000 SF) C3. Restroom upgrades (903 SF) C4. New Corridor (2,445 SF) C5. New Elevator (200 SF) See 4.2A C6. New 2-story Entry Lobby and grand stair (3,270 SF) EXISTING FIRST FLOOR ADDITION Property Line Main Entry Secondary Entry Service Entry 4.2B

11 Conceptual Utilization Plan Legend: C2. Refurbish Instructional Space - furniture, lighting, equipment, aesthetics (7,404 SF) See 4.3B See 4.3B SECOND FLOOR 4.3A

12 Conceptual Utilization Plan Legend: C2. Refurbish Instructional Space - furniture, lighting, equipment, aesthetics (13,932 SF) C3. Restroom upgrades (997 SF) C6. New 2-story Entry Lobby and grand stair (See 4.2B) C7. New Student Commons (7,654 SF) C8. Upgrade Cafeteria (7,786 SF) C9. Cafeteria expansion (4,930 SF) EXISTING ADDITION SECOND FLOOR 4.3B

13 Conceptual Utilization Plan Legend: C2. Refurbish Instructional Space - furniture, lighting, equipment, aesthetics (16,268 SF) C3. Restroom upgrades (1,124 SF) C10. New shared centralized learning area (3,081 SF) THIRD FLOOR 4.4

14 Conceptual Utilization Plan Legend: C2. Refurbish Instructional Space - furniture, lighting, equipment, aesthetics (17,509 SF) C3. Restroom upgrades (912 SF) C4. New Corridor (450 SF) C10. New shared centralized learning area (4,798 SF) C11. upgrades (8,496 SF) FOURTH FLOOR 4.5

15 Conceptual Construction Plan Scope Package Light Remodel Finishes Only A B 270 SF 1,194 SF 5,328 SF C TOTAL 270 SF 1,194 SF 5,328 SF Line Items Unit Lump Sum Air Quality Security System BASEMENT Light Remodel Finishes Only No Work 5.1

16 Conceptual Construction Plan Scope Package Light Remodel Finishes Only A 1,452 SF B 2,285 SF 15,522 SF C TOTAL 2,285 SF 16,974 SF Line Items Unit Lump Sum Air Quality Security System FIRST FLOOR Light Remodel Finishes Only No Work 5.2A

17 Conceptual Construction Plan Scope Package Light Remodel Finishes Only A 9,327 SF 4,081 SF 4,573 SF B 903 SF SEE 5.2A C TOTAL 9,327 SF 4,984 SF 4,573 SF Line Items Unit Lump Sum Air Quality Security System EXISTING FIRST FLOOR ADDITION New Main Entry, grand stair and elevator Light Remodel Finishes Only No Work 5.2B

18 Conceptual Construction Plan Scope Package Light Remodel Finishes Only A B 9, 075 SF SEE 5.3B C TOTAL 9, 075 SF Line Items Unit Lump Sum Air Quality Security System SECOND FLOOR Light Remodel Finishes Only No Work 5.3A

19 Conceptual Construction Plan Scope Package Light Remodel Finishes Only A 10,058 SF 3,087 SF 9, 496 SF B 997 SF 14,377 SF C TOTAL 10,058 SF 4,084 SF 9, 496 SF 14,377 SF SEE 5.3A Line Items Unit Lump Sum Air Quality Security System Remove stair EXISTING ADDITION SECOND FLOOR New Main Entry, grand stair and elevator Light Remodel Finishes Only No Work 5.3B

20 Conceptual Construction Plan Scope Package Light Remodel Finishes Only A B 14,388 SF C 625 SF 5,385 SF TOTAL 625 SF 5,385 SF 14,388 SF Line Items Unit Lump Sum Air Quality Security System Typical at 3 areas: Expand Instructional Space footprint, remove existing exterior wall and add new glazing Remove walls and add sliding glass partitions to provide flexible learning areas THIRD FLOOR Light Remodel Finishes Only No Work 5.4

21 Conceptual Construction Plan Scope Package Light Remodel Finishes Only A B 17,347 SF C 625 SF 13,922 SF TOTAL 625 SF 13,922 SF 17,347 SF Line Items Unit Lump Sum Air Quality Security System Typical at 3 areas: Expand Instructional Space footprint, remove existing exterior wall and add new glazing Remove walls and add sliding glass partitions to provide flexible learning areas FOURTH FLOOR Light Remodel Finishes Only No Work 5.5

John A Johnson Elementary School

John A Johnson Elementary School 740 York Avenue Project Summary: An Acheivement Plus school John A Johnson is located adjacent to the East Side YMCA, jointly serving their communities educational, recreation, and wellness needs. The

More information

Cherokee Heights Elementary School

Cherokee Heights Elementary School 694 Charlton Street Project Summary: Cherokee Heights Elementary is about to start its exciting transition to a Montessori learning model. The school is connected to the Baker Center which is currently

More information

Harding Senior High School

Harding Senior High School 1540 Sixth Street East Project Summary:, located in the Eastview area of St. Paul, offers students in grades 9 through 12 a wide range of curriculum options ranging from International Baccalaureate to

More information

Horace Mann Elementary

Horace Mann Elementary 2001 Eleanor Avenue Project Summary: Horace Mann is a neighborhood school filled with students who are excited to be here taught by teachers who transform excitement into achievement. Expectations are

More information

Adams Spanish Immersion 615 Chatsworth Street South

Adams Spanish Immersion 615 Chatsworth Street South Project Summary: Adams Spanish Immersion is an international education without the travel expense. Our school is a place where families and staff value the opportunities gained from learning a second language.

More information

Linwood Monroe Upper 810 Palace Avenue

Linwood Monroe Upper 810 Palace Avenue 810 Palace Avenue Project Summary: Spanning a child s first classroom experience all the way through middle school, Linwood Monroe s Plus lays a foundation for creativity and exploration in the arts. Accelerated

More information

CAPITAL IMPROVEMENT PROGRAM

CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT PROGRAM Public Work Session No. 2 Project Narrative Submittal December 18, 2017 Prepared for: HALLSVILLE R-IV SCHOOL DISTRICT 421 East Highway 124 Hallsville, MO 65255 Prepared by:

More information

ASSIGNMENT 04: Library Massing + Program

ASSIGNMENT 04: Library Massing + Program ASSIGNMENT 04: Library Massing + Program THE IMPORTANCE OF PROGRAM AND MASSING DIAGRAMMING: Program and Massing diagrams are critical tools used to visually describe the relationship between the way a

More information

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic GENERAL SITE PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS Scope of work narrative Building code review Description of construction Documentation on drawings as List of applicable

More information

AVAILABLE FOR LEASE OFFICE AND LABORATORY SPACE Approximately 322,384 RSF

AVAILABLE FOR LEASE OFFICE AND LABORATORY SPACE Approximately 322,384 RSF AVAILABLE FOR LEASE AND SPACE Approximately 322,384 RSF 2400 Ellis Road Research Triangle Park, North Carolina www.goellisresearchcenter.com PROPERTY DESCRIPTION Administrative Wing Cafeteria Lobby/Atrium

More information

Huntington Beach City School District. M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y

Huntington Beach City School District. M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y Huntington Beach City School District M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y 0 1 7 Agenda 1. Where are we in the process?. Measure Q Bond Program

More information

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document.

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document. Enroll in GMFI Program Image Consultation Design Intent Document Preparation Preliminary Drawings Final Drawings Design Intent Document You are here. 1-2 Construction Documents Services performed by dealer

More information

CAC MEETING, FEB. 28 TH, 2017 NADAAA

CAC MEETING, FEB. 28 TH, 2017 NADAAA ADAMS STREET BRANCH LIBRARY PROGRAMMING STUDY FOR CITY OF BOSTON BOSTON PUBLIC LIBRARY AND PUBLIC FACILITY DEPARTMENT CAC MEETING, FEB. 28 TH, 2017 NADAAA 1 AGENDA 1.0 SCHEDULE 2.0 SUMMARY OF PROJECT GOAL

More information

ADMINISTRATION DEPARTMENT Plant Management Division. An Inventory of Its State Office Building Drawings

ADMINISTRATION DEPARTMENT Plant Management Division. An Inventory of Its State Office Building Drawings MINNESOTA HISTORICAL SOCIETY Minnesota State Archives ADMINISTRATION DEPARTMENT Plant Management Division An Inventory of Its State Office Building Drawings OVERVIEW OF THE RECORDS Agency: Minnesota. Dept.

More information

Phalen Lake Hmong Studies Magnet

Phalen Lake Hmong Studies Magnet Phalen Lake Hmong Studies Magnet 1089 ypress Street Project Summary: the Hmong people. Phalen Lake students and staff incorporate personalized learning through technology into daily lessons, square feet.

More information

March 1, Buildings for Our Future: 2016 Update

March 1, Buildings for Our Future: 2016 Update March 1, 2016 Buildings for Our Future: 2016 Update Buildings For Our Future: Project Objectives Transform five elementary schools in poor and worsening condition into 21st century centers of learning

More information

11/29/12. Des Moines Social Club Urban Design Review Project Narrative

11/29/12. Des Moines Social Club Urban Design Review Project Narrative 11/9/1 Des Moines Social Club Urban Design Review Project Narrative Strategically located at 9th and Walnut, the Des Moines Social Club (DMSC) will become a critical link between the Court Avenue Entertainment

More information

At Fair Lakes Office Park, you will discover an environment that helps your business attract and

At Fair Lakes Office Park, you will discover an environment that helps your business attract and 12450 12500 12600 12700 12750 12701 12730 FAIR LAKES CIRCLE FAIRFAX VA Overview Office Park At Fair Lakes Office Park, you will discover an environment that helps your business attract and 25 retain top

More information

1001 Feehanville Drive Phone Mt. Prospect, IL Fax

1001 Feehanville Drive Phone Mt. Prospect, IL Fax NICHOLAS & ASSOCIATES, INC. 1001 Feehanville Drive Phone 847.394.6200 Mt. Prospect, IL 60056 Fax 847.394.6205 November 29, 2016 Community Unit School District 200 130 West Park Avenue Wheaton, IL 60189

More information

11SIXTY5 Weaver Dairy Road

11SIXTY5 Weaver Dairy Road SITEPLAN NOTES 2 C-2.0 BICYCLE RACK NTS Weaver Dairy Road Job Number: 1529 WLR, MTC, VJC WLR, VJC 11-30-17 STAIR SITE PLAN 1 C-2.0 SITE PLAN 1" = 30' 0 15 30 60 3 C-2.0 PLAZA DETAIL PLAN 1" = 20' 0 10

More information

Snohomish County Courthouse Renovation + Addition COUNCIL PRESENTATION 6 MARCH 2017

Snohomish County Courthouse Renovation + Addition COUNCIL PRESENTATION 6 MARCH 2017 Review the Process Building Assessment Prioritize into Tiered Matrix Develop Cost Estimate per Scope Items Schematic Design Renovation + Addition Schematic Drawings Interior + Exterior Perspectives Recommendations

More information

BASEBALL PLAYER FACILITIES CLEMSON, SOUTH CAROLINA

BASEBALL PLAYER FACILITIES CLEMSON, SOUTH CAROLINA THROUGH THE YEARS THROUGH THE YEARS VIEW FROM RIGHT FIELD VIEW FROM DUGOUT VIEW FROM NEW GRANDSTAND EXISTING CONDITIONS EXTERIOR PHOTOS PLAYER S LOUNGE LOCKER ROOM TRAINING AREA COACH S OFFICE CORRIDOR

More information

Idaho State Historical Museum Renovation and Addition

Idaho State Historical Museum Renovation and Addition Idaho State Historical Museum Renovation and Addition History is essential to understanding America. Lessons from the past enhance historical literacy, create an informed citizenry, deepen our connections

More information

Richardson olmsted complex core project Community Presentation. buffalo, new york

Richardson olmsted complex core project Community Presentation. buffalo, new york Richardson olmsted complex core project Community Presentation buffalo, new york 20 AUGUST 2013 DESIGN TEAM ARCHITECT Consulting design ARCHITECT consulting historic Preservation ARCHITECT Landscape ARCHITECT

More information

OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN

OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN KBE APPROVAL DATE: APRIL 2013 including Finding #1 g g OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN PLAN OF SCHOOL ORGANIZATION 1. Current Plan PS, K-5, 6-8, 9-12 2. Long Range Plan PS, K-5, 6-8, 9-12

More information

Required Documents for Commercial Permits Permit Types 1. New Structure 2. Addition 3. Remodel 4. Tenant Finish 5. Change of Tenant/Use 6.

Required Documents for Commercial Permits Permit Types 1. New Structure 2. Addition 3. Remodel 4. Tenant Finish 5. Change of Tenant/Use 6. Required Documents for Commercial Permits Permit Types 1. New Structure 2. Addition 3. Remodel 4. Tenant Finish 5. Change of Tenant/Use 6. Temporary Use 7. Decks over 30 inches 8. Re-Roof 9. Plumbing 10.

More information

Prototype Design Guide

Prototype Design Guide 2015 Choice Hotels International, Inc. All rights reserved. 06/2015/1,000. CAM-PROTO-15 CAMBRIADEVELOPMENT.COM Prototype Design Guide A fresh strategy. An untapped market. A smart new prototype. Insightful

More information

Knight Abbey ID 439 Contract Design I

Knight Abbey ID 439 Contract Design I Knight Abbey ID 439 Contract Design I Due: May 7 th Project Description: Students enrolled in ID-439, Contract Design I during the spring 2014 semester will be working on an office design solution for

More information

NDUS/UND IT Facility Office Building/Data Center

NDUS/UND IT Facility Office Building/Data Center NDUS/UND IT Facility Building/Data Center Building Option 3 $9,133,128 Data Center $4,937,500 Tier 2 to Tier 3 (add on) $1,356,250 Total $15,426,878 Legislative Appropriation $12,500,000 Difference $2,926,878

More information

SANTA MONICA BOULEVARD BEVERLY HILLS OWNER: 9908 SANTA MONICA BLVD., LLC SAN VICENTE BLVD. SUITE 550

SANTA MONICA BOULEVARD BEVERLY HILLS OWNER: 9908 SANTA MONICA BLVD., LLC SAN VICENTE BLVD. SUITE 550 BEVERLY HILLS OWNER: 777 SAN VICENTE BLVD. 550 SHEET INDEX: A-000.00 A-00.00 A-00.00 A-003.00 A-004.00 A-005.00 A-006.00 A-007.00 A-080.00 A-090.00 A-00.00 A-0.00 A-0.00 A-30.00 A-40.00 A-50.00 A-00.00

More information

Ashby, Pepperell, Townsend North Middlesex Regional High School. Feasibility Study Update

Ashby, Pepperell, Townsend North Middlesex Regional High School. Feasibility Study Update Ashby, Pepperell, Townsend North Middlesex Regional High School Feasibility Study Update June 6, 2013 AGENDA Preliminary Design Program (PDP) District Capacity Analysis Preferred Schematic Report (PSR)

More information

MEETING MINUTES. SPS SWS at TT Minor TCF Architecture Project Number: Seattle World School SWS SDAT Workshop 3 2 December 2013

MEETING MINUTES. SPS SWS at TT Minor TCF Architecture Project Number: Seattle World School SWS SDAT Workshop 3 2 December 2013 Seattle World School SWS SDAT Workshop 3 2 December 203 SPS SWS at TT Minor TCF Architecture Project Number: 203 002 MEETING MINUTES Attendance: Name Representing Role Paul Wight Seattle Public Schools

More information

American Institute of Architects New Hampshire Chapter High School Design Competition Program

American Institute of Architects New Hampshire Chapter High School Design Competition Program American Institute of Architects New Hampshire Chapter 2009 2010 High School Design Competition Program Educational Objectives To increase your awareness of the relationships between space, human scale

More information

DESERT MOUNTAIN MEDICAL PLAZA

DESERT MOUNTAIN MEDICAL PLAZA DESERT MOUNTAIN MEDICAL PLAZA FOR LEASE Generous Tenant Improvement Allowance Contact Broker for details PROPERTY RENOVATIONS COMPLETE UPDATED AREAS INCLUDE: New furnishings and artwork in lobbies Fully

More information

ARCH 405bL SPRING 2016 LUCY EGBE + NICK HALSEY + KELLY LYNCH ERIN YAMASHITA ISSUED 04/26/16. Site Plan. Site Plan 1" = 50'-0" 1" = 50'-0" SCALE A-500

ARCH 405bL SPRING 2016 LUCY EGBE + NICK HALSEY + KELLY LYNCH ERIN YAMASHITA ISSUED 04/26/16. Site Plan. Site Plan 1 = 50'-0 1 = 50'-0 SCALE A-500 04/6/6 Site Plan " = 50'-0" Site Plan " = 50'-0" A-500 LOWLINE PARK WARHOL MUSEUM BASEMENT 6.67% Up 6.67% Down 03/0/6 Level P /3" = '-0" UP TYPICAL PARKING PLAN /3" = '-0" A-50P ESSEX ST. MARKET WARHOL

More information

BRYANT HERITAGE PLAZA 5301 Magasin Avenue Beaumont, AB

BRYANT HERITAGE PLAZA 5301 Magasin Avenue Beaumont, AB BRYANT HERITAGE PLAZA, AB RE-ISSUED FOR BUILDING PERMIT May 9, 206 L I S T O F D R A W I N G S HD ENGINEERING SERVICES LTD. D.B.K. ENGINEERING LTD. D.B.K. ENGINEERING LTD. JUBILEE ENGINEERING CONSULTANTS

More information

Marcus Moziah Garvey Elementary School

Marcus Moziah Garvey Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

ELLIS. Ellis Research Center PROPERTY HIGHLIGHTS BRIAN CARR, CCIM LEE CLYBURN. Research Triangle Park North Carolina.

ELLIS. Ellis Research Center PROPERTY HIGHLIGHTS BRIAN CARR, CCIM LEE CLYBURN. Research Triangle Park North Carolina. ELLIS Research Triangle Park North Carolina Ellis Research Center Office and Lab PROPERTY HIGHLIGHTS 2400 Ellis Rd RTP, NC 27709 Size 331,898 RSF Floors 4 Parking Power 519 Shared parking spaces 480/277

More information

SCARSDALE PUBLIC SCHOOLS. Greenacres Feasibility Study

SCARSDALE PUBLIC SCHOOLS. Greenacres Feasibility Study SCARSDALE PUBLIC SCHOOLS Greenacres - 2015 Feasibility Study Committee List Lee Maude Scott Silberfein Stuart Mattey John Trenholm Liz Marrinan Sharon Hill Paul Berger Karen Guardino Carole Phillips Joan

More information

Module 1: Building Model Creation

Module 1: Building Model Creation INSTRUCTIONAL MODULES DEMONSTRATING BUILDING ENERGY ANALYSIS USING A BUILDING INFORMATION MODEL Christian Daniel Douglass Industrial and Enterprise Systems Engineering December 1, 2010 Module Summary In

More information

Deck Tutorial. Chapter 8: Decks and Porches

Deck Tutorial. Chapter 8: Decks and Porches Chapter 8: Deck Tutorial Now we ll continue where the Landscaping Tutorial left off and create a deck off the back of the house, connecting it to the terrain with an exterior staircase. You may want to

More information

Deck Tutorial. Chapter 6: Decks and Porches

Deck Tutorial. Chapter 6: Decks and Porches Chapter 6: Deck Tutorial Now we ll continue where the Landscaping Tutorial left off and create a deck off the back of the house, connecting it to the terrain with an exterior staircase. You may want to

More information

COMPONENT FLOW CHART & SEQUENCING DIAGRAMS

COMPONENT FLOW CHART & SEQUENCING DIAGRAMS Oak Park and River Forest High School Master Facilities Plan COMPONENT FLOW CHART & SEQUENCING DIAGRAMS The following is a narrative intended to accompany the component flow chart and sequencing diagrams

More information

THE. Harbor Master ELEVATION 2

THE. Harbor Master ELEVATION 2 THE Harbor Master ELEVATION 2 Additional Elevations ELEVATION 1 ELEVATION 3 Lower Level Patio 28'10" x 12'0" Mechanicals on Raised Platform H Lower Entry HVAC Parking 20'4" x 48'0" Side Entry Garage Side

More information

Railroad Ave. Ramp Down STAIR S4 158 SF STAIR S5 163 SF. 1 Bedroom SF. 1L Bedroom SF. 1L Bedroom SF. 2 Bedroom SF

Railroad Ave. Ramp Down STAIR S4 158 SF STAIR S5 163 SF. 1 Bedroom SF. 1L Bedroom SF. 1L Bedroom SF. 2 Bedroom SF 3"='-" OE BEDROOM COMMERCIAL UIT -/"='-" Railroad Ave. C:\Users\darguin\Documents\ 5 Stories 7-4-7_darguin.fortuna@the-bac.edu.rvt IF THIS SHEET IS OT 4 X 36 IT IS A REDUCED PRIT - ACCORDIGLY 5 4 8 ' '

More information

NEW LEBANON ELEMENTARY SCHOOL

NEW LEBANON ELEMENTARY SCHOOL NEW LEBANON ELEMENTARY SCHOOL EDUCATIONAL SPECIFICATIONS for the NEW LEBANON ELEMENTARY SCHOOL November 10, 2014 PETER GISOLFI ASSOCIATES Architects Landscape Architects, LLP NEW LEBANON ELEMENTARY SCHOOL

More information

NEW LEBANON ELEMENTARY SCHOOL

NEW LEBANON ELEMENTARY SCHOOL NEW LEBANON ELEMENTARY SCHOOL EDUCATIONAL SPECIFICATIONS for the NEW LEBANON ELEMENTARY SCHOOL October 9, 2014 PETER GISOLFI ASSOCIATES Architects Landscape Architects, LLP NEW LEBANON ELEMENTARY SCHOOL

More information

Required Supporting Information and Documentation for Historic Preservation Certification Applications

Required Supporting Information and Documentation for Historic Preservation Certification Applications Required Supporting Information and Documentation for Historic Preservation Certification Applications Part 1 Submittal- Evaluation of Significance Descriptive Information Describe the major features of

More information

DESIGN-BUILD CONSTRUCTION SERVICES OCEAN VIEW ELEMENTARY SCHOOL RE-BUILD

DESIGN-BUILD CONSTRUCTION SERVICES OCEAN VIEW ELEMENTARY SCHOOL RE-BUILD ALBANY UNIFIED SCHOOL DISTRICT DESIGN-BUILD CONSTRUCTION SERVICES OCEAN VIEW ELEMENTARY SCHOOL RE-BUILD BOARD OF EDUCATION PRESENTATION JANUARY 22, 2019 DOUG ESPLAND Sr. Precon Manager & Project Director

More information

State College Area School District

State College Area School District State College Area School District The following is a guideline for project design submittals to the Facility Committee of the State College Area School District. During the design process the committee

More information

Jackie Robinson Elementary School

Jackie Robinson Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

PROJECT ENTITLEMENT APPLICATION

PROJECT ENTITLEMENT APPLICATION GENERAL REQUIREMENTS (Print or Type) Name of Proposed Project: Location of Project: Legal Description of Project (Assessor s Parcel/Allotment No., Township/Range/Section): Staff Use Only CASE NO.: RELATED

More information

ADDENDUM #2 September 12, 2018

ADDENDUM #2 September 12, 2018 Physical Plant Services Project Management 1000 Rim Drive Phone: (970) 247-7523 Fax: (970) 247-7555 Project No. 2007-130P18 Whalen Gymnasium Expansion and Renovation for Exercise Science Request for Qualifications

More information

Mahalia Jackson Elementary School 917 W 88th St Chicago, IL 60620

Mahalia Jackson Elementary School 917 W 88th St Chicago, IL 60620 W 88th St Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

754 Sir Francis Drake Boulevard

754 Sir Francis Drake Boulevard APN: 006-09 - 39 Town of San Anselmo Submittal Number : April 06 Revised June 0, 06 PROJECT TEAM INDEX TO DRAWINGS APPLICANT MONFREDINI PROPERTIES LLC South San Francisco, California 94080 (650) 873-0440

More information

RIT CAD Specifications

RIT CAD Specifications RIT CAD Specifications The design team shall provide RIT with Revit, AutoCAD, and PDF files that capture the construction conditions of the associated project. This document outlines requirements for submitting

More information

Updated Sheet Index for DRC Submittal A0.1

Updated Sheet Index for DRC Submittal A0.1 Sheet Index Landscape Architecture A0.0 Cover Sheet A0.1 Sheet Index A0.2 Enhanced Perspective A0.3 Enhanced Perspective A0.4 Enhanced Perspective A0.5 Enhanced Perspective A0.6 Enhanced Perspective A0.7

More information

UTSA Facilities Condition Assessment. Out Brief August XX, 2009

UTSA Facilities Condition Assessment. Out Brief August XX, 2009 UTSA Facilities Condition Assessment Out Brief August XX, 2009 Agenda Opening Remarks FCA Results Summary by Category Example Deficiencies FCA Results Summary by Building Proposed Project List Potential

More information

Delivering Reliability. Services. Strength You Can Count On. oldcastleprecast.com/services

Delivering Reliability. Services. Strength You Can Count On. oldcastleprecast.com/services Delivering Reliability A Strength You Can Count On SERVICES TENANT IMPROVEMENTS Above And Below Ground Solutions Strength You Can Count On Oldcastle Precast is well trained and knowledgeable in all aspects

More information

214 Wilshire Blvd., Suite 102 Santa Monica California 90401

214 Wilshire Blvd., Suite 102 Santa Monica California 90401 Wilshire Blvd., Suite 0 Santa Monica California 900 7 W a l l a c e P l. C a l i f o r n i a 9 8 t e l : 0 7 7 N ND COURT PROPERTY LINE 0.00' THE RENOVATION AND CHANGE OF USE OF AN EXISTING BOOK STORE

More information

Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review

Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review Step 1: Request for Conditional Approval, page 1 of 5 Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review I,, the Property Owner, or Owner

More information

Paul Cuffe Math-Science Technology Academy ES 8324 S Racine Ave Chicago, IL 60620

Paul Cuffe Math-Science Technology Academy ES 8324 S Racine Ave Chicago, IL 60620 82 S Racine Ave Chicago, IL 020 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

ouglas Intermediate School

ouglas Intermediate School ouglas Intermediate School DOUGLAS INTERMEDIATE/ELEMENTARY SCHOOL Board of Selectmen / Finance Committee February 15, 2011 DiNisco Design www.dinisco.com Site Discussion Site Discussion Site Discussion

More information

DRAFT FOR INTERNAL DISCUSSION ONLY

DRAFT FOR INTERNAL DISCUSSION ONLY Jameson St. 2 Riser Room Cistern Base Men's Locker Room Women's Locker Room Mud Room Stair Elev. Entry Lobby Shipping and Receiving Stair EO/IO Breakdown A40 Shop / Warehouse Alley Gilman Pl. Storage Room

More information

New Denver, BC FEASIBILITY REPORT OCTOBER 2018 BOSUN HALL. p f

New Denver, BC FEASIBILITY REPORT OCTOBER 2018 BOSUN HALL.   p f BOSUN HALL New Denver, BC FEASIBILITY REPORT OCTOBER 2018 www.coverac.ca p. 250.354.4445 f. 250.352.0017 OVERVIEW Bosun Hall is the heart of New Denver community life, and provide space for events such

More information

Gated Apartment Community. Silver Springs LUXURY LIVING SPACES

Gated Apartment Community. Silver Springs LUXURY LIVING SPACES Gated Apartment Community Silver Springs LUXURY LIVING SPACES BE IN THE MOST DELIGHTFUL WORLD THERE IS... Welcome to an idea called Invicon! Invicon, located in Tambaram, the bustling hub that scores on

More information

James Shields Middle School 2611 W 48th St Chicago, IL 60632

James Shields Middle School 2611 W 48th St Chicago, IL 60632 2 W 48th St Chicago, IL 02 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

DOCUMENT SUBMITTAL REQUIREMENTS FOR A NEW MULTI-FAMILY DWELLING

DOCUMENT SUBMITTAL REQUIREMENTS FOR A NEW MULTI-FAMILY DWELLING INFORMATION BULLETIN / GENERAL INFORMATION REFERENCE NO.: None DOCUMENT NO. P/GI 2014-007 Previously Issued As: P/GI 2011-007 Effective: 01-01-2014 Revised: DOCUMENT SUBMITTAL REQUIREMENTS FOR A NEW MULTI-FAMILY

More information

Monarch THE. Estate Series ELEVATION 3

Monarch THE. Estate Series ELEVATION 3 THE Monarch ELEVATION 3 Estate Series Additional Elevations ELEVATION 1 ELEVATION 2 ELEVATION 3 ELEVATION 4 Morning 14'0" x 13'9" Gas Famy First Floor Kitchen 22'0" x 16'7" But-In Sliding Glass oor Gas

More information

Architectural Design Process

Architectural Design Process Architectural Design Process Custom Residential A. Schematic Design Phase Pre-Design Meeting Site Analysis Site Survey Conceptual Design & Project Scope Design Program Guideline Project Team Formation

More information

Town of Belmont, NH. Town Space Needs and Feasibility Study. January 10, 2019

Town of Belmont, NH. Town Space Needs and Feasibility Study. January 10, 2019 Town of Belmont, NH Town Space Needs and Feasibility Study January 10, 2019 Police Department EXISTING POLICE DEPARTMENT FULLER STREET MEETING HOUSE SARGENT STREET TOWN OF BELMONT POLICE DEPARTMENT EXISTING

More information

Contents OVERVIEW INTRODUCTION TO CHIEF ARCHITECT GETTING READY TO DRAW QUICK START VACATION CABIN: FLOOR PLAN. How this Book is Put Together

Contents OVERVIEW INTRODUCTION TO CHIEF ARCHITECT GETTING READY TO DRAW QUICK START VACATION CABIN: FLOOR PLAN. How this Book is Put Together Contents OVERVIEW How this Book is Put Together Conventions Icon Key Files on the Website INTRODUCTION TO CHIEF ARCHITECT The Chief Architect Interface Working with the Toolbars Chief Architect s Views

More information

Wendell E Green Elementary School 1150 W 96th St Chicago, IL 60643

Wendell E Green Elementary School 1150 W 96th St Chicago, IL 60643 11 W 9th St Chicago, IL 3 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

LAWRENCE PUBLIC LIBRARY ADDITION/RENOVATION creating a new civic hub for the city of lawrence, kansas

LAWRENCE PUBLIC LIBRARY ADDITION/RENOVATION creating a new civic hub for the city of lawrence, kansas LAWRENCE PUBLIC LIBRARY ADDITION/RENOVATION creating a new civic hub for the city of lawrence, kansas Visibility to neighborhood The continuous wrap of the new addition is designed to respond to each of

More information

Allan Hancock College

Allan Hancock College Allan Hancock College Project Planning Board Workshop February 17, 2009 Agenda Objective Funding Allocation Space Demand Analysis Project Overview Bond Measure I Program Schedule Charge: To review funding

More information

COTTAGES AT OVERBROOK THE 'WOODSIDE' 541 LOWNDES HILL ROAD GREENVILLE, SC

COTTAGES AT OVERBROOK THE 'WOODSIDE' 541 LOWNDES HILL ROAD GREENVILLE, SC GREENVILLE, SC TYPE: MUNICIPAL ADDRESS: CUSTOM RESIDENTIAL XXX STREET GREENVILLE SC, 9607 A E J P T : OWNER:, LLC TAX MAP #: PROPERTY AREA: ZONING DISTRICT: BUILDING MATERIAL: BUILDING HEIGHT: FOUNDATION

More information

Deck Tutorial. Chapter 8: Decks and Porches

Deck Tutorial. Chapter 8: Decks and Porches Decks and Porches Chapter 8: Deck Tutorial Now we ll continue where the Landscaping Tutorial left off and create a deck off the back of the house, connecting it to the terrain with an exterior staircase.

More information

GUIDELINES FOR SUBMISSION OF FINAL PLAN MATERIALS FOR BOARD OF TRUSTEES PRESENTATIONS MAJOR PROJECTS

GUIDELINES FOR SUBMISSION OF FINAL PLAN MATERIALS FOR BOARD OF TRUSTEES PRESENTATIONS MAJOR PROJECTS Updated: June 2018 GUIDELINES FOR SUBMISSION OF FINAL PLAN MATERIALS FOR BOARD OF TRUSTEES PRESENTATIONS MAJOR PROJECTS 1. Formal Presentations are made to the University's Board of Trustees in February,

More information

Get out your notes and turn to Understand, Identify, and Label Floor Plans. If you don t have notes yet you can pick up copies on the back counter.

Get out your notes and turn to Understand, Identify, and Label Floor Plans. If you don t have notes yet you can pick up copies on the back counter. Get out your notes and turn to Understand, Identify, and Label Floor Plans If you don t have notes yet you can pick up copies on the back counter. It costs no more to build a house with a good plan, than

More information

Presented by Steven Hallam 8/8/2017 (209)

Presented by Steven Hallam 8/8/2017 (209) Prepared for Presented by Steven Hallam 8/8/2017 (209) 538-5756 steve.hallam@ci.ceres.ca.us Properties for Lease 1 1768-1788 Mitchell Road, Space Available 1,200-4,665 SF Rental Rate Yr $17.40-18 /SF/Yr

More information

A-1. CDP and Use Permit Amendment. Title Sheet. the. Attachment. 1. Railing a soffit: trex Composite d in tree hous. 2. storefro BRonze ano aluminum F

A-1. CDP and Use Permit Amendment. Title Sheet. the. Attachment. 1. Railing a soffit: trex Composite d in tree hous. 2. storefro BRonze ano aluminum F the Arri. Railing a soffit: trex Composite d in tree hous. storefro BRonze ano aluminum F 3. glulam t Wood stain White (sw3 4. landscap Walls: Boa ConCRete 5. exterior a Wall: shou Ban Wood p CDP and Use

More information

Continuing Education Credit

Continuing Education Credit BIM + CM-at-RISK = Saves You Time & $$$ Especially on Renovation Projects PeterMcElwain,AIA ArtCampbell,AIA Facilities/Planning RickScott,LEEDAP,CPC JohnCook.CPC CM-at-Risk/Construction JenniferS.Henrikson,AIA,LEEDAP

More information

Michelle Muro, AIA, NCARB

Michelle Muro, AIA, NCARB Michelle Muro, AIA, NCARB Portfolio of Work jj_mj_muro@yahoo.com 720 425 0842 AT & T Broadband World Headquarters, Denver, Colorado Barber Architecture, Intern: 1997 2001 For the interiors, Barber Architecture

More information

DOWNTOWN WESTMINSTER, CO KEY PLAN ARCHITECTURAL CONCEPT PLAN W 92ND AVE B-6 C-7 90TH AVE D-5 D-6 CENTRAL AVE C-6 B-7 A-5 D-4 EATON ST B-5

DOWNTOWN WESTMINSTER, CO KEY PLAN ARCHITECTURAL CONCEPT PLAN W 92ND AVE B-6 C-7 90TH AVE D-5 D-6 CENTRAL AVE C-6 B-7 A-5 D-4 EATON ST B-5 APPROVAL OF THE ARCHITECTURAL CONCEPT PLAN SIGNIFIES THAT THE GENERAL ARCHITECTURAL AND MASSING ALIGNS WITH THE VISION FOR THE DOWNTOWN. DEVELOPMENT REVIEW AGAINST THE STANDARDS AND GUIDELINES OF THE DOWNTOWN

More information

Dimension Below are the critical settings in AutoCAD. Other software should follow the same settings.

Dimension Below are the critical settings in AutoCAD. Other software should follow the same settings. 8.1 Drawing Standard 8.1.1 Introduction This drawing standard applies to all building drawings being prepared for the University of Calgary (UCalgary) by external consultants or vendors and internal staff

More information

Michigan THE. Colonial Series ELEVATION 4

Michigan THE. Colonial Series ELEVATION 4 THE Michigan ELEVATION 4 Colonial Series Additional Elevations ELEVATION 1 ELEVATION 2 ELEVATION 3 ELEVATION 4 f. ce met First Floor Wall Oven Gourmet Gourmet Pantry Pan Morning Sliding Glass Pantry Pantry

More information

Amos Alonzo Stagg Elementary School

Amos Alonzo Stagg Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

RESOLUTION NO. R VILLAGE OF SHOREWOOD HILLS A RESOLUTION APPROVING A SPECIFIC DEVELOPMENT PLAN FOR PROPERTY LOCATED AT 2801 MARSHALL COURT

RESOLUTION NO. R VILLAGE OF SHOREWOOD HILLS A RESOLUTION APPROVING A SPECIFIC DEVELOPMENT PLAN FOR PROPERTY LOCATED AT 2801 MARSHALL COURT RESOLUTION NO. R-2018-8 VILLAGE OF SHOREWOOD HILLS A RESOLUTION APPROVING A SPECIFIC DEVELOPMENT PLAN FOR PROPERTY LOCATED AT 2801 MARSHALL COURT RECITALS 1. The Village of Shorewood Hills ("Village")

More information

Exhibit A Project Identification. Exhibit B Project Charter / Project Intent. Exhibit C Project Scope. Exhibit C Project Schedule

Exhibit A Project Identification. Exhibit B Project Charter / Project Intent. Exhibit C Project Scope. Exhibit C Project Schedule Exhibit A Project Identification Exhibit B Project Charter / Project Intent Exhibit C Project Scope Exhibit C Project Schedule Exhibit D Project Budget Exhibit E Owner Supplied Documents Exhibit F Sample

More information

CS2.0 COVER SHEET VOL. 2

CS2.0 COVER SHEET VOL. 2 ARCHITECT GEORGE CROMWELL ELEMENTARY SCHOOL REVITALIZATION 525 Wellham Avenue Glen Burnie, Maryland 21061 OWNER ANNE ARUNDEL COUNTY PUBLIC SCHOOLS 9034 FT. SMALLWOOD ROAD PASADENA, MARYLAND 21122 tel:

More information

Design Process. Hand Sketching for Interiors Developing Visual Illustration Techniques SDC. Better Textbooks. Lower Prices.

Design Process. Hand Sketching for Interiors Developing Visual Illustration Techniques SDC. Better Textbooks. Lower Prices. Design Process Hand Sketching for Interiors Developing Visual Illustration Techniques Rick L. Bartholomew, RID SDC P U B L I C AT I O N S Schroff Development Corporation Better Textbooks. Lower Prices.

More information

NON-RESIDENTIAL DEVELOPMENT

NON-RESIDENTIAL DEVELOPMENT GENERAL REQUIREMENTS (Print or Type) Name of Proposed Project: Location of Project: Legal Description of Project (Assessor s Parcel No. or T, R,S): Staff Use Only FILE NO.: RELATED FILES: Applicant s Name:

More information

1. Name the horizontal member that rests on the foundation wall to support other wood members.

1. Name the horizontal member that rests on the foundation wall to support other wood members. Student Name: Teacher: Date: District: Rowan Assessment: 9_12 T and I IC62 - Drafting - Architr II Test 1 Description: Unit C - Floorplans - Test 3 (ALL) Form: 501 1. Name the horizontal member that rests

More information

St. John s United Methodist Church Facility Stewardship Plan Last update: 9 May 2011

St. John s United Methodist Church Facility Stewardship Plan Last update: 9 May 2011 As responsible stewards of our facility, this list is maintained by the trustees to identify tasks we need to have completed to keep our church well groomed and attractive to present a welcoming, safe,

More information

For Lease CLASS A MEDICAL/OFFICE/CREATIVE SPACE

For Lease CLASS A MEDICAL/OFFICE/CREATIVE SPACE MAJOR RENOVATIONS UNDERWAY For Lease CLASS A MEDICAL/OFFICE/CREATIVE SPACE 10301 N. 92ND ST SCOTTSDALE, ARIZONA COLLIERS INTERNATIONAL 8360 E. RAINTREE DR. SUITE 130 SCOTTSDALE, AZ 85260 www.colliers.com/greaterphoenix

More information

Summary of Modifications/Changes in this Update

Summary of Modifications/Changes in this Update Summary of Modifications/Changes in this Update This Summary of Changes is for information only. It is not a part of the referenced document, and should not be used for project documentation. U.S. Department

More information

Deck Tutorial. Decks and Porches. Drawing Decks

Deck Tutorial. Decks and Porches. Drawing Decks Deck Tutorial The Deck Tutorial continues where the Landscaping Tutorial left off, and explains how to create a deck off the back of the house and connect it to the terrain with an exterior staircase.

More information

ENGINEERING GRAPHICS AND DESIGN

ENGINEERING GRAPHICS AND DESIGN GUIDELINES FOR THE PRACTICAL ASSESSMENT TASK GRADE 12 2016 ENGINEERING GRAPHICS AND DESIGN EXTERNALLY MODERATED AND APPROVED BY UMALUSI THIS GUIDELINE CONSISTS OF 14 PAGES 1. INTRODUCTION: A. The Structure

More information

Wendell Smith Elementary School

Wendell Smith Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual