1 Solano Community College District Project and RFP #8-00 ADDENDUM TO RFP DOCUMENTS ADDENDUM #0 Project: Solano Community College District Vacaville Center HVAC Upgrade Project Project #8 00 Date: February, 08 Addendum # 0 The following clarifications are provided based on questions received and must be added/considered when completing your submittal: Acknowledgement of receipt of this ADDENDUM is required in the proposal s cover letter of introduction. Please clearly note the addendum date and number. ITEM: ITEM NO. SECTION 00, Item Bid Date The bid date has been extended by two () weeks to Thursday, March, 08 at :00 PM in order to be able to incorporate technical Mechanical, Electrical, Architectural and Structural specifications into the bid documents. These specifications will be included in the upcoming Addendum. The location and process for submission of bids remains unchanged. ITEM NO. ARCHITECTURAL PLAN SHEETS A3. & A3.8 Replace Plan Sheets A3. and A3.8 with the attached Addendum Plan Sheets A3. and A3.8. Revisions include the clarification between demolition and replacement of existing ceilings.. ITEM NO. 3 STRUCTURAL DETAIL SK Add the attached Structural Detail Addendum SK, which clarifies the extension of the parapet wall at the roof. ITEM NO. ANSWERS TO SUBMITTED QUESTIONS QUESTION During the job walk, it was mentioned that the IT department for the college will remove the computers as needed in the classrooms and server room during construction. Please confirm that Solano College will be responsible for removing the computer equipment as needed. ANSWER A preconstruction walk will be held with the IT department and the successful contractor to establish which computer equipment will need to be temporarily relocated during construction. All relocation and re installation work will be performed by the District s IT department. February, 08 Vacaville Center HVAC Upgrade Project ADDENDUM # 0 Page of
2 Solano Community College District Project and RFP #8-00 QUESTION New Rooftop units will be provided with duct smoke detectors. Duct smoke detectors will need to be interconnected with the existing fire alarm. Please provide the contact information of the existing fire alarm service provider. ANSWER The Fire Alarm Monitoring company is Sac. Valley Alarm. The contact is Brad Niblinc at (9) 8. Repairs and technical information on the system are covered by Quality Sound. The contact is Matt Cooper at (09)98 0. QUESTION It was mentioned on the job walk that there will be no summer school. Please confirm there will be no summer school. ANSWER Confirmed, although there will be summer school activity in the adjacent Biotech Building, which has a connecting lobby to the Vacaville Center. The existing MDF Room will need to remain in operation, with the required level of cooling maintained, throughout the project as it serves both facilities. February, 08 Vacaville Center HVAC Upgrade Project ADDENDUM # 0 Page of
3 Pre-Bid-00 Request For Information Bell Products, Inc. DELIVERIES: Soscol Avenue MAILING: PO Box 39 Napa CA Phone: (0) -8 Fax: (0) -908 Project: Solano College- Vacaville Center HVAC Upgrades Job #: BPI RFI Number: Submitted By: Co-Author: Pre-Bid-00 Rolando Roldan Casey Clark Specification Number: Drawing Number: Sent Date: Sheet A Submitted To: Sent To: Date Required: Scott Glover ASAP Copies To: Potential Time Impact: Potential Cost Impact: of: days of: ~ Subject: nd Floor South Reflected Ceiling Plan Routing: - OWNER - PM - File - HVAC FO PIPING FO Information Requested: Sheet A.3 has a hand written note to extend parapet wall to achieve min.. Please provide a structural detail to extend the parapet wall that includes roofing and flashing. Response: Extend the existing parapet per the attached SK. Katy Briggs BASE Design February 0, 08
4
5 Pre-Bid-00 Request For Information Bell Products, Inc. DELIVERIES: Soscol Avenue MAILING: PO Box 39 Napa CA Phone: (0) -8 Fax: (0) -908 Project: Solano College- Vacaville Center HVAC Upgrades Job #: BPI RFI Number: Submitted By: Co-Author: Pre-Bid-00 Rolando Roldan Casey Clark Specification Number: Drawing Number: Sent Date: Sheet A3. & A Submitted To: Sent To: Date Required: Scott Glover ASAP Copies To: Potential Time Impact: Potential Cost Impact: of: days of: ~ Subject: New RCP for new work Routing: - OWNER - PM - File - HVAC FO PIPING FO Information Requested: The second floor North and South reflected ceiling plans shown on A3. & A3.8 are identical to the second floor North reflected ceiling plans shown on A3.3 & A3. Please provide the corrected sheet showing the new work. Response:
6 NOTES:. REFER TO MECHANICAL DRAWINGS FOR ADDITIONAL INFORMATION.. ALL DIMENSIONS ARE TO BE FIELD VERIFIED. 3. PATCH AND REPAIR FINISHES TO MATCH ADJACENT FINISHES AFFECTED BY DEMOLITION. REFLECTED CEILING PLAN NOTES:. REFER TO MECHANICAL FOR ADDITIONAL EQUIPMENT INFORMATION. 3 A (TYP ) B C D E (TYP ) (E) EA RISER 80 CFM "Ø 80 CFM COMPUTER LAB (E)SA RISER "Ø (E)0x (E)X xl (E)0X (E)SA RISER 30 CFM xl xl xl x xl (E)x "Ø (E)x xl STAIR 3 0 CFM "Ø xl 3 CFM (TYP ) 0 CFM (E)TRANSFER/RELIEF DUCT, CEILING GRILLE AND WALL LOUVER (TYP). SOLANO COMMUNITY COLLEGE DISTRICT VACAVILLE CENTER 00 N VILLAGE PKWY VACAVILLE, CA 988 SERVER ROOM 0 IT SUPPORT 09 (E) EA RISER (TYP ) F "Ø x G 80 CFM (TYP ) COMPUTER LAB CFM xl xl xl (E)SA RISER 3 xl (E)0x "ØL 0 CFM 8 CFM (TYP ) CONSULTANT (E)x H CFM (TYP ) 00 CFM "Ø 0 CFM (E)RESTROOM EXHAUST SYSTEM TO REMAIN. MEN'S REST ROOM 9 J (E)X (E)0x (E)0x 0 3 xl DSA BACK CHECK 0 xl WOMEN'S REST ROOM 0 K STUDY LOUNGE 0 30 CFM (TYP ) 00 CFM (TYP ) NO DATE BY DESCRIPTION REVISIONS DRAWN: CHECKED: L SEE CONTINUATION MATCH LINE /A3.8 DATE: SCALE: PROJECT NUMBER: 900 REFLECTED CEILING PLAN DRAWING NUMBER:
7 NOTES:. REFER TO MECHANICAL DRAWINGS FOR ADDITIONAL INFORMATION.. ALL DIMENSIONS ARE TO BE FIELD VERIFIED. 3. PATCH AND REPAIR FINISHES TO MATCH ADJACENT FINISHES AFFECTED BY DEMOLITION. REFLECTED CEILING PLAN NOTES:. REFER TO MECHANICAL FOR ADDITIONAL EQUIPMENT INFORMATION. (TYP ) SEE CONTINUATION MATCH LINE /A3. N CONFERENCE 3 ROOF DECK STAFF LOUNGE CFM (TYP 3) 3 (E)0x 300 CFM (TYP ) 00 CFM 0 CFM xl (E)"Ø (E)0x 80 CFM (TYP ) (E)"Ø "Ø 0 CFM xl (E)0"Ø (E)x0 DATA xl x0 30 CFM 0 CFM STAIR STAFF RESTROOM 3 9 (E)0"Ø 0"Ø 8 3 MACH 0 "Ø 0x "Ø 0 CFM (TYP ) STUDY/PHONE 30 3 " HIGH RA PLENUM (E)x 80 CFM (TYP 3) (E)"Ø 30 CFM "Ø (E)0"Ø 0 CFM (E)x8 0 CFM 30 CFM 0 30 CFM 30 CFM 39 0 CFM 00 CFM (E) JANITOR STORAGE CFM 00 CFM 3 CFM (TYP ) X (E)X CFM (TYP ) 80 CFM (TYP ) P Q R S T U SOLANO COMMUNITY COLLEGE DISTRICT VACAVILLE CENTER CONSULTANT 00 N VILLAGE PKWY VACAVILLE, CA CFM 3 80 CFM 300 CFM 0 (E)0"Ø 80 CFM 00 CFM (TYP 3) COPY/WORK ALCOVE DSA BACK CHECK NO DATE BY DESCRIPTION REVISIONS DRAWN: DATE: CHECKED: SCALE: PROJECT NUMBER: 900 REFLECTED CEILING PLAN DRAWING NUMBER:
Bid No. B14-02 Building 100 HVAC Improvements
Bid No. B14-02 Building 100 HVAC Improvements Addendum No. 1 This Addendum No. 1 sets forth modifications to portions of the bid and contract documents for the above-referenced work described as: Building
More informationADDENDUM TO RFQ/P DOCUMENTS PROJECT # ADDENDUM: #01
ADDENDUM TO RFQ/P DOCUMENTS PROJECT #14-013 ADDENDUM: #01 Solano Community College District SCCD REQUEST FOR QUALIFICATIONS/PROPOSAL Project: HVAC & EMS Efficiency Project Implementation Date: 03/28/2014
More information4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118
PART 1: GENERAL This section of the design standard outlines general requirements for electrical and telecommunications designs to be performed for the University of Texas at Austin. This standard is intended
More informationADDENDUM 1. This Addendum forms part of and modifies Proposal Documents dated, October 31, 2018, with amendments and additions noted below.
DATE: November 16, 2018 PROJECT: JJL Library & Street Level Renovation RFP NO: 744-R1903 OWNER: The University of Texas Health Science Center at Houston TO: Prospective Proposers This Addendum forms part
More informationLincoln County Tax Appraisal Office Project No. RFB
Red Bike Architecture, PLLC James M. Ratliff, Architect, NCARB P.O. Box 574, Rutherford College, NC 28671-0574 Phone: 828-413-2276 Email: ratliffarch@outlook.com Addendum #1 July 3, 2018 Project: Interior
More informationADDENDUM NO. 1 REQUEST FOR QUALIFICATIONS (RFQ) AND REQUEST FOR PROPOSALS (RFP) FOR. RFQ/RFP No. 15P40. Campus Center East HVAC Unit Replacement
ADDENDUM NO. 1 REQUEST FOR QUALIFICATIONS (RFQ) AND REQUEST FOR PROPOSALS (RFP) FOR RFQ/RFP 15P40 Campus Center East HVAC Unit Replacement CHAFFEY COMMUNITY COLLEGE DISTRICT February 26, 2015 CHAFFEY COMMUNITY
More informationBIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D
HOSKINS ARCHITECTURE, LLC 1721 4 th AVENUE NORTH, SUITE 101 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 7 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS
More informationADDENDUM NOTICE INTERIOR RENOVATIONS AT THE BATHURST CLARK RESOURCE LIBRARY, 900 CLARK AVENUE WEST, VAUGHAN, ON
The City of Vaughan Procurement Services Department 2141 Major Mackenzie Drive Vaughan, ON L6A 1T1 Tel (905) 832-8555 ADDENDUM NOTICE ADDENDUM NO. 3 Total of (5) page BID NO. T18-003 DESCRIPTION: INTERIOR
More informationAcknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may disqualify Bidder.
ADDENDUM TWO Client: The Abla Griffin Partnership Project Name: Sooner Elementary Media Center Saferoom Project Location: Oklahoma City, OK Issue Date: February 22, 2018 Owner: Moore Public Schools Engineer:
More informationADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC.
ADDENDUM NO. 2 PROJECT: OWNER: ENGINEER / ARCHITECT: PROJECT LOCATION: Saginaw County Community Mental Health Authority Germania Club Renovation Phase 2 Saginaw County Community Mental Health Authority
More informationApril 7, City of Verona Adam Sayre, AICP Director of Planning & Development 111 Lincoln St. Verona, WI 53593
April 7, 2016 City of Verona Adam Sayre, AICP Director of Planning & Development 111 Lincoln St. Verona, WI 393 RE: Conditional Use Arby s Restaurant Multi-Tenant Development 631 Hometown Circle-Lot 6
More informationSpecifications: Other: sign in sheet
To: All Vendors Bidding on The College of New Jersey Nursing Simulation Lab Fit-Out Project From: Roselle Horodeski Finance & Business Services Date: July 29, 2015 ADDENDUM NO. 1 ISSUE DATE: July 29, 2015
More information12560 W. Cedar Drive Lakewood, CO Barry Himmelman President
Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 16-BS-2260 ADDENDUM NUMBER FOUR January 8, 2016 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM
More informationDecember 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions
December 31, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y16-721-MM / ADDENDUM No. 1 ORANGE COUNTY CONVENTION CENTER PHASE III VALENCIA BALLROOM RENOVATION Bid Opening Date: January 12, 2016
More informationCLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017.
June 15, 2017 GS#108-281 Greene Hall Renovations University of Southern Mississippi Hattiesburg, Mississippi 00.910 ADDENDUM NO 1. This Addendum contains 6 pages and 21 pages of attachments for a total
More informationCHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT
1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department October 25, 2010 Addendum No. 09.R INVITATION FOR BID NO.: 11-05 Modernization of Classroom Building 300 Chabot
More informationStantec Architecture Inc South Flores Street Suite 201 San Antonio TX Tel: (210) Fax: (210)
Stantec Architecture Inc. 1344 South Flores Street Suite 201 San Antonio TX 78204-1672 Tel: (210) 223-9588 Fax: (210) 223-9589 ADDENDUM #1 07/11/2014 TO PLANS AND SPECIFICATIONS FOR RENOVATION AND ADDITION
More informationELECTRICAL GENERAL DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL Electrical/Telecommunications Design
PART 1: GENERAL 1.01 Electrical/Telecommunications Design A. This section of the design and construction standard outlines general requirements for electrical and telecommunications designs to be performed
More informationBidders and Others to Whom Bidding Documents have been issued by the Architect and/or CM.
ADDENDUM NO. March 3, 202 Re: MCC Student Center Addition, Manchester, NH To: Bidders and Others to Whom Bidding Documents have been issued by the Architect and/or CM. All items in this Addendum shall
More information2. Electrical rooms shall be centrally located and stacked so that feeder conduits and bus duct are run as straight and short as possible.
PART 1: GENERAL 1.01 Electrical/Telecommunications Design A. This section of the design and construction standard outlines general requirements for electrical and telecommunications designs to be performed
More informationCity Plaza Energy Upgrades Timeline of Events Pella Window Cancellation
City Plaza Energy Upgrades Timeline of Events Pella Window Cancellation June 3, 2010 Pella asks what is needed for submittals. See Attachment #1. June 7, 2010 Pella (Matt Tison) confirms the receipt of
More informationADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION
July 6, 2011 City of Miami Fire Station #13 ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION This Addendum is issued to modify the previously issued Bidding and Contractual Documents,
More informationTri-County Commercial Application Checklist
TRI-COUNTY SERVICE CENTER TRI-COUNTY SERVICE CENTER State of Oregon Clackamas Multnomah Washington C O U N T I E S Tri-County Commercial Application Checklist Department of Consumer & Business Services
More informationPROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic
GENERAL SITE PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS Scope of work narrative Building code review Description of construction Documentation on drawings as List of applicable
More informationM1.0 MECHNANICAL FLOOR PLAN
GENERAL NOTES A. CONTRACTORS AND SUB CONTRACTORS SHALL CAREFULLY REVIEW THE CONSTRUCTION DOCUMENTS. INFORMATION REGARDING THE COMPLETE WORK IS DISPERSED THROUGHOUT THE DOCUMENT SET AND CANNOT BE ACCURATELY
More informationADDENDUM #1. April 29, 2009
April 29, 2009 Re: HACC, Central Pennsylvania s Community College Midtown 1 CCTA Phase 2 Solicitation # 09-17 From: Eastern pcm, LLC Construction Manager HACC 212 Locust Street, Suite 604 Harrisburg, PA
More informationPLAN SUBMITTAL REQUIREMENTS
DEPARTMENT OF ECONOMIC AND COMMUNITY DEVELOPMENT BUILDING DIVISION PLAN SUBMITTAL REQUIREMENTS Residential and Commercial Projects Welcome to the South San Francisco Building Division. We are providing
More informationCHICAGO LANDMARKS PERMIT APPLICATION AND PRE-PERMIT SUBMISSION REQUIREMENTS
CHICAGO LANDMARKS PERMIT APPLICATION AND PRE-PERMIT SUBMISSION REQUIREMENTS The Commission on Chicago Landmarks reviews all permit applications for work to designated and proposed Chicago Landmarks and
More informationA/E REVIEW CHECKLIST HVAC
A/E CHECKLIST HVAC Reviewers should - Use Checklists when reviewing any type of VA construction project for the following disciplines: Site and Landscape, Architectural, Structural, Plumbing, Fire Protection,
More informationCommercial Infill Project Guide
Commercial Infill Project Guide City of Nixa PO Box 395 715 W. Mt. Vernon P (417)725-5850 F(417)724-5750 If you are moving your business into an existing building that is considered an infill and a permit
More informationFAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014
FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services ADDENDUM #4 December 5, 2014 This Addendum is issued to provide answers to questions from potential bidders
More informationWWRC, Inc W. 7th Clovis, NM (575) Fax (575) SIERRA MIDDLE SCHOOL ADDITION & RENOVATIONS ROSWELL INDEPENDENT SCHOOL DIST.
WWRC, Inc. 1716 W. 7th Clovis, NM 88101 (575)769-2618 Fax (575)742-3209 November 10, 2008 SIERRA MIDDLE SCHOOL ADDITION & RENOVATIONS ROSWELL INDEPENDENT SCHOOL DIST. MEETING MINUTES DATE OF MEETING: Tuesday
More information03/7/12 Issuance UTD Section Page 1 of 5 Electrical General
SECTION 26 01 00 ELECTRICAL GENERAL PART 1: GENERAL 1.1 Electrical/Telecommunications Design 1.1.1 This section of the design and construction standard outlines general requirements for electrical and
More informationSECTION D BIM COORDINATION DRAWINGS - CONTRACTORS
END OF SECTION 01 30 00 SECTION 01 31 21-3D BIM COORDINATION DRAWINGS - CONTRACTORS PART 1 - GENERAL 1.01 RELATED DOCUMENTS Attention is directed to Bidding and Contract Requirements, and to Division 1,
More informationREVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty
HOT AISLE CONTAINMENT SYSTEM (HACS) REVISION #1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. B. C. Drawings and general provisions of the Contract, including General and Supplementary. Conditions apply to
More informationADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS
ADDENDUM NO. TWO To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS Prepared By: ARCHITECT Bhide & Hall Architects, P.A. 1329-C Kingsley
More informationThe following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents, Inquiry No. 17-WDI-031.
ADDENDUM NO. 2 April 11, 2017 Page 1 The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents,. These Exhibits are re-issued in their entirety, unless
More informationDESIGN REVIEW BOARD APPLICATION EXTERIOR PLAN / LANDSCAPE PLAN
209 S. Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org DESIGN REVIEW BOARD APPLICATION EXTERIOR PLAN / LANDSCAPE PLAN *** IMPORTANT INFORMATION Please
More informationADDENDUM NO. 2. The Bid Opening has not changed it remains December 8, 2016 AT 1:30 P.M.
ADDENDUM NO. TO: PLANS AND SPECIFICATIONS FOR STATE OF MISSOURI Health Center Renovation Missouri School for the Blind NO. E60-0 The Bid Opening has not changed it remains December 8, 06 AT :30 P.M. GENERAL
More informationADDENDUM NO. 1 PAGE 1 of 2
Rochester Buffalo Syracuse Capital District OWN OF BRIGHON - PUBLIC SAFEY WING - HVAC UPGRADES M/E Reference 5009 November 5, 05 NO. PAGE of his Addendum contains changes to the requirements of the Bidding
More informationAnswer: Only to ChurchWoods, LLC.
ADDENDUM ADDENDUM NO.: 3 DATE: 06/27/16 PROJECT: CHW ChurchWoods PROJECT ADDRESS: 4130 Old Post Road Charlestown, RI TO: All Bidders of Record: This Addendum forms a part of and modifies the bidding requirements
More informationSECTION PROJECT MANAGEMENT AND COORDINATION
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationPRESENT: Dr. George Mannon TUSD Superintendent Dr. Donald Stabler TUSD Deputy Superintendent. Marybeth Spadafino Committee Member: Admin.
MEETING DATE: March 22, 2010 PROJECT: Bert Lynn Middle School Modernization Site Committee Meeting #5 HMC PROJECT #: 3203-037-000 PRESENT: Dr. George Mannon TUSD Superintendent Dr. Donald Stabler TUSD
More informationFIRE STATION NO TH STREET NORTH ST. PETERSBURG, FL M-1 SCOPE OF WORK SYMBOL DESCRIPTION SYMBOL DESCRIPTION HVAC SYMBOL LEGEND
HVAC SYMBOL LEGEND HVAC PIPING AND VALVES LEGEND HVAC GENERAL NOTES SCOPE OF WORK SYMBOL DESCRIPTION SYMBOL DESCRIPTION SYMBOL DESCRIPTION SYMBOL DESCRIPTION PHASING OF WORK HVAC ABBREVIATIONS ABBREVIATION
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 2
SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 2 PROJECT: June Jordan School for Equity DATE: April 17, 2017 Security Cameras & Science Classrooms Improvements Project
More informationCity of Thousand Oaks
TENANT IMPROVEMENT SUBMITTAL CHECKLIST SUBMIT THREE SETS OF SCALED DRAWINGS (ONE TO BE A BLACKLINE SET) WITH THE FOLLOWING INFORMATION: 1. 2. 3. 4. 5. 6. 7. 8. 9. SITE PLAN: Show building location (vicinity
More informationTo Contractor: Cris Goldy GH Phipps Construction Companies 5995 Greenwood Plaza Blvd, Suite 100 Greenwood Village, CO , Ext 1255
Seventeenth Street Denver Colorado 00 0 Fax 0 0 amd@amdarchitects.com Anderson ndersonmason asondale ale Architects WORK CHANGE PROPOSAL REQUEST # 00 Date: June 0 Project #: 0.00 Project: DU RSECS + Knoebel
More informationS T U D I O P C M A R T I N E Z EXISTING SITE PLAN SCALE: 1" = 10' - 0" SET # GENERAL NOTES: Site/Roof Drainage Plan OCTOBER 16, 2015 CHABAD
\\CANDELA\projects\-Chabad Center\Current Drawings\Chabad - -A-.0-extg-demo-site-plan.dwg, 0/0/0 :: PM, DWG To PDF.pc A-.0 SITE PLAN SCALE: " = 0' - 0" NORTH GENERAL NOTES: Site/Roof Drainage Plan. THE
More informationFIRE SPRINKLER SYSTEM SUBMITTAL CHECKLIST AND APPLICATION
PERMITS AND INSPECTIONS FIRE SPRINKLER SYSTEM SUBMITTAL CHECKLIST AND APPLICATION 911 Assigned PROJECT Subdivision: Lot: Blk: Sec: PROJECT New Construction Addition/Remodel Demolition Other: Number of
More informationAPPLICATION FOR CERTIFICATE OF APPROPRIATENESS IN THE HISTORIC DESIGN REVIEW DISTRICT
209 South Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org APPLICATION FOR CERTIFICATE OF APPROPRIATENESS IN THE HISTORIC DESIGN REVIEW DISTRICT *** IMPORTANT
More information754 Sir Francis Drake Boulevard
APN: 006-09 - 39 Town of San Anselmo Submittal Number : April 06 Revised June 0, 06 PROJECT TEAM INDEX TO DRAWINGS APPLICANT MONFREDINI PROPERTIES LLC South San Francisco, California 94080 (650) 873-0440
More informationRequest for Information 0026
Request for Information 0026 Detailed, RFIs Grouped by RFI Number SLAC Photon Science Lab (PSLB) Project # 02001.105960 2575 Sand Hill Road Tel: Fax: Menlo Park, CA 94025 RFI #: 0026 Date Created: 4/4/2017
More informationMontclair, NJ ADDENDUM NO. 1 Issue Date: May 15, 2017
Montclair, NJ 0704 ADDENDUM NO. Issue Date: May 5, 207 Request for Proposal # 294 Building 47 West Renovation- Phase 6a Number of Pages: 2 plus 5 sketches Date of Original Bidding Documents: April 26,
More informationMarshall Truck Station Laboratory Addition Project No. TZ MnDOT
Marshall Truck Station Laboratory Addition Project No. TZ-91523 MnDOT 13-6574 ADDENDUM NUMBER 2 DATED September 19, 2013 Marshall Truck Station Laboratory Addition Project No. TZ-91523 MnDOT 13-6574 Architect:
More information1.01 NOTICE TO BIDDERS
ADDENDUM NO. 1 1.01 NOTICE TO BIDDERS A. Date: 15 March 2013 B. From: Bahr Vermeer and Haecker Architects, Ltd. C. To: Prospective Bidders. D. Project: Lexington Public Schools Lexington Middle School
More information05BDB ADDENDUM 002. Thomas W. Wathen Business Division Building Renovation GENERAL ITEMS:
ADDENDUM 002 Addendum - 002 to the Drawings and Specifications dated, March, 2019, for Vincennes University, located at the Vincennes Campus in Vincennes, Indiana, as prepared by Andrew Young, Campus Architect,
More informationMSU Barnard Hall 105 Cleanroom Installation PPA # Page 1
ADDENDUM NUMBER 1 DATE: February 10, 2017 PROJECT: MSU Barnard Hall Room 105 Cleanroom Installation PPA# 16-0002 (Consulting Design Solutions, Inc. Project # 1613) BID DATE: February 23, 2017 2:00 PM,
More informationSECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationAddress: South Elgin, IL Phone: ( ) - Fax: ( ) - Cell: ( ) - Contractor Type: Phone: ( ) - Fax: ( ) - Cell: ( ) - Contact Type:
Community Development Department 10 N. Water Street Monday Friday 847 741 3894 8:30 a.m. 5:00 p.m. 847 741 3959 FAX www.southelgin.com BASEMENT REMODEL APPLICATION PROPERTY INFORMATION South Elgin, IL
More informationCITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT
CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS For EQUIPMENT FOR THE 2014 CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT WASTEWATER TREATMENT PLANT IMPROVEMENT PROJECT:
More informationWayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009
ADDENDUM NO 2 OWNER: Wayne State University DATE: January 4 th, 2019 PROJECT: NM Project Number: 18113.0 ARCHITECT: ENGINEER: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009 IMEG 26200 Town
More informationTO WHOM IT MAY CONCERN:
TO WHOM IT MAY CONCERN: A lot of questions are asked throughout the year as to when a building permit is required. This list may help identify some of the instances when a permit would be required: Permit
More informationAPPLICATION FOR COMMERCIAL CONSTRUCTION FIRE AND LIFE SAFETY PLAN REVIEW PROJECT INFORMATION: Project phone: Project Address: City: State: Zip:
Central Lyon County Fire Protection District 246 Dayton Valley Rd Suite 106 Dayton, NV 89403 Rich Harvey, Chief Office (775) 246-6209, Fax (775)246-6204 TTY 7-1-1 APPLICATION FOR COMMERCIAL CONSTRUCTION
More informationState College Area School District
State College Area School District The following is a guideline for project design submittals to the Facility Committee of the State College Area School District. During the design process the committee
More informationREQUEST FOR INFORMATION (RFI)
Planning, Development & Facilities 349 Magnolia Avenue Glendale, California 91204 Tel: 818.507.0201 Fax: 818.507.4911 Project Name: Jefferson ES-12 Classroom Bldg. DSA No: A#:03-114361, File#:19-41 District
More informationCS2.0 COVER SHEET VOL. 2
ARCHITECT GEORGE CROMWELL ELEMENTARY SCHOOL REVITALIZATION 525 Wellham Avenue Glen Burnie, Maryland 21061 OWNER ANNE ARUNDEL COUNTY PUBLIC SCHOOLS 9034 FT. SMALLWOOD ROAD PASADENA, MARYLAND 21122 tel:
More informationMcKenzie County Healthcare Systems
McKenzie County Healthcare Systems Hospital Replacement and Long-Term Care Replacement Watford City, North Dakota Request for Proposal (RFP) for Distributed Antenna System Table of Contents Introducti
More informationA. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationWTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) CITY OF CARTERSVILLE
WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) ADDENDUM NO.1 ADDENDUM NO. 1 DATE: OCTOBER 16, 2018 To BID, CONTRACT, BONDS AND SPECIFICATIONS FOR CONSTRUCTING WATER TREATMENT PLANT FILTERS REHABILITATION
More informationWendell E Green Elementary School 1150 W 96th St Chicago, IL 60643
11 W 9th St Chicago, IL 3 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationDOCUMENT LIST OF DRAWINGS, TABLES AND SCHEDULES
DOCUMENT 00 0115 LIST OF DRAWINGS, TABLES AND SCHEDULES DRAWINGS GENERAL A0.0 COVER SHEET ADDENDUM #2 revised A0.01 TITLE SHEET ADDENDUM #2 revised CIVIL C1.0 TOPO C2.0 DEMOLITION C3.0 TEMPORARY STREET
More informationADDENDUM #2 September 12, 2018
Physical Plant Services Project Management 1000 Rim Drive Phone: (970) 247-7523 Fax: (970) 247-7555 Project No. 2007-130P18 Whalen Gymnasium Expansion and Renovation for Exercise Science Request for Qualifications
More informationPROJECT LOCATION BOZEMAN HIGH SCHOOL. ELECTRICAL ENGINEER: Van Dykken Engineering 37 Spanish Peak Drive Bozeman, MT Phone:
DRAWING INDEX GENERAL C. PROJECT COVER G-WING A/V IMPROVEMENTS.0 AREA PLAN ST FLOOR SOUTH. TYP. PROJECTOR MOUNTING & PROJECTOR NOTES.2 G-WING TECHNOLOGY CABINET ELEVATIONS.3 G-WING WIRING DIAGRAM.4 G-WING
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1
SAN FRANCISCO UNIFIED DISTRICT, DESIGN AND ADDENDUM NO. PROJECT: ADA Site Improvements of April 0, 08 Upper Play Yard at Noriega EES 775 44 th -Avenue San Francisco, CA 94 SFUSD Project No. 004 OWNER:
More informationPMA ONLINE TRAINING. Commercial Drawings. One Hour Continuing Education
PMA ONLINE TRAINING Commercial Drawings One Hour Continuing Education PMA training disclaimer The information provided in this document is intended for use as a guideline and is not intended as, nor does
More informationCity of Lompoc Building & Safety Services Section 100 Civic Center Plaza Lompoc, CA Phone: Fax:
City of Lompoc Building & Safety Services Section 100 Civic Center Plaza Lompoc, CA 93436 Phone: 805-875-8220 Fax: 805-875-8198 RESIDENTIAL BUILDING PLANS SUBMITTAL REQUIREMENTS A. APPLICATION PROCESS
More informationChuck Caesar. VIA: /Webposting April 27, 2017
VIA: Email/Webposting April 27, 2017 O Haver Contractors 12831 O Connor Road San Antonio, TX 78233 Telephone 210-590-2889 Fax 210/657-5888 Attn: John Zamoyski, Project Manager Email johnz@ohcltd.net John
More informationThis Revision No. 01 becomes as fully a part of the first issued documents as if originally issued therewith or originally contained therein.
Revision No. 01 Issued February 19, 2016 Page 1 This Revision No. 01 becomes as fully a part of the first issued documents as if originally issued therewith or originally contained therein. This Revision
More informationEstimated Cost of Project Contractor License No. Contractor Qualifier No.
Building, Safety and Zoning Department COMMERCIAL Application for Building Permit Owners and/or Contractors: Please fill out all the information listed below and submit those documents needed for your
More informationCHAPMAN GRIFFIN LANIER SUSSENBACH ARCHITECTS, INC. ARCHITECT S ADDENDUM NO. 06
CGLS A R C H I T E C T S CHAPMAN GRIFFIN LANIER SUSSENBACH ARCHITECTS, INC. 2500 Cumberland Parkway Suite 350 Atlanta, Georgia 30339 404.733.5493 (voice) 404.733.6804 (fax) www.cglsarchitects.com ARCHITECT
More informationResidential Construction Checklist Single and Two Family Construction
DATE: _ Building Inspection Submittal Requirements Residential Construction Checklist Single and Two Family Construction Submit a City of Big Spring Permit Application, checklist, and 3 complete hard copy
More informationOLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN
KBE APPROVAL DATE: APRIL 2013 including Finding #1 g g OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN PLAN OF SCHOOL ORGANIZATION 1. Current Plan PS, K-5, 6-8, 9-12 2. Long Range Plan PS, K-5, 6-8, 9-12
More informationNETWORK CIRCLE SANTA CLARA CA
4160-4200 & 4050 PALM DRIVE ±302,066 SF Office Space Available For Lease in Silicon Valley ROMY ZEID +1 650 492 5206 romy.zeid@colliers.com CA License No. 01433654 JAKE SMART +1 650 492 5216 jake.smart@colliers.com
More informationMarcus Moziah Garvey Elementary School S Morgan St Chicago, IL 60643
Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM SOTA-AAS HIGH SCHOOL MODERNIZATION ADDENDUM NO. 2
SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM SOTA-AAS HIGH SCHOOL MODERNIZATION ADDENDUM NO. 2 Owner: San Francisco Unified School District Date: Dec. 10, 2014 135 Van Ness Avenue
More informationDesign Deliverables. Summary. A. Expectations for Design Deliverables:
Design Deliverables Summary A. Expectations for Design Deliverables: The Design Team is obligated to advance and deliver the project with a professional manner and standard of care that meets the expectations
More informationADDENDUM NO. 3, March 14, 2017 A.B.C. No
ADDENDUM NO. 3, March 14, 2017 A.B.C. No. 2017044 RE: UM Harman Hall Mechanical Renovation Montevallo, Alabama 35115 Architect s job no. 2747 FROM: TurnerBatson 1950 Stonegate Drive, Suite 200 Birmingham,
More informationBUILDING PLAN REVIEW REQUIREMENTS
TOWNSHIP OF NORTH FAYETTE BUILDING DEPARTMENT COMMERCIAL PLAN REVIEW REQUIREMENTS BUILDING PLAN REVIEW REQUIREMENTS In order to perform a thorough Building Plan Review, the following specifications, drawings
More informationCHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT
1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department August 11, 2010 Addendum No. 2 INVITATION FOR BID NO.: 11-07 Industrial Technology Center, Buildings 1400/1600
More informationDesign Phase Submission Requirements
Design Guidance May 18, 2000 Table of Contents Page # Goals and Objectives 1 Overview 1 Design Review Presentation Requirements 1 Technical Plan Review Requirements 2 UC Standards 4 Schematic Design 5
More informationNDUS/UND IT Facility Office Building/Data Center
NDUS/UND IT Facility Building/Data Center Building Option 3 $9,133,128 Data Center $4,937,500 Tier 2 to Tier 3 (add on) $1,356,250 Total $15,426,878 Legislative Appropriation $12,500,000 Difference $2,926,878
More informationHuntington Beach City School District. M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y
Huntington Beach City School District M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y 0 1 7 Agenda 1. Where are we in the process?. Measure Q Bond Program
More informationTHREE-YEAR RE-INSPECTION and ASBESTOS MANAGEMENT PLAN for the
SCHOOL DISTRICT OF PHILADELPHIA Asbestos Hazard Emergency Response Act AHERA THREE-YEAR RE-INSPECTION 2015-2016 and ASBESTOS MANAGEMENT PLAN for the Luis Munoz Marin Elementary School ULCS# 5680 Building
More informationMPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA
MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA RESPONSES TO QUESTIONS and/or RFI s Date: 12/7/2017 The attention of Contractors submitting
More informationTO: All Recipients Date: March 20, 2015
CITY OF VALDEZ Project Title: Valdez Museum, Library, Elementary School roof replacements Project No.: 15-310-4250, 15-310-4260, 15-310-9513 Contract No.: 1214 TO: All Recipients Date: March 20, 2015 SUBJECT:
More informationCOUNTY OF NORTHUMBERLAND Addendum No. 3 Request for Quotations To Renovate the Grafton Recreation Centre for a Licensed Child Care Centre
April 12, 2019 COUNTY OF NORTHUMBERLAND Addendum No. 3 Request for Quotations 19-10 - To Renovate the Grafton Recreation Centre for a Licensed Child Care Centre The attached information, questions and
More informationBUILDING PLANS. BUILDING DEPARTMENT
BUILDING PLANS BUILDING DEPARTMENT 952-446-1660 www.cityofminnetrista.com This handout is intended only as a guide and is based in part on the 2015 Minnesota Residential Code, Minnetrista City ordinances,
More informationJohann W von Goethe Elementary School 2236 N Rockwell St Chicago, IL 60647
3 Rockwell St Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationAddition and Renovations to Upper Bucks County Technical School
Additions and Renovations to Upper Bucks County Technical School SECTION 00 91 14 - ADDENDUM NUMBER 2 23 April 2014 RE: From: To: Addition and Renovations to Upper Bucks County Technical School Godshall
More informationADDENDUM ADDENDUM NO.: 01 PROJECT NO.: CONTRACT NO.: DATE OF ISSUE: January 12, 2018
ADDENDUM ADDENDUM NO.: 0 PROJECT NAME: Williams Park Fieldhouse PROJECT NO.: 320 CONTRACT NO.: C593 DATE OF ISSUE: January 2, 208 NOTICE OF CHANGES, MODIFICATIONS, OR CLARIFICATIONS TO CONTRACT DOCUMENTS