1 Where To Start: Collegiate Space Needs & Planning Standards
2 Where To Start: Space Needs & Planning Standards Stephen E. DeHekker, AIA, LEED AP BD+C Senior Vice President James Gabel, AIA, LEED AP Senior Associate This seminar was created for the live learning environment of the Athletic Business Conference & Expo Stephen DeHekker and James Gabel have received no financial interest/arrangement that would be considered a conflict of interest
3 Presentation Objectives Understand pre-design and space programming in the design process Recognize valid metrics used to predict space demand Determine space requirements to meet future needs for facilities Build comprehensive and accurate project budgets and schedules
4 Presentation Outline I. Introduction II. III. IV. Programming Process Space Programming Standards Budgeting V. Case Study VI. Summary
5 Introduction
6
7 Building Process Pre-Design Programming Design Construction Occupancy
8 Process Analogy Pre-Design Programming Design & Construction Occupancy
9 One Chance To Get It Right Every Project Is One And Done No Tomorrow No Next Year One Opportunity To Succeed Pre-Design Phase Is Key Foundation For Entire Project
10 Sustainable Approach Reduction is first priority Right-Sizing is key Maximize use Meet demand Reduce excess Opportunity to reuse space Potential to recycle facilities
11 Cost Control
12 Team Formation PROJECT CHAMPION Strong Project Advocate Leadership Position College President VP Respected Figure Networked Communicator Consensus Builder Fundraising Ability
13 Team Formation STEERING COMMITTEE Major Decision Making Body Project Leadership Project Visionaries Milestone Review Committee Participation For Life Of Project Final Approval Body
14 Team Formation WORKING COMMITTEE Day-To-Day Review Committee Interface With Professional Team Project Expertise Some Overlap With Steering Committee Participation For Life Of Project Steering Committee Liaisons
15 Team Formation STEERING COMMITTEE President VP Business VP Student Affairs VP Advancement Student Representative Athletics Director Recreation Director Director Of Facilities Campus Architect WORKING COMMITTEE Recreation Director Athletics Director Fitness Director Aquatics Director Intramural Sport Director Outdoor Program Director Head Of Maintenance Campus Architect
16 Team Formation Team Owner Key Players Steering Committee Working Committee Architect/Consultants Architect Engineers Programmer Cost Consultant Sustainability Consultant Aquatic Consultant Operations Consultant
17 Programming Process
18 Programming Factors Formal Survey National Standards Peer Comparison Focus Groups Project Needs Professional Judgment
19 Programming Factors Formal Survey National Standards Peer Comparison Focus Groups Project Needs Professional Judgment
20 Focus Groups Students Donors Faculty Organizations Project Leadership Administration Committees Staff
21 Focus Groups FOCUS GROUP SURVEY Informal Survey Initial Indicators Preliminary Priorities Only One Measure Not Statistically Valid
22 Focus Groups
23 Programming Factors Formal Survey National Standards Peer Comparison Focus Groups Project Needs Professional Judgment
24 Formal Survey Web Based Mass distribution Statistically Significant Sample Incentivize Register to win prize for participation Basis For Project Requirements Priorities Needs Financial Support
25 Formal Survey SURVEY COMPONENTS People Age, Gender Residential Status Participation Activities Day/Time Potential Fee Tolerance
26 Formal Survey
27 Formal Survey
28 Formal Survey
29 Formal Survey
30 Formal Survey How often would you participate? BASKETBALL FREE WEIGHTS WEIGHT MACHINES FITNESS - CARDIO RACQUETBALL SQUASH BADMINTON VOLLEYBALL LAP SWIMMING RECREATONAL SWIMMING Never Once a month (1 x mo.) Actual = /wk Once a week Actual = 1 /wk Times a week Actual = 3 /wk Daily Actual = 7 /wk TOTAL SURVEYS /wk Or More Partic /wk Or More Percent 8% 64% 67% 85% 4% 1% 8% 17% 18% 13% 14% 8% Total Weekly Visits Total Daily Visits WATER AEROBICS ICE HOCKEY
31 Formal Survey What Time Of Day? BASKETBALL FREE WEIGHTS WEIGHT MACHINES FITNESS - CARDIO RACQUETBALL SQUASH BADMINTON VOLLEYBALL LAP SWIMMING RECREATONAL SWIMMING 6-8 am am - 12 pm pm pm pm pm pm - 12 am TOTAL SURVEYS Peak User Group WATER AEROBICS ICE HOCKEY
32 Formal Survey Option A - $150 Fee Option B - $100 Fee Option C - $75 Fee 3 court gymnasium 3 court gymnasium 3 court gymnasium Multi-activity court (MAC) gym Multi-activity court (MAC) gym Elevated jogging track Elevated jogging track Elevated jogging track Weight and fitness area Weight and fitness area Weight and fitness area MP rooms for aerobics, etc. MP rooms for aerobics, etc. MP rooms for aerobics, etc. Rock climbing wall Rock climbing wall Comprehensive wellness center Basic wellness center Social lounge and game room Social lounge Leisure pool Whirlpool and sauna Meeting room Sports club offices
33 Formal Survey Activity Peak Demand Unit SF Need Activity Type Unit Need Recom'd. Units Total SF FREE WEIGHTS /sf Individual 61 3,355/sf WEIGHT MACHINES /sf Individual 70 3,850/sf SUBTOTAL Demand Based Requirements for Peak Need 7,205/sf CARDIO MACHINES /sf Individual 92 4,600/sf SUBTOTAL 4,600/sf AEROBICS 70 50/sf Individual 70 3,500/sf DANCE CLASSES 92 50/sf Individual 92 4,600/sf YOGA / PILATES /sf Individual 126 6,300/sf SPINNING / STATIONARY CYCLE /sf Individual 103 2,575/sf MARTIAL ARTS 56 50/sf Individual 56 2,800/sf SUBTOTAL 19,775/sf CLIMBING WALL 78 36/sf pairs ,404/sf BOULDERING WALL 46 36/sf Individual 46 1,656/sf SUBTOTAL 3,060/sf
34 Programming Factors Formal Survey National Standards Peer Comparison Focus Groups Project Needs Professional Judgment
35 National Planning Standards National Intramural Recreation Sports Association National Collegiate Athletic Association National Sporting Goods Association American College of Sports Medicine
36 Programming Factors Formal Survey National Standards Peer Comparison Focus Groups Project Needs Professional Judgment
37 Peer Comparison Indoor space
38 Peer Comparison Outdoor space
39 Programming Factors Formal Survey National Standards Peer Comparison Focus Groups Project Needs Professional Judgment
40 Professional Judgment Big Picture Evaluation Experience Sharing Political Factors History Perceptions Trends in Recreation Institutional Identity/Demographics Finalize Project Requirements
41 Programming Factors Formal Survey National Standards Peer Comparison Focus Groups Project Needs Professional Judgment
42 Building Program Space Requirements Quantity Itemized Room List Net Area Total Gross Area Calculation Quality Technical Requirements Adjacency
43 Space Requirements No. Component Type Quantity Unit SF Total SF 1.00 Activity Space 44,961 sf 1.01 Gymnasium (3 Court) 1 room 18,500 sf 18,500 sf 1.02 Gymnasium Storage 2 rooms 300 sf 600 sf 1.03 Suspended Running Track 1 track 5,367 sf 5,367 sf 1.04 Racquetball Court 2 courts 800 sf 1,600 sf 1.05 Climbing Wall 1 area 397 sf 397 sf 1.06 Bouldering Wall 1 area 260 sf 260 sf 1.07 Climbing Wall Office 1 room 117 sf 117 sf 1.08 Circuit & Free Weights 2 areas 3,500 sf 7,000 sf 1.09 Circuit & Free Weight Storage 1 room 300 sf 300 sf 1.10 Cardio & Stretching 1 area 4,216 sf 4,216 sf 1.11 MP Room - Large 1 room 2,531 sf 2,531 sf 1.12 MP Rooms Storage 1 room 395 sf 395 sf 1.13 MP Room - Small 1 room 2,283 sf 2,283 sf 1.14 MP Rooms Storage 1 room 242 sf 242 sf 1.15 Quiet Fitness Area 1 area 1,153 sf 1,153 sf PROGRAM SUMMARY 1.00 Activity Space 44,961 SF 2.00 Natatorium 15,022 SF 3.00 Outdoor Adventure 8,250 SF 4.00 Office Suite 1,724 SF 5.00 User Support 2,781 SF 6.00 Building Support 7,381 SF Net Building Area 75% 80,119 SF Circulation and Walls 25% 26,706 SF Gross Building Area 106,825 SF
44 Technical Data Requirements
45 Adjacency Diagram A103 Storage A104 Observation Direct Connection A101 MAC Gymnasium Indirect Connection A105 Team Benches S103 Locker Rooms C101 Concourse
46 Design Narratives Architectural Mechanical/Electrical Plumbing/Fire Protection Technology A/V Systems Aquatics Sustainability
47 Design Concept Graphic Program Multiple Options New Construction Renovation/Expansion Plan Concepts 3D Images Communication Tool Promotional / Fundraising Basis For Cost Model
48 Cost Model Balance Budget Quality Quantity Total Project Cost Construction Cost Soft Cost Contingencies Escalation Space Program Quantity Quality Aesthetic Durability
49 Cost Model Total Project Cost Construction Related Costs Soft Costs Include Contingencies Address Inflation A Construction Cost Cost A1 Construction cost $33,000,000 A2 Construction contingency 5.0% $1,650,000 A3 Total Construction Cost $34,650,000 B Construction Related Cost B1 Hazardous materials abatement $235,360 B2 Lead paint management $50,000 B3 Temporary facilities $200,000 B4 Total Construction Related Cost $485,360 C Fixtures, Furnishings & Equipment (FFE) C1 Furniture $275,000 C2 Fitness Equipment $725,000 C3 A/V equipment $120,000 C4 Telephone and IT systems $50,000 C5 Pool timing system $200,000 C6 Total FFE $1,370,000 D Professional Fees & Expenses D1 A/E fee - Basic services 8.00% $2,772,000 D2 Specialty consultants 1.00% $346,500 D3 Furniture design fee 10% $27,500 D4 LEED Consulting and Documentation $128,248 D5 Survey $13,234 D6 Geotechnical report $9,900 D7 Reimbursable expenses $150,000 D8 Moving expenses $60,000 D9 Legal Fees $50,000 D10 Financing Fees $40,000 D11 Total Professional Fees & Expenses $3,597,382 E1 Sub Total $40,102,742 E2 Project Contingency 5.00% $2,005, E3 Inflation 3.00% $1,263,236 E4 Total Project Cost $43,371,115
50 Final Evaluation Leadership Leadership input Stakeholder input Professional/technical input Consensus decision Justifiable Defensible Sellable Stake Holders Consensus Technical
51 Space Programming Standards
52 NIRSA # of Students Indoor Component < 3,000 3,000-9,999 10,000-19,999 >20,000 BB Courts (# courts per 1,000 students) Free Weights (sf per student) Machine Weights (sf per student) Cardio Fitness (sf per student) Multi-Purpose Space (sf per student) NA Group Exercise Space (sf per student) Strength Equipment Space
53 NIRSA # of Students Outdoor Component < 3,000 3,000-9,999 10,000-19,999 >20,000 Total outdoor fields (number of acres per 1,000 students) NA 0.94 Outdoor Basketball courts (# courts per 1,000 students) Soccer fields (# fields per 1,000 students) Softball fields (# fields per 1,000 students) Tennis Courts (# courts per 1,000 students) Volleyball Courts (# courts per 1,000 students)
54 NCAA Basketball Court Competition Dimensions= 94 x 50 Court Area= 4,700 sf Overall Area= 7,980 sf Recreation Dimensions= 84 x 50 Court Area= 4,200 sf Overall Area= 7,280 sf
55 NCAA Competition Soccer Field Width yards Length yards Maximum Field Area = 81,000 sf Maximum Overall Area = 106,000 sf Minimum Field Area = 72,450 sf Minimum Overall Area = 96,250 sf
56 NCAA Competition Swimming Long Course Pool Dimensions: 50m (164 ft 0.5 in) x 75 ft providing (8) 9 foot lanes. Water depth 7 feet min.. Short Course Pool Dimensions: 25y (164 ft 0.5 in) x 60 ft providing (8) 7 foot lanes. Water depth 7 feet min. 50 m x 75 ft pool 50 m x 75 ft pool and dive well
57 National Sporting Goods Association
58 ACSM Multipurpose Gymnasium Temperature 68 to 72 degrees F Humidity < 60% Air Circulation 8 to 12 air changes per hour Light Minimum 50 FC Court Size 50 x perimeter
59 ACSM Fitness Center Temperature 68 to 72 degrees F Humidity < 60% Air Circulation 8-12 air changes per hour Outside Air 40% preferred 10% minimum Flooring Antistatic, antifungal, nonabsorbent
60 Space Program Needs No Standard Demand Based Space Demand Operations Based Demand Based Activity space Dedicated lockers Competition Natatorium Operations Based Offices No Standard Lobbies Lounges General lockers
61 Locker Rooms General Users Limited demand Demand Based Users Rental Faculty Club Aquatic General use Team use Athletic
62 Locker Rooms Athletic Locker Room Analysis Varsity Season Post Season Non Traditional Start Women's Sports Locker AUGUST SEP OCT NOV DEC JAN FEB MAR APRIL MAY Cross Country Field Hockey Golf Soccer Tennis Volleyball Swimming / Diving Basketball Track Indoor Lacrosse Softball Track Outdoor Total Total Excluding Non Traditional
63 6-Lane 25 Yard Pool 7,704 SF room area 107 X 72 3,375 SF tank area 75 X 45 Deck dimensions 15 end decks 10 /15 side decks
64 8-Lane 25 Yard Pool 9,309 SF room area 107 X 87 4,500 SF tank area 75 X 60 Deck dimensions 15 end decks 10 /15 side decks
65 25 Yard/25 Meter Pool 12,768 SF room area 114 X 112 6,150 SF tank area 82 X 75 Deck dimensions 20 /15 end decks 15 side decks
66 8-lane Stretch Pool 14,355 SF room area 165 X 87 7,680 SF tank area 128 X 60 Deck dimensions 15 /20 end decks 10 /15 side decks (1) 6 bulkhead
67 10-lane Stretch Pool 17,655 SF room area 165 X 107 9,600 SF tank area 128 X 75 Deck dimensions 15 /20 end decks 15 side decks (1) 6 bulkhead
68 50-Meter Pool 23,520 SF room area 210 X ,900 SF tank area 172 X 75 Deck dimensions 15 /20 end decks 15 /20 side decks (2) 4 bulkheads
69 50-Meter Pool + Diving 32,816 SF room area 293 X ,200 SF pool tank area 176 X 75 4,350 SF diving tank area 58 X 75 Deck dimensions 15 /20 end decks 18 side decks (2) 6 bulkheads
70 Competitive Pool Summary Configuration Water Area Total Area (approximate) Ratio 6 lane 25 yard 3,375 SF 7,704 SF lane 25 yard 4,500 SF 9,309 SF yard/25 meter 6,150 SF 12,768 SF lane stretch 7,680 SF 14,355 SF lane stretch 9,600 SF 17,655 SF meter 12,900 SF 23,520 SF meter + diving 17,550 SF 32,816 SF 1.9
71 Leisure Pools Primary Factors Demand Budget Features Occupancy 15 SF/person max 30 SF/person typical
72 Administration/Office Space Staff Full and part time Future Support Space Work room / Break room Storage Conference Location Proximity to control
73 Public Space No Published Standards Intangible Value Contributes to Wow Factor Right Size Special Event Potential Requires Clearly Defined Use
74 Space Programming Standards Building Component Breakdown 9% 10% 11% 9% Public Spaces Recreation/Athletics Admin./Office User Support Bldg. Support 62%
75 Budgeting
76 Construction Cost Components $200/SF $225/SF $230/SF $235/SF $240/SF $250/SF $260/SF $260/SF $275/SF $325/SF $335/SF $350/SF
77 Fixtures, Furnishings & Equipment FFE FURNISHINGS Lounge Office Meeting Unit Cost $30/SF - $34/SF $24/SF - $28/SF $28/SF - $32/SF EQUIPMENT Fitness Equipment General (balls, covers, IT, etc.) $45/SF - $55/SF $3/SF - $4/SF
78 Preliminary Space Program Construction Cost Furniture Cost Equipment Cost Component Units Area SF Total SF Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost 1.00 Public Spaces 1.01 Lobby 1 1,200 SF 1,200 SF $275/SF $330,000 $34/SF $40,800 $3/SF $3, Lounge 1 2,400 SF 2,400 SF $275/SF $660,000 $34/SF $81,600 $3/SF $7, Public Toilets SF 600 SF $325/SF $195,000 $0/SF $0 $3/SF $1,800 4,200 SF $1,185,000 $122,400 $12, Gymnasium Court Gymnasium 1 20,000 SF 20,000 SF $235/SF $4,700,000 $0/SF $0 $3/SF $60, MAC Court 1 9,800 SF 9,800 SF $250/SF $2,450,000 $0/SF $0 $3/SF $29, Jogging Track 1 7,500 SF 7,500 SF $260/SF $1,950,000 $0/SF $0 $3/SF $22,500 37,300 SF $9,100,000 $0 $111, Fitness 3.01 Fitness Center 1 22,000 SF 22,000 SF $225/SF $4,950,000 $0/SF $0 $50/SF $1,100, Small Group Exercise 2 1,000 SF 2,000 SF $250/SF $500,000 $0/SF $0 $3/SF $6, Large Group Exercise 2 2,400 SF 4,800 SF $250/SF $1,200,000 $0/SF $0 $3/SF $14,400 28,800 SF $6,650,000 $0 $1,120,400
79 Preliminary Space Program Construction Cost Furniture Cost Equipment Cost Component Units Area SF Total SF Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost 4.00 Aquatic Center 4.01 Lap Pool Tank 4,500 SF $175/SF $787,500 $0/SF $ Lap Pool Enclosure 1 9,300 SF 9,300 SF $250/SF $2,325,000 $0/SF $0 $3/SF $27, Leisure Pool Tank 4,000 SF $200/SF $800,000 $0/SF $ Leisure Pool Enclosure 1 8,000 SF 8,000 SF $250/SF $2,000,000 $0/SF $0 $3/SF $24, Whirlpool SF 200 SF $400/SF $80,000 $0/SF $0 $3/SF $ Wet Classroom SF 720 SF $300/SF $216,000 $32/SF $23,040 $3/SF $2, Offices SF 240 SF $230/SF $55,200 $28/SF $6,720 $3/SF $720 18,460 SF $6,263,700 $29,760 $55, Administration 5.01 Reception SF 120 SF $230/SF $27,600 $34/SF $4,080 $3/SF $ Director's Office SF 200 SF $230/SF $46,000 $28/SF $5,600 $3/SF $ Staff Offices SF 960 SF $230/SF $220,800 $28/SF $26,880 $3/SF $2, Conference Room SF 300 SF $230/SF $69,000 $32/SF $9,600 $3/SF $ Break/Kitchen SF 120 SF $250/SF $30,000 $28/SF $3,360 $3/SF $360 1,700 SF $393,400 $49,520 $5, User Support 6.01 Equipment Issue / Laundry 1 1,000 SF 1,000 SF $225/SF $225,000 $28/SF $28,000 $3/SF $3, Men's Locker Room 1 2,400 SF 2,400 SF $325/SF $780,000 $0/SF $0 $3/SF $7, Women's Locker Room 1 2,400 SF 2,400 SF $325/SF $780,000 $0/SF $0 $3/SF $7, Gender Neutral Locker Room SF 180 SF $325/SF $58,500 $0/SF $0 $3/SF $540 5,980 SF $1,843,500 $28,000 $17,940
80 Preliminary Space Program Construction Cost Furniture Cost Equipment Cost Component Units Area SF Total SF Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost 7.00 Building Support 7.01 Mechanical Space 1 8,000 SF 8,000 SF $200/SF $1,600,000 $0/SF $0 $3/SF $24, Electrical Space 1 1,400 SF 1,400 SF $200/SF $280,000 $0/SF $0 $3/SF $4, Storage 1 3,200 SF 3,200 SF $200/SF $640,000 $0/SF $0 $3/SF $9,600 12,600 SF $2,520,000 $0 $37,800 Net Assignable Building Area 109,040 SF $27,955,600 Circulation and Walls 20% 21,808 SF $250/SF $5,452,000 TOTAL 130,848 SF $255/SF $33,407,600 $229,680 $1,361,120
81 Total Project Cost A Construction Cost Cost Total A1 Construction Cost $33,407,600 A2 Site Work 5.0% $1,670,380 A3 Construction contingency 5.0% $1,753,899 A4 Total Construction Cost 81% $36,831,879 B Fixtures, Furnishings & Equipment (FFE) B1 Furniture $229,680 B2 Fixtures and Equipment $1,361,120 B3 Total FFE 3.5% $1,590,800 C Professional Fees & Expenses C1 Architectural/Engineering fees 7.5% $2,762,391 C2 Specialty Consultants 2.5% $920,797 Programming Aquatic Sustainability (LEED) A/V systems C3 CM Fee 3.0% $1,104,956 C4 Survey 1.0% $16,704 C5 Geotechnical report 1.0% $16,704 C6 Material Testing $0.75/SF $98,136 C7 Reimbursable expenses $4,000 C8 Building permit 0.50% $167,038 C9 Legal costs $0 C10 Endowment $0 C11 Total Professional Fees & Expenses 11% $5,090,726 D1 Sub Total $43,513,405 $43,513,405 D2 Project Contingency 5.0% $2,175,670 D3 Total Project Cost $349/SF 1.24 $45,689,075
82 Case Study
83 Colorado State University Public land grant university Fort Collins, CO 22,565 undergraduates 7,458 graduates 51/49% female/male 81/19% in-state/out-of-state 112 majors Division I athletics
84 Colorado State University
85 Colorado State University
86 Colorado State University
87 Colorado State University Project Program Renovation & expansion Space needs Technical data Sustainability requirements Plan concept Exterior concept Project budget
88 Colorado State University
89 Colorado State University
90 Colorado State University
91 Colorado State University First Level Plan Second Level Plan
92 Colorado State University
93 Colorado State University Original New Entrance
94 Colorado State University
95 Colorado State University Original Entrance New Fitness Center
96 Colorado State University Original Fitness Center New Fitness Center
97 Colorado State University Recreation Pool MAC Gymnasium
98 Colorado State University Lobby/Lounge Outdoor Adventure
99 Colorado State University Multi-Purpose Room Climbing Wall
100 Summary
101 Cost of Space Programming 1/4 1/2% Of Construction Cost $37,500 - $150,000 ($15M - $30M Project) < 0.1% lifetime building cost Lifetime Building Cost
102 Timeline weeks Team Formation Space Program Program Concept Final Report 4 weeks 6 8 weeks 6 8 weeks 4 weeks
103 Summary Programming Is Critical First Step Start With A Qualified Team Consider Multiple Factors Stakeholder input Survey analysis Peers Industry standards Professional judgment Build Comprehensive Budget
104 You Should Now Understand pre-design and space programming in the design process Recognize valid metrics used to predict space demand Determine space requirements to meet future needs for facilities Build comprehensive and accurate project budgets and schedules
105 Follow-Up Contact Stephen E. DeHekker, AIA, LEED AP BD+C Senior Vice President James Gabel, AIA, LEED AP Senior Associate
Southern Oregon University
Southern Oregon University Public Meeting Notice August 5, 05 TO: FROM: RE: Southern Oregon University Board of Trustees, Finance Committee Sabrina Prud homme, University Board Secretary Notice of special
More informationWEST HOLLYWOOD PARK MASTER PLAN 2004
WEST HOLLYWOOD PARK MASTER PLAN 2004 Total of 5.23 acres of uninterrupted grass and trees including playground areas and tree-lined promenades compared with only 1.86 acres of park open space in the existing
More informationOak Park and River Forest High School District North Scoville Avenue Oak Park, IL
Oak Park and River Forest High School District 200 201 North Scoville Avenue Oak Park, IL 60302-2296 To: Board of Education From: Tod Altenburg, CSBO Phil Prale, ASCI Date: August 16, 2016 Re: Requested
More informationState College Area School District
State College Area School District The following is a guideline for project design submittals to the Facility Committee of the State College Area School District. During the design process the committee
More informationNDUS/UND IT Facility Office Building/Data Center
NDUS/UND IT Facility Building/Data Center Building Option 3 $9,133,128 Data Center $4,937,500 Tier 2 to Tier 3 (add on) $1,356,250 Total $15,426,878 Legislative Appropriation $12,500,000 Difference $2,926,878
More informationAV Services is a self pickup and deliver service provided for all GMU Staff and Faculty. Call x32206 for details
APPENDIX III FEES ASSOCIATED WITH UNIVERSITY FACILITIES & SERVICES. A. s The fees associated with the use of George Mason University facilities and services are presented in this section. The fees listed
More informationAshby, Pepperell, Townsend North Middlesex Regional High School. Feasibility Study Update
Ashby, Pepperell, Townsend North Middlesex Regional High School Feasibility Study Update June 6, 2013 AGENDA Preliminary Design Program (PDP) District Capacity Analysis Preferred Schematic Report (PSR)
More informationHarman Swim Center 7300 SW Scholls Ferry Road Beaverton, TriMet Route #56
Harman Swim Center 7300 SW Scholls Ferry Road Beaverton, 97008 503-629-6314 TriMet Route #56 Aquatic Facility Supervisor: Heath Wright Feb. 8 - Mar. 27, 2016 Mar. 28 - June 19, 2016 Office Hours: Monday-Thursday
More informationELLIS. Ellis Research Center PROPERTY HIGHLIGHTS BRIAN CARR, CCIM LEE CLYBURN. Research Triangle Park North Carolina.
ELLIS Research Triangle Park North Carolina Ellis Research Center Office and Lab PROPERTY HIGHLIGHTS 2400 Ellis Rd RTP, NC 27709 Size 331,898 RSF Floors 4 Parking Power 519 Shared parking spaces 480/277
More information1001 Feehanville Drive Phone Mt. Prospect, IL Fax
NICHOLAS & ASSOCIATES, INC. 1001 Feehanville Drive Phone 847.394.6200 Mt. Prospect, IL 60056 Fax 847.394.6205 November 29, 2016 Community Unit School District 200 130 West Park Avenue Wheaton, IL 60189
More informationouglas Intermediate School
ouglas Intermediate School DOUGLAS INTERMEDIATE/ELEMENTARY SCHOOL Board of Selectmen / Finance Committee February 15, 2011 DiNisco Design www.dinisco.com Site Discussion Site Discussion Site Discussion
More informationCOMPONENT FLOW CHART & SEQUENCING DIAGRAMS
Oak Park and River Forest High School Master Facilities Plan COMPONENT FLOW CHART & SEQUENCING DIAGRAMS The following is a narrative intended to accompany the component flow chart and sequencing diagrams
More informationPAR AG presentation. May ROCKVILLE PIKE ELEMENTARY & PRESCHOOL BUILDING
PAR AG presentation May 8 2018 agenda 1 project scope 2 site design 3 building design 4 budget and schedule 5 questions & answers A beautiful site project key data o o o o Capacity: 700 students Class
More informationAllan Hancock College
Allan Hancock College Project Planning Board Workshop February 17, 2009 Agenda Objective Funding Allocation Space Demand Analysis Project Overview Bond Measure I Program Schedule Charge: To review funding
More informationCAPITAL IMPROVEMENT PROGRAM
CAPITAL IMPROVEMENT PROGRAM Public Work Session No. 2 Project Narrative Submittal December 18, 2017 Prepared for: HALLSVILLE R-IV SCHOOL DISTRICT 421 East Highway 124 Hallsville, MO 65255 Prepared by:
More informationCenter for Access and Student Success (CASS)
Center for Access and Student Success (CASS) PRESENTED BY Dr. William Hudson Jr., Vice President Student Affairs Ms. Angela Poole, CPA, Vice President Finance and Administration/CFO Mr. Sameer Kapileshwari,
More informationNEW LEBANON ELEMENTARY SCHOOL
NEW LEBANON ELEMENTARY SCHOOL EDUCATIONAL SPECIFICATIONS for the NEW LEBANON ELEMENTARY SCHOOL November 10, 2014 PETER GISOLFI ASSOCIATES Architects Landscape Architects, LLP NEW LEBANON ELEMENTARY SCHOOL
More informationFor questions or feedback please contact Perspective Views
NORTHEAST NORTHEAST NORTHEAST NORTHEAST - EAST EAST 3 - EAST 3 - EAST SOUTHWEST SOUTHWEST SOUTHWEST SOUTHWEST - WEST WEST - WEST For questions or feedback please contact memberfeedback@centralparktennisclub.com.
More informationNEW LEBANON ELEMENTARY SCHOOL
NEW LEBANON ELEMENTARY SCHOOL EDUCATIONAL SPECIFICATIONS for the NEW LEBANON ELEMENTARY SCHOOL October 9, 2014 PETER GISOLFI ASSOCIATES Architects Landscape Architects, LLP NEW LEBANON ELEMENTARY SCHOOL
More informationSCARSDALE PUBLIC SCHOOLS. Greenacres Feasibility Study
SCARSDALE PUBLIC SCHOOLS Greenacres - 2015 Feasibility Study Committee List Lee Maude Scott Silberfein Stuart Mattey John Trenholm Liz Marrinan Sharon Hill Paul Berger Karen Guardino Carole Phillips Joan
More informationExhibit A Project Identification. Exhibit B Project Charter / Project Intent. Exhibit C Project Scope. Exhibit C Project Schedule
Exhibit A Project Identification Exhibit B Project Charter / Project Intent Exhibit C Project Scope Exhibit C Project Schedule Exhibit D Project Budget Exhibit E Owner Supplied Documents Exhibit F Sample
More informationJuly 30, 2018 Monday. July 31, 2018 Tuesday. September 16, 2018 Sunday Girls Volleyball "Sit Out Period" Ends
July 10, 2018 Tuesday Coaching Education 1:00 PM @ Madison HS, Rm. 1002 July 17, 2018 Tuesday Coaching Education 1:00 PM @ Madison HS, Rm. 1002 July 30, 2018 Monday Football Fall Season Practice/Tryouts
More informationPerspective Views NORTHEAST VIEW 1 SOUTHWEST VIEW 2 AERIAL VIEW - EAST AERIAL VIEW - WEST NORTHEAST VIEW SOUTHWEST VIEW AERIAL VIEW - WEST
NORTHEAST NORTHEAST NORTHEAST NORTHEAST - EAST EAST 3 SOUTHWEST SOUTHWEST SOUTHWEST SOUTHWEST - WEST WEST - EAST 3 - EAST - WEST - WEST Perspective Views Annual Meeting June, 7 Northeast View Interior
More informationAUBURN VILLAGE SCHOOL ADDITION & RENOVATION Executive Team Meeting Minutes
AUBURN VILLAGE SCHOOL ADDITION & RENOVATION Executive Team Meeting Minutes Meeting No. 4 Date: 5/12/2018 Job No. Meeting Location: AVS Conference Room The following notes were taken during a meeting on
More informationChecklist for Minor Plan Modification
Checklist for Minor Plan Modification All submittal information shall be provided to the Community Development Department. All submittal information shall be presented along with the Uniform Application,
More informationSMALL PROJECTS & IMPROVEMENTS: DOG RUNS, PATIO ENCLOSURES & FENCES, EXTERIOR IMPROVEMENTS (Abbreviated Design Review Application)
REVIEW TYPE: PRELIMINARY FINAL LANDSCAPE ABBREVIATED ADDITION COLOR BOARD Application Form* X X X X X Design Review Fee* X X X Registered Survey** X Site Plan X X X X X Floor Plans X X X Elevations X X
More informationOLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN
KBE APPROVAL DATE: APRIL 2013 including Finding #1 g g OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN PLAN OF SCHOOL ORGANIZATION 1. Current Plan PS, K-5, 6-8, 9-12 2. Long Range Plan PS, K-5, 6-8, 9-12
More informationDESIGN REVIEW PROCESS AND APPLICATION
DESIGN REVIEW PROCESS AND APPLICATION Design review is the first step in the process of any construction project requiring permits. The Community Redevelopment Agency (CRA) Board is responsible for ensuring
More informationAloha Swim Center. Women-only Swim June 17 July 15 Aug :30 pm
Aloha Swim Center 18650 SW Kinnaman Road Aloha, 97078 503-629-6311 TriMet Routes #52, #57, #88 Aquatic Facility Supervisor: Brian Powers Summer Term: June 26-Sept. 4, 2017 Office Hours: Schedule subject
More informationNew Denver, BC FEASIBILITY REPORT OCTOBER 2018 BOSUN HALL. p f
BOSUN HALL New Denver, BC FEASIBILITY REPORT OCTOBER 2018 www.coverac.ca p. 250.354.4445 f. 250.352.0017 OVERVIEW Bosun Hall is the heart of New Denver community life, and provide space for events such
More informationHuntington Beach City School District. M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y
Huntington Beach City School District M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y 0 1 7 Agenda 1. Where are we in the process?. Measure Q Bond Program
More informationZONING R-LI Low Intensity Residential District. [Amended by Ord. No. 1684] PERMITTED USES BY RIGHT.
130.19. R-LI Low Intensity Residential District. [Amended 10-2-95 by Ord. No. 1684] 130.19.1. Purpose. To preserve steep slopes, floodplains, and other sensitive natural areas and to provide opportunities
More informationSUBMITTAL REQUIREMENTS FOR USE PROCESS III OR PROCESS IV
COMMUNITY DEVELOPMENT DEPARTMENT 33325 8 th Avenue South Federal Way WA 98003 253-835-2607; Fax 253-835-2609 www.cityoffederalway.com SUBMITTAL REQUIREMENTS FOR USE PROCESS III OR PROCESS IV USE PROCESS
More informationOak Park and River Forest High School District 200 Pool Project Community Engagement Phase I Findings
Oak Park and River Forest High School District 200 Pool Project Community Engagement Phase I Findings Presented May 17, 2016 Oak Park and River Forest High School District 200 Pool Project Community Engagement
More informationPROJECT ENTITLEMENT APPLICATION
GENERAL REQUIREMENTS (Print or Type) Name of Proposed Project: Location of Project: Legal Description of Project (Assessor s Parcel/Allotment No., Township/Range/Section): Staff Use Only CASE NO.: RELATED
More informationRecreation Facility Hours
NORMAL HOURS Recreation Facility Hours August 1, 2016 July 31, 2017 Last Revised: July 29, 2016 Effective Dates 2016: AUG 23 31, SEP 1 2, SEP 6 16, SEP 18 23, SEP 25 30, OCT 1 7, OCT 9 18, OCT 24 30, NOV
More informationChecklist for Tentative Subdivision Map
Checklist for Tentative Subdivision Map All submittal information shall be provided to the Community Development Department. All submittal information shall be presented along with the Uniform Application,
More informationArchitectural Design Process
Architectural Design Process Custom Residential A. Schematic Design Phase Pre-Design Meeting Site Analysis Site Survey Conceptual Design & Project Scope Design Program Guideline Project Team Formation
More informationGREENWICH PUBLIC SCHOOLS New Lebanon ES Feasibility Expansion Study
GREENWICH PUBLIC SCHOOLS New Lebanon ES Feasibility Expansion Study New Lebanon School (K-5) 25 Mead Avenue, Greenwich, CT 20 March 2014 KSQ Architects PC 20 March 2014 GREENWICH PUBLIC SCHOOLS NEW LEBANON
More informationFee: $138.75/4 classes Fee: $173.50/5 classes. Age: 7-10 years
Campers aged under 7 years will not participate in recreational swimming. Alternate programming will be provided. Summer Camps All-Star Camp Two great sports - basketball and soccer - one great camp! Develop
More informationGUIDELINES FOR SUBMISSION OF FINAL PLAN MATERIALS FOR BOARD OF TRUSTEES PRESENTATIONS MAJOR PROJECTS
Updated: June 2018 GUIDELINES FOR SUBMISSION OF FINAL PLAN MATERIALS FOR BOARD OF TRUSTEES PRESENTATIONS MAJOR PROJECTS 1. Formal Presentations are made to the University's Board of Trustees in February,
More informationOutdoor Recreation Facility Assessment Park and Recreation Board Briefing June 4, 2015
Outdoor Recreation Facility Assessment Park and Recreation Board Briefing June 4, 2015 1 Agenda Process Facility Evaluation Methodology Golf Course Findings and Recommendations Tennis Center Findings and
More informationAmerican Institute of Architects New Hampshire Chapter High School Design Competition Program
American Institute of Architects New Hampshire Chapter 2009 2010 High School Design Competition Program Educational Objectives To increase your awareness of the relationships between space, human scale
More information2018 AURORA AWARDS GALA Friday August 17, :30pm Cocktails & Networking 6:30pm 8:30pm Dinner & Awards Ceremony Elegant Attire Required
2018 AURORA AWARDS GALA Friday August 17, 2018 5:30pm Cocktails & Networking 6:30pm 8:30pm Dinner & Awards Ceremony Elegant Attire Required Established in 1979, AURORA Awards are presented annually to
More informationPlanning and Zoning Application & Checklist
City of Driggs, Idaho Planning & Zoning 60 S. Main Street PO Box 48 Driggs, ID 83422 Ph: (208) 354-2362 Fax: (208) 354-8522 www.driggs.govoffice.com Planning and Zoning Application & Checklist DESIGN REVIEW
More informationHostos Community College Master Plan Amendment
Hostos Community College Master Plan Amendment Prepared for: The City University of New York 1 Introduction College Overview Located in the South Bronx at the nexus of Mott Haven & Melrose neighborhoods
More informationThe PLAN The ReALITY The ReMeDY
The PLAN The REALITY The REMEDY PRZ s (Prescription Root Zone) Sports Field Assessment utilizes the following tools to produce an objective study of your sports fields: Initial site evaluation Our comprehensive
More informationNON-RESIDENTIAL DEVELOPMENT
GENERAL REQUIREMENTS (Print or Type) Name of Proposed Project: Location of Project: Legal Description of Project (Assessor s Parcel No. or T, R,S): Staff Use Only FILE NO.: RELATED FILES: Applicant s Name:
More informationAPPENDIX IV.A.3 Technical Memo Summarizing and Analyzing Illustrative Athletic Field Lighting Plan (January 2010)
APPENDIX IV.A.3 Technical Memo Summarizing and Analyzing Illustrative Athletic Field Lighting Plan (January 1) Technical Memo Summarizing and Analyzing Illustrative Athletic Field Lighting Plan for the
More informationCentral High School. 275 Lexington Parkway North. Project Summary: Issues Identified By School Community In 2015
275 Lexington Parkway North Project Summary: Central is the oldest high school in the state of Minnesota, beginning its 150th year. Its rich traditions, including academic excellence, are widely celebrated.
More informationCheney Building & Bennet Academy Town of Manchester Phase 1 Study Presentation - April 10, 2013 DRAFT
Cheney Building & Bennet Academy own of Manchester Phase 1 Study Presentation - April 10, 2013 Schools Modernization & Reinvestment eam Revisited Board of Directors Board of Education DRAF ai Soo Kim Partners
More informationGENERAL REQUIREMENTS (Print or Type) PROJECT DESCRIPTION OWNER CERTIFICATION
GENERAL REQUIREMENTS (Print or Type) Name of Proposed Project: Location of Project: Legal Description of Project (Assessor s Parcel No. or T, R S,): Staff Use Only CASE NO.: RELATED FILES: Applicant s
More informationCARES. Project Description: Center for Advancement of Research and Education in Sustainability ID 240 Interior Design II Project 1 Spring 2013
CARES Center for Advancement of Research and Education in Sustainability Objectives: 1) Researching client needs 2) Writing a detailed programming document 3) Preparing quick schematic solutions to a design
More informationCAC MEETING, FEB. 28 TH, 2017 NADAAA
ADAMS STREET BRANCH LIBRARY PROGRAMMING STUDY FOR CITY OF BOSTON BOSTON PUBLIC LIBRARY AND PUBLIC FACILITY DEPARTMENT CAC MEETING, FEB. 28 TH, 2017 NADAAA 1 AGENDA 1.0 SCHEDULE 2.0 SUMMARY OF PROJECT GOAL
More informationProcedure for Obtaining Design Review Committee Approval
Procedure for Obtaining Design Review Committee Approval The Declarations, Restrictions & Covenants of Hallbrook require that approval of the HOA DRC Committee must be obtained prior to commencing certain
More informationTown of Belmont, NH. Town Space Needs and Feasibility Study. January 10, 2019
Town of Belmont, NH Town Space Needs and Feasibility Study January 10, 2019 Police Department EXISTING POLICE DEPARTMENT FULLER STREET MEETING HOUSE SARGENT STREET TOWN OF BELMONT POLICE DEPARTMENT EXISTING
More informationProject: EIR for Carondelet High School Sports Complex
Attachment 7 May 4, 2016 Project: EIR for Carondelet High School Sports Complex Prepared by: Ronald Zeiger, PE Scope of Project: The proposed outdoor sports lighting consists of the following: Soccer/lacrosse
More informationContinuing Education Credit
BIM + CM-at-RISK = Saves You Time & $$$ Especially on Renovation Projects PeterMcElwain,AIA ArtCampbell,AIA Facilities/Planning RickScott,LEEDAP,CPC JohnCook.CPC CM-at-Risk/Construction JenniferS.Henrikson,AIA,LEEDAP
More informationGREENWICH PUBLIC SCHOOLS. Greenwich, Connecticut REQUEST FOR BOARD ACTION OR PRESENTATION OF INFORMATIONAL ITEM
Date of Meeting: March 20, 2014 GREENWICH PUBLIC SCHOOLS Greenwich, Connecticut Title of Item: New Lebanon School Pre-Feasibility Study Policy Reference: E - 051 REQUEST FOR BOARD ACTION OR PRESENTATION
More informationSITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS
INCORPORATED VILLAGE OF ROCKVILLE CENTRE BUILDING DEPARTMENT SITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS Presubmission - Prior to a formal submission, the applicant should meet in person with
More informationWILTON MANORS, Island City 2020 WILTON DRIVE, WILTON MANORS, FLORIDA 33305
WILTON MANORS, Island City 2020 WILTON DRIVE, WILTON MANORS, FLORIDA 33305 COMMUNITY DEVELOPMENT SERVICES (954) 390-2180 FAX: (954) 567-6069 This package includes: General Submittal Procedures Submittal
More informationProposed Telecommunications Facilities within the Prince George s County Public School System October 11, 2013
Proposed Telecommunications Facilities within the Prince George s County Public School System October 11, 2013 1. Background Wireless carries are searching for eight base station sites to provide cellular
More informationOUR GOAL IS TO GET 10 MILLION KIDS AND THEIR FAMILIES PLAYING & ENJOYING SPORTS, GETTING FIT & BEING ENTERTAINED IN POSITIVE WAYS.
2018 OUR GOAL IS TO GET 10 MILLION KIDS AND THEIR FAMILIES PLAYING & ENJOYING SPORTS, GETTING FIT & BEING ENTERTAINED IN POSITIVE WAYS. WE NEED TO BE PROFITABLE FOR THIS EFFORT TO BE SUSTAINABLE AND OUR
More informationSt. John Paul II Catholic Parish
St. John Paul II Catholic Parish 167th & Ridgeview Road Olathe, Kansas Master Plan Town Hall October 30, 2018 Purpose [ The Church s ] mission consists essentially in offering people an opportunity not
More informationAloha Swim Center. Summer Splash Swim Team
Aloha Swim Center 18650 SW Kinnaman Road, Aloha, 97078 503-629-6311 TriMet Routes #52, #57, #88 Aquatic Facility Supervisor: Brian Powers Summer Term: June 20 - Sept. 5, 2016 Office Hours: Schedule subject
More informationMADISON PUBLIC LIBRARY PINNEY PINNEY LIBRARY COMMUNITY UPDATE 11 / 09 / 2017
MADISON LIBRARY PINNEY PINNEY LIBRARY COMMUNITY UPDATE 11 / 09 / 2017 MADISON LIBRARY PINNEY CURRENT TIMELINE TIMELINE MADISON LIBRARY PINNEY MING/ PRE-DESIGN 1 SCHEMATIC DESIGN 2 DESIGN DEVELOPMENT 3
More informationOperating Standards Attachment to Development Application
Planning & Development Services 2255 W Berry Ave. Littleton, CO 80120 Phone: 303-795-3748 Mon-Fri: 8am-5pm www.littletongov.org Operating Standards Attachment to Development Application 1 SKETCH PLANS
More informationA. ARTICLE 4 SKETCH PLAN REQUIREMENTS, MAJOR SUBDIVISION AND/OR LAND DEVELOPMENT
400. 402.A. ARTICLE 4 SKETCH PLAN REQUIREMENTS, MAJOR SUBDIVISION AND/OR LAND DEVELOPMENT SECTION 400 PURPOSE The purpose of the Sketch Plan is to provide an opportunity for the applicant to consult early
More informationMEMORANDUM. March 31, President Michael K. Young President, Texas A&M University TO: CBE Recommendation: Softball Complex SUBJECT:
COUNCIL FOR THE BUlL T ENVIRONMENT Co-Chairs: Dr. Karan L. Watson, Provost and Executive Vice President Dr. Jerry R. Strawser, Vice President for Finance and Administration March 31, 2016 MEMORANDUM TO:
More informationWOODWARD BUILDING. Join a Corporate Community that Inspires
WOODWARD BUILDING Join a Corporate Community that Inspires EXPERIENCE The Ballantyne Advantage Abundant active green spaces Best access to extensive nearby talent pool for recruiting, retention and productivity
More informationMichelle Muro, AIA, NCARB
Michelle Muro, AIA, NCARB Portfolio of Work jj_mj_muro@yahoo.com 720 425 0842 AT & T Broadband World Headquarters, Denver, Colorado Barber Architecture, Intern: 1997 2001 For the interiors, Barber Architecture
More informationPUBLIC ART PLAN FOR THE NEW PATIENT TOWER, ETOBICOKE GENERAL HOSPITAL CAMPUS 101 HUMBER COLLEGE BLVD. TORONTO ONTARIO
PUBLIC ART PLAN FOR THE NEW PATIENT TOWER, ETOBICOKE GENERAL HOSPITAL CAMPUS 101 HUMBER COLLEGE BLVD. TORONTO ONTARIO FOR PRESENTATION TO THE TORONTO PUBLIC ART COMMISSION OCTOBER, 2016 Main Entrance,
More informationFCPS Rock Creek School Replacement and Final Site Selection Design Meeting #12 Notes
FCPS Rock Creek School Replacement and Final Site Selection Design Meeting #12 Notes Meeting Date: 15 March 2018 9:30 AM Meeting Location: Rock Creek School, Media Center Current Design Phase: Schematic
More information25,000 A BRAND LED BY DESIGN IDEOLOGY CRAFTED OVER 20 MILLION SQ.FT. DELIVERED DREAMS OF OVER BUILT A WIDE RANGE OF 80 DIVERSIFIED PROJECTS
MASTERPIECE IN A BRAND LED BY DESIGN IDEOLOGY BUILT A WIDE RANGE OF 80 DIVERSIFIED PROJECTS DELIVERED DREAMS OF OVER 25,000 HAPPY FAMILIES CRAFTED OVER 20 MILLION SQ.FT. Rendered Image Phase - 2, 2.5,
More informationCAS Section 7 Facilities/Technology/Equipment Team member comments and recommendation
CAS Section 7 Facilities/Technology/Equipment Team member comments and recommendation Ratings sub-sec The program has adequate, suitably located facilities, technology and equipment to 7.1 support its
More informationHorace Mann Elementary
2001 Eleanor Avenue Project Summary: Horace Mann is a neighborhood school filled with students who are excited to be here taught by teachers who transform excitement into achievement. Expectations are
More informationEvidence can be: a screenshot, photos, video, a diary, recipes, the finished product or even a blog.
Welcome to the Duke of Edinburgh s Award. You are required to complete one (1) of the following for 6 months and two (2) for 3 months. Please make sure you start the 6 month commitment during the break.
More informationBy Design Ideology. 80 DIVER SIFIED PROJEC TS 20 MILLI ON PROFIC IE NT TO DEVELOP 7.50 LAKH SQ.F T. PER ANNUM A BRAND LED C RAF TED OVER
DELIVERED DREAMS OF OVER 40,000 HAPPY FAMILIE S PROFIC IE NT TO DEVELOP 7.50 LAKH BUILT A WIDE RANGE OF SQ.F T. PER ANNUM 80 DIVER SIFIED PROJEC TS C RAF TED OVER 20 MILLI ON SQ.F T. A BRAND LED By Design
More informationART 3600, Interior Architecture Studio III Fall Grover Center W330 Tuesday & Thursday 1:30 4:20PM
ART 3600, Interior Architecture Studio III Fall 2018-2019 Grover Center W330 Tuesday & Thursday 1:30 4:20PM Matthew Ziff, M.Arch, Associate Professor, Area Chair Grover W325 740-593-2869 ziff@ohio.edu
More informationJoint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building
Joint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building City of Tacoma Steve Victor, Deputy City Attorney 253-591-5638 svictor@ci.tacoma.wa.us Pierce
More informationPLANNING DEPARTMENT SUBMITTAL REQUIREMENTS FOR CONDITIONAL USE PERMITS CLASS 4 DEVELOPMENT REVIEW PROCESS. A. Written Material
PLANNING DEPARTMENT 970.668.4200 0037 Peak One Dr. PO Box 5660 www.summitcountyco.gov Frisco, CO 80443 SUBMITTAL REQUIREMENTS FOR CONDITIONAL USE PERMITS CLASS 4 DEVELOPMENT REVIEW PROCESS Per the provisions
More informationOperating Standards Attachment to Development Application
Operating Standards Attachment to Development Application Planning & Development Services 2255 W Berry Ave. Littleton, CO 80120 Phone: 303-795-3748 Mon-Fri: 8am-5pm www.littletongov.org SITE DEVELOPMENT
More informationDOWNTOWN DEVELOPMENT REVIEW BOARD APPLICATION
This application, including the Conceptual Review Presentation, must be completed and submitted to the Downtown Development Review Board (DDRB) Staff twenty (20) business days prior to the upcoming DDRB
More informationSIXTH GRADE MATHEMATICS CHAPTER 10 AREA AND PERIMETER TOPICS COVERED:
SIXTH GRADE MATHEMATICS CHAPTER 10 AREA AND PERIMETER TOPICS COVERED: Perimeter of Polygons Area of Parallelograms Area of Triangles Area of a Trapezoid Area of Irregular Figures Activity 10-1: Sixth Grade
More informationISLAMIC CENTER OF MARYLAND
Paving the Way to an Enlightened Future.... What? Why? and How? Where Did We Start? In 1980 a group of brothers working in Bechtel Corporation started a prayer gathering (musalla) at Casey Community Center
More informationProximity to Employee Housing and Centers of commerce. 2 Minutes to Georgetown. 3 Minutes to The Pentagon
Proximity to Employee Housing and Centers of commerce 270 95 2 Minutes to Georgetown 3 Minutes to The Pentagon 4 Minutes to K Street 8 Minutes to Reagan National 9 Minutes to The White House 11 Minutes
More informationSPARTAN DAY CAMP 4814 FREEDOM RING RD
484 FREEDOM RING RD PROJECT DATA GENERAL PROJECT NOTES: LOCATION:. DIMENSIONS ARE TO FACE OF STUD OR TO COLUMN CENTERLINE UNLESS NOTED OTHERWISE. VERIFY ALL EXISTING CONDITIONS AND ADJUST WALL DIMENSIONS
More informationToronto Reference Library Premium Rental Space Renovation Award of Tender
STAFF REPORT ACTION REQUIRED 13. Toronto Reference Library Premium Rental Space Renovation Award of Tender Date: February 22, 2016 To: From: Toronto Public Library Board City Librarian SUMMARY The purpose
More informationChapter 24 Outdoor Lighting Ordinance
Chapter 24 Outdoor Lighting Ordinance Section 10:24:1 Section 10:24:2 Section 10:24:3 Section 10:24:4 Section 10:24:5 Section 10:24:6 Section 10:24:7 Section 10:24:8 Purpose Scope and Applicability Conformances
More informationA Higher Status 6901, 6903, 6905 ROCKLEDGE DRIVE BETHESDA, MARYLAND
A Higher Status 6901, 6903, 6905 ROCKLEDGE DRIVE BETHESDA, MARYLAND ELEVATE YOUR WORK DAY Whether it s stepping out for fresh air and taking a stroll through our quarter-mile of walking paths, participating
More informationHOMELAND DEFENSE/ NEIGHBORHOOD IMPROVEMENT BOND OVERSIGHT BOARD AGENDA
HOMELAND DEFENSE/ NEIGHBORHOOD IMPROVEMENT BOND OVERSIGHT BOARD AGENDA 4/22/14 6:00 P.M. CITY OF MIAMI CITY HALL CHAMBERS 3500 PAN AMERICAN DRIVE MIAMI, FLORIDA 33133 I. APPROVAL OF THE MINUTES FOR THE
More informationCLIPPER ESTATES HOMEOWNER S ASSOCIATION DESIGN GUIDELINES
CLIPPER ESTATES HOMEOWNER S ASSOCIATION DESIGN GUIDELINES CLIPPER ESTATES DESIGN GUIDELINES FEBRUARY 1995 INTRODUCTION 1 THE DESIGN REVIEW PROCESS 1 Design Review Approval 2 Architectural Submission 2
More informationGAZEBO BELMONT PUBLIC LIBRARY MAIN STREET TOWN OF BELMONT TOWN HALL 12/14/2018 EXISTING CONDITIONS
GAZEBO BELMONT LIBRARY STREET TOWN OF BELMONT TOWN HALL EXISTING CONDITIONS DRIVING LANE 6 4 WELLFARE 378 SF TOWN CLERK 800 SF LOBBY 256 SF COMMON SPACES 665 SF LG MEETING RM 600 SF DRIVING LANE TOWN ADMIN.
More informationMarch 23, 2015 Total Project Cost 18,553,027
Executive Summary Charles City CSD Middle School Addition 25% CD Up April 3, 205 Project Approach This up to be considered recap of changes since March 23, 205 budget. It is intended to reflect significant
More informationA BEST IN CLASS OFFICE CENTER CAMPUS CREATIVE SPACES AVAILABLE WITH ROOM TO GROW
A BEST IN CLASS OFFICE CENTER CAMPUS CREATIVE SPACES AVAILABLE WITH ROOM TO GROW AVAILABILITIES A VARIETY OF CREATIVE SPACES WITH ROOM TO GROW UP TO 195,000 SF Planned New Cafe & Fitness Center Expo Line
More informationBartlett High School MASTER PLAN May 25, 2017
Bartlett High School MASTER PLAN May 25, 2017 Facility Assessment Summary I. I.1 - Site Appraisal Site Appraisal The current high school was built in multiple phases, which presents challenges in layout
More informationMODULE 4 Planning your house continued
MODULE 4 Planning your house continued Planning Entrances Identify the purpose, uses and activities at the main entrance in a residence. Describe possible moods or feelings that a designer may try to convey/evoke
More informationNEWS. News Sports A&E Opinion Blogs Multimedia. UC Berkeley robot fleet takes over California waterways to gather data RELATED POSTS NEWS CAMPUS
Monday, May 21, 2012 ADVERTISE JOB BOARD PRESS PASS SUBSCRIBE DONATE ABOUT News Sports A&E Opinion Blogs Multimedia Search Research & Ideas SUNDAY, MAY 20, 2012 UC Berkeley robot fleet takes over California
More informationCONFEDERATION LINE PRESENTATION TO RPIC CONFERENCE
CONFEDERATION LINE PRESENTATION TO RPIC CONFERENCE Dennis Gratton Manager, Rail planning, Rail Implementation Office & Annie Hillis Public Art Coordinator, Rail Implementation Office November 7, 2013 OVERVIEW
More informationSite Plan/Building Permit Review
Part 6 Site Plan/Building Permit Review 1.6.01 When Site Plan Review Applies 1.6.02 Optional Pre- Application Site Plan/Building Permit Review (hereafter referred to as Site Plan Review) shall be required
More information