Modeling of Three-phase or Bank of Three Single Phase Three Winding Transformers Zero-phase-sequence Leakage Impedance in PSS E Short Circuit Module
|
|
- Philip McKenzie
- 6 years ago
- Views:
Transcription
1 Siemens Industry, Inc. Power Technology Issue 125 Modeling of Three-phase or Bank of Three Single Phase Three Winding Transformers Zero-phase-sequence Leakage Impedance in PSS E Short Circuit Module Carlos Grande-Moran, Ph.D. Principal Consultant carlos.grande@siemens.com The zero-phase-sequence impedance characteristics of three phase three winding transformers or a bank of three single phase three winding transformers depend on the winding connections and sometimes on their core construction. Presence of a delta winding connection introduces a path from the winding terminals to the reference of the zero-phase-sequence (ZPS) network. Two winding connections are presented in this newsletter because of their extensive use in 2x1 combined cycle plants and transmission substations. One is the connection Dyn0d and the other is the connection YN0yn0d with conventional 3 winding transformers or YNa0d with three-phase three-winding autotransformers. The Dyn0d connection is often used in 2x1 combined cycle plants to connect the two GTG units to the D connected windings and the wye grounded winding (HV) connects these 2 generating units to the transmission system. The connection YN0yn0d or YNa0d is often used in transmission substations connecting EHV and HV networks. Figures 1 and 2 below show the ZPS representation of these winding connections. Note that N0 is the reference (i.e., ground) for the ZPS network and 3ZG represents the grounding impedance that can be connected between the neutral point of wye connected windings and ground. If the wye connected windings are solidly grounded then ZG=0 and thus a zero impedance jumper is required in the model to connect the physical winding terminal and the terminal associated with the winding in the T equivalent network used for modeling 3 winding transformers. When the neutral of the wye connected windings is ungrounded the value for ZG is and thus an open circuit is used in the model to connect the physical winding terminal and the terminal associated with the winding in the T equivalent network. P Z01 R Z02 Z03 3ZG2 S t N0 Figure 1 - ZPS Equivalent Network for the Dyn0d Connection
2 P 3ZG1 Z01 R Z02 Z03 3ZG2 S t N0 Figure 2 - ZPS Equivalent Network for the or YN0yn0d or YNa0d Connection The ZPS data provided by the equipment manufacturer for the Dyn0d connected windings will be an equivalent zero sequence impedance between the terminals of the wye grounded winding and N0, Z0 in per unit on a three-phase MVA rating of the wye connected windings and the winding phase-phase base voltage. Now, since there is only one known impedance value and three unknowns (Z01, Z02 and Z03) then there are two degrees of freedoms when choosing the values of two of three unknown impedances. If, we select Z02 = Z0/2 then Z01=Z03=Z0 which is as good of a choice as any other for this winding connection. The user can select any other combination as long as it satisfies Eqn. 1 below, Z0 = Z01* Z03 Z02 Z01 Z03 Eqn. 1 Regarding the YN0yn0d or YNa0d winding connection, the equipment manufacturer provides the ZPS leakage impedances Z01, Z02 and Z03 in per unit on a winding common three-phase MVA base and phase-phase winding voltages. Occasionally, the equipment manufacturer provides the impedance voltage test report where the following tests are shown (assumption - winding 1 and winding 2 are wye connected with externally available neutral and winding 3 is delta connected) [1] : 1. Test 1: with phases A, B and C terminals of winding 1 short circuited apply a single phase voltage (Vph) between the shorted terminals and its neutral. All other windings are open circuited. The ratio Vph/Itest = Z013 = Z01 Z03 from Figure Test 2: with phases A, B and C terminals of winding 2 short circuited apply a single phase voltage (Vph) between the shorted terminals and its neutral. All other windings are open circuited. The ratio Vph/Itest = Z023 = Z02 Z03 from Figure Test 3: with phases A, B and C terminals of winding 1 short circuited apply a single phase voltage (Vph) between the shorted terminals and its neutral. Short the terminals A, B and C of winding 2. All other windings may be open-circuited or shorted. The ratio Vph/Itest =Z1NS = Z01 Z02//Z03. From Test 3 results, the impedance Z03 can be obtained using Eqn. 2 below, Page 2 Z03 = Z023 * (Z013 - Z1NS) Eqn. 2 Now, using the result from Eqn.2 one can compute the leakage impedances Z10 and Z20 from the results obtained in Tests 1 and 2 as follows, Z013 - Z03 Z01= Eq. 3 Z02 = Z023 - Z03 Eqn. 4
3 It is important to note transformer units with a 5 leg core type and shell type design have a zero-phase sequence leakage impedance that is equal to its positive-phase sequence leakage impedance and thus zero sequence voltage impedance tests are generally not needed. In the event that a test is performed then the 3 tests listed above should be carried out. The ZPS leakage impedance data required by the short circuit module in PSS E for three winding transformers of the type presented in this newsletter are as follows, 1. Dyn0d: a. CC=3 ; Z01, Z20 and Z30 b. CC=13 ; Z012 = Z01 Z02, Z023 = Z02 Z03 and Z031 = Z013 = Z01 Z03 c. If the neutral of the wye winding is grounded then enter ZG2 Note that the wye connected winding can be assigned to any of the 3 windings of the three-phase three winding transformer. Using the User Code option with the connection code (CC) flag, one can specify CC=133 and ZG1 for the YN0dd winding connection and CC=331 and ZG3 for the Ddyn0. Also it is important to note that the indices used in Eqn.1 ought to be changed accordingly to account for the location of the wye connected winding. 2. YN0yn0d or YNa0d: a. CC=2 ; Z01, Z02 and Z03 (for conventional 3 winding transformers) b. CC=12 ; Z012 = Z01 Z02, Z023 = Z02 Z03 and Z031 = Z013 = Z01 Z03 (for conventional 3 winding transformers) c. CC=17 ; Z012 = Z01 Z02, Z023 = Z02 Z03 and Z031 = Z013 = Z01 Z03 (for 3 winding autotransformers) d. If the neutral of the wye windings for conventional transformers are grounded then enter ZG1 for winding 1 and ZG2 for winding 2 e. If the neutral of the wye connected windings of the three winding autotransformer is grounded then enter ZG2 The delta winding connection can be assigned to any of the 3 windings in conventional three winding transformers. What is needed is to use the connection code flag CC with the option User Code. For example, if the delta winding is assigned to winding 1, the connection code will be CC=311 and grounding impedances ZG2 and ZG3 in the events the neutral of the wye connected windings is grounded through and impedance, and if the delta winding is assigned to winding 2 then CC=131 and the grounding impedances will be ZG1 and ZG3. Note that for the case CC=311, first the impedance Z10 (winding 1 is connected delta) is determined from Eqn. 2 replacing 3 with 1 and performing Test 1 to obtain the impedance Z021, Test 2 to obtain the impedance Z031 and Test 3 to obtain the impedance Z2NS = Z02 Z03// Z01. Then using Eqns. 3 and 4 the impedances Z02 and Z03 are determined replacing 1 with 3. Numerical Example The following original equipment manufacturer (OEM) test data is provided: Three-phase, three-winding autotransformer connected YNa0d solidly grounded HV circuit rated voltage 230 kv, MV circuit rated 115 kv and tertiary LV circuit rated 14.4 kv Impedance values are in percent on common MVA base of 168 MVA and 230/115/14.4 kv voltage base. Where NOMV1 = 230, NOMV2 = 115 and NOMV3 = Test 1: HV energized with single-phase voltage applied to A, B, C short circuited phase terminals. MV and LV open circuited. Z0HV-LV = Z0HV Z0LV = 0.778% j % 2. Test 2: MV energized with single-phase voltage applied to A, B, C short circuited phase terminals. HV and LV open circuited. Z0MV-LV = Z0MV Z0LV = 0.285% j 7.413% 3. Test 3: HV energized with single-phase voltage applied to A, B, C short circuited phase terminals. MV phase terminals short circuited and LV open or short circuited. Z1NS = Z0HV Z0MV //Z0LV = 0.291% j 5.364%. Page 3
4 Below is the test data provided by the OEM: From Test 3 and Eqn. 2, the zero-phase sequence impedance Z0LV is obtained: Z0LV = (Z0MV - LV) * (Z0HV - LV - Z1NS) = ( j ) * ( j ) Z0LV = = = j pu on 168MVA,230/115/14.4 kv base From Eqns. 3 and 4, Z0HV = Z0HV-LV Z0LV = j per unit on 168 MVA, 230/115/14.4 kv base Z0MV = Z0MV-LV Z0LV = j per unit on 168 MVA, 230/115/14.4 kv base Choosing W1 connected to a 230 kv bus (BASKV=230), W2 to a 115 kv bus (BASKV=115), W3 to a 13.8 kv bus (BASKV=13.8), CZ=CZ0=2, CZG=1, connection code CC=17 and vector group YNa0d1. The zero-phase impedance data is entered as follows: R01 j X01 = Z0HV-LV = Z120 = j pu on 168 MVA, 230/115/14.4 kv base R02 j X02 = Z0MV-LV = Z230 = j on 168 MVA, 230/115/14.4 kv base R03 j X03 = Z0HV-LV = Z310 = j on 168 MVA, 230/115/14.4 kv base ZG2 = 0.0 j 0.0 (solidly grounded) Page 4
5 Figures 3 and 4 below show the zero-phase sequence data record for the 3W autotransformer connected YNa0d Figure 3-3W Autotransformer Vector Group, Connection Code and Z0HV-LV Impedance Figure 4-3W Autotransformer Z0MV-LV and Z0HV-LV Impedances Figure 5 shows the GUI in PSS E that displays the connection and vector group for a three-phase, three winding autotransformer connected YNa0d Note that a phase shift of 11 (30 ), 1 (-30 ), 7 (150 ) and 5 (-150 ) can be chosen for the delta connected windings. Figure 5 - Vector Group and Connection Code for 3W Autotransformer Connected YNa0d1 Reference: [1] IEEE Std C , IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers, Sections 9.5.1, 9.5.2, and Page 5
Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved.
Pomona, CA, May 24 & 25, 2016 Tertiary Winding Design in wye-wye Connected Transformers Scope of Presentation > Tertiary vs. Stabilizing Winding? Tertiary vs. Stabilizing Winding? Need for Stabilizing
More informationGrounding Resistance
Grounding Resistance Substation grounding resistance is the resistance in ohms between the substation neutral and earth ground (zeropotential reference) An actual fall of potential test is the best way
More informationThe Advantages and Application of Three Winding Transformers
The Advantages and Application of Three Winding Transformers MSc, CEng, FIEE, FIMechE, FIPENZ Principal, Sinclair Knight Merz Abstract Although seldom used in Australia and New Zealand, three winding transformers
More information148 Electric Machines
148 Electric Machines 3.1 The emf per turn for a single-phase 2200/220- V, 50-Hz transformer is approximately 12 V. Calculate (a) the number of primary and secondary turns, and (b) the net cross-sectional
More informationBE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %
BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and
More informationLessons Learned in Model Validation for NERC Compliance
Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification
More informationRegional Technical Seminar TAP CHANGERS
Regional Technical Seminar TAP CHANGERS SPX Transformer Solutions, Inc. September 4, 2018 De-Energized and Load Tap Changers Jason Varnell Lead Design Engineer jason.varnell@spx.com SPX Transformer Solutions,
More informationSAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS)
SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS) SLIDE In this video, we will cover a sample exam problem for the Power PE Exam. This exam problem falls under the topic of Protection, which accounts for
More informationOPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES
OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES U AJMAL, GE Grid Solutions UK Ltd, usman.ajmal@ge.com S SUBRAMANIAN, GE Grid Solutions UK Ltd, sankara.subramanian@ge.com H Ha GE Grid Solutions
More informationUnderstanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON
Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser - OMICRON Transformers Diagnostic Testing - OVERALL DGA Oil Screen Power Factor / Capacitance Exciting Current Transformer
More informationLessons Learned in Model Validation for NERC Compliance
Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification
More informationThe Effect of Transformer s Vector Group on Retained Voltage Magnitude and Sag Frequency at Industrial Sites Due to Faults
The Effect of Transformer s Vector Group on Retained Voltage Magnitude and Sag Frequency at Industrial Sites Due to Faults M. N. Moschakis, V. V. Dafopoulos, I. G. Andritsos, E. S. Karapidakis, and J.
More informationShortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller
Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer Anura Perera, Paul Keller System Operator - Eskom Transmission Introduction During the design phase of
More informationGround Fault Detection using Zigzag Grounding Transformer in Ungrounded System
Ground Fault Detection using Zigzag Grounding Transformer in Ungrounded System Dhruvita Mandaliya 1, Ajay M. Patel 2, Tarang Thakkar 3 1 PG Student, Electrical Engineering Department, Birla Vishvakarma
More informationThe Polytransformer. The Multivoltage Substation Power Transformer
The Polytransformer The Multivoltage Substation Power Transformer The need for a single transformer for different transmission systems. Change of electric power industry to a fully competitive and deregulated
More informationRarely used, problems with unbalanced loads.
THREE-PHASE TRANSFORMERS Transformers used in three-phase systems may consist of a bank of three single-phase transformers or a single three-phase transformer which is wound on a common magnetic core.
More informationCourse 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC)
Name: Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC) 1. T F In three-phase four-wire delta systems rated 240/120 volts, sometimes
More informationDIFFERENTIAL PROTECTION METHODOLOGY FOR ARBITRARY THREE-PHASE POWER TRANSFORMERS
DFFERENTAL PROTECTON METHODOLOGY FOR ARBTRARY THREE-PHASE POWER TRANSFORMERS Z. Gaji ABB AB-SA Products, Sweden; zoran.gajic@se.abb.com Keywords: power transformer, phase shifting transformer, converter
More informationTesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis
feature By brandon dupuis An Introduction to Electrical diagnostic TesTIng of Power Transformers 38 Transformers are the largest, most expensive, and highly critical components of most utility substations.
More informationThree-Phase/Six-Phase Conversion Autotransformers
1554 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 18, NO. 4, OCTOBER 2003 Three-Phase/Six-Phase Conversion Autotransformers Xusheng Chen, Member, IEEE Abstract The first commercial demonstration of six-phase
More informationA Process for Evaluating the Degree of Susceptibility of a fleet of Power Transformers to Effects of GIC
1 A Process for Evaluating the Degree of Susceptibility of a fleet of Power Transformers to Effects of GIC Ramsis Girgis, Kiran Vedante, and Gary Burden ABB Power Transformers Abstract: There has been
More information86 chapter 2 Transformers
86 chapter 2 Transformers Wb 1.2x10 3 0 1/60 2/60 3/60 4/60 5/60 6/60 t (sec) 1.2x10 3 FIGURE P2.2 2.3 A single-phase transformer has 800 turns on the primary winding and 400 turns on the secondary winding.
More informationIn Class Examples (ICE)
In Class Examples (ICE) 1 1. A 3φ 765kV, 60Hz, 300km, completely transposed line has the following positive-sequence impedance and admittance: z = 0.0165 + j0.3306 = 0.3310 87.14 o Ω/km y = j4.67 410-6
More informationISSN: [IDSTM-18] Impact Factor: 5.164
IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY A REVIEW OF ROUTINE TESTING ON DISTRIBUTION TRANSFORMER Sukhbir Singh 1, Parul Jangra 2, Anoop Bhagat 3, Vipin Saini 4 1 Assistant
More informationReport on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL)
Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL) 1.0 Introduction: 1.1 DTL vide letter No. F.DTL/206/F.06/2015-16/Mgr(Bawana)/353 dated
More informationGrounding Recommendations for On Site Power Systems
Grounding Recommendations for On Site Power Systems Revised: February 23, 2017 2017 Cummins All Rights Reserved Course Objectives Participants will be able to: Explain grounding best practices and code
More informationNotes 1: Introduction to Distribution Systems
Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission
More informationUnderstanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA
Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser, OMICRON electronics Corp. USA Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser,
More informationQUESTIONNAIRE for Wind Farm Power Stations only
TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21
More informationReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria
ReliabilityFirst Regional Criteria 1 Disturbance Monitoring and Reporting Criteria 1 A ReliabilityFirst Board of Directors approved good utility practice document which are not reliability standards. ReliabilityFirst
More informationSimulations of open phase conditions on the high voltage side of YNd05-power plant transformers
Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers Disclaimer: All information presented in the report, the results and the related computer program, data,
More informationTransient Recovery Voltage at Transformer Limited Fault Clearing
Transient Recovery Voltage at Transformer Limited Fault Clearing H. Kagawa (Tokyo Electric power Company, Japan) A. Janssen (Liander N.V., the Netherlands) D. Dufounet (Consultant, France) H. Kajino, H.
More informationThe measurement and normalisation of dielectric dissipation factor for diagnostics of transformer insulation
DIAGNOSIS The measurement and normalisation of dielectric dissipation factor for diagnostics of transformer insulation Introduction The Dielectric Dissipation Factor (DDF) is known as the loss factor or
More informationPower Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.
Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the
More informationREPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD.
REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD. (DTL) 1.0 Introduction: 1.1 DTL vide letter No. F.DTL/206/2015-16/Mgr(T)O&M-E-2/22
More informationTertiary Winding in Power Transformers P Ramachandran,India
Tertiary Winding in Power Transformers P Ramachandran,India 1. What is the function of tertiary and stabilizing tertiary windings in a Transformer? Tertiary Winding: An additional winding (third winding
More informationEN Assignment No.1 - TRANSFORMERS
EN-06 - Assignment No.1 - TRANSFORMERS Date : 13 th Jan 01 Q1) A 0kVA 00/0 Volts, 60Hz, single phase transformer is found to have the following equivalent circuit parameter referred to the high potential
More informationIDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)
IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone
More informationValidation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit
Validation of a Power Transformer Model for Ferroresonance with System Tests on a 4 kv Circuit Charalambos Charalambous 1, Z.D. Wang 1, Jie Li 1, Mark Osborne 2 and Paul Jarman 2 Abstract-- National Grid
More informationRelay-assisted commissioning
Relay-assisted commissioning by Casper Labuschagne and Normann Fischer, Schweitzer Engineering Laboratories (SEL) Power transformer differential relays were among the first protection relays to use digital
More informationProblems connected with Commissioning of Power Transformers
Problems connected with Commissioning of Power Transformers ABSTRACT P Ramachandran ABB India Ltd, Vadodara, India While commissioning large Power Transformers, certain abnormal phenomena were noticed.
More informationChapter 2: Transformers
Chapter 2: Transformers 2-1. The secondary winding of a transformer has a terminal voltage of v s (t) = 282.8 sin 377t V. The turns ratio of the transformer is 100:200 (a = 0.50). If the secondary current
More informationNeed for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design
IEEE PES Transmission and Distribution Conference 2008 Panel Session Large Wind Plant Collector Design Wind Farm Collector System Grounding by Steven W. Saylors, P.E. Chief Electrical Engineer Vestas Americas
More informationAPPLICATION OF DISTANCE PROTECTION FOR TRANSFORMERS IN ESKOM TRANSMISSION
APPLICATION OF DISTANCE PROTECTION FOR TRANSFORMERS IN ESKOM TRANSMISSION Kubendran Naicker In partial fulfilment of the requirements for the degree Master of Science in Power and Energy Systems School
More informationTutorial on Symmetrical Components
Tutorial on Symmetrical Components Part : Examples Ariana Amberg and Alex Rangel, Schweitzer Engineering Laboratories, nc. Abstract Symmetrical components and the per-unit system are two of the most fundamental
More informationTransformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications
The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications Minnesota Power Systems Conference November 3 5, 2009 Earl Brown Heritage Center University of
More informationTab 2 Voltage Stresses Switching Transients
Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles
More informationTransformer Thermal Impact Assessment White Paper (Draft) Project (Geomagnetic Disturbance Mitigation)
Transformer Thermal Impact Assessment White Paper (Draft) Project 2013-03 (Geomagnetic Disturbance Mitigation) TPL-007-1 Transmission System Planned Performance during Geomagnetic Disturbances Background
More informationTransformer Thermal Impact Assessment White Paper TPL Transmission System Planned Performance for Geomagnetic Disturbance Events
Transformer Thermal Impact Assessment White Paper TPL-007-2 Transmission System Planned Performance for Geomagnetic Disturbance Events Background Proposed TPL 007 2 includes requirements for entities to
More informationImpedance protection on power transformer.
Impedance protection on power transformer www.siemens.com/siprotec5 SIPROTEC 5 Application Impedance Protection on Power Transformer APN-045, Edition 1 Content 1...3 1.1 Introduction...3 1.2 Application
More informationCHAPTER 11. Balanced Three-Phase Circuits
CHAPTER 11 Balanced Three-Phase Circuits 11.1 Balanced Three-Phase Voltages Three sinusoidal voltages Identical amplitudes and frequencies Out of phase 120 with each other by exactly As the a-phase voltage,
More informationGMD Impacts on Generators
Walling Energy Systems Consulting, LLC GMD Impacts on Generators Reigh Walling 1 CME interacts with earth magnetic field Large solar flare - Coronal Mass Ejection (CME) Protons and electrons in solar wind
More informationUnderstanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques
Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Charles Sweetser, Services Manager, PRIM Engineering, Waltham, Mass. Topics of Discussion
More informationR10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours
Code No: R3 R1 Set No: 1 III B.Tech. II Semester Supplementary Examinations, January -14 POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Max Marks: 75 Answer any FIVE Questions
More informationPower Transformers Basics
Power Transformers Basics Transformer Basic Objective Introduce Basic Transformer Theory as it Relates to Diagnostics Provide a Better Understanding of the Diagnostic Test Environment Identify Important
More informationA Comprehensive Approach for Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique
A Comprehensive Approach Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique Mahmoud Elfayoumy 1, Member, IEEE, and Carlos Grande Moran 2, Senior Member, IEEE Abstract: The
More informationTransformer Thermal Impact Assessment White Paper TPL Transmission System Planned Performance for Geomagnetic Disturbance Events
Transformer Thermal Impact Assessment White Paper TPL-007-2 Transmission System Planned Performance for Geomagnetic Disturbance Events Background Proposed TPL-007-2 includes requirements for entities to
More informationTopic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017
Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length
More informationTPL is a new Reliability Standard to specifically address the Stage 2 directives in Order No. 779.
Transformer Thermal Impact Assessment White Paper Project 2013-03 (Geomagnetic Disturbance Mitigation) TPL-007-12 Transmission System Planned Performance for Geomagnetic Disturbance Events Background On
More informationPROBLEMS on Transformers
PROBLEMS on Transformers (A) Simple Problems 1. A single-phase, 250-kVA, 11-kV/415-V, 50-Hz transformer has 80 turns on the secondary. Calculate (a) the approximate values of the primary and secondary
More informationAS the power distribution networks become more and more
IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 21, NO. 1, FEBRUARY 2006 153 A Unified Three-Phase Transformer Model for Distribution Load Flow Calculations Peng Xiao, Student Member, IEEE, David C. Yu, Member,
More informationThis document covers common questions concerning the design of an effectively grounded system.
This document covers common questions concerning the design of an effectively grounded system. To prevent against temporary overvoltage conditions when a line-to-ground fault occurs on the power grid.
More informationShort-Circuit Apparent Power of System Survey Comments
WG Item 87 Short-Circuit Apparent Power of System Survey Comments Again, the values given in Table 18 are totally unrealistic of system conditions. I do not know any systems for which the short-circuit
More informationUnit 27 Three-Phase Circuits
Unit 27 Three-Phase Circuits Objectives: Discuss the differences between threephase and single-phase voltages. Discuss the characteristics of delta and wye connections. Compute voltage and current values
More informationSmart Ground Test Report. Springfield Energy - Springfield Power Station Grounding System Evaluation
Smart Ground Test Report Springfield Energy - Springfield Power Station Grounding System Evaluation Prepared for *C.M. Burns *Springfield Energy Springfield Power Station U.S.A. Prepared by A. P. Sakis
More informationGround Fault Currents in Unit Generator-Transformer at Various NGR and Transformer Configurations
Ground Fault Currents in Unit Generator-Transformer at Various NGR and Transformer Configurations A.R. Sultan, M.W. Mustafa, M.Saini Faculty of Electrical Engineering Universiti Teknologi Malaysia (UTM)
More informationTRANSFORMER TECHNOLOGY GPT
Core-Form TRANSFORMER TECHNOLOGY GlobalPT Corporation performs research and engineering developments and co-ordination of works of technical partners in the field of technological progress and commercial
More informationSubstation Testing and Commissioning: Power Transformer Through Fault Test
1 Substation Testing and Commissioning: Power Transformer Through Fault Test M. Talebi, Member, IEEE, Power Grid Engineering Y. Unludag Electric Power System Abstract This paper reviews the advantage of
More informationPhase Shifting Transformers. Presented by
Phase Shifting Transformers Presented by Phase Shifting Transformers (PST s) (a.k.a. Phase Angle Regulators) VS φ S P V V S = X L L X L sin( φ φ ) L S VL φ L PST s are power flow control devices between
More informationLOW-RESISTANCE grounding resistors (LRGs) appear
IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 44, NO. 5, SEPTEMBER/OCTOBER 2008 1311 Grounding the Neutral of Electrical Systems Through Low-Resistance Grounding Resistors: An Application Case Massimo
More informationOptimization of power transformers based on operative service conditions for improved performance
21, rue d Artois, F-75008 PARIS A2-207 CIGRE 2012 http : //www.cigre.org SUMMARY Optimization of power transformers based on operative service conditions for improved performance A.Prieto, M.Cuesto, P.Pacheco,
More informationTransformers. 4.1 Basics
4 Transformers Ac transformers are one of the keys to allowing widespread distribution of electric power as we see it today. Transformers efficiently convert electricity to higher voltage for long distance
More informationECE 528 Understanding Power Quality
ECE 528 Understanding Power Quality http://www.ece.uidaho.edu/ee/power/ece528/ Paul Ortmann portmann@uidaho.edu 208-733-7972 (voice) Lecture 22 1 Today Homework 5 questions Homework 6 discussion More on
More informationएस.आर.प.स 40व प र ट क शनउप सम त क ब ठकक मऱएएज ड Additional Agenda Points for 40 th meeting of Protection Sub-Committee of SRPC
ANNEXURE I एस.आर.प.स 40व प र ट क शनउप सम त क ब ठकक मऱएएज ड Additional Agenda Points for 40 th meeting of Protection Sub-Committee of SRPC 1. ग र डडडस टबबन स / ग र डइन सडन टक वववरण - Details of Grid incidents:
More informationThis webinar brought to you by the Relion product family Advanced protection and control IEDs from ABB
This webinar brought to you by the Relion product family Advanced protection and control IEDs from ABB Relion. Thinking beyond the box. Designed to seamlessly consolidate functions, Relion relays are smarter,
More informationGENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW
GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy Interconnection Coordinator 1945
More informationDISTRIBUTION TRANSFORMERS
The University of New South Wales School of Electrical Engineering and Telecommunications Industrial and Commercial Power Systems Topic 4 DISTRIBUTION TRANSFORMERS A transformer is a static device that
More informationTransformer Thermal Impact Assessment White Paper Project (Geomagnetic Disturbance Mitigation)
Transformer Thermal Impact Assessment White Paper Project 2013-03 (Geomagnetic Disturbance Mitigation) TPL-007-1 Transmission System Planned Performance for Geomagnetic Disturbance Events Background On
More informationHarmonic Planning Levels for Australian Distribution Systems
Abstract Harmonic Planning Levels for Australian Distribution Systems V.J. Gosbell 1, V.W. Smith 1, D. Robinson 1 and W. Miller 2 1 Integral Energy Power Quality Centre, University of Wollongong 2 Standards
More informationADVANCES IN INDUSTRIAL SUBSTATION DESIGN USING THREE WINDING POWER TRANSFORMERS
ADVANCES IN INDUSTRIAL SUBSTATION DESIGN USING TREE WINDING POWER TRANSFORMERS Copyright Material IEEE Paper No. PCIC-2008-XX Doug Brooks P.Eng Don Morency P.Eng. Pascal Tang P.Eng Senior Member, IEEE
More informationCork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)
Cork Institute of Technology Bachelor of Science (Honours) in Electrical Power Systems - Award Instructions Answer FIVE questions. (EELPS_8_Y4) Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Examiners:
More informationDiscipline Electrical Testing Issue Date Certificate Number T-2837 Valid Until Last Amended on - Page 1 of 6 LOCATION 1
Post: Last Amended on - Page 1 of 6 LOCATION 1 I. TRANSFORMERS AND REACTORS 1. 500 MVA, 765 kv 500 MVA, 400 kv Ratio & Polarity Check Magnetic Balance & Magnetizing Current Measurement at Low Voltage Vector
More informationPROCEDURE. Part 3.5: Site-Specific Loss Adjustments PUBLIC. Market Manual 3: Metering. Issue 8.0 MDP_PRO_0011
PUBLIC MDP_PRO_0011 PROCEDURE Market Manual 3: Metering Part 3.5: Site-Specific Loss Adjustments Issue 8.0 This document provides guidance to metering service providers on how to calculate and submit Site-Specific
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationTab 8 Surge Arresters
s en em Tab 8 Surge Arresters Si Distribution System Engineering Course Unit 10 2017 Industry Inc., All Rights Reserved Surge Arresters The main protective devices against system transient overvoltages.
More informationPower Factor Insulation Diagnosis: Demystifying Standard Practices
Power Factor Insulation Diagnosis: Demystifying Standard Practices Dinesh Chhajer, PE 4271 Bronze Way, Dallas Tx Phone: (214) 330 3238 Email: dinesh.chhajer@megger.com ABSTRACT Power Factor (PF) testing
More informationNumbering System for Protective Devices, Control and Indication Devices for Power Systems
Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements
More informationTraining Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch.
Training Title POWER TRANSFORMERS Training Duration 5 days Training Venue and Dates Power transformers 5 20-24 May $3,300 Abu Dhabi In any of the 5 star hotel. The exact venue will be informed soon. Training
More informationImpact Assessment Generator Form
Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project
More informationSDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-II) OVERHEAD NETWORK GROUNDING. Rev. 01
SEC DISTRIBUTION GROUNDING STANDARD SDCS-03 Part-II Rev.01 SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-II) OVERHEAD NETWORK GROUNDING Rev. 01 This specification is property of SEC
More informationof the improved scheme is presented. Index Terms Inrush current, power quality, transformer.
208 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 22, NO. 1, JANUARY 2007 A Sequential Phase Energization Method for Transformer Inrush Current Reduction Transient Performance and Practical Considerations
More informationPower Systems Modelling and Fault Analysis
Power Systems Modelling and Fault Analysis Theory and Practice Nasser D. Tleis BSc, MSc, PhD, CEng, FIEE AMSTERDAM BOSTON HEIDELBERG LONDON NEW YORK OXFORD PARIS SAN DIEGO SAN FRANCISCO SINGAPORE SYDNEY
More informationExtensive LV cable network. Figure 1: Simplified SLD of the transformer and associated LV network
Copyright 2017 ABB. All rights reserved. 1. Introduction Many distribution networks around the world have limited earth-fault current by a resistor located in the LV winding neutral point of for example
More informationTPL Transmission System Planned Performance for Geomagnetic Disturbance Events
TPL-007-1 Transmission System Planned Performance for Geomagnetic Disturbance Events Stan Sliwa Transmission Planning RSCS Meeting May 18, 2017 www.pjm.com TPL-007-1 Purpose: Establish requirements for
More informationCompany Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System
Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels
More informationVoltage Sag Mitigation by Neutral Grounding Resistance Application in Distribution System of Provincial Electricity Authority
Voltage Sag Mitigation by Neutral Grounding Resistance Application in Distribution System of Provincial Electricity Authority S. Songsiri * and S. Sirisumrannukul Abstract This paper presents an application
More informationCode No: R Set No. 1
Code No: R05310204 Set No. 1 III B.Tech I Semester Regular Examinations, November 2007 ELECTRICAL MACHINES-III (Electrical & Electronic Engineering) Time: 3 hours Max Marks: 80 Answer any FIVE Questions
More information2 Grounding of power supply system neutral
2 Grounding of power supply system neutral 2.1 Introduction As we had seen in the previous chapter, grounding of supply system neutral fulfills two important functions. 1. It provides a reference for the
More informationCourse ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation
Course ELEC0014 - Introduction to electric power and energy systems Additional exercises with answers December 2017 Exercise A1 Consider the system represented in the figure below. The four transmission
More informationKeywords: Power Transformer, On-load Tap Changer, AVR, Low Voltage Variation, Change Positions, OLTC Control.
www.semargroup.org, www.ijsetr.com ISSN 2319-8885 Vol.03,Issue.11 June-2014, Pages:2487-2493 Advance OLTC Control for Improving Power System Voltage Stability NWE NWE SOE 1, KYAW SAN LWIN 2 1 Dept of Electrical
More information