1 ADDENDUM NO. TWO To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS Prepared By: ARCHITECT Bhide & Hall Architects, P.A C Kingsley Ave. Orange Park, FL Certificate No. AAC Date: June 28, 2016 Index: Number Discipline Topic 1 Non-Technical RFI #001 Reply 2 Architectural Architectural drawing revisions Attachment A 3 Civil Civil Engineering drawing revisions Attachment B 4 Structural Structural Engineering drawing revisions Attachment C 5 Mechanical Mechanical Engineering drawing revisions Attachment D 6 Fire Protection Fire Protection Engineering drawing revisions Attachment E 7 Electrical Electrical Engineering drawing revisions Attachment F 8 Technology Technology Engineering drawing revisions Attachment G 9 Specifications Specification Section , Firestopping added 10 Specifications Specification Section , City of Palm Coast Standard Pump Station added 11 Specifications Multiple Electrical specification sections modified. 12 Specifications Specification Section revised. 13 Specifications Specification Section revised. 10 ITEMS TOTAL Item No. 1, RFI #001 reply. Responses to RFI #001 submitted by Bidders is attached. Question: What are the sizes of the utility pipes, what is the method of insulation, what is the method of excavation depth? Answer: The sizes of the utility pipes are in question are specified on the Civil Engineering drawings. The means and methods for the installation of these utilities shall be determined by the Contractor. Page 1 of 3

2 Item No. 2, Architectural drawing revisions Attachment A See attached revised architectural drawings and Revision Summary (Attachment A ) for modifications and/or clarifications to select drawings. Item No. 3, Civil Engineering drawing revisions Attachment B See attached revised civil engineering drawings and Revision Summary (Attachment B ) for modifications and/or clarifications to select drawings. Item No. 4, Structural Engineering drawing revisions Attachment C See attached revised structural engineering drawings and Revision Summary (Attachment C ) for modifications and/or clarifications to select drawings. Item No. 5, Mechanical Engineering drawing revisions Attachment D See attached revised mechanical engineering drawings and Revision Summary (Attachment D ) for modifications and/or clarifications to select drawings. Item No. 6, Fire Protection Engineering drawing revisions Attachment E See attached revised fire protection engineering drawings and Revision Summary (Attachment E ) for modifications and/or clarifications to select drawings. Item No. 7, Electrical Engineering drawing revisions Attachment F See attached revised electrical engineering drawings and Revision Summary (Attachment F ) for modifications and/or clarifications to select drawings. Item No. 8, Technology Engineering drawing revisions Attachment G See attached revised electrical engineering drawings and Revision Summary (Attachment G ) for modifications and/or clarifications to select drawings. Item No. 9, Specification Section , Firestopping added. Specification Section , Firestopping has been added to the specifications. The added Section is attached herewith. Item No. 10, Specification Section , City of Palm Coast Standard Pump Station added. Specification Section , City of Palm Coast Standard Pump Station has been added to the specifications to provide additional information regarding the Sanitary Sewer Lift Station included as part of Section , Allowances. The added Section is attached herewith. Item No. 11, Multiple electrical specification sections modified. The following electrical specification sections have been modified to correct and/or deleted erroneous specification section references: Section , Section , Section , Section , Section , Section , Section and Section The revised Sections are attached herewith. Page 2 of 3

3 Item No. 12, Specification Section , General Technology Provisions revised. Specification Section , General Technology Provisions has been revised to accommodate the G6 standards required by FLARNG. The revised Section is attached herewith. Item No. 13, Specification Section , Structured Cabling revised. Specification Section , Structured Cabling has been adjusted to change the cabling standard. END OF ADDENDUM NO. TWO Page 3 of 3

4 ADDENDUM NO. TWO Attachment A Architectural Drawing Revision Summary: G Revised and updated list of drawings for Mechanical, Electrical and Technology (Vol 2) disciplines to match sheets contained within the Volume 2 set of drawings. 1LS1 1. Symbol and notation for Type K fire extinguisher added to Life Safety Legend. 2. Removed northern fire alarm annunciator panel from Room 100, Lobby. A Gate access control keypad has been relocated to north side of roadway. 2. Dumpster enclosure size increased to allow for two dumpsters 3. Loading ramp on east side of property moved to west approximately 10 feet 4. Asphalt apron at loading ramp increased approximately 10 feet to the north foot wide asphalt driveway added at LP tank enclosure A Notation for gate latch and keeper hardware added to elevation of dumpster enclosure on Detail Elevation of dumpster enclosure on Detail 9 updated to match plan 3. Dumpster enclosure shown on Detail 8 enlarged to accommodate two dumpsters. A Detail 4 added to sheet to provide scope of work for gate access control keypad. 2. Proposed location of gate access control keypad has been added to gate plan located on this sheet. 1A Door 126A removed from the project. 2. Fire extinguisher cabinet located at door 136A has been relocated to the adjacent Corridor 5 (Room 134) wall. 3. Door 186B has been renumbered to Door 186A. 1A Exterior door 145B has been renumbered to door 145A. 1A Addition information added to steel columns at Room 137, Gear Lockers. 1A Door 186C has been renumbered to Door 186B. 1A Door 250A added to Room 250, Electrical 3. 1A Detail 2/Sheet 1A3.2 callout added to Elevation 1. 1A Elevation notation on Section 7 changed from SECOND FLOOR to TOP OF VAULT. 1A Pipe bollard and wall finish information added to Section 2. 1A Additional information included at Details 1 and 5 regarding extents of wall and valley flashing/underlayment. 2. Detail 5 in bottom right corner of drawing renumbered to Detail 6. 1A Additional dimensions included at ceiling dome in Room 101, Lobby. 2. Motorized projection screens added to Room A Motorized projection screens added to Rooms 177 and 179. Page 1 of C Kingsley Avenue Orange Park Florida 32073

5 1A Decorative star medallion removed from Detail Additional dimensions included at ceiling Details 1 and 2. 1A Motorized projection screens added to Rooms 203, 226, 227, and 106 (Assembly Hall). 2. Adjusted location of Room 220 room number for clarity. 3. Decorative star medallions removed (16 locations) from ceiling of Room 106, Assembly Hall. 1A Motorized projection screens added to Rooms 235, 238, and A Door 126A eliminated from Door Schedule. 2. Door 168B renamed to Door 168A. 3. Finish of doors and frames for Doors 149A, 153A, and 157A have been changed from P, paint to FF, factory finish to match specifications. 1A Door 250A added to Door Schedule. 1A Added Type V designation to Detail 1 drawing title. 3A Additional dimensions included regarding distance between Unheated Storage Building and Loading Ramp shown on plan. END OF ADDENDUM NO. TWO ATTACHMENT A Page 2 of C Kingsley Avenue Orange Park Florida 32073

6 ADDENDUM NO. TWO Attachment B Civil Engineering Drawing Revision Summary: C Loading ramp on east side of property moved to west approximately 10 feet. 2. Asphalt apron at loading ramp increased approximately 10 feet to the north. 3. Addition dimensions added to loading ramp area foot wide asphalt driveway added at LP tank enclosure. 5. Concrete equipment pad added at southwest corner of Maintenance Building for electrical transformer. C Loading ramp on east side of property moved to west approximately 10 feet. 2. Asphalt apron at loading ramp increased approximately 10 feet to the north. C Additional notation regarding sanitary sewer lift station scope of work added for clarity. 2. Location of water service entering Readiness Center has been moved slightly east to avoid conflict with fire protection water line in the affected area. END OF ADDENDUM NO. TWO ATTACHMENT B Page 1 of 1

7 ADDENDUM NO. TWO Attachment C Structural Engineering Drawing Revision Summary: 1S1.1A 1S1.1B 1S1.1C 1S1.1D 1S1.2A 1S1.2B 1. Add section cut 10/S3.8 near column grid A Add Plan Note 21, Refer to Sheet S3.3 for Contractor Selected options for pipes crossing footings. 3. Delete door 126A into Women Shower room. 1. Add section cut 10/S3.8 near column grid F Add Plan Note 21, Refer to Sheet S3.3 for Contractor Selected options for pipes crossing footings. 1. Add Plan Note 21, Refer to Sheet S3.3 for Contractor Selected options for pipes crossing footings. 1. Add Plan Note 21, Refer to Sheet S3.3 for Contractor Selected options for pipes crossing footings. 1. Add section cut 10/S3.8 near column grid A Add section cut 10/S3.8 near column grid F Add door to Electrical room neat column grid F-3. 2S Add Plan Note 8, Refer to Sheet S3.3 for Contractor Selected options for pipes crossing footings. END OF ADDENDUM NO. TWO ATTACHMENT C Page 1 of 1

8 ADDENDUM NO. TWO Attachment D Mechanical Engineering Drawing Revision Summary: M Revised VTU notes to indicate all 24V control power to the boxes from the transformers are by the controls contractor. M Added clearance dimensions for the chiller yard. M Added notes to clarify where ducts route into the attic space. M Added notes to clarify where ducts route into the attic space. M Relocate fan coil FCU-1S-1 to be located above the door. 2. Added note that all dampers are to be 24V and all 24V control power will be provided by the controls contractor. M Rerouted ductwork through the attic space. Clarified ducts located in the attic. M Rerouted ductwork through the attic space. Clarified ducts located in the attic. M Provided sizes for the VRF piping. M Provided sizes for the VRF piping. M Provided sizes for the VRF piping. M Provided sizes for the VRF piping. M Provided sizes for the VRF piping. M Provided sizes for the VRF piping. M Located AHU-2M above door. M Provided clarification for ductwork routed through the attic. M Provided clarification for ductwork routed through the attic. M Duct/structural coordination. M Boiler Detail added showing housekeeping pad. END OF ADDENDUM NO. TWO ATTACHMENT D Page 1 of 1

9 ADDENDUM NO. TWO Attachment E Fire Protection Engineering Drawing Revision Summary: F Added ansul system scope for second kitchen hood. END OF ADDENDUM NO. TWO ATTACHMENT E Page 1 of 1

10 ADDENDUM NO. TWO Attachment F Electrical Engineering Drawing Revision Summary: E Relocated irrigation pump and the controller. 2. Revised site lighting circuit. E All homerun circuit designations were revised to provide more appropriate breaker layout in panels. E All homerun circuit designations were revised to provide more appropriate breaker layout in panels. E All homerun circuit designations were revised to provide more appropriate breaker layout in panels. E All homerun circuit designations were revised to provide more appropriate breaker layout in panels. E All homerun circuit designations were revised to provide more appropriate breaker layout in panels. E All homerun circuit designations were revised to provide more appropriate breaker layout in panels. E Revised circuits for kitchen equipment. Revised circuit for coffee urn to match cutsheet. E Added note for coordination location water proof disconnect in elevator pit. E Revised and added general lighting notes. E Revised and added general lighting notes. 2. Correct lighting circuiting E Revised and added general lighting notes. 2. Relocated lighting relays E Revised and added general lighting notes. E Revised and added general lighting notes. E Revised and added general lighting notes. E Relocated fire alarm speakers E Relocated fire alarm speakers E Relocated fire alarm speakers E Relocated fire alarm speakers E Relocated fire alarm speakers E Panel changes per plan circuiting revisions. E Panel changes per plan circuiting revisions. E Panel changes per plan circuiting revisions. Page 1 of 2

11 Sheet Revision E Panel changes per plan circuiting revisions. E Panel changes per plan circuiting revisions. E Panel changes per plan circuiting revisions. E Panel changes per plan circuiting revisions. END OF ADDENDUM NO. TWO ATTACHMENT F Page 2 of 2

12 ADDENDUM NO. TWO Attachment G Technology Engineering Drawing Revision Summary: T Vault cable tray segments have been reduced due to a comment from owner. Note added to Technology symbol legend to refer to technology specifications for the guards G6 standard.2. T Vault cable tray segments have been reduced due to a comment from owner. Note added to Technology symbol legend to refer to technology specifications for the guards G6 standard. END OF ADDENDUM NO. TWO ATTACHMENT G Page 1 of 1

SECTION PROJECT COORDINATION VIA BIM

SECTION PROJECT COORDINATION VIA BIM SECTION 01 31 13 PROJECT COORDINATION VIA BIM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

ADDENDUM #1. April 29, 2009

ADDENDUM #1. April 29, 2009 April 29, 2009 Re: HACC, Central Pennsylvania s Community College Midtown 1 CCTA Phase 2 Solicitation # 09-17 From: Eastern pcm, LLC Construction Manager HACC 212 Locust Street, Suite 604 Harrisburg, PA

More information

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic GENERAL SITE PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS Scope of work narrative Building code review Description of construction Documentation on drawings as List of applicable

More information

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS ARCHITECTURE, LLC 1721 4 th AVENUE NORTH, SUITE 101 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 7 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS

More information

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017.

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017. !!! Addendum EXP Project No: MTA Project No: WIND-17-01 Project: Windsor Hall Renovations October 12, 2017 Addendum No: 3 The following information supplements and/or supersedes the bid documents. This

More information

ADDENDUM No. 4 Page 1 of 8 (includes attachment)

ADDENDUM No. 4 Page 1 of 8 (includes attachment) ADDENDUM No. 4 Page 1 of 8 (includes attachment) Date Issued: November 27, 2017 Project: TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J

More information

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA RESPONSES TO QUESTIONS and/or RFI s Date: 12/7/2017 The attention of Contractors submitting

More information

TRIBAL BUILDING AND DEVELOPMENT Plan Check Submittal

TRIBAL BUILDING AND DEVELOPMENT Plan Check Submittal TRIBAL BUILDING AND DEVELOPMENT Plan Check Submittal Complete sets of plans are required. Plans shall be stamped and wet signed by the architect or engineer. (signed and accompanied with letter from Homeowners

More information

Answer: Only to ChurchWoods, LLC.

Answer: Only to ChurchWoods, LLC. ADDENDUM ADDENDUM NO.: 3 DATE: 06/27/16 PROJECT: CHW ChurchWoods PROJECT ADDRESS: 4130 Old Post Road Charlestown, RI TO: All Bidders of Record: This Addendum forms a part of and modifies the bidding requirements

More information

Residential Room Addition / Remodel Submittal Requirement Checklist

Residential Room Addition / Remodel Submittal Requirement Checklist City of Elko Building Department 1753 College Avenue Elko, Nevada 89801 (775) 777-7220 fax (775) 777-7229 Residential Room Addition / Remodel Submittal Requirement Checklist TWO COMPLETE SETS OF PROPERLY

More information

DOCUMENT SUBMITTAL REQUIREMENTS FOR A NEW MULTI-FAMILY DWELLING

DOCUMENT SUBMITTAL REQUIREMENTS FOR A NEW MULTI-FAMILY DWELLING INFORMATION BULLETIN / GENERAL INFORMATION REFERENCE NO.: None DOCUMENT NO. P/GI 2014-007 Previously Issued As: P/GI 2011-007 Effective: 01-01-2014 Revised: DOCUMENT SUBMITTAL REQUIREMENTS FOR A NEW MULTI-FAMILY

More information

INVITATION TO TENDER ITT No. PS FIRE HALL 5 + HOUSING CONSTRUCTION. ADDENDUM No. 2 and AMENDMENT No. 2

INVITATION TO TENDER ITT No. PS FIRE HALL 5 + HOUSING CONSTRUCTION. ADDENDUM No. 2 and AMENDMENT No. 2 FINANCE, RISK AND BUSINESS PLANNING Supply Chain Management May 17, 2016 INVITATION TO TENDER ITT No. PS20160468 FIRE HALL 5 + HOUSING CONSTRUCTION ADDENDUM No. 2 and AMENDMENT No. 2 RE: Various additions

More information

ADDENDUM #2 September 12, 2018

ADDENDUM #2 September 12, 2018 Physical Plant Services Project Management 1000 Rim Drive Phone: (970) 247-7523 Fax: (970) 247-7555 Project No. 2007-130P18 Whalen Gymnasium Expansion and Renovation for Exercise Science Request for Qualifications

More information

TELEPHONE: (215) Addendum No Cooling Plant Replacement SDP Contracts No. B-080C, B-081C and B-082 of 2017/18

TELEPHONE: (215) Addendum No Cooling Plant Replacement SDP Contracts No. B-080C, B-081C and B-082 of 2017/18 THE SCHOOL DISTRICT OF PHILADELPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, 3 rd Floor Suite 371 Philadelphia, PA 19130 TELEPHONE: (215) 400-4730 Addendum No. 001 Subject:

More information

University of Houston Master Construction Specifications Insert Project Name SECTION MECHANICAL SCOPE OF WORK PART 1 - GENERAL

University of Houston Master Construction Specifications Insert Project Name SECTION MECHANICAL SCOPE OF WORK PART 1 - GENERAL SECTION 23 00 10 - MECHANICAL SCOPE OF WORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements", and Section 23 01

More information

MTJ Outdoor Baggage Claim

MTJ Outdoor Baggage Claim MTJ Outdoor Baggage Claim 915 S. Tenth St. Montrose, CO 8101 p: (970) 29-1980 f: (970) 797-6811 www.motleyarc.com Drawings and Dimensions 1. ATTENTION ALL USERS OF THESE DRAWINGS, GENERAL CONTRACTORS,

More information

ADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC.

ADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC. ADDENDUM NO. 2 PROJECT: OWNER: ENGINEER / ARCHITECT: PROJECT LOCATION: Saginaw County Community Mental Health Authority Germania Club Renovation Phase 2 Saginaw County Community Mental Health Authority

More information

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118 PART 1: GENERAL This section of the design standard outlines general requirements for electrical and telecommunications designs to be performed for the University of Texas at Austin. This standard is intended

More information

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

ELECTRICAL GENERAL DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL Electrical/Telecommunications Design

ELECTRICAL GENERAL DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL Electrical/Telecommunications Design PART 1: GENERAL 1.01 Electrical/Telecommunications Design A. This section of the design and construction standard outlines general requirements for electrical and telecommunications designs to be performed

More information

State College of Florida, Manatee-Sarasota

State College of Florida, Manatee-Sarasota State College of Florida, Manatee-Sarasota SCF Venice Chiller Plant Upgrade Project FAC2017-58 Project No. 7-17-2-11 and 3-17-2-12 ADDENDUM NUMBER #1 Date: December 4, 2017 NOTE: THIS ADDENDUM SHOULD BE

More information

2. Electrical rooms shall be centrally located and stacked so that feeder conduits and bus duct are run as straight and short as possible.

2. Electrical rooms shall be centrally located and stacked so that feeder conduits and bus duct are run as straight and short as possible. PART 1: GENERAL 1.01 Electrical/Telecommunications Design A. This section of the design and construction standard outlines general requirements for electrical and telecommunications designs to be performed

More information

December 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions

December 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions December 31, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y16-721-MM / ADDENDUM No. 1 ORANGE COUNTY CONVENTION CENTER PHASE III VALENCIA BALLROOM RENOVATION Bid Opening Date: January 12, 2016

More information

SECTION PROJECT MANAGEMENT AND COORDINATION

SECTION PROJECT MANAGEMENT AND COORDINATION SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

9. Pay for the power consumed until the project has been accepted as substantially complete.

9. Pay for the power consumed until the project has been accepted as substantially complete. 9. Pay for the power consumed until the project has been accepted as substantially complete. A4-2. SECTION 01 23 00 ALTERNATES A. Reference Page 2, Paragraph 1.03.: Modification: Add the following paragraph:

More information

Residential Construction Checklist Single and Two Family Construction

Residential Construction Checklist Single and Two Family Construction DATE: _ Building Inspection Submittal Requirements Residential Construction Checklist Single and Two Family Construction Submit a City of Big Spring Permit Application, checklist, and 3 complete hard copy

More information

Wayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009

Wayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009 ADDENDUM NO 2 OWNER: Wayne State University DATE: January 4 th, 2019 PROJECT: NM Project Number: 18113.0 ARCHITECT: ENGINEER: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009 IMEG 26200 Town

More information

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT 1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department October 25, 2010 Addendum No. 09.R INVITATION FOR BID NO.: 11-05 Modernization of Classroom Building 300 Chabot

More information

SECTION D BIM COORDINATION DRAWINGS - CONTRACTORS

SECTION D BIM COORDINATION DRAWINGS - CONTRACTORS END OF SECTION 01 30 00 SECTION 01 31 21-3D BIM COORDINATION DRAWINGS - CONTRACTORS PART 1 - GENERAL 1.01 RELATED DOCUMENTS Attention is directed to Bidding and Contract Requirements, and to Division 1,

More information

CYPRESS FAIRBANKS MEDICAL CENTER HOSPITAL

CYPRESS FAIRBANKS MEDICAL CENTER HOSPITAL T Architecture Interiors Planning 1165 BRITTMOORE RD. HOUSTON, TEXAS 7704 (T) 71.626.400 (F) 71.626.401 in association with: www.garnerfritsche.com CYPRESS FAIRBANKS MEDICAL CENTER HOSPITAL An HCA Affiliated

More information

BUILDING PLAN REVIEW REQUIREMENTS

BUILDING PLAN REVIEW REQUIREMENTS TOWNSHIP OF NORTH FAYETTE BUILDING DEPARTMENT COMMERCIAL PLAN REVIEW REQUIREMENTS BUILDING PLAN REVIEW REQUIREMENTS In order to perform a thorough Building Plan Review, the following specifications, drawings

More information

HOENER ASSOCIATES INC. ARCHITECTS

HOENER ASSOCIATES INC. ARCHITECTS HOENER ASSOCIATES INC. ARCHITECTS BRUCE D. DELL MARK REUTHER ADDENDUM NO. 1 PROJECT 15-22C RENOVATION AND SITE WORK AT: BUILDING B DDRB OF ST. CHARLES DEVELOPMENT DISABILITIES RESOURCE BOARD ST. CHARLES,

More information

Addendum #1 - Bid Package #

Addendum #1 - Bid Package # Addendum #1 - Bid Package #6929-08 Project Name: Lincoln Public Schools District Office 5901 O Street Lincoln, NE Project No.: 11065 Issued: September 18, 2012 This Addendum is issued by Hampton Construction

More information

Notre Dame High Addition/Renovation Addendum 3 Page 1

Notre Dame High Addition/Renovation Addendum 3 Page 1 School Notre Dame High Addition/Renovation Addendum 3 Page 1 PROJECT: Notre Dame High School Addition/ Renovation Calgary. Alberta DATE November 15, 2012 ADDENDUM NO. 3 Attachment pages Addendum: Page(s)

More information

The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents, Inquiry No. 17-WDI-031.

The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents, Inquiry No. 17-WDI-031. ADDENDUM NO. 2 April 11, 2017 Page 1 The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents,. These Exhibits are re-issued in their entirety, unless

More information

ADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016

ADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016 ADDENDUM NO. 1 DATE: MARCH 1, 2016 PROJECT: ARCHITECT: TO: 2017 BAND ADDITION, ROOF REPLACEMENT AND AIR-CONDITIONING WORK ROCK FALLS HIGH SCHOOL 101 12 TH STREET ROCK FALLS, IL 61071 BCA PROJECT NO. 1620

More information

Hall of Waters List of Historic Drawings

Hall of Waters List of Historic Drawings List of Historic Drawings The following represents the historic drawings of the PROJECT PWA PROJECT NUMBER JOB NUMBER SHEET NUMBER SHEET TITLE DATE NOTES 1935 Drawing Piping Layout at Tank Room for Mineral

More information

Commercial Infill Project Guide

Commercial Infill Project Guide Commercial Infill Project Guide City of Nixa PO Box 395 715 W. Mt. Vernon P (417)725-5850 F(417)724-5750 If you are moving your business into an existing building that is considered an infill and a permit

More information

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: 08012.00 SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA ADDENDUM NUMBER 1 to the BID SET August 10, 2009 General This Addendum will become part

More information

03/7/12 Issuance UTD Section Page 1 of 5 Electrical General

03/7/12 Issuance UTD Section Page 1 of 5 Electrical General SECTION 26 01 00 ELECTRICAL GENERAL PART 1: GENERAL 1.1 Electrical/Telecommunications Design 1.1.1 This section of the design and construction standard outlines general requirements for electrical and

More information

HAMMEL ASSOCIATES ARCHITECTS, LLC 2 5 E A S T G R A N T S T R E E T, S U I T E L A N C A S T E R, P E N N S Y L V A N I A

HAMMEL ASSOCIATES ARCHITECTS, LLC 2 5 E A S T G R A N T S T R E E T, S U I T E L A N C A S T E R, P E N N S Y L V A N I A CHL ASSOCIATES ARCHITECTURE 1 5 7 0 R I V E R R O A D, M A R I E T T A, P E N N S Y L V A N I A 1 7 5 4 7 HAMMEL ASSOCIATES ARCHITECTS, LLC 2 5 E A S T G R A N T S T R E E T, S U I T E 1 0 2 L A N C A

More information

Bid No. B14-02 Building 100 HVAC Improvements

Bid No. B14-02 Building 100 HVAC Improvements Bid No. B14-02 Building 100 HVAC Improvements Addendum No. 1 This Addendum No. 1 sets forth modifications to portions of the bid and contract documents for the above-referenced work described as: Building

More information

HUSSEY GAY BELL SAVANNAH, GEORGIA

HUSSEY GAY BELL SAVANNAH, GEORGIA HUSSEY GAY BELL SAVANNAH, GEORGIA ------------------------------------------------------------------------------------------------------------ ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS

More information

Addendum to Description of Services for Building and Planning, Digital Design. The Association of of Consulting Engineers

Addendum to Description of Services for Building and Planning, Digital Design. The Association of of Consulting Engineers Addendum to Description of Services for Building and Planning, 2012 8.4 Digital Design 2016 The Association of of Consulting Engineers FRI and DANSKE ARK Addendum to Description of Services for Building

More information

State College Area School District

State College Area School District State College Area School District The following is a guideline for project design submittals to the Facility Committee of the State College Area School District. During the design process the committee

More information

ADDENDUM 1. This Addendum forms part of and modifies Proposal Documents dated, October 31, 2018, with amendments and additions noted below.

ADDENDUM 1. This Addendum forms part of and modifies Proposal Documents dated, October 31, 2018, with amendments and additions noted below. DATE: November 16, 2018 PROJECT: JJL Library & Street Level Renovation RFP NO: 744-R1903 OWNER: The University of Texas Health Science Center at Houston TO: Prospective Proposers This Addendum forms part

More information

05BDB ADDENDUM 002. Thomas W. Wathen Business Division Building Renovation GENERAL ITEMS:

05BDB ADDENDUM 002. Thomas W. Wathen Business Division Building Renovation GENERAL ITEMS: ADDENDUM 002 Addendum - 002 to the Drawings and Specifications dated, March, 2019, for Vincennes University, located at the Vincennes Campus in Vincennes, Indiana, as prepared by Andrew Young, Campus Architect,

More information

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT 1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department August 11, 2010 Addendum No. 2 INVITATION FOR BID NO.: 11-07 Industrial Technology Center, Buildings 1400/1600

More information

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202 Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 May 24, 2017 ADDENDUM NUMBER: Three (3) TITLE: Construction Services for Arlington

More information

Request for Information 0026

Request for Information 0026 Request for Information 0026 Detailed, RFIs Grouped by RFI Number SLAC Photon Science Lab (PSLB) Project # 02001.105960 2575 Sand Hill Road Tel: Fax: Menlo Park, CA 94025 RFI #: 0026 Date Created: 4/4/2017

More information

1. Land survey Work. 2. Civil and Structural engineering services.

1. Land survey Work. 2. Civil and Structural engineering services. SECTION 01050 FIELD ENGINEERING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification

More information

PMA ONLINE TRAINING. Commercial Drawings. One Hour Continuing Education

PMA ONLINE TRAINING. Commercial Drawings. One Hour Continuing Education PMA ONLINE TRAINING Commercial Drawings One Hour Continuing Education PMA training disclaimer The information provided in this document is intended for use as a guideline and is not intended as, nor does

More information

MSU Barnard Hall 105 Cleanroom Installation PPA # Page 1

MSU Barnard Hall 105 Cleanroom Installation PPA # Page 1 ADDENDUM NUMBER 1 DATE: February 10, 2017 PROJECT: MSU Barnard Hall Room 105 Cleanroom Installation PPA# 16-0002 (Consulting Design Solutions, Inc. Project # 1613) BID DATE: February 23, 2017 2:00 PM,

More information

To the Drawings and/or Specifications for. Board of Education of Harford County Lancaster, PA 17603

To the Drawings and/or Specifications for. Board of Education of Harford County Lancaster, PA 17603 ENDUM NO. 2 To the Drawings and/or Specifications for Gilbert Architects Youth s Benefit Elementary School - #0729 626 N. Charlotte St. Board of Education of Harford County Lancaster, PA 17603 June 2,

More information

DOCUMENT LIST OF DRAWINGS, TABLES AND SCHEDULES

DOCUMENT LIST OF DRAWINGS, TABLES AND SCHEDULES DOCUMENT 00 0115 LIST OF DRAWINGS, TABLES AND SCHEDULES DRAWINGS GENERAL A0.0 COVER SHEET ADDENDUM #2 revised A0.01 TITLE SHEET ADDENDUM #2 revised CIVIL C1.0 TOPO C2.0 DEMOLITION C3.0 TEMPORARY STREET

More information

INDEX OF SHEETS FLAMING GORGE RANGER DISTRICT OFFICE ADDITION REGION 4 INTERMOUNTAIN REGION ASHLEY NATIONAL FOREST DRAWING SHEET INDEX

INDEX OF SHEETS FLAMING GORGE RANGER DISTRICT OFFICE ADDITION REGION 4 INTERMOUNTAIN REGION ASHLEY NATIONAL FOREST DRAWING SHEET INDEX INDEX OF SHEETS SHT. DWG. SHEET TITLE GENERAL 1 G1 COVER SHEET, VICINITY MAP, PROJECT DESCRIPTION 43 A402 INTERIOR ELEVATIONS WOMENS 44 A403 INTERIOR ELEVATIONS MENS 45 A404 INTERIOR ELEVATIONS BUILDING-PLUMBING

More information

Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review

Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review Step 1: Request for Conditional Approval, page 1 of 5 Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review I,, the Property Owner, or Owner

More information

ADDENDUM NO. 1 November 10, 2016

ADDENDUM NO. 1 November 10, 2016 COUER D ALENE CITY HALL PROJECT NO. 2016-009 REMODEL AND ADDITION COEUR D ALENE, IDAHO ADDENDUM NO. 1 November 10, 2016 This addendum is hereby incorporated into and is an integral part of the bidding

More information

DOCUMENT SUBMITTAL REQUIREMENTS FOR AN ALTERATION OR ADDITION TO AN EXISTING SINGLE-FAMILY DWELLING OR MULTI-FAMILY DWELLING

DOCUMENT SUBMITTAL REQUIREMENTS FOR AN ALTERATION OR ADDITION TO AN EXISTING SINGLE-FAMILY DWELLING OR MULTI-FAMILY DWELLING INFORMATION BULLETIN / PUBLIC - GENERAL INFORMATION REFERENCE NO.: Effective: 10-01-99 DOCUMENT NO. P/GI 2002-008 Revised: 11-01-02 Previously Issued As: IB ST-4 DOCUMENT SUBMITTAL REQUIREMENTS FOR AN

More information

Marshall Truck Station Laboratory Addition Project No. TZ MnDOT

Marshall Truck Station Laboratory Addition Project No. TZ MnDOT Marshall Truck Station Laboratory Addition Project No. TZ-91523 MnDOT 13-6574 ADDENDUM NUMBER 2 DATED September 19, 2013 Marshall Truck Station Laboratory Addition Project No. TZ-91523 MnDOT 13-6574 Architect:

More information

Permits (Submitted to Permit Counter) APPLICATION CHECKLIST

Permits (Submitted to Permit Counter) APPLICATION CHECKLIST Permits (Submitted to Permit Counter) APPLICATION CHECKLIST SUBMITTAL REQUIREMENTS: 1. Completed signed and notarized Development Services Department Permit Application, submit to Permit Counter. 2. Copy

More information

1.01 NOTICE TO BIDDERS

1.01 NOTICE TO BIDDERS ADDENDUM NO. 1 1.01 NOTICE TO BIDDERS A. Date: 15 March 2013 B. From: Bahr Vermeer and Haecker Architects, Ltd. C. To: Prospective Bidders. D. Project: Lexington Public Schools Lexington Middle School

More information

July 3, CASCO Project Managers St. Louis, Missouri PETSMART STORES. 13K Q Prototype Narrative (Delta 5) Bulletin No.

July 3, CASCO Project Managers St. Louis, Missouri PETSMART STORES. 13K Q Prototype Narrative (Delta 5) Bulletin No. July 3, 2013 CASCO Project Managers St. Louis, Missouri PETSMART STORES 13K Q2 2013 Prototype Narrative (Delta 5) Bulletin No. Five CHANGES TO THE DRAWINGS: 1. Sheet A0.0, Revision No. 5: Revised project

More information

ADDENDUM NO. 02 July 31, 2012

ADDENDUM NO. 02 July 31, 2012 Post Point Wastewater Treatment Plant Improvements Owner: Engineer: GC/CM: City of Bellingham Carollo Engineers Mortenson Construction ADDENDUM NO. 02 July 31, 2012 THIS ADDENDUM MUST BE ACKNOWLEDGED ON

More information

This specification describes the minimum technical requirements for drawings, as applicable to all disciplines.

This specification describes the minimum technical requirements for drawings, as applicable to all disciplines. SPEC-0800 1/5 1.0 PURPOSE This specification describes the minimum technical requirements for drawings, as applicable to all disciplines. 2.0 VALE DRAWING TYPE DEFINITIONS Engineering Drawings Engineering

More information

CHAPTER 5 ARCHITECTURE

CHAPTER 5 ARCHITECTURE CHAPTER 5 ARCHITECTURE 5.1 GENERAL... 4 5.2 CONCEPT/PROJECT DEFINITION DESIGN (30%) SUBMITTAL REQUIREMENTS... 4 5.2.1 DESIGN ANALYSIS... 4 5.2.1.1 Design Criteria... 4 5.2.1.2 Narratives... 4 5.2.1.2.1

More information

A/E REVIEW CHECKLIST HVAC

A/E REVIEW CHECKLIST HVAC A/E CHECKLIST HVAC Reviewers should - Use Checklists when reviewing any type of VA construction project for the following disciplines: Site and Landscape, Architectural, Structural, Plumbing, Fire Protection,

More information

OCPS Submittal Register for Product Data and Shop Drawing Reviews

OCPS Submittal Register for Product Data and Shop Drawing Reviews OCPS mittal Register for Product Data and Shop Drawing s Project ification Drawings - D Shop Drawings - Product Data - Test - TR Test Data - TD Calculations - Calc Certification - Cert 02 22 27 Pre-demolition

More information

Quality Control Checklist - Design Drawings

Quality Control Checklist - Design Drawings Quality Control Checklist - Design Drawings Date Company Name Address Telephone Fax Email Job Number 1) Drawing Set a) Drawing one is site/location/incoming power i) Should contain location map if not

More information

Community & Economic Development Department Planning Division Frederick Street PO Box 8805 Moreno Valley, CA SUBMITAL REQUIREMENTS

Community & Economic Development Department Planning Division Frederick Street PO Box 8805 Moreno Valley, CA SUBMITAL REQUIREMENTS Community & Economic Development Department Planning Division 14177 Frederick Street PO Box 8805 Moreno Valley, CA 92552-0805 (951) 413-3206 Fax (951) 413-3210 SECOND UNITS Completed and Signed Project

More information

U of I Facilities Standards Updates for 2017

U of I Facilities Standards Updates for 2017 U of I Facilities Standards Updates for 2017 Updates to the U of I Facilities Standards will occur on a periodic basis (typically all standards will be reviewed for accuracy & completeness every 3 years),

More information

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO PAGE PROJECT NO. 0-0 0 0 0 0 0 DATE: PROJECT: GATEWAY STEM ATHLETICE FIELD ALTERATIONS GATEWAY STEM HIGH SCHOOL - ST. LOUIS PUBLIC SCHOOLS 0 MCRTEE AVENUE ST. LOUIS, MISSOURI 0 TO BID DOCUMENTS DATED DECEMBER,

More information

February 18, Re: Zephyr Lakes Amenity Center Zephyrhills, Florida

February 18, Re: Zephyr Lakes Amenity Center Zephyrhills, Florida February 18, 2019 Re: Zephyr Lakes Amenity Center Zephyrhills, Florida These are the responses to the RFIs received by 2:00 PM on Monday, February 11, 2019. All items that are not answered in the following

More information

BUILDING STANDARDS BUILDING AND DEVELOPMENT PERMIT APPLICATION DRAWING REQUIREMENTS

BUILDING STANDARDS BUILDING AND DEVELOPMENT PERMIT APPLICATION DRAWING REQUIREMENTS Building and Development Permit Applications Definitions: Type A Residential Projects: All projects related to one and two unit dwellings Type B Residential Projects: All projects related to Apartments,

More information

TO WHOM IT MAY CONCERN:

TO WHOM IT MAY CONCERN: TO WHOM IT MAY CONCERN: A lot of questions are asked throughout the year as to when a building permit is required. This list may help identify some of the instances when a permit would be required: Permit

More information

HANSCOM FIELD ARFF AND CBP BUILDING

HANSCOM FIELD ARFF AND CBP BUILDING HANSCOM FIELD ARFF AND CBP BUILDING AERIAL VIEW OF AIRFIELD PROJECT SITE HANSCOM AIR FIELD CIVIL AIR TERMINAL HANSCOM AIR FORCE BASE 95 AIRFIELD MAIN ENTRY SITE AERIAL PLAN VIEW OF AIRFIELD N MASSACHUSETTS

More information

Customer Connection Guide Updates Effective May 2017

Customer Connection Guide Updates Effective May 2017 This document provides a list of the updates to the EPCOR Distribution and Transmission Inc. (EDTI) Customer Connection Guide. If you have any questions, please contact EDTI Customer Engineering Services

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending

More information

James W. Moore, PE / Brandon D. Enevold, PE / Kjersten E. Kuhta, PE Dylan J. Cunningham, PE / Jacob L. Deering, PE / Joel R.

James W. Moore, PE / Brandon D. Enevold, PE / Kjersten E. Kuhta, PE Dylan J. Cunningham, PE / Jacob L. Deering, PE / Joel R. ADDENDUM NO. 1 October 21, 2016 PROJECT: CWU CAMPUS GENERATOR PROJECT #: CWU Project No. 12238-02 The additions, clarifications and corrections contained herein shall be made to the Project Manual, Drawings

More information

Bestall Collaborative Limited Planning Environment Construction Management Development

Bestall Collaborative Limited Planning Environment Construction Management Development November 18, 2017 Bestall Collaborative Limited Lori Hight, AICP, Senior Planner City Development Department City of Thornton City Hall 9500 Civic Center Drive Thornton, Colorado 80229-4326 RE: River Valley

More information

SPARTAN DAY CAMP 4814 FREEDOM RING RD

SPARTAN DAY CAMP 4814 FREEDOM RING RD 484 FREEDOM RING RD PROJECT DATA GENERAL PROJECT NOTES: LOCATION:. DIMENSIONS ARE TO FACE OF STUD OR TO COLUMN CENTERLINE UNLESS NOTED OTHERWISE. VERIFY ALL EXISTING CONDITIONS AND ADJUST WALL DIMENSIONS

More information

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017.

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017. June 15, 2017 GS#108-281 Greene Hall Renovations University of Southern Mississippi Hattiesburg, Mississippi 00.910 ADDENDUM NO 1. This Addendum contains 6 pages and 21 pages of attachments for a total

More information

Stantec Architecture Inc South Flores Street Suite 201 San Antonio TX Tel: (210) Fax: (210)

Stantec Architecture Inc South Flores Street Suite 201 San Antonio TX Tel: (210) Fax: (210) Stantec Architecture Inc. 1344 South Flores Street Suite 201 San Antonio TX 78204-1672 Tel: (210) 223-9588 Fax: (210) 223-9589 ADDENDUM #1 07/11/2014 TO PLANS AND SPECIFICATIONS FOR RENOVATION AND ADDITION

More information

PROJECT: ARCHITECT S SUPPLEMENTAL INSTRUCTION NO.: 002 Marquis Newberg 3914 Hayes Street Newberg, Oregon OWNER ARCHITECT X CONSULTANT

PROJECT: ARCHITECT S SUPPLEMENTAL INSTRUCTION NO.: 002 Marquis Newberg 3914 Hayes Street Newberg, Oregon OWNER ARCHITECT X CONSULTANT ARCHITECT S SUPPLEMENTAL INSTRUCTIONS PROJECT: ARCHITECT S SUPPLEMENTAL INSTRUCTION NO.: 002 Marquis Newberg 3914 Hayes Street Newberg, Oregon 97132 OWNER ARCHITECT X CONSULTANT OWNER: DATE OF ISSUANCE:

More information

KidsAbility Guelph Hub Renovation ADDENDUM #2 Project No.:

KidsAbility Guelph Hub Renovation ADDENDUM #2 Project No.: KidsAbility Guelph Hub Renovation ADDENDUM #2 This Addendum amends and forms part of the Bidding and Contract Documents for the above Project as follows: CLARIFICATIONS Q1. Is it possible to set up a secondary

More information

November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT

November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y18-703-CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT REVISED BID OPENING DATE: DECEMBER 5, 2017 This addendum is hereby incorporated

More information

Industrial Pipe Marking

Industrial Pipe Marking Industrial Pipe Marking Pipe and Valve Identification Specialists SPECIFICATIONS ASME (ANSI) Standard A13.1-2007 The ASME (ANSI) Standard for pipe identification is a widely used guideline in determining

More information

April 7, City of Verona Adam Sayre, AICP Director of Planning & Development 111 Lincoln St. Verona, WI 53593

April 7, City of Verona Adam Sayre, AICP Director of Planning & Development 111 Lincoln St. Verona, WI 53593 April 7, 2016 City of Verona Adam Sayre, AICP Director of Planning & Development 111 Lincoln St. Verona, WI 393 RE: Conditional Use Arby s Restaurant Multi-Tenant Development 631 Hometown Circle-Lot 6

More information

NEW SEVICE CENTER BOB HART CHEVROLET. 495 S. 7th St. E:\RE Smith New Logo.jpg VINITA, OK RE SMITH BOB HART CHEVROLET NEW SERVICE CENTER

NEW SEVICE CENTER BOB HART CHEVROLET. 495 S. 7th St. E:\RE Smith New Logo.jpg VINITA, OK RE SMITH BOB HART CHEVROLET NEW SERVICE CENTER NEW SEVICE CENTER VINITA, OK 70 9 S. 7th St. VINITA, OK 70 06 W. 2nd St., Joplin, MO 680 Phone: 7-62- Fax: 7-782-678 GENERAL G0.0 COVER CIVIL C.0 SITE DEMO C. SITE PLAN C.2 GRADING PLAN (FORTHCOMING) ARCHITECTURAL

More information

This Revision No. 01 becomes as fully a part of the first issued documents as if originally issued therewith or originally contained therein.

This Revision No. 01 becomes as fully a part of the first issued documents as if originally issued therewith or originally contained therein. Revision No. 01 Issued February 19, 2016 Page 1 This Revision No. 01 becomes as fully a part of the first issued documents as if originally issued therewith or originally contained therein. This Revision

More information

Travis County ESD #1. Building Plan Submittals. Information Bulletin. Fire Marshal Hancock

Travis County ESD #1. Building Plan Submittals. Information Bulletin. Fire Marshal Hancock Travis County ESD #1 Information Bulletin Building Plan Submittals Fire Marshal Hancock Effective Date 12/12/2018 Table of Contents INTRODUCTION 3 SECTION I. SUPPORTING DOCUMENTATION 4 SECTION II. GENERAL

More information

Spec Section: , Complete Elec, Comm, and Fire Alarm , Complete Elec, Comm, and Fire Alarm Data Sheets RAN/GCAN

Spec Section: , Complete Elec, Comm, and Fire Alarm , Complete Elec, Comm, and Fire Alarm Data Sheets RAN/GCAN SUBMITTAL REVIEW Submittal: No. 019.00 Spec Section: 26 0000, 28 0000 Complete Elec, Comm, and Fire Alarm Reviewed By: Laura Landon, Comma-Q Architecture Date: June 29, 2012 Project: BPS Belgrade Elementary

More information

This is being reviewed, additional comment to follow Marmoleum tile has been removed and replaced with a biobased VCT.

This is being reviewed, additional comment to follow Marmoleum tile has been removed and replaced with a biobased VCT. Dr. Checks Comment Responses Review: 100% Building Package B Review Project: (G168476) Ft. Gillem, Enclave Force Protection Latest Update: 03-03-2010 8:30 am 1. 3079320 We will coordinate and add to the

More information

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA RESPONSES TO QUESTIONS and/or RFI s Date: 11/29/2017 The attention of Contractors submitting

More information

12560 W. Cedar Drive Lakewood, CO Barry Himmelman President

12560 W. Cedar Drive Lakewood, CO Barry Himmelman President Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 16-BS-2260 ADDENDUM NUMBER FOUR January 8, 2016 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM

More information

Design Deliverables. Summary. A. Expectations for Design Deliverables:

Design Deliverables. Summary. A. Expectations for Design Deliverables: Design Deliverables Summary A. Expectations for Design Deliverables: The Design Team is obligated to advance and deliver the project with a professional manner and standard of care that meets the expectations

More information

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014 FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services ADDENDUM #4 December 5, 2014 This Addendum is issued to provide answers to questions from potential bidders

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 230553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Provisions of the Contract and of the Contract Documents apply to this Section. 1.2 SUBMITTALS A.

More information

SECTION EMERGENCY RESPONDER RADIO COVERAGE SYSTEMS

SECTION EMERGENCY RESPONDER RADIO COVERAGE SYSTEMS 510.1 Emergency responder radio coverage in new buildings. Approved radio coverage for emergency responders shall be provided within all buildings meeting any one of the following conditions: 1. There

More information

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION 01 3100 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information