1 Montclair, NJ ADDENDUM NO. 2 Issue Date: June 18, 2010 Request for Proposal # 898 Finley Hall Renovation Number of Pages: 14 (plus attachment) Date of Original Bidding Documents: April 28, 2010 INTENT: This Addendum forms a part of the Contract Documents and modifies the Original Bidding Documents and Prior Addenda, if any, as identified above. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject Bidder to disqualification. I. Points of Information: The following questions were submitted by potential bidders: 1. Question: After reviewing Addendum #1, I see that it contained Sketch SKA-014 which shows a motorized shade at the head of the second floor windows by Draper see specs. First, there are no specs on the motorized shades. This is probably because Dwgs. A904 and A905 indicate an Item K which are motorized shades by others. As such, unless informed otherwise by addendum or clarification, we assume that all shades, including those in the addendum sketch, are by the owner and the shade information indicated in the addendum is for informational purposes only. Response: Motorized shades will be provided, installed, and wired by others. G.C. is to provide power wiring, junction boxes for power, and switch boxes and conduit with pull string as shown on electrical drawings. 2. Question: Drawing E-101, column lines 5-L-M shows an occupancy sensor without a subscript A, B, C, and D. Please confirm and advise if this type D occupancy sensor? Response: Type D 3. Question: Drawing E-101, to the left of column line 4-A shows 3 fixtures without a fixture type. Please confirm and advise the correct fixture types for these fixtures? Response: The 3 shall be fixture type S Finley Hall Renovation Page 1 of 14

2 4. Question: Drawing E-102 shows many occupancy sensors without a subscript A, B, C, or D. Please confirm and advise if all of these occupancy sensors without subscripts to be counted as type D? Response: Type D 5. Question: Drawing E-102, Janitor s Closet #232 shows a fixture without a fixture type associated with it. Please confirm and advise if this is fixture type F? Response: It shall be Fixture Type F 6. Question: Drawing E-103, Conference Room #318 shows a fixture without a fixture type associated with it. Please confirm and advise if this is fixture type Q? Response: It shall be Fixture Type Q 7. Question: Fixture schedule on drawing E-403 lists fixture type C but we did not find any fixtures of this type on the Electrical Lighting floor plans. Please confirm and advise where is this fixture type C shown on the E-series drawings? Response: This Fixture has been removed from use on this project at this time. 8. Question: Fixture schedule on drawing E-403 lists fixture type D but we did not find any fixtures of this type on the Electrical Lighting floor plans. Please confirm and advise where is this fixture type C shown on the E-series drawings? Response: This Fixture has been removed from use on this project at this time. 9. Question: Fixture schedule on drawing E-403 lists fixture type G but we did not find any fixtures of this type on the Electrical Lighting floor plans. Please confirm and advise where is this fixture type C shown on the E-series drawings? Response: This Fixture has been removed from use on this project at this time 10. Question: Panel schedule for Relay Panel LC1 is shown on two drawings, E-101 & E-402. Please confirm and advise which panel schedule is to be used? Response: Use the one on E-402, the one on E-101 will be removed 11. Question: Drawing E-201B shows a symbol RS in a square but this symbol is not defined on the symbol list on drawing E-001. Please confirm and advise what does this symbol represent in terms of Electrical Contractor s scope of work? Response: RS = an electronic sign display. See additional information in Section VIII below. 12. Question: Drawing E-201B shows a symbol C in a circle but this symbol is not defined on the symbol list on drawing E-001. Please confirm and advise what does this symbol represent in terms of Electrical Contractor s scope of work? Finley Hall Renovation Page 2 of 14

3 Response: C = camera 13. Question: Drawing E-201B shows a symbol MM in a square but this symbol is not defined on the symbol list on drawing E-001. Please confirm and advise if this symbol represents a monitor module as part of the Fire Alarm system? Response: MM = Monitor Module for Fire alarm system 14. Question: Drawing E-202B shows a symbol D in a square but this symbol is not defined on the symbol list on drawing E-001. Please confirm and advise what does this symbol represent in terms of Electrical Contractor s scope of work? Response: D = door hold open for fire egress 15. Question: Drawing E-202B indicates that key note #17 is Not Used however it is being referenced on this drawing along column lines G-2. Please confirm and advise what this key note #17 entails. Response: This Key note is deleted. 16. Question: Drawing E-203B does not define any key notes but key notes such as #23 are being referenced on this drawing. Please provide all the key notes that are missing from this drawing. Response: Key notes from E-203A are applicable to E-203B 17. Question: Please confirm and advise if the Emergency fixtures require Emergency Ballasts? Currently, it is unclear because a reference to the Emergency Ballasts is made in notes that are provided as part of the Fixture Schedule on drawing E-403 but the symbol list on drawing E-001 indicates that emergency ballasts are not required if the emergency fixtures are fed from a panel backed-up by a Generator which is the case for this project. Response: All emergency lighting fed from EM panel will not require Ballasts 18. Question: Please provide manufacturer and catalogue information for the Battery operated Emergency Lighting. Response: See Lighting Schedule 19. Question: Specifications section calls for a Lightning Protection System. Please provide drawing for this system. Response: Lighting Protection System shall be provided based on the spec section 20. Question: Drawing PD-01 1 st floor key note #1 states all existing piping to be removed and replaces in kind. Drawing P-101 key note #6 states connect to new mains in corridor. Finley Hall Renovation Page 3 of 14

4 Nowhere on any of the plumbing drawings does it reference and/or show any pipe sizes for the existing mains to be replaced in kind. Please advise. Response: It is the contractors responsibility to field verify the existing pipe sizes and locations and replace in kind. 21. Question: Specifications clearly want the contractors to recycle material created by our work. Has the owner tested the masonry material (i.e. brick; blocks; concrete etc.) in accordance with the DEP requirements for recycling of masonry material? Response: No testing as been performed. General Contractor is responsible for compliance with all applicable regulatory requirements per Specification Section 01690, paragraph 1.5.A. 22. Question: Asbestos abatement and hazardous materials removal is by others. a. When will the owner s contractor clean-up its material (i.e. desks, chairs, and tables on the second floor, personal air conditioners, drums, scrap wood etc. outside the buildings) Response: G.C. shall remove and dispose of all items, furniture, materials, etc. in the building and within the fenced in staging area. b. Please provide asbestos abatement report. Response: An Abatement report will be provided to the contractor after award. c. Timing of abatement contractor s removals we need the materials removed prior to our start of work. The curtain walls are on both sides of the 72-0 wide building and our personnel cannot work within 25-0 of the abatement removals unless others put up containment. The containment and abatement work will inhibit our work and removal operations. Response: Abatement operations need to be coordinated with the successful G.C. and are not expected to be concluded before the award of a contract. MSU will coordinate schedule with the G.C. upon award. d. Will the abatement contractor put up the OSHA cable on the second and third floors for fall protection as it removes the curtain walls? Response: No. General Contractor shall be responsible for installing all required OSHA protection. e. The abatement contractor has left glue pucks on the underside of the 1 st and 2 nd floor slabs. The glue pucks usually contain asbestos. Have the glue pucks been tested and who is responsible for the removals? Response: Glue does not contain asbestos. Glue pucks may remain in areas where they will be covered by new ceilings. Any removal necessary shall be done by G.C. f. There is a hidden spline ceiling the third floor stairwell. Does the ceiling hide more asbestos containing materials and who is responsible for its removal was the abatement contractor originally responsible for the ceiling removal? Response: The spline ceiling does not contain asbestos and removal is to be performed by G.C. Finley Hall Renovation Page 4 of 14

5 g. Somebody has stored trash and demolished material in the third floor space. Who is responsible for the removal? Response: G.C. shall remove and dispose of all items, materials, etc. in the building. 23. Question: On the second floor there is a large area of buckled plywood flooring with a layer of flooring beneath it. The large flooring area is not noted on the demolition drawings for removal. Is the area being removed under the abatement contract or the demolition contract? Response: Flooring does not contain asbestos. Contractor to remove plywood and flooring beneath. 24. Question: Note 4 on drawings A003 notes the removal of the raised slab from the former greenhouse area. The raised slab continues into the existing third floor area what is the limit of the removal? Response: Per Drawing A003, Third Floor Demolition Plan, raised floor area of the entire 3 rd floor area (hatched area) is to be removed per keynote # Question: Who will provide air monitoring (i.e. LEL; etc)? Response: Owner s consultants and contractors will perform all air monitoring required for abatement work. 26. Question: Note 12 calls for the removal of the two (2) precast stairwells including risers, handrails, railings, intermediate landings and structural supports. Is there a detail showing the construction of the area where the reinforced the concrete supports are being disconnected from the remaining reinforced concrete platforms? Response: See Structural Drawing S103, details 5 and 6 for additional information. 27. Question: Drawings E201B and E202B show a key note #14 for cutting and patching of the floor. This key note #14 is not referenced anywhere on these two aforementioned drawings. Please confirm and advise if this key not #14 shall be deleted. Response: Key note #14 shall be E.C. shall provide whips for desk as shown. 28. Question: Question: With reference to the projection screens plans are unclear as to which rooms are to be Faculty Training. Please clarify. Response: Question is not clear. Recessed electrically roll down screens are to be installed in classrooms and conference rooms as shown on plans. 29. Question: The single line Drawing E301 calls for the panel CDP to be located on the second floor. The panel schedule for CDP on Drawing E401 calls for its location to be in room 101 which is on the first floor. The panel CDP is being referenced (via key note #3) in the basement on drawing E204A. Please confirm and advise which location is correct for this panel CDP? Please note we believe the correct location shall be as shown on drawing E203A. Response: CDP will be in the Basement Finley Hall Renovation Page 5 of 14

6 30. Question: The single line drawing E301 calls for the new generator to be located in the Mechanical Mezzanine. The floor plan drawing E203A shows the Generator to be located on the Roof. Please confirm and advise which location is correct for this Generator? Please note we believe the correct location shall be as shown on drawing E203A. Response: Generator shall be on the Roof 31. Question: Please confirm and advise if the new Generator requires a WP Enclosure? Response: As shown on drawing E302A. New Emergency Generator in Weatherproof Enclosure 32. Question: The single line Drawing E301 calls for the ATS to be located in the second floor Network room. The floor plan drawing E-202A does not show this ATS in the second floor Network room. Please confirm and advise the correct location for this ATS. Please note we believe the correct location shall be as called for on the single line drawing E-301 in the second floor Network room #229 on drawing E202A. Response: ATS shall be located in the Basement 33. Question: The single line Drawing E301 calls for the panel EM to be located in the second floor Network room #229. The panel schedule for EM on drawing E-402 calls for its location to be in the Basement. The panel EM is not shown on either one of the two floor plans, E-202A for the second floor or E-203A for the Basement. Please confirm and advise which location is correct for this panel EM? Please note we believe the correct location shall be as called for on the single line drawing E-301 in the second floor Network room #229 on drawing E202A. Response: Panel EM shall be located in the second floor network room 34. Question: The single line Drawing E301 and the panel schedule on drawing E-401 both call for the panel P2 to be located in the second floor Electric Closet #219. The floor plan drawing E-202A for the second floor does not show this panel anywhere. Please confirm and advise of the correct location for this panel P2? Please note we believe the key note #11 on drawing E-202A should be changed to reference to panel P2. Response: P2 shall be located in Closet # Question: The single line Drawing E301 and the panel schedule on drawing E-401 both call for the panel R1B to be located in the First floor Electrical Closet #121. The floor plan drawing E-201A for the First floor foes not show this panel anywhere. Please confirm and advise of the correct location for this panel R1B? Please note we believe this panel R1B shall be located next to panel R1 in the Electric Closet #121. Response: R1B shall be located in Closet # Question: The single line drawing E301 calls for the panel R1B to be fed from panel R1. The panel schedule on drawing E-401 calls for the panel R1B to be fed from MDP. Please confirm and advise which feeder is correct? Please note we believe the single line drawing E-301 is correct. Response: R1B shall be fed from panel R1 Finley Hall Renovation Page 6 of 14

7 37. Question: What is the seismic design category for this project? Response: As per IBC 2006 New Jersey Edition, we need to follow Uniform Construction Code for the alteration and addition of the existing building. The seismic design criteria are not applicable for the existing building. 38. Question: The existing trees are very close to the building. Who is responsible for trimming the trees to allow adequate space for construction? Response: The University will be responsible for trimming of trees. The extent of trimming required will be determined upon award of contract and coordination with contractor. II. Special Notice of Bid Extension: NA III. Changes to Prior Addenda: NA IV. Changes to Bidding Requirements: NA V. Changes to Agreement and Other Contract Forms: NA VI. Changes to Conditions of the Contract: NA VII. Changes to Specifications: A. Regarding Specification Section Metal Stairs, ADD paragraph2.8.a.6 reading Where stringers abut side walls, install continuous steel closure plate to cover gap. Weld plate to top of stringer, scribe tight to wall. Finish to match stringer. B. Regarding Specification Section Finish Hardware, REVISE the paragraph C.6 to read as follows: 6. Provide network switch(es) and Cat5 network cable as required to connect to Owner s existing PERSONA system. All switches shall be Cisco 3750E to match Owner standard. C. Regarding Specification Section Projection Screens, DELETE paragraph 2.2.A and 2.2.B.1. REVISE paragraph 2.2.C.1.a to read Da-Lite Screen Co., Inc., Tensioned Advantage Electrol. REVISE paragraph 2.2.D.2 to add the following sentence Screen fabric shall be tab-tensioned.. REVISE paragraph 2.2.D.4 to read Drop: Provide 12 extra black masking drop at top of viewing area.. REVISE paragraph 2.2.D. 5.a to read Screen shall have viewing area with an aspect ratio of 16:10 and a viewing area 60 by 96 inches. DELETE paragraph 2.2.D.5.b. Finley Hall Renovation Page 7 of 14

8 D. Regarding Specification Section Rooftop Air Conditioners, paragraph 2.2.B, ADD paragraph 2.2.B.5 Annexair. VIII. Changes to Drawings: A. For all cold formed metal framing for exterior non-load bearing walls and roof rafter framing, General Contractor is responsible for the structural design and installation and shall provide shop drawings and structural calculations signed and sealed by a licensed NJ engineer. Design and installation shall be in accordance with the performance criteria and loads as shown in Specification Section and the Structural Drawings. B. General Contractor shall provide blocking at all locations where wall mounted equipment is shown (flat screens, marker boards, toilet accessories, etc) whether or not the equipment is provided or installed by the G.C. C. Regarding Drawing A-104 Roof Plan, Provide and install (2) layers 1/2" fire rated moisture resistant gypsum board on each side of roof truss at column locations "D" & 'L" at both sides of building (total of 4 locations) to provide draftstopping between the rated roof assembly and non-rated roof assembly. Refer to firestopping details for sealing of any mechanical penetrations. typ. D. At doors # 1VES1G, # 1VES3A, #1VES3C and #1VES2B, G.C. to provide and install ADA door operator with push button by LCN model # 4600 Electric AutoEqualizer with hardwired wall mounted actuators in stainless steel finish with engraved ADA symbol in a 6" diameter mount. Push button actuator to be integrated with card readers at door locations. G.C. to provide a fully functional door including all conduits, power and control wiring, electric strikes, etc. E. Regarding Drawing A101 First Floor Plan, wall section tag on stair 1STR2 reading 4/A601.3 SIM is Changed to read 3/A601.3 SIM F. Regarding Drawing A102 First Floor Plan, wall section tag on stair 1STR2 reading 4/A601.3 SIM is Changed to read 3/A601.3 SIM. Wall section tag on exterior wall of room #242 reading 4/A601.3 is Changed to read 3/A601.3 G. Regarding Drawing A301.2, Section 2, at the footing on Column line 1 & 6, fill space between new and existing foundation walls with ¾ crushed stone. H. Regarding Drawings A401 and A402, soffits in new Elevator Lobby 1VES1 and 2COR2 shall be tagged with Detail Tag 5/A403. I. Regarding Drawing A503, Section 1, Change note reading Layers 5/8 fire rated gypsum board over 2-5/8... to read Two (2) layers 5/8 fire rated gypsum board J. Regarding Drawing A601.1, Wall Section 4 shall be constructed in accordance with UL Design U418. K. Regarding Drawing A601.2, Detail 6, interior window sill shall be solid surfacing material. L. Regarding Drawing A702.1, Detail 9, provide steel framing around roof hatch opening in accordance with Typical Roof Opening Detail on Drawing S201. Finley Hall Renovation Page 8 of 14

9 M. Regarding Drawing A702.1 Details 10 and 12 and A702.3, Details 1 and 2, Change note reading Cont. treated wood blocking as required. Anchored to existing structure. to read Cont. pressure treated wood blocking as required to achieve proper roof pitch. Anchored to existing structure. N. Regarding Drawings A904 and A904.1, Key Tag D Overhead Projector - Overhead Projector will be provided and installed by others. GC to provide and install projector mount consisting of 8 square mounting plate #CMA110, adjustable pipe #CMS012018, and electrical enclosure #CMA160 by Chief Manufacturing. Provide 12 guage solid steel mounting channels P1000 by Unistrut as required. Provide power and data as shown on Electrical Drawings. Typical for all Overhead Projector Locations. O. Regarding Drawing E001, Electrical General Notes, DELETE Note #3. P. Regarding Electrical Drawings, New electrical circuits 20A, 1P, 120V shall be provided with 2#12AWG+1#12GND conductors in 3/4in Conduit. Q. Regarding Electrical Drawings, IT and Power Through-Slab Poke-Throughs shall be RC-4 Multi- Service Device by Wiremold, Inc. or approved equal. R. Regarding Electrical Drawings, Audio-Visual Through-Slab Poke-throughs shall be 2 RC9AM2TC Single Service Device by Wiremold, Inc. or approved equal. S. Regarding Drawing E101, see the following modifications or clarifications: 1) Lighting fixtures type N circuit is changed to EM-11. They are located at West and South 1 st Floor entrances. 2) Lighting fixtures located on the stairs 1STR1 and 1STR2 are to be connected to emergency power circuit EM- 11 and EM-13. 3) Rooms: 101, 105, 119, 125, 135,104, 110, 122, 132 Lighting controls are changed as follows: each room is to have 2 light zones: one zone for the front light fixtures located in the proximity of the projector screen and one zone for remaining light fixtures. The two zones will be controlled by the light switches already shown on the drawings. 4) Booth 101A, 101B, 119A, 119B, 119C, 119D Add one lighting switch and one junction box for booth light control for each booth. Booth light fixture to be furnished by the booth s supplier. 5) Room 104, 119, 122 Light switches to be Dimming Switches. 6) Room 108 Light fixture circuit is changed to normal power L ) Room 119 Add the circuit number supplying the light fixtures: L1-15 and L ) Room 125- Add one (1) wall mounted emergency lighting unit with battery backup. 9) Light fixtures type O on the exterior wall north side of the building to be powered from a new 20A, 120V circuit L ) Rooms132A, 132B Lighting circuit is changed to L ) Rooms 1WOM1 and 1 MEN1 Occupancy sensor type is changed to type D. T. Regarding Drawing E102, see the following modifications or clarifications: 1) Stairs 2STR1 and 2STR2 - Lighting fixture are to be connected to emergency power circuit EM- 15 and EM-17. 2) Room 2COR2 Add the circuit numbers supplying the fixtures on this corridor: EM-15 and L2-18. Finley Hall Renovation Page 9 of 14

10 3) Rooms 2WOM1 and 2MEN1 Occupancy sensor type is changed to type D. 4) Room 227 Add (2) Light fixtures type (E). 5) Room 227, 229 Add (1) wall mounted emergency light unit with battery backup in each room. 6) Rooms: 202, 204 and 214 Lighting control is changed as follows: each room has 2 light zones: one zone for the front light fixtures located in the proximity of the projector screen and one zone for remaining light fixtures. The two zones will be controlled by the light switches already shown on the drawings. 7) Room 222 Add (1) Light switch. 8) Room 218 South (Open to below) Light fixture type Q circuit number is changed to L ) Building exterior wall mounted light fixtures type N is deleted. U. Regarding Drawing E103, see the following modifications or clarifications: 1) Stairs 3STR1 and 3STR2 - Lighting fixtures are to be connected to emergency power circuit EM- 19 and EM-21. 2) Rooms: 389, 311, 319, 327, 329, Lighting control is changed as follows: each room has 2 light zones: one zone for the front light fixtures located in the proximity of the projector screen and one zone for remaining light fixtures. The two zones will be controlled by the light switches already shown on the drawings. 3) North Corridor Lighting circuits are to be L3-13, L3-17. Add (1) occupancy sensor type C. 4) South Corridor Lighting circuits are to be L3-15, L3-19. Add (3) occupancy sensors type C. 5) Room 316 Lighting circuit for (2) fixtures is to be L3-18. Add (1) Occupancy sensor type B. 6) Room 3WOM1 and 3MEN 1 Occupancy sensor type is changed to type D. 7) Room 348 Light switch is to be replaced with (1) occupancy sensor switch. 8) Basement Mechanical Room - Emergency lighting circuit is to be EM-25. Stairs light fixtures are to be connected to emergency power circuit EM-25. V. Regarding Drawing E201A, see the following modifications or clarifications: 1) Room 101 Delete Projector power, data/av receptacles were deleted. Add (1)LCD monitor. Add(1) Power quad receptacle, data and AV outlets for AV Rack, new Power circuit to be 20A, 120V, 1P from circuit R ) Booth 101A, 101B, 119C, 119D, 119A, 119B Add at each booth (1) Booth fan control circuit including (1) control switch, wired to (1) duplex receptacle located above the Booth. Add at each booth (1) Wiremold Raceway with power and telecommunication receptacles to be installed above the booth work desk. 3) Room 105 AV Rack power and data receptacles are relocated to the North West corner of the room. The Front Lighting control switch, Motorized Shades control switches and Motorized screen control switch are to be grouped and located near the Teacher desk. 4) Room The AV Rack power quad receptacle and data receptacles are to be located in South- East corner of room. New Power circuit will be from C The Front Lighting control switch, Motorized Shades control switches and Motorized screen control switches are to be grouped and located near the Teacher s desk 5) Room 1WOM1 Dryers circuits are changed to P1(36, 38) and P1(40,42) 6) Room 2MEN1 - Dryers circuit is changed to P1(32, 34) 7) Room 125, The Front Lighting control switches, Motorized Shades control switches and Motorized screen control switches are to be grouped and located near the Teacher s desk. 8) Corridor 1COR1 Add RS power and data outlets for Sign displays at seven (7) door locations on the North side of the corridor. Power to be supplied from (1) new circuit C Finley Hall Renovation Page 10 of 14

11 h) Corridor 1COR1 Add RS power and data outlets for Sign displays at five (5) door locations on the South side of the corridor. Power is to be supplied from (1) new circuit C ) Room 104 Add (2) Floor boxes including power, data and AV between 1 st and 2 nd chair rows; new power circuits R1B-35 and R1B-37 to supply the quad receptacles from the floor boxes. AV Rack quad receptacle to be supplied by circuit C1-33. Add Power and data outlets for (1) new LCD monitor on the east side wall. The Front Lighting control switch, Motorized Shades control switches and Motorized screen control switches are to be grouped and located near the Teacher s desk. 10) Room The Front Lighting control switch, Motorized Shades control switches and Motorized screen control switches are to be grouped and located between the motorized screens. 11) Room The Front Lighting control switch, Motorized Shades control switches and Motorized screen control switches are to be grouped and located near the Teacher s desk. Add (4) new circuits C101-9,11, 10, 12 to serve the AV rack new quad receptacle and other room power requirements. 12) Room Projector power and data receptacles were deleted. Add power and date for (3) new LCD monitors, power to be supplied from R1B-32, 34, 36. The Front Lighting control switch and Motorized Shades control switch are to be grouped and located on the East side wall. Add data and (1) Printer duplex receptacle on circuit R1B-24. Add RS power and data for Sign displays at door to Room 132 from circuit R ) Room 140 Add (1) new Floor box including power and data outlets. Power is to be provided from a new circuit C1-3. LCD monitor power is to be supplied from new circuit R1-5 14) Add Key Note #35 reading: Floor boxes shall be FSR Inc Model# FL500P-4-SLP unless otherwise indicated. 15) RS - Digital Sign to include 120V receptacle and data box. W. Regarding Drawing E201B, see the following modifications or clarifications: 1) Room 1VES1, 1STR1, 1STR2 For reference, Sprinkler system (1) Tamper switch and (1)Water Flow Switch is to be located in each space. 2) Corridor 1COR1 Add (2) Horne/Strobes. 3) Room 104 Add Data and Power receptacles for (3) Cameras. Power to be supplied by one new 20A, 120V, circuit EM-22 via 2#12AWG +1#12GND in 3/4in Conduit. 4) Room Add Data and Power receptacles for (3) Cameras. Power to be supplied from one new 20A, 120V, circuit EM-22. X. Regarding Drawing E202A, see the following modifications or clarifications: 1) Room 217 Add Data and power for New LCD monitor, to be supplied from circuit R ) Room 2WOM1 and 2MEN1- Change dryer circuits to P2-(6,8) and P2-(2,4) 3) Room 219 Change (1) duplex receptacle circuit to EM-26 4) Room 228 Add (1) new duplex receptacle and data receptacle, power to be supplied from new circuit R ) Room 227 Add (3) new emergency power circuits (EM- 24, 26, 28 ) to supply (3) new quads receptacle to be located on the Telecom Racks. 6) Room 229 Add (4) new emergency power circuits (EM- 30, 32, 34, 36 ) to supply (4) new quads receptacle to be located on the Telecom Racks 7) Add Keynote 22 reading Provide (2) 4in conduits, core drill and sleeves to ceiling below for tel/data use. Route conduits into corridor ceiling below. Conduits to be located in corner of room by door. 8) Corridor 2COR1 Add (1) wall phone data receptacle and (1) Wireless Access Point(WAP) data receptacle. Add RS power and data receptacles for Digital Sign displays at (3) door locations; power supplied from new circuit C2-41. Finley Hall Renovation Page 11 of 14

12 9) Room 202,204, Provide power for Motorized shades new 20A, 120V circuit R2-52 and ) Room 202, 204, The Front Lighting control switch, the Motorized Shades control switch and projection screen control switch are to be grouped and located on the South wall. 11) Room 202, 204, Junction Boxes symbol located under the table are changed to a FSR model type for power, data and AV outlets (see H.14 above). Add (3) New duplex receptacles, one in each room to be supplied from (1) new circuit R2-36 and R ) Room 214 Projector power circuit is changed to new circuit R ) Room 208- Add Key Note#19 reading Provide Wiremold raceway with (2) quad receptacles and (8) telecom outlets above the counter. Wiremold to be on wall with adjoining conference room. 14) Room 208A- Power for Motorized shades is deleted. 15) Room 222G Add duplex power and data outlets for (1) LCD monitor. Power to be supplied from new circuit R )Room 230 Add (2) new circuits for room: C2-41, )Room 240- Add duplex power and data outlets for (1) LCD monitor. Power to be provided from new circuit R2-54. Add (1) New Duplex receptacle, supplied from a new circuit R ) Room 242- Add (2) New duplex receptacles supplied from new circuit R2-40. Change Junction boxes home run key note #17 to #22 (2 locations) and Keynote #18 change to #23. 19) Delete General Note#7 and Key Notes#13, 15 and 18. Y. Regarding Drawing E202B, see the following modifications or clarifications: 1) Room COR2, 2STR1, 2STR2 For reference, Sprinkler system (1) Tamper switch and (1)Water Flow Switch is to be located in each space. 2) Corridor 2COR1- Add (2) Horne/Strobes. 3) Room 202, 204, 214 Add (2) speakers locations in each room. 4) Room 222G Add (1) Strobe 5) Room 222 Add (1) Smoke detector. 6) Room 230 Add (1) Horn/strobe and (1) strobe. Z. Regarding Drawing E203A, see the following modifications or clarifications: 1) At each Enclosed Office, delete Junction Box and provide (1) quad receptacle and (3) Tel/data outlets (Typical for all Offices) 2) Room 3VES1 Add (1) new duplex receptacle and data outlet. Power to be supplied from new circuit R ) Room 300B Add duplex power and data outlets for (1) LCD monitor. 4) Room 305, 309, 380 Delete Under-table junction boxes. 5) Room 316 Receptacles power circuit are changed to new circuit R ) Room 318 Add under table junction box with Key Note 38. Keynote #38 to read Provide whips for (6)Data and (3) Quad receptacles. 7) Room 389 Circuits for floor boxes labeled C3-xx are to be C3-31 and C3-33. AV Rack quad receptacle is to be supplied from new circuit C3-39. Front light control switch and motorized projection screen control is to be located on the north wall. 8) Room 311, 319, 327, 329,337 - At Teacher s desk in each room, Add (1)FSR floor box with power to supplied from circuits C3-29,37, 20, 30,38. At AV Racks in each room, Add (1) quad receptacle. At each room, front light control switch and motorized projection screen control is to be located in the Teacher s desk proximity. Circuits for Student desk floor boxes in Room 311shall be circuits C3-43, 45, 47, 49,51, 53. Circuits for Student desk floor boxes in Room 319shall be Circuits C3-55,57,59,61,63,65. Circuits for student desk floor boxes in Room 327 shall be Circuits C3-44,46,48,50,52,54. Circuits for student desk floor boxes in Room 329 shall be Circuits C3- Finley Hall Renovation Page 12 of 14

13 56,58,60,62,64,66. Circuits for student desk floor boxes in Room 337 shall be Circuits C3-68,70,72,74,76,78. 9) Room 353- Add (1) new duplex receptacle and data outlet, supplied from circuit R ) Room 339 Add (1) new duplex receptacle and data outlet, supplied from new circuit R3-17. Add (1) new circuit for the work stations, circuit C ) Room 344 Add (2) Quad receptacles supplied from (2) new circuits EM-16, ) Corridor 300E- Add RS power and data outlets for Sign displays at seven (6) door locations. Power to be supplied from new circuit R ) Corridor 300C- Add RS power and data outlets for Sign displays at seven (5) door locations. Power to be supplied from new circuit R ) Room 3WOM1 and 3MEN1- Power circuit for dryers are changed to P3-(40,42), P3-(36,38), P3- (32,34), P3-(28,30) 15) Basement Mechanical Room B100, B103 Add (1) duplex receptacle in each room supplied from new circuit EM-24. Add (1) New circuit EM-12 supplying HVAC control equipment. For reference, Sprinkler system (4) Tamper switches and (1)Water Flow Switch is to be located in B103. Add (3) Circuits for Water Heater Circulating Pumps and Hot Water Heater control circuit from Panel PPB including 30A, 1P disconnect switches. Add Note: EC shall reconnect electrical circuits feeding existing mechanical equipment to remain from Panel PPB. Extend wires and conduits as required. 16) Roof plan Add (1) new circuit (R3-41) to feed RTU1-1, 2 and RTU2-1,2 receptacles. 17) Delete Key Notes 14 and ) Room 329 Add Key Note 39 reading Provide (5) 3in conduits for satellites to Tech Room ceiling. Add Key Note 40 reading Provide(4) 3in conduits to Tech Room Ceiling. Route conduits down from 3 rd floor ceiling, in wall of Room 329, and into Tech Room ceiling. AA. Regarding Drawing E203B, see the following modifications or clarifications: 1) Room 3VES1, 3STR1, 3STR2 For reference, Sprinkler system (1) Tamper switch and (1)Water Flow Switch is to be located in each space. 2) Corridor 300E Add 3 Horn/strobes. 3) Corridor 300C Add (1) Horn/strobe. 4) Room 311, 319, 327, 329, 337 Add (2) Speakers in each room. BB. Regarding Drawing E301, Generator Set model number is changed to Generac SG050 Sound Level 1. All other characteristics remain unchanged. CC. Regarding Drawing E403, Lighting Fixture Schedule is revised. See attached Sketch SKE-1. DD. Regarding Drawing P101, Detail 02 Plumbing Fixture Schedule, Add No.P-4 reading Domestic Water Heater AO Smith Cyclone XHE BTH gallon storage, 173 GPH 100 deg. Temp Rise, 150,000 btu/hr. See plans for pipe sizing. EE. Regarding Drawing P101, Detail 02 Plumbing Fixture Schedule, Change No.P-2 to read Urinal American Standard FloWise Flush Free Waterless Urinal Waste 2 Vent 1-1/2 Provide manufacturers support and minimum two replacement kits. FF. Regarding Drawing HP001, Detail 04 Natural Gas riser Diagram, at H.W. Heater, Delete Gas Fired HW...150,000 btu/hr and refer to Detail P101/02 Plumbing Fixture Schedule, No.P-4. Finley Hall Renovation Page 13 of 14

14 Please acknowledge receipt of this Addendum No. 2 via fax. The fax number is Re: RFP 898 Finley Hall Renovation Company Name (please print) Date Signature Title Contact Name (please print) Distribution: All Bidders D. Roche/MSU Henry Ornovitz C. Danish/MSU C. Sarajian/MSU Project File Attachments: SKE-1 Finley Hall Renovation Page 14 of 14

15

December 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions

December 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions December 31, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y16-721-MM / ADDENDUM No. 1 ORANGE COUNTY CONVENTION CENTER PHASE III VALENCIA BALLROOM RENOVATION Bid Opening Date: January 12, 2016

More information

Montclair, NJ ADDENDUM NO. 1 Issue Date: May 15, 2017

Montclair, NJ ADDENDUM NO. 1 Issue Date: May 15, 2017 Montclair, NJ 0704 ADDENDUM NO. Issue Date: May 5, 207 Request for Proposal # 294 Building 47 West Renovation- Phase 6a Number of Pages: 2 plus 5 sketches Date of Original Bidding Documents: April 26,

More information

Residential Construction Checklist Single and Two Family Construction

Residential Construction Checklist Single and Two Family Construction DATE: _ Building Inspection Submittal Requirements Residential Construction Checklist Single and Two Family Construction Submit a City of Big Spring Permit Application, checklist, and 3 complete hard copy

More information

ADDENDUM No. 4 Page 1 of 8 (includes attachment)

ADDENDUM No. 4 Page 1 of 8 (includes attachment) ADDENDUM No. 4 Page 1 of 8 (includes attachment) Date Issued: November 27, 2017 Project: TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J

More information

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic GENERAL SITE PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS Scope of work narrative Building code review Description of construction Documentation on drawings as List of applicable

More information

ADDENDUM NOTICE INTERIOR RENOVATIONS AT THE BATHURST CLARK RESOURCE LIBRARY, 900 CLARK AVENUE WEST, VAUGHAN, ON

ADDENDUM NOTICE INTERIOR RENOVATIONS AT THE BATHURST CLARK RESOURCE LIBRARY, 900 CLARK AVENUE WEST, VAUGHAN, ON The City of Vaughan Procurement Services Department 2141 Major Mackenzie Drive Vaughan, ON L6A 1T1 Tel (905) 832-8555 ADDENDUM NOTICE ADDENDUM NO. 3 Total of (5) page BID NO. T18-003 DESCRIPTION: INTERIOR

More information

Wayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009

Wayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009 ADDENDUM NO 2 OWNER: Wayne State University DATE: January 4 th, 2019 PROJECT: NM Project Number: 18113.0 ARCHITECT: ENGINEER: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009 IMEG 26200 Town

More information

ADDENDUM #1. April 29, 2009

ADDENDUM #1. April 29, 2009 April 29, 2009 Re: HACC, Central Pennsylvania s Community College Midtown 1 CCTA Phase 2 Solicitation # 09-17 From: Eastern pcm, LLC Construction Manager HACC 212 Locust Street, Suite 604 Harrisburg, PA

More information

To the Drawings and/or Specifications for. Board of Education of Harford County Lancaster, PA 17603

To the Drawings and/or Specifications for. Board of Education of Harford County Lancaster, PA 17603 ENDUM NO. 2 To the Drawings and/or Specifications for Gilbert Architects Youth s Benefit Elementary School - #0729 626 N. Charlotte St. Board of Education of Harford County Lancaster, PA 17603 June 2,

More information

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014 FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services ADDENDUM #4 December 5, 2014 This Addendum is issued to provide answers to questions from potential bidders

More information

03/7/12 Issuance UTD Section Page 1 of 5 Electrical General

03/7/12 Issuance UTD Section Page 1 of 5 Electrical General SECTION 26 01 00 ELECTRICAL GENERAL PART 1: GENERAL 1.1 Electrical/Telecommunications Design 1.1.1 This section of the design and construction standard outlines general requirements for electrical and

More information

ELECTRICAL GENERAL DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL Electrical/Telecommunications Design

ELECTRICAL GENERAL DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL Electrical/Telecommunications Design PART 1: GENERAL 1.01 Electrical/Telecommunications Design A. This section of the design and construction standard outlines general requirements for electrical and telecommunications designs to be performed

More information

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT 1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department October 25, 2010 Addendum No. 09.R INVITATION FOR BID NO.: 11-05 Modernization of Classroom Building 300 Chabot

More information

2. Electrical rooms shall be centrally located and stacked so that feeder conduits and bus duct are run as straight and short as possible.

2. Electrical rooms shall be centrally located and stacked so that feeder conduits and bus duct are run as straight and short as possible. PART 1: GENERAL 1.01 Electrical/Telecommunications Design A. This section of the design and construction standard outlines general requirements for electrical and telecommunications designs to be performed

More information

PROJECT LOCATION BOZEMAN HIGH SCHOOL. ELECTRICAL ENGINEER: Van Dykken Engineering 37 Spanish Peak Drive Bozeman, MT Phone:

PROJECT LOCATION BOZEMAN HIGH SCHOOL. ELECTRICAL ENGINEER: Van Dykken Engineering 37 Spanish Peak Drive Bozeman, MT Phone: DRAWING INDEX GENERAL C. PROJECT COVER G-WING A/V IMPROVEMENTS.0 AREA PLAN ST FLOOR SOUTH. TYP. PROJECTOR MOUNTING & PROJECTOR NOTES.2 G-WING TECHNOLOGY CABINET ELEVATIONS.3 G-WING WIRING DIAGRAM.4 G-WING

More information

SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5. February 25, 2013

SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5. February 25, 2013 SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5 February 25, 2013 Owner: Architect: Administrative Office of the Courts 2860 Gateway Oaks Drive, Suite 400 Sacramento,

More information

University of Houston Master Construction Specifications Insert Project Name SECTION MECHANICAL SCOPE OF WORK PART 1 - GENERAL

University of Houston Master Construction Specifications Insert Project Name SECTION MECHANICAL SCOPE OF WORK PART 1 - GENERAL SECTION 23 00 10 - MECHANICAL SCOPE OF WORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements", and Section 23 01

More information

ADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016

ADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016 ADDENDUM NO. 1 DATE: MARCH 1, 2016 PROJECT: ARCHITECT: TO: 2017 BAND ADDITION, ROOF REPLACEMENT AND AIR-CONDITIONING WORK ROCK FALLS HIGH SCHOOL 101 12 TH STREET ROCK FALLS, IL 61071 BCA PROJECT NO. 1620

More information

TELEPHONE: (215) Addendum No. 1

TELEPHONE: (215) Addendum No. 1 THE SCHOOL DISTRICT OF PHILADELPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, Third Floor - Suite 371 Philadelphia, PA 19130-4015 TELEPHONE: (215) 400-4730 Addendum No.

More information

MSU Barnard Hall 105 Cleanroom Installation PPA # Page 1

MSU Barnard Hall 105 Cleanroom Installation PPA # Page 1 ADDENDUM NUMBER 1 DATE: February 10, 2017 PROJECT: MSU Barnard Hall Room 105 Cleanroom Installation PPA# 16-0002 (Consulting Design Solutions, Inc. Project # 1613) BID DATE: February 23, 2017 2:00 PM,

More information

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017.

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017. !!! Addendum EXP Project No: MTA Project No: WIND-17-01 Project: Windsor Hall Renovations October 12, 2017 Addendum No: 3 The following information supplements and/or supersedes the bid documents. This

More information

James Shields Middle School 2611 W 48th St Chicago, IL 60632

James Shields Middle School 2611 W 48th St Chicago, IL 60632 2 W 48th St Chicago, IL 02 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

CHAPTER 5 ARCHITECTURE

CHAPTER 5 ARCHITECTURE CHAPTER 5 ARCHITECTURE 5.1 GENERAL... 4 5.2 CONCEPT/PROJECT DEFINITION DESIGN (30%) SUBMITTAL REQUIREMENTS... 4 5.2.1 DESIGN ANALYSIS... 4 5.2.1.1 Design Criteria... 4 5.2.1.2 Narratives... 4 5.2.1.2.1

More information

Specifications: Other: sign in sheet

Specifications: Other: sign in sheet To: All Vendors Bidding on The College of New Jersey Nursing Simulation Lab Fit-Out Project From: Roselle Horodeski Finance & Business Services Date: July 29, 2015 ADDENDUM NO. 1 ISSUE DATE: July 29, 2015

More information

TO WHOM IT MAY CONCERN:

TO WHOM IT MAY CONCERN: TO WHOM IT MAY CONCERN: A lot of questions are asked throughout the year as to when a building permit is required. This list may help identify some of the instances when a permit would be required: Permit

More information

ARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI)

ARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI) ARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI) PROJECT: Villa Joseph Marie High School - Auditorium Addition ARCHITECTS PROJECT NO: 2339 ASI NO: 001 DATE OF ISSUANCE: 12/5/2017 TO: Twining Construction Co.

More information

ADDENDUM NO. 1 THOROUGHBRED ROOM RENOVATION PHASE II DINING AREA MURRAY STATE UNIVERSITY, MURRAY, KY PROJECT #

ADDENDUM NO. 1 THOROUGHBRED ROOM RENOVATION PHASE II DINING AREA MURRAY STATE UNIVERSITY, MURRAY, KY PROJECT # ADDENDUM NO. 1 THOROUGHBRED ROOM RENOVATION PHASE II DINING AREA MURRAY STATE UNIVERSITY, MURRAY, KY PROJECT #13-046 10-23-2013 Bidders shall acknowledge receipt of this Addendum on the Bid Form, in the

More information

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017.

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017. June 15, 2017 GS#108-281 Greene Hall Renovations University of Southern Mississippi Hattiesburg, Mississippi 00.910 ADDENDUM NO 1. This Addendum contains 6 pages and 21 pages of attachments for a total

More information

Residential Room Addition / Remodel Submittal Requirement Checklist

Residential Room Addition / Remodel Submittal Requirement Checklist City of Elko Building Department 1753 College Avenue Elko, Nevada 89801 (775) 777-7220 fax (775) 777-7229 Residential Room Addition / Remodel Submittal Requirement Checklist TWO COMPLETE SETS OF PROPERLY

More information

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS ARCHITECTURE, LLC 1721 4 th AVENUE NORTH, SUITE 101 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 7 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS

More information

ADDENDUM NO. 02 July 31, 2012

ADDENDUM NO. 02 July 31, 2012 Post Point Wastewater Treatment Plant Improvements Owner: Engineer: GC/CM: City of Bellingham Carollo Engineers Mortenson Construction ADDENDUM NO. 02 July 31, 2012 THIS ADDENDUM MUST BE ACKNOWLEDGED ON

More information

RENOVATION OF THE FARMERS MARKET Reference Number:

RENOVATION OF THE FARMERS MARKET Reference Number: RENOVATION OF THE FARMERS MARKET Reference Number: 13-098 A D D E N D U M NO. 1 The following shall form part of the tender documents issued by the City of Guelph s Purchasing Department, June, 2013. NOTE:

More information

Friedrich Ludwig Jahn Elementary School 3149 N Wolcott Ave Chicago, IL 60657

Friedrich Ludwig Jahn Elementary School 3149 N Wolcott Ave Chicago, IL 60657 39 Wolcott Ave Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

SUBMITTAL REQUIREMENTS FOR COMMERCIAL BUILDING PROJECTS

SUBMITTAL REQUIREMENTS FOR COMMERCIAL BUILDING PROJECTS SUBMITTAL REQUIREMENTS FOR COMMERCIAL BUILDING PROJECTS When submitting your application for Commercial projects please include the following: 1. Completed Building Permit Application with page 2 stamped

More information

ADDENDUM NO. 3. Ellis County Elections Building

ADDENDUM NO. 3. Ellis County Elections Building AUSTIN ARCHITEXAS DALLAS ARCHITECTURE, PLANNING AND HISTORIC PRESERVATION, INC. ADDENDUM NO. December 8, 2014 to the BIDDING DOCUMENTS for Ellis County Elections Building Waxahachie, Texas By ARCHITEXAS

More information

INVITATION TO TENDER ITT No. PS FIRE HALL 5 + HOUSING CONSTRUCTION. ADDENDUM No. 2 and AMENDMENT No. 2

INVITATION TO TENDER ITT No. PS FIRE HALL 5 + HOUSING CONSTRUCTION. ADDENDUM No. 2 and AMENDMENT No. 2 FINANCE, RISK AND BUSINESS PLANNING Supply Chain Management May 17, 2016 INVITATION TO TENDER ITT No. PS20160468 FIRE HALL 5 + HOUSING CONSTRUCTION ADDENDUM No. 2 and AMENDMENT No. 2 RE: Various additions

More information

ADDENDUM 1. This Addendum forms part of and modifies Proposal Documents dated, October 31, 2018, with amendments and additions noted below.

ADDENDUM 1. This Addendum forms part of and modifies Proposal Documents dated, October 31, 2018, with amendments and additions noted below. DATE: November 16, 2018 PROJECT: JJL Library & Street Level Renovation RFP NO: 744-R1903 OWNER: The University of Texas Health Science Center at Houston TO: Prospective Proposers This Addendum forms part

More information

12560 W. Cedar Drive Lakewood, CO Barry Himmelman President

12560 W. Cedar Drive Lakewood, CO Barry Himmelman President Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 16-BS-2260 ADDENDUM NUMBER FOUR January 8, 2016 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM

More information

ADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC.

ADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC. ADDENDUM NO. 2 PROJECT: OWNER: ENGINEER / ARCHITECT: PROJECT LOCATION: Saginaw County Community Mental Health Authority Germania Club Renovation Phase 2 Saginaw County Community Mental Health Authority

More information

Thomas A Edison Regional Gifted Center ES 4929 N Sawyer Ave Chicago, IL Co-locating on this campus are EDISON and ALBANY PARK

Thomas A Edison Regional Gifted Center ES 4929 N Sawyer Ave Chicago, IL Co-locating on this campus are EDISON and ALBANY PARK Facility Assessment Report 4929 Sawyer Ave Chicago, IL 025 Co-locating on this campus are EDISO and ALBA PARK This report contains a summary of the results from the facility assessment completed on the

More information

Paul Cuffe Math-Science Technology Academy ES 8324 S Racine Ave Chicago, IL 60620

Paul Cuffe Math-Science Technology Academy ES 8324 S Racine Ave Chicago, IL 60620 82 S Racine Ave Chicago, IL 020 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

A/E REVIEW CHECKLIST HVAC

A/E REVIEW CHECKLIST HVAC A/E CHECKLIST HVAC Reviewers should - Use Checklists when reviewing any type of VA construction project for the following disciplines: Site and Landscape, Architectural, Structural, Plumbing, Fire Protection,

More information

Charles P Caldwell Academy of Math & Science ES 8546 S Cregier Ave Chicago, IL 60617

Charles P Caldwell Academy of Math & Science ES 8546 S Cregier Ave Chicago, IL 60617 S Cregier Ave Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Jackie Robinson Elementary School

Jackie Robinson Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Marcus Moziah Garvey Elementary School

Marcus Moziah Garvey Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

OCPS Submittal Register for Product Data and Shop Drawing Reviews

OCPS Submittal Register for Product Data and Shop Drawing Reviews OCPS mittal Register for Product Data and Shop Drawing s Project ification Drawings - D Shop Drawings - Product Data - Test - TR Test Data - TD Calculations - Calc Certification - Cert 02 22 27 Pre-demolition

More information

Marshall Truck Station Laboratory Addition Project No. TZ MnDOT

Marshall Truck Station Laboratory Addition Project No. TZ MnDOT Marshall Truck Station Laboratory Addition Project No. TZ-91523 MnDOT 13-6574 ADDENDUM NUMBER 2 DATED September 19, 2013 Marshall Truck Station Laboratory Addition Project No. TZ-91523 MnDOT 13-6574 Architect:

More information

ADDENDUM #2 September 12, 2018

ADDENDUM #2 September 12, 2018 Physical Plant Services Project Management 1000 Rim Drive Phone: (970) 247-7523 Fax: (970) 247-7555 Project No. 2007-130P18 Whalen Gymnasium Expansion and Renovation for Exercise Science Request for Qualifications

More information

Amos Alonzo Stagg Elementary School

Amos Alonzo Stagg Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

PLAN SUBMITTAL REQUIREMENTS

PLAN SUBMITTAL REQUIREMENTS DEPARTMENT OF ECONOMIC AND COMMUNITY DEVELOPMENT BUILDING DIVISION PLAN SUBMITTAL REQUIREMENTS Residential and Commercial Projects Welcome to the South San Francisco Building Division. We are providing

More information

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT 1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department August 11, 2010 Addendum No. 2 INVITATION FOR BID NO.: 11-07 Industrial Technology Center, Buildings 1400/1600

More information

Ellen Mitchell Elementary School 2233 W Ohio St Chicago, IL 60612

Ellen Mitchell Elementary School 2233 W Ohio St Chicago, IL 60612 33 W Ohio St Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Single-Family Dwelling Submittal Requirements

Single-Family Dwelling Submittal Requirements Single-Family Dwelling Submittal Requirements The purpose of this guideline is to assist our customers in preparing for plan submittal. The items listed must be included before your plans can be accepted

More information

EPIC Academy High School

EPIC Academy High School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

STEM Magnet Academy. Definitions EXTERIOR W Fillmore St Chicago, IL 60607

STEM Magnet Academy. Definitions EXTERIOR W Fillmore St Chicago, IL 60607 Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Everett McKinley Dirksen Elementary School

Everett McKinley Dirksen Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Hiram H Belding Elementary School 4257 N Tripp Ave Chicago, IL 60641

Hiram H Belding Elementary School 4257 N Tripp Ave Chicago, IL 60641 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item

More information

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118 PART 1: GENERAL This section of the design standard outlines general requirements for electrical and telecommunications designs to be performed for the University of Texas at Austin. This standard is intended

More information

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Daniel S Wentworth Elementary School

Daniel S Wentworth Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

TELEPHONE: (215) Addendum No New Solomon Solis-Cohen Elementary School SDP Contracts No. B-075C, B-076C, B-077C and B-078C of 2017/18

TELEPHONE: (215) Addendum No New Solomon Solis-Cohen Elementary School SDP Contracts No. B-075C, B-076C, B-077C and B-078C of 2017/18 THE SCHOOL DISTRICT OF PHILADELPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, 3 rd Floor Suite 371 Philadelphia, PA 19130 TELEPHONE: (215) 400-4730 Addendum No. 003 Subject:

More information

Andrew Carnegie Elementary School

Andrew Carnegie Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Architecture, Construction, and Engineering Technical Charter

Architecture, Construction, and Engineering Technical Charter Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

North Lawndale College Prep Charter - Collins

North Lawndale College Prep Charter - Collins Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Jonathan Burr Elementary School

Jonathan Burr Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Johann W von Goethe Elementary School 2236 N Rockwell St Chicago, IL 60647

Johann W von Goethe Elementary School 2236 N Rockwell St Chicago, IL 60647 3 Rockwell St Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Hall of Waters List of Historic Drawings

Hall of Waters List of Historic Drawings List of Historic Drawings The following represents the historic drawings of the PROJECT PWA PROJECT NUMBER JOB NUMBER SHEET NUMBER SHEET TITLE DATE NOTES 1935 Drawing Piping Layout at Tank Room for Mineral

More information

Travis County ESD #1. Building Plan Submittals. Information Bulletin. Fire Marshal Hancock

Travis County ESD #1. Building Plan Submittals. Information Bulletin. Fire Marshal Hancock Travis County ESD #1 Information Bulletin Building Plan Submittals Fire Marshal Hancock Effective Date 12/12/2018 Table of Contents INTRODUCTION 3 SECTION I. SUPPORTING DOCUMENTATION 4 SECTION II. GENERAL

More information

Franklin Elementary Fine Arts Center 225 W Evergreen Ave Chicago, IL 60610

Franklin Elementary Fine Arts Center 225 W Evergreen Ave Chicago, IL 60610 22 W Evergreen Ave Chicago, IL 1 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: 08012.00 SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA ADDENDUM NUMBER 1 to the BID SET August 10, 2009 General This Addendum will become part

More information

Nathanael Greene Elementary School 3525 S Honore St Chicago, IL 60609

Nathanael Greene Elementary School 3525 S Honore St Chicago, IL 60609 athanael Greene Elementary School 32 S Honore St Chicago, IL 009 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the

More information

Can you please issue the most recent Soils Report as prepared by Strata? Updated Soils Report to be posted to Christenson Corporation web site

Can you please issue the most recent Soils Report as prepared by Strata? Updated Soils Report to be posted to Christenson Corporation web site CCH ioneer anor Skilled Nursing Facility Questions June, 0 A-Wyoming Can you please issue the most recent Soils Report as prepared by Strata? Updated Soils Report to be posted to Christenson Corporation

More information

Harriet Beecher Stowe Elementary School 3444 W Wabansia Ave Chicago, IL 60647

Harriet Beecher Stowe Elementary School 3444 W Wabansia Ave Chicago, IL 60647 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item

More information

KIPP Charter Bloom. Definitions EXTERIOR S Lowe Ave Chicago, IL Co-locating on This Campus: Hope HS and Kipp Chtr Bloom

KIPP Charter Bloom. Definitions EXTERIOR S Lowe Ave Chicago, IL Co-locating on This Campus: Hope HS and Kipp Chtr Bloom Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

A. Product Data: For each electrical identification product indicated.

A. Product Data: For each electrical identification product indicated. SECTION 16075 - ELECTRICAL IDENTIFICATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

1. Name the horizontal member that rests on the foundation wall to support other wood members.

1. Name the horizontal member that rests on the foundation wall to support other wood members. Student Name: Teacher: Date: District: Rowan Assessment: 9_12 T and I IC62 - Drafting - Architr II Test 1 Description: Unit C - Floorplans - Test 3 (ALL) Form: 501 1. Name the horizontal member that rests

More information

Charles G Hammond Elementary School 2819 W 21st Pl Chicago, IL 60623

Charles G Hammond Elementary School 2819 W 21st Pl Chicago, IL 60623 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item

More information

BUILDING PLAN REVIEW REQUIREMENTS

BUILDING PLAN REVIEW REQUIREMENTS TOWNSHIP OF NORTH FAYETTE BUILDING DEPARTMENT COMMERCIAL PLAN REVIEW REQUIREMENTS BUILDING PLAN REVIEW REQUIREMENTS In order to perform a thorough Building Plan Review, the following specifications, drawings

More information

William H Seward Communication Arts Academy ES 4600 S Hermitage Ave Chicago, IL 60609

William H Seward Communication Arts Academy ES 4600 S Hermitage Ave Chicago, IL 60609 S Hermitage Ave Chicago, IL 9 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

Charles N Holden Elementary School

Charles N Holden Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Philip Rogers Elementary School

Philip Rogers Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Josefa Ortiz De Dominguez Elementary School 3000 S Lawndale Ave Chicago, IL 60623

Josefa Ortiz De Dominguez Elementary School 3000 S Lawndale Ave Chicago, IL 60623 3000 S Lawndale Ave Chicago, IL 023 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This

More information

Thomas Chalmers Specialty Elementary School 2745 W Roosevelt Rd Chicago, IL 60608

Thomas Chalmers Specialty Elementary School 2745 W Roosevelt Rd Chicago, IL 60608 W Roosevelt Rd Chicago, IL 8 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report

More information

Joseph E Gary Elementary School

Joseph E Gary Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Morton School of Excellence

Morton School of Excellence Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

University of Chicago Charter - Carter G Woodson

University of Chicago Charter - Carter G Woodson Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

George Washington Elementary School 3611 E 114th St Chicago, IL 60617

George Washington Elementary School 3611 E 114th St Chicago, IL 60617 3 E th St Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up

More information

University of Chicago - North Kenwood/Oakland 1119 E 46th St Chicago, IL Co-locating on this campus are U OF C - NKO and ARIEL

University of Chicago - North Kenwood/Oakland 1119 E 46th St Chicago, IL Co-locating on this campus are U OF C - NKO and ARIEL Facility Assessment Report 9 E 4th St Chicago, IL 03 This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

Lorenz Brentano Math & Science Academy ES 2723 N Fairfield Ave Chicago, IL 60647

Lorenz Brentano Math & Science Academy ES 2723 N Fairfield Ave Chicago, IL 60647 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item

More information

This Revision No. 01 becomes as fully a part of the first issued documents as if originally issued therewith or originally contained therein.

This Revision No. 01 becomes as fully a part of the first issued documents as if originally issued therewith or originally contained therein. Revision No. 01 Issued February 19, 2016 Page 1 This Revision No. 01 becomes as fully a part of the first issued documents as if originally issued therewith or originally contained therein. This Revision

More information

SECTION PROJECT COORDINATION VIA BIM

SECTION PROJECT COORDINATION VIA BIM SECTION 01 31 13 PROJECT COORDINATION VIA BIM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Alexander Graham Bell Elementary School

Alexander Graham Bell Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

John Palmer Elementary School 5051 N Kenneth Ave Chicago, IL 60630

John Palmer Elementary School 5051 N Kenneth Ave Chicago, IL 60630 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item

More information

ADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS

ADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS ADDENDUM NO. TWO To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS Prepared By: ARCHITECT Bhide & Hall Architects, P.A. 1329-C Kingsley

More information

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA RESPONSES TO QUESTIONS and/or RFI s Date: 11/29/2017 The attention of Contractors submitting

More information

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA RESPONSES TO QUESTIONS and/or RFI s Date: 12/7/2017 The attention of Contractors submitting

More information

Design Deliverables. Summary. A. Expectations for Design Deliverables:

Design Deliverables. Summary. A. Expectations for Design Deliverables: Design Deliverables Summary A. Expectations for Design Deliverables: The Design Team is obligated to advance and deliver the project with a professional manner and standard of care that meets the expectations

More information

Spec Section: , Complete Elec, Comm, and Fire Alarm , Complete Elec, Comm, and Fire Alarm Data Sheets RAN/GCAN

Spec Section: , Complete Elec, Comm, and Fire Alarm , Complete Elec, Comm, and Fire Alarm Data Sheets RAN/GCAN SUBMITTAL REVIEW Submittal: No. 019.00 Spec Section: 26 0000, 28 0000 Complete Elec, Comm, and Fire Alarm Reviewed By: Laura Landon, Comma-Q Architecture Date: June 29, 2012 Project: BPS Belgrade Elementary

More information

SECTION D BIM COORDINATION DRAWINGS - CONTRACTORS

SECTION D BIM COORDINATION DRAWINGS - CONTRACTORS END OF SECTION 01 30 00 SECTION 01 31 21-3D BIM COORDINATION DRAWINGS - CONTRACTORS PART 1 - GENERAL 1.01 RELATED DOCUMENTS Attention is directed to Bidding and Contract Requirements, and to Division 1,

More information

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030 ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO. 2018-008-COM.00030 To: Prospective Bidders of Record Date: January 8, 2019 The following changes, additions, revisions, and/or deletions