Var Control. Adding a transformer and transformer voltage regulation. engineers loadflow program. The control system engineers loadflow.

Size: px
Start display at page:

Download "Var Control. Adding a transformer and transformer voltage regulation. engineers loadflow program. The control system engineers loadflow."

Transcription

1 November 2012 Adding a transformer and transformer voltage regulation to the control system engineers loadflow program The control system engineers loadflow program The loadflow program used by this website is principle tailored for 1. developing and testing voltage regulation routines in subsystems. 2. applying settings to reactive plant control routines. 3. understanding voltage regulation events in subsystem. The load flow program provides a steady state voltage solution for a particular subsystem loading condition. The load flow program is an excel VBA program that uses the Gauss-Seidel iteration method to find a solution. The excel workbook is separated into three sheets, the load flow worksheet,the subsystem worksheet and miscellaneous worksheet called potpourri. The subsystem worksheet starts with a diagram of the subsystem under investigation. The loadflow program s results will take up about the first 28 rows of the subsystem worksheet and the subsystem diagram can be placed below the loadflow results. The power and reactive power values can be transferred down to the diagram by referencing the loadflow result s row and column as a formula. The load flow sheet is the entry point for the subsystem parameters. There are two tables the bus connection table and the busbar table. The bus connection table is where the transmission line or transformer π equivalent circuits are added adjacent the assigned source busbar and destination busbar numbers. (see transformer tapchanger control article for details on the transformer π equivalent circuit) The busbar table is the entry point for peak busbar loads and generation and the percentage of the peak load required for a particular solution. Also the busbar name and the assumed busbar volts can be changed. The potpourri worksheet is for miscellaneous tables used to store data. The subsystem diagram below show the subsystem impedance parameters in blue. These are subsystem values that are entered on the loadflow worksheet.

2 Page 2 The bus connection table below shows an entry for the main system transformer connected between source bus one and destination bus two. The reactance and transformer tap are the only fields entered. The transformer tap is reference from the subsystem worksheet as show in the formula bar. For an initial run place a value of say 1.02 in the subsystem worksheet cell referenced by the transformer tap cell. The connection status is discussed later and the field is left blank. To add a line to the bus connection table select the source bus and destination bus numbers and add the resistance reactance and line charging fields in per cent on 100MVA base. The diagram below shows the entries for lines between buses 2 and 3 and between buses 2 to 5. The value in cell F27 is the line conductance in pu and the value in cell G27 the line series susceptance in pu. Cells H27 and I27 are shunt susceptance in pu split at each end of the line. These values are used by the loadflow program.

3 Page 3 The busbar table is shown below. This is where the busbar peak load and any generation is added in MW and MVArs. The load value can be adjusted by using the percentage of peak load column. Busbar 1 is the swing bus at which the voltage is specified and the power and reactance power are the variables. The busbar names can be added for clarity. busbar volts loadflow results are displayed in the calculated bus volts column in pu quantities. The calculated bus volts column can be transferred to the subsystem diagram and multiplied by the base volts. The main system 132 busbar volts on the subsystem worksheet diagram cell is selected and the formula bar shows the formula that is transferred from the loadflow worksheetcalculated bus volts column. Reactive plant can be added to busbars such as shown on busbar 6 where 12MVAr is shown. The

4 Page 4 All of the loadflow commands are on the custumize quick access tool bar at the very top of the excel window. The circled i will run the loadflow program. However before running the loadflow program the transformer off-nominal tap ratio has to be added to the transformers. As shown in the adjacent diagram below the transformer symbol place tap= in the left cell and a tap number in the adjacent cell. The transformer tapchanger ratio icon is then selected on the quick access toolbar. tapchanger_ratio bus_volts_and_loadflow

5 Page 5 The transformer tapchanger ratio userform is displayed with two options a main system transformer or a subsystem transformer. The main system transformer is selected in this case and the tap position cell below the transformer symbol is added to the userform. The off-nominal tap ratio formula will be added to the right of the tap position. The off-nominal tap ratio has to be transferred back to the loadflow worksheet as shown in the formula bar below. The off-nominal tap operation needs to be repeated for all subsys- tem transformers. The transformer voltage regulation now needs to be added to the transformers. The transformervr table is selected on the quick access toolbar and userform completed as shown below.

6 Page 6 The transformer voltage regulation table is added as shown in the diagram adjacent below the transformer tap position. The tapchanger command has been highlighted in red and the per cent error shows that about five tapchange operations are required. The setpointv in kv is the voltage on the loadline. The error is the difference between the setpointv and the busbar volts expressed as a per cent of nominal volts. The tap position needs to be raised to tap 7 before the tapchanger raise command is removed. The error need to be below 0.9 percent to be in the deadband. The three diagrams show the tap position adjusted to show the difference tapchanger commands. The load drop compensation on the main system transformer only boosts the voltage to 105 percent of nominal. This is because generation in the subsystem can be kept at a voltage below 110 percent.

7 Page 7 The subsystem worksheet diagram with all of the transformer tapchangers and voltage regulation added is shown below. The subsystem substations loading is peak load with the subsystem transformer boosting the distribution system voltage to 105 per cent. A 12MVAr capacitor is in service at Kaputar 66kV busbar. The subsystem substation loading is adjusted to light loading conditions at about 30 per cent of peak load with the subsystem transformer regulating the distribution system voltage to 100 per cent. The Kaputar 12MVAr capacitor has been left in service. This has the affect at light loading of cause the main system transformer to be near the tapchanger limit (tap 2). The main system voltage can be above 105 per cent and this would cause the tapchanger to reach its limit. The control system engineer is responsible for keeping the tapchangers within limits and the capacitor would need to be remove from service for light loads. Capacitor are entered into the loadflow program in the busbar table on the loadflow worksheet. The capacitor MVArs at busbar column required the nominal rating of the reactive plant. The nominal rating is the same value as the susceptance in per cent for 100MVA base. Multiplier top and bottom by V b = B * V 2 b / V b * I b *100 = MVAr rating / 100 MVA * 100 = MVAr rating %B susceptance = B/B base *100 = B / I b /V b *100 = B*V b /I b * 100

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Level 6 Graduate Diploma in Engineering Electrical Energy Systems 9210-114 Level 6 Graduate Diploma in Engineering Electrical Energy Systems Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler,

More information

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Code No: R3 R1 Set No: 1 III B.Tech. II Semester Supplementary Examinations, January -14 POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Max Marks: 75 Answer any FIVE Questions

More information

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation Course ELEC0014 - Introduction to electric power and energy systems Additional exercises with answers December 2017 Exercise A1 Consider the system represented in the figure below. The four transmission

More information

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur Lecture - 10 Transmission Line Steady State Operation Voltage Control (Contd.) Welcome

More information

Voltage Source Converter Modelling

Voltage Source Converter Modelling Voltage Source Converter Modelling Introduction The AC/DC converters in Ipsa represent either voltage source converters (VSC) or line commutated converters (LCC). A single converter component is used to

More information

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014 Constant Terminal Voltage Working Group Meeting 4 19 th September 014 Overview Options summary System under investigation Options analysis Discussion Options Option 1 Constant Terminal Voltage controlled

More information

SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS)

SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS) SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS) SLIDE In this video, we will cover a sample exam problem for the Power PE Exam. This exam problem falls under the topic of Protection, which accounts for

More information

Grounding Resistance

Grounding Resistance Grounding Resistance Substation grounding resistance is the resistance in ohms between the substation neutral and earth ground (zeropotential reference) An actual fall of potential test is the best way

More information

In Class Examples (ICE)

In Class Examples (ICE) In Class Examples (ICE) 1 1. A 3φ 765kV, 60Hz, 300km, completely transposed line has the following positive-sequence impedance and admittance: z = 0.0165 + j0.3306 = 0.3310 87.14 o Ω/km y = j4.67 410-6

More information

Exercises on overhead power lines (and underground cables)

Exercises on overhead power lines (and underground cables) Exercises on overhead power lines (and underground cables) 1 From the laws of Electromagnetism it can be shown that l c = 1 v 2 where v is the speed of propagation of electromagnetic waves in the environment

More information

UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2016

UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2016 UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2016 FACULTY OF SCIENCE AND ENGINEERING DEPARTMENT OF ELECTRICAL AND ELECTRONIC ENGINEERING TITLE OF PAPER: POWER SYSTEM ANALYSIS AND OPERATION COURSE

More information

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 % BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and

More information

Initial Application Form for Connection of Distributed Generation (>10kW)

Initial Application Form for Connection of Distributed Generation (>10kW) Please complete the following information and forward to Vector Contact Details Primary Contact (who we should contact for additional information) Contact person Company name Contact numbers Daytime: Cell

More information

Analysis of a 405 km transmission line with series compensation

Analysis of a 405 km transmission line with series compensation Analysis of a 405 km transmission line with series compensation by Dr. Rupert Gouws, North-West University This paper presents an investigative case study and energy efficiency analysis of the 405 km,

More information

Case Identification Data. Bus Data. Load Data. Fixed Bus Shunt Data. Generator Data. Non-Transformer Branch Data. Transformer Data

Case Identification Data. Bus Data. Load Data. Fixed Bus Shunt Data. Generator Data. Non-Transformer Branch Data. Transformer Data Case Identification Data Bus Data Load Data Fixed Bus Shunt Data Generator Data Non-Transformer Branch Data Transformer Data Area Interchange Data Two-Terminal DC Transmission Line Data Voltage Source

More information

Impact of Thyristor Controlled Series Capacitor on Voltage Profile of Transmission Lines using PSAT

Impact of Thyristor Controlled Series Capacitor on Voltage Profile of Transmission Lines using PSAT Impact of Thyristor Controlled Series Capacitor on Voltage Profile of Transmission Lines using PSAT Babar Noor 1, Muhammad Aamir Aman 1, Murad Ali 1, Sanaullah Ahmad 1, Fazal Wahab Karam. 2 Electrical

More information

ELEN 460 Computer Laboratory Exercise No: 2 Analysis and Operation of Three-Phase Power Systems

ELEN 460 Computer Laboratory Exercise No: 2 Analysis and Operation of Three-Phase Power Systems Objectives: ELEN 460 Computer Laboratory Exercise No: 2 nalysis and Operation of Three-Phase Power Systems 1. Learn the basics of using PowerWorld Simulator to model balanced three-phase systems. 2. Correct

More information

Primii pasi in PSS/E. Hardware and Software Requirements

Primii pasi in PSS/E. Hardware and Software Requirements Univesitatea Tehnică a Moldovei Facultatea de Energetică Catedra Electroenergetica Primii pasi in PSS/E lect.sup. Victor Gropa «Programarea si Utilizarea Calculatoarelor II» Hardware and Software Requirements

More information

Keywords: Power Transformer, On-load Tap Changer, AVR, Low Voltage Variation, Change Positions, OLTC Control.

Keywords: Power Transformer, On-load Tap Changer, AVR, Low Voltage Variation, Change Positions, OLTC Control. www.semargroup.org, www.ijsetr.com ISSN 2319-8885 Vol.03,Issue.11 June-2014, Pages:2487-2493 Advance OLTC Control for Improving Power System Voltage Stability NWE NWE SOE 1, KYAW SAN LWIN 2 1 Dept of Electrical

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Incorporation of Self-Commutating CSC Transmission in Power System Load-Flow

Incorporation of Self-Commutating CSC Transmission in Power System Load-Flow Queensland University of Technology From the SelectedWorks of Lasantha Bernard Perera Spring September 25, 2005 Incorporation of Self-Commutating CSC Transmission in Power System Load-Flow Lasantha B Perera,

More information

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods Proceedings of the th WSEAS International Conference on Power Systems, Beijing, China, September -, 200 Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing

More information

QUESTIONNAIRE for Wind Farm Power Stations only

QUESTIONNAIRE for Wind Farm Power Stations only TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

Techniques for the Control of Steady State Voltage in MV and LV Networks

Techniques for the Control of Steady State Voltage in MV and LV Networks Techniques for the Control of Steady State Voltage in MV and LV Networks by Dr Robert Barr, Electric Power Consulting Pty Ltd Prof. Vic Gosbell, University of Wollongong Mr Chis Halliday, Electrical Consulting

More information

Harmonic Planning Levels for Australian Distribution Systems

Harmonic Planning Levels for Australian Distribution Systems Abstract Harmonic Planning Levels for Australian Distribution Systems V.J. Gosbell 1, V.W. Smith 1, D. Robinson 1 and W. Miller 2 1 Integral Energy Power Quality Centre, University of Wollongong 2 Standards

More information

Summary of Relaying Reviews Reporting

Summary of Relaying Reviews Reporting Revised Attachment B (Agenda Item 6) Summary of Relaying Reviews -- 12-31-04 Reporting This form shall be used without modification to provide a summary of relaying reviews performed by each Transmisission

More information

Procedure for Obtaining data by Implementing Agency for Determination of PoC Transmission Charges and Losses

Procedure for Obtaining data by Implementing Agency for Determination of PoC Transmission Charges and Losses Procedure for Obtaining data by Implementing Agency for Determination of PoC Transmission Charges and Losses In compliance of Central Electricity Regulatory Commission (Sharing of inter-state Transmission

More information

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL Basically the HVDC transmission consists in the basic case of two convertor stations which are connected to each other by a transmission link consisting of an overhead

More information

A New Model For Outaging Transmission Lines In Large Electric Networks

A New Model For Outaging Transmission Lines In Large Electric Networks PE-018-PWRS-0-06-1998 This is a reformatted version of this paper. An original can be obtained from the IEEE. A New Model For Outaging Transmission s In Large Electric Networks Eugene G. Preston, M City

More information

Transactions on Information and Communications Technologies vol 16, 1996 WIT Press, ISSN

Transactions on Information and Communications Technologies vol 16, 1996 WIT Press,  ISSN An expert system for teaching voltage control in power systems M. Negnevitsky & T. L. Le Department of Electrical & Electronic Engineering University of Tasmania GPO Box 252C Hobart, Tasmania 7001, Australia

More information

The Advantages and Application of Three Winding Transformers

The Advantages and Application of Three Winding Transformers The Advantages and Application of Three Winding Transformers MSc, CEng, FIEE, FIMechE, FIPENZ Principal, Sinclair Knight Merz Abstract Although seldom used in Australia and New Zealand, three winding transformers

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

POWER CORPORATION. Power Quality. Specifications and Guidelines for Customers. Phone: Fax:

POWER CORPORATION. Power Quality. Specifications and Guidelines for Customers. Phone: Fax: POWER CORPORATION Power Quality Specifications and Guidelines for Customers Phone: 403-514-3700 Fax: 403-514-3719 1 GENERAL OVERVIEW........................................ 1.1 WHAT DOES THIS SPECIFICATION

More information

Exercise 1: Power Division

Exercise 1: Power Division Power in AC Circuits AC 2 Fundamentals Exercise 1: Power Division EXERCISE OBJECTIVE When you have completed this exercise, you will be able to determine ac power division among the components of an RLC

More information

ERCOT shall post the extraordinary dispatch details used in each case to the POI website.

ERCOT shall post the extraordinary dispatch details used in each case to the POI website. Docket Nos. 44547 & 44649 CAL-NRG 01-34 Attachment 3 ERCOT Steady State Working Group Procedure Manual doc Page 20 of 58 ERCOT shall post the extraordinary dispatch details used in each case to the POI

More information

Fault Ride Through Technical Assessment Report Template

Fault Ride Through Technical Assessment Report Template Fault Ride Through Technical Assessment Report Template Notes: 1. This template is intended to provide guidelines into the minimum content and scope of the technical studies required to demonstrate compliance

More information

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination Phase Distance (21) and Voltage-Controlled or Voltage-Restrained Overcurrent Protection (51V) NERC Protection Coordination Webinar Series June

More information

Power Quality enhancement of a distribution line with DSTATCOM

Power Quality enhancement of a distribution line with DSTATCOM ower Quality enhancement of a distribution line with DSTATCOM Divya arashar 1 Department of Electrical Engineering BSACET Mathura INDIA Aseem Chandel 2 SMIEEE,Deepak arashar 3 Department of Electrical

More information

Application of a thyristor-controlled series reactor to reduce arc furnace flicker

Application of a thyristor-controlled series reactor to reduce arc furnace flicker ELEKTROTEHNIŠKI VESTNIK 78(3): 112-117, 2011 ENGLISH EDITION Application of a thyristor-controlled series reactor to reduce arc furnace flicker Ljubiša Spasojević, Boštjan Blažič, Igor Papič University

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS

LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS Giuseppe Di Marzio NTNU giuseppe.di.marzio@elkraft.ntnu.no Olav B. Fosso NTNU olav.fosso@elkraft.ntnu.no Kjetil Uhlen SINTEF

More information

Wheels Diameter / Conversion of Units

Wheels Diameter / Conversion of Units Note to the teacher On this page, students will learn about the relationships between wheel diameter, circumference, revolutions and distance. They will also convert measurement units and use fractions

More information

Development and Analysis of Nordic32 Power System Model in PowerFactory

Development and Analysis of Nordic32 Power System Model in PowerFactory KTH Electrical Engineering Development and Analysis of Nordic32 Power System Model in PowerFactory Master Thesis by Dimitrios Peppas Supervisor: Valerijs Knazkins Examiner: Mehrdad Ghandhari XR-EE-ES 2008:007

More information

Harmonics Issues that Limit Solar Photovoltaic Generation on Distribution Circuits

Harmonics Issues that Limit Solar Photovoltaic Generation on Distribution Circuits WREF 01 Paper # 048 Harmonics Issues that Limit Solar Photovoltaic Generation on Distribution Circuits Ketut Dartawan Ricardo Austria, Le Hui and Mark Suehiro* Pterra Consulting Maui Electric Company*

More information

148 Electric Machines

148 Electric Machines 148 Electric Machines 3.1 The emf per turn for a single-phase 2200/220- V, 50-Hz transformer is approximately 12 V. Calculate (a) the number of primary and secondary turns, and (b) the net cross-sectional

More information

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009 Lab 1 Objectives In this lab, our objective is to simulate a simple single machine infinite bus configuration using the PowerWorld Simulator software. We design a local generator system (a synchronous

More information

ETAP PowerStation 4.0

ETAP PowerStation 4.0 ETAP PowerStation 4.0 User Guide Copyright 2001 Operation Technology, Inc. All Rights Reserved This manual has copyrights by Operation Technology, Inc. All rights reserved. Under the copyright laws, this

More information

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES C.E.T. Foote*, G.W. Ault*, J.R. McDonald*, A.J. Beddoes *University of Strathclyde, UK EA Technology Limited, UK c.foote@eee.strath.ac.uk

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines

Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines David K Olson Paul Nyombi Xcel Energy Pratap G Mysore Pratap Consulting Services Minnesota Power Systems Conference St.

More information

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014 BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014 Expiry Year: 2018 APPROVED BY: Original signed by: Paul

More information

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting Document C-29 Procedures for System Modeling: January 5 th, 2016 TFSS Revisions Clean Open Process Posting Prepared by the SS-37 Working Group on Base Case Development for the Task Force on System Studies.

More information

The power transformer

The power transformer ELEC0014 - Introduction to power and energy systems The power transformer Thierry Van Cutsem t.vancutsem@ulg.ac.be www.montefiore.ulg.ac.be/~vct November 2017 1 / 35 Power transformers are used: to transmit

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

~ RG1 ~ RG2 ~ RG3 COORDINATION OF REGULATION SYSTEMS FOR GENERATORS AND TRANSFORMERS IN AN INDUSTRIAL COMBINED HEAT AND POWER PLANT 1.

~ RG1 ~ RG2 ~ RG3 COORDINATION OF REGULATION SYSTEMS FOR GENERATORS AND TRANSFORMERS IN AN INDUSTRIAL COMBINED HEAT AND POWER PLANT 1. 49 COORDINATION OF REGULATION SYSTEMS FOR GENERATORS AND TRANSFORMERS IN AN INDUSTRIAL COMBINED HEAT AND POWER PLANT 1. INTRODUCTION All the national combined heat and power plants work with the national

More information

Transient Stability Improvement Of IEEE 9 Bus System With Shunt FACTS Device STATCOM

Transient Stability Improvement Of IEEE 9 Bus System With Shunt FACTS Device STATCOM Transient Stability Improvement Of IEEE 9 Bus System With Shunt FACTS Device STATCOM P.P. Panchbhai 1, P.S.Vaidya 2 1Pratiksha P Panchbhai, Dept. of Electrical Engineering, G H Raisoni College of Engineering

More information

Power System Analysis (EE-456) For BE (EE)

Power System Analysis (EE-456) For BE (EE) PRACTICAL WORK BOOK Power System Analysis (EE-456) For BE (EE) Name: Roll Number: Year: Batch: Department: Section: Semester: N.E.D. University of Engineering & Technology, Karachi SAFETY RULES 1. Please

More information

Harmonics Appendix A2, PCFLO User Manual, June Summary of PCFLO Files

Harmonics Appendix A2, PCFLO User Manual, June Summary of PCFLO Files 1. Summary of PCFLO Files Input (note any lines in input files that begin with a colon in column 1 are treated as comments and are skipped) ADAT.CSV: Loadflow area input data. (PCFLO also creates temporary

More information

Static Synchronous Compensator (STATCOM) for the improvement of the Electrical System performance with Non Linear load 1

Static Synchronous Compensator (STATCOM) for the improvement of the Electrical System performance with Non Linear load 1 Static Synchronous Compensator (STATCOM) for the improvement of the Electrical System performance with Non Linear load MADHYAMA V. WANKHEDE Department Of Electrical Engineering G. H. Raisoni College of

More information

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström EH27401 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsn@ics.kth.se 1 Course map 2 Outline 1. Power System Topologies Transmission Grids vs Distribution grids Radial grids

More information

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Presenter Mark McVey C4/B5.41 INTERNATIONAL COUNCIL ON LARGE

More information

IGEE 402 Power System Analysis. FINAL EXAMINATION Fall 2004

IGEE 402 Power System Analysis. FINAL EXAMINATION Fall 2004 IGEE 40 Power System Analysis FINAL EXAMINATION Fall 004 Special instructions: - Duration: 150 minutes. - Material allowed: a crib sheet (double sided 8.5 x 11), calculator. - Attempt 4 out of 7 questions.

More information

EL 403 MODEL TEST PAPER - 1 POWER SYSTEMS. Time: Three Hours Maximum Marks: 100

EL 403 MODEL TEST PAPER - 1 POWER SYSTEMS. Time: Three Hours Maximum Marks: 100 POWER SYSTEMS Time: Three Hours Maximum Marks: 0 Answer five questions, taking ANY TWO from Group A, any two from Group B and all from Group C. All parts of a question (a, b, etc. ) should be answered

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Applicability 1 Section 502.8 applies to: (a) the legal owner of a generating unit: (i) connected to the transmission facilities in the balancing authority area

More information

APPENDIX A MATLAB CODE FOR CALCULATION OF MOTOR TORQUE

APPENDIX A MATLAB CODE FOR CALCULATION OF MOTOR TORQUE APPENDIX A MATLAB CODE FOR CALCULATION OF MOTOR TORQUE Table 1 MATLAB code for calculating motor torque[1] %Definition of Motor Parameters V=4000/sqrt(3); %Phase voltage NoPh=3; %Number of Phase NoPo=2

More information

PIONEER RESEARCH & DEVELOPMENT GROUP

PIONEER RESEARCH & DEVELOPMENT GROUP IJREAT International Journal of Research in Engineering & Advanced Technology, Volume 2, Issue 5, Oct-Nov, 14 ISSN: 23 8791 (Impact Factor: 1.479) Ac Network Analyzer A A Dynamic Benchmark For System Study

More information

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Cork Institute of Technology Bachelor of Science (Honours) in Electrical Power Systems - Award Instructions Answer FIVE questions. (EELPS_8_Y4) Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Examiners:

More information

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Unit Auxiliary Transformer (UAT) Relay Loadability Report Background and Objective Reliability Standard, PRC 025 1 Generator Relay Loadability (standard), developed under NERC Project 2010 13.2 Phase 2 of Relay Loadability: Generation, was adopted by the NERC

More information

Optimal Placement of UPFC for Voltage Drop Compensation

Optimal Placement of UPFC for Voltage Drop Compensation International Journal of Automation and Power Engineering, 2012, 1: 112-117 - 112 - Published Online August 2012 www.ijape.org Optimal Placement of UPFC for Voltage Drop Compensation Saber Izadpanah Tous

More information

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS Enrique PÉREZ Santiago REMENTERIA Aitor LAKA Arteche Spain Arteche Spain Ingeteam Power Technology-Spain ep@arteche.es sr@arteche.es Aitor.Laka@ingeteam.com

More information

CERN - ST Division THE NEW 150 MVAR, 18 KV STATIC VAR COMPENSATOR FOR SPS: BACKGROUND, DESIGN AND COMMISSIONING

CERN - ST Division THE NEW 150 MVAR, 18 KV STATIC VAR COMPENSATOR FOR SPS: BACKGROUND, DESIGN AND COMMISSIONING EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH ORGANISATION EUROPÉENNE POUR LA RECHERCHE NUCLÉAIRE CERN - ST Division ST-Note-2003-023 4 April 2003 THE NEW 150 MVAR, 18 KV STATIC VAR COMPENSATOR FOR SPS: BACKGROUND,

More information

ELECTRICAL POWER ENGINEERING

ELECTRICAL POWER ENGINEERING Introduction This trainer has been designed to provide students with a fully comprehensive knowledge in Electrical Power Engineering systems. The trainer is composed of a set of modules for the simulation

More information

UNIT TWO: Data for Simple Calculations. Enter and format a title Modify font style and size Enter column headings Move data Edit data

UNIT TWO: Data for Simple Calculations. Enter and format a title Modify font style and size Enter column headings Move data Edit data UNIT TWO: Data for Simple Calculations T o p i c s : Enter and format a title Modify font style and size Enter column headings Move data Edit data I. Entering and Formatting Titles: The information used

More information

each time the Frequency is above 51Hz. Continuous operation is required

each time the Frequency is above 51Hz. Continuous operation is required GC0101 EXTRACT OF EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 08/01/2018. ECC.6 ECC.6.1 ECC.6.1.1 ECC.6.1.2 ECC.6.1.2.1 ECC.6.1.2.1.1 ECC.6.1.2.1.2 ECC.6.1.2.1.3 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA

More information

POWER SYSTEM II LAB MANUAL

POWER SYSTEM II LAB MANUAL POWER SYSTEM II LAB MANUAL (CODE : EE 692) JIS COLLEGE OF ENGINEERING (An Autonomous Institution) Electrical Engineering Department Kalyani, Nadia POWER SYSTEM II CODE : EE 692 Contacts :3P Credits : 2

More information

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 Charles J. Mozina, Consultant Beckwith Electric Co., Inc. www.beckwithelectric.com I. Introduction During the 2003 blackout,

More information

A Comprehensive Approach for Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique

A Comprehensive Approach for Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique A Comprehensive Approach Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique Mahmoud Elfayoumy 1, Member, IEEE, and Carlos Grande Moran 2, Senior Member, IEEE Abstract: The

More information

University of Jordan School of Engineering Electrical Engineering Department. EE 219 Electrical Circuits Lab

University of Jordan School of Engineering Electrical Engineering Department. EE 219 Electrical Circuits Lab University of Jordan School of Engineering Electrical Engineering Department EE 219 Electrical Circuits Lab EXPERIMENT 7 RESONANCE Prepared by: Dr. Mohammed Hawa EXPERIMENT 7 RESONANCE OBJECTIVE This experiment

More information

Transient stability improvement by using shunt FACT device (STATCOM) with Reference Voltage Compensation (RVC) control scheme

Transient stability improvement by using shunt FACT device (STATCOM) with Reference Voltage Compensation (RVC) control scheme I J E E E C International Journal of Electrical, Electronics ISSN No. (Online) : 2277-2626 and Computer Engineering 2(1): 7-12(2013) Transient stability improvement by using shunt FACT device (STATCOM)

More information

Optimal Voltage Regulators Placement in Radial Distribution System Using Fuzzy Logic

Optimal Voltage Regulators Placement in Radial Distribution System Using Fuzzy Logic Optimal Voltage Regulators Placement in Radial Distribution System Using Fuzzy Logic K.Sandhya 1, Dr.A.Jaya Laxmi 2, Dr.M.P.Soni 3 1 Research Scholar, Department of Electrical and Electronics Engineering,

More information

AUTOMATIC CALCULATION OF RELAY SETTINGS FOR A BLOCKING PILOT SCHEME

AUTOMATIC CALCULATION OF RELAY SETTINGS FOR A BLOCKING PILOT SCHEME AUTOMATIC CALCULATION OF RELAY SETTINGS FOR A BLOCKING PILOT SCHEME Donald M. MACGREGOR Electrocon Int l, Inc. USA eii@electrocon.com Venkat TIRUPATI Electrocon Int l, Inc. USA eii@electrocon.com Russell

More information

Some aspects regarding harmonic s distortions propagation in large medium voltage distribution system

Some aspects regarding harmonic s distortions propagation in large medium voltage distribution system Some aspects regarding harmonic s distortions propagation in large medium voltage distribution system L. E. PETREAN 1, D. C. PETER 1, M. HORGOŞ 1, A. BUCHMANN 1, L. PETREAN 2 1 Electrical Engineering Department,

More information

ECEN 615 Methods of Electric Power Systems Analysis Lecture 8: Advanced Power Flow

ECEN 615 Methods of Electric Power Systems Analysis Lecture 8: Advanced Power Flow ECEN 615 Methods of Electric Power Systems nalysis Lecture 8: dvanced Power Flow Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas &M University overbye@tamu.edu nnouncements Read Chapter

More information

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/ ITC Holdings Planning Criteria Below 100 kv * Category: Planning Type: Policy Eff. Date/Rev. # 12/09/2015 000 Contents 1. Goal... 2 2. Steady State Voltage & Thermal Loading Criteria... 2 2.1. System Loading...

More information

Transmission Facilities Rating Methodology for Florida

Transmission Facilities Rating Methodology for Florida Document title Transmission Facilities Rating Methodology for Florida Document number EGR-TRMF-00001 Applies to: Transmission Engineering, Transmission System Operations, and Transmission Planning Duke

More information

Optimal Allocation of TCSC Devices Using Genetic Algorithms

Optimal Allocation of TCSC Devices Using Genetic Algorithms Proceedings of the 14 th International Middle East Power Systems Conference (MEPCON 10), Cairo University, Egypt, December 19-21, 2010, Paper ID 195. Optimal Allocation of TCSC Devices Using Genetic Algorithms

More information

Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link.

Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link. Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link. Mr.S.B.Dandawate*, Mrs.S.L.Shaikh** *,**(Department of Electrical Engineering, Walchand College of

More information

CHAPTER 3 COMBINED MULTIPULSE MULTILEVEL INVERTER BASED STATCOM

CHAPTER 3 COMBINED MULTIPULSE MULTILEVEL INVERTER BASED STATCOM CHAPTER 3 COMBINED MULTIPULSE MULTILEVEL INVERTER BASED STATCOM 3.1 INTRODUCTION Static synchronous compensator is a shunt connected reactive power compensation device that is capable of generating or

More information

Increasing Dynamic Stability of the Network Using Unified Power Flow Controller (UPFC)

Increasing Dynamic Stability of the Network Using Unified Power Flow Controller (UPFC) Increasing Dynamic Stability of the Network Using Unified Power Flow Controller (UPFC) K. Manoz Kumar Reddy (Associate professor, Electrical and Electronics Department, Sriaditya Engineering College, India)

More information

Fatima Michael college of Engineering and Technology

Fatima Michael college of Engineering and Technology Fatima Michael college of Engineering and Technology DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING EE2303 TRANSMISSION AND DISTRIBUTION SEM: V Question bank UNIT I INTRODUCTION 1. What is the electric

More information

Working with Formulas and Functions

Working with Formulas and Functions Working with Formulas and Functions Objectives Create a complex formula Insert a function Type a function Copy and move cell entries Understand relative and absolute cell references Objectives Copy formulas

More information

Electrical Power Systems

Electrical Power Systems Electrical Power Systems CONCEPT, THEORY AND PRACTICE SECOND EDITION SUBIR RAY Professor MVJ College of Engineering Bangalore PHI Learning Pfcte tofm Delhi-110092 2014 Preface xv Preface to the First Edition

More information

Information Document Facility Modelling Data ID # R

Information Document Facility Modelling Data ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Design and Simulation of Passive Filter

Design and Simulation of Passive Filter Chapter 3 Design and Simulation of Passive Filter 3.1 Introduction Passive LC filters are conventionally used to suppress the harmonic distortion in power system. In general they consist of various shunt

More information

Identification of weak buses using Voltage Stability Indicator and its voltage profile improvement by using DSTATCOM in radial distribution systems

Identification of weak buses using Voltage Stability Indicator and its voltage profile improvement by using DSTATCOM in radial distribution systems IOSR Journal of Electrical And Electronics Engineering (IOSRJEEE) ISSN : 2278-1676 Volume 2, Issue 4 (Sep.-Oct. 2012), PP 17-23 Identification of weak buses using Voltage Stability Indicator and its voltage

More information

Improving the Transient and Dynamic stability of the Network by Unified Power Flow Controller (UPFC)

Improving the Transient and Dynamic stability of the Network by Unified Power Flow Controller (UPFC) International Journal of Scientific and Research Publications, Volume 2, Issue 5, May 2012 1 Improving the Transient and Dynamic stability of the Network by Unified Power Flow Controller (UPFC) K. Manoz

More information

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements Robert Nelson Senior Expert Engineering Manager and Manager of Codes, Standards, and Regulations Siemens Wind Turbines -

More information

POWER WORLD LINEAR SENSITIVITY TOOLS

POWER WORLD LINEAR SENSITIVITY TOOLS POWER WORLD LINEAR SENSITIVITY TOOLS PWUWG #7 [6/30/15 7/1/15] Daniel Kuraspediani, -BPA - WHERE IS IT LOCATED Run mode Tools/Sensitivities PTDF s TLR/GSF LODF s & LCDF s Flow and Voltage Loss PTDF S Power

More information

Experience with Connecting Offshore Wind Farms to the Grid

Experience with Connecting Offshore Wind Farms to the Grid Oct.26-28, 2011, Thailand PL-22 CIGRE-AORC 2011 www.cigre-aorc.com Experience with Connecting Offshore Wind Farms to the Grid J. FINN 1, A. SHAFIU 1,P. GLAUBITZ 2, J. LOTTES 2, P. RUDENKO 2, M: STEGER

More information