Town of Belmont, NH. Town Space Needs and Feasibility Study. January 10, 2019
|
|
- Kristopher Morton
- 5 years ago
- Views:
Transcription
1 Town of Belmont, NH Town Space Needs and Feasibility Study January 10, 2019
2 Police Department
3 EXISTING POLICE DEPARTMENT FULLER STREET MEETING HOUSE SARGENT STREET TOWN OF BELMONT POLICE DEPARTMENT EXISTING CONDITIONS
4 FIRST FLOOR EXISTING FOOTPRINT (3,600 SF) 3 IMPOUND LOT ACCESSORY VEHICLES SECURITY FENCE 7 PD CRUISERS PD CRUISERS U P SALLY PORT 440 SF SALLY PORT SUPPORT 965 SF EVIDENCE STOR. LONG TERM EVIDENCE COLD ST. SUPPORT 1,020 SF LOCKERS KITCHEN/BREAK RM TECH RM ARMORY JANITORIAL MECHANICAL BOOKING & INTAKE 508 SF 4 VISITOR PARKING PUBLIC SPACES 394 SF DISPATCH 225 SF PUBLIC SPACES MAIN U P ADDITION VEHICLE AREAS: NET GROSS UPPER LEVEL 2,052 SF 2,462 SF LOWER LEVEL 3,552 SF 4,200 SF TOTAL 5,604 SF 6,662 SF PARKING TOTALS: VISITOR PARKING: 4 SPACES EMPLOYEE PARKING: 13 SPACES PD CRUISERS: 13 SPACES IMPOUND LOT: 3 SPACES ACCESS. VEHICLES: 3 SPACES TOTAL SPACES: 36 SPACES FULLER STREET 3 LEGEND EMPLOYEE PARKING 5 MEETING HOUSE EXISTING BUILDING VEHICLE EXIT NEW ADDITION SARGENT STREET TOWN OF BELMONT POLICE DEPARTMENT OPTION A
5 SECOND FLOOR EXISTING FOOTPRINT (3,600 SF) U P ADMIN SUITE 672 SF ADMIN SUITE ROOF BELOW CONFERENCE 240 SF ROOF BELOW PD STAFF PD STAFF 1,140 SF ROOF BELOW U P ADDITION AREAS: NET GROSS UPPER LEVEL 2,052 SF 2,462 SF LOWER LEVEL 3,552 SF 4,200 SF TOTAL 5,604 SF 6,662 SF PARKING TOTALS: VISITOR PARKING: 4 SPACES EMPLOYEE PARKING: 13 SPACES PD CRUISERS: 13 SPACES IMPOUND LOT: 3 SPACES ACCESS. VEHICLES: 3 SPACES FULLER STREET TOTAL SPACES: 36 SPACES PARKING BELOW MEETING HOUSE LEGEND EXISTING BUILDING NEW ADDITION SARGENT STREET TOWN OF BELMONT POLICE DEPARTMENT OPTION A
6 GAZEBO BELMONT PUBLIC LIBRARY MAIN STREET TOWN OF BELMONT POLICE DEPARTMENT EXISTING CONDITIONS
7 VEHICLE VEHICLE EXIT EMPLOYEE PARKING DRIVING LANE 519 FT VISITOR PARKING SECURITY GATE 7 MAIN 4 SALLY PORT DRIVING LANE SALLY PORT 440 SF BOOKING & INTAKE 508 SF IMPOUND LOT SUPPORT 660 SF CONFERENCE TECH RM ARMORY JANITORIAL/MECHANICAL SUPPORT 965 SF EVIDENCE STOR. LONG TERM EVIDENCE COLD STORAGE EMPLOYEE PARKING 9 ACCESSORY VEHICLES PUBLIC SPACES 394 SF SUPPORT 600 SF 120 FT DRIVING LANE DISPATCH 225 SF LOCKER ROOMS KITCHEN STAFF BREAK ROOM PD STAFF 1140 SF STAFF 519 FT PD CRUISERS ADMIN SUITE 672 SF 3 PD CRUISERS PD CRUISERS 56 FT 3 MILL STREET LEVEL PARKING TOTALS: VISITOR PARKING: 4 SPACES EMPLOYEE PARKING: 16 SPACES PD CRUISERS: 13 SPACES IMPOUND LOT: 3 SPACES ACCESS. VEHICLES: 3 SPACES TOTAL PD SPACES: 39 SPACES GAZEBO BELMONT PUBLIC LIBRARY FT MAIN STREET TOWN OF BELMONT POLICE DEPARTMENT OPTION B ONE STORY ON BANK SITE (+/- 6,700 GSF)
8 VEHICLE DRIVING LANE VEHICLE EXIT DRIVING LANE 10 EMPLOYEE PARKING 12 PD CRUISERS SECURITY GATE 519 FT SALLY PORT DRIVING LANE ACCESSORY VEHICLES 2 U P SALLY PORT 440 SF SUPPORT 625 SF EVIDENCE STORAGE IMPOUND LOT IMPOUND LOT 3 BOOKING & INTAKE 508 SF LONG TERM EVIDENCE 196 SF SUPPORT 660 SF SUPPORT 500 SF LOCKERS KITCHEN BREAK RM SCREEN WALL 88 FT AREAS: NET GROSS UPPER LEVEL 2,671 SF 3,205 SF LOWER LEVEL 2,929 SF 3,515 SF TOTAL 5,600 SF 6,720 SF PARKING TOTALS: VISITOR PARKING: 9 SPACES EMPLOYEE PARKING: 15 SPACES PD CRUISERS: 12 SPACES IMPOUND LOT: 3 SPACES ACCESS. VEHICLES: 2 SPACES TOTAL SPACES: 36 SPACES GAZEBO BELMONT PUBLIC LIBRARY DRIVING LANE RETAINING WALL U P TECH RM COLD STORAGE ARMORY JANITORIAL MECHANICAL RETAINING WALL PARKING ABOVE AT MAIN STREET LEVEL 528 FT LOWER LEVEL (MILL STREET LEVEL) MAIN STREET TOWN OF BELMONT POLICE DEPARTMENT OPTION C TWO-STORY ON BANK SITE
9 519 FT SECURITY GATE 519 FT SCREEN WALL U P CONFERENCE 240 SF AREAS: NET GROSS UPPER LEVEL 2,671 SF 3,205 SF LOWER LEVEL 2,929 SF 3,515 SF PARKING BELOW ADMIN SUITE 672 SF TOTAL PARKING TOTALS: 5,600 SF 6,720 SF PD STAFF 1,140 SF PUBLIC SPACES 394 SF EXTERIOR BALCONY DISPATCH 225 SF 88 FT VISITOR PARKING: 9 SPACES EMPLOYEE PARKING: 15 SPACES PD CRUISERS: 12 SPACES IMPOUND LOT: 3 SPACES ACCESS. VEHICLES: 2 SPACES TOTAL SPACES: 36 SPACES BELMONT PUBLIC LIBRARY U P GAZEBO RETAINING WALL RETAINING WALL 8 MAIN 6 0 ft. 12 ft. 20 ft. 40 ft. EMPLOYEE & VISITOR PARKING EMPLOYEE & VISITOR PARKING EXISTING VEHICLE EXIT 528 FT VISITOR PARKING UPPER LEVEL (MAIN STREET LEVEL) EXISTING VEHICLE MAIN STREET TOWN OF BELMONT POLICE DEPARTMENT OPTION C TWO-STORY ON BANK SITE
10 528 FT MAIN STREET UPPER LEVEL LOWER LEVEL MILL STREET 519 FT SITE SECTION BANK SITE 2-STORY OPTION OPTION C TWO-STORY ON BANK SITE 528 FT MAIN STREET 1-STORY MILL STREET 519 FT SITE SECTION BANK SITE 1-STORY OPTION OPTION B ONE STORY ON BANK SITE TOWN OF BELMONT POLICE DEPARTMENT CONCEPTUAL SITE SECTIONS
11 APRROX. 212 FEET 3 IMPOUND LOT 3 ACCESSORY VEHICLES 15 EMPLOYEE PARKING PARKING TOTALS: VISITOR PARKING: 4 SPACES EMPLOYEE PARKING: 15 SPACES PD CRUISERS: 12 SPACES IMPOUND LOT: 3 SPACES ACCESS. VEHICLES: 3 SPACES STAFF SUPPORT 965 SF TOTAL SPACES: 37 SPACES APPROX. 122 FT 12 PD CRUISERS SALLY PORT BOOKING & INTAKE 508 SF SALLY PORT 440 SF SUPPORT 660 SF SUPPORT 965 SF EVIDENCE STORAGE LONG TERM EVIDENCE COLD STORAGE CONFERENCE TECH ROOM ARMORY JANITORIAL/MECHANICAL PD STAFF 1140 SF ADMIN SUITE 672 SF SUPPORT 600 SF LOCKER ROOMS KITCHEN STAFF BREAK ROOM PUBLIC SPACES 394 SF DISPATCH 225 SF 2 MAIN 2 VISITOR PARKING VISITOR PARKING SECURITY GATE POTENTIAL VEHICULAR & EXIT SECURITY GATE POTENTIAL VEHICULAR & EXIT ONE STORY +/- 6,700 GSF APPROX. SITE = 25,864 SF / 0.6 ACRES POTENTIAL VEHICULAR & EXIT TOWN OF BELMONT POLICE DEPARTMENT SCALE: 1" = 16'-0" OPTION D ONE-STORY NEW BUILDING ON UNDETERMINED SITE
12 Town Hall
13 GAZEBO BELMONT PUBLIC LIBRARY MAIN STREET TOWN OF BELMONT TOWN HALL EXISTING CONDITIONS
14 DRIVING LANE 519 FT VISITOR PARKING VISITOR PARKING 6 MAIN 4 WELLFARE 378 SF TOWN CLERK 800 SF LOBBY 256 SF PUBLIC COMMON SPACES 665 SF LG MEETING RM 600 SF DRIVING LANE TOWN ADMIN SF CONFERENCE 192 SF GAZEBO TOWN STORAGE 1340 SF LAND USE OFF-SITE ST. SEASONAL ITEMS ST. ADMIN, FININANCE, CLERK ST. STAFF SUPPORT 283 SF LAND USE 1488 SF 3 PARKS & REC 1204 SF BELMONT PUBLIC LIBRARY PARKING TOTALS: 519 FT DRIVING LANE EMPLOYEE PARKING STAFF EMPLOYEE PARKING VISITOR PARKING: 10 SPACES EMPLOYEE PARKING: 15 SPACES TOTAL SPACES: 25 SPACES FT MAIN STREET TOWN OF BELMONT TOWN HALL OPTION A ONE-STORY ON BANK SITE (+/- 9,400 GSF)
15 519 FT DRIVING LANE EMPLOYEE PARKING VISITOR & EMPLOYEE PARKING 6 5 U P WELLFARE 387 SF PARKS & REC 1204 SF TOWN ADMIN SF CONFERENCE 192 SF TOWN STORAGE 1140 SF LAND USE OFF-SITE ST. SEASONAL ITEMS ST. ADMIN, FININANCE, CLERK ST. AREAS: NET GROSS UPPER LEVEL 4,146 SF 5,890 SF LOWER LEVEL 4,092 SF 5,890 SF TOTAL PARKING TOTALS: 8,238 SF 11,780 SF VISITOR PARKING: 10 SPACES EMPLOYEE PARKING: 15 SPACES TOTAL SPACES: 25 SPACES GAZEBO BELMONT PUBLIC LIBRARY U P RETAINING WALL RETAINING WALL PARKING ABOVE AT MAIN STREET LEVEL 528 FT LOWER LEVEL (MILL STREET LEVEL) MAIN STREET TOWN OF BELMONT TOWN HALL OPTION B TWO-STORY ON BANK SITE
16 519 FT U P PARKING BELOW PARKING BELOW TOWN CLERK 800 SF LAND USE 1488 SF AREAS: NET GROSS UPPER LEVEL 4,146 SF 5,890 SF LOWER LEVEL 4,092 SF 5,890 SF TOTAL 8,238 SF 11,780 SF LG MEETING RM 600 SF U P LOBBY 256 SF COMMON SPACES 948 SF COPY/PRINTER SUPPLIES/MAIL BREAK ROOM TOILETS MECHANICAL CUST. / IT PARKING TOTALS: VISITOR PARKING: 10 SPACES EMPLOYEE PARKING: 15 SPACES TOTAL SPACES: 25 SPACES GAZEBO BELMONT PUBLIC LIBRARY RETAINING WALL RETAINING WALL EMPLOYEE PARKING 8 9 EXISTING VEHICLE EXIT VISITOR PARKING 528 FT MAIN 6 VISITOR PARKING EXISTING VEHICLE UPPER LEVEL (MAIN STREET LEVEL) MAIN STREET TOWN OF BELMONT TOWN HALL OPTION B TWO-STORY ON BANK SITE
17 528 FT MAIN STREET UPPER LEVEL LOWER LEVEL MILL STREET 519 FT SITE SECTION BANK SITE 2-STORY OPTION OPTION B TWO-STORY ON BANK SITE 528 FT MAIN STREET 1-STORY MILL STREET 519 FT SITE SECTION BANK SITE 1-STORY OPTION OPTION A ONE-STORY ON BANK SITE TOWN OF BELMONT TOWN HALL CONCEPTUAL SITE SECTIONS
18 EXISTING MILL BUILDING MILL STREET EXISTING CONDITIONS
19 8 EMPLOYEE PARKING EMPLOYEE PARKING 6 MAIN ELEV VEST. MECH. MECH. FIRST FLOOR EXISTING GROSS AREA: 3,955 SF PARKING TOTALS: EMPLOYEE PARKING DRIVING LANE VISITOR PARKING 10 8 TOWN STORAGE 1340 SF LAND USE OFF-SITE STOR. ADMIN, FINANCE, CLERK STOR. SEASONAL ITEMS STOR. TLT 75 SF CUST. 80 SF LOBBY 256 SF TLT 75 SF TOILETS 150 SF WELLFARE 378 SF TOWN CLERK 584 SF VISITOR PARKING: 17 SPACES EMPLOYEE PARKING: 24 SPACES TOTAL SPACES: 40 SPACES VISITOR PARKING EXISTING VEHICLE /EXIT 12 9 EXISTING VEHICLE MILL STREET OPTION C MILL BUILDING SITE
20 ELEV ELEV ELEV ROOF PARKS & BELOW TOWN RECREATION LAND USE ADMINISTRATOR DEPARTMENT VEST. VEST. DEPARTMENT VEST. DEPARTMENT ELEC. ELEC. ELEC. P&R DIR. 100 SF SUPER. OFF. 100 SF FILES 100 SF KITCHEN 120 SF 600 SF LG MEETING RM BUILDING OFFICIAL 300 SF CLERK 64 SF ADMIN 64 SF MECH. 150 SF LAND USE WORK RM 520 SF FINANCE DIRECTOR 140 SF SECRETARY 140 SF TLT 75 SF CONFERENCE 192 SF WATER/SEWER 160 SF FUNCTION RM EXERCISE RM 600 SF RECEPT. 64 SF 150 SF EXERCISE TOILETS STOR. 100 SF TOILETS 150 SF COMMON SPACES 320 SF COMMON 320 SF SPACES COPY/PRINTER COPY/PRINTER SUPPLIES/MAIL SUPPLIES/MAIL BREAK ROOM BREAK ROOM PLANNER 120 SF PUBLIC ACCESS 120 SF TOILETS 150 SF TOWN CLERK DEAD FILES 216 SF LAND USE TECH 300 SF TOWN. ADMIN OFFICE 192 SF ASSIST. TA 140 SF TLT 75 SF ST. FILE ROOM 180 SF BLDG & GND ST. 100 SF BLDG & GROUNDS 150 SF 80 ITSF 55 ITSF CUST. 80 SF 55 ITSF IT 55 SF 2 ND FLOOR EXISTING GROSS AREA: 3,821 SF 3 RD FLOOR EXISTING GROSS AREA: 3,817 SF 4 TH FLOOR EXISTING GROSS AREA: 3,222 SF OPTION C MILL BUILDING SITE
21 8 EMPLOYEE PARKING EMPLOYEE PARKING 6 MAIN ELEV VEST. MECH. MECH. FIRST FLOOR EXISTING GROSS AREA: 3,955 SF PARKING TOTALS: RENTAL SPACE 1340 SF LOBBY 256 SF TLT 75 SF WELLFARE 378 SF VISITOR PARKING: 17 SPACES EMPLOYEE PARKING: 24 SPACES TOTAL SPACES: 40 SPACES EMPLOYEE PARKING DRIVING LANE VISITOR PARKING 10 8 TLT 75 SF CUST. 80 SF TOILETS RENTAL SPACE 150 SF 584 SF NOTE: PARKS & REC AND TOWN STOAGE WILL BE LOCATED IN THE RENOVATED PD BUILDING (BASED ON PD RELOCATION) VISITOR PARKING EXISTING VEHICLE /EXIT 12 9 EXISTING VEHICLE MILL STREET OPTION C-1 MILL BUILDING SITE
22 ELEV ELEV ELEV ROOF BELOW TOWN TOWN CLERK LAND USE ADMINISTRATOR DEPARTMENT VEST. VEST. DEPARTMENT VEST. DEPARTMENT ELEC. ELEC. ELEC. TOWN CLERK DEPUTY CLERK FILES 600 SF LG MEETING RM BUILDING OFFICIAL CLERK ADMIN MECH. LAND USE WORK RM FINANCE DIRECTOR SECRETARY TLT CONFERENCE WATER/SEWER DEAD FILES PUBLIC ACCESS WORK STATION 150 VAULT SF TOILETS TOILETS COMMON SPACES 320 SF COMMON SPACES COPY/PRINTER COPY/PRINTER SUPPLIES/MAIL SUPPLIES/MAIL BREAK ROOM BREAK ROOM PLANNER PUBLIC ACCESS TOILETS LAND USE STORAGE LAND USE TECH TOWN. ADMIN OFFICE ASSIST. TA TLT ST. FILE ROOM BLDG & GND ST. BLDG & GROUNDS 80 ITSF IT CUST. 80 SF IT IT 2 ND FLOOR EXISTING GROSS AREA: 3,821 SF 3 RD FLOOR EXISTING GROSS AREA: 3,817 SF 4 TH FLOOR EXISTING GROSS AREA: 3,222 SF NOTE: PARKS & REC AND TOWN STOAGE WILL BE LOCATED IN THE RENOVATED PD BUILDING (BASED ON PD RELOCATION) OPTION C-1 MILL BUILDING SITE
23 Conceptual Budgets
24
25
26
GAZEBO BELMONT PUBLIC LIBRARY MAIN STREET TOWN OF BELMONT TOWN HALL 12/14/2018 EXISTING CONDITIONS
GAZEBO BELMONT LIBRARY STREET TOWN OF BELMONT TOWN HALL EXISTING CONDITIONS DRIVING LANE 6 4 WELLFARE 378 SF TOWN CLERK 800 SF LOBBY 256 SF COMMON SPACES 665 SF LG MEETING RM 600 SF DRIVING LANE TOWN ADMIN.
More informationDRAFT FOR INTERNAL DISCUSSION ONLY
Jameson St. 2 Riser Room Cistern Base Men's Locker Room Women's Locker Room Mud Room Stair Elev. Entry Lobby Shipping and Receiving Stair EO/IO Breakdown A40 Shop / Warehouse Alley Gilman Pl. Storage Room
More informationSt. John Paul II Catholic Parish
St. John Paul II Catholic Parish 167th & Ridgeview Road Olathe, Kansas Master Plan Town Hall October 30, 2018 Purpose [ The Church s ] mission consists essentially in offering people an opportunity not
More informationCAC MEETING, FEB. 28 TH, 2017 NADAAA
ADAMS STREET BRANCH LIBRARY PROGRAMMING STUDY FOR CITY OF BOSTON BOSTON PUBLIC LIBRARY AND PUBLIC FACILITY DEPARTMENT CAC MEETING, FEB. 28 TH, 2017 NADAAA 1 AGENDA 1.0 SCHEDULE 2.0 SUMMARY OF PROJECT GOAL
More informationSouthern Oregon University
Southern Oregon University Public Meeting Notice August 5, 05 TO: FROM: RE: Southern Oregon University Board of Trustees, Finance Committee Sabrina Prud homme, University Board Secretary Notice of special
More informationouglas Intermediate School
ouglas Intermediate School DOUGLAS INTERMEDIATE/ELEMENTARY SCHOOL Board of Selectmen / Finance Committee February 15, 2011 DiNisco Design www.dinisco.com Site Discussion Site Discussion Site Discussion
More informationROBERT TURNER COLLEGE AND CAREER HIGH SCHOOL
ROBERT TURER COLLEGE AD CAREER HIGH SCHOOL SCHEMATIC DESIG PRESETATIO 23 MAY 2017 Project Milestones Schematic Design..... March May 2017 SD Presentation to Board of Trustees...... 23 May, 2017 Design
More informationASSIGNMENT 04: Library Massing + Program
ASSIGNMENT 04: Library Massing + Program THE IMPORTANCE OF PROGRAM AND MASSING DIAGRAMMING: Program and Massing diagrams are critical tools used to visually describe the relationship between the way a
More informationCORR 823 SF RR 152 ELEC 156 RR - B RR - G 159 LIBRARY 129 BREAK OUT AREA 1203 SF 796 SF 577 SF 142 COMMONS 130 CORR SF (120 STUDENTS)
Classrooms 2-3 scientists Morrison Maierle Classrooms K-1 Specials 146 planners Support surveyors 870 SF RR 147 148 RR 149 engineers 839 SF 150 COPYRIGHT (C) MORRISON-MAIERLE, INC., 2017 Admin Phone: 406.752.2216
More information754 Sir Francis Drake Boulevard
APN: 006-09 - 39 Town of San Anselmo Submittal Number : April 06 Revised June 0, 06 PROJECT TEAM INDEX TO DRAWINGS APPLICANT MONFREDINI PROPERTIES LLC South San Francisco, California 94080 (650) 873-0440
More informationRichardson olmsted complex core project Community Presentation. buffalo, new york
Richardson olmsted complex core project Community Presentation buffalo, new york 20 AUGUST 2013 DESIGN TEAM ARCHITECT Consulting design ARCHITECT consulting historic Preservation ARCHITECT Landscape ARCHITECT
More informationA-1. CDP and Use Permit Amendment. Title Sheet. the. Attachment. 1. Railing a soffit: trex Composite d in tree hous. 2. storefro BRonze ano aluminum F
the Arri. Railing a soffit: trex Composite d in tree hous. storefro BRonze ano aluminum F 3. glulam t Wood stain White (sw3 4. landscap Walls: Boa ConCRete 5. exterior a Wall: shou Ban Wood p CDP and Use
More informationAVAILABLE FOR LEASE OFFICE AND LABORATORY SPACE Approximately 322,384 RSF
AVAILABLE FOR LEASE AND SPACE Approximately 322,384 RSF 2400 Ellis Road Research Triangle Park, North Carolina www.goellisresearchcenter.com PROPERTY DESCRIPTION Administrative Wing Cafeteria Lobby/Atrium
More informationELLIS. Ellis Research Center PROPERTY HIGHLIGHTS BRIAN CARR, CCIM LEE CLYBURN. Research Triangle Park North Carolina.
ELLIS Research Triangle Park North Carolina Ellis Research Center Office and Lab PROPERTY HIGHLIGHTS 2400 Ellis Rd RTP, NC 27709 Size 331,898 RSF Floors 4 Parking Power 519 Shared parking spaces 480/277
More informationCOPYRIGHT ARCHITECT SUSAN DESKO-AIA
B:\03 ACAD Files\2 200.02.2 This Is It\DESIGN REVIEW\DR-0-.dwg 7/3/200 0:4 AM COVERED DROP-OFF 2 RECEPTION 3 LOBBY [2,800 SF] 4 WAITING AREA [450 SF] 5 FRONT DOOR & PATIO 6 VESTIBULE & AFTER HOURS ELEVATOR
More informationCentral High School. 275 Lexington Parkway North. Project Summary: Issues Identified By School Community In 2015
275 Lexington Parkway North Project Summary: Central is the oldest high school in the state of Minnesota, beginning its 150th year. Its rich traditions, including academic excellence, are widely celebrated.
More informationPacific Avenue Design Rationale 1155 Pacific Avenue, Kelowna, BC
Design Rationale On behalf of our client, Necessary Homes Inc, we have prepared a Development Permit application for a unit rental multi-family building at The site area of the property is 9 SM and is
More informationCherokee Heights Elementary School
694 Charlton Street Project Summary: Cherokee Heights Elementary is about to start its exciting transition to a Montessori learning model. The school is connected to the Baker Center which is currently
More information10300 / Eaton Place Fairfax, VA. Your Workday REIMAGINED
10300 / 10306 Eaton Place Fairfax, VA Your Workday REIMAGINED 66 20 MINUTES TO WASHINGTON, DC 123 12 MINUTES TO TYSONS CORNER EATON PLACE 50 25 MINUTES TO DULLES INTERNATIONAL AIRPORT Tenant Lounge Coming
More informationCohasset Town Hall. Programming Study A1.0. Town of Cohasset. 41 Highland Ave. Cohasset, MA NOT FOR CONSTRUCTION. Existing Basement Plan
Vault 008 29 SF Mechanical 002 395 SF 004 45 SF Cell 005 45 SF WATER SERVICE IN Cell 006 55 SF Jail 003 63 SF 007 92 SF Basement 00 740 SF Machine 027 60 SF Hall 009 275 SF 0 SF 00 54 SF Elevator 028 50
More informationA100 NOT FOR CONSTRUCTION 01 - SITE PLAN 01 - SITE KEYPLAN 1" = 60'-0"
4 PHEASANT LANE NORTH OAKS, MN 5527 P: 62.868.3636 206 RYLAUR LLC. 3405 ANNAPOLIS LANE, STE 00 SITE STATISTICS: SITE AREA: HARD SURFACE: GREEN AREA: BLDG AREA: 9,92 SF 7'-" RAIN GARDEN TODDLER PLAY AREA,756
More informationGUIDELINES FOR SUBMISSION OF FINAL PLAN MATERIALS FOR BOARD OF TRUSTEES PRESENTATIONS MAJOR PROJECTS
Updated: June 2018 GUIDELINES FOR SUBMISSION OF FINAL PLAN MATERIALS FOR BOARD OF TRUSTEES PRESENTATIONS MAJOR PROJECTS 1. Formal Presentations are made to the University's Board of Trustees in February,
More informationPlease comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at
Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf when using this file. Thank you. Target Value Design Case Study
More informationBASEBALL PLAYER FACILITIES CLEMSON, SOUTH CAROLINA
THROUGH THE YEARS THROUGH THE YEARS VIEW FROM RIGHT FIELD VIEW FROM DUGOUT VIEW FROM NEW GRANDSTAND EXISTING CONDITIONS EXTERIOR PHOTOS PLAYER S LOUNGE LOCKER ROOM TRAINING AREA COACH S OFFICE CORRIDOR
More informationSonoma Cheese Factory
WEST SPAIN STREET 1ST STREET WEST 1ST STREET EAST 0 10 25 2 W E S T S PA I N S T R E E T - S O N O M A, C A L I F O R N I A EXISTING AREA PLAN 50 100 w w w. s m s - a r c h. c o m WEST SPAIN STREET 1ST
More informationGREENWICH PUBLIC SCHOOLS New Lebanon ES Feasibility Expansion Study
GREENWICH PUBLIC SCHOOLS New Lebanon ES Feasibility Expansion Study New Lebanon School (K-5) 25 Mead Avenue, Greenwich, CT 20 March 2014 KSQ Architects PC 20 March 2014 GREENWICH PUBLIC SCHOOLS NEW LEBANON
More informationAshby, Pepperell, Townsend North Middlesex Regional High School. Feasibility Study Update
Ashby, Pepperell, Townsend North Middlesex Regional High School Feasibility Study Update June 6, 2013 AGENDA Preliminary Design Program (PDP) District Capacity Analysis Preferred Schematic Report (PSR)
More informationBluerock Center LONE TREE WAY > ANTIOCH, CA > OFFICE > RETAIL
Project Summary BLUEROCK CENTER in Antioch, CA is a Class A medical, office and retail project consisting of 121,000 square feet of state of the art buildings in a campus setting. The project is located
More informationCBRE - Las Vegas 3993 Howard Hughes Pkwy., Suite 700 Las Vegas, NV
TIVOLI VILLAGE HAS SET A NEW STANDARD FOR MIXED USE DEVELOPMENTS IN LAS VEGAS AND ACROSS THE COUNTRY. THIS 28-ACRE DEVELOPMENT RICH WITH EUROPEAN ARCHITECTURAL DETAILS OFFERS AN EXCLUSIVE DESTINATION ENVIRONMENT
More informationAUBURN VILLAGE SCHOOL ADDITION & RENOVATION Executive Team Meeting Minutes
AUBURN VILLAGE SCHOOL ADDITION & RENOVATION Executive Team Meeting Minutes Meeting No. 4 Date: 5/12/2018 Job No. Meeting Location: AVS Conference Room The following notes were taken during a meeting on
More information3,728 SF to 32,907 SF of contiguous space available
FOR LEASE One North Commerce Center 3,728 SF to 32,907 SF of contiguous space available A SIX-building, SinGle-Story office and flex park in North Raleigh + + Easy access to I-540 + + At the intersection
More informationCONCEPT SITE PLAN HOLLAND MIDDLE SCHOOL ADDITIONS & RENOVATIONS COUNCIL ROCK SCHOOL DISTRICT 400 EAST HOLLAND ROAD HOLLAND, PA 18966
COCEPT SITE PLA Scale: MECH. BAD CHORAL PRIC. SEC. COF. COPY/MAIL/ WORK MAI CLER. URSE SUITE COF. U. CLASS KITCHE TECH. TECH. CLASS CLASS STAGE AUDITORIUM 450 seats COTROL LARGE GRO 1150 SF CLASS LOBBY
More informationONE NORTH COMMERCE CENTER
3,728 SF TO 32,907 SF OF CONTIGUOUS SPACE AVAILABLE A SIX-BUILDING, SINGLE-STORY AND FLEX PARK IN NORTH RALEIGH + + Easy access to I-540 + + At the intersection of Capital Boulevard and Spring Forest Road,
More informationApril 7, Notice of Project Change Hyde Park Avenue, Jamaica Plain Phase C Rental Portion of Parcel U. Dear Director Golden:
April 7, 16 Mr. Brian Golden, Director Boston Redevelopment Authority One City Hall Square, Ninth Floor 021 Attn: Phil D. Cohen, Project Manager Re: Notice of Project Change nue, Jamaica Plain Phase C
More information24' - 0" 99' - 0" B15 B16 B17 B18 B19 SLOPE SLOPE BIKE STOR. / SERVICE 2 ACCESSIBLE COMMUNITY ACCESIBLE BIKE BIKE STORAGE ROOM STORAGE
5' ' 6 /4" RETAINING WALL ALONG BOUNDARY ILLUMINATED SIGNAGE TBD MOUNTED TO TOP AND/OR FACE OF RETAININGS WALL PROPERTIES FENCE TO REMAIN SIDEWALK ENTRY TIE NEW SIDE WALK INTO EXISTING SIDEWALKS AS CURRENTLY
More informationSpace Needs Summary: SPS/Health Center
3.3.1 Program Summary: SPS/Health Center 167 Space Needs Summary: SPS/Health Center PROGRAM ELEMENT PROPOSED NOTES No. (N) Type Name s Area Sub. ASF Total ASF STN. 10.0 Special Programs & Services / Project
More informationPBK 100% Schematic Design Presentation Dawson High School Additions and Renovations Pearland Independent School District \\ March 2017
PBK 100% Schematic Design Presentation Dawson High School Additions and Renovations Pearland Independent School District \\ March 2017 ARCHITECTURE \\ ENGINEERING \\ PLANNING \\ INTERIORS \\ TECHNOLOGY
More informationCohasset Town Hall - Programming Study REVIEW SET 7/07/2017 NOT FOR CONSTRUCTION. 41 Highland Ave. Cohasset, MA LOCUS MAP
- REVIEW SET 7/07/07 Highland Ave. Sheet Number DRAWING LIST Sheet Name A0.0 Cover A0. Site Plan - Existing A.0 Existing Basement Plan A. Existing First Floor Plan A. Existing Second Floor Plan A.0 Site
More informationCBRE - Las Vegas 3993 Howard Hughes Pkwy., Suite 700 Las Vegas, NV
TIVOLI VILLAGE HAS SET A NEW STANDARD FOR MIXED USE DEVELOPMENTS IN LAS VEGAS AND ACROSS THE COUNTRY. THIS 28-ACRE DEVELOPMENT RICH WITH EUROPEAN ARCHITECTURAL DETAILS OFFERS AN EXCLUSIVE DESTINATION ENVIRONMENT
More informationGREENWICH PUBLIC SCHOOLS. Greenwich, Connecticut REQUEST FOR BOARD ACTION OR PRESENTATION OF INFORMATIONAL ITEM
Date of Meeting: March 20, 2014 GREENWICH PUBLIC SCHOOLS Greenwich, Connecticut Title of Item: New Lebanon School Pre-Feasibility Study Policy Reference: E - 051 REQUEST FOR BOARD ACTION OR PRESENTATION
More informationThe Morgan School: Facility Assessment Findings and Recommendations of the Morgan School Building Committee. Clinton Town Hall January 20, 2011
The Morgan School: Facility Assessment Findings and Recommendations of the Morgan School Building Committee Clinton Town Hall January 20, 2011 Tonight s Agenda History of Morgan School and of the Building
More informationContinuing Education Credit
BIM + CM-at-RISK = Saves You Time & $$$ Especially on Renovation Projects PeterMcElwain,AIA ArtCampbell,AIA Facilities/Planning RickScott,LEEDAP,CPC JohnCook.CPC CM-at-Risk/Construction JenniferS.Henrikson,AIA,LEEDAP
More informationThe NEW Inner Harbor... Underway!!! Architects: QPK Design & Dalpos Architects Rendering: Spine 3D
The NEW Inner Harbor... Underway!!! Architects: QPK Design & Dalpos Architects Rendering: Spine 3D TRUE PROJECT KEY 1. MIXED-USE RETAIL / RESIDENTIAL 2. MIXED-USE RETAIL / RESIDENTIAL 3. LUXURY APARTMENTS
More information11/29/12. Des Moines Social Club Urban Design Review Project Narrative
11/9/1 Des Moines Social Club Urban Design Review Project Narrative Strategically located at 9th and Walnut, the Des Moines Social Club (DMSC) will become a critical link between the Court Avenue Entertainment
More informationRezoning Application for Planning Commission
36725 Division Road, P.O. Box 457, Richmond, MI 48062 Building and Planning Department 586-727-7571 ext. 128 586-727-2489 Fax Rezoning Application for Planning Commission For a complete list of application
More informationFCPS Rock Creek School Replacement and Final Site Selection Design Meeting #12 Notes
FCPS Rock Creek School Replacement and Final Site Selection Design Meeting #12 Notes Meeting Date: 15 March 2018 9:30 AM Meeting Location: Rock Creek School, Media Center Current Design Phase: Schematic
More information11SIXTY5 Weaver Dairy Road
SITEPLAN NOTES 2 C-2.0 BICYCLE RACK NTS Weaver Dairy Road Job Number: 1529 WLR, MTC, VJC WLR, VJC 11-30-17 STAIR SITE PLAN 1 C-2.0 SITE PLAN 1" = 30' 0 15 30 60 3 C-2.0 PLAZA DETAIL PLAN 1" = 20' 0 10
More informationGROSS SF. FL SF
STEP DOWN GROSS SF. FL-00 3375 SF WELLNESS STUDIO 001A 803 SF LOBBY 001 219 SF BOILER ROOM 001B 484 SF UNEXCAVATED FOUNDATION 7329 SQ. FT. NOT INCLUDED IN GROSS SF CALCULATION 00-ST 170 SF 00-STW 143 SF
More informationFUTURE ACTION ITEM #6 WSU Pullman, Troy Hall Renovation - Schematic Design and Construction (Olivia Yang)
FUTURE ACTION ITEM #6 WSU Pullman, - Schematic Design and Construction (Olivia Yang) TO ALL MEMBERS OF THE BOARD OF REGENTS SUBJECT: PROPOSED: SUBMITTED BY: SUPPORTING INFORMATION: WSU Pullman,, Schematic
More informationCAPITAL IMPROVEMENT PROGRAM
CAPITAL IMPROVEMENT PROGRAM Public Work Session No. 2 Project Narrative Submittal December 18, 2017 Prepared for: HALLSVILLE R-IV SCHOOL DISTRICT 421 East Highway 124 Hallsville, MO 65255 Prepared by:
More information3647 N SOUTHPORT AVE CHICAGO, IL 60613
DEVELOPER P.O. BOX 1041 EVANSTON, ILLINOIS 60204 P: (773) 529-3700 P: (773) 977-8072 C O P Y R I G H T 2 0 1 7, S U L L I V A N G O U L E T T E W I L S O N, L T D. ARCHITECT SULLIVAN GOULETTE & WILSON,
More informationEXISTING SITE PLAN. Consultants: Civil: Evans Engineering, Inc Old Post Rd. Harrisburg, PA (717) Harrisburg, PA 17110
330 orth Third St. Architecture Renovations to: O. DESCRIPTIO DATE SGA PROJECT UMBER: EXISTIG SITE PLA Drawing umber: EX00 SCHEMATIC DESIG D D0 OFFICIAL'SVESTIBULE LOCKER D03 D04 D02 COACHES D05 GYMASIUM
More informationLEED Council Available Properties in the Addison and North Branch Industrial Corridors (Source: Property Listings from Listing Broker)
LEED Council Available Properties in the Addison and North Branch Industrial Corridors (Source: Property Listings from Listing Broker) Addison Industrial Corridor Area Location: Lease/Sale 4141 N. Rockwell
More informationA0.0 WOODBURY GENERAL INFORMATION SITE PLAN & GENERAL INFORMATION PARKING CALCULATION PROJECT BUILDING AREA CALCULATION
07' 04 S t u a r t s t r e e t, S u i t e B 9 5. 8 3. 6 6 3 f a x VICINITY MAP CONTEXT MAP SHEET INDEX PROJECT CALCULATIONS GENERAL INFORMATION PROJECT SITE These drawings are instruments of service and
More informationCOMING SOON Flex Industrial / Office / Showroom FOR SALE. 200 Victoria Drive, Vancouver, BC
COMING SOON / / Showroom FOR SALE 200 Victoria Drive, Vancouver, BC For More Information Contact: Matthew MacLean Personal Real Estate Corporation Vice President 604 640 5855 matthew.maclean@ca.cushwake.com
More informationProposed Hotel, Restaurant. and Banquet Facility
Proposed Hotel, Restaurant PROJECT # : 60-0 and Banquet Facility ARCHITECTURAL 7 Logy Bay Road P.O. Box 09 St. John's, NL, Canada AA 5B T: (709) 79-80 F: (709) 7-80 E: info@fougeremenchenton.ca Issued
More informationADDENDUM NO. 1 November 10, 2016
COUER D ALENE CITY HALL PROJECT NO. 2016-009 REMODEL AND ADDITION COEUR D ALENE, IDAHO ADDENDUM NO. 1 November 10, 2016 This addendum is hereby incorporated into and is an integral part of the bidding
More informationUpdated Sheet Index for DRC Submittal A0.1
Sheet Index Landscape Architecture A0.0 Cover Sheet A0.1 Sheet Index A0.2 Enhanced Perspective A0.3 Enhanced Perspective A0.4 Enhanced Perspective A0.5 Enhanced Perspective A0.6 Enhanced Perspective A0.7
More informationPLAN A at Gulfstream Preserve Workforce Housing
PLAN A 788 sq. ft. 1 Bedroom 1 Bathroom Lanai Plan A Gulfstream Preserve Plans and elevations are artist s renderings and may not accurately represent the actual condition of a home as constructed, and
More informationElementary Grade Configuration School Current Recommendation
To: Board of Education From: Mark P Duerwaechter, Superintendent Date: January 7, 2019 Re: Action Team Recommendation Workshop Information and Discussion Only The Master Planning Action Team met on December
More informationCity of Colleyville Community Development Department. Site/Landscape Plan Application Packet
City of Colleyville Community Development Department Site/Landscape Plan Application Packet 1 Development Application Fees City of Colleyville 100 Main Street Colleyville TX 76034 817.503.1050 Zoning Zoning
More informationWhere To Start: Collegiate Space Needs & Planning Standards
Where To Start: Collegiate Space Needs & Planning Standards Where To Start: Space Needs & Planning Standards Stephen E. DeHekker, AIA, LEED AP BD+C Senior Vice President James Gabel, AIA, LEED AP Senior
More informationFOR LEASE. Prime Downtown Orlando Office Space. Competitive Parking rates! Property Details
250 N. Orange ave. orlando, FL 32801 FOR LEASE Prime Downtown Orlando Office Space Available suites Suite 100 4,900 SF Suite 100A 3,500 SF Suite 200 - Shell 7,016 SF Suite 550 3,520 SF Suite 590 1,257
More informationMEMORANDUM. March 31, President Michael K. Young President, Texas A&M University TO: CBE Recommendation: Softball Complex SUBJECT:
COUNCIL FOR THE BUlL T ENVIRONMENT Co-Chairs: Dr. Karan L. Watson, Provost and Executive Vice President Dr. Jerry R. Strawser, Vice President for Finance and Administration March 31, 2016 MEMORANDUM TO:
More informationSANTA MONICA BOULEVARD BEVERLY HILLS OWNER: 9908 SANTA MONICA BLVD., LLC SAN VICENTE BLVD. SUITE 550
BEVERLY HILLS OWNER: 777 SAN VICENTE BLVD. 550 SHEET INDEX: A-000.00 A-00.00 A-00.00 A-003.00 A-004.00 A-005.00 A-006.00 A-007.00 A-080.00 A-090.00 A-00.00 A-0.00 A-0.00 A-30.00 A-40.00 A-50.00 A-00.00
More informationDESIGN-BUILD CONSTRUCTION SERVICES OCEAN VIEW ELEMENTARY SCHOOL RE-BUILD
ALBANY UNIFIED SCHOOL DISTRICT DESIGN-BUILD CONSTRUCTION SERVICES OCEAN VIEW ELEMENTARY SCHOOL RE-BUILD BOARD OF EDUCATION PRESENTATION JANUARY 22, 2019 DOUG ESPLAND Sr. Precon Manager & Project Director
More informationMELROSE ELEMENTARY SCHOOL MODULAR ADDITION STUDY Melrose, Ma.
MELROSE ELEMENTARY SCHOOL MODULAR ADDITION STUDY Melrose, Ma. Hoover, Winthrop and Horace Mann Elementary Schools September 27, 2016 Tappe Architects Inc. HOOVER ELEMENTARY SCHOOL - SITE PLAN REMOVE EXISITNG
More informationTOWN OF MANCHESTER PLANNING AND ZONING COMMISSION. 7:00 P.M. 494 Main Street AGENDA
TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION September 18, 2017 Lincoln Center Hearing Room 7:00 P.M. 494 Main Street AGENDA PUBLIC HEARING: 1. TOWN OF MANCHESTER PLANNING & ZONING COMMISSION To revise
More informationPOLICE FACILITY NEEDS ASSESSMENT LAWRENCE, KANSAS
POLICE FACILITY NEEDS ASSESSMENT LAWRENCE, KANSAS THE STUDY PROCESS EXPERIENCE & APPROACH EXISTING FACILITIES STUDY FINDINGS NEXT STEPS EXPERIENCE EXCLUSIVE DEDICATION with LOCAL COMMITMENT METHOD AND
More informationThe Minutes of the meeting held on Tuesday 25 April 2012 were unanimously
MINUTE BOOK MINUTES OF BRADDAN PARISH COMMISSIONERS held in Commissioners Office, Close Corran, Union Mills, Braddan at 7.50pm on Thursday 31S May 2012 In Attendance: Mrs M Hodge Mr A Jessopp Mr P Halsall
More informationSCARSDALE PUBLIC SCHOOLS
SCARSDALE PUBLIC SCHOOLS GREENACRES FEASIBILITY STUDY PROGRESS REPORT BOARD OF EDUCATION Mary Beth Gose Leila Shames Maude Lewis Leone, Jr. Christopher Morin William Natbony Suzanne Seiden Scott E. Silberfein
More informationHarding Senior High School
1540 Sixth Street East Project Summary:, located in the Eastview area of St. Paul, offers students in grades 9 through 12 a wide range of curriculum options ranging from International Baccalaureate to
More informationSCARSDALE PUBLIC SCHOOLS. Greenacres Feasibility Study
SCARSDALE PUBLIC SCHOOLS Greenacres - 2015 Feasibility Study Committee List Lee Maude Scott Silberfein Stuart Mattey John Trenholm Liz Marrinan Sharon Hill Paul Berger Karen Guardino Carole Phillips Joan
More informationOperating Standards Attachment to Development Application
Planning & Development Services 2255 W Berry Ave. Littleton, CO 80120 Phone: 303-795-3748 Mon-Fri: 8am-5pm www.littletongov.org Operating Standards Attachment to Development Application 1 SKETCH PLANS
More informationBartlett High School MASTER PLAN May 25, 2017
Bartlett High School MASTER PLAN May 25, 2017 Facility Assessment Summary I. I.1 - Site Appraisal Site Appraisal The current high school was built in multiple phases, which presents challenges in layout
More informationBAYCARE BLOOMINGDALE HEALTH CENTER Bloomingdale Ave. Valrico, FL RETAIL SPACE FOR LEASE
PROPERTY HIGHLIGHTS Retail Space Available: 876 SF -,000 SF Located on Bloomingdale Ave. just east of the signalized intersection of Bloomingdale Ave. and Lithia Pinecrest Rd. Brand new state-of-the-art
More informationINCOMPLETE APPLICATION WILL NOT BE ACCEPTED COMPLETE ALL INFORMATION BELOW. Construction Value: $
CITY OF PORT ORCHARD Permit Center Office located at 720 Prospect Street Mailing address: 216 Prospect Street Port Orchard, WA 98366 (360) 874-5533 permitcenter@cityofportorchard.us COMMERCIAL or MULTI-FAMILY
More informationJackie Robinson Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNOW LEASING NOW LEASING DOWNTOWN VANCOUVER GRANVILLE ISLAND
TO 25,300 SQUARE FEET OF NEW BUILD PREMISES IN THE WESTSIDE OF VANCOUVER 1296 W BROADWAY Burrard Street Burrard Bridge Granville Street Bridge DOWNTOWN VANCOUVER GRANVILLE ISLAND W 4th Avenue W 6th Avenue
More informationMEETING MINUTES. SPS SWS at TT Minor TCF Architecture Project Number: Seattle World School SWS SDAT Workshop 3 2 December 2013
Seattle World School SWS SDAT Workshop 3 2 December 203 SPS SWS at TT Minor TCF Architecture Project Number: 203 002 MEETING MINUTES Attendance: Name Representing Role Paul Wight Seattle Public Schools
More informationMarch 2018 Exclusive Listings
March 2018 Exclusive Listings Acton Auburn Ayer Bellingham Boxborough Chelmsford Concord Devens Harvard Hudson Lincoln Littleton Lowell Marlborough Maynard Northborough Stow Tyngsborough Waltham Westford
More informationHuntington Beach City School District. M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y
Huntington Beach City School District M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y 0 1 7 Agenda 1. Where are we in the process?. Measure Q Bond Program
More informationA201 SCALE: 1" = 10'-0"
A B C D E F G G.5 H I J 0' - 0" 8' - 6" 7' - 0" 5 6 7 8 9 0 4 4 77' - 0" 6' - 0" UNEXCAVATED 7' - 6" 4 0 BELOW GRADE PARKING VP 9 (4 STALLS) 8 6 NON- COMPLIANT BIKE PARKING STALLS 7 ARCHITECTURE ENGINEERING
More informationPrototype Design Guide
2015 Choice Hotels International, Inc. All rights reserved. 06/2015/1,000. CAM-PROTO-15 CAMBRIADEVELOPMENT.COM Prototype Design Guide A fresh strategy. An untapped market. A smart new prototype. Insightful
More information675 Sierra Rose Drive Reno Quail Executive Suites. Suite 201 1,006 SF $.95/MG 2 large corner offices, reception and running water
675 Sierra Rose Drive Reno Quail Executive Suites OFFICE SPACE AVAILABLE Garrett Hallenbeck CCIM, CPM Suite 103 198 SF $875/month Suite 105 228 SF $1,000/month Suite 106 181 SF $800/month Suite 110 193
More informationCITY OF BURLINGAME - PLANNING COMMISSION SUBMITTAL REQUIREMENTS RESIDENTIAL DESIGN REVIEW
CITY OF BURLINGAME - PLANNING COMMISSION SUBMITTAL REQUIREMENTS RESIDENTIAL DESIGN REVIEW Application to the must include certain minimum information before a project can be scheduled for a hearing. The
More informationStaff Review Date: May 11, 2016 HDC PID#
Charlotte Historic District Commission Application for a Certificate of Appropriateness Staff Review Date: May 11, 2016 HDC 2016-086 PID# 07102333 LOCAL HISTORIC DISTRICT: PROPERTY ADDRESS: SUMMARY OF
More informationNew Denver, BC FEASIBILITY REPORT OCTOBER 2018 BOSUN HALL. p f
BOSUN HALL New Denver, BC FEASIBILITY REPORT OCTOBER 2018 www.coverac.ca p. 250.354.4445 f. 250.352.0017 OVERVIEW Bosun Hall is the heart of New Denver community life, and provide space for events such
More informationCupertino Village Hotel
Cupertino Village Hotel CERTINO VILLAGE LP PLANNING SBMITTAL September 25, 2018 Architects & Planners 170 Maiden Lane San Francisco California 94108 Telephone 415.391.1080 design@hwiarchitects.com September
More informationArticle 4.0 Measurements and Exceptions
This Article identifies and explains some of the more common forms of measurement used throughout this Ordinance. It also specifies exceptions to certain requirements of this Ordinance. Sec. 4.1 Measurements
More informationNDUS/UND IT Facility Office Building/Data Center
NDUS/UND IT Facility Building/Data Center Building Option 3 $9,133,128 Data Center $4,937,500 Tier 2 to Tier 3 (add on) $1,356,250 Total $15,426,878 Legislative Appropriation $12,500,000 Difference $2,926,878
More informationOLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN
KBE APPROVAL DATE: APRIL 2013 including Finding #1 g g OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN PLAN OF SCHOOL ORGANIZATION 1. Current Plan PS, K-5, 6-8, 9-12 2. Long Range Plan PS, K-5, 6-8, 9-12
More informationDOWNTOWN DEVELOPMENT REVIEW BOARD APPLICATION
This application, including the Conceptual Review Presentation, must be completed and submitted to the Downtown Development Review Board (DDRB) Staff twenty (20) business days prior to the upcoming DDRB
More informationAMES COMMUNITY SCHOOL DISTRICT SAWYER ELEMENTARY
Exhibit D-4 AMES COMMUNIY SCHOOL DISRIC SAWYER ELEMENARY Schematic Development Project Manual June 25th 2014 RDG Planning & Design 301 Grand Avenue Des Moines, Iowa 50309 architectural narrative Summarized
More informationWEST HOLLYWOOD PARK MASTER PLAN 2004
WEST HOLLYWOOD PARK MASTER PLAN 2004 Total of 5.23 acres of uninterrupted grass and trees including playground areas and tree-lined promenades compared with only 1.86 acres of park open space in the existing
More informationD OWNTOWN TEMECULA CLASS A OFFICE / RETAIL SPACE FOR LEASE
M anage m e n t B r oke r age L e a s i n g Los Angeles Ontario 80 min. 45 min. D OWNTOWN TEMECULA CLASS A OFFICE / RETAIL SPACE FOR LEASE Rancho California Rd 15 Ynez Ynez rd rd Irvine 75 min. Palm Springs
More informationCOMPONENT FLOW CHART & SEQUENCING DIAGRAMS
Oak Park and River Forest High School Master Facilities Plan COMPONENT FLOW CHART & SEQUENCING DIAGRAMS The following is a narrative intended to accompany the component flow chart and sequencing diagrams
More informationA-001 BOGLE FAMILY FARMHOUSE MODERN HOME-PLEX WEST JORDAN STREET SITE PLAN 3D VIEW COVER SHEET SITE PLAN COVER SHEET & GENERAL INFO LANDSCAPE PLANS
75'- 6" PROPERTY LINE UNDER FENCE 5' Boise, ID 8370 Phone: 08.608.9796 SET BACK LINE EXISTING CONSTRUCTION 8'-".4 ACER 0,937.5 SQFT 58'-7 /" A-03 DEMO EXISTING CONSTRUCTION 9" NEW CONSTRUCTION A-04 '-6
More informationDESERT MOUNTAIN MEDICAL PLAZA
DESERT MOUNTAIN MEDICAL PLAZA FOR LEASE Generous Tenant Improvement Allowance Contact Broker for details PROPERTY RENOVATIONS COMPLETE UPDATED AREAS INCLUDE: New furnishings and artwork in lobbies Fully
More informationHigh Traffic Retail and Restaurant Space in the Heart of Downtown Oakland s Business Center.
Oakland City Center High Traffic Retail and Restaurant Space in the Heart of Downtown Oakland s Business Center. Convenient and convivial, Oakland City Center has a variety of retail and restaurant opportunities
More information