REVISIONS TO SPECIFICATION SECTIONS: Section Allowances: 12. Replace paragraphs 1.05, A and B with the following:

Size: px
Start display at page:

Download "REVISIONS TO SPECIFICATION SECTIONS: Section Allowances: 12. Replace paragraphs 1.05, A and B with the following:"

Transcription

1

2 b. Lithonia Lighting LP6FN 42TRT 6O9A 120 ECOS TRW 9. Luminaire Schedule L-18D: a. Lithonia Lighting LP6FN 42TRT 6O9A MVOLT ECOS TRW b. Lithonia Lighting LP6FN 42TRT 6O9A 120 ADEZ TRW 10. Luminaire Schedule L-19: a. Lithonia Lighting LP6FN 42TRT 6W9A MVOLT TRW b. Lithonia Lighting LP6FN 42TRT FW9A MVOLT TRW 11. Luminaire Schedule L-22: a. Healthcare Lighting HUC LED40-S1-AM b. Elite LED EUL x WH REVISIONS TO SPECIFICATION SECTIONS: Section Allowances: 12. Replace paragraphs 1.05, A and B with the following: A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include taxes, freight, and delivery to Project site. B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials selected by Architect under allowance shall be included as part of the Contract Sum and not part of the allowance. 13. Replace paragraph 3.03, A, 1 with the following: 1. Include the sum of $11,000 for one Digital Switch, 24-port, model 3750 by Cisco. All necessary hardware and software must be procured from The New Mexico Department of Information Technology (DoIT). Installation, network integration, and configuration loading and testing of infrastructure equipment shall be performed by a DoIT approved contractor. NMSA, we are including the DoIT requirements in the allowance section of the specifications as that is the location describing the scope and pricing requirements for the digital switch. Do you want the requirements REVISIONS TO DRAWING SHEETS: Sheet A-201: 14. Replace Elevation A4 - Break Hall 127B East with Elevation A4 shown on SKA-201.A 15. Replace Elevation A8 - Break Hall 127B West with Elevation A8 shown on SKA-201.A

3 Sheet A-502: 16. Replace Detail E5 Casework Section - Sink with Detail E5 shown on SKA-502.A 17. Replace Detail E7 Casework Section with Detail E7 shown on SKA-502.A Sheet ET-101: 18. Add to General Notes: 3. ALL NECESSARY HARDWARE AND SOFTWARE FOR DIGITAL SWITCH MUST BE PROCURED FROM THE NEW MEXICO DEPARTMENT OF INFORMATION TECHNOLOGY (DOIT). INSTALLATION, NETWORK INTEGRATION, CONFIGURATION LOADING AND TESTING OF INFRASTRUCTURE EQUIPMENT SHALL BE PERFORMED BY A DOIT APPROVED CONTRACTOR. Sheet E Replace Luminaire Schedule L-16 fixture with the following fixture: a. Columbia #TRA24-332G-CLO-EPU CLARIFICATIONS: The following are responses to questions that have been submitted in writing. 1. Question: The spec book states Liquidated Damages to be both $1, and $1, Please Clarify. Clarification: The liquidated damages are to be $1, per consecutive calendar day as issued in Addendum 1, Item Question: Is section to be used for the crusher fines or will you provide a different gradation spec for that material? Clarification: The intent is to utilize the same material as that used elsewhere on the site for walkways. The material used was a Franklin Red ¾ landscape aggregate mix. Alternatives may be utilized subject to approval by OWNER. Also, the material is to be compacted to 90% of maximum density. 3. Question: For the 6 Islands will that be a single layer of material and can this material be taken from a 4-6 Rip Rap material? Clarifications: A single layer of 4-6 material is acceptable 4. Question: There is no specification for the Type of HMAC desired. Will a standard NMDOT Type B with PG64-22 oil be acceptable? Clarification: NMDOT Type B (PG64-22) is acceptable. Placement will be in accordance with NMDOT Standard Specifications. 5. Question: What Controls are currently installed and being used at the facility? Please provide the company name and contact info. Clarification: Any new controls are to tie into the existing Daiken control panel in the facility. The Contractor is to coordinate with the Owner s representatives and vendors to integrate the controls into the facility.

4 6. Clarification: Attached is the Pre-Proposal Conference Agenda & Sign-In END OF ADDENDUM

5 C E5 A-502 SIM E7 A-502 OPEN TO BEYOND A2 PL B2 SS-01 OPEN TO BEYOND N A1 PL /2" A A A A 24" 43" ± 3/4" A4 BREAK HALL - 127B EAST 1/4" = 1'-0" CLEAR E7 E5 SKA-502.A SKA-502.A 7/8" 33" 33" ± 7/8" B OPEN TO BEYOND A2 PL B2 SS /2" N A1 PL-03 A8 1 ± 7/8" 33" 34" A CLEAR BREAK HALL - 127B WEST 1/4" = 1'-0" SPACEPORT OPERATIONS CENTER (SOC) FIT OUT ELEVATIONS - BREAK HALL 127B Project number Date /15/13 AM SKA-201.A 115 Amherst Drive SE, Albuquerque, New Mexico Drawn by T F CONSTRUCTION Checked by PF & DH Scale 1/4" = 1'-0"

6 24 3/4" ± 3/8" 1 3/8" E A A A A A B A B B 28 1/4" 4" 1 1/4" 30" 24 3/4" 1/2" E A A A A B A E 4" SKA-502.A 20 1/2" Scale 33 1/2" 27 1/4" 1" 1 1/4" 2" 33 1/2" 20 1/2" 30" 1" = 1'-0" A A A A B B E N A A A B A REFERENCE KEYNOTES BASE CABINET, PLASTIC LAMINATE UPPER CABINET, PLASTIC LAMINATE KNIFE EDGE PULL ROUTED INTO BOTTOM OF CABINET DOOR PANEL WITH APRON FOR LIGHT FIXTURE, 1/4" SHORTER THAN CABINET PANEL; COORDINATE WITH ELECTRICAL. APRON, PLASTIC LAMINATE, ALIGN WITH FACE OF BASE CABINET BODY COUNTER TOP, SOLID SURFACING COUNTERTOP ANGLE LEDGER, ALUMINUM ADJUSTABLE SHELF, PLASTIC LAMINATE REVEAL, 1", WITH KNIFE EDGE PULL ROUTED INTO TOP OF CABINET DOOR PANEL. BACK OF REVEAL TO BE FINISHED TO MATCH CABINET PANEL. SEALANT RESILIENT BASE SINK INSULATE SUPPLY AND WASTE LINES LIGHT FIXTURE, SEE ELECTRICAL DRAWINGS CASEWORK SECTIONS Project number 03/14/13 Date SPACEPORT OPERATIONS CENTER (SOC) FIT OUT CONSTRUCTION Author 09 TOP OF SINK TO BE 34" MAX AFF SHEET KEYNOTES Drawn by Checker Checked by A E5 CASEWORK SECTION - SINK 1" = 1'-0" E7 CASEWORK SECTION 1" = 1'-0" 3" 115 Amherst Drive SE, Albuquerque, New Mexico T F

7

8

9

10

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017.

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017. !!! Addendum EXP Project No: MTA Project No: WIND-17-01 Project: Windsor Hall Renovations October 12, 2017 Addendum No: 3 The following information supplements and/or supersedes the bid documents. This

More information

Addendum #1 - Bid Package #

Addendum #1 - Bid Package # Addendum #1 - Bid Package #6929-08 Project Name: Lincoln Public Schools District Office 5901 O Street Lincoln, NE Project No.: 11065 Issued: September 18, 2012 This Addendum is issued by Hampton Construction

More information

SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5. February 25, 2013

SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5. February 25, 2013 SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5 February 25, 2013 Owner: Architect: Administrative Office of the Courts 2860 Gateway Oaks Drive, Suite 400 Sacramento,

More information

Specifications: Other: sign in sheet

Specifications: Other: sign in sheet To: All Vendors Bidding on The College of New Jersey Nursing Simulation Lab Fit-Out Project From: Roselle Horodeski Finance & Business Services Date: July 29, 2015 ADDENDUM NO. 1 ISSUE DATE: July 29, 2015

More information

December 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions

December 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions December 31, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y16-721-MM / ADDENDUM No. 1 ORANGE COUNTY CONVENTION CENTER PHASE III VALENCIA BALLROOM RENOVATION Bid Opening Date: January 12, 2016

More information

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017.

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017. June 15, 2017 GS#108-281 Greene Hall Renovations University of Southern Mississippi Hattiesburg, Mississippi 00.910 ADDENDUM NO 1. This Addendum contains 6 pages and 21 pages of attachments for a total

More information

Answer: Only to ChurchWoods, LLC.

Answer: Only to ChurchWoods, LLC. ADDENDUM ADDENDUM NO.: 3 DATE: 06/27/16 PROJECT: CHW ChurchWoods PROJECT ADDRESS: 4130 Old Post Road Charlestown, RI TO: All Bidders of Record: This Addendum forms a part of and modifies the bidding requirements

More information

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014 FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services ADDENDUM #4 December 5, 2014 This Addendum is issued to provide answers to questions from potential bidders

More information

Music Area Casework General 1.01 Summary Related Sections Definitions Qualifications and Quality Assurance

Music Area Casework General 1.01 Summary Related Sections Definitions Qualifications and Quality Assurance 1.00 General 1.01 Summary Music Area Casework A. This section includes the following Scope of Work as referred to in the plans: 1. Thermally Fused Laminate manufactured casework, for use in music areas,

More information

ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION

ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION July 6, 2011 City of Miami Fire Station #13 ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION This Addendum is issued to modify the previously issued Bidding and Contractual Documents,

More information

ARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI)

ARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI) ARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI) PROJECT: Villa Joseph Marie High School - Auditorium Addition ARCHITECTS PROJECT NO: 2339 ASI NO: 001 DATE OF ISSUANCE: 12/5/2017 TO: Twining Construction Co.

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-12 36 00.00 20 (August 2011) --------------------------------- Preparing Activity: NAVFAC Superseding UFGS-12 36 00.00 20 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

Architect s Supplemental Instructions (attachment to AIA Form G710)

Architect s Supplemental Instructions (attachment to AIA Form G710) Architect s Supplemental Instructions (attachment to AIA Form G70) ASI No: 0 Date: January 7, 06 Project: PR-07 Great Work Montessori School Owner: Great Work Inc. Architect: Cuningham Group Copy To: File

More information

TELEPHONE: (215) Addendum No Cooling Plant Replacement SDP Contracts No. B-080C, B-081C and B-082 of 2017/18

TELEPHONE: (215) Addendum No Cooling Plant Replacement SDP Contracts No. B-080C, B-081C and B-082 of 2017/18 THE SCHOOL DISTRICT OF PHILADELPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, 3 rd Floor Suite 371 Philadelphia, PA 19130 TELEPHONE: (215) 400-4730 Addendum No. 001 Subject:

More information

ADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016

ADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016 ADDENDUM NO. 1 DATE: MARCH 1, 2016 PROJECT: ARCHITECT: TO: 2017 BAND ADDITION, ROOF REPLACEMENT AND AIR-CONDITIONING WORK ROCK FALLS HIGH SCHOOL 101 12 TH STREET ROCK FALLS, IL 61071 BCA PROJECT NO. 1620

More information

ID0.1 PALO VERDE 8000 WEST US HIGHWAY 290 AUSTIN, TX SHEET INDEX: CONTACT INFORMATION: DISCLOSURES: DOCUMENT GENERAL NOTES:

ID0.1 PALO VERDE 8000 WEST US HIGHWAY 290 AUSTIN, TX SHEET INDEX: CONTACT INFORMATION: DISCLOSURES: DOCUMENT GENERAL NOTES: CONTACT INFORMATION: SHEET INDEX: DISCLOSURES: DOCUMENT GENERAL NOTES: CLIENT ARDENT RESIDENTIAL 5453 BURNET RD. SUITE 203 AUSTIN, TX 78756 ARCHITECT DAVIES COLLABORATIVE 5453 BURNET RD. SUITE 202 AUSTIN,

More information

Merrick Pet Care New Distribution Center Hereford, Texas

Merrick Pet Care New Distribution Center Hereford, Texas Merrick Pet Care New Distribution Center Hereford, Texas DATE: March 16, 2015 ARCHITECTURAL/ELECTRICAL ADDENDUM #6 FROM: TO: PROJECT: Lavin Associates, Architects Plan Holders of Record Merrick Pet Care,

More information

Wayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009

Wayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009 ADDENDUM NO 2 OWNER: Wayne State University DATE: January 4 th, 2019 PROJECT: NM Project Number: 18113.0 ARCHITECT: ENGINEER: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009 IMEG 26200 Town

More information

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form. McKee and Associates Architecture and Interior Design Addendum No. THREE Date: 12.11.17 Project: A NEW BUILDING FOR THE GREATER LIMESTONE COUNTY CHAMBER OF COMMERCE ATHENS, ALABAMA A3.1 GENERAL PROJECT

More information

This is being reviewed, additional comment to follow Marmoleum tile has been removed and replaced with a biobased VCT.

This is being reviewed, additional comment to follow Marmoleum tile has been removed and replaced with a biobased VCT. Dr. Checks Comment Responses Review: 100% Building Package B Review Project: (G168476) Ft. Gillem, Enclave Force Protection Latest Update: 03-03-2010 8:30 am 1. 3079320 We will coordinate and add to the

More information

ADDENDUM NOTICE INTERIOR RENOVATIONS AT THE BATHURST CLARK RESOURCE LIBRARY, 900 CLARK AVENUE WEST, VAUGHAN, ON

ADDENDUM NOTICE INTERIOR RENOVATIONS AT THE BATHURST CLARK RESOURCE LIBRARY, 900 CLARK AVENUE WEST, VAUGHAN, ON The City of Vaughan Procurement Services Department 2141 Major Mackenzie Drive Vaughan, ON L6A 1T1 Tel (905) 832-8555 ADDENDUM NOTICE ADDENDUM NO. 3 Total of (5) page BID NO. T18-003 DESCRIPTION: INTERIOR

More information

DESIGN INSTRUCTIONS TO ARCHITECTS AND ENGINEERS [ ] SCHEMATICS [ ] DESIGN [ ] CONSTRUCTION

DESIGN INSTRUCTIONS TO ARCHITECTS AND ENGINEERS [ ] SCHEMATICS [ ] DESIGN [ ] CONSTRUCTION DEPARTMENT OF VETERANS AFFAIRS DESIGN INSTRUCTIONS TO ARCHITECTS AND ENGINEERS LOCATION : VAMC, PROJECT TITLE : PROJECT NO. : [ ] SCHEMATICS [ ] DESIGN [ ] CONSTRUCTION DEVELOPMENT DOCUMENTS EQUIPMENT

More information

1.01 NOTICE TO BIDDERS

1.01 NOTICE TO BIDDERS ADDENDUM NO. 1 1.01 NOTICE TO BIDDERS A. Date: 15 March 2013 B. From: Bahr Vermeer and Haecker Architects, Ltd. C. To: Prospective Bidders. D. Project: Lexington Public Schools Lexington Middle School

More information

PROJECT LOCATION BOZEMAN HIGH SCHOOL. ELECTRICAL ENGINEER: Van Dykken Engineering 37 Spanish Peak Drive Bozeman, MT Phone:

PROJECT LOCATION BOZEMAN HIGH SCHOOL. ELECTRICAL ENGINEER: Van Dykken Engineering 37 Spanish Peak Drive Bozeman, MT Phone: DRAWING INDEX GENERAL C. PROJECT COVER G-WING A/V IMPROVEMENTS.0 AREA PLAN ST FLOOR SOUTH. TYP. PROJECTOR MOUNTING & PROJECTOR NOTES.2 G-WING TECHNOLOGY CABINET ELEVATIONS.3 G-WING WIRING DIAGRAM.4 G-WING

More information

Lincoln County Tax Appraisal Office Project No. RFB

Lincoln County Tax Appraisal Office Project No. RFB Red Bike Architecture, PLLC James M. Ratliff, Architect, NCARB P.O. Box 574, Rutherford College, NC 28671-0574 Phone: 828-413-2276 Email: ratliffarch@outlook.com Addendum #1 July 3, 2018 Project: Interior

More information

12560 W. Cedar Drive Lakewood, CO Barry Himmelman President

12560 W. Cedar Drive Lakewood, CO Barry Himmelman President Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 16-BS-2260 ADDENDUM NUMBER FOUR January 8, 2016 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM

More information

Attached is Addendum No. 2 to SEPTA Sealed Bid APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House.

Attached is Addendum No. 2 to SEPTA Sealed Bid APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House. Dear Sir/Madam: Attached is Addendum No. 2 to SEPTA Sealed Bid 17-00222-APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House. The Bid due date and time is changed from Thursday, Nov.

More information

Notre Dame High Addition/Renovation Addendum 3 Page 1

Notre Dame High Addition/Renovation Addendum 3 Page 1 School Notre Dame High Addition/Renovation Addendum 3 Page 1 PROJECT: Notre Dame High School Addition/ Renovation Calgary. Alberta DATE November 15, 2012 ADDENDUM NO. 3 Attachment pages Addendum: Page(s)

More information

SECTION PRE-MANUFACTURED CABINETS

SECTION PRE-MANUFACTURED CABINETS SECTION 12390 PRE-MANUFACTURED PART 1 GENERAL 1.1 DESCRIPTION OF WORK A. The work includes furnishing all labor, materials and equipment required to complete the Pre-Manufactured Cabinet work as shown

More information

Chapter 22 - Cabinets & Vanities

Chapter 22 - Cabinets & Vanities Chapter 22 - Cabinets & Vanities Contents Chapter 22 - Cabinets & Vanities... 22-1 Timing & Prerequisites... 22-2 Cabinets... 22-3 Cabinet Layout... 22-3 Wall Cabinets... 22-4 Assemble the Wall Units...

More information

ADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS

ADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS ADDENDUM NO. TWO To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS Prepared By: ARCHITECT Bhide & Hall Architects, P.A. 1329-C Kingsley

More information

ADDENDUM NO. 3. Ellis County Elections Building

ADDENDUM NO. 3. Ellis County Elections Building AUSTIN ARCHITEXAS DALLAS ARCHITECTURE, PLANNING AND HISTORIC PRESERVATION, INC. ADDENDUM NO. December 8, 2014 to the BIDDING DOCUMENTS for Ellis County Elections Building Waxahachie, Texas By ARCHITEXAS

More information

ADDENDUM_04. > narrative objective Addendum 04 Revision Changes Defined. > narrative content. end of memo. 5Gstudio_collaborative.

ADDENDUM_04. > narrative objective Addendum 04 Revision Changes Defined. > narrative content. end of memo. 5Gstudio_collaborative. ADDENDUM_04 1 page(s) I 1 project number CIN001 project name Cinemark XD12 Altoona, IA issue date December 16, 2013 venue > distribution Jeff Duffy EDC jduffy@edcweb.com Justin Couch VCC USA jcouch@vccusa.com

More information

CaseworkUSA. specifications. 1.1 General 1.2 Summary. 1.3 Related Sections. 1.4 Definitions. 1.5 Qualifications and Quality Assurance

CaseworkUSA. specifications. 1.1 General 1.2 Summary. 1.3 Related Sections. 1.4 Definitions. 1.5 Qualifications and Quality Assurance 1.1 General 1.2 Summary A. This section includes the following Scope of Work as referred to in the plans: 1. Plastic laminate manufactured casework 2. Plastic laminate countertops 1.3 Related Sections

More information

The CAD Technician s Role in Office Practice and Procedure

The CAD Technician s Role in Office Practice and Procedure COMMERCIAL DRAFTING AND DETAILING 4TH EDITION JEFFERIS SOLUTIONS MANUAL Full download at: https://testbankreal.com/download/commercial-drafting-detailing-4th-editionjefferis-solutions-manual/ Chapter 2

More information

ADDENDUM #1. April 29, 2009

ADDENDUM #1. April 29, 2009 April 29, 2009 Re: HACC, Central Pennsylvania s Community College Midtown 1 CCTA Phase 2 Solicitation # 09-17 From: Eastern pcm, LLC Construction Manager HACC 212 Locust Street, Suite 604 Harrisburg, PA

More information

RENOVATION OF THE FARMERS MARKET Reference Number:

RENOVATION OF THE FARMERS MARKET Reference Number: RENOVATION OF THE FARMERS MARKET Reference Number: 13-098 A D D E N D U M NO. 1 The following shall form part of the tender documents issued by the City of Guelph s Purchasing Department, June, 2013. NOTE:

More information

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS For EQUIPMENT FOR THE 2014 CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT WASTEWATER TREATMENT PLANT IMPROVEMENT PROJECT:

More information

Addendum No. 4 page 1

Addendum No. 4 page 1 Addendum No. 4 page 1 Project: Proj. No: 1541.01 Athletic Support Building and Site Improvements Woehrle Athletic Complex Jeffersonville, Indiana Date: December 11, 2015 This addendum is a part of the

More information

SCI-FAB Product Specifications. Casework Section 1. Part 1 General

SCI-FAB Product Specifications. Casework Section 1. Part 1 General SCI-FAB Product Specifications Casework Section 1 Part 1 General 1.1 SCOPE OF WORK Includes all factory fabricated stainless steel casework as required by the project drawings. 1.2 TYPICAL INCLUSIONS A.

More information

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty HOT AISLE CONTAINMENT SYSTEM (HACS) REVISION #1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. B. C. Drawings and general provisions of the Contract, including General and Supplementary. Conditions apply to

More information

ADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC.

ADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC. ADDENDUM NO. 2 PROJECT: OWNER: ENGINEER / ARCHITECT: PROJECT LOCATION: Saginaw County Community Mental Health Authority Germania Club Renovation Phase 2 Saginaw County Community Mental Health Authority

More information

Chapter 25. Lighting Plans

Chapter 25. Lighting Plans Chapter 25 Lighting Plans The following are changes, additions or deletions to the January 2014, Topic #625-000-008, Plans Preparation Manual (PPM), for use on Turnpike projects only. 25.1 General Replace

More information

ADDENDUM No. 4 Page 1 of 8 (includes attachment)

ADDENDUM No. 4 Page 1 of 8 (includes attachment) ADDENDUM No. 4 Page 1 of 8 (includes attachment) Date Issued: November 27, 2017 Project: TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J

More information

SECTION FINISH CARPENTRY. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION FINISH CARPENTRY. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 062000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

SECTION CUSTOM CASEWORK

SECTION CUSTOM CASEWORK PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 06 41 00 CUSTOM CASEWORK A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections,

More information

ADDENDUM NO. 1 November 10, 2016

ADDENDUM NO. 1 November 10, 2016 COUER D ALENE CITY HALL PROJECT NO. 2016-009 REMODEL AND ADDITION COEUR D ALENE, IDAHO ADDENDUM NO. 1 November 10, 2016 This addendum is hereby incorporated into and is an integral part of the bidding

More information

The following information supplements and/or supersedes the bid documents issued on July 10, 2017.

The following information supplements and/or supersedes the bid documents issued on July 10, 2017. Addendum No. 02 ADDENDUM Pages 2 Project No. 1706 Date: July 21, 2017 Project: West End Lofts 44 MacDonald Street, Arnprior, ON The following information supplements and/or supersedes the bid documents

More information

Can you please issue the most recent Soils Report as prepared by Strata? Updated Soils Report to be posted to Christenson Corporation web site

Can you please issue the most recent Soils Report as prepared by Strata? Updated Soils Report to be posted to Christenson Corporation web site CCH ioneer anor Skilled Nursing Facility Questions June, 0 A-Wyoming Can you please issue the most recent Soils Report as prepared by Strata? Updated Soils Report to be posted to Christenson Corporation

More information

Montclair, NJ ADDENDUM NO. 1 Issue Date: May 15, 2017

Montclair, NJ ADDENDUM NO. 1 Issue Date: May 15, 2017 Montclair, NJ 0704 ADDENDUM NO. Issue Date: May 5, 207 Request for Proposal # 294 Building 47 West Renovation- Phase 6a Number of Pages: 2 plus 5 sketches Date of Original Bidding Documents: April 26,

More information

James W. Moore, PE / Brandon D. Enevold, PE / Kjersten E. Kuhta, PE Dylan J. Cunningham, PE / Jacob L. Deering, PE / Joel R.

James W. Moore, PE / Brandon D. Enevold, PE / Kjersten E. Kuhta, PE Dylan J. Cunningham, PE / Jacob L. Deering, PE / Joel R. ADDENDUM NO. 1 October 21, 2016 PROJECT: CWU CAMPUS GENERATOR PROJECT #: CWU Project No. 12238-02 The additions, clarifications and corrections contained herein shall be made to the Project Manual, Drawings

More information

Product Guide Specification

Product Guide Specification Shield Casework February 2014 3421 Merriam Lane Overland Park, Kansas 66203 Phone 913-744-2183 Fax 913-384-3477 Website www.shieldcasework.com E-mail info@shieldcasework.com Product Guide Specification

More information

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents, Inquiry No. 17-WDI-031.

The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents, Inquiry No. 17-WDI-031. ADDENDUM NO. 2 April 11, 2017 Page 1 The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents,. These Exhibits are re-issued in their entirety, unless

More information

SSI CASEWORK CATALOG E. Second Avenue P.O. Box 76071, Tampa, Florida WOOD FAX:

SSI CASEWORK CATALOG E. Second Avenue P.O. Box 76071, Tampa, Florida WOOD FAX: SSI CASEWORK CATALOG 1307 E. Second Avenue P.O. Box 76071, Tampa, Florida 1-800-922-WOOD 813-247-4429 FAX: 813-248-5046 www.s-scraftsmen.com SSI CASEWORK CATALOG 1307 E. Second Avenue P.O. Box 76071, Tampa,

More information

C. Installation shall be by experienced carpenters. Coordinate with plumbing and electrical contractors.

C. Installation shall be by experienced carpenters. Coordinate with plumbing and electrical contractors. 12300 - MANUFACTURED CASEWORK PART 1 - GENERAL 1.01 STIPULATIONS A. The specifications sections General Conditions, Special Requirements, and General Requirements form a part of this section by this reference

More information

Solid Surface Countertops

Solid Surface Countertops USE THIS SECTION FOR COUNTERTOPS. USE SECTION 06 61 16 FOR OTHER SOLID SURFACING APPLICATIONS INCLUDING WALL CLADDING AND MISCELLANEOUS FABRICATIONS. GENERAL NOTES TO SPECIFIER: THIS SPECIFICATION SECTION

More information

Addendum Number: 1 WT White HS Additions and Renovations, Dallas ISD

Addendum Number: 1 WT White HS Additions and Renovations, Dallas ISD Addendum #1 July 9, 2018 Addendum Number: 1 Project: WT White HS Additions and Renovations, Dallas ISD Bid Package: BP#215 Project Number: 1719 - ORG 021 The following items modify the plans and specifications

More information

ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.

ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO. ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO. PS 061 SEVEN SPRINGS WASTEWATER TREATMENT FACILITY IMPROVEMENTS PASCO COUNTY,

More information

KidsAbility Guelph Hub Renovation ADDENDUM #2 Project No.:

KidsAbility Guelph Hub Renovation ADDENDUM #2 Project No.: KidsAbility Guelph Hub Renovation ADDENDUM #2 This Addendum amends and forms part of the Bidding and Contract Documents for the above Project as follows: CLARIFICATIONS Q1. Is it possible to set up a secondary

More information

TELEPHONE: (215) Addendum No. 01

TELEPHONE: (215) Addendum No. 01 THE SCHOOL DISTRICT OF PHILADELPHIA BOARD OF EDUCATION Office of Capital Programs 0 North Broad Street, Third Floor - Suite Philadelphia, PA 0-0 TELEPHONE: () 00-0 Addendum No. 0 Subject: Location: Potter

More information

MTJ Outdoor Baggage Claim

MTJ Outdoor Baggage Claim MTJ Outdoor Baggage Claim 915 S. Tenth St. Montrose, CO 8101 p: (970) 29-1980 f: (970) 797-6811 www.motleyarc.com Drawings and Dimensions 1. ATTENTION ALL USERS OF THESE DRAWINGS, GENERAL CONTRACTORS,

More information

ADDENDUM #2 September 12, 2018

ADDENDUM #2 September 12, 2018 Physical Plant Services Project Management 1000 Rim Drive Phone: (970) 247-7523 Fax: (970) 247-7555 Project No. 2007-130P18 Whalen Gymnasium Expansion and Renovation for Exercise Science Request for Qualifications

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM SOTA-AAS HIGH SCHOOL MODERNIZATION ADDENDUM NO. 2

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM SOTA-AAS HIGH SCHOOL MODERNIZATION ADDENDUM NO. 2 SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM SOTA-AAS HIGH SCHOOL MODERNIZATION ADDENDUM NO. 2 Owner: San Francisco Unified School District Date: Dec. 10, 2014 135 Van Ness Avenue

More information

B. Shop Drawings: For residential casework. Include plans. elevations, details, and attachments to other work.

B. Shop Drawings: For residential casework. Include plans. elevations, details, and attachments to other work. HVAC 1Sunporch 1Fire Alarm Renovation SECTION 123530 RESIDENTIAL CASEWORK PART 1 - GENERAL 1.1 SUMMARY A. Section includes laundry room cabinets. 1.2 ACTION SUBMITTALS A. Product Data: For each type of

More information

HIA AIR CARGO HAMILTON ADDENDUM #3. Addendum No. A03 (Architectural) o Text 1 page o SK-10a o SK-10b o SK-11

HIA AIR CARGO HAMILTON ADDENDUM #3. Addendum No. A03 (Architectural) o Text 1 page o SK-10a o SK-10b o SK-11 HIA AIR CARGO HAMILTON ADDENDUM # (This Addendum consists of six () pages) Cover sheet Schedule time lines for Architectural Precast, Miscellaneous Metals, Insulated Metal Panels, Roofing and Aluminum

More information

Public Art Opportunity Request for Qualifications & Letter of Interest for Outdoor Latino Heritage Mural

Public Art Opportunity Request for Qualifications & Letter of Interest for Outdoor Latino Heritage Mural Public Art Opportunity Request for Qualifications & Letter of Interest for Outdoor Latino Heritage Mural The Port of Kennewick is seeking an artist or team of artists to create mural artwork to be installed

More information

TG Glazing Design-Build

TG Glazing Design-Build TG08.1 - Glazing Design-Build Question No. 0040 0041 0042 0043 Submission Date Question 7.14.2011 Is it acceptable to use 304 stainless in lieu of 316 where the material will be painted per 09 97 15? 7.14.2011

More information

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT 1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department August 11, 2010 Addendum No. 2 INVITATION FOR BID NO.: 11-07 Industrial Technology Center, Buildings 1400/1600

More information

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: 08012.00 SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA ADDENDUM NUMBER 1 to the BID SET August 10, 2009 General This Addendum will become part

More information

ADDENDUM NO. 2. The Bid Opening has not changed it remains December 8, 2016 AT 1:30 P.M.

ADDENDUM NO. 2. The Bid Opening has not changed it remains December 8, 2016 AT 1:30 P.M. ADDENDUM NO. TO: PLANS AND SPECIFICATIONS FOR STATE OF MISSOURI Health Center Renovation Missouri School for the Blind NO. E60-0 The Bid Opening has not changed it remains December 8, 06 AT :30 P.M. GENERAL

More information

CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO

CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO. 18-04 ADDENDUM NO. ONE DATE: September 07, 27 CLIENT / PROJECT: Chabot-Las Positas CCD Campus Master

More information

WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) CITY OF CARTERSVILLE

WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) CITY OF CARTERSVILLE WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) ADDENDUM NO.1 ADDENDUM NO. 1 DATE: OCTOBER 16, 2018 To BID, CONTRACT, BONDS AND SPECIFICATIONS FOR CONSTRUCTING WATER TREATMENT PLANT FILTERS REHABILITATION

More information

Effective this date, this addendum forms part of the contract documents and modifies the original RFP.

Effective this date, this addendum forms part of the contract documents and modifies the original RFP. ADDENDUM # 02 Date: April 6, 2017 Reference: Network Electronics RFP Number: 117-24-4-19 The following questions were submitted for clarification and/or to request additional information. All questions

More information

10930 W. Sam Houston Parkway N., Suite 900

10930 W. Sam Houston Parkway N., Suite 900 ADDENDUM NO. 1 10930 W Sam Houston Pkwy. North Suite 900 Houston, Texas 77064 281.664.1900 281.664.1912 (f) www.salasobrien.com March 21, 2018 Project: Prepared by: Taylor Career Center Welding Labs Beaumont

More information

SECTION COMMUNICATIONS COPPER OSP CABLING

SECTION COMMUNICATIONS COPPER OSP CABLING SECTION 27 13 14 COMMUNICATIONS COPPER OSP CABLING PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such construction,

More information

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202 Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 May 24, 2017 ADDENDUM NUMBER: Three (3) TITLE: Construction Services for Arlington

More information

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO PAGE PROJECT NO. 0-0 0 0 0 0 0 DATE: PROJECT: GATEWAY STEM ATHLETICE FIELD ALTERATIONS GATEWAY STEM HIGH SCHOOL - ST. LOUIS PUBLIC SCHOOLS 0 MCRTEE AVENUE ST. LOUIS, MISSOURI 0 TO BID DOCUMENTS DATED DECEMBER,

More information

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN Approval Amendment Record Approval Date Version Description 01/04/2014 1 Initial Issue under MTM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 7 Table of Contents

More information

DESIGN REVIEW BOARD APPLICATION EXTERIOR PLAN / LANDSCAPE PLAN

DESIGN REVIEW BOARD APPLICATION EXTERIOR PLAN / LANDSCAPE PLAN 209 S. Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org DESIGN REVIEW BOARD APPLICATION EXTERIOR PLAN / LANDSCAPE PLAN *** IMPORTANT INFORMATION Please

More information

SECTION PROJECT MANAGEMENT AND COORDINATION

SECTION PROJECT MANAGEMENT AND COORDINATION SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

STEVE ENNIS ARCHITECT 1108 EAST JACKSON STREET MEDFORD, OREGON 97504

STEVE ENNIS ARCHITECT 1108 EAST JACKSON STREET MEDFORD, OREGON 97504 ATTACH TO STRUC- TURE ABOVE 1/8"Ø BOLT W/ LOCKING NUT #12 WIRE TIE IN PLANE EACH TEE ANGLED 45 FROM HORIZ ATTACH 2" FROM INTERSECTION COMPRESSION POST LOCATE WITHIN 2" OF TEE INTERSECTION SIZE STRUTS FOR

More information

ROWAN COUNTY AIRPORT APRIL 2017 TERMINAL EXPANSION

ROWAN COUNTY AIRPORT APRIL 2017 TERMINAL EXPANSION SECTION 12300 - MANUFACTURED CASEWORK PART 1 - GENERAL RELATED DOCUMENTS: Drawings, General Conditions and Supplementary General Conditions and other Division-1 Specification Sections, apply to this Section.

More information

MPA Project No. M545-C2 Project Title: New Berth 10 Project - Phase II Location: Conley Terminal, South Boston, Massachusetts

MPA Project No. M545-C2 Project Title: New Berth 10 Project - Phase II Location: Conley Terminal, South Boston, Massachusetts MPA Project No. M545-C2 Project Title: New Berth 10 Project - Phase II Location: Conley Terminal, South Boston, Massachusetts RESPONSES TO QUESTIONS and/or RFI s # 3 Date: 09/14/18 The attention of Contractors

More information

Coordinate installation of rough carpentry members specified in other sections.

Coordinate installation of rough carpentry members specified in other sections. 1 1.03 Preservative treated wood materials. Concealed wood blocking, nailers, and C. Miscellaneous wood nailers, furring, and grounds. PART2 2.01 See Section 01 30 00 =Administrative Requirements, for

More information

Single-Family Dwelling Submittal Requirements

Single-Family Dwelling Submittal Requirements Single-Family Dwelling Submittal Requirements The purpose of this guideline is to assist our customers in preparing for plan submittal. The items listed must be included before your plans can be accepted

More information

Company. Signed: Date:

Company. Signed: Date: ADDENDUM No. 1 For: Please acknowledge receipt of this Addendum No. 1 Sign and return by fax to 856-424-1688: Company Signed: BURLINGTON TOWNSHIP BOARD OF EDUCATION RENOVATIONS TO B, C & H WING GANG TOILET

More information

RFP # CULVER CITYBUS: BUS SIGNAL PRIORITY SYSTEMS PROJECT Response to Questions

RFP # CULVER CITYBUS: BUS SIGNAL PRIORITY SYSTEMS PROJECT Response to Questions RFP #1587 - CULVER CITYBUS: BUS SIGNAL PRIORITY SYSTEMS PROJECT Response to Questions 1. Question: Spec requires connects to bitrans, are you going to modify the specs? Answer: City of Culver City s ATCS

More information

RENOVATION TO STUDENT SERVICES/HOUSING FROM HOSPITAL DAKOTA STATE UNIVERSITY MADISON, SOUTH DAKOTA

RENOVATION TO STUDENT SERVICES/HOUSING FROM HOSPITAL DAKOTA STATE UNIVERSITY MADISON, SOUTH DAKOTA RENOVATION TO STUDENT SERVICES/HOUSING FROM HOSPITAL DAKOTA STATE UNIVERSITY MADISON, SOUTH DAKOTA KOCH HAZARD ARCHITECTS ADDENDUM DATE:. SCOPE OF THIS ADDENDUM: The following becomes a part of the original

More information

SECTION ARCHITECTURAL WOOD CASEWORK

SECTION ARCHITECTURAL WOOD CASEWORK PART 1 GENERAL 1.01 SECTION INCLUDES A. Specially fabricated cabinet units. B. Countertops. C. Cabinet hardware. D. Factory finishing. E. Preparation for installing utilities. 1.02 SUBMITTALS SECTION 06

More information

PMA ONLINE TRAINING. Commercial Drawings. One Hour Continuing Education

PMA ONLINE TRAINING. Commercial Drawings. One Hour Continuing Education PMA ONLINE TRAINING Commercial Drawings One Hour Continuing Education PMA training disclaimer The information provided in this document is intended for use as a guideline and is not intended as, nor does

More information

*********************************************************************************************************

********************************************************************************************************* 10400 IDENTIFYING DEVICES ********************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 10 14 00 *********************************************************************************************************

More information

Custom Millwork Fabrications

Custom Millwork Fabrications Custom Millwork Fabrications Laminate Casework Lab Casework Excellence To experience quality craftsmanship and service excellence, choose Northwest Cabinets, Inc. for all of your custom casework manufacturing.

More information

DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS

DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS PART 1 GENERAL 1.01 Scope of Work A. Provide material, accessories, tools, equipment and labor as required for the complete fabrication

More information

PROJECT: ARCHITECT S SUPPLEMENTAL INSTRUCTION NO.: 002 Marquis Newberg 3914 Hayes Street Newberg, Oregon OWNER ARCHITECT X CONSULTANT

PROJECT: ARCHITECT S SUPPLEMENTAL INSTRUCTION NO.: 002 Marquis Newberg 3914 Hayes Street Newberg, Oregon OWNER ARCHITECT X CONSULTANT ARCHITECT S SUPPLEMENTAL INSTRUCTIONS PROJECT: ARCHITECT S SUPPLEMENTAL INSTRUCTION NO.: 002 Marquis Newberg 3914 Hayes Street Newberg, Oregon 97132 OWNER ARCHITECT X CONSULTANT OWNER: DATE OF ISSUANCE:

More information

ARCHITECTURAL REVIEW COMMITTEE TOWN APARTMENT CONSTRUCTION SUBMITTAL FORM AND APPLICATION

ARCHITECTURAL REVIEW COMMITTEE TOWN APARTMENT CONSTRUCTION SUBMITTAL FORM AND APPLICATION For Office Use Only Date Received: Approved: ARC Non-Refundable Fees ARC Refundable Deposit Pd: For Office Use Only Plat Name: Lot # Street Address: New Construction Alteration Preliminary Final ARCHITECTURAL

More information

Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review

Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review Step 1: Request for Conditional Approval, page 1 of 5 Owner / Architect Certification of Complete Documentation for the Additions and Remodels Conditional Approval Review I,, the Property Owner, or Owner

More information

NORTHWEST FLORIDA STATE COLLEGE MONUMENT SIGNS WITH LED DISPLAYS

NORTHWEST FLORIDA STATE COLLEGE MONUMENT SIGNS WITH LED DISPLAYS PREPARED FOR: FOUNDATION PLAN & STRUCTURAL NOTES DESIGNED BY: NJB DRAWN BY: NJB REVIEWED BY: BLSE S1 PREPARED FOR: FRAMING PLANS DESIGNED BY: NJB DRAWN BY: NJB REVIEWED BY: BLSE S2 PREPARED FOR: SECTION

More information

INVITATION TO TENDER ITT No. PS FIRE HALL 5 + HOUSING CONSTRUCTION. ADDENDUM No. 2 and AMENDMENT No. 2

INVITATION TO TENDER ITT No. PS FIRE HALL 5 + HOUSING CONSTRUCTION. ADDENDUM No. 2 and AMENDMENT No. 2 FINANCE, RISK AND BUSINESS PLANNING Supply Chain Management May 17, 2016 INVITATION TO TENDER ITT No. PS20160468 FIRE HALL 5 + HOUSING CONSTRUCTION ADDENDUM No. 2 and AMENDMENT No. 2 RE: Various additions

More information

READING ARCHITECTURAL PLANS

READING ARCHITECTURAL PLANS READING ARCHITECTURAL PLANS ARCHITECTURAL DRAWINGS FOR A HOUSE Architectural drawings contain information about the size, shape, and location of all parts of the house ARCHITECTURAL DRAWINGS FOR A HOUSE

More information