MV network design & devices selection EXERCISE BOOK
|
|
- Cornelius Atkinson
- 5 years ago
- Views:
Transcription
1 MV network design & devices selection EXERCISE BOOK
2 EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C MV substation 04 - Max. distance between surge arrester and MV equipment 05 - Calculation of MV cable cross-section 06 - Calculation of Isc 07 - CTs for MV metering 08 - CTs for MV protection 09 - Earth-fault relay settings 10 - Capacitors MV network design & devices selection - Aug
3 Exercise 1: MV substation architectures Define: 1. Type of LV or MV metering 2. Architecture and choice of cubicles 3. Type and rating of fuse that protects the transformer Consumer substation on energy supplier loop: 20kV 1 800kVA transformer with 20kV/400V secondary Short-circuit power 250 MVA MV network design & devices selection - Aug
4 Exercise 2: MV substation architectures Define: 1. Type of LV or MV metering 2. Architecture and choice of cubicles Consumer substation on energy supplier loop: 15kV 2500kVA transformer with 400V secondary, 3-phase Short-circuit power 350 MVA MV network design & devices selection - Aug
5 Exercise 3: C MV substation Use the data below to define: 1. the flow diagram of the MV part of the installation 2. the subtransmission substation diagram, indicating: types of cubicles fuse ratings An industrial MV consumer is supplied directly with 20kV (24KV, 125kV impulse; Isc = 12.5kA) The power distribution system is a loop. In case of interruption, a radial feeder powers the entire installation (the system must automatically switch back to the loop if power is restored to the loop) The plant includes 1 B1 2000kVA non-priority loop supplying different substations 1 T1 250kVA non-priority transformer 1 B2 2000kVA priority loop 1 T2 800kVA priority transformer The plant also has a 380V/20kV diesel genset to back up priority loads. MV network design & devices selection - Aug
6 Exercise 4: Max. distance between surge arrester and MV equipment (optional, for information purposes) Max. distance between transformer MV terminals and surge arrester? 20KV transformer protected by MV surge arrester Residual voltage of surge arrester 75KV D in m MV network design & devices selection - Aug
7 Exercise 5: Calculation of MV cable cross-section 1 Us rated operating voltage 15 kv 2 Type of insulating material PR 3 Type of conductor ALU 4 Type of cable (single or 3-wire) 3 5 Ir rated operating current 210 A 6 Operating state (discontinuous or continuous) DISC 7 Installation method column 1or2 K1 Buried 8 Ambiant temperature on ground K2 25 C 9 Type of ground K3 Damp 10 Proximity K4 Alone 11 Isc upstream 18 ka 12 Tripping time 0.4 MV network design & devices selection - Aug
8 Exercise 5 Verification Formula to be used to verify the thermal withstand of cables in case of short-circuit Isc S = k t Isc = in Amperes t = in seconds k = factor for type of cable S = cross-section in mm 2 MV network design & devices selection - Aug
9 Exercise 6: Calculation of Isc Calculation of short-circuit currents in a MV network Questions 1. Determine the breaking capacity of circuit breakers CB1 to CB7 2. Determine the minimum cross-section of cables linking substations A-B and A-C, given that only one transformer is supplied in each substation 3. Determine the breaking capacity and making capacity of circuit breakers CB8 to CB11 Data Power supply: 63kV Short-circuit power: 2000MVA Network impedance 63kV (can be calculated directly for 10kV) Network configuration: The network includes 2 transformers and 1 AC generator in parallel Each of the satellite substations includes 2 transformers, but a single transformer is sufficient to power the loads We find the Isc from the network «upstream with the 2 transformers in parallel» and add the Isc from the AC generator The (PR)ALU cables are buried directly in dry calcareous ground at 20 C, with nothing nearby For substation B, provision should be made for 2 cables in parallel 9
10 Upstream network 63kV Short-circuit power 2000 MVA calculation of Isc 15 MVA Usc =10% T1 T2 G1 20 MVA Usc =10% G 15 MVA Usc Sub =15% Usc Trans= 20% CB1 D2 CB3 10KV busbar 10KV busbar 10KV busbar Substation A CB4 CB5 CB6 CB7 15 MVA Usc=10% T4 T5 15 MVA Usc=10% In each substation 1 single transformer in operation 0.5 km Substation C CB18 3KV CB19 CB8 1 km Substation B CB9 CB10 T8 5 MVA CB11 T9 5 MVA 10 MVA T6 CB12 T7 CB13 10 MVA CB16 3KV CB17 3KV 10
11 Location or observation point R X Z Isc BC MC = BC*2.5 Upstream network, downstream view 15 MVA TR 20 MVA TR 2 TRs and 15 MVA genset in parallel TRs in series with network 15 MVA genset in subtransient 15 MVA genset in transient Values at busbar in transient Values at busbar in subtransient Cable of substation B Busbar input, substation B, transient Busbar input, substation B, subtrans. Upstream, downstream view, substation B, subtransient 10 MVA TR substation B Series upstream network + TR10 sub. Series upstream network + TR10 trans. Reminders: Resistivity of copper: ρ = Ω. mm 2 /m Resistivity of aluminium: ρ = Ω. mm 2 /m 11
12 Calculation of short-circuit currents Upstream network impedances: Impedance viewed downstream of transformers: 10 KV Short-circuit power = 2000 MVA Application of relative impedance formula: 15 MVA transformer impedance 15 MVA 20MVA transformer impedance 20 MVA 12
13 15 MVA genset impedance 1 - Transient (Usc = 20%) 15 MVA G 2 - Subtransient (Usc = 15%) Impedance of 2 transformers in parallel Impedance of 2 transfos in // + network in series T1 Upstream network 63KV Short-circuit power 2000 MVA T2 CB1 CB2 Substation A 13
14 Upstream network 63KV Short-circuit power 2000 MVA 15 MVA Usc =10% T1 T2 G1 20 MVA Usc =10% G 15 MVA Usc Sub =15% Usc Trans= 20% 10KV busbar CB1 CB2 D3 Substation A 10KV busbar 10KV busbar CB4 CB5 CB6 CB7 Impedance of 2 transfos // + network + genset 1 - transient (Usc = 20%) 2 - subtransient (Usc = 15%) 14
15 Calculation of Isc, breaking capacity and making capacity Breaking capacity of circuit breakers CB4 to CB7 (transient) Making capacity of CB4 to CB7 as asymmetrical peak kâ (2.5) and subtransient Breaking capacity of CB3 (genset circuit breaker) Making capacity of CB3 as peak kâ (genset circuit breaker) 15
16 Breaking capacity of CB1 (15 MVA transformer) (Ik3 to be considered = Ik3 20 MVA transf. + Ik3 genset transf.) Impedance of upstream network + 20 MVA transformer Parallel connection network + transformer and genset in transient Making capacity of CB1 (15 MVA transfomer) Parallel connection network + transformer and genset in subtransient Making capacity of CB1 as peak kâ (15 MVA transformer circuit breaker) 16
17 Upstream network 63KV Short-circuit power 2000 MVA Example for comparison 15 MVA Usc =10% T1 T2 G1 20 MVA Usc =10% G 15 MVA Usc Sub =15% Usc Trans= 20% 10KV busbar CB1 CB2 CB3 10KV busbar 10KV busbar Substation A CB4 CB5 CB6 CB7 Breaking capacity of CB2 (20 MVA transformer) Impedance of network + 15 MVA transformer T1 Parallel connection network + transformer and genset in transient Making capacity of CB2 (20 MVA transformer) Parallel connection network + transformer and genset in subtransient Making capacity of CB2 as peak kâ (20 MVA transformer circuit breaker) 17
18 Simplified version of calculations for substation A Direct calculation of impedance Z and cumulative total of resulting Ik3 Impedance of upstream network Upstream network 63KV Short-circuit power 2000 MVA Impedance of 15 and 20 MVA transformer in // Impedance of network + 2 TR in // Ik3 of network + TR in // T1 CB1 T2 CB2 Impedance of network + T1 Substation A Impedance of network + T2 Ik3 supplied by (network + T1) Ik3 supplied by (network + T2) 18
19 GE current Isc GE transient Isc GE subtransient Breaking capacity of CB1 (15 MVA transformer circuit breaker): Breaking capacity of CB2 (20 MVA transformer circuit breaker): Making capacity of CB1 (15 MVA transformer circuit breaker): Making capacity of CB2 (20 MVA transformer circuit breaker): Breaking capacity CB4 to CB7 (global Ik3): (network + 2 TR + GE) Making capacity CB4 to CB7: (network + 2 TR + GE) 19
20 Choice of cables for substations B and C (detailed method) Single-pole AI PR cables, buried directly in dry, calcareous ground, temperature 20 C, continuous operation, Substation B: Operational current Ir: Substation A 10KV busbar CB6 1 km Substation B 2 cables in // imposed Installation mode factor = Temperature factor = Proximity factor = Ground factor = Chosen theoretical currents: CB8 T6 10 MVA CB12 3KV CB9 T7 10 MVA CB13 Substation C: Operational current Ir: Installation mode factor = Temperature factor = Proximity factor = Ground factor = Chosen theoretical currents: cables to substation C: per phase Substation A CB10 T8 5 MVA CB16 CB7 0,5 km Substation C 10KV busbar CB11 T9 5 MVA CB17 3KV 20
21 Verification of short-circuit current withstand of cables Upstream protection circuit breaker tripping time: 0.4 sec. Permissible temperature rise in cables: 160 (+90 =250 ) Calculation of short-circuit currents in substations B and C Impedance of the 2 cables of substation B Impedance of the cable of substation C 21
22 Short-circuit currents with 10 kv in substation B Calculation of impedance in substation B, transient. Substation A 10KV busbar CB6 short-circuit current and breaking capacity CB8 and CB9: 1 km Substation B Calculation of impedance in substation B, subtransient. CB8 T6 10 MVA CB12 CB9 T7 10 MVA CB13 short-circuit current and making capacity CB8 and CB9: 3KV 22
23 Short-circuit currents with 10 kv in substation C Calculation of impedance in substation C, transient, 185 mm 2 cable Substation A 10KV busbar CB7 0.5 km Substation C short-circuit current and breaking capacity CB10 and CB11: Calculation of impedance in substation C, subtransient. CB10 T8 5 MVA CB16 CB11 T9 5 MVA CB17 3KV short-circuit current and making capacity CB10 and CB11: 23
24 Calculation of short-circuit currents with 3 kv in substation B Reminder of values with 10 kv in substation B: - Transient Substation A 10KV busbar CB6 - Subtransient: Application of relative impedance formula: R (downstream) = R (upstream) 1) Impedance, Ik3 and breaking capacity in transient U U 2 2 (secondary) (primary) CB8 T6 10 MVA 1 km Substation B CB9 T7 10 MVA Impedance of transformer CB12 CB13 Isc and breaking capacity of CB12 and CB13 3KV 2) Impedance,I k3 and making capcity in subtransient Isc and making capacity of CB12 and CB13 24
25 Calculation of short-circuit currents with 3 kv in substation C Reminder of values with 10 kv in substation C: - Transient 10KV busbar CB7 - Subtransient: Application of relative impedance formula: 0.5 km Substation C U R (downstream) = R (upstream) U 1) Impedance, Ik3 and breaking capacity in transient 2 2 (secondary) (primary) CB10 T8 5 MVA CB16 CB11 T9 5 MVA CB17 Impedance of transformer 3KV Isc and breaking capacity of CB16 and CB17 2) Impedance, Isc and making capacity in subtransient Isc and making capacity of CB16 and CB17 25
26 Exercise 7: CTs for MV metering Determine the characteristics of the CT to be used according to the following data: U= 5.5 KV Predicted active power P = 760 KW p.f. = 0.93 Isc 8.5 KA Power consumed by meter 2.5 VA Meter input 5A CT line < > meter = 20m (total 2 ways) in 6mm² 26
27 Exercise 8: CTs for MV protection Definition of CTs? U= 6 KV Large motor feeder 2500 KW p.f. 0.9 efficiency 0.94 Starting current 6 x In Isc 8.5 KA Power consumed by protection relay 1.8 VA Relay input 5A Line 42m (total 2 ways) in 6mm² 27
28 Exercise 9: Earth-fault relay settings 1. Position the earth fault protection devices in the diagram so as to have discrimination. 2. Calculate the capacitive currents generated when faults occur. 3. The protection setting range starts at 2 A To what should IL be limited by the earth fault resistance in order to protect 90% of the star winding of the motor or motors? 3.2. is the value compatible with: 2.Ic<IL? 3.3. what is the continuous permissible current for the earth fault resistance (zero-sequence generator)? 3.4. if the protection of motor 9.2 does not work: - what back-up protection is there? - what is its pick-up setting? - what happens with the earth fault resistance? (zero-sequence generator) 3.5. what are the settings for the zero-sequence generator? 4. Length of the double 9.2 power supply cable - can 90% of the motor winding still be protected? - what solutions do you propose? - case of delta motor? 28
29 Capacitive current of connections upon network earth fault Conn. Cable Nb. of cables Length Linear capacity Ic in // per phase km µf/km A 1 1* ,5 2 1* * * * * * * * * * Ic = 3 V C n L ω TOTAL Operating voltage U=5.5 kv L = length of trunking in km n = number of cables in // per phase V = ph-to-neutral voltage in V C = linear capacity of cable in F/km ω = pulsation in rad/s 29
30 Earth-fault relay settings G Gh 1 X X 2 RGh X X X 6 X 7 X 8 X 9 X 9.1 X 9.2 M M M M M 30
31 Exercise 10: Capacitors A transfomer with power = 630 kva (410 V) supplies a load with active power P 1 = 250 kw with an average p.f. of There is a plan to double the installation and this will call for additional active power P 2 : 250 kw with p.f. = QUESTIONS: 1) Without power factor correction, determine the apparent power at the transformer terminals. What do you notice? 2) Calculate the maximum reactive power that the 630 kva transformer can supply for this project. 3) Calculate the total active power to be supplied to the load before power factor correction. 4) Determine the minimum power of the capacitor bank to be installed. 5) What is the p.f. value (transformer load 100%) 6) A decision is made to raise the p.f. to What is the minimum power of the capacitor bank to be installed? 7) Determine the rating of the circuit breaker to be installed. 31
3-phase short-circuit current (Isc) at any point within a LV installation
3-phase short-circuit current (Isc) at any point within a LV installation In a 3-phase installation Isc at any point is given by: where U 20 = phase-to-phase voltage of the open circuited secondary windings
More informationThree-phase short-circuit current (Isc) calculation at any point within a LV installation using impedance method
Three-phase short-circuit current (Isc) calculation at any point within a LV installation using impedance method Calculation of Isc by the impedance method In a 3-phase installation Isc at any point is
More informationTABLE OF CONTENT
Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES
More informationImpact Assessment Generator Form
Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project
More informationPOWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS
POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS Juan Manuel Gers, PhD Protection coordination principles Relay coordination is the process of selecting settings that will assure that the relays
More informationELECTRICAL POWER TRANSMISSION TRAINER
ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER This training system has been designed to provide the students with a fully comprehensive knowledge in Electrical Power Engineering
More informationBE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %
BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and
More information, ,54 A
AEB5EN2 Ground fault Example Power line 22 kv has the partial capacity to the ground 4,3.0 F/km. Decide whether ground fault currents compensation is required if the line length is 30 km. We calculate
More informationEarth Fault Protection
Earth Fault Protection Course No: E03-038 Credit: 3 PDH Velimir Lackovic, Char. Eng. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877) 322-4774
More informationProtection of Electrical Networks. Christophe Prévé
Protection of Electrical Networks Christophe Prévé This Page Intentionally Left Blank Protection of Electrical Networks This Page Intentionally Left Blank Protection of Electrical Networks Christophe Prévé
More informationPOWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS
POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS Juan Manuel Gers, PhD Example - Single Line Example 1 - Data Calculate the following: 1. The three phase short circuit levels on busbars
More informationET 51 - Electrician Theory Examination Marking Schedule
ET 51 - Electrician Theory Examination Marking Schedule Notes:1. means that the preceding statement/answer earns 1 mark. 2. This schedule sets out the accepted answers to the examination questions. A marker
More informationChapter G Sizing and protection of conductors
Chapter G Sizing and protection of conductors 1 2 3 4 5 6 7 8 Contents General 1.1 Methodology and definition G2 1.2 Overcurrent protection principles G4 1.3 Practical values for a protective scheme G4
More informationNotes 1: Introduction to Distribution Systems
Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission
More informationThe Upgradabilty of Conventional Three Phase Delta/Star Networks
The Upgradabilty of Conventional Three Phase Delta/Star Networks WHY NEW STANDARDS? CAPITAL COSTS Initial Final OPERATIONAL COSTS UPGRADABILITY SAFETY MAINTAINANCE CONVENTIONAL CONFIGURATION Electrification
More informationImpedance protection on power transformer.
Impedance protection on power transformer www.siemens.com/siprotec5 SIPROTEC 5 Application Impedance Protection on Power Transformer APN-045, Edition 1 Content 1...3 1.1 Introduction...3 1.2 Application
More informationWHITE PAPER. Medium Voltage On-Site Generation Overview. BY MIKE KIRCHNER Technical Support Manager at Generac Power Systems
WHITE PAPER Medium Voltage On-Site Generation Overview BY MIKE KIRCHNER Technical Support Manager at Generac Power Systems INTRODUCTION It seems that just about everyone is looking for more power. As our
More informationPredicting the Voltage Sag Performance of Electricity Distribution Networks
Predicting the Voltage Sag Performance of Electricity Distribution Networks by Dr Robert Barr, Prof. Vic Gosbell, Mr Chris Halliday, Figure - Typical Rectangular Voltage Sag PU Supply Voltage..2 0.8 0.6
More informationTopic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017
Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length
More informationConnection Impact Assessment Application
Connection Impact Assessment Application This form is for generators applying for Connection Impact Assessment (CIA) and for generators with a project size >10 kw. Please return the completed form by email,
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationSHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP
SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP Kiran V. Natkar 1, Naveen Kumar 2 1 Student, M.E., Electrical Power System, MSS CET/ Dr. B.A.M. University, (India) 2 Electrical Power System,
More informationConventional Paper-II-2011 Part-1A
Conventional Paper-II-2011 Part-1A 1(a) (b) (c) (d) (e) (f) (g) (h) The purpose of providing dummy coils in the armature of a DC machine is to: (A) Increase voltage induced (B) Decrease the armature resistance
More informationELECTRICIAN S THEORY EXAMINATION 15 November 2014 QUESTION AND ANSWER BOOKLET
Candidate Code No. ET51 For Board Use Only Result Date Int Result Date Int ELECTRICIAN S THEORY EXAMINATION 15 November 2014 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three
More informationAGN 005 Fault Currents and Short Circuit Decrement Curves
Application Guidance Notes: Technical Information from Cummins Generator Technologies AGN 005 Fault Currents and Short Circuit Decrement Curves DESCRIPTION To facilitate the correct design of an electrical
More information1. general. 1.1 methodology and definitions. methodology
1. general 1.1 methodology and definitions component parts of an electric circuit and its protection are determined such, that all normal and abnormal operating constraints are satisfied. methodology Following
More informationBus Protection Fundamentals
Bus Protection Fundamentals Terrence Smith GE Grid Solutions 2017 Texas A&M Protective Relay Conference Bus Protection Requirements High bus fault currents due to large number of circuits connected: CT
More informationLIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION
LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION Andreas SUMPER sumper@citcea.upc.es Antoni SUDRIÀ sudria@citcea.upc.es Samuel GALCERAN galceran@citcea.upc.es Joan RULL rull@citcea.upc.es
More informationCONTENTS. 1. Introduction Generating Stations 9 40
CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific
More informationHow to maximize reliability using an alternative distribution system for critical loads
White Paper WP024001EN How to maximize reliability using an alternative distribution system for critical loads Executive summary The electric power industry has several different distribution topologies
More informationSafety through proper system Grounding and Ground Fault Protection
Safety through proper system Grounding and Ground Fault Protection November 4 th, 2015 Presenter: Mr. John Nelson, PE, FIEEE, NEI Electric Power Engineering, Inc. Event to start shortly Scheduled time:
More informationRAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements
RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements User s Guide General Most faults in power systems can be detected by applying
More informationPROTECTION of electricity distribution networks
PROTECTION of electricity distribution networks Juan M. Gers and Edward J. Holmes The Institution of Electrical Engineers Contents Preface and acknowledgments x 1 Introduction 1 1.1 Basic principles of
More informationCork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)
Cork Institute of Technology Bachelor of Science (Honours) in Electrical Power Systems - Award Instructions Answer FIVE questions. (EELPS_8_Y4) Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Examiners:
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationChapter 6. WIRING SYSTEMS Safe Electrical Design
Chapter 6 WIRING SYSTEMS Safe Electrical Design Topic 6-3 CABLE SELECTION BASED ON CURRENT CARRYING CAPACITY REQUIREMENTS INSTALLATION CONDITIONS Current carrying capacity (CCC) is the maximum continuous
More informationTertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved.
Pomona, CA, May 24 & 25, 2016 Tertiary Winding Design in wye-wye Connected Transformers Scope of Presentation > Tertiary vs. Stabilizing Winding? Tertiary vs. Stabilizing Winding? Need for Stabilizing
More informationFINAL - ET 60 - Electrician Theory Examination Marking Schedule
FINAL - ET 60 - Electrician Theory Examination Marking Schedule Notes:1. means that the preceding statement/answer earns 1 mark. 2. This schedule sets out the accepted answers to the examination questions.
More informationHow To Ground Electronic Equipment In Southern Company? Imagination at work
How To Ground Electronic Equipment In Southern Company? Imagination at work Surge Protection of Capacitor Feeder Controllers Robert Cheney Alabama Power John Skliutas GE Digital Energy Don Guinn Progress
More informationCourse No: 1 13 (3 Days) FAULT CURRENT CALCULATION & RELAY SETTING & RELAY CO-ORDINATION. Course Content
Course No: 1 13 (3 Days) FAULT CURRENT CALCULATION & RELAY SETTING & RELAY CO-ORDINATION Sr. No. Course Content 1.0 Fault Current Calculations 1.1 Introduction to per unit and percentage impedance 1.2
More informationStandard Prices for Generators 2010
Standard Prices for Generators 2010 Distribution System Operator ESB Networks Page 1 of 13 CONTENTS 1.0 Background...3 2.0 Standard Pricing Approach...3 Schedule of Charges for generators excluding VAT...6
More informationA Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation Equipment
International Research Journal of Engineering and Technology (IRJET) eissn: 23 0056 Volume: 04 Issue: 02 Feb 2017 www.irjet.net pissn: 072 A Review Comprehension: Guideline for Testing of HV, EHV and UHV
More informationRemotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application
General Application Information Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application Hydro One Remote Communities Inc. Lori.Rice@hydroone.com 1-807-474-2828 This Application
More informationR10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours
Code No: R3 R1 Set No: 1 III B.Tech. II Semester Supplementary Examinations, January -14 POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Max Marks: 75 Answer any FIVE Questions
More informationIntegration between the MV protection and control unit REF542 and the LV protection trip unit PR123: selectivity and earth fault 1SDC007402G0201
1SDC007402G0201 Index 1. Introduction... 2 2. Theoretical outline 2.1 Restricted earth fault... 3 2.2 Selectivity between medium and low voltage... 4 3. Application examples and wiring logic 3.1 Restricted
More informationChapter N Characteristics of particular sources and loads
Chapter N Characteristics of particular sources and loads 1 2 3 4 5 Contents Protection of a LV generator set and the downstream circuits 1.1 Generator protection N2 1.2 Downstream LV network protection
More informationFunctional Range. IWE - Earth Fault Relay. C&S Protection & Control Ltd.
Functional Range - Earth Fault Relay C&S Protection & Control Ltd. 2 Contents Page No. 1. Application 2. Operating Principle. Current Transformer Connections 5. Connections, Contact Arrangement and Setting
More informationDesign Approaches for Hospital Distribution Systems With Considerations for Future Expansion, Operator Safety, and Cost
Design Approaches for Hospital Distribution Systems With Considerations for Future Expansion, Operator Safety, and Cost Adam T. Powell, PE President Emerald Engineering, Inc. Jeffrey L. Small, Sr. Senior
More informationR10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering)
R10 Set No. 1 Code No: R41023 1. a) Explain how arc is initiated and sustained in a circuit breaker when the CB controls separates. b) The following data refers to a 3-phase, 50 Hz generator: emf between
More informationConnection Impact Assessment Application Form
Connection Impact Assessment Application Form This Application Form is for Generators applying for a Connection Impact Assessment (CIA). In certain circumstances, London Hydro may require additional information
More informationMV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer
PART 1: GENERAL 1.01 Transformer A. This section includes liquid filled, pad mounted distribution transformers with primary voltage of 12kV or 4.16kV (The University will determine primary voltage), with
More informationShort-Circuit Current Calculations
Basic Point-to-Point Calculation Procedure Step. Determine the transformer full load amps (F.L.A.) from either the nameplate, the following formulas or Table : Multiplier = 00 *% Z transformer Step 2.
More informationSubstation Preventive Maintenance
Substation Preventive Maintenance PROVINCIAL ELECTRICITY AUTHORITY 1 Presentation Contents 1) A kind of substation 2) Electrical equipment details of AIS substation 3) Electrical equipment details of GIS
More informationShort Circuit Current Calculations
Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that
More informationFERRORESONANCE SIMULATION STUDIES USING EMTP
FERRORESONANCE SIMULATION STUDIES USING EMTP Jaya Bharati, R. S. Gorayan Department of Electrical Engineering Institute of Technology, BHU Varanasi, India jbharatiele@gmail.com, rsgorayan.eee@itbhu.ac.in
More information3. (a) List out the advantages and disadvantages of HRC fuse (b) Explain fuse Characteristics in detail. [8+8]
Code No: RR320205 Set No. 1 1. (a) Explain about Bewley s Lattice diagrams and also mention the uses of these diagrams. [6+2] (b) A line of surge impedance of 400 ohms is charged from a battery of constant
More informationNumbering System for Protective Devices, Control and Indication Devices for Power Systems
Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements
More informationLevel 6 Graduate Diploma in Engineering Electrical Energy Systems
9210-114 Level 6 Graduate Diploma in Engineering Electrical Energy Systems Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler,
More informationTransmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection
Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection 133 1. Pilot wire differential relays (Device 87L) The pilot wire differential relay is a high-speed
More informationBusbars and lines are important elements
CHAPTER CHAPTER 23 Protection of Busbars and Lines 23.1 Busbar Protection 23.2 Protection of Lines 23.3 Time-Graded Overcurrent Protection 23.4 Differential Pilot-Wire Protection 23.5 Distance Protection
More informationElectrical Protection System Design and Operation
ELEC9713 Industrial and Commercial Power Systems Electrical Protection System Design and Operation 1. Function of Electrical Protection Systems The three primary aims of overcurrent electrical protection
More informationPower Quality and Reliablity Centre
Technical Note No. 8 April 2005 Power Quality and Reliablity Centre TRANSIENT OVERVOLTAGES ON THE ELECTRICITY SUPPLY NETWORK CLASSIFICATION, CAUSES AND PROPAGATION This Technical Note presents an overview
More informationThe Advantages and Application of Three Winding Transformers
The Advantages and Application of Three Winding Transformers MSc, CEng, FIEE, FIMechE, FIPENZ Principal, Sinclair Knight Merz Abstract Although seldom used in Australia and New Zealand, three winding transformers
More informationLine protection with transformer in the protection zone
Line protection with transformer in the protection zone www.siemens.com/siprotec5 Three-end line protection with transformer in the protection range SIPROTEC 5 Application Three-end line protection with
More informationthepower to protect the power to protect i-gard LITERATURE Low and medium voltage
thepower to protect i-gard LITERATURE Low and medium voltage distribution systems Arc Flash Hazards and High Resistance Grounding Grounding of Standby and Emergency Power Systems Neutral Grounding Resistors
More informationChapter L Power factor correction and harmonic filtering
Chapter L Power factor correction and 1 2 3 4 5 6 7 8 9 10 Contents Reactive energy and power factor 1.1 The nature of reactive energy L2 1.2 Equipment and appliances requiring reactive energy L2 1.3 The
More informationProtective earthing, protective conductor and automatic disconnection in case of a fault (Fault protection)
Protective earthing, protective conductor and automatic disconnection in case of a fault (Fault protection) FIGURE 1.2 Fig.1 Earth fault loop path. Figure 1 shows the earth fault system which provides
More informationIn Class Examples (ICE)
In Class Examples (ICE) 1 1. A 3φ 765kV, 60Hz, 300km, completely transposed line has the following positive-sequence impedance and admittance: z = 0.0165 + j0.3306 = 0.3310 87.14 o Ω/km y = j4.67 410-6
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationLa protection sélective des réseaux électriques
La protection sélective des réseaux électriques ULG 21. 11. 2012 The T&D grids Generation Transmission Distribution Industry The electricity network ensure an efficient supply of energy High Voltage Transformers
More informationUtility Interconnection and System Protection
Utility Interconnection and System Protection Alex Steselboim President, Advanced Power Technologies, Inc. Utility paralleling vs. isolated operation. Isochronous kw load sharing Reactive power (VAR) sharing
More informationMINISTRY OF ELECTRICITY
MINISTRY OF ELECTRICITY IRAQ SUPERGRID PROJECTS 400/132 KV GIS SUBSTATIONS VOLUME 3 TECHNICAL SCHEDULES JANUARY 2007 LIST OF REVISIONS 1 2 3 4 5 Current Rev. Date 19.11.04 18.03.05 Aug 05 Oct 05 Jan 07
More informationConventional Paper-II-2013
1. All parts carry equal marks Conventional Paper-II-013 (a) (d) A 0V DC shunt motor takes 0A at full load running at 500 rpm. The armature resistance is 0.4Ω and shunt field resistance of 176Ω. The machine
More informationMaintenance/Connection/Installation Service life C/O cyclesx1000
EasyPact MVS 2016 CPB100000 CPB100014 Circuit breaker. Switch disconnector. Common characteristics Number of poles Rated insulation voltage (V) Impulse withstand voltage (kv) Rated operational voltage
More informationEcodial Advance Calculation. Technical help
Ecodial Advance Calculation Technical help Contents Component names Main changes following the Cenelec TR50480 report Types of system earthing Types of transformer losses Diversity factor Ks Switchgear
More informationCourse ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation
Course ELEC0014 - Introduction to electric power and energy systems Additional exercises with answers December 2017 Exercise A1 Consider the system represented in the figure below. The four transmission
More informationSingle Line Diagram of Substations
Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission lines are
More informationFatima Michael college of Engineering and Technology
Fatima Michael college of Engineering and Technology DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING EE2303 TRANSMISSION AND DISTRIBUTION SEM: V Question bank UNIT I INTRODUCTION 1. What is the electric
More informationDiscipline Electrical Testing Issue Date Certificate Number T-2837 Valid Until Last Amended on - Page 1 of 6 LOCATION 1
Post: Last Amended on - Page 1 of 6 LOCATION 1 I. TRANSFORMERS AND REACTORS 1. 500 MVA, 765 kv 500 MVA, 400 kv Ratio & Polarity Check Magnetic Balance & Magnetizing Current Measurement at Low Voltage Vector
More information2 Grounding of power supply system neutral
2 Grounding of power supply system neutral 2.1 Introduction As we had seen in the previous chapter, grounding of supply system neutral fulfills two important functions. 1. It provides a reference for the
More informationELECTRICAL POWER ENGINEERING
Introduction This trainer has been designed to provide students with a fully comprehensive knowledge in Electrical Power Engineering systems. The trainer is composed of a set of modules for the simulation
More informationMEDIUM VOLTAGE PRODUCT. PARAMETERS GUIDE How to specify the indoor instrument transformers correctly
MEDIUM VOLTAGE PRODUCT PARAMETERS GUIDE How to specify the indoor instrument transformers correctly The range of electric values in the power supply systems is very extensive. This is why it is necessary
More informationELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS
101135-ELE-CMOS-E-2001 Electrical Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and has over 14 years hands-on experience, including 13 years working in operation, maintenance, construction
More informationIndex. b back-flashover 245 biomass 207 breakers 74 buchholz protection 235 busbar sectionalizer 193 business enterprises 18
331 Index a activity plan 318 agricultural enterprise 21 annual increase factor 12 annuity factor 44, 156 annuity method 38 ANSI code numbers 237 arrester, protection level 245 assessment of losses 38
More informationMV/LV transformer substations: theory and examples of short-circuit calculation
2 September 2005 1SDC007101G0201 Technical Application Papers MV/LV transformer substations: theory and examples of short-circuit calculation Technical Application Papers MV/LV transformer substations:
More informationDPF-MAC Auto power factor controller
Digital Electric& Electronics System DPF-MAC Auto power factor controller MULTI POWER FACTOR AUTOMATIC MULTI POWER FACTOR AUTOMATIC Introduction DPF-MAC increases usage efficiency by controlling the power
More informationTab 8 Surge Arresters
s en em Tab 8 Surge Arresters Si Distribution System Engineering Course Unit 10 2017 Industry Inc., All Rights Reserved Surge Arresters The main protective devices against system transient overvoltages.
More information10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY
9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor
More informationHigh voltage engineering
High voltage engineering Overvoltages power frequency switching surges lightning surges Overvoltage protection earth wires spark gaps surge arresters Insulation coordination Overvoltages power frequency
More informationEARTH FAULT PROTECTION VIS-A-VIS GENERATOR GROUNDING SYSTEM
EARTH FAULT PROTECTION VIS-A-VIS GENERATOR GROUNDING SYSTEM BY MR. H. C. MEHTA AT 1 ST INDIA DOBLE PROTECTION AND AUTOMATION CONFERENCE, NOV 2008 POWER-LINKER Wisdom is not Virtue but Necessity hcmehta@powerlinker.org
More informationCourse 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC)
Name: Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC) 1. T F In three-phase four-wire delta systems rated 240/120 volts, sometimes
More informationUnit 27 Three-Phase Circuits
Unit 27 Three-Phase Circuits Objectives: Discuss the differences between threephase and single-phase voltages. Discuss the characteristics of delta and wye connections. Compute voltage and current values
More informationSimulations of open phase conditions on the high voltage side of YNd05-power plant transformers
Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers Disclaimer: All information presented in the report, the results and the related computer program, data,
More informationDesign a Power System Simulator Model and Implement the Generator and Motor Controlling
Design a Power System Simulator Model and Implement the Generator and Motor Controlling G.U De Silva, G.B Alahendra, A.C.P Aluthgama, P.G.L Arachchi Supervised by: Prof. J Rohan Lucas, Eng. J. Karunanayake
More informationGenerator Advanced Concepts
Generator Advanced Concepts Common Topics, The Practical Side Machine Output Voltage Equation Pitch Harmonics Circulating Currents when Paralleling Reactances and Time Constants Three Generator Curves
More informationProblems connected with Commissioning of Power Transformers
Problems connected with Commissioning of Power Transformers ABSTRACT P Ramachandran ABB India Ltd, Vadodara, India While commissioning large Power Transformers, certain abnormal phenomena were noticed.
More informationDMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW)
DELHI METRO RAIL CORPORATION LIMITED DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW) SPECIFICATION NO. DMES- 0005/ DMRC-E-TR-TRANSF-05 SPECIFICATIONS FOR THREE PHASE 33 kv/415 V AUXILIARY Issued on: Date
More informationTS RES - OUTSTANDING ISSUES
TS RES - OUTSTANDING ISSUES This document has been officially issued as DRAFT until the following outstanding issues have been resolved. At that time the document will be officially reissued as the next
More informationCircuit breakers for direct current applications
Circuit breakers for direct current applications Complementary technical information schneider-electric.com Complementary technical information Circuit breakers for direct current applications Contents
More informationChapter B Connection to the MV utility distribution network
Chapter B Connection to the MV utility 1 2 3 4 5 6 Contents Supply of power at medium voltage 1.1 Power supply characteristics of medium voltage B2 utility 1.2 Different MV service connections B11 1.3
More information