Experience with Connecting Offshore Wind Farms to the Grid

Size: px
Start display at page:

Download "Experience with Connecting Offshore Wind Farms to the Grid"

Transcription

1 Oct.26-28, 2011, Thailand PL-22 CIGRE-AORC Experience with Connecting Offshore Wind Farms to the Grid J. FINN 1, A. SHAFIU 1,P. GLAUBITZ 2, J. LOTTES 2, P. RUDENKO 2, M: STEGER 2, A. ZSCHAU 2 1 Siemens, United Kingdom 2 Siemens, Germany SUMMARY Siemens Transmission and Distribution Ltd (STDL) are involved in connecting five of the UK Round 2 offshore wind farms to the Grid system. These projects range in size from 250MW to 630 MW in capacity. The paper intends to share STDL s experience on the design, installation, commissioning and delivery of these five wind farms. This will mainly be focused on scope split models used, onshore and offshore substation layout considerations, system study requirements and commissioning. KEYWORDS Grid Code, OFTO, Reactive Power Compensation, Voltage Sourced Converter, offshore platform layout, onshore substation layout, system studies. ahmed.shafiu@siemens.com.

2 1. Introduction Siemens has been involved in the design, installation and commissioning of five of the UK Round 2 offshore wind farms to the UK transmission and distribution network. These wind farm projects vary from 250MW to 630 MW in capacity. Two of these wind farms are connected onshore at 132kV whilst the other three are connected at 400kV. In the UK, the transmission assets at or above 132kV cannot be owned by a Generation Company and to this definition, the offshore transmission assets must be owned by an Offshore Transmission Operator (OFTO) for wind farm connections. Two of the wind farms have been commissioned and are in successful operation at present. The following sections share experience on design and delivery of offshore wind farms. In particular, the paper will look at the different contractual/scope split models used on these projects and present how the final solution of the grid connection has been engineered and delivered. The system studies required for the design of these wind farms are discussed considering the whole of the connection including how the steady state and dynamic reactive power requirements of the Grid Code are fulfilled by means of the use of hybrid Static Var Compensators (SVC) located at the onshore substation. The reasons for the different solutions adopted on the different wind farms are explained and considerations given to onshore and offshore substation layout/arrangement are discussed. 2 Overview of an offshore wind farm The main items of a Round 2 offshore wind farm are array cables, an offshore substation, export cables and an onshore substation as shown in Fig. 1. offshore substation onshore substation array string cables export cable Fig. 1. Main elements of an offshore wind farm The array cables form the Wind Turbine Generator (WTG) collection system which is connected to the offshore substation. The medium voltage collection system has always been at 33kV for the wind farms in UK. At the offshore substation, the collection voltage is stepped up to a suitable voltage for transmission which has mainly been from 33kV to 132kV except for one project where this has been from 33kV to 150kV. The export cable transmits the bulk power from the offshore substation to the onshore substation. The export cable in many instances has a significant land run which depends on the onshore connection point with the transmission or distribution network and the cable corridor for which the planning permission is available. For the five wind farms export cable lengths range from 23km to 60km. One significant feature of the onshore substation is the presence of a dynamic reactive power compensation plant which is required to meet the site specific connection agreement which basically requires wind farms to behave like conventional synchronous generators in terms of reactive power capability. The size of this compensation plant, depends on the wind farm MW entry capacity at the connection entry point (as stated in the Connection agreement), the export cable length and the available fixed compensation on the wind farm. The fixed compensation is from shunt reactors, filters and WTGs. 1

3 3 Wind farm Design Studies A number of studies are required to establish the design basis for the wind farm primary equipment. Such studies include load flow and losses, short circuit, harmonics, dynamic stability, insulation coordination, voltage fluctuation, protection coordination, earthing and electro magnetic interference studies. The size of the dynamic reactive power compensation plant is determined in the load flow study. An important point to note in the load flow study is the consideration given to the possibility of a harmonic filter for the wind farm. However, generally it has not been possible to do the harmonic studies upfront to establish the filter size. This is due to unavailability of connection point network impedance loci and background harmonic distortions at an early stage of the project. The approach adopted is to make an engineering judgment on the size of filter required and use this information in the load flow study. In all our designs, where the client has agreed, the WTG reactive power capability is used to provide fixed compensation. By using the capability of the WTGs, shunt reactors for fixed compensation is avoided which reduces the offshore platform weight and space requirements. In establishing an optimum size for the dynamic compensation plant, an appropriate size of fixed compensation is used to place the net reactive power of the system so as to achieve symmetrical compensation at 50% and 100% MW loading against the grid code requirement. 4 Onshore substations layout and connections On each of the five wind farms, a single onshore substation has been used to connect the wind farm to the transmission or distribution network regardless of the number of offshore platforms. An exception to this is in one wind farm where the dynamic reactive power compensation plant is installed in special elliptical pods outside the main substation. This has been done mainly for aesthetic reasons rather than being technical. In all the wind farm designs, the connections from the wind farm to the transmission or distribution network interface point is made using cable connections. In one of the projects, the onshore utility breaker that was provided for the export cable connection was not able to meet the capacitive duty of the wind farm export cable. In this case a late change to the layout was necessary to introduce an additional breaker in the wind farm onshore compound to cater for this requirement. In this particular design, the utility breaker is allowed to energize the wind farm onshore busbar only. Special electrical interlocks were put in place to ensure that during switching in/out of the export cable, the utility breaker cannot switch in/out the export cable prior to the operation of this dedicated breaker which was introduced later in the design. At the onshore substation, a dedicated dynamic compensation plant is provided to meet the requirements of the grid code. The STATCOM used by Siemens for this purpose is a state of the art Voltage Sourced Converter type (VSC), also referred to as SVC PLUS. In all of the five projects this technology has been used together with Mechanically Switched Capacitor banks and Mechanically Switched Reactors as a hybrid solution to reduce the overall cost of the compensation plant. A +/- 50MVAr SVC PLUS occupies approximately 21x25m including external equipment that goes with the SVC PLUS system. This includes SVC PLUS phase reactors, a high frequency blocking filter, medium voltage switchgear and auxiliary transformers and external coolers. In most of the onshore connections, a single busbar arrangement is used at 132kV or 150kV level except for one wind farm where a double busbar has been used due to the client s specific request. Due to its compact design and limited space requirements, Siemens Highly Integrated Switchgear (HIS) type 8DN8 suitable for out door application has been use in the onshore substation at 132kV level. On the project that used 150kV, Siemens Gas Insulated Switchgear (GIS) type 8DN9 was used. Among the five projects, at 132kV level a total of 28 HIS bays were used of which 24 had Circuit Breakers (CBs), at 150kV level a total of 4 GIS bays with CBs were used and at 420kV 2 HIS bays were used without CBs. The 420kV switchgear used was Siemens HIS type 8DQ1. What is also critical in the layout as mentioned earlier is that it is not possible to confirm the requirement for a harmonic filter at the initial stage of layout design and for this reason space reservation has to be made for a possible harmonic filter. 2

4 5 Offshore substations layout and connections As already mentioned two of the wind farms were connected to onshore 132kV systems whilst the other three were connected to 400kV onshore networks so that onshore transformation took place. In general, the 400kV connections aligned with the larger power ratings in excess of 500MW but in one case the power rating was less than 300MW. On the larger wind farms two offshore substations were utilized to gather the power from the wind turbines. This assisted in reducing the lengths of inter array cabling and produced two almost identical offshore substations each with two transformers and two export cable connections to the shore. With this style of platform the power flow can be from one side of the platform to the other with 33kV switchgear on one side, transformers and then HV switchgear on the other side. For the wind farms with generated power of 300MW or less, only one offshore substation has been used. The majority of the offshore substations feature two transformers and two export cables with the transformer ratings varying from 160MVA via 180MVA up to 240MVA. Also the transformers have varied from three winding design to two winding design. Transformers are the item of plant which gives rise to the most variations in the design of the platform as they are by far the heaviest item of plant. On the five projects variations have included the location of the coolers with some projects featuring tank mounted coolers and other using separately located radiator banks. The separate radiator banks solve certain problems such as fire protection simplifying the use of water mist systems and enabling the transformer tank to be located in an almost enclosed environment. However the connections from the tank to the radiator banks give rise to problems due to the forces experienced during barge transportation of the substation. Another variant is the method of connection between the transformer and the switchgear on both the HV and LV sides. The original project used gas insulated bus duct connections at 132kV and solid insulated bus ducts on the 33kV side. In some of the other projects cables have been used on either the HV or LV sides of the transformers. Again each of the connection methods has advantages and disadvantages. The 33kV bus duct solutions minimizes the number of connections required at 33kV as the rating of these connections can be 2500A and it allows virtually right angle bends to be achieved. However the solution is fairly expensive and the installation can be challenging. Transportation of gas insulated bus duct connections fully gassed up has to be done carefully. One of the 132kV connected wind farms with rating of 500MW was originally to be connected by a single offshore substation using three 180MVA transformers, but due to commercial and political reasons it became necessary to locate some of the wind turbines on a separate sand bank and this gave rise to the need for a second offshore substation. In this case the three transformers were retained on the main platform and a second platform with two smaller (90MVA) two winding transformers was established on the second sand bank. In this case the smaller platform was not directly connected to the shore but was connected by a submarine cable to the master platform and connected via switchgear to one of the three export cables to the shore. As this extra length of submarine cable was added at a late stage in the compensation design shunt reactors were also located on the new offshore platform to compensate the length of the connecting cable. The amount of HV switchgear has also varied quite significantly at client request from minimal, namely only disconnectors, earth switches and surge arresters on two of the projects, through to having circuit breakers to separate the cable from the transformer to a full five circuit breaker switchboard on one of the projects providing separate CBs for the transformers, cables and a bus section. In all platforms except one, HIS switchgear shown in Fig. 2 has been used at 132kV level. The HIS is modular and can be accommodated into the available space in the offshore platform. Adapting the HIS switchgear layout in the main platform to accommodate a second platform connection at a later stage of the project as stated above was easily achieved with the HIS. In total among the projects that used 132kV voltage, a total of 18 HIS bays were used of which 12 had CBs. 3

5 Fig. 2. Siemens Highly Integrated Switchgear (HIS) being installed in one of the platforms In one project, where the offshore HV voltage was at 150kV, the HV switchgear offered is Siemens GIS switchgear 8DN9. In this project four bays were used all without CB. Out of the five projects, the platforms on four projects have used jacket foundations whilst the one which had a separate platform contract has used a monopile construction. Monopile construction was quite common on the early single transformer platforms however experience has shown that some of these are prone to excessive vibration from wind and wave forces acting on the platform. One other layout consideration is the cable deck and whether this is integrated with the topside or provided as part of the jacket foundation. The latter solution can give more flexibility in the construction programme in that the cabling can be pulled in before the arrival of the topside. Of the five projects three have had integrated cable decks with the topside whilst two have had the cable deck as part of the jacket foundation. The previous paragraphs have discussed the main plant items but the platform layout must also consider the cabling and access for terminating the cables and the material handling to enable equipment and tools to be lifted onto the platform and then moved to the appropriate locations for work. The whole issue of access to the platforms is a key consideration in the layout design. Access will normally be required from boats but helicopter access may also be required as was the case on one of the projects. This introduces a whole new set of requirements into the layout of the platform taking into account wind directions and approach direction for the helicopter as well as the access to the helideck, constraints on the crane location and the additional fire fighting requirements associated with a helideck. 6 Commissioning Commissioning for offshore wind farm connections has two major differences from normal substation commissioning activities. The first is that the pre commissioning activities associated with the offshore substation are mainly carried out onshore before the substation platform leaves the construction yard. This is important as the cost of any activities carried out offshore is approximately ten times that of the same activities performed onshore. It is important to allow sufficient time in the construction programme to carry out this onshore commissioning activity as the sail out date is linked to the very expensive hire of the heavy lift vessel. The commissioning activities to be carried out offshore should be kept to the absolute minimum to prove that the equipment has not been damaged in transit and is functioning correctly and of course those items which can only be proved when the substation is in situ and the cables connected. The second difference is the need for a set of grid code compliance tests on the whole wind farm to ensure that the wind farm meets the reactive power, voltage control and frequency control requirements. For the GB Grid Code these tests require the demonstration of the capability of the wind farm to generate and absorb reactive power up to the maximum levels defined. Also the capability of 4

6 the wind farm to respond to dynamic changes in voltage in accordance with the set point and slope settings applied has to be demonstrated. In all of the five Round 2 wind farms the IGBT based SVC PLUS with mechanical switched components has been used. In the majority of cases both switched reactors and switched capacitors have been employed but on one project only switched reactors were required. 7 Way forward A lot of experience has been gained on wind farm design and installation from working on these five Round 2 projects and the experience gained on transformer and platform design will be fed back into the new designs. However, this does not mean that there will not still be significant challenges in responding to the connection of Round 3 wind farms in which the AC onshore system and the offshore AC system is likely to be coupled via a HVDC system. If voltage sourced converter HVDC is used, which seems most likely, then the need for SVC systems should be removed. However the fundamental design of the offshore AC systems will need careful consideration because of the effective decoupling between the onshore and offshore systems caused by the HVDC link. The opportunity to choose an optimal frequency and voltage for the offshore system can be considered. Higher frequency may lead to smaller lighter transformer designs but the higher frequency will lead to higher VAR generation from the power cables. Higher voltages will hopefully lead to lower losses but again higher voltage will lead to higher VAR generation. One of the fundamental issues to be decided is what is the correct size for the offshore collector substations? This will need to be a compromise between minimizing the number of offshore substations and hence HV connections required taken together with keeping down the length and losses of inter array cables. With so many large wind farms being considered in Round 3 thus requiring a large number of HVDC connections with ratings of the order of 1000MW there will be a need for some form of interconnection between these links to cover for the loss of one HVDC link. Should this be achieved by multi terminal DC or should the interconnection be achieved on the AC side? However some issues now well understood with regard to fault levels and protection will need to be reconsidered. With AC connected wind farms the transformer impedance had to be chosen to limit the fault levels and then the impact of these high impedances on the reactive compensation balance had to be considered. With a HVDC link the fault level from the onshore system will be limited to approximately 1.2 times full load current at most. This means that the whole concept for choosing transformer impedance values will need to be reconsidered and this may avoid the need for tap changers on the offshore transformers. The reactive compensation for the offshore network can no longer be achieved by locating compensation plant onshore, again because of the effective decoupling of the two systems. This leaves the question as to the optimum way to control reactive power on the offshore network. Should this be achieved by using the STATCOM capabilities of the HVDC converters, or should there be static devices such as shunt reactors mounted on the offshore platforms or can the reactive capability of the wind turbines be utilized? The answer may lie in an intelligent combination of a number or all of these possible sources. The effective decoupling of the onshore and offshore networks will certainly have a significant effect upon the protection systems used particularly for the inter array cables where either plain or directional overcurrent protection has been used in the existing projects. Because of the lack of fault infeed from the onshore network this method will not be possible in the future and the use of distance protection or possibly voltage controlled overcurrent protection may provide the answer. 5

7 Short Bio-data of Main Author Study of electrical engineering at St. Petersburg State Polytechnic University in Russia, graduation as engineer in PhD in the field of power networks at RWTH Aachen University in Germany, graduation as Dr. in Power system analyst at engineering consulting company Lahmeyer International, Germany, till Sales and marketing responsibility at Siemens AG in Germany for the high voltage substations in CIS countries till Now responsible for the technical marketing of the high voltage substations at Siemens AG. 6

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter 1 Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter Nee, Staffan Norrga, Remus Teodorescu ISBN-10: 1118851560

More information

High Voltage DC Transmission 2

High Voltage DC Transmission 2 High Voltage DC Transmission 2 1.0 Introduction Interconnecting HVDC within an AC system requires conversion from AC to DC and inversion from DC to AC. We refer to the circuits which provide conversion

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

Grid integration of offshore wind farms using HVDC links: HVDC-VSC technology overview

Grid integration of offshore wind farms using HVDC links: HVDC-VSC technology overview Grid integration of offshore wind farms using HVDC links: HVDC-VSC technology overview ICREPQ 2013, Basque Country, 22 nd March 2013 Salvador Ceballos Salvador.ceballos@tecnalia.com Introduction OWPP layouts

More information

Overview of Actuation Thrust

Overview of Actuation Thrust Overview of Actuation Thrust Fred Wang Thrust Leader, UTK Professor ECE 620 CURENT Course September 13, 2017 Actuation in CURENT Wide Area Control of Power Power Grid Grid Measurement &Monitoring HVDC

More information

Application of SVCs to Satisfy Reactive Power Needs of Power Systems

Application of SVCs to Satisfy Reactive Power Needs of Power Systems 1 Application of SVCs to Satisfy Reactive Power Needs of Power Systems H. K. Tyll, Senior Member, IEEE Abstract In the early days of power transmission problems like voltage deviation during load changes

More information

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors May 11, 2010 Slide 1 Why phase-shifting transformers

More information

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

UProtection Requirements. Ufor a Large scale Wind Park. Shyam Musunuri Siemens Energy

UProtection Requirements. Ufor a Large scale Wind Park. Shyam Musunuri Siemens Energy UProtection Requirements Ufor a Large scale Wind Park Shyam Musunuri Siemens Energy Abstract: In the past wind power plants typically had a small power rating when compared to the strength of the connected

More information

Trans Bay Cable A Breakthrough of VSC Multilevel Converters in HVDC Transmission

Trans Bay Cable A Breakthrough of VSC Multilevel Converters in HVDC Transmission Trans Bay Cable A Breakthrough of VSC Multilevel Converters in HVDC Transmission Siemens AG Power Transmission Solutions J. Dorn, joerg.dorn@siemens.com CIGRE Colloquium on HVDC and Power Electronic Systems

More information

HVDC Transmission. Michael Muhr. Institute of High Voltage Engineering and System Performance Graz University of Technology Austria P A S S I O N

HVDC Transmission. Michael Muhr. Institute of High Voltage Engineering and System Performance Graz University of Technology Austria P A S S I O N S C I E N C E P A S S I O N T E C H N O L O G Y HVDC Transmission Michael Muhr Graz University of Technology Austria www.tugraz.at 1 Definition HV High Voltage AC Voltage > 60kV 220kV DC Voltage > 60kV

More information

ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for Michigan s Eastern Upper and Northern Lower Peninsulas

ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for Michigan s Eastern Upper and Northern Lower Peninsulas 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for

More information

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES C.E.T. Foote*, G.W. Ault*, J.R. McDonald*, A.J. Beddoes *University of Strathclyde, UK EA Technology Limited, UK c.foote@eee.strath.ac.uk

More information

Overview of Actuation Thrust

Overview of Actuation Thrust Overview of Actuation Thrust Fred Wang Thrust Leader, UTK Professor Prepared for CURENT Course September 4, 2013 Actuation in CURENT Wide Area Control of Power Power Grid Grid Measurement &Monitoring HVDC

More information

Power transformers. Shunt reactors Proven history for future success

Power transformers. Shunt reactors Proven history for future success Power transformers Shunt reactors Proven history for future success Shunt reactors an investment for today and for the future 2 Shunt reactors Improving power quality and reducing transmission costs Shunt

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products

More information

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements

More information

The Advantages and Application of Three Winding Transformers

The Advantages and Application of Three Winding Transformers The Advantages and Application of Three Winding Transformers MSc, CEng, FIEE, FIMechE, FIPENZ Principal, Sinclair Knight Merz Abstract Although seldom used in Australia and New Zealand, three winding transformers

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

VSC Transmission. Presentation Overview. CIGRE B4 HVDC and Power Electronics HVDC Colloquium, Oslo, April LCC HVDC Transmission

VSC Transmission. Presentation Overview. CIGRE B4 HVDC and Power Electronics HVDC Colloquium, Oslo, April LCC HVDC Transmission CIGRE B4 HVDC and Power Electronics HVDC Colloquium, Oslo, April 2006 VSC Transmission presented by Dr Bjarne R Andersen, Andersen Power Electronic Solutions Ltd Presentation Overview - Basic Characteristics

More information

Should we transform our lines to HVDC?

Should we transform our lines to HVDC? Should we transform our lines to HVDC? HVDC versushvac Gaurav Dabhi 1, Nishit Sanghvi 2, Pinkesh Patel 3 1 Electrical Eng., G.H. Patel college of Eng. & Tech., dabhi60@gmail.com 2 Electrical Eng., G.H.

More information

each time the Frequency is above 51Hz. Continuous operation is required

each time the Frequency is above 51Hz. Continuous operation is required GC0101 EXTRACT OF EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 08/01/2018. ECC.6 ECC.6.1 ECC.6.1.1 ECC.6.1.2 ECC.6.1.2.1 ECC.6.1.2.1.1 ECC.6.1.2.1.2 ECC.6.1.2.1.3 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA

More information

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH Requirements for Offshore Grid Connections in the Grid of TenneT TSO GmbH Bernecker Straße 70, 95448 Bayreuth Updated: 5th October 2010 1/10 Requirements for Offshore Grid Connections in the Grid of TenneT

More information

Integration of Wind Generation into Weak Grids

Integration of Wind Generation into Weak Grids Integration of Wind Generation into Weak Grids Jason MacDowell GE Energy Consulting NERC ERSTF Atlanta, GA December 10-11, 2014 Outline Conventional and Power Electronic (PE) Sources Stability limitations

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

Quanta Technology Advancing the Grid. Flexible AC Transmission System (FACTS) BGE Technology - Application Cases January 4, 2008 Q U A N T A SERVI CES

Quanta Technology Advancing the Grid. Flexible AC Transmission System (FACTS) BGE Technology - Application Cases January 4, 2008 Q U A N T A SERVI CES National Conference of State Legislatures The Forum for America s Ideas April 2011 National Association of Regulatory Utility Commissioners Q U A N T A SERVI CES Quanta Technology Advancing the Grid Flexible

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision By Date V1D1 For Comments Yaoyu Huang October 27, 2016 V1 For Issuance Yaoyu Huang November 21, 2016 Section 5.3 updated Transformer

More information

Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom

Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom Downloaded from orbit.dtu.dk on: Aug 3, 018 Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom Wu, Qiuwei; Solanas, Jose Ignacio Busca; Zhao, Haoran; Kocewiak,

More information

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements Robert Nelson Senior Expert Engineering Manager and Manager of Codes, Standards, and Regulations Siemens Wind Turbines -

More information

Power Frequency Withstand Voltage On-site testing of 400 kv GIS

Power Frequency Withstand Voltage On-site testing of 400 kv GIS Power Frequency Withstand Voltage On-site testing of 400 kv GIS D. Anaraki Ardakani, A. Omidkhoda, M. Solati High Voltage Engineering Center ACECR Tehran, Iran Da_ardakani@yahoo.com Paper Reference Number:

More information

Fundamental Concepts of Dynamic Reactive Compensation. Outline

Fundamental Concepts of Dynamic Reactive Compensation. Outline 1 Fundamental Concepts of Dynamic Reactive Compensation and HVDC Transmission Brian K. Johnson University of Idaho b.k.johnson@ieee.org 2 Outline Objectives for this panel session Introduce Basic Concepts

More information

Protection of Electrical Networks. Christophe Prévé

Protection of Electrical Networks. Christophe Prévé Protection of Electrical Networks Christophe Prévé This Page Intentionally Left Blank Protection of Electrical Networks This Page Intentionally Left Blank Protection of Electrical Networks Christophe Prévé

More information

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström EH27401 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsn@ics.kth.se 1 Course map 2 Outline 1. Power System Topologies Transmission Grids vs Distribution grids Radial grids

More information

NETS SQSS Modification Proposal

NETS SQSS Modification Proposal NETS SQSS Modification Proposal Operational and Planning Criteria for 220kV Transmission Assets Panel Paper by Bless Kuri, SHE Transmission For presentation to the SQSS Panel Meeting on 1 st April 2015

More information

Constant Terminal Voltage. Working Group 1 29 st January 2014

Constant Terminal Voltage. Working Group 1 29 st January 2014 Constant Terminal Voltage Working Group 1 29 st January 2014 Overview Objectives of Working Group ENTSO-E RfG Implications Options Summary Discussion 2 Objectives of Work Group National Grid in consultation

More information

Joe Warner, Electric Power Industry Conference (EPIC), November 15, 2016 Advances in Grid Equipment Transmission Shunt Compensation

Joe Warner, Electric Power Industry Conference (EPIC), November 15, 2016 Advances in Grid Equipment Transmission Shunt Compensation Joe Warner, Electric Power Industry Conference (EPIC), November 15, 2016 Advances in Grid Equipment Transmission Shunt Compensation Slide 1 Excerpt from the BoA BoA: Book of Acronyms MSC/MSR: Mechanically

More information

East-South HVDC Interconnector II, India : in commercial operation since 2003

East-South HVDC Interconnector II, India : in commercial operation since 2003 8006/0 5 HVDC / FACTS Highlights http://www.siemens.com/facts http://www.siemens.com/hvdc NEW! >>> Welcome to Siemens Highlights & Innovations in Transmission and Distribution East-South HVDC Interconnector

More information

Power Quality enhancement of a distribution line with DSTATCOM

Power Quality enhancement of a distribution line with DSTATCOM ower Quality enhancement of a distribution line with DSTATCOM Divya arashar 1 Department of Electrical Engineering BSACET Mathura INDIA Aseem Chandel 2 SMIEEE,Deepak arashar 3 Department of Electrical

More information

General Technical Specifications of Frequency Converters for Tokyo-Chubu Interconnection Project

General Technical Specifications of Frequency Converters for Tokyo-Chubu Interconnection Project General Technical Specifications of Converters for Tokyo-Chubu Interconnection Project Note: It is possible that the contents of these specifications may be changed according to our detailed studies. Present

More information

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods Proceedings of the th WSEAS International Conference on Power Systems, Beijing, China, September -, 200 Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing

More information

HV AC TESTING OF SUPER-LONG CABLES

HV AC TESTING OF SUPER-LONG CABLES HV AC TESTING OF SUPER-LONG CABLES Stefan SCHIERIG, (Germany), schierig@highvolt.de Peter COORS, (Germany), coors@highvolt.de Wolfgang HAUSCHILD, IEC, CIGRE, (Germany), hauschild@highvolt.de ABSTRACT The

More information

High voltage shunt capacitor banks HIGH VOLTAGE COMPENSATION AND HARMONIC FILTERING PRODUCTS

High voltage shunt capacitor banks HIGH VOLTAGE COMPENSATION AND HARMONIC FILTERING PRODUCTS High voltage shunt capacitor banks Alstom Grid high voltage shunt capacitor bank offering is divided in: By bank construction HV open rack capacitor banks HV enclosed capacitor banks By bank design HV

More information

CERN - ST Division THE NEW 150 MVAR, 18 KV STATIC VAR COMPENSATOR FOR SPS: BACKGROUND, DESIGN AND COMMISSIONING

CERN - ST Division THE NEW 150 MVAR, 18 KV STATIC VAR COMPENSATOR FOR SPS: BACKGROUND, DESIGN AND COMMISSIONING EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH ORGANISATION EUROPÉENNE POUR LA RECHERCHE NUCLÉAIRE CERN - ST Division ST-Note-2003-023 4 April 2003 THE NEW 150 MVAR, 18 KV STATIC VAR COMPENSATOR FOR SPS: BACKGROUND,

More information

LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS

LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS Giuseppe Di Marzio NTNU giuseppe.di.marzio@elkraft.ntnu.no Olav B. Fosso NTNU olav.fosso@elkraft.ntnu.no Kjetil Uhlen SINTEF

More information

Fault Ride Through Technical Assessment Report Template

Fault Ride Through Technical Assessment Report Template Fault Ride Through Technical Assessment Report Template Notes: 1. This template is intended to provide guidelines into the minimum content and scope of the technical studies required to demonstrate compliance

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

INTEGRATED TRANSMISSION PLAN Glossary

INTEGRATED TRANSMISSION PLAN Glossary INTEGRATED TRANSMISSION PLAN Glossary SEPTEMBER 2017 GLOSSARY Term AC ACM asset health and asset health index (AHI) automatic underfrequency load shedding (AUFLS) availability bus cable capacitor bank

More information

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1.1 INTRODUCTION 2 WFPS1.2 OBJECTIVE 2 WFPS1.3 SCOPE 3 WFPS1.4 FAULT RIDE THROUGH REQUIREMENTS 4 WFPS1.5 FREQUENCY REQUIREMENTS 5 WFPS1.6 VOLTAGE

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

VI 3 - i TABLE OF CONTENTS

VI 3 - i TABLE OF CONTENTS VI 3 - i TABLE OF CONTENTS 3 PROJECT SPECIFIC DATA... 1 3.1 DEFINITIONS... 1 3.1.1 Design Data, High and Medium Voltage... 1 3.1.2 Design Data, Low Voltage Equipment... 2 3.1.3 Phase Relationship... 3

More information

G. KOEPPL Koeppl Power Experts Switzerland

G. KOEPPL Koeppl Power Experts Switzerland PS3: Substation Design: New Solutions and Experiences Bus-Node Substation A Big Improvement in Short-Circuit and Switching Properties at Reduced Substation Costs G. KOEPPL Koeppl Power Experts Switzerland

More information

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL Basically the HVDC transmission consists in the basic case of two convertor stations which are connected to each other by a transmission link consisting of an overhead

More information

Open Access Simulation Toolbox for Wind Power Transmission using High Voltage Direct Current Technology

Open Access Simulation Toolbox for Wind Power Transmission using High Voltage Direct Current Technology Open Access Simulation Toolbox for Wind Power Transmission using High Voltage Direct Current Technology Daniel Adeuyi (Cardiff University, Wales) Sheng WANG, Carlos UGALDE-LOO (Cardiff University, Wales);

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Applicability 1 Section 502.8 applies to: (a) the legal owner of a generating unit: (i) connected to the transmission facilities in the balancing authority area

More information

Hamdy Faramawy Senior Application Specialist ABB Sweden

Hamdy Faramawy Senior Application Specialist ABB Sweden Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy

More information

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider Shunt Reactors Global Top Energy, Machinery & Plant Solution Provider Our Business Brief introduction of Hyosung Power & Industrial Systems PG While Hyosung is an established name for world-class electrical

More information

Power transmission systems for offshore wind farms: Technical-economic analysis 1. Abstract

Power transmission systems for offshore wind farms: Technical-economic analysis 1. Abstract Power transmission systems for offshore wind farms: Technical-economic analysis 1 Abstract Several studies claim that wind power will play a major role in the energy supply of the European Union, forecasting

More information

SYSTEMS AND COMPONENTS FOR TRANSFORMER TESTING

SYSTEMS AND COMPONENTS FOR TRANSFORMER TESTING SYSTEMS AND COMPONENTS FOR TRANSFORMER TESTING 9.11/2 Transformer Testing n Type tests n Routine tests n Special tests n Applicable for tests on power and distribution transformers in factory and on-site

More information

Facilitating Bulk Wind Power Integration Using LCC HVDC

Facilitating Bulk Wind Power Integration Using LCC HVDC 21, rue d Artois, F-758 PARIS CIGRE US National Committee http : //www.cigre.org 213 Grid of the Future Symposium Facilitating Bulk Wind Power Integration Using LCC HVDC A. HERNANDEZ * R.MAJUMDER W. GALLI

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 AORC Technical meeting 2014 http : //www.cigre.org B1-1110 Development of ±160 kv XLPE Cable and its Application to the World s First Three-terminal VSC HVDC System in China Lin-jie Zhao, Hong Rao, Xiao-lin

More information

Coil Products Beginnings 1960 State of the Art. Customer partnership around the globe. Continuous innovation since 1900

Coil Products Beginnings 1960 State of the Art. Customer partnership around the globe. Continuous innovation since 1900 Coil Products Coil Products Customer partnership around the globe More than 250,000 coil products delivered to more than 170 countries. More than 60 years of operational experience. 35,000 in Europe 13,000

More information

ATC s Mackinac Back to Back. Summary

ATC s Mackinac Back to Back. Summary ATC s Mackinac Back to Back HVDC Project Update Michael B. Marz American Transmission Company Summary The Need For Flow Control at Mackinac Mackinac Flow Control Requirements Available Flow Control Technologies

More information

Partial Power Operation of Multi-level Modular Converters under Subsystem Faults

Partial Power Operation of Multi-level Modular Converters under Subsystem Faults Partial Power Operation of Multi-level Modular Converters under Subsystem Faults Philip Clemow Email: philipclemow@imperialacuk Timothy C Green Email: tgreen@imperialacuk Michael M C Merlin Email: michaelmerlin7@imperialacuk

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Voltage Source Converter Modelling

Voltage Source Converter Modelling Voltage Source Converter Modelling Introduction The AC/DC converters in Ipsa represent either voltage source converters (VSC) or line commutated converters (LCC). A single converter component is used to

More information

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels

More information

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION ATTACHMENT - AESO FUNCTIONAL SPECIFICATION Functional Specification Revision History Revision Description of Revision By Date D1 For internal Comments Yaoyu Huang January 8, 2018 D2 For external Comments

More information

Kriegers Flak Wind Farm Tender Q&A on interfaces 2nd February 2016 (revised 12th February 2016)

Kriegers Flak Wind Farm Tender Q&A on interfaces 2nd February 2016 (revised 12th February 2016) To Participating companies Revised version 12 th February 2016 Kriegers Flak Wind Farm Tender Q&A on interfaces 2nd February 2016 (revised 12th February 2016) 12. februar 2016 JCH/JCH The Danish Energy

More information

Transformers TRANS FORM ERS

Transformers TRANS FORM ERS Transformers TRANS FORM ERS Meiden Transformers are standard design, standard quality. Our Factories on world-wide supply chain Since its founding in 1897 Meidensha Corporation has not only built up a

More information

DC Chopper Based Test Circuit for High Voltage DC Circuit Breakers

DC Chopper Based Test Circuit for High Voltage DC Circuit Breakers DC Chopper Based Test Circuit for High Voltage DC Circuit Breakers D. Jovcic*, M.H. Hedayati *University of Aberdeen,UK, d.jovcic@abdn.ac.uk University of Aberdeen,UK, mhh@abdn.ac.uk Keywords: High Voltage

More information

Analysis of a 405 km transmission line with series compensation

Analysis of a 405 km transmission line with series compensation Analysis of a 405 km transmission line with series compensation by Dr. Rupert Gouws, North-West University This paper presents an investigative case study and energy efficiency analysis of the 405 km,

More information

CONTENTS. 1. Introduction Generating Stations 9 40

CONTENTS. 1. Introduction Generating Stations 9 40 CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific

More information

MMC Design Aspects and Applications. John Strauss Siemens AG.

MMC Design Aspects and Applications. John Strauss Siemens AG. MMC Design Aspects and Applications John Strauss Siemens AG. John.Strauss@Siemens.com 1 VSC-HVDC with MMC Basic Scheme Reference HVDC PLUS Converter Arm Converter Module Power Module Electronics (PME)

More information

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting Document C-29 Procedures for System Modeling: January 5 th, 2016 TFSS Revisions Clean Open Process Posting Prepared by the SS-37 Working Group on Base Case Development for the Task Force on System Studies.

More information

ELEMENTS OF FACTS CONTROLLERS

ELEMENTS OF FACTS CONTROLLERS 1 ELEMENTS OF FACTS CONTROLLERS Rajiv K. Varma Associate Professor Hydro One Chair in Power Systems Engineering University of Western Ontario London, ON, CANADA rkvarma@uwo.ca POWER SYSTEMS - Where are

More information

A Study on Ferroresonance Mitigation Techniques for Power Transformer

A Study on Ferroresonance Mitigation Techniques for Power Transformer A Study on Ferroresonance Mitigation Techniques for Power Transformer S. I. Kim, B. C. Sung, S. N. Kim, Y. C. Choi, H. J. Kim Abstract--This paper presents a comprehensive study on the ferroresonance mitigation

More information

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter 1 Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter Nee, Staffan Norrga, Remus Teodorescu ISBN-10: 1118851560

More information

IMPROVING POWER QUALITY AND ENHANCING THE LIFE OF POWER EQUIPMENT, IN RAILWAY TSSs

IMPROVING POWER QUALITY AND ENHANCING THE LIFE OF POWER EQUIPMENT, IN RAILWAY TSSs IMPROVING POWER QUALITY AND ENHANCING THE LIFE OF POWER EQUIPMENT, IN RAILWAY TSSs Mr. P. Biswas, ABB ABSTRACT The Indian Railways employ single phase 25 kv Traction sub-station (TSS) for supplying power

More information

Medium-voltage in-phase regulator system Energy Management

Medium-voltage in-phase regulator system Energy Management Medium-voltage in-phase regulator system Energy Management Challenges Distributed power generation can have an enormous impact on grid performance. The challenge of equalizing voltage fluctuations is especially

More information

Published in: Proceedings of the 2016 IEEE International Conference on Power Electronics, Drives and Energy Systems (PEDES)

Published in: Proceedings of the 2016 IEEE International Conference on Power Electronics, Drives and Energy Systems (PEDES) Aalborg Universitet Voltage Feedback based Harmonic Compensation for an Offshore Wind Power Plant Chaudhary, Sanjay K.; Lascu, Cristian Vaslie; Teodorescu, Remus; Kocewiak, ukasz Published in: Proceedings

More information

Design and Simulation of Passive Filter

Design and Simulation of Passive Filter Chapter 3 Design and Simulation of Passive Filter 3.1 Introduction Passive LC filters are conventionally used to suppress the harmonic distortion in power system. In general they consist of various shunt

More information

J Project Methods. V (%) Network with high generation and low load. Network with low generation and high load

J Project Methods. V (%) Network with high generation and low load. Network with low generation and high load J Project Methods Background The management of voltage is a growing concern with the integration of low carbon technologies, particularly distributed generation (DG), within electricity networks. The issue

More information

QUESTIONNAIRE for Wind Farm Power Stations only

QUESTIONNAIRE for Wind Farm Power Stations only TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21

More information

Gwynt y Môr Offshore Wind Farm

Gwynt y Môr Offshore Wind Farm Gwynt y Môr Offshore Wind Farm Toby Edmonds Project Director, Gwynt y Môr Liverpool, 12 September 2012 Forward Looking Statement This presentation contains certain forward-looking statements within the

More information

HVDC Solutions for Integration of the Renewable Energy Resources

HVDC Solutions for Integration of the Renewable Energy Resources HVDC Solutions for Integration of the Renewable Energy Resources Comparison of Technical Alternatives and System Configurations Marcus Haeusler Energy Management, Large Transmission Solutions Siemens AG

More information

SUMMARY. KEYWORDS Advanced Control, Type 4 WTG, Offshore, HVDC, Grid Access, Diode Rectifier Unit. 21, rue d Artois, F PARIS B4-121 CIGRE 2016

SUMMARY. KEYWORDS Advanced Control, Type 4 WTG, Offshore, HVDC, Grid Access, Diode Rectifier Unit. 21, rue d Artois, F PARIS B4-121 CIGRE 2016 21, rue d Artois, F-75008 PARIS B4-121 CIGRE 2016 http : //www.cigre.org Diode-Rectifier HVDC link to onshore power systems: Dynamic performance of wind turbine generators and Reliability of liquid immersed

More information

A cost effective hybrid HVDC transmission system with high performance in DC line fault handling

A cost effective hybrid HVDC transmission system with high performance in DC line fault handling 2, rue d Artois, F-758 PARIS B4-7 CIGRE 28 http : //www.cigre.org A cost effective hybrid HVDC transmission system with high performance in DC line fault handling Mats Andersson, Xiaobo ang and ing-jiang

More information

High Wind Speed Shutdown / Power Available

High Wind Speed Shutdown / Power Available High Wind Speed Shutdown / Power Available Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS

ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS R. A. Walling, K. Clark, N. W. Miller, J. J. Sanchez-Gasca GE Energy USA reigh.walling@ge.com ABSTRACT

More information

Harmonic resonances due to transmission-system cables

Harmonic resonances due to transmission-system cables International Conference on Renewable Energies and Power Quality (ICREPQ 14) Cordoba (Spain), 8 th to 1 th April, 214 Renewable Energy and Power Quality Journal (RE&PQJ) ISSN 2172-38 X, No.12, April 214

More information

U I. HVDC Control. LCC Reactive power characteristics

U I. HVDC Control. LCC Reactive power characteristics Lecture 29 HVDC Control Series Compensation 1 Fall 2017 LCC Reactive power characteristics LCC HVDC Reactive compensation by switched filters and shunt capacitor banks Operates at lagging power factor

More information

Appendix D Fault Levels

Appendix D Fault Levels Appendix D Fault Levels Page 1 Electricity Ten Year Statement November 2013 D.1 Short Circuit Currents Short Circuit Currents Three phase to earth and single phase to earth short circuit current analyses

More information

Technologies data base and technological innovation needs up to 2050

Technologies data base and technological innovation needs up to 2050 Session IV : Long-term grid development Technology and operations Technologies data base and technological innovation needs up to 2050 Eric Peirano, Technofi Work Package leader e-highway2050 I Final Conference

More information

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology Condition Assessment of High Voltage Insulation in Power System Equipment R.E. James and Q. Su The Institution of Engineering and Technology Contents Preface xi 1 Introduction 1 1.1 Interconnection of

More information

ELEC Transmission i and

ELEC Transmission i and ELEC-1104 Lecture 5: Transmission i and Distribution ib ti Power System Layout Transmission and Distribution The transmission system is to transmit a large amount of energy from the power stations s to

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Requirements Applicability 1 Subject to subsections 2 and 3 below, section 502.8 applies to: (a) (c) (d) the legal owner of a generating unit or an aggregated

More information

Analysis of the Effectiveness of Grid Codes for Offshore Wind Farms Connected to Onshore Grid via VSC-Based HVDC

Analysis of the Effectiveness of Grid Codes for Offshore Wind Farms Connected to Onshore Grid via VSC-Based HVDC Conference of the Wind Power Engineering Community Analysis of the Effectiveness of Grid Codes for Offshore Wind Farms Connected to Onshore Grid via VSC-Based HVDC Moritz Mittelstaedt, Andreas Roehder,.Hendrik

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information