MODELING OF TRANSFORMERS IN WECC BASE CASES. For WECC SRWG By Rohan Chatterjee Electrical Engineer Transmission Planning

Size: px
Start display at page:

Download "MODELING OF TRANSFORMERS IN WECC BASE CASES. For WECC SRWG By Rohan Chatterjee Electrical Engineer Transmission Planning"

Transcription

1 MODELING OF TRANSFORMERS IN WECC BASE CASES For WECC SRWG By Rohan Chatterjee Electrical Engineer Transmission Planning

2 Present Utility Practices Problems with present practices PowerWorld Use of Transformer Base data for calculating System Base values. PSLF Use of Transformer Base data for calculating System Base values. PSLF EPC file exported to PowerWorld & PTI RAW file format. Examples Used PGE 230/13.8kV GSU, Avista 230/115kV LTC transformer (at Boulder substation). Conclusions 2 T&D Planning

3 Present Utility Practices Modeling of transformers in various software platforms such as PowerWorld, PSLF, and PSSE is crucial to the accuracy of powerflow solutions and the efficacy of planning/operations studies. Present WECC base cases contain transformer data for most Northwest utilities in the System Base. Inconsistencies in how different utilities enter their transformer data in System Base. PGE & Avista transmission planning have discussed the benefits of having a process in place to calculate transformer modeling data from the most accurate source, i.e test reports. To accurately convert transformer data into the System Base, PowerWorld and PSLF require that the data be provided on the Transformer Base. PSSE on the other hand, offers user flexibility to provide data in either the System Base or the Transformer Base. 3 T&D Planning

4 Problems With Present Practices When provided with Transformer Base data PowerWorld, PSLF & PSSE convert it to the System Base. When provided with data on the System Base (from the.epc file), PowerWorld may not necessarily do a 1:1 transformation of this data. It calculates incorrect values for tap ratios, impedance & magnetizing admittance parameters on the System Base. Similar to PW, when provided with data in the System Base (from the.epc file), PSLF calculates incorrect System Base values for the impedance & magnetizing admittance parameters. It uses FROM & TO side input tap ratios and calculates incorrect values for transformer tap ratios on the System Base. 4 T&D Planning

5 Problems With Present Practices When.EPC files are exported to.raw file format, the impedance, nominal MVA and nominal kvs get stored as Transformer Base values by default. If the.epc file contains System Base data, much like PW & PSLF, this causes PSSE to calculate incorrect System base values for transformer tap ratios, impedance and magnetizing admittance parameters. There is a need for a standardized manual for transformer modeling. 5 T&D Planning

6 When provided with data on the System Base, PSLF calculates incorrect values for System Base transformer tap ratios, impedance & mag. admittance parameters..epc files (WECC base cases) containing System Base transformer data When provided with data on the System Base, PSSE calculates incorrect values for System Base transformer tap ratios, impedance & mag. admittance parameters. Same Issues regardless of the software platform. This isn t a software issue. The user needs to ensure that the input data is in the Transformer Base. When provided with data on the System Base, PW calculates incorrect System Base values for tap ratios, impedance & mag. admittance parameters. 6 T&D Planning

7 PowerWorld When provided with Transformer Base data PowerWorld converts it to the System Base. Transformer Base model utilized by PowerWorld System Base model utilized by PowerWorld Equations used to calculate impedance and magnetizing admittance parameters on the System Base 7 T&D Planning

8 PGE GSU Test Report Schematic diagram of the no-load loss test: a) Test Setup, b) Bushings Connection, c) Equivalent circuit Schematic diagram of the load loss test: a) Test Setup, b) Bushings Connection, c) Equivalent circuit 8 T&D Planning

9 PGE GSU Nameplate HV & LV Nominal kvs (on the Transformer/Winding base) Per Phase Impedance % Connection Information (Wye-Delta) DETC settings on the HV side 9 T&D Planning

10 Incorrect Modeling TRANSFORMER DATA ENTERED IN POWERWORLD SYSTEM BASE THE SYSTEM BASE Nominal MVA 100 Nominal MVA 100 Nominal kv (GSU High Side) Nominal kv (GSU Low Side) Nominal kv (GSU High Side) Nominal kv (GSU Low Side) R on System Base R X on System Base X Mag B on Sys. Base Mag B Mag G on Sys. Base Mag G If the impedance & magnetizing admittance parameters are entered in the System Base, their transformation will not result in identical values, because of the tap ratio on the TO side (as circled in red below). Transformer Data (from epc file) Is Entered In the System Base Equations used to calculate impedance and magnetizing admittance parameters on the System Base 10 T&D Planning

11 Correct Modeling Transformer Base System Base Nominal MVA 130 Nominal MVA 100 Nominal kv (GSU High Side) Nominal kv (GSU High Side) 230 Nominal kv (GSU Low Side) 13.2 Nominal kv (GSU Low Side) 13.8 R on XF Base R If the impedance & magnetizing admittance parameters are entered in the Transformer Base, they will be correctly transformed to the corresponding System Base values. X on XF Base X Mag B on XF Base Mag B Mag G on XF Base Mag G GSU Test Report Transformer Data Is In the Transformer Base GSU Nameplate It is therefore critical that the impedance and magnetizing admittance parameters be entered into PowerWorld in the Transformer Base. 11 T&D Planning

12 Equations used to calculate the transformer tap ratio on the System Base TTTTTTTTTTTTTT = 11 FFFFFFFFFFFFFFFFFFFF TTTT NNNNNNNNNNNNNN SSSSSS NNNNNNNNNNNNNN TTTT NNNNNNNNNNNNNNNNNN TTTT NNNNNNNNNNNNNNNNNN SSSSSS TTTTTTTTTTTTTT = = TTTTTT SSSSSSSSSSSS = CCCCCCCCCCCCCC TTTTTT RRRRRRRRRR TTTT + FFFFFFFFFFFFFFFFFFFFFFFF TTTT 11 TTTTTTTTTTTTTT = = If the FROM & TO side tap ratios are entered in the System Base, it ends up calculating incorrect System Base values for transformer tap ratio. 12 T&D Planning

13 If the FROM & TO side tap ratios are entered in the Transformer Base, PowerWorld correctly calculates the System Base transformer tap ratio. TTTTTTTTTTTTTT = 11 FFFFFFFFFFFFFFFFFFFF TTTT NNNNNNNNNNNNNN SSSSSS NNNNNNNNNNNNNN TTTT NNNNNNNNNNNNNNNNNN TTTT NNNNNNNNNNNNNNNNNN SSSSSS TTTTTTTTTTTTTT = = TTTTTT SSSSSSSSSSSS = CCCCCCCCCCCCCC TTTTTT RRRRRRRRRR TTTT + FFFFFFFFFFFFFFFFFFFFFFFF TTTT 11 TTTTTTTTTTTTTT = = All calculations have been documented in the manual on the modeling of PGE transformers. These are values calculated by PowerWorld in the System Base (i.e 100 MVA, 230kV & 13.8kV). It is therefore critical that FROM & TO side tap ratios be entered in PowerWorld in the Transformer Base. 13 T&D Planning

14 GE PSLF When provided with Transformer Base input data PSLF converts it to the System Base. Transformer Base model utilized by PSLF When provided with System Base input data, the tap ratios, impedance & magnetizing admittance parameters are calculated incorrectly in the System Base. Please note that PSLF requires that the Nominal MVA (i.e tbase) and the data items tapp, tapfp, tapfs, vnomp and vnoms be entered on the Transformer Base. The conversion of the data from the individual transformer bases to a common system base for network solutions is handled internally by PSLF. 14 T&D Planning

15 Round Butte VR3 * From bus ROUNDB N R from-tert pu * Variable V tap pu * To bus ROUND B X from-tert pu * Step size pu(deg) * Circuit Id 1 R to-tert pu Max var. tap pu(deg) Project Id 0 X to-tert pu Min var. tap pu(deg) * Trans Status 1 *From wind nom volt Kv Max Cont V(P) pu (MW) The table shows the information pertaining to nominal MVA, nominal kv, impedance and admittance parameters in an epc file. (all in System Base). Normal Status 0 *To wind nom volt Kv Min Cont V(P) pu (MW) * Tap control type 1 *Tert wind nom volt Kv G-Core loss pu * From-To Base MVA * From fixed tap pu B-Magnetizing pu R from-to pu * To fixed tap pu * X from-to pu * Tert fixed tap pu If the FROM & TO side tap ratios are entered in the System Base, it results in incorrect System Base values for transformer tap ratio. TTTTTT RRRRRRRRRR SSSSSSSSSSSS BBBBBBBB = tttttttt + tttttttttt 11 tttttttttt TTTT kkvv nnnnnnssssss TTTT kkvv nnnnnntttt FFFFFFFF kkvv nnnnnntttt FFFFFFFF kkvv nnnnnnssssss ; TTTTTT RRRRRRRRRR SSyyyyyyyyyy BBaaaaaa = = (IIIIIIIIIIIIIIIIII) OOOOOO NNNNNNNNNNNNNN TTTTTT RRRRRRRRRR SSSSSSSSSSSS BBBBBBBB = kkkk LLLL, VVVVVVVVVVVVVVVV/FFFFFFFFFF TTTTTT PPPPPPPPPPPPPP kkkkllll, SSSSSSSSSSSS NNNNNNNNNNNNNN kkkk LLLL, FFFFFFFFFF TTTTTT PPPPPPPPPPPPPPPP kkkkllll, SSSSSSSSSSSS NNNNNNNNNNNNNN = = (Correct) 15 T&D Planning

16 * From bus ROUNDB N R from-tert pu * Variable V tap pu * To bus ROUND B X from-tert pu * Step size pu(deg) * Circuit Id 1 R to-tert pu Max var. tap pu(deg) Project Id 0 X to-tert pu Min var. tap pu(deg) * Trans Status 1 *From wind nom volt Kv Max Cont V(P) pu (MW) 0.00 The table shows the information pertaining to nominal MVA, nominal kv, impedance and admittance parameters in an epc file for Round Butte VR3. (all in Transformer Base). Normal Status 0 *To wind nom volt Kv Min Cont V(P) pu (MW) * Tap control type 1 *Tert wind nom volt Kv G-Core loss pu * From-To Base MVA * From fixed tap pu B-Magnetizing pu R from-to pu * To fixed tap pu * X from-to pu * Tert fixed tap pu If the FROM & TO side tap ratios are entered in the Transformer Base, it results in correct System Base values for transformer tap ratio. TTTTTT RRRRRRRRRR ssssssssssss bbbbbbbb = = When this epc file is opened in PowerWorld, we see the input information as it should be on the Transformer Base. Using the input Transformer Base data, these are values calculated by PowerWorld in the System Base. 16 T&D Planning

17 The Nominal KV, impedance parameters and Nominal MVA are stored in the Transformer Base. I/O code 2 in PSSE parlance. The magnetizing admittance parameters are stored in the System Base. I/O code 1 in PSSE parlance. When the epc file containing the data in the System Base is exported to the Siemens PSSE raw file format, it is stored in the raw file in the Transformer Base. This creates the following issues; The FROM & TO winding nominal kvs and the winding nominal MVA are set equal to their respective nominal System Base values. The System Base transformer tap ratio is calculated incorrectly. The System Base values for impedance and magnetizing admittance parameters are calculated incorrectly. tt SSSSSSSSSSSS BBBBBBBB = tt ii tt jj VV bbbbbbbb ii nnnnnnnnnnnnnnnnnn VV bbbbbbbb ii dddddddddddddd VV bbbbbbbb jj dddddddddddddd VV bbbbbbbb jj nnnnnnnnnnnnnnnnnn = = (iiiiiiiiiiiiiiiiii) PSSE Two-Winding Transformer Circuit RR ssssssssssss BBBBBBBB = tt jj 22 RRTTTTTTTTTTTTTTTTTTTTTT BBBBBBBB VV bbbbbbbb jj nnnnnnnnnnnnnnnn VV bbbbbbbb ii dddddddddddddd 22 MMMMMM dddddddddddddd MMMMMM nnnnnnnnnnnnnnnnnn = = pp. uu (iiiiiiiiiiiiiiiiii) 17 T&D Planning

18 The Nominal KV, impedance parameters and Nominal MVA are stored in the Transformer Base. I/O code 2 in PSSE parlance. The magnetizing admittance parameters are stored in the System Base. I/O code 1 in PSSE parlance. When the epc file containing the data in the Transformer Base is exported to the Siemens PSSE raw file format, it is stored correctly in the raw file in the Transformer Base. This results in; The FROM & TO winding nominal kvs and the winding nominal MVA are set equal to their respective nominal Transformer Base values. The System Base transformer tap ratio is calculated correctly. The System Base values for impedance and magnetizing admittance parameters are calculated correctly. tt SSSSSSSSSSSS BBBBBBBB = tt ii tt jj VV bbbbbbbb ii nnnnnnnnnnnnnnnnnn VV bbbbbbbb ii dddddddddddddd VV bbbbbbbb jj dddddddddddddd VV bbbbbbbb jj nnnnnnnnnnnnnnnnnn = = (cccccccccccccc) PSSE Two-Winding Transformer Circuit RR ssssssssssss BBBBBBBB = tt jj 22 RRTTTTTTTTTTTTTTTTTTTTTT BBBBBBBB VV bbbbbbbb jj nnnnnnnnnnnnnnnn VV bbbbbbbb ii dddddddddddddd 22 MMMMMM dddddddddddddd MMMMMM nnnnnnnnnnnnnnnnnn = = pp. uu (cccccccccccccc) 18 T&D Planning

19 Avista Boulder Substation 19 T&D Planning

20 Avista Boulder Substation 20 T&D Planning

21 Avista Boulder LTC Transformer Test Report Schematic diagram of load losses test: a) Test Setup, b) Bushings Connection, c) Equivalent circuit Schematic diagram of no-load losses test: a) Test Setup, b) Bushings Connection, c) Equivalent circuit 21 T&D Planning

22 Avista Boulder LTC Transformer Nameplate Information HV & LV Nominal kvs (on the Transformer/Winding base) LTC/NLTC settings on the HV/LV sides Per Phase Impedance % Wye-Wye primary-secondary connection with delta connected tertiary winding 22 T&D Planning

23 Boulder (Incorrect Modeling) TRANSFORMER DATA ENTERED IN POWERWORLD SYSTEM BASE THE SYSTEM BASE Nominal MVA 100 Nominal MVA 100 Nominal kv (GSU High Side) Nominal kv (GSU Low Side) Nominal kv (GSU High Side) Nominal kv (GSU Low Side) If the impedance & magnetizing admittance parameters are entered in the System Base, their transformation will not result in identical values, because of the tap ratio on the TO side (as circled in red below). R on System Base R X on System Base X Mag B on Sys. Base 0 Mag B 0 Mag G on Sys. Base 0 Mag G 0 Transformer Data (from aux file) Is Entered In the System Base Equations used to calculate impedance and magnetizing admittance parameters on the System Base 23 T&D Planning

24 Boulder (Correct Modeling) Transformer Base System Base Nominal MVA 250 Nominal MVA 100 Nominal kv (GSU High Side) Nominal kv (GSU High Side) 230 Nominal kv (GSU Low Side) Nominal kv (GSU Low Side) 115 R on XF Base R If the impedance & magnetizing admittance parameters are entered in the Transformer Base, they will be correctly transformed to the corresponding System Base values. X on XF Base X Mag B on XF Base 0 Mag B 0 Mag G on XF Base 0 Mag G 0 Boulder LTC Test Report Boulder LTC Nameplate Information Transformer Data Is In the Transformer Base It is therefore critical that the impedance and magnetizing admittance parameters be entered into PowerWorld in the Transformer Base. 24 T&D Planning

25 Conclusions New PGE practice - All transformer data required for the ColumbiaGrid/WECC base case development process will be provided by PGE in the Transformer Base. EPC files containing Transformer Base data can be faithfully exported to the PowerWorld and PSSE platforms without any data skews or distortions. Providing Transformer Base input parameters to the software platforms enables their accurate internal conversion to the corresponding System Base parameters. PGE & Avista agree & strongly recommend that utilities submit transformer data in the Transformer Base for the WECC base case development process. This will result in WECC-wide uniformity in transformer modeling for system planning studies. Update the Data Preparation Manual to have utilities provide their transformer data only in the Transformer Base. 25 T&D Planning

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Grounding Resistance

Grounding Resistance Grounding Resistance Substation grounding resistance is the resistance in ohms between the substation neutral and earth ground (zeropotential reference) An actual fall of potential test is the best way

More information

SECTION 1 INTRODUCTION

SECTION 1 INTRODUCTION Power PE Engineering Pro Guides Full Exam 80 exam difficulty level problems and detailed solutions Tests concepts not tested by other sample exams. Follows the exam outline and covers the main topics.

More information

WECC Data Preparation Manual

WECC Data Preparation Manual WECC Data Preparation Manual for Interconnection-wide Cases Applicable to the 2017 Base Case Compilation Schedule System Review Work Group Technical Studies Subcommittee 155 North 400 West, Suite 200 Salt

More information

Tom Ernst GE Digital Energy Craig Talbot Minnesota Power

Tom Ernst GE Digital Energy Craig Talbot Minnesota Power Tom Ernst GE Digital Energy Craig Talbot Minnesota Power Introduction Traditional 3-phase testing method Traditional 1-phase testing method Alternate 1-phase testing method Application examples 3-Phase

More information

WECC Data Preparation Manual

WECC Data Preparation Manual WECC Data Preparation Manual for Interconnection-wide Cases Applicable to the 2016 Base Case Compilation Schedule System Review Work Group Technical Studies Subcommittee 155 North 400 West, Suite 200 Salt

More information

Generator Voltage Protective Relay Settings

Generator Voltage Protective Relay Settings ERO Enterprise Endorsed Generator Voltage Protective Relay Settings Implementation Guidance PRC-024-2 Requirement R2 January 19, 2018 Submitting Pre-Qualified Organization: NERC Planning Committee (PC)

More information

ECEN 615 Methods of Electric Power Systems Analysis Lecture 8: Advanced Power Flow

ECEN 615 Methods of Electric Power Systems Analysis Lecture 8: Advanced Power Flow ECEN 615 Methods of Electric Power Systems nalysis Lecture 8: dvanced Power Flow Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas &M University overbye@tamu.edu nnouncements Read Chapter

More information

Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions

Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions PRC-001: System protection coordination PRC-019: Coordination with voltage regulating control

More information

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved.

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved. Pomona, CA, May 24 & 25, 2016 Tertiary Winding Design in wye-wye Connected Transformers Scope of Presentation > Tertiary vs. Stabilizing Winding? Tertiary vs. Stabilizing Winding? Need for Stabilizing

More information

Generator Voltage Protective Relay Settings

Generator Voltage Protective Relay Settings Generator Voltage Protective Relay Settings Implementation Guidance PRC-024-2 January 19, 2018 NERC Report Title Report Date I Table of ContentsPreface... iii Overview... 4 Background... 4 Purpose... 4

More information

Regional Technical Seminar TAP CHANGERS

Regional Technical Seminar TAP CHANGERS Regional Technical Seminar TAP CHANGERS SPX Transformer Solutions, Inc. September 4, 2018 De-Energized and Load Tap Changers Jason Varnell Lead Design Engineer jason.varnell@spx.com SPX Transformer Solutions,

More information

Rarely used, problems with unbalanced loads.

Rarely used, problems with unbalanced loads. THREE-PHASE TRANSFORMERS Transformers used in three-phase systems may consist of a bank of three single-phase transformers or a single three-phase transformer which is wound on a common magnetic core.

More information

Modelling Parameters. Affect on DER Impact Study Results

Modelling Parameters. Affect on DER Impact Study Results Modelling Parameters Affect on DER Impact Study Results Agenda Distributed Energy Resources (DER) Impact Studies DER Challenge Study Steps Lessons Learned Modeling Reverse Power Transformer Configuration

More information

DER_A Benchmark Update

DER_A Benchmark Update DER_A Benchmark Update Deepak Ramasubramanian, EPRI Anish Gaikwad, EPRI Pouyan Pourbeik, PEACE NERC LMTF October 31 st 2017 Austin, TX DISCLAIMER The DER_A model is still a beta model under test and development

More information

Success Story: Practical Use of Synchrophasor Technology in ISO-NE Operations

Success Story: Practical Use of Synchrophasor Technology in ISO-NE Operations 2018-10- 23 PHILADELPHIA, PA Success Story: Practical Use of Synchrophasor Technology in ISO-NE Operations NASPI Work Group Meeting Xiaochuan Luo TECHNICAL MANAGER BUSINESS ARCHITECTURE AND TECHNOLOGY

More information

148 Electric Machines

148 Electric Machines 148 Electric Machines 3.1 The emf per turn for a single-phase 2200/220- V, 50-Hz transformer is approximately 12 V. Calculate (a) the number of primary and secondary turns, and (b) the net cross-sectional

More information

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting Document C-29 Procedures for System Modeling: January 5 th, 2016 TFSS Revisions Clean Open Process Posting Prepared by the SS-37 Working Group on Base Case Development for the Task Force on System Studies.

More information

PROCEDURE. Part 3.5: Site-Specific Loss Adjustments PUBLIC. Market Manual 3: Metering. Issue 8.0 MDP_PRO_0011

PROCEDURE. Part 3.5: Site-Specific Loss Adjustments PUBLIC. Market Manual 3: Metering. Issue 8.0 MDP_PRO_0011 PUBLIC MDP_PRO_0011 PROCEDURE Market Manual 3: Metering Part 3.5: Site-Specific Loss Adjustments Issue 8.0 This document provides guidance to metering service providers on how to calculate and submit Site-Specific

More information

Modeling of Three-phase or Bank of Three Single Phase Three Winding Transformers Zero-phase-sequence Leakage Impedance in PSS E Short Circuit Module

Modeling of Three-phase or Bank of Three Single Phase Three Winding Transformers Zero-phase-sequence Leakage Impedance in PSS E Short Circuit Module Siemens Industry, Inc. Power Technology Issue 125 Modeling of Three-phase or Bank of Three Single Phase Three Winding Transformers Zero-phase-sequence Leakage Impedance in PSS E Short Circuit Module Carlos

More information

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements Robert Nelson Senior Expert Engineering Manager and Manager of Codes, Standards, and Regulations Siemens Wind Turbines -

More information

INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY Internal Use Only Date Received Time Received Received By: 1. The undersigned Interconnection Customer submits this request to interconnect its Large

More information

Substation Testing and Commissioning: Power Transformer Through Fault Test

Substation Testing and Commissioning: Power Transformer Through Fault Test 1 Substation Testing and Commissioning: Power Transformer Through Fault Test M. Talebi, Member, IEEE, Power Grid Engineering Y. Unludag Electric Power System Abstract This paper reviews the advantage of

More information

Chapter 2: Transformers

Chapter 2: Transformers Chapter 2: Transformers 2-1. The secondary winding of a transformer has a terminal voltage of v s (t) = 282.8 sin 377t V. The turns ratio of the transformer is 100:200 (a = 0.50). If the secondary current

More information

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY WN U-60 Attachment C to Schedule 152, Page 1 SCHEDULE 152 APPLICATION FOR INTERCONNECTING A GENERATING FACILITY TIER 2 OR TIER 3 This Application is considered complete when it provides all applicable

More information

Lessons Learned in Model Validation for NERC Compliance

Lessons Learned in Model Validation for NERC Compliance Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification

More information

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels

More information

APPENDIX 1 to LGIP INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

APPENDIX 1 to LGIP INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY APPENDIX 1 to LGIP INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY 1. The undersigned Interconnection Customer submits this request to interconnect its Large Generating Facility with Transmission

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 Charles J. Mozina, Consultant Beckwith Electric Co., Inc. www.beckwithelectric.com I. Introduction During the 2003 blackout,

More information

Lessons Learned in Model Validation for NERC Compliance

Lessons Learned in Model Validation for NERC Compliance Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification

More information

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 % BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and

More information

Catastrophic Relay Misoperations and Successful Relay Operation

Catastrophic Relay Misoperations and Successful Relay Operation Catastrophic Relay Misoperations and Successful Relay Operation Steve Turner (Beckwith Electric Co., Inc.) Introduction This paper provides detailed technical analysis of several catastrophic relay misoperations

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC)

Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC) Name: Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC) 1. T F In three-phase four-wire delta systems rated 240/120 volts, sometimes

More information

GMD Voltage Collapse Study

GMD Voltage Collapse Study GMD Voltage Collapse Study Terry Volkmann 2016 Fall Reliability Conference November 2, 2016 1 GMD Voltage Collapse Studies in Wisconsin and Maine Overview: Modeling shows GMD Voltage Collapse Issues: Power

More information

WECC Data Preparation Manual

WECC Data Preparation Manual WECC Data Preparation Manual for Interconnection-wide Cases Applicable to the 2018 Base Case Compilation Schedule System Data Work Group Data Subcommittee 155 North 400 West, Suite 200 Salt Lake City,

More information

Generation Interconnection Study Data Sheet Synchronous Machines

Generation Interconnection Study Data Sheet Synchronous Machines FOR INTERNAL USE ONLY GTC Project Number: Queue Date: Generation Interconnection Study Data Sheet Synchronous Machines Customers must provide the following information in its entirety. GTC will not proceed

More information

Fault Ride Through Technical Assessment Report Template

Fault Ride Through Technical Assessment Report Template Fault Ride Through Technical Assessment Report Template Notes: 1. This template is intended to provide guidelines into the minimum content and scope of the technical studies required to demonstrate compliance

More information

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number:  Address: NORTH CAROLINA INTERCONNECTION REQUEST Utility: Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: An is considered complete when it provides all applicable and correct information

More information

ERCOT shall post the extraordinary dispatch details used in each case to the POI website.

ERCOT shall post the extraordinary dispatch details used in each case to the POI website. Docket Nos. 44547 & 44649 CAL-NRG 01-34 Attachment 3 ERCOT Steady State Working Group Procedure Manual doc Page 20 of 58 ERCOT shall post the extraordinary dispatch details used in each case to the POI

More information

Relay-assisted commissioning

Relay-assisted commissioning Relay-assisted commissioning by Casper Labuschagne and Normann Fischer, Schweitzer Engineering Laboratories (SEL) Power transformer differential relays were among the first protection relays to use digital

More information

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Charles Sweetser, Services Manager, PRIM Engineering, Waltham, Mass. Topics of Discussion

More information

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis feature By brandon dupuis An Introduction to Electrical diagnostic TesTIng of Power Transformers 38 Transformers are the largest, most expensive, and highly critical components of most utility substations.

More information

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser - OMICRON Transformers Diagnostic Testing - OVERALL DGA Oil Screen Power Factor / Capacitance Exciting Current Transformer

More information

Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller

Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer Anura Perera, Paul Keller System Operator - Eskom Transmission Introduction During the design phase of

More information

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser, OMICRON electronics Corp. USA Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser,

More information

86 chapter 2 Transformers

86 chapter 2 Transformers 86 chapter 2 Transformers Wb 1.2x10 3 0 1/60 2/60 3/60 4/60 5/60 6/60 t (sec) 1.2x10 3 FIGURE P2.2 2.3 A single-phase transformer has 800 turns on the primary winding and 400 turns on the secondary winding.

More information

QUESTIONNAIRE for Wind Farm Power Stations only

QUESTIONNAIRE for Wind Farm Power Stations only TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

Considerations in Choosing Directional Polarizing Methods for Ground Overcurrent Elements in Line Protection Applications

Considerations in Choosing Directional Polarizing Methods for Ground Overcurrent Elements in Line Protection Applications Working Group D-3, Line Protection Subcommittee IEEE PES Power System Relaying Committee Considerations in Choosing Directional Polarizing Methods for Ground Overcurrent Elements in Line Protection Applications

More information

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur Lecture - 10 Transmission Line Steady State Operation Voltage Control (Contd.) Welcome

More information

Var Control. Adding a transformer and transformer voltage regulation. engineers loadflow program. The control system engineers loadflow.

Var Control. Adding a transformer and transformer voltage regulation. engineers loadflow program. The control system engineers loadflow. November 2012 Adding a transformer and transformer voltage regulation to the control system engineers loadflow program The control system engineers loadflow program The loadflow program used by this website

More information

Kestrel Power Engineering

Kestrel Power Engineering [Type text] [Type text] [Type text] Kestrel Power Engineering 1660 Twelve Oaks Way #206, North Palm Beach, FL, 33408 ph (516) 972-8049 01 Subject: Steady State Calculations for This memo compares the steady

More information

Imperial Irrigation District System Planning ATTACHMENT A

Imperial Irrigation District System Planning ATTACHMENT A ATTACHMENT A A typical System Impact Study includes Power Flow, Transient Stability, Post-Transient Stability, and Short Circuit Analysis. If the size and/or technology type of the project is different

More information

DIFFERENTIAL PROTECTION METHODOLOGY FOR ARBITRARY THREE-PHASE POWER TRANSFORMERS

DIFFERENTIAL PROTECTION METHODOLOGY FOR ARBITRARY THREE-PHASE POWER TRANSFORMERS DFFERENTAL PROTECTON METHODOLOGY FOR ARBTRARY THREE-PHASE POWER TRANSFORMERS Z. Gaji ABB AB-SA Products, Sweden; zoran.gajic@se.abb.com Keywords: power transformer, phase shifting transformer, converter

More information

State of North Dakota Engineering data submittal Page 1 For interconnection of distributed generation to Otter Tail Power Company

State of North Dakota Engineering data submittal Page 1 For interconnection of distributed generation to Otter Tail Power Company Engineering data submittal Page 1 WHO SHOULD FILE THIS SUBMITTAL : Anyone in the final stages of in terconnecting a Generation System with Otter Tail Power. This submittal shall be completed and provided

More information

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES U AJMAL, GE Grid Solutions UK Ltd, usman.ajmal@ge.com S SUBRAMANIAN, GE Grid Solutions UK Ltd, sankara.subramanian@ge.com H Ha GE Grid Solutions

More information

UBC Technical Guidelines Section Edition Medium-Voltage Transformers Page 1 of 5

UBC Technical Guidelines Section Edition Medium-Voltage Transformers Page 1 of 5 Page 1 of 5 1.0 GENERAL 1.1 Coordination Requirements.1 UBC Energy & Water Services.2 UBC Building Operations 1.2 Description.1 UBC requirements for Substation Transformers. 2.0 MATERIAL AND DESIGN REQUIREMENTS

More information

Apprentice Electrical Technician Test (ETT) Preparation Guide

Apprentice Electrical Technician Test (ETT) Preparation Guide Apprentice Electrical Technician Test (ETT) Preparation Guide APPRENTICE ELECTRICAL TECHNICIAN TEST (ETT) About the Test There are 40 questions with a maximum time limit of three hours. This is a closed

More information

PROTECTION OF TRANSFORMERS M-3311A TEST PLAN

PROTECTION OF TRANSFORMERS M-3311A TEST PLAN PROTECTION OF TRANSFORMERS M-3311A TEST PLAN Chuck Mozina -- is a Consultant, Protection and Protection Systems for Beckwith Electric and resides in Palm Harbor (near Tampa), Florida.. He is a Life Fellow

More information

EN Assignment No.1 - TRANSFORMERS

EN Assignment No.1 - TRANSFORMERS EN-06 - Assignment No.1 - TRANSFORMERS Date : 13 th Jan 01 Q1) A 0kVA 00/0 Volts, 60Hz, single phase transformer is found to have the following equivalent circuit parameter referred to the high potential

More information

SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS)

SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS) SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS) SLIDE In this video, we will cover a sample exam problem for the Power PE Exam. This exam problem falls under the topic of Protection, which accounts for

More information

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 Nkosinathi Buthelezi Senior Consultant: Power Transformers and Reactors Presentation Content Standardization of Power

More information

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009 Lab 1 Objectives In this lab, our objective is to simulate a simple single machine infinite bus configuration using the PowerWorld Simulator software. We design a local generator system (a synchronous

More information

Kestrel Power Engineering

Kestrel Power Engineering Kestrel Power Engineering 1660 Twelve Oaks Way #206, North Palm Beach, FL ph (561) 972 8049 Subject: Any questions should be directed to Les Hajagos. Leonardo Lima Kestrel Power Engineering leo@kestrelpower.com

More information

CLNR Trial Analysis Real-Time Thermal Rating for Power Transformers

CLNR Trial Analysis Real-Time Thermal Rating for Power Transformers CLNR Trial Analysis Real-Time Thermal Rating for Power Transformers DOCUMENT NUMBER CLNR-L130 AUTHORS Peter Davison, Newcastle University ISSUE DATE 23 December 2014 Copyright Northern Powergrid (Northeast)

More information

INTERPRETATION METHODOLOGY TO IDENTIFY FAULT LOCATION IN A POWER TRANSFORMER

INTERPRETATION METHODOLOGY TO IDENTIFY FAULT LOCATION IN A POWER TRANSFORMER Volume: 03 Issue: 07 July16 www.irjet.net p-issn: 2395-0072 INTERPRETATION METHODOLOGY TO IDENTIFY FAULT LOCATION IN A POWER TRANSFORMER Sameer S. Patel 1, 1 Student, Electrical Dept, Rajasthan Institute

More information

Keywords: Power Transformer, On-load Tap Changer, AVR, Low Voltage Variation, Change Positions, OLTC Control.

Keywords: Power Transformer, On-load Tap Changer, AVR, Low Voltage Variation, Change Positions, OLTC Control. www.semargroup.org, www.ijsetr.com ISSN 2319-8885 Vol.03,Issue.11 June-2014, Pages:2487-2493 Advance OLTC Control for Improving Power System Voltage Stability NWE NWE SOE 1, KYAW SAN LWIN 2 1 Dept of Electrical

More information

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative: Address: Fax Number:

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative:  Address: Fax Number: Interconnection of a Customer-Owned Renewable Generation System of Greater than 100 KW and Less than or Equal to 1 MW to the LCEC Electric Grid Tier 3 Application and Compliance Form Instructions: Complete

More information

APPENDIX A MATLAB CODE FOR CALCULATION OF MOTOR TORQUE

APPENDIX A MATLAB CODE FOR CALCULATION OF MOTOR TORQUE APPENDIX A MATLAB CODE FOR CALCULATION OF MOTOR TORQUE Table 1 MATLAB code for calculating motor torque[1] %Definition of Motor Parameters V=4000/sqrt(3); %Phase voltage NoPh=3; %Number of Phase NoPo=2

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE The following is PG&E's procedure for pre-energization inspections. For PG&E to provide the Load

More information

S C Strength of Winding Exits and Leads : A critical area for Failure Prevention in Power Transformers

S C Strength of Winding Exits and Leads : A critical area for Failure Prevention in Power Transformers S C Strength of Winding Exits and Leads : A critical area for Failure Prevention in Power Transformers by MANAN PANDYA SIEMENS LTD. manan.pandya@siemens.com 1 Introduction Short circuit withstand capability

More information

Diploma in Electrical Installations. (Buildings and Structures) Unit 202 Workbook PRE-ATTENDANCE REVISION V1

Diploma in Electrical Installations. (Buildings and Structures) Unit 202 Workbook PRE-ATTENDANCE REVISION V1 2365-02 Diploma in Electrical Installations (Buildings and Structures) Unit 202 Workbook PRE-ATTENDANCE REVISION V1 Welcome This booklet is designed to outline the areas that you will study when you complete

More information

A Study on Ferroresonance Mitigation Techniques for Power Transformer

A Study on Ferroresonance Mitigation Techniques for Power Transformer A Study on Ferroresonance Mitigation Techniques for Power Transformer S. I. Kim, B. C. Sung, S. N. Kim, Y. C. Choi, H. J. Kim Abstract--This paper presents a comprehensive study on the ferroresonance mitigation

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE

MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE Scott Storrar Contributors: Bill Hansen, Kyle Reddell, Tom McGrath Basic Mobile Sub Design Equipment mounted on semi-trailer Power transformer

More information

Case Identification Data. Bus Data. Load Data. Fixed Bus Shunt Data. Generator Data. Non-Transformer Branch Data. Transformer Data

Case Identification Data. Bus Data. Load Data. Fixed Bus Shunt Data. Generator Data. Non-Transformer Branch Data. Transformer Data Case Identification Data Bus Data Load Data Fixed Bus Shunt Data Generator Data Non-Transformer Branch Data Transformer Data Area Interchange Data Two-Terminal DC Transmission Line Data Voltage Source

More information

Exercises on overhead power lines (and underground cables)

Exercises on overhead power lines (and underground cables) Exercises on overhead power lines (and underground cables) 1 From the laws of Electromagnetism it can be shown that l c = 1 v 2 where v is the speed of propagation of electromagnetic waves in the environment

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Unit 29 Three-Phase Transformers

Unit 29 Three-Phase Transformers Unit 29 Three-Phase Transformers Objectives: Discuss the construction of three-phase transformers. Discuss the formation of a three-phase transformer bank. Discuss primary and secondary connections. Objectives:

More information

SECTION 4: TRANSMISSION LINES. ESE 470 Energy Distribution Systems

SECTION 4: TRANSMISSION LINES. ESE 470 Energy Distribution Systems SECTION 4: TRANSMISSION LINES ESE 470 Energy Distribution Systems 2 Introduction Transmission Lines 3 Transmission and distribution of electrical power occurs over metal cables Overhead AC or DC Underground

More information

Phase Shifting Transformers. Presented by

Phase Shifting Transformers. Presented by Phase Shifting Transformers Presented by Phase Shifting Transformers (PST s) (a.k.a. Phase Angle Regulators) VS φ S P V V S = X L L X L sin( φ φ ) L S VL φ L PST s are power flow control devices between

More information

TRAX Transformer and Substation Test System

TRAX Transformer and Substation Test System Replaces need for multiple test sets Saves time by eliminating need for multiple instruments learning User-friendly interface reduces training and testing time Portable and compact system components for

More information

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch.

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch. Training Title POWER TRANSFORMERS Training Duration 5 days Training Venue and Dates Power transformers 5 20-24 May $3,300 Abu Dhabi In any of the 5 star hotel. The exact venue will be informed soon. Training

More information

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW Electric Utility Contact Information DTE Energy Interconnection Coordinator One Energy Plaza, SB

More information

Power Transformers Basics

Power Transformers Basics Power Transformers Basics Transformer Basic Objective Introduce Basic Transformer Theory as it Relates to Diagnostics Provide a Better Understanding of the Diagnostic Test Environment Identify Important

More information

Transformer Technology Seminar Winding Selection

Transformer Technology Seminar Winding Selection Pomona, CA May 24 25, 2016 Transformer Technology Seminar Siemens AG Transformers siemens.com/answers Windings: Page 2 Example GSU 274/464MVA H0 H1 H2 H3 U U I I H L H L N = N N = N L H H L HV: 405kV ±8x1.25%

More information

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations Case Study 1 Power System Planning and Design: Power Plant, Transmission Lines, and Substations Lindsay Thompson, 5203120 Presented to Riadh Habash ELG 4125 11/10/2013 1.0 ABSTRACT A power plant delivers

More information

Calculating and compensating for power transformer and cable (or line) losses - standard methods

Calculating and compensating for power transformer and cable (or line) losses - standard methods Guidance Calculating and compensating for power transformer and cable (or line) losses - standard methods Foreword This guidance sets out basic standard methods for calculating electrical loss compensation

More information

TRANSFORMER OPERATION

TRANSFORMER OPERATION Chapter 3 TRANSFORMER OPERATION 1 A transformer is a static device (no moving parts) used to transfer energy from one AC circuit to another. This transfer of energy may involve an increase or decrease

More information

AS the power distribution networks become more and more

AS the power distribution networks become more and more IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 21, NO. 1, FEBRUARY 2006 153 A Unified Three-Phase Transformer Model for Distribution Load Flow Calculations Peng Xiao, Student Member, IEEE, David C. Yu, Member,

More information

Appendix C-1. Protection Requirements & Guidelines Non-Utility Generator Connection to Okanogan PUD

Appendix C-1. Protection Requirements & Guidelines Non-Utility Generator Connection to Okanogan PUD A. Introduction Appendix C-1 Protection Requirements & Guidelines to Okanogan PUD The protection requirements identified in this document apply to Non-Utility Generating (NUG) facilities, Independent Power

More information

ETAP PowerStation. Electrical Transient Analyzer Program. ETAP PowerStation. Short Circuit Analysis. ANSI Standard 3-Phase Fault Currents

ETAP PowerStation. Electrical Transient Analyzer Program. ETAP PowerStation. Short Circuit Analysis. ANSI Standard 3-Phase Fault Currents Page: 1 Electrical Transient Analyzer Program Short Circuit Analysis ANSI Standard 3-Phase Fault Currents Number of Buses: Swing Generator Load Total 1 0 4 5 Number of Branches: XFMR2 XFMR3 Reactor Line/Cable

More information

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy Interconnection Coordinator 1945

More information

Phase Shifter Application Workshop. Siemens Energy, Inc.

Phase Shifter Application Workshop. Siemens Energy, Inc. Phase Shifter Application Workshop Siemens Energy, Inc. PJM Power Pool, March, 2015 siemens.com/energy Phase Shifter Application Workshop Phase Shifting Transformers Principles, Design Aspects and Operation

More information

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System WHO SHOULD FILE THIS SUBMITTAL: Anyone in the final stages of interconnecting a Generation System with Nodak Electric Cooperative, Inc. This submittal shall be completed and provided to Nodak Electric

More information

Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom

Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom Downloaded from orbit.dtu.dk on: Aug 3, 018 Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom Wu, Qiuwei; Solanas, Jose Ignacio Busca; Zhao, Haoran; Kocewiak,

More information