Tom Ernst GE Digital Energy Craig Talbot Minnesota Power

Size: px
Start display at page:

Download "Tom Ernst GE Digital Energy Craig Talbot Minnesota Power"

Transcription

1 Tom Ernst GE Digital Energy Craig Talbot Minnesota Power

2 Introduction Traditional 3-phase testing method Traditional 1-phase testing method Alternate 1-phase testing method Application examples

3 3-Phase testing can be challenging Straight forward magnitude & phase angles Requires 6 high-current test set channels 1-phase testing Requires only 2 high-current test set channels Requires non-obvious multipliers Does not simulate real-world loading on Deltawye transformers

4 There is always a way to do this better

5 Alternate 1-phase testing method Requires only 2 high-current test set channels Simulates real-world 1-phase loading conditions No phase shifts No non-obvious multipliers Suitable for commission testing: tests the transformer installation not the relay settings

6 Slope characteristic tests Requires simultaneous injection of test currents into a minimum of 2 relay windings Some test sets do not include 6 high-current channels Magnitude relationship of the currents based on the transformer 3-phase voltage ratio

7 Slope characteristic tests Phase shift between test currents can be challenging for delta grd wye transformers Function of the transformer internal and external connections: phases A, B & C might not be on bushings 1, 2 & 3 Requires thorough understanding of 3-phase power Same transformer can be 30 lag or 30 lead

8 Typical delta - grd wye transformer and associated 3- phase test currents (30 lag)

9 Typical delta - grd wye transformer with rolled phasing and associated 3- phase test currents (30 lead)

10 3-Phase testing connections for a 30 lag transformer

11 Slope characteristic tests Checks the functionality of each phase Only requires 2 current channels May require multipliers and phase shifts that are not obvious (Delta Grd Wye transformers)

12 Relay Test Set 1-Phase testing connections Differential Relay Ia Ib Ic Ia Channel 1 Ib Channel 2 Ic Com

13 Some alternate ideas are better than others

14 Slope characteristic tests Connections are related to the transformer internal and external 3-line diagrams Very affective for commissioning Simulates real-world load and short circuit conditions No non-obvious multipliers No non-obvious phase shifts

15 Differentially balanced 1- phase throughcurrent for a delta - grd wye transf (30 lag) Test Currents to Relay 2.5@ @0 H1 115,000 13,800/7970 GY 20 MVA A B C 100@0 H2 N1/N2 = 115/8 H3 200/5 A C (H3) C (X3) Nameplate H1 H3 Installed A (H1) X3 X0 B (H2) A (X1) X0 B (X2) H2 X1 X0 X2 X1 X2 X3 3.61@ /5 A 1443@0 A B C

16 Differentially balanced 1- phase test connections for a delta - grd wye transf (30 lag) Differential Relay 3.61@180 Relay Test Set Ia Ib Channel 1 Ic Ia Ib Channel 2 Ic Com

17 Differentially balanced 1- phase throughcurrent for a delta - grd wye transf (30 lead) Test Currents to Relay 2.5@ @0 115,000 13,800/7970 GY 20 MVA A B C 100@0 H3 H2 H1 N1/N2 = 115/8 200/5 A C (H1) A (X3) X0 C (X1) Nameplate H1 H3 Installed A (H3) X3 X0 B (H2) B (X2) H2 X1 X0 X2 X3 X2 X1 3.61@ /5 A 1443@0 A B C

18 Differentially balanced 1- phase test connections for a delta - grd wye transf (30 lead) Differential Relay 3.61@180 Relay Test Set Ia Ib Channel 1 Ic Ia Ib Channel 2 Ic Com

19 Slope characteristic tests Test currents calculated based on N1/N2 turns-ratio not voltage ratio 3 multiplier inherent No 0-seq filtering multiplier required Currents always 180 apart Test results clearly indicate if differential phase shift is set correctly

20 Differentially balanced through-current condition with correct phase shift setting

21 Differentially balanced through-current condition with incorrect phase shift setting

22 Slope verification with angle of winding 2 rolled until relay trips. S = 0.13/0.50 = 0.26 (26%)

23 Test connections for a 2 winding 30 degree lag delta-wye connection transformer Test ID Winding 1 (delta) connections Winding 2 (wye) connections A In on A & out on C A B In on B & out on A B C In on C & out on B C

24 Test connections for a 2 winding 30 degree lead delta-wye connection transformer Test ID Winding 1 (delta) connections Winding 2 (wye) connections A In on A & out on B A B In on B & out on C B C In on C & out on A C

25 Wake up. This is the interesting part

26 Transformer nameplate

27 3-line installation diagram - differentially balanced 1-phase load N1/N2 = 115/ A 1200/5 MR 300/5 Tap 0 A (H1) C (H3) B (H2) A (X1) C (X3) X0 B (X2) 1200/5 MR 1200/5 Tap A

28 Test definitions

29 Transformer nameplate

30 A B C 3-line installation diagram - differentially balanced 1-phase load A (H3) C (H1) B (H2) A (X3) X0 B (X2) C (X1) 600/5 MR 400/5 Tap 160 A 0 N1/N2 = 115/ /5 SR 2240 A

31 Test definitions

32 Transformer differential tripped on external feeder fault Caused by wrong angle setting Alternate method not used No load available at time of construction for inservice checks Using the alternate method might have prevented the trip

33 HV Winding 1 Differential Current LV Winding 2 Differential Current Waveform Capture

34 Traditional 3-phase testing method can be challenging Traditional 1-phase testing method does not simulate real-world loading Alternate 1-phase testing method simulates real-world and tests the settings against the installation

35

Verifying Transformer Differential Compensation Settings

Verifying Transformer Differential Compensation Settings Verifying Transformer Differential Compensation Settings Edsel Atienza and Marion Cooper Schweitzer Engineering Laboratories, Inc. Presented at the 6th International Conference on Large Power Transformers

More information

Rarely used, problems with unbalanced loads.

Rarely used, problems with unbalanced loads. THREE-PHASE TRANSFORMERS Transformers used in three-phase systems may consist of a bank of three single-phase transformers or a single three-phase transformer which is wound on a common magnetic core.

More information

Relay-assisted commissioning

Relay-assisted commissioning Relay-assisted commissioning by Casper Labuschagne and Normann Fischer, Schweitzer Engineering Laboratories (SEL) Power transformer differential relays were among the first protection relays to use digital

More information

PROTECTION OF TRANSFORMERS M-3311A TEST PLAN

PROTECTION OF TRANSFORMERS M-3311A TEST PLAN PROTECTION OF TRANSFORMERS M-3311A TEST PLAN Chuck Mozina -- is a Consultant, Protection and Protection Systems for Beckwith Electric and resides in Palm Harbor (near Tampa), Florida.. He is a Life Fellow

More information

Transformer Protection

Transformer Protection Transformer Protection Transformer Protection Outline Fuses Protection Example Overcurrent Protection Differential Relaying Current Matching Phase Shift Compensation Tap Changing Under Load Magnetizing

More information

Substation Testing and Commissioning: Power Transformer Through Fault Test

Substation Testing and Commissioning: Power Transformer Through Fault Test 1 Substation Testing and Commissioning: Power Transformer Through Fault Test M. Talebi, Member, IEEE, Power Grid Engineering Y. Unludag Electric Power System Abstract This paper reviews the advantage of

More information

Differential Protection with REF 542plus Feeder Terminal

Differential Protection with REF 542plus Feeder Terminal Differential Protection with REF 542plus Application and Setting Guide kansikuva_bw 1MRS 756281 Issued: 09.01.2007 Version: A Differential Protection with REF 542plus Application and Setting Guide Contents:

More information

Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller

Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer Anura Perera, Paul Keller System Operator - Eskom Transmission Introduction During the design phase of

More information

Fuseless Capacitor Bank Protection

Fuseless Capacitor Bank Protection Fuseless Bank Protection Minnesota Power Systems Conference St. Paul, MN. November 2, 1999 by: Tom Ernst, Minnesota Power Other Papers of Interest Presented at Western Protective Relay Conference, Oct.

More information

Hands On Relay School Open Lecture Transformer Differential Protection Scott Cooper

Hands On Relay School Open Lecture Transformer Differential Protection Scott Cooper Hands On Relay School Open Lecture Transformer Differential Protection Scott Cooper Transformer Differential Protection ntroduction: Transformer differential protection schemes are ubiquitous to almost

More information

DISTRIBUTION DEVICE COORDINATION

DISTRIBUTION DEVICE COORDINATION DISTRIBUTION DEVICE COORDINATION Kevin Damron & Calvin Howard Avista Utilities Presented March th, 08 At the 5 th Annual Hands-On Relay School Washington State University Pullman, Washington TABLE OF CONTENTS

More information

g GE POWER MANAGEMENT

g GE POWER MANAGEMENT 745 FREQUENTLY ASKED QUESTIONS 1 I get a communication error with the relay when I try to store a setpoint. This error can occur for several different reasons. First of all, verify that the address is

More information

IMPROVEMENTS IN PROTECTION AND COMMISSIONING OF DIGITAL TRANSFORMER RELAYS AT MEDIUM VOLTAGE INDUSTRIAL FACILITIES

IMPROVEMENTS IN PROTECTION AND COMMISSIONING OF DIGITAL TRANSFORMER RELAYS AT MEDIUM VOLTAGE INDUSTRIAL FACILITIES IMPOVEMENTS IN POTECTION AND COMMISSIONING OF DIGITAL TANSFOME ELAYS AT MEDIUM VOLTAGE INDUSTIAL FACILITIES Copyright Material IEEE Paper No. PCIC-AN84 Charles J. Mozina, P.E. Life Fellow Member, IEEE

More information

Power Measurements. Technology Consulting

Power Measurements. Technology Consulting Technology Consulting William H. Hardy, PhD 6386 Avington Place Gainesville, VA 20155 Cell: (865) 279-1090 www.powermeasurements.com Bill.Hardy@PowerMeasurements Metering US Services The US has the widest

More information

This webinar brought to you by the Relion product family Advanced protection and control IEDs from ABB

This webinar brought to you by the Relion product family Advanced protection and control IEDs from ABB This webinar brought to you by the Relion product family Advanced protection and control IEDs from ABB Relion. Thinking beyond the box. Designed to seamlessly consolidate functions, Relion relays are smarter,

More information

Hands On Relay School Open Lecture Transformer Differential Protection Scott Cooper

Hands On Relay School Open Lecture Transformer Differential Protection Scott Cooper Hands On Relay School Open Lecture Transformer Differential Protection Scott Cooper Transformer Differential Protection ntroduction: Transformer differential protection schemes are ubiquitous to almost

More information

Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC)

Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC) Name: Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC) 1. T F In three-phase four-wire delta systems rated 240/120 volts, sometimes

More information

Pinhook 500kV Transformer Neutral CT Saturation

Pinhook 500kV Transformer Neutral CT Saturation Russell W. Patterson Tennessee Valley Authority Presented to the 9th Annual Fault and Disturbance Analysis Conference May 1-2, 26 Abstract This paper discusses the saturation of a 5kV neutral CT upon energization

More information

Forward to the Basics: Selected Topics in Distribution Protection

Forward to the Basics: Selected Topics in Distribution Protection Forward to the Basics: Selected Topics in Distribution Protection Lee Underwood and David Costello Schweitzer Engineering Laboratories, Inc. Presented at the IEEE Rural Electric Power Conference Orlando,

More information

DIFFERENTIAL PROTECTION METHODOLOGY FOR ARBITRARY THREE-PHASE POWER TRANSFORMERS

DIFFERENTIAL PROTECTION METHODOLOGY FOR ARBITRARY THREE-PHASE POWER TRANSFORMERS DFFERENTAL PROTECTON METHODOLOGY FOR ARBTRARY THREE-PHASE POWER TRANSFORMERS Z. Gaji ABB AB-SA Products, Sweden; zoran.gajic@se.abb.com Keywords: power transformer, phase shifting transformer, converter

More information

Phase Shifting Transformers. Presented by

Phase Shifting Transformers. Presented by Phase Shifting Transformers Presented by Phase Shifting Transformers (PST s) (a.k.a. Phase Angle Regulators) VS φ S P V V S = X L L X L sin( φ φ ) L S VL φ L PST s are power flow control devices between

More information

EASUN REYROLLE LIMITED

EASUN REYROLLE LIMITED OCTOBER 2003 APPLICATION AND COMMISSIONING MANUAL FOR NUMERICAL BIASED DIFFERENTIAL PROTECTION RELAY TYPE - MIB202 EASUN REYROLLE LIMITED 1 ISSUE NO : 1 st Issue DATE OF ISSUE : 01-10 - 2003 DEPARTMENT

More information

NEW DESIGN OF GROUND FAULT PROTECTION

NEW DESIGN OF GROUND FAULT PROTECTION NEW DESIGN OF GROUND FAULT PROTECTION J. Blumschein*, Y. Yelgin* *SIEMENS AG, Germany, email: joerg.blumschein@siemens.com Keywords: Ground fault protection, directional element, faulted phase selection

More information

Tutorial on Symmetrical Components

Tutorial on Symmetrical Components Tutorial on Symmetrical Components Part : Examples Ariana Amberg and Alex Rangel, Schweitzer Engineering Laboratories, nc. Abstract Symmetrical components and the per-unit system are two of the most fundamental

More information

Impact of Incipient Faults on Sensitive Protection

Impact of Incipient Faults on Sensitive Protection Impact of Incipient Faults on Sensitive Protection Paper Authors: Ilia Voloh GE Grid Solutions Zhihan Xu, Ilia Voloh GE Grid Solutions Leonardo Torelli CSE-Uniserve Presented by: Tom Ernst GE Grid Solutions

More information

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved.

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved. Pomona, CA, May 24 & 25, 2016 Tertiary Winding Design in wye-wye Connected Transformers Scope of Presentation > Tertiary vs. Stabilizing Winding? Tertiary vs. Stabilizing Winding? Need for Stabilizing

More information

Transformer Protection Principles

Transformer Protection Principles Transformer Protection Principles 1. Introduction Transformers are a critical and expensive component of the power system. Due to the long lead time for repair of and replacement of transformers, a major

More information

Overcurrent Elements

Overcurrent Elements Exercise Objectives Hands-On Relay Testing Session Overcurrent Elements After completing this exercise, you should be able to do the following: Identify overcurrent element settings. Determine effective

More information

Considerations and Experiences in Implementing Ground Differential Protection for Transformer Protection at TVA

Considerations and Experiences in Implementing Ground Differential Protection for Transformer Protection at TVA Considerations and Experiences in Implementing Ground Differential Protection for Transformer Protection at TVA Meyer Kao - Consultant, Gary Kobet - Tennessee Valley Authority George Pitts -Tennessee Valley

More information

Testing Numerical Transformer Differential Relays

Testing Numerical Transformer Differential Relays Feature Testing Numerical Transformer Differential Relays Steve Turner Beckwith Electric Co., nc. ntroduction Numerical transformer differential relays require careful consideration as to how to test properly.

More information

Using a Multiple Analog Input Distance Relay as a DFR

Using a Multiple Analog Input Distance Relay as a DFR Using a Multiple Analog Input Distance Relay as a DFR Dennis Denison Senior Transmission Specialist Entergy Rich Hunt, M.S., P.E. Senior Field Application Engineer NxtPhase T&D Corporation Presented at

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS

STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS 1 STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS Z. GAJIĆ S. HOLST D. BONMANN D. BAARS ABB AB, SA Products ABB AB, SA Products ABB AG, Transformers ELEQ bv Sweden Sweden Germany Netherlands zoran.gajic@se.abb.com

More information

REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD.

REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD. REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD. (DTL) 1.0 Introduction: 1.1 DTL vide letter No. F.DTL/206/2015-16/Mgr(T)O&M-E-2/22

More information

Three Phase Transformers

Three Phase Transformers Three Phase Transformers Theory and Calculations 8/29/2016 Copyright 2016 Dan Dudley & Associates Page 1 DELTA Transformer 8/29/2016 Copyright 2016 Dan Dudley & Associates Page 2 WYE Transformer 8/29/2016

More information

DISTRIBUTION SYSTEM VOLTAGE SAGS: INTERACTION WITH MOTOR AND DRIVE LOADS

DISTRIBUTION SYSTEM VOLTAGE SAGS: INTERACTION WITH MOTOR AND DRIVE LOADS DISTRIBUTION SYSTEM VOLTAGE SAGS: INTERACTION WITH MOTOR AND DRIVE LOADS Le Tang, Jeff Lamoree, Mark McGranaghan Members, IEEE Electrotek Concepts, Inc. Knoxville, Tennessee Abstract - Several papers have

More information

Transformer Fault Categories

Transformer Fault Categories Transformer Fault Categories 1. Winding and terminal faults 2. Sustained or uncleared external faults 3. Abnormal operating conditions such as overload, overvoltage and overfluxing 4. Core faults 1 (1)

More information

MV network design & devices selection EXERCISE BOOK

MV network design & devices selection EXERCISE BOOK MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester

More information

Chapter 7 Conclusion 7.1 General

Chapter 7 Conclusion 7.1 General Chapter 7 7.1 General The mechanical integrity of a transformer winding is challenged by several mechanisms. Many dielectric failures in transformers are direct results of reduced mechanical strength due

More information

Catastrophic Relay Misoperations and Successful Relay Operation

Catastrophic Relay Misoperations and Successful Relay Operation Catastrophic Relay Misoperations and Successful Relay Operation Steve Turner (Beckwith Electric Co., Inc.) Introduction This paper provides detailed technical analysis of several catastrophic relay misoperations

More information

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES COMPANY OVERVIEW EPS is a recognised company specialising in Electrical, Instrumentation, Structural, Mechanical and

More information

Back to the Basics Current Transformer (CT) Testing

Back to the Basics Current Transformer (CT) Testing Back to the Basics Current Transformer (CT) Testing As test equipment becomes more sophisticated with better features and accuracy, we risk turning our field personnel into test set operators instead of

More information

Need for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design

Need for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design IEEE PES Transmission and Distribution Conference 2008 Panel Session Large Wind Plant Collector Design Wind Farm Collector System Grounding by Steven W. Saylors, P.E. Chief Electrical Engineer Vestas Americas

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

Bus Protection Fundamentals

Bus Protection Fundamentals Bus Protection Fundamentals Terrence Smith GE Grid Solutions 2017 Texas A&M Protective Relay Conference Bus Protection Requirements High bus fault currents due to large number of circuits connected: CT

More information

Impact Assessment Generator Form

Impact Assessment Generator Form Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project

More information

Problems connected with Commissioning of Power Transformers

Problems connected with Commissioning of Power Transformers Problems connected with Commissioning of Power Transformers ABSTRACT P Ramachandran ABB India Ltd, Vadodara, India While commissioning large Power Transformers, certain abnormal phenomena were noticed.

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

7SG14 Duobias-M Transformer Protection

7SG14 Duobias-M Transformer Protection 7SG14 Duobias-M Transformer Protection Document Release History This document is issue 2010/02. The list of revisions up to and including this issue is: Pre release Revision Date Change 2010/02 Document

More information

Extensive LV cable network. Figure 1: Simplified SLD of the transformer and associated LV network

Extensive LV cable network. Figure 1: Simplified SLD of the transformer and associated LV network Copyright 2017 ABB. All rights reserved. 1. Introduction Many distribution networks around the world have limited earth-fault current by a resistor located in the LV winding neutral point of for example

More information

Unit Protection Differential Relays

Unit Protection Differential Relays Unit Protection PROF. SHAHRAM MONTASER KOUHSARI Current, pu Current, pu Protection Relays - BASICS Note on CT polarity dots Through-current: must not operate Internal fault: must operate The CT currents

More information

MODELING OF TRANSFORMERS IN WECC BASE CASES. For WECC SRWG By Rohan Chatterjee Electrical Engineer Transmission Planning

MODELING OF TRANSFORMERS IN WECC BASE CASES. For WECC SRWG By Rohan Chatterjee Electrical Engineer Transmission Planning MODELING OF TRANSFORMERS IN WECC BASE CASES For WECC SRWG By Rohan Chatterjee Electrical Engineer Transmission Planning rohan.chatterjee@pgn.com Present Utility Practices Problems with present practices

More information

Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL)

Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL) Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL) 1.0 Introduction: 1.1 DTL vide letter No. F.DTL/206/F.06/2015-16/Mgr(Bawana)/353 dated

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Power System Protection. Dr. Lionel R. Orama Exclusa, PE Week 3

Power System Protection. Dr. Lionel R. Orama Exclusa, PE Week 3 Power System Protection Dr. Lionel R. Orama Exclusa, PE Week 3 Operating Principles: Electromagnetic Attraction Relays Readings-Mason Chapters & 3 Operating quantities Electromagnetic attraction Response

More information

Protective Relays Digitrip 3000

Protective Relays Digitrip 3000 New Information Technical Data Effective: May 1999 Page 1 Applications Provides reliable 3-phase and ground overcurrent protection for all voltage levels. Primary feeder circuit protection Primary transformer

More information

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES 3.1. Introduction Power Transformer is the nerve centre of any power distribution system. The capacity of power transformers is generally decided

More information

EE188: Transformer Design, Construction, Testing & Maintenance

EE188: Transformer Design, Construction, Testing & Maintenance EE188: Transformer Design, Construction, Testing & Maintenance EE188 Rev.001 CMCT COURSE OUTLINE Page 1 of 5 Training Description: This intensive training covers the design, theory, operation, maintenance

More information

Event Analysis Tutorial

Event Analysis Tutorial 1 Event Analysis Tutorial Part 1: Problem Statements David Costello, Schweitzer Engineering Laboratories, Inc. Abstract Event reports have been an invaluable feature in microprocessor-based relays since

More information

Differential Protection Optimal differential protection for phase shifter transformers and special transformers

Differential Protection Optimal differential protection for phase shifter transformers and special transformers Differential Protection Optimal differential protection for phase shifter transformers and special transformers Due to the energy transition, a demand for renewable energy sources integration into power

More information

Electrical Systems - Course 135 COMPOSITE ELECTRICAL PROTECTIVE SCHEMES: PART I

Electrical Systems - Course 135 COMPOSITE ELECTRICAL PROTECTIVE SCHEMES: PART I Electrical Systems - Course 135 COMPOSTE ELECTRCAL PROTECTVE SCHEMES: PART BUSES AND TRANSFORMERS L.0 ntroducton Following on from lesson 135.03-1, this lesson shows componte protective schemes for buses

More information

Modelling Parameters. Affect on DER Impact Study Results

Modelling Parameters. Affect on DER Impact Study Results Modelling Parameters Affect on DER Impact Study Results Agenda Distributed Energy Resources (DER) Impact Studies DER Challenge Study Steps Lessons Learned Modeling Reverse Power Transformer Configuration

More information

एस.आर.प.स 40व प र ट क शनउप सम त क ब ठकक मऱएएज ड Additional Agenda Points for 40 th meeting of Protection Sub-Committee of SRPC

एस.आर.प.स 40व प र ट क शनउप सम त क ब ठकक मऱएएज ड Additional Agenda Points for 40 th meeting of Protection Sub-Committee of SRPC ANNEXURE I एस.आर.प.स 40व प र ट क शनउप सम त क ब ठकक मऱएएज ड Additional Agenda Points for 40 th meeting of Protection Sub-Committee of SRPC 1. ग र डडडस टबबन स / ग र डइन सडन टक वववरण - Details of Grid incidents:

More information

Power System Protection Part VII Dr.Prof.Mohammed Tawfeeq Al-Zuhairi. Differential Protection (Unit protection)

Power System Protection Part VII Dr.Prof.Mohammed Tawfeeq Al-Zuhairi. Differential Protection (Unit protection) Differential Protection (Unit protection) Differential Protection Differential protection is the best technique in protection. In this type of protection the electrical quantities entering and leaving

More information

INSTRUCTION MANUAL TRANSFORMER PROTECTION RELAY GRT100 - B

INSTRUCTION MANUAL TRANSFORMER PROTECTION RELAY GRT100 - B INSTRUCTION MANUAL TRANSFORMER PROTECTION RELAY GRT00 - B Toshiba Energy Systems & Solutions Corporation 207 All Rights Reserved. ( Ver. 3.) Safety Precautions Before using this product, be sure to read

More information

Benefits of SFRA - Case Studies

Benefits of SFRA - Case Studies 6 th International Conference on Large Power Transformers- Modern Trends Benefits of SFRA - Case Studies B B Ahir Gujarat Energy Transmission Corporation Limited 1 Outline Condition Monitoring in GETCO

More information

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES U AJMAL, GE Grid Solutions UK Ltd, usman.ajmal@ge.com S SUBRAMANIAN, GE Grid Solutions UK Ltd, sankara.subramanian@ge.com H Ha GE Grid Solutions

More information

Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security

Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security Steve Turner Senior Application Engineer Beckwith Electric Company Introduction Summarize conclusions from NERC

More information

GENERALS ELECTRIC INSTRUCTIONS POWER SYSTEMS MANAGEMENT DEPARTMENT PHILADELPHIA, PA. GEK Insert Booklet GEK RESTRAINT CIRCUITS

GENERALS ELECTRIC INSTRUCTIONS POWER SYSTEMS MANAGEMENT DEPARTMENT PHILADELPHIA, PA. GEK Insert Booklet GEK RESTRAINT CIRCUITS PHILADELPHIA, PA. TYPE STD29C GENERALS ELECTRIC POWER SYSTEMS MANAGEMENT DEPARTMENT 6 RESTRAINT CIRCUITS WITH PERCENTAGE AND HARMONIC RESTRAiNT TRANSFORMER DIFFERENTIAL RELAY GEK 45316 Insert Booklet GEK-45307

More information

Multi Differential Relay, MDR-2 DESCRIPTION OF OPTIONS

Multi Differential Relay, MDR-2 DESCRIPTION OF OPTIONS Multi Differential Relay, MDR-2 DESCRIPTION OF OPTIONS Option C4 Block differential current protection Description of option Functional descriptions Parameter list Document no.: 4189340397C SW version:

More information

MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE

MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE Scott Storrar Contributors: Bill Hansen, Kyle Reddell, Tom McGrath Basic Mobile Sub Design Equipment mounted on semi-trailer Power transformer

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

IVE(TY) Department of Engineering. Electrical Machines 1. Electrical Machines 1. Hour 13. slide 1

IVE(TY) Department of Engineering. Electrical Machines 1. Electrical Machines 1. Hour 13. slide 1 Hour 3 slide Three Phase Transformer (sect. 2.6) A set of three similar single phase transformers may be connected to form a three-phase transformer (three-phase transformer bank). The primary and secondary

More information

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Cork Institute of Technology Bachelor of Science (Honours) in Electrical Power Systems - Award Instructions Answer FIVE questions. (EELPS_8_Y4) Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Examiners:

More information

Overcurrent and Overload Protection of AC Machines and Power Transformers

Overcurrent and Overload Protection of AC Machines and Power Transformers Exercise 2 Overcurrent and Overload Protection of AC Machines and Power Transformers EXERCISE OBJECTIVE When you have completed this exercise, you will understand the relationship between the power rating

More information

Transformer Factory Testing

Transformer Factory Testing Transformer Factory Testing John J. Foschia Test Engineer John.Foschia@spx.com September 2018 Reasons for Testing Compliance with user specifications Assessment of quality and reliability Verification

More information

ELECTRICAL POWER TRANSMISSION TRAINER

ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER This training system has been designed to provide the students with a fully comprehensive knowledge in Electrical Power Engineering

More information

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Charles Sweetser, Services Manager, PRIM Engineering, Waltham, Mass. Topics of Discussion

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS Juan Manuel Gers, PhD Example - Single Line Example 1 - Data Calculate the following: 1. The three phase short circuit levels on busbars

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

148 Electric Machines

148 Electric Machines 148 Electric Machines 3.1 The emf per turn for a single-phase 2200/220- V, 50-Hz transformer is approximately 12 V. Calculate (a) the number of primary and secondary turns, and (b) the net cross-sectional

More information

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch.

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch. Training Title POWER TRANSFORMERS Training Duration 5 days Training Venue and Dates Power transformers 5 20-24 May $3,300 Abu Dhabi In any of the 5 star hotel. The exact venue will be informed soon. Training

More information

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis feature By brandon dupuis An Introduction to Electrical diagnostic TesTIng of Power Transformers 38 Transformers are the largest, most expensive, and highly critical components of most utility substations.

More information

XD1-T - Transformer differential protection relay

XD1-T - Transformer differential protection relay XD1-T - Transformer differential protection relay Contents 1. Application and features 2. Design 3. Characteristics 3.1 Operating principle of the differential protection 3.2 Balancing of phases and current

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS Juan Manuel Gers, PhD Protection coordination principles Relay coordination is the process of selecting settings that will assure that the relays

More information

thepower to protect the power to protect i-gard LITERATURE Low and medium voltage

thepower to protect  the power to protect i-gard LITERATURE Low and medium voltage thepower to protect i-gard LITERATURE Low and medium voltage distribution systems Arc Flash Hazards and High Resistance Grounding Grounding of Standby and Emergency Power Systems Neutral Grounding Resistors

More information

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser - OMICRON Transformers Diagnostic Testing - OVERALL DGA Oil Screen Power Factor / Capacitance Exciting Current Transformer

More information

XD1-T Transformer differential protection relay. Manual XD1-T (Revision A)

XD1-T Transformer differential protection relay. Manual XD1-T (Revision A) XD1-T Transformer differential protection relay Manual XD1-T (Revision A) Woodward Manual XD1-T GB Woodward Governor Company reserves the right to update any portion of this publication at any time. Information

More information

POWER TRANSFORMER. Failure Analysis & Troubleshooting. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

POWER TRANSFORMER. Failure Analysis & Troubleshooting. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E POWER TRANSFORMER Failure Analysis & Troubleshooting H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae ictd@ictd.ae Course Introduction: Electricity is high-grade energy. Working

More information

Transformer Protection

Transformer Protection 1 Presenter Contact Info Wayne Hartmann Senior VP, Customer Excellence Beckwith Electric Company whartmann@beckwithelectric.com 904 238 3844 Wayne is the top strategist for delivering innovative technology

More information

INSTRUCTIONS. GE Protection and Control. 205 Great Valley Parkway Malvern, PA GE K-45307K TRANSFORMER DIFFERENTIAL RELAYS WITH

INSTRUCTIONS. GE Protection and Control. 205 Great Valley Parkway Malvern, PA GE K-45307K TRANSFORMER DIFFERENTIAL RELAYS WITH INSTRUCTIONS 205 Great Valley Parkway Malvern, PA 19355-1337 GE Protection and Control GE K-45307K TRANSFORMER DIFFERENTIAL RELAYS WITH PERCENTAGE AN!) HARMONIC RESTRAINT TYPES STD15C and STD16C I Determination

More information

Solution for Effect of Zero Sequence Currents on Y-Y Transformer Differential Protection

Solution for Effect of Zero Sequence Currents on Y-Y Transformer Differential Protection ABSTRACT National conference on Engineering Innovations and Solutions (NCEIS 2018) International Journal of Scientific Research in Computer Science, Engineering and Information Technology 2018 IJSRCSEIT

More information

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length

More information

Hamdy Faramawy Senior Application Specialist ABB Sweden

Hamdy Faramawy Senior Application Specialist ABB Sweden Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy

More information

ELECTROTECHNOLOGY ELTK1200 ASSIGNMENT #8 SOLUTIONS

ELECTROTECHNOLOGY ELTK1200 ASSIGNMENT #8 SOLUTIONS ELECTROTECHNOLOGY ELTK1200 ASSIGNMENT #8 SOLUTIONS 1. 2. 3. Full-load: This has not changed. 187 a Full-load Load is a of Full-load, current will be a of Full-load current (voltage is the same). Fe loss

More information

Chapter 1 Electrical Theory and Part C Series Parallel and Code Questions Multiwire Branch Circuits Unit 1 Electrician s Math

Chapter 1 Electrical Theory and Part C Series Parallel and Code Questions Multiwire Branch Circuits Unit 1 Electrician s Math Chapter 1 Electrical Theory and Code Questions 1 Unit 1 Electrician s Math and Basic Electrical Formulas 3 Part A Electrician s Math 3 1 1 Fractions 3 1 2 Kilo 4 1 3 Knowing Your Answer 4 1 4 Multiplier

More information

Tap Changer Analyzer & Winding Ohmmeter RMO60TD

Tap Changer Analyzer & Winding Ohmmeter RMO60TD Tap Changer Analyzer & Winding Ohmmeter RMO60TD Test current 5 ma 60 A DC Rapid automatic demagnetization AC Current monitoring channel Lightweight 13 kg Measuring range 0,1-2 k Two voltage sense channels

More information

3-Phase Transformers. Author: Sergey Dubatov. belfuse.com/signal

3-Phase Transformers. Author: Sergey Dubatov. belfuse.com/signal 3-Phase Transformers Author: Sergey Dubatov 2 A transformer is an electrical device which, by electromagnetic induction, transforms power between circuits at the same frequency, usually changing the values

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

Christopher Substation

Christopher Substation Lessons Learned Relay work is hard and stressful, somedays you are the hero.other days you are the goat. Here are some true stories from the field that demonstrate some hero, but mostly goat. Lessons Learned

More information