July/August/September Traffic Adaptive Installation Preparation, July-September 2017

Size: px
Start display at page:

Download "July/August/September Traffic Adaptive Installation Preparation, July-September 2017"

Transcription

1 V July/August/September Traffic Adaptive Installation Preparation, July-September 2017 The Traffic Operations group intends to kick-off their traffic adaptive trial installation in October The project area encompasses 28 intersections in the Great Neck Road, Virginia Beach Boulevard, London Bridge Road and Lynnhaven Parkway corridors. All the servers, mid-block detection, intersection video detection, and high resolution data traffic controllers have been installed. Staff also installed bluetooth detection on high volume corridors. These devices track MAC addresses from cell phones/bluetooth devices and provide travel times for vehicles proceeding through a corridor. This will help determine the efficiency of the travel adaptive installation. Staff training on the new system will begin in October. Metrics to measure the performance of the new system will begin immediately. Months of before data has already been collected. Overall Area Map of bluetooth detection device installations Twenty five (25) installations are in place

2 The Traffic Adaptive project will involve 28 intersections on Lynnhaven Parkway, Virginia Beach Boulevard, and Great Neck Road corridors. Bluetooth detection device installations within the Traffic Adaptive Corridor 2

3 The in-ground vehicle detectors collect traffic count information and calculate vehicle occupancy; information needed by the traffic control software to perform real-time adjustments to the traffic signal timings. An added benefit is road surface temperature detection. Road surface temperatures are especially important during snow/ice season; enabling the TMC to provide information to the snow/ice removal teams on which roads need anti-icing treatment. Virginia Beach Boulevard/Great Neck Road In-Ground Detection Data Sample Traffic Counts/detections highlighted on left. Surface temperatures in column highlighted on right Virginia Beach Boulevard/Great Neck Road In-Ground Detector Vehicle volume and occupancy data 3

4 Mid block and stop bar traffic detection are vital components in the traffic adaptive set-up. We have installed over 196 mid block detection devices into the pavement sub layer at the project intersections. We have also modified our video detection camera hardware to enable vehicle detection at the stop bar. Mid-block detection at the Virginia Beach Boulevard/Great Neck Road/London Bridge Road intersection. Staff also installed 20 access points along the project corridors. These access points allow two-way communications between roadside traffic controllers, our dedicated server, and the traffic management system. This real-time exchange of vehicle detection information is key to providing real-time traffic signal retiming calculations and forwarding this information into the signal controllers in the field. We will be working with the traffic adaptive set-up installation through the November/December timeframe. The mix of school traffic, holiday traffic at Lynnhaven Mall, and variable traffic flows from I-264 should provide a great opportunity to test the flexibility and effectiveness of the traffic adaptive technology. 4

5 Traffic Management Operations Division Response Information Some of the vital statistics we addressed July thru September Number of Traffic Counts Completed Number of Utility Locate Tickets (Miss Utility) Received/Checked/Marked 5,376/809/ Number of Traffic Signal Preventive Maintenance Actions completed Number of Traffic Signal Work Orders Received Number of Traffic Sign Work Orders Completed Linear feet of Thermoplastic Applied to Roadway 40, Guardrail Work Items Completed: a. Preventative Maintenance.: 60 b. Guardrail repair/replacement: 4 c. Erosion control: 4 d. Graffiti removal: 7 8. Provided event support for the following Special Events a. Allen Stone b. Laser Show c. Africana Virginia Beach d. East Coast Surfing Championship e. FunkFest f. Mount Trashmore Event g. Beach Street USA h. American Music Festival i. Masa parade j. Neptune Festival Weekend 5

I. Travel Time Determinations on London Bridge Road and_i-264 Corridor using of Bluetooth Detection Devices

I. Travel Time Determinations on London Bridge Road and_i-264 Corridor using of Bluetooth Detection Devices October/November/December 2016 I. Travel Time Determinations on London Bridge Road and_i-264 Corridor using of Bluetooth Detection Devices The TMC recently installed blue tooth devices for a pilot project

More information

April/May/June Reaching Outlying Sites from the Westin Hotel, May 31, 2017

April/May/June Reaching Outlying Sites from the Westin Hotel, May 31, 2017 V April/May/June 2017 1. Reaching Outlying Sites from the Westin Hotel, May 31, 2017 Throughout the City of Virginia Beach there are 55 traffic signals, 82 school zone flashers, and remote traffic sensitive

More information

Roadmap to Successful Deployment of Adaptive Systems

Roadmap to Successful Deployment of Adaptive Systems Smart Information for a Sustainable World Roadmap to Successful Deployment of Adaptive Systems Farhad Pooran Telvent Transportation North America Hampton Roads Transportation Operation Sub- Committee June

More information

EVALUATING AN ADAPTIVE SIGNAL CONTROL SYSTEM IN GRESHAM. James M. Peters, P.E., P.T.O.E., Jay McCoy, P.E., Robert Bertini, Ph.D., P.E.

EVALUATING AN ADAPTIVE SIGNAL CONTROL SYSTEM IN GRESHAM. James M. Peters, P.E., P.T.O.E., Jay McCoy, P.E., Robert Bertini, Ph.D., P.E. EVALUATING AN ADAPTIVE SIGNAL CONTROL SYSTEM IN GRESHAM James M. Peters, P.E., P.T.O.E., Jay McCoy, P.E., Robert Bertini, Ph.D., P.E. ABSTRACT Cities and Counties are faced with increasing traffic congestion

More information

1 of REV:0

1 of REV:0 1 of 5 683-10573-0418 This specification sets forth the minimum requirements for purchase and installation of an aboveground Radar Advance Detection Device (RADD) system for a real-time, advance vehicle-detection

More information

ADAPTIVE TRAFFIC SIGNAL CONTROL PILOT PROJECT FOR THE CITY OF SURREY

ADAPTIVE TRAFFIC SIGNAL CONTROL PILOT PROJECT FOR THE CITY OF SURREY ADAPTIVE TRAFFIC SIGNAL CONTROL PILOT PROJECT FOR THE CITY OF SURREY Joseph K. Lam, P.Eng., Managing Director Delcan Corporation 625 Cochrane Drive, Suite 500, Markham, Ontario, Canada, L3R 9R9 Tel: +1-905-943-0521,

More information

ACS-Lite. The Next Generation of Traffic Signal Control. Eddie Curtis, FHWA HOTM / Resource Center February 28, 2007

ACS-Lite. The Next Generation of Traffic Signal Control. Eddie Curtis, FHWA HOTM / Resource Center February 28, 2007 ACS-Lite The Next Generation of Traffic Signal Control Eddie Curtis, FHWA HOTM / Resource Center February 28, 2007 Outline Background on adaptive traffic signal Systems ACS-Lite Goals Development Functionality

More information

Signal Performance Metrics Charlie Wetzel, PE, PTOE

Signal Performance Metrics Charlie Wetzel, PE, PTOE Signal Performance Metrics Charlie Wetzel, PE, PTOE County Traffic Engineer Seminole County Florida 1 Who is Seminole County? Small County located just north of Orange County and the City of Orlando Population:

More information

Area Traffic Control System (ATCS)

Area Traffic Control System (ATCS) Area Traffic Control System (ATCS) 1. Introduction: Area Traffic Control System is an indigenous solution for Indian Road Traffic, which optimizes traffic signal, covering a set of roads for an area in

More information

USING BLUETOOTH TM TO MEASURE TRAVEL TIME ALONG ARTERIAL CORRIDORS

USING BLUETOOTH TM TO MEASURE TRAVEL TIME ALONG ARTERIAL CORRIDORS USING BLUETOOTH TM TO MEASURE TRAVEL TIME ALONG ARTERIAL CORRIDORS A Comparative Analysis Submitted To: City of Philadelphia Department of Streets Philadelphia, PA Prepared By: KMJ Consulting, Inc. 120

More information

MINUTES OF MEETING BOARD OF COUNTY COMMISSIONERS ST. JOHNS COUNTY, FLORIDA MAY 1, :00 A.M.

MINUTES OF MEETING BOARD OF COUNTY COMMISSIONERS ST. JOHNS COUNTY, FLORIDA MAY 1, :00 A.M. MINUTES OF MEETING BOARD OF COUNTY COMMISSIONERS ST. JOHNS COUNTY, FLORIDA MAY 1, 2017 9:00 A.M. Proceedings of a joint meeting of the Board of County Commissioners (BCC) of St. Johns County, Florida,

More information

Currently 2 vacant engineer positions (1 Engineer level, 1 Managing Engineer level)

Currently 2 vacant engineer positions (1 Engineer level, 1 Managing Engineer level) INDOT Agency Factoids (System/Comm.) Number of signalized intersections- 2570 200 connected by fiber 300 connected by radio 0 connected by twisted pair 225 connected by cellular 1500 not connected to communication

More information

Getting Through the Green: Smarter Traffic Management with Adaptive Signal Control

Getting Through the Green: Smarter Traffic Management with Adaptive Signal Control Getting Through the Green: Smarter Traffic Management with Adaptive Signal Control Presented by: C. William (Bill) Kingsland, Assistant Commissioner, Transportation Systems Management Outline 1. What is

More information

An Operational Test of Adaptive Signal Control. Campbell Road Corridor Richardson, Texas

An Operational Test of Adaptive Signal Control. Campbell Road Corridor Richardson, Texas An Operational Test of Adaptive Signal Control Campbell Road Corridor Richardson, Texas September 2011 Robert Saylor and John Black, City of Richardson Operational Test Objectives Install Rhythm adaptive

More information

Minnesota Department of Transportation Rural Intersection Conflict Warning System (RICWS) Reliability Evaluation

Minnesota Department of Transportation Rural Intersection Conflict Warning System (RICWS) Reliability Evaluation LLLK CENTER FOR TRANSPORTATION STUDIES Minnesota Department of Transportation Rural Intersection Conflict Warning System (RICWS) Reliability Evaluation Final Report Arvind Menon Max Donath Department of

More information

2. ROADSIDE TOLL COLLECTION SECTION 01.

2. ROADSIDE TOLL COLLECTION SECTION 01. 2. ROADSIDE TOLL COLLECTION 1 SECTION 01. Toll System Configuration Cash Tolls Violation Enforcement/Video Toll Collection Systems 2 Toll System Configuration Open (barrier tolls) Tolls collected as vehicles

More information

Traffic Signal System Upgrade Needs

Traffic Signal System Upgrade Needs Traffic Signal System Upgrade Needs Presented to: Dallas City Council November 20, 2013 DEPARTMENT OF STREET SERVICES Purpose The City of Dallas has a program to achieve and maintain street pavement condition

More information

The Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP).

The Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP). The Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP). A 7-day public comment period regarding the amendment begins February

More information

Traffic Operations Division. FY Budget Presentation

Traffic Operations Division. FY Budget Presentation FY 2018-19 Budget Presentation Goals and Accomplishments Prior Year Accomplishments in FY 2017-2018 Signals o Installed/Replaced 10 traffic signals o Upgraded 27 traffic signals with ITS equipment Signs

More information

San Antonio Wrong Way Driver Initiative

San Antonio Wrong Way Driver Initiative San Antonio Wrong Way Driver Initiative Brian G. Fariello, P.E. Traffic Management Engineer- TransGuide San Antonio District- TxDOT brian.fariello@txdot.gov The San Antonio Wrong Way Driver Task Force

More information

Ohio Department of Transportation Office of Roadway Engineering January 18, 2013

Ohio Department of Transportation Office of Roadway Engineering January 18, 2013 Ohio Department of Transportation Office of Roadway Engineering January 18, 2013 To: Holders of the Traffic Standard Construction Drawings (SCDs) and Plan Insert Sheets (PISs) As of January 18, 2013, eighteen

More information

Validation Plan: Mitchell Hammock Road. Adaptive Traffic Signal Control System. Prepared by: City of Oviedo. Draft 1: June 2015

Validation Plan: Mitchell Hammock Road. Adaptive Traffic Signal Control System. Prepared by: City of Oviedo. Draft 1: June 2015 Plan: Mitchell Hammock Road Adaptive Traffic Signal Control System Red Bug Lake Road from Slavia Road to SR 426 Mitchell Hammock Road from SR 426 to Lockwood Boulevard Lockwood Boulevard from Mitchell

More information

Georgia Department of Transportation. Automated Traffic Signal Performance Measures Reporting Details

Georgia Department of Transportation. Automated Traffic Signal Performance Measures Reporting Details Georgia Department of Transportation Automated Traffic Signal Performance Measures Prepared for: Georgia Department of Transportation 600 West Peachtree Street, NW Atlanta, Georgia 30308 Prepared by: Atkins

More information

DATACAR ADVANCED MULTILANE TRAFFIC MONITORING SYSTEM

DATACAR ADVANCED MULTILANE TRAFFIC MONITORING SYSTEM DATACAR Doc 9723 0030 ADVANCED MULTILANE TRAFFIC MONITORING SYSTEM Suitable both for permanent and temporary installations Non-Intrusive System Accurate detection, speed, counting and classifying traffic

More information

COMMITTEE OF THE WHOLE MEETING JUNE 26, 2017

COMMITTEE OF THE WHOLE MEETING JUNE 26, 2017 REPORT #ENG-2017-37 COMMITTEE OF THE WHOLE MEETING JUNE 26, 2017 INTRODUCTION OF PARKING AND TRAFFIC BY-LAWS IN THE VICINITY OF SIDEROAD 10 AND THE 11TH LINE, TOWN OF NEW TECUMSETH RECOMMENDATION That

More information

Constructing a Traffic Control Process Diagram

Constructing a Traffic Control Process Diagram 22 Constructing a Traffic Control Process Diagram The purpose of this assignment is to help you improve your understanding of the operation of an actuated traffic controller system by studying eight cases

More information

Charlton/Oxford Route 20 Reconstruction Project

Charlton/Oxford Route 20 Reconstruction Project Public Informational Meeting February 1, 2017 Oxford High School Charlton/Oxford Route 20 Reconstruction Project Project File No. 602659 2014 HDR, Inc., all rights reserved. Public Informational Meeting

More information

Deploying Transit Signal Priority Systems

Deploying Transit Signal Priority Systems Deploying Transit Signal Priority Systems Christopher Poe, Ph.D., P.E. Assistant Agency Director ITS Annual Meeting Austin, September 5, 2008 Acknowledgements n DART - Abed Abukar, Chris Patrick, and Koorosh

More information

Staff Application Form

Staff Application Form Staff Application Form Personal Details: Name Date / / Address. Phone (HM) Phone (Cell).... Email address. Date of Birth / / Age.. Medical: Please circle or fill out the following questions: Health : Excellent

More information

Deep Creek Canyon US Highway 12

Deep Creek Canyon US Highway 12 Deep Creek Canyon US Highway 12 ABC Techniques in Rural Montana Jim Scoles Morrison-Maierle 1 Location Deep Creek Canyon US Highway 12 Helena National Forest Great Falls Map of mid MT showing Location

More information

AUTOMATED TRAFFIC SIGNAL PERFORMANCE MEASURES

AUTOMATED TRAFFIC SIGNAL PERFORMANCE MEASURES AUTOMATED TRAFFIC SIGNAL PERFORMANCE MEASURES ITS California Technical Session 9 - Innovative Technology for Local Cities Thursday, October 16, 2014 Mark Taylor, P.E., PTOE Traffic Signal Operations Engineer

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL Engineering Design Services for the Preliminary Engineering of Lake Nepessing/Davison/Genesee Intersection Improvements Sections 1, 2, 11 and 12 of Elba Township Lapeer County, Michigan

More information

Arterial Connected Vehicle Test Bed Deployment and Lessons Learned

Arterial Connected Vehicle Test Bed Deployment and Lessons Learned ARIZONA CONNECTED VEHICLE PROGRAM Arterial Connected Vehicle Test Bed Deployment and Lessons Learned Faisal Saleem ITS Branch Manager & SMARTDrive Program Manager Maricopa County Department of Transportation

More information

GUJARAT TECHNOLOGICAL UNIVERSITY

GUJARAT TECHNOLOGICAL UNIVERSITY Subject Code Subject Name Date Time Branch 01: Aeronautical Engineering 160101 Aerodynamics-II 27-11-2013 02:30 To 05:00 160102 Fundamentals of Jet Propulsion 29-11-2013 02:30 To 05:00 160103 Vibration

More information

Planarization & Routing Guide

Planarization & Routing Guide Metro Regional Centerlines Collaborative Planarization & Routing Guide Document: Version. Published: July 8, 25 Prepared and edited by: Matt Koukol, MRCC Project Technical Lead Ramsey County GIS Manager

More information

Exploring Pedestrian Bluetooth and WiFi Detection at Public Transportation Terminals

Exploring Pedestrian Bluetooth and WiFi Detection at Public Transportation Terminals Exploring Pedestrian Bluetooth and WiFi Detection at Public Transportation Terminals Neveen Shlayan 1, Abdullah Kurkcu 2, and Kaan Ozbay 3 November 1, 2016 1 Assistant Professor, Department of Electrical

More information

1. Travel time measurement using Bluetooth detectors 2. Travel times on arterials (characteristics & challenges) 3. Dealing with outliers 4.

1. Travel time measurement using Bluetooth detectors 2. Travel times on arterials (characteristics & challenges) 3. Dealing with outliers 4. 1. Travel time measurement using Bluetooth detectors 2. Travel times on arterials (characteristics & challenges) 3. Dealing with outliers 4. Travel time prediction Travel time = 2 40 9:16:00 9:15:50 Travel

More information

GUJARAT TECHNOLOGICAL UNIVERSITY

GUJARAT TECHNOLOGICAL UNIVERSITY 01 AERONAUTICAL 160101 AERODYNAMICS-II 160102 FUNDAMANTALS OF JET PROPULSION 160103 VIBRATION AND NOISE CONTROL 160104 BASIC CONTROL THEORY 160105 COMPUTATIONAL FLUID DYANAMICS -II 160106 AVIONICS 02 AUTOMOBILE

More information

MoDOT ACEC St. Louis Partnering Meeting. September 14, 2017

MoDOT ACEC St. Louis Partnering Meeting. September 14, 2017 MoDOT ACEC St. Louis Partnering Meeting September 14, 2017 Agenda Introductions & Department Update Bill Schnell Design/Planning Updates Tom Evers STL City Jeff Bohler STL North County Lisa Kuntz I-270

More information

Managing traffic through Signal Performance Measures in Pima County

Managing traffic through Signal Performance Measures in Pima County CASE STUDY Miovision TrafficLink Managing traffic through Signal Performance Measures in Pima County TrafficLink ATSPM Case Study Contents Project overview (executive summary) 2 Project objective 2 Overall

More information

siemens.com/mobility Sitraffic Wimag Easy, reliable and cost-effective traffic and parking space monitoring

siemens.com/mobility Sitraffic Wimag Easy, reliable and cost-effective traffic and parking space monitoring siemens.com/mobility Easy, reliable and cost-effective traffic and parking space monitoring Our family of detectors: state-of-the-art detection and wireless technology Compact dimensions (7.5 7.5 5.0 cm),

More information

GUJARAT TECHNOLOGICAL UNIVERSITY

GUJARAT TECHNOLOGICAL UNIVERSITY 01 Aeronautical 160101 Aerodynamics-II 16/05/2011 160102 Fundamantals of Jet Propulsion 17/05/2011 160103 Vibration and Noise Control 19/05/2011 160104 Basic Control Theory 21/05/2011 160105 Computational

More information

DELINEATOR REFERENCE POINT 200' TYPICAL SPACING (YELLOW DELINEATORS) END OF MERGE LANE TAPER DELINEATOR REFERENCE POINT

DELINEATOR REFERENCE POINT 200' TYPICAL SPACING (YELLOW DELINEATORS) END OF MERGE LANE TAPER DELINEATOR REFERENCE POINT 200' TYP. 600' < EACH SIDE BOTH ROADWAYS END OF MERGE LANE TAPER TYPICAL FOR ALL 2-LANE MERGES EXCEPT WHERE THERE IS A MERGE FROM THE RIGHT AND NO OFFSET IN THE THROUGH LANES END OF MERGE LANE TAPER 200'

More information

Historic Preservation DESIGN GUIDELINES

Historic Preservation DESIGN GUIDELINES CITY OF GRANBURY Historic Preservation DESIGN GUIDELINES 8. SIGNS Commentary: These guidelines apply to all signs within a City of Granbury historic district or signs on the property of a City of Granbury

More information

State Road A1A North Bridge over ICWW Bridge

State Road A1A North Bridge over ICWW Bridge Final Report State Road A1A North Bridge over ICWW Bridge Draft Design Traffic Technical Memorandum Contract Number: C-9H13 TWO 5 - Financial Project ID 249911-2-22-01 March 2016 Prepared for: Florida

More information

STANDARD DRAWINGS INDEX MODIFIED FOR CENTRAL REGION Revised August 6, 2018

STANDARD DRAWINGS INDEX MODIFIED FOR CENTRAL REGION Revised August 6, 2018 SYMBOLS STANDARD DRAWINGS INDEX No Statewide Standard - Use Regional A3 Legend Detail Sheet BRIDGE AND STRUCTURES B-08.00 Bin Walls 1 CONSTRUCTION-BARRICADES AND SIGNING C-04.12 Location of Double Traffic

More information

Georgia s Regional Traffic Operations Program

Georgia s Regional Traffic Operations Program Georgia s Regional Traffic Operations Program Shahram Malek, PhD, PE Vice President, ARCADIS US Inc. Regional Traffic Operations Project Manager Koushik Arunachalam, PE Associate Project Manager, ARCADIS

More information

Parts Included: T-Feet Assembly

Parts Included: T-Feet Assembly Parts Included: T-Feet Assembly Foot Kit: J-Rail Kit: Column Kit: 2 Feet 2 T-Top Supports 2 J-Rails Hex Rod to be Included on a Crank Assembly only. 2 Electric or Crank Columns 3 rd Leg option for 3 leg

More information

Street Acceptance Guidelines

Street Acceptance Guidelines Street Acceptance Guidelines Fairfax County Guidelines Flowcharts and Examples October 1, 2009 Table of Contents: Procedural Guidelines Overall Procedure... 2 Contact Information... 2 Initial Street Acceptance

More information

MACOMB COUNTY DEPARTMENT OF ROADS TRAFFIC OPERATIONS CENTER PERFORMANCE MEASURES. August 2017

MACOMB COUNTY DEPARTMENT OF ROADS TRAFFIC OPERATIONS CENTER PERFORMANCE MEASURES. August 2017 MACOMB COUNTY DEPARTMENT OF ROADS TRAFFIC OPERATIONS CENTER To provide and maintain a reliable real time traffic operations system, in coordination with county stakeholders, that enables a safe, efficient,

More information

THE GRAFFITI CONSULTANTS CONSIDERATIONS

THE GRAFFITI CONSULTANTS CONSIDERATIONS THE GRAFFITI CONSULTANTS CONSIDERATIONS NOTE: Please remember that the best way to implement many of these Considerations is to give them a try on a trial basis and see if they work for you. We are always

More information

This page is intentionally left blank

This page is intentionally left blank This page is intentionally left blank This page is intentionally left blank MnDOT Metro District Fact Sheet Mpls./St. Paul District Offices: Roseville-Water's Edge (HQ), Golden Valley, Oakdale mndot.gov/metro/

More information

Standard Plate 7036 is discontinued. It is replaced by Standard Plan Pedestrian Curb Ramp Details.

Standard Plate 7036 is discontinued. It is replaced by Standard Plan Pedestrian Curb Ramp Details. DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management & Technical Support, Design Support Section TRANSMITTAL LETTER NO. (12-02) MANUAL: Standard Plates DATED: May 11, 2012 SUBJECT: Standard

More information

HIGHWAY WORK ZONE DATA COLLECTION INSTRUMENT

HIGHWAY WORK ZONE DATA COLLECTION INSTRUMENT HIGHWAY WORK ZONE DATA COLLECTION INSTRUMENT Case ID: MI Date of Investigation Respondent Employer Information 1. Is the employer the primary contractor or a subcontractor working at the site? Victim Information

More information

2008 ConnDOT Photolog Program Overview

2008 ConnDOT Photolog Program Overview 2008 ConnDOT Photolog Program Overview Brad Overturf, Transportation Photolog Supervisor Northeast Pavement Preservation Partnership 2008 Good morning. Thank you to the Northeast Pavement Preservation

More information

INSTRUCTIONS: 1. Record the transmittal letter number, date, and subject on the transmittal record sheet located in the front of the manual.

INSTRUCTIONS: 1. Record the transmittal letter number, date, and subject on the transmittal record sheet located in the front of the manual. MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Technical Support Design Services Section TRANSMITTAL LETTER NO. (0-03) MANUAL: Standard Plates DATED: September

More information

Introduction to Civil Engineering Systems

Introduction to Civil Engineering Systems Introduction to Civil Engineering Systems LECTURE What is a System? Sam Labi Purdue University, West Lafayette, Indiana 1 Topics for today s conversation System? What the is that? General and Specific

More information

Plan Preparation Checklist

Plan Preparation Checklist Appendix D Plan Preparation Checklist It is the responsibility of the Designer to complete and submit this checklist along with all required drawings for OUC (EFP) Review. All drawings submitted for OUC

More information

WHITE PAPER BENEFITS OF OPTICOM GPS. Upgrading from Infrared to GPS Emergency Vehicle Preemption GLOB A L TRAFFIC TE CHNOLOGIE S

WHITE PAPER BENEFITS OF OPTICOM GPS. Upgrading from Infrared to GPS Emergency Vehicle Preemption GLOB A L TRAFFIC TE CHNOLOGIE S WHITE PAPER BENEFITS OF OPTICOM GPS Upgrading from Infrared to GPS Emergency Vehicle Preemption GLOB A L TRAFFIC TE CHNOLOGIE S 2 CONTENTS Overview 3 Operation 4 Advantages of Opticom GPS 5 Opticom GPS

More information

DEVELOPMENT PLAN CHECKLIST

DEVELOPMENT PLAN CHECKLIST Project Identification Information: DEVELOPMENT PLAN CHECKLIST 1.0 GENERAL 1.1 Additional information as required by specific Land Use 1.2 All sheets to include sheet number ( of ) 1.3 Seal and signature

More information

Bluetooth Low Energy Sensing Technology for Proximity Construction Applications

Bluetooth Low Energy Sensing Technology for Proximity Construction Applications Bluetooth Low Energy Sensing Technology for Proximity Construction Applications JeeWoong Park School of Civil and Environmental Engineering, Georgia Institute of Technology, 790 Atlantic Dr. N.W., Atlanta,

More information

FM 691 CORRIDOR STUDY

FM 691 CORRIDOR STUDY FM 691 CORRIDOR STUDY Transportation Policy Board Meeting August 13, 2008 Agenda Project Overview US 75/FM 691 Interchange US 75 Ramping Alternatives FM 691 Corridor Typical Sections Extension to SH 289

More information

Survey Data and TOPO Checklist

Survey Data and TOPO Checklist Checklists Survey Data and TOPO Preliminary Plan Field Review Plans o Field Review Erosion Control Right-of-Way and Utility Meeting Plans Final Plan Field Review Plans Methods of Plan Markups Plan-in-Hand

More information

Jointing Rural Intersections

Jointing Rural Intersections Design Manual Chapter 5 - Roadway Design 5G - PCC Pavement Joints 5G-4 Jointing Rural Intersections This section describes how to joint rural intersections by following the guidelines outlined in Iowa

More information

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges 50.24 Culverts, Bridges and Culvert Bridges Type, Size and Location (T, S & L) Plans shall be required for all Bridges, Culvert Bridges and Culverts of eight-foot (8') clear span or greater as follows:

More information

Jackson County 2018 Traffic Summit

Jackson County 2018 Traffic Summit Jackson County 2018 Traffic Summit MDOT University Region Contact Information Jackson Transportation Service Center (JTSC) 2750 N. Elm Rd Jackson, MI 49201 (517) 780-7540 Kelby Wallace, P.E. Manager Sam

More information

Current Standard Plates including Transmittal Letters are available on the web at:

Current Standard Plates including Transmittal Letters are available on the web at: MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Project Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (17-04) MANUAL: Standard

More information

Laser Road Surface Sensor - LRSS

Laser Road Surface Sensor - LRSS Laser Road Surface Sensor - LRSS Authors: Thorvald A. Paulsen (Scanmatic) Paul Schmokel (Goodrich) www.scanmatic.no www.goodrich.com Background: Scanmatic have been producing Road Weather Stations for

More information

SUBJECT: Standard Plate 9102 Turf Establishment Areas At Pipe Culvert Ends

SUBJECT: Standard Plate 9102 Turf Establishment Areas At Pipe Culvert Ends MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Project Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (17-03) MANUAL: Standard

More information

General Wireless Permit Package Submission and Review Guidelines. Non VDOT (Existing and New) Structures within VDOT Right of Way

General Wireless Permit Package Submission and Review Guidelines. Non VDOT (Existing and New) Structures within VDOT Right of Way General Wireless Permit Package Submission and Review Guidelines Non VDOT (Existing and New) Structures within VDOT Right of Way January 1, 2018 This document applies to new wireless installations on new

More information

Guide Sign Policy for Secondary State Highways Edition

Guide Sign Policy for Secondary State Highways Edition Massachusetts Highway Department, Ten Park Plaza, Boston, MA 02116-3973 ` Guide Sign Policy for Secondary State Highways 2005 Edition Revised September 2005 1. PURPOSE The Massachusetts Highway Department

More information

CHAPTER 14: TRAFFIC SIGNAL STANDARDS Introduction and Goals Administration Standards Standard Attachments 14.

CHAPTER 14: TRAFFIC SIGNAL STANDARDS Introduction and Goals Administration Standards Standard Attachments 14. 14.00 Introduction and Goals 14.01 Administration 14.02 Standards 14.03 Standard Attachments 14.1 14.00 INTRODUCTION AND GOALS The purpose of this chapter is to outline the City s review process for traffic

More information

icite Product Line DA-DATA AGGREGATOR DA-100B

icite Product Line DA-DATA AGGREGATOR DA-100B icite Product Line DA-DATA AGGREGATOR DA-100B DA-DATA AGGREGATOR DA-100B BASIC CABINET MONITORING The first system to provide cost effective remote traffic cabinet status and intersection data without

More information

City of Surrey Adaptive Signal Control Pilot Project

City of Surrey Adaptive Signal Control Pilot Project City of Surrey Adaptive Signal Control Pilot Project ITS Canada Annual Conference and General Meeting May 29 th, 2013 1 2 ASCT Pilot Project Background ASCT Pilot Project Background 25 Major Traffic Corridors

More information

PHASE ONE PROJECT REPORT

PHASE ONE PROJECT REPORT MOORHEAD AREA INTEGRATED TRAIN DETECTION AND TRAFFIC CONTROL SYSTEM PHASE ONE PROJECT REPORT December 2000 Prepared for: Minnesota Department of Transportation Office of Advanced Transportation Systems

More information

Single Point Urban Interchange (SPUI) with Signals

Single Point Urban Interchange (SPUI) with Signals 1 Single Point Urban Interchange (SPUI) with Signals Allows for concurrent left turns on Wurzbach Parkway and on NW Military Traffic Signal added on NW Military Hwy at Fairfield Bend/ Turnberry Way Large

More information

Columbia Junction Washington Blvd., Jessup, MD Retail/Commercial Center Serving North Laurel, Columbia, Ft.

Columbia Junction Washington Blvd., Jessup, MD Retail/Commercial Center Serving North Laurel, Columbia, Ft. 860., Jessup, MD 20794 Retail/Commercial Center Serving North Laurel, Columbia, Ft. Meade & Elkridge SPACE FOR LEASE Spaces now available for office or retail use Flexible use and opportunity for growth

More information

Columbus Computerized Traffic Signal System

Columbus Computerized Traffic Signal System Where have we been? Where are we today? Where are we going? Eagan L. Foster, P.E. Transportation Division Columbus Public Service Department The Importance of Coordinated Traffic Signal Systems Reduce

More information

2015 GDOT PowerPoint. Title Page

2015 GDOT PowerPoint. Title Page Cartersville MPO Regional Travel Demand Model Update Joint Policy Committee (PC) and Technical Coordinating Committee (TCC) Meeting May 20, 1 BACKGROUND Federal legislation requires Long-Range Transportation

More information

Sandboxing Wireless/RF Vulnerability Research of Connected Systems

Sandboxing Wireless/RF Vulnerability Research of Connected Systems 1 Sandboxing Wireless/RF Vulnerability Research of Connected Systems Michael Calabro 5 October 2016 33rd Annual International Test and Evaluation Symposium Outline What is Wireless Motivating Wireless

More information

Demolition of Ramp C (SN ): Westbound Ontario Street to Eastbound I-90/94) over I-90/94 (JF Kennedy Expressway)

Demolition of Ramp C (SN ): Westbound Ontario Street to Eastbound I-90/94) over I-90/94 (JF Kennedy Expressway) I-90/94 (Kennedy Expressway) at Ohio Street Structure Replacement and Rehabilitation Section Number 0303-474HB-R D-91-177-09 Contract 60F63 Cook County, Region One, District One City of Chicago Project

More information

AN ABSTRACT OF THE DISSERTATION OF. Title: Utilizing Wireless-based Data Collection Units for Automated Vehicle. Abstract approved: David S.

AN ABSTRACT OF THE DISSERTATION OF. Title: Utilizing Wireless-based Data Collection Units for Automated Vehicle. Abstract approved: David S. AN ABSTRACT OF THE DISSERTATION OF Amirali Saeedi for the degree of Doctor of Philosophy in Industrial Engineering presented on February 22, 2013. Title: Utilizing Wireless-based Data Collection Units

More information

Remote PED Assistant. Gabriel DeRuwe. Department of Electrical & Computer Engineering

Remote PED Assistant. Gabriel DeRuwe. Department of Electrical & Computer Engineering Remote PED Assistant Gabriel DeRuwe NIATT Department of Electrical & Computer Engineering Smart Signals Research Advanced Pedestrian Assistant What is it: A handheld device for activation of pedestrian

More information

CHAPTER 28 ACTIVATING/DEACTIVATING A SIGNAL

CHAPTER 28 ACTIVATING/DEACTIVATING A SIGNAL CHAPTER 28 ACTIVATING/DEACTIVATING A SIGNAL ACTIVATING/DEACTIVATING A SIGNAL Activating a traffic control signal requires careful planning and coordination between the project engineer, the contractor

More information

Context Aware Dynamic Traffic Signal Optimization

Context Aware Dynamic Traffic Signal Optimization Context Aware Dynamic Traffic Signal Optimization Kandarp Khandwala VESIT, University of Mumbai Mumbai, India kandarpck@gmail.com Rudra Sharma VESIT, University of Mumbai Mumbai, India rudrsharma@gmail.com

More information

Autodesk InfraWorks & Autodesk InfraWorks 360 Fundamentals Course Length: 3 days

Autodesk InfraWorks & Autodesk InfraWorks 360 Fundamentals Course Length: 3 days Autodesk InfraWorks & Autodesk InfraWorks 360 Fundamentals Course Length: 3 days Note: This guide is based on the June 2015 release of the Autodesk InfraWorks 360 software. There might be slight differences

More information

PLANNING AND DEVELOPMENT

PLANNING AND DEVELOPMENT OVERVIEW Effective January 1, 1992 all applications for multi-family residential and all non-residential building permits require site plan approval before permit issuance. All new developments and existing

More information

SUBJECT: Standard Plate Turf Establishment Areas (at Pipe Culvert Ends)

SUBJECT: Standard Plate Turf Establishment Areas (at Pipe Culvert Ends) MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (14-01) MANUAL: Standard

More information

Operational Fault Detection in Cellular Wireless Base-Stations

Operational Fault Detection in Cellular Wireless Base-Stations Operational Fault Detection in Cellular Wireless Base-Stations Sudarshan Rao IEEE Transactions on Network and Service Management 2006 Motivation Improve reliability of cellular network Build reliable systems

More information

Guidelines for the Preparation of Traffic Signal & Intelligent Transportation System Plans on Design-Build Projects August 2007

Guidelines for the Preparation of Traffic Signal & Intelligent Transportation System Plans on Design-Build Projects August 2007 Guidelines for the Preparation of Traffic Signal & Intelligent Transportation System Plans on Design-Build Projects August 2007 INTRODUCTION Use the following Guidelines in conjunction with the Traffic

More information

Positioning Challenges in Cooperative Vehicular Safety Systems

Positioning Challenges in Cooperative Vehicular Safety Systems Positioning Challenges in Cooperative Vehicular Safety Systems Dr. Luca Delgrossi Mercedes-Benz Research & Development North America, Inc. October 15, 2009 Positioning for Automotive Navigation Personal

More information

Proposal #18: Support Literacy and Education. Contributor: Renda Broadcasting. RAB's Nontraditional Revenue Proposal Collection: Volume #6 NTR TIP:

Proposal #18: Support Literacy and Education. Contributor: Renda Broadcasting. RAB's Nontraditional Revenue Proposal Collection: Volume #6 NTR TIP: RAB's Nontraditional Revenue Proposal Collection: Volume #6 Proposal #18: Support Literacy and Education Contributor: Renda Broadcasting NTR TIP: The scrapes and scratches of childhood often need an extra

More information

2. Remove from the Standard Plate manual: Standard Plate Index, Sheets 1-4 of 4, Numerical Index of Standard Plates (August 31, 2012)

2. Remove from the Standard Plate manual: Standard Plate Index, Sheets 1-4 of 4, Numerical Index of Standard Plates (August 31, 2012) MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management & Technical Support, Design Support Section TRANSMITTAL LETTER NO. (12-04) MANUAL: Standard

More information

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422 B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422 422.1 GENERAL The work under these tender items consists of the fabrication and installation in open cut of precast reinforced

More information

Deployment and Testing of Optimized Autonomous and Connected Vehicle Trajectories at a Closed- Course Signalized Intersection

Deployment and Testing of Optimized Autonomous and Connected Vehicle Trajectories at a Closed- Course Signalized Intersection Deployment and Testing of Optimized Autonomous and Connected Vehicle Trajectories at a Closed- Course Signalized Intersection Clark Letter*, Lily Elefteriadou, Mahmoud Pourmehrab, Aschkan Omidvar Civil

More information

Please consider being a vendor and helping visitors to experience the magic of the Steubenville Nutcracker Village! Sincerely,

Please consider being a vendor and helping visitors to experience the magic of the Steubenville Nutcracker Village! Sincerely, You are invited to be part of the 3 rd Annual Steubenville Nutcracker Village and Advent Market to be held in Fort Steuben Park in downtown Steubenville, Ohio. This special holiday attraction and market,

More information

Adaptive Signal System Mt. Juliet, TN. SR-171 (Mt. Juliet Road)

Adaptive Signal System Mt. Juliet, TN. SR-171 (Mt. Juliet Road) Adaptive Signal System Mt. Juliet, TN SR-171 (Mt. Juliet Road) Project Background Project Location Mt. Juliet, TN: 2015 Census: 28,159 Doubled since 2000 Immediately east of Metro Nashville Mt. Juliet

More information

TMC Simulator for Operator Training Using Micro-Simulation

TMC Simulator for Operator Training Using Micro-Simulation TMC Simulator for Operator Training Using Micro-Simulation Lianyu Chu California Center for Innovative Transportation University of California Berkeley 653 East Peltason Dr Irvine, CA 92697-3600 Tel: (949)824-1876

More information

Traffic Surveillance with Wireless Magnetic Sensors

Traffic Surveillance with Wireless Magnetic Sensors Paper 4779 Traffic Surveillance with Wireless Magnetic Sensors Sing Yiu Cheung, Sinem Coleri Ergen * and Pravin Varaiya University of California, Berkeley, CA 94720-1770, USA *Tel: (510) 642-5270, csinem@eecs.berkeley.edu

More information

Manhole or Catch Basin Type A & B Cone Sections Precast - Design F Manhole or Catch Basin Cover (Reducer Cone Section Precast) Design D

Manhole or Catch Basin Type A & B Cone Sections Precast - Design F Manhole or Catch Basin Cover (Reducer Cone Section Precast) Design D MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (14-02) MANUAL: Standard

More information