50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges

Save this PDF as:
 WORD  PNG  TXT  JPG

Size: px
Start display at page:

Download "50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges"

Transcription

1 50.24 Culverts, Bridges and Culvert Bridges Type, Size and Location (T, S & L) Plans shall be required for all Bridges, Culvert Bridges and Culverts of eight-foot (8') clear span or greater as follows: 1) For all new Subdivision and Special Use Permit Projects. The T, S & L plans for the proposed structure shall be submitted prior to grading plan approval. The completion of a geotechnical report which conforms to Section or Section is necessary to submit T, S & L plans which will be satisfactory to the Department. 2) For St. Louis County Projects designed by consultants where indicated in the consultant contract. Acceptable T, S & L plans will be submitted on a single 24" x 36" sheet and will be arranged and drafted in a legible manner. The T, S & L plans will contain the following views and information: Plan View 1) Provide span lengths; out-to-out structure length; skew angle; out-to-out structure width; and roadway horizontal clearance between curbs, barriers or railings. 2) Show stations and elevations along profile grade line. 3) Show station equation for intersecting reference line on roadways. 4) Show stations and offsets to roadway tapers that are across or under the structure. 5) Bridges are to be laid out with stationing going from the left side of the sheet to the right side of the sheet. 6) Culverts are to be laid out with stationing going from the bottom of the sheet to the top of the sheet. (Culvert lengths from the roadway centerline to the culvert ends along its centerline should be rounded off to the nearest 1"). 7) Show stationing direction on road under, if applicable. 8) Show location of point of minimum vertical under-clearance on bridges over roadways or railroads. 9) Show horizontal clearances of proposed piers to under-passing roadways. 10) Show horizontal clearance from edge of roadway to culvert headwall. 11) Show stage construction line and temporary sheet piling location when applicable. 9/1/ Culverts, Bridges and Culvert Bridges

2 12) Show deck drains and spacing. 13) Plot boring locations. 14) Show proposed channel paving or ungrouted revetment within twenty feet (20') upstream and downstream from bridge. 15) Show outline of limits of existing structure (where applicable) including piers. 16) Show embankment slopes adjacent to structure. 17) Show slope of channel paving at right angle to stream. 18) Show any pipe culverts and local drainage near structure. 19) Add shoulder-widening note for guardrail where structures are wider than approach roadway. "The width between the guardrails shall be the width between the bridge rails or parapets which will require approach shoulder widening." 20) Where required, show proposed bridge approach slabs and bridge approach pavement. 21) Show location of bridge railing or barrier, bridge anchor sections, barrier transition, curb transitions, approach sidewalks and guardrail terminations. 22) Check for proper drafting (particularly at bridge ends). 23) Show railroad mile post information and railroad deck drain note where applicable. 24) Show north arrow. 25) Show all retaining walls and provide appropriate details. Elevation View 1) Use same scales for vertical and horizontal dimensioning. 2) Show bridge exception stations. 3) Show back elevation of barrier and/or railing. 4) Show estimated footing elevations, pile type with estimated capacities and lengths and battered piles as needed for foundations on piles and allowable soil bearing pressures for foundations and spread footings. 5) Show proposed culvert opening dimensions if applicable. 6) Show pipe culverts through embankment if required. 7) Show pier elevation consistent with pier sketch. 9/1/ Culverts, Bridges and Culvert Bridges

3 8) Plot natural ground line. 9) Show stream bed elevation where applicable. 10) Show proposed structural excavation datum, if any. 11) Place culvert flowline in accordance with the provisions of Section ) Show high water elevation and design storm. 13) Show pier thickness (stream crossing only). 14) Add note for bridges over railroads - "No deck drains will be permitted in the span over tracks or within 10' of cross arms of a railroad pole line." 15) Provide vertical scale to determine natural ground elevations. Upper Left Hand Corner Data 1) Show benchmark note. 2) Show existing structure description, length, width and old structure number (if applicable). 3) Show staging instructions, if applicable. 4) Add note when to remove existing structure, if necessary. 5) Show salvage materials, if any. Cross Section 1) The following should be shown on each cross section: a) Dimension bridge roadway and shoulder widths. b) Slab thickness. c) Stringer size, spacing, haunches and note indicating composite action (if applicable). d) Rail or barrier type and vertical dimensions. e) Crown configuration and location of profile grade application. f) Median and sidewalks. g) For box culverts, show channel slope. 9/1/ Culverts, Bridges and Culvert Bridges

4 h) For curved bridges: Offset tangent, all beams...radii. i) Staging details with type of temporary barrier to be used. j) Deck Drains - Omit drains over roadways and sidewalks, over railroads as previously noted and on the high side of superelevation. Section thru Abutment 1) Show proper type along with a partial elevation of the superstructure extending from the abutment. 2) Show bridge exception application location. 3) Show approach slab. 4) Show only dimensions that are necessary for planning purposes. 5) Show all bearing types. 6) Show vertical drain. 7) Show Class A Underdrain. Pier Sketch 1) Show proper type of pier or abutment used. 2) Show correct number of columns. 3) Make sketch to scale for aesthetic evaluation of pier shape. 4) Add crash wall for bridges over railroads. 5) Provide dimension from ground line to top of crash wall. 6) Show location and type of all proposed construction joints. Supplemental Sections 1) Show section thru paved slope protection. 2) Show section through riprap. 9/1/ Culverts, Bridges and Culvert Bridges

5 Title Block 1) General plan, road name over feature name, project number, bridge number, name of development (if applicable), name and address of consulting engineer, name and address of developer (if applicable). Profile Grade 1) Show location, grades, curve length and elevations and stations of PVC, PVT and PVI. 2) Show all profiles for roads over and under. Horizontal Curve Data 1) PI Station, I, D, R, L, T, E, PC Station, SE and SE or crown attainment stations. Location Sketch 1) Show Range, Township, Principle Meridian, Section Numbers, North Arrow and Proposed Structure. Design Stresses 1) Show for both cast-in-place and precast units. 2) Indicate both HS-25 and St. Louis County T45 loading unless one loading type controls the design of all structural components. 3) Indicate future wearing surface loading. 4) Indicate the design specifications used. 5) For culverts and culvert bridges, indicate the design lateral pressure and surcharge loadings used. 6) For bridges, indicate the seismic performance category, acceleration coefficient and site coefficient. 9/1/ Culverts, Bridges and Culvert Bridges

6 Other 1) Required Hydraulic Table for Bridges and Culvert Bridges - All plans submitted for structures which are considered to be bridges or culvert bridges shall contain a completed version of the following table regardless of the actual design flow: HYDROLOGIC DATA Drainage Area = Design Discharge = Design High Water Elevation = Frequency = BASIC FLOOD DATA Q 100 = High Water Elevation = 2) Show roadway data (Classification), including design ADT, DHV, and ADTT. 3) Show offset sketches for horizontally curved roadways. 9/1/ Culverts, Bridges and Culvert Bridges

Survey Data and TOPO Checklist

Survey Data and TOPO Checklist Checklists Survey Data and TOPO Preliminary Plan Field Review Plans o Field Review Erosion Control Right-of-Way and Utility Meeting Plans Final Plan Field Review Plans Methods of Plan Markups Plan-in-Hand

More information

DEVELOPMENT PLAN CHECKLIST

DEVELOPMENT PLAN CHECKLIST Project Identification Information: DEVELOPMENT PLAN CHECKLIST 1.0 GENERAL 1.1 Additional information as required by specific Land Use 1.2 All sheets to include sheet number ( of ) 1.3 Seal and signature

More information

Project Name: County File No.: Checked by: For: Date:

Project Name: County File No.: Checked by: For: Date: Project Name: County File No.: Checked by: For: Date: Print name Firm or agency Items noted in the checklist shall be considered the minimum amount of information necessary for submission of construction

More information

CONTRACT PLANS READING

CONTRACT PLANS READING CONTRACT PLANS READING A training course developed by the FLORIDA DEPARTMENT OF TRANSPORTATION This 2009 revision was carried out under the direction of Ralph Ellis, P. E., Associate Professor of Civil

More information

MICHIGAN DESIGN MANUAL ROAD DESIGN CHAPTER

MICHIGAN DESIGN MANUAL ROAD DESIGN CHAPTER 1.01 DEVELOPMENT METHODS 1.01.01 References 1.01.02 General 1.01.03 Survey and Mapping Methods 1.02 PLAN SHEETS MICHIGAN DESIGN MANUAL 1.02.01 Title Sheet A. Project Location B. Traffic Data C. Project

More information

Town of Westlake Construction Plans Review Checklist

Town of Westlake Construction Plans Review Checklist CONSTRUCTION PLANS CONTENTS All Drawings 24 x 36 Cover Sheet Final Plat Site Plan Demolition Plan Utility Plan Drainage Area Map and Calculations Paving Plan & Profile Sheets Storm Drain Plan & Profile

More information

580 - NOISE BARRIERS OPSS 580 INDEX

580 - NOISE BARRIERS OPSS 580 INDEX 580 - OPSS 580 INDEX 580.1 GENERAL 580.1.1 Noise Barrier Design Elements 580.1.1.1 Wind-Load Designs 580.1.1.2 Sound-Absorptive Barriers 580.1.1.3 Noise Barrier Colour, Pattern and Texture 580.1.2 Grading

More information

CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION:

CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION: CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION: LOG NO.: LEGEND REVIEW REVIEWED BY DATE / - Requirement satisfied 1 O Requirement not satisfied 2?

More information

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422 B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422 422.1 GENERAL The work under these tender items consists of the fabrication and installation in open cut of precast reinforced

More information

PART XIII: HYDRAULIC/ HYDROLOGY SURVEYS

PART XIII: HYDRAULIC/ HYDROLOGY SURVEYS PART XIII: HYDRAULIC/ HYDROLOGY SURVEYS 13.1 Purpose and Scope Hydraulic surveys are required for flow analysis to determine bridge and culvert design characteristics. A hydraulic survey is usually but

More information

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for preparation

More information

Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02

Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02 Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02 1. INTRODUCTION This standard is written to provide the professional surveyor (Surveyor) and the client with a guideline for producing

More information

AASHTO/NSBA Steel Bridge Collaboration G Design Drawing Presentation Guidelines. AASHTO/NSBA Steel Bridge Collaboration

AASHTO/NSBA Steel Bridge Collaboration G Design Drawing Presentation Guidelines. AASHTO/NSBA Steel Bridge Collaboration AASHTO/NSBA Steel Bridge Collaboration G 1.2-2003 Design Drawing Presentation Guidelines AASHTO/NSBA Steel Bridge Collaboration Preface This document is a standard developed by the AASHTO/NSBA Steel Bridge

More information

Survey Requirements. Design Guidelines and Standards. June Office of the University Architect

Survey Requirements. Design Guidelines and Standards. June Office of the University Architect Design Guidelines and Standards Survey Requirements June 2004 Office of the University Architect Construction Management P.O. Box 210181 Cincinnati, Ohio 45221-0181 Table of Contents Survey Requirements

More information

City of Regina Standard Construction Specification SECTION 2999 LISTING OF ROADWAY STANDARD DRAWINGS

City of Regina Standard Construction Specification SECTION 2999 LISTING OF ROADWAY STANDARD DRAWINGS City of Regina Standard Construction Specification SECTION 2999 LISTING OF ROADWAY STANDARD DRAWINGS R-1 Alternate Pavement Structures July/10 R-2 Typical Cross Sections for Asphaltic Concrete Pavements

More information

Overview of Precast ABC Projects in the Pacific Northwest. Chuck Prussack, P.E., Oldcastle Precast, Inc - Spokane

Overview of Precast ABC Projects in the Pacific Northwest. Chuck Prussack, P.E., Oldcastle Precast, Inc - Spokane Overview of Precast ABC Projects in the Pacific Northwest Chuck Prussack, P.E., Oldcastle Precast, Inc - Spokane 1 Techniques Additional prefabrication of units to reduce field timeline Simplify deck installation

More information

MAINTENANCE HOLES, CATCH BASINS AND DITCH INLETS - MTC FORM 407 INDEX

MAINTENANCE HOLES, CATCH BASINS AND DITCH INLETS - MTC FORM 407 INDEX 407-1 - MAINTENANCE HOLES, CATCH BASINS AND DITCH INLETS - MTC FORM 407 INDEX 407-1.1 GENERAL Tender Items Specifications Standard Drawings 407-1.1.1 Frame and Grate Selection 407-1.1.2 Selection of Structure

More information

Revised BRIDGE REPORT AND LAYOUT PAVEMENT STRUCTURE DESIGN CHAPTER VII UTILITIES CHAPTER VIII TRAFFIC CONTROL DEVICES

Revised BRIDGE REPORT AND LAYOUT PAVEMENT STRUCTURE DESIGN CHAPTER VII UTILITIES CHAPTER VIII TRAFFIC CONTROL DEVICES CHAPTER I CHAPTER II CHAPTER III CHAPTER IV CHAPTER V CHAPTER VI GENERAL INFORMATION PRELIMINARY DESIGN SURVEYS DETAIL DESIGN BRIDGE REPORT AND LAYOUT PAVEMENT STRUCTURE DESIGN CHAPTER VII UTILITIES Revised

More information

3. DESIGN SPECIFICATIONS

3. DESIGN SPECIFICATIONS Schedule H to Bylaw 7452, Subdivision Bylaw Page 10 3. DESIGN SPECIFICATIONS 3.1 General 3.1.1 The Design Specifications apply to the design of sanitary sewers, storm drains, waterworks, roadways, and

More information

City of Beaumont. Public Works Engineering. Street Improvement Plan Checklist REV 4/18/16

City of Beaumont. Public Works Engineering. Street Improvement Plan Checklist REV 4/18/16 City of Beaumont Public Works Engineering Project Name: TR: Project No.: Date: Street Improvement Plan Checklist Chk A. All Sheets 1. 24" x 36" 2. Signed by the engineer-of-work 3. Marked with the contact

More information

1.1 GENERAL RECORD DRAWING REQUIREMENTS

1.1 GENERAL RECORD DRAWING REQUIREMENTS Page 1 of 5 VILLAGE OF ROMEOVILLE RECORD DRAWINGS CHECKLIST PART I GENERAL Record drawings are required to provide a means of schematic verification that the intent of the approved engineering design has

More information

Deep Creek Canyon US Highway 12

Deep Creek Canyon US Highway 12 Deep Creek Canyon US Highway 12 ABC Techniques in Rural Montana Jim Scoles Morrison-Maierle 1 Location Deep Creek Canyon US Highway 12 Helena National Forest Great Falls Map of mid MT showing Location

More information

SCHEDULE 10 ENGINEERING DRAWING SUBMISSION

SCHEDULE 10 ENGINEERING DRAWING SUBMISSION SCHEDULE 10 ENGINEERING DRAWING SUBMISSION Subdivision, Development and Servicing Bylaw No. 1535 10. ENGINEERING DRAWING SUBMISSIONS TABLE OF CONTENTS 1.0 General 3 1.1. Introduction 3 1.2. General Requirements

More information

CITY OF DANA POINT DEVELOPMENT REVIEW

CITY OF DANA POINT DEVELOPMENT REVIEW Section I EARTHWORK CITY OF DANA POINT DEVELOPMENT REVIEW COST ESTIMATE UNIT PRICE LIST May 2002 Page 1 of 12 Section I EARTHWORK TABLE OF CONTENTS SECTION AND TOPICS...PAGE INTRODUCTION... i I EARTHWORK...

More information

Construction Plan Reading Basics & Applications

Construction Plan Reading Basics & Applications Construction Plan Reading Basics & Applications July 12 th, 2016 / 4 p.m. Richland County Transportation Penny Office Instructor Ben W. Lewis, PE Welcome & Introductions Instructor Ben W. Lewis, PE Project

More information

PROJECT NAME: TRACT, PARCEL MAP PROJECT ID NO. PLAN CHECKED BY: 1ST CHECK 3RD CHECK 2ND CHECK COMMENTS FINAL MYLAR DATE CHECKED:

PROJECT NAME: TRACT, PARCEL MAP PROJECT ID NO. PLAN CHECKED BY: 1ST CHECK 3RD CHECK 2ND CHECK COMMENTS FINAL MYLAR DATE CHECKED: CITY OF COLTON PUBLIC WORKS/ENGINEERING DEPARTMENT STREET IMPROVEMENT PLAN REVIEW LIST (PROVIDE SEPARATE ON-SITE & OFF-SITE STREET IMPROVEMENT PLAN SETS) PROJECT NAME: TRACT, PARCEL MAP PROJECT ID NO.

More information

Ohio Department of Transportation, VBA Documentation

Ohio Department of Transportation, VBA Documentation Contents 1.1 Current Versions... 2 1.2 Overview... 3 1.3 Supporting Files and Standards... 4 1.3.1 ODOT_Drainage.cel... 4 1.3.2 ODOT2013.ddb... 5 1.4 ODOT_StormSewerPlan2013.mvba... 6 1.4.1 Mode: Place

More information

Ecological Restoration Drafting & Design Guidelines

Ecological Restoration Drafting & Design Guidelines Ecological Restoration Drafting & Design Guidelines Version 2.0 July 2017 Philadelphia Water Ecological Restoration Drafting & Design Guidelines Table of Contents 1.0 INTRODUCTION...2 2.0 GENERAL PLAN

More information

Article 4 PROCEDURES for PLOT PLAN and SITE PLAN REVIEW

Article 4 PROCEDURES for PLOT PLAN and SITE PLAN REVIEW Article 4 PROCEDURES for PLOT PLAN and SITE PLAN REVIEW Section 4.01 Purpose It is the intent of this Article to specify standards, application and data requirements, and the review process which shall

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL Engineering Design Services for the Preliminary Engineering of Lake Nepessing/Davison/Genesee Intersection Improvements Sections 1, 2, 11 and 12 of Elba Township Lapeer County, Michigan

More information

Grease Interceptor Design Checklist

Grease Interceptor Design Checklist CHECKLIST C2 Revised 5/2/2016 Grease Interceptor Design Checklist Public Works DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling private

More information

9 LAND SURVEYING. 9.1 General. 9.2 Administrative Requirements Standards Meetings Survey Data Provided to the Design-Builder

9 LAND SURVEYING. 9.1 General. 9.2 Administrative Requirements Standards Meetings Survey Data Provided to the Design-Builder 9 LAND SURVEYING 9.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with land surveying, including Project and supplemental horizontal and vertical control

More information

REQUIREMENTS. for ENGINEERING SERVICES PUBLIC CONSTRUCTION PROJECTS

REQUIREMENTS. for ENGINEERING SERVICES PUBLIC CONSTRUCTION PROJECTS REQUIREMENTS for ENGINEERING SERVICES on PUBLIC CONSTRUCTION PROJECTS April, 2007 David W. Johnson Senior Engineer Design & Construction Requirements for Engineering Services on Public Construction Projects

More information

PART 4 STANDARD DRAWINGS FOR CONSTRUCTION

PART 4 STANDARD DRAWINGS FOR CONSTRUCTION 4.0. INTRODUCTION PART 4 STANDARD DRAWINGS FOR CONSTRUCTION In this document, Ivins City adopts the most recent edition (currently 2007), including all amendments, of the APWA Utah Chapter s Manual of

More information

Oil-Water Separator Design Checklist

Oil-Water Separator Design Checklist CHECKLIST C3 Revised 5/2/2016 Oil-Water Separator Design Checklist DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling private oil-water

More information

MINIMUM DRAWING REQUIREMENTS FOR WATER AND SEWER LINE PROJECTS

MINIMUM DRAWING REQUIREMENTS FOR WATER AND SEWER LINE PROJECTS Public Works Department Water & Wastewater Services WATER & WASTEWATER ENGINEERING DIVISION 2555 West Copans Road Pompano Beach, Florida 33369 954-831-0745 FAX 954-831-0798/0925 MINIMUM DRAWING REQUIREMENTS

More information

PLANNING AND DEVELOPMENT

PLANNING AND DEVELOPMENT OVERVIEW Effective January 1, 1992 all applications for multi-family residential and all non-residential building permits require site plan approval before permit issuance. All new developments and existing

More information

EXCAVATION AND BACKFILL

EXCAVATION AND BACKFILL Standard Specification 2565.3, 2451, and 1805 A basic understanding of specifications is needed to properly replace the disturbed soil and restore the condition of the excavated area. The size of the disturbed

More information

September 21, Mannik Smith Group 1771 North Dixie Highway Monroe, Michigan RE: LA Fitness City File No.: CVLP

September 21, Mannik Smith Group 1771 North Dixie Highway Monroe, Michigan RE: LA Fitness City File No.: CVLP CITY OF ANN ARBOR, MICHIGAN Public Services Area / Engineering 301 E. Huron Street, P.O. Box 8647 Ann Arbor, Michigan 48107 Phone (734) 794-6410 Fax (734) 994-1744 Web: www.a2gov.org Printed on recycled

More information

KC Water Rules and Regulations For Water Main Extensions and Relocations

KC Water Rules and Regulations For Water Main Extensions and Relocations KC Water Rules and Regulations For Water Main Extensions and Relocations MAY 2017 NOTE: Changes from 2016 are highlighted in yellow and appear on Pages 5, 8, 10-11, 13, and 15. Additional changes made

More information

Application for Site Plan Review

Application for Site Plan Review Application for Site Plan Review 3275 Central Blvd., Hudsonville, Michigan 49426-1450, 616.669.0200 fax 616.669.2330 It is STRONGLY recommended that any application that must go before the Planning Commission

More information

Record Drawing Standards for Projects Version 2.1

Record Drawing Standards for Projects Version 2.1 for Projects Version 2.1 Updated September 21, 2016 Department: Spatial Data Group Engineering & Maintenance 1. INTRODUCTION... 1 2. GENERAL STANDARDS... 1 2.1 Drawing Standards... 1 2.2 Digital Submission

More information

(DTM) OFFICE OF DESIGN ENGLISH PRELIMINARY SURVEY SPECIFICATIONS

(DTM) OFFICE OF DESIGN ENGLISH PRELIMINARY SURVEY SPECIFICATIONS August, 2008 (DTM) OFFICE OF DESIGN ENGLISH PRELIMINARY SURVEY SPECIFICATIONS A. GENERAL These specifications describe the collection of preliminary field survey data. This data must be sufficiently detailed

More information

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS All plans for sanitary sewer main extensions, improvements and modifications

More information

Date Requested, 200_ Work Order No. Funding source Name of project Project limits: Purpose of the project

Date Requested, 200_ Work Order No. Funding source Name of project Project limits: Purpose of the project Bureau of Engineering SURVEY DIVISION REQUEST FOR TOPOGRAPHIC SURVEY Date Requested, 200_ Work Order No. Funding source Name of project Project limits: Purpose of the project Caltrans involvement (must

More information

MSD STANDARD DRAWINGS LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT 700 WEST LIBERTY STREET LOUISVILLE, KENTUCKY

MSD STANDARD DRAWINGS LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT 700 WEST LIBERTY STREET LOUISVILLE, KENTUCKY MSD M etr o p olitan S e w e r Di s t r ict STANDARD DRAWINGS LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT 700 WEST LIBERTY STREET LOUISVILLE, KENTUCKY 40203-1911 STANDARD DRAWINGS DIVISION

More information

Construction Documents (CDs) Checklist

Construction Documents (CDs) Checklist Development Services Department 100 N. Wilcox Street, Castle Rock CO 80104 Project Manager 720-733-3582 Construction Documents (CDs) Checklist A complete Construction Document (CD) submittal will contain

More information

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for

More information

CHAPTER 1: TITLE SHEET and GENERAL LAYOUT

CHAPTER 1: TITLE SHEET and GENERAL LAYOUT CHAPTER 1: TITLE SHEET and GENERAL LAYOUT AREA OF ENVIRONMENTAL SENSITIVITY It is important to show the areas of environmental sensitivity in the plan to make sure these areas are not impacted. These locations

More information

Public Projects Plan Submittal Guidelines Revised August 4, 2017 Plan submittal Process: 10% Plans 25% Plans 30% Plans 60% Plans 90% Plans

Public Projects Plan Submittal Guidelines Revised August 4, 2017 Plan submittal Process: 10% Plans 25% Plans 30% Plans 60% Plans 90% Plans Plan submittal Process: 10% Plans - Based on survey and include detailed horizontal geometry per Public Project Checklist. 25% Plans - Plans include profiles, typical sections, phasing & cross sections

More information

SUBMITTAL REQUIREMENTS FOR USE PROCESS III OR PROCESS IV

SUBMITTAL REQUIREMENTS FOR USE PROCESS III OR PROCESS IV COMMUNITY DEVELOPMENT DEPARTMENT 33325 8 th Avenue South Federal Way WA 98003 253-835-2607; Fax 253-835-2609 www.cityoffederalway.com SUBMITTAL REQUIREMENTS FOR USE PROCESS III OR PROCESS IV USE PROCESS

More information

Any of the above may be used as source documents. Let's discuss each of these types of documentation.

Any of the above may be used as source documents. Let's discuss each of these types of documentation. INTRODUCTION TO DOCUMENTATION Much of the work of preparing final estimates involves careful and orderly documentation of measurements and computations. You will become familiar with the various types

More information

Charlotte County Utilities DESCRIPTION

Charlotte County Utilities DESCRIPTION As-built Drawings / Surveyor 1. Electronic copy of survey data in tabular form of the utility assets 2. A signed and sealed letter with the following statement: "I hereby certify that the as-built location

More information

DIVISION PAVEMENT MARKINGS AND MARKERS

DIVISION PAVEMENT MARKINGS AND MARKERS DIVISION 61 66 PAVEMENT MARKINGS AND MARKERS 66.01 SCOPE: The purpose of these specifications is to describe the minimum requirements of the City of Chesapeake for pavement markings and shall be in addition

More information

Public Works City of Lebanon, Tennessee; Department of Public Works

Public Works City of Lebanon, Tennessee; Department of Public Works SECTION 1 GENERAL 1. DEFINITIONS Public Works City of Lebanon, Tennessee; Department of Public Works City City of Lebanon, Wilson County, Tennessee City Engineer Employed by the City of Lebanon, Registered

More information

Suggested Reinforcement Detailing Practices Based on comments from R&D and ES ESS Committees

Suggested Reinforcement Detailing Practices Based on comments from R&D and ES ESS Committees Suggested Reinforcement Detailing Practices Based on comments from R&D and ES ESS Committees General 1. When detailing substructures, it is preferable not to use series bars unless necessary. The first

More information

OVER-HEIGHT FENCE/RETAINING WALL CERTIFICATION APPLICATION

OVER-HEIGHT FENCE/RETAINING WALL CERTIFICATION APPLICATION OVER-HEIGHT FENCE/RETAINING WALL CERTIFICATION APPLICATION Application information below to be completed by Applicant/Agent//Owner APN PROPERTY ADDRESS PROPERTY LOCATION (if no address) APPLICANT S NAME

More information

APPLICATION FOR SITE PREPARATION PERMIT

APPLICATION FOR SITE PREPARATION PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision/Plat Name: Location Description/ Nearest Intersection: Acreage: APPLICATION FOR SITE PREPARATION PERMIT No.

More information

P.E. Civil Exam Review:

P.E. Civil Exam Review: P.E. Civil Exam Review: Geometric Design J.P. Mohsen Email: jpm@louisville.edu Horizontal Curves Slide 2 Back tangent Forward tangent T T Slide 3 Back tangent Forward tangent T T P.C. or T.C. P.T. Slide

More information

TECHNICAL NOTE SEGMENTAL BRIDGE WIZARD. Introduction. Segmental Bridge Span Assembly

TECHNICAL NOTE SEGMENTAL BRIDGE WIZARD. Introduction. Segmental Bridge Span Assembly COMPUTERS AND STRUCTURES, INC., MARCH 2015 TECHNICAL NOTE SEGMENTAL BRIDGE WIZARD Introduction This document describes the use of the segmental bridge wizard, including functionality, options, and terminology.

More information

SECTION 3 - GUIDELINES FOR ROADWAY PROJECTS

SECTION 3 - GUIDELINES FOR ROADWAY PROJECTS SECTION 3 - GUIDELINES FOR ROADWAY PROJECTS 3.1 GENERAL The use of tables is encouraged where items can be listed in one area rather than having them scattered all over the drawing (e.g., culvert tables

More information

The Basics. HECRAS Basis Input. Geometry Data - the basics. Geometry Data. Flow Data. Perform Hydraulic Computations. Viewing the Output

The Basics. HECRAS Basis Input. Geometry Data - the basics. Geometry Data. Flow Data. Perform Hydraulic Computations. Viewing the Output The Basics HECRAS Basis Input Geometry Data. Flow Data. Perform Hydraulic Computations by G. Parodi WRS ITC The Netherlands Viewing the Output ITC Faculty of Geo-Information Science and Earth Observation

More information

CITY OF MERCER ISLAND

CITY OF MERCER ISLAND CITY OF MERCER ISLAND DEVELOPMENT SERVICES GROUP 9611 SE 36TH STREET MERCER ISLAND, WA 98040 PHONE: 206.275.7605 www.mercergov.org NONLAND USE APPLICATION- PLAN SET GUIDE The applicant for a land use approval

More information

8.1 Control. 8.2 Sheet Setup

8.1 Control. 8.2 Sheet Setup 8.1 Control Responsibility for development of the pipe data sheets is in the hands of the project s drainage or roadway designer. Pipe data sheets should be developed after the drainage design is fairly

More information

A WORD ABOUT BRACING PART A - BUILDING A STRAIGHT, PILE BENT, OPEN DECK TRESTLE. Built in Place, Straight

A WORD ABOUT BRACING PART A - BUILDING A STRAIGHT, PILE BENT, OPEN DECK TRESTLE. Built in Place, Straight BUILDING LARGE SCALE TRESTLES You have many options when building a large scale trestle. The choices you make may be based on the prototype you are modeling; the era or industry you are modeling; or, simply

More information

What Plans Do I Need for a Building Permit?

What Plans Do I Need for a Building Permit? What Plans Do I Need for a Building Permit? 6 CITY OF PORTLAND, OREGON - BUREAU OF DEVELOPMENT SERVICES 1900 SW 4th Avenue, Por tland, Oregon 97201 503-823-7300 www.portlandoregon.gov/bds This brochure

More information

North Carolina No-Rise Guidance Document

North Carolina No-Rise Guidance Document North Carolina No-Rise Guidance Document June 4, 2015 Atlanta, GA Dan Brubaker, PE, CFM NFIP Engineer (919) 825-2300 Dan.Brubaker@ncdps.gov Purpose Provide guidance for No-Rise preparation Engineers Provide

More information

THE ONTARIO CONCRETE PIPE ASSOCIATION

THE ONTARIO CONCRETE PIPE ASSOCIATION THE ONTARIO CONCRETE PIPE ASSOCIATION PRECAST BOX & CULVERT GUIDELINE Table of Contents 1 INTRODUCTION... 6 1.1 Background... 6 1.2 Existing Handbook and Drawings... 6 1.3 Distribution... 6 1.4 Revisions...

More information

CHECKLIST FOR DEVELOPMENT PLAN REVIEW & SUBDIVISION MAPS

CHECKLIST FOR DEVELOPMENT PLAN REVIEW & SUBDIVISION MAPS Planning Division 245 East Bonita Ave., San Dimas CA 91773 (909) 394-6250 CHECKLIST FOR DEVELOPMENT PLAN REVIEW & SUBDIVISION MAPS The Development Plan Review process is provided to encourage and promote

More information

RESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST

RESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST RESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST The purpose of this form is to inform applicants of: 1) the requirements for building permits and stormwater permits for residential demolition projects;

More information

Checklist MISCELLANEOUS REQUIREMENTS G G G G G G G G

Checklist MISCELLANEOUS REQUIREMENTS G G G G G G G G Background The City of North Las Vegas strives to provide the development community with adequate information to ensure the successful completion of any project in the City. To aid in the submittal of

More information

PORT OF ST. HELENS SCAPPOOSE INDUSTRIAL AIRPARK PARALLEL TAXIWAY B RELOCATON AIP PROJECT ADDENDUM NO. 1

PORT OF ST. HELENS SCAPPOOSE INDUSTRIAL AIRPARK PARALLEL TAXIWAY B RELOCATON AIP PROJECT ADDENDUM NO. 1 PORT OF ST. HELENS SCAPPOOSE INDUSTRIAL AIRPARK PARALLEL TAXIWAY B RELOCATON AIP PROJECT 3-41-0056-024-2018 ADDENDUM NO. 1 Addendum No. 1 hereby amends the contract documents and drawings for the Scappoose

More information

Phase 2 Silver Line Update

Phase 2 Silver Line Update Phase 2 Silver Line Update Committee for Dulles Leslie Pereira, Communications & Outreach Manager Capital Rail Constructors February 16, 2017 Safety Since Notice to Proceed: Manpower Hours: 3,280,898

More information

PLANNING DEPARTMENT SUBMITTAL REQUIREMENTS FOR CONDITIONAL USE PERMITS CLASS 4 DEVELOPMENT REVIEW PROCESS. A. Written Material

PLANNING DEPARTMENT SUBMITTAL REQUIREMENTS FOR CONDITIONAL USE PERMITS CLASS 4 DEVELOPMENT REVIEW PROCESS. A. Written Material PLANNING DEPARTMENT 970.668.4200 0037 Peak One Dr. PO Box 5660 www.summitcountyco.gov Frisco, CO 80443 SUBMITTAL REQUIREMENTS FOR CONDITIONAL USE PERMITS CLASS 4 DEVELOPMENT REVIEW PROCESS Per the provisions

More information

Survey Control Point Observations

Survey Control Point Observations Level Name SURVEY_CTRL SURVEY_CTRL_CHK_NODE SURVEY_CTRL_NODE SURVEY_CTRL_OBS SURVEY_CTRL_REF_SYM SURVEY_CTRL_SETUPS SURVEY_CTRL_SYM SURVEY_CTRL_TXT SURVEY_DTM_BREAKLINE SURVEY_DTM_BREAKLINE_NODE SURVEY_DTM_CHECK_NODE

More information

Conceptual, Preliminary and Final Site Plan Review in Holladay City

Conceptual, Preliminary and Final Site Plan Review in Holladay City Conceptual, Preliminary and Final Site Plan Review in Holladay City The City of Holladay incorporated in December, 1999 and adopted its own zoning ordinance in May, 2000. All land use decisions are made

More information

SUBSTATION SECURITY WALL INSTALLATION MANUAL

SUBSTATION SECURITY WALL INSTALLATION MANUAL SUBSTATION SECURITY WALL INSTALLATION MANUAL JULY 26, 2016 OLDCASTLE PRECAST, INC. 3000 New McEver Rd, Acworth, Ga 30101 Substation Security Wall Installation Manual This Installation Manual is intended

More information

VILLAGE OF VILLA PARK CENTRAL BOULEVARD IMPROVEMENTS LOCATION MAP (NOT TO SCALE) CORTESI AVE. MYRTLE AVE. CENTRAL BLVD.

VILLAGE OF VILLA PARK CENTRAL BOULEVARD IMPROVEMENTS LOCATION MAP (NOT TO SCALE) CORTESI AVE. MYRTLE AVE. CENTRAL BLVD. Q:\VillaPark_IL\11283000 Astor-Myrtle Sewer Separation Preliminary Design\D.4 CAD\Sheets\North\1. Cover.dwg INDEX OF SHEETS 1 COVER 2 GENERAL NOTES 3 SUMMARY OF QUANTITIES 4 ALIGNMENT 5-9 DRAINAGE AND

More information

Checklist MISCELLANEOUS REQUIREMENTS G G G G G G G G

Checklist MISCELLANEOUS REQUIREMENTS G G G G G G G G Background The City of North Las Vegas strives to provide the development community with adequate information to ensure the successful completion of any project in the City. To aid in the submittal of

More information

Mailing Address: Fax number: City: State: Zip: Property Owner: City: State: Zip: City: State: Zip:

Mailing Address: Fax number: City: State: Zip:   Property Owner: City: State: Zip:   City: State: Zip: / Department of Community Development ARCHITECTURAL REVIEW APPLICATION 73-510 Fred Waring Drive Palm Desert California 92260 (760) 346-0611 Fax (760) 776-6417 Applicant: Telephone: Mailing Address: Fax

More information

PUBLICATION 213. Think Safety First

PUBLICATION 213. Think Safety First PUBLICATION 213 (67 PA CODE, CHAPTER 212) Think Safety First Pub 213 (02-08) Appendix Appendix A - Temporary/Portable

More information

Quality Control and Quality Assurance Guide

Quality Control and Quality Assurance Guide Quality Control and Quality Assurance Guide Bridge Division, Design Section April 2017 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants... 6

More information

Harris County Flood Control District. CAD Standards Manual

Harris County Flood Control District. CAD Standards Manual Harris County Flood Control District CAD Standards Manual September 2016 HCFCD CAD Standards Manual!"#$ Table of Contents 1.1 INTRODUCTION... 5 1.2 REFERENCES... 5 1.3 IMPLEMENTATION... 5 2. PLAN REQUIREMENTS

More information

CHAPTER 3 CIVIL/SITE DEVELOPMENT ENGINEERING

CHAPTER 3 CIVIL/SITE DEVELOPMENT ENGINEERING CHAPTER 3 CIVIL/SITE DEVELOPMENT ENGINEERING CHAPTER 3 CIVIL/SITE DEVELOPMENT ENGINEERING TABLE OF CONTENTS 3.1 GENERAL... 4 3.1.1 SCOPE OF WORK... 4 3.1.2 SPECIFIC REQUIREMENTS... 4 3.1.2.1 Site Evaluation...

More information

Hillside & Foothills Development Application

Hillside & Foothills Development Application Hillside & Foothills Development Application This box for office use only File #: Cross Referenced File(s): Fee: Zone(s): Are Pre-Application materials attached? Yes No This application is a request to

More information

Planning Permit Application LAND USE PRELIMINARY APPLICATION (LUP)

Planning Permit Application LAND USE PRELIMINARY APPLICATION (LUP) Planning Permit Application LAND USE PRELIMINARY APPLICATION (LUP) 415 W 6 th ST ~ Vancouver, WA 98660 PO Box 1995 ~ Vancouver, WA 98668 Phone (360) 487-7800 www.cityofvancouver.us Type Of Work Type I

More information

ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION

ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION 1. Scope 4. Underlayment 2. 1.1 This roofing application standard has been developed to provide a responsive

More information

Engineering Plan Submittal Requirements. Revised: October 2, Page 1 of 13

Engineering Plan Submittal Requirements. Revised: October 2, Page 1 of 13 Engineering Plan Submittal Requirements Revised: October 2, 2014 Page 1 of 13 Introduction: These Engineering Plan Submittal Requirements are intended to standardize City requirements for civil engineering

More information

ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION

ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION ROOFING APPLICATION STANDARD (RAS) No. 115 STANDARD PROCEDURES FOR ASPHALTIC SHINGLE INSTALLATION 1. Scope 4. Underlayment 2. 1.1 This roofing application standard has been developed to provide a responsive

More information

Charlton/Oxford Route 20 Reconstruction Project

Charlton/Oxford Route 20 Reconstruction Project Public Informational Meeting February 1, 2017 Oxford High School Charlton/Oxford Route 20 Reconstruction Project Project File No. 602659 2014 HDR, Inc., all rights reserved. Public Informational Meeting

More information

APPENDIX C: MAIN RIVER BRIDGE PLANS. The graphics in this appendix depict the Practical Alternatives.

APPENDIX C: MAIN RIVER BRIDGE PLANS. The graphics in this appendix depict the Practical Alternatives. APPENDIX C: MAIN RIVER BRIDGE PLANS The graphics in this appendix depict the Practical Alternatives. NO. DESCRIPTION BY 4:36:17 PM 10/3/2007 STA.10+843.000 \ PYLON 6.000 5.000 (TYP) PYLON ELEVATION 210.000

More information

Part 1 - Common Comments on Erosion and Sediment Control Plans (Walter Hamilton, SDID)

Part 1 - Common Comments on Erosion and Sediment Control Plans (Walter Hamilton, SDID) COMMON ERRORS Typical Site Review issues Part 1 - Common Comments on Erosion and Sediment Control Plans (Walter Hamilton, SDID) E&S Phase I Constructability (PFM 11-0109.3) Safety during construction and

More information

ARMOUR TOWNSHIP SITE PLAN APPLICATION REQUIREMENTS

ARMOUR TOWNSHIP SITE PLAN APPLICATION REQUIREMENTS SITE PLAN CONTROL ARMOUR TOWNSHIP SITE PLAN APPLICATION REQUIREMENTS Site Plan Control is a process involving municipal approval of the lay-out, design and appearance of certain new developments, as authorized

More information

adopted in Hong Kong

adopted in Hong Kong Prefabricated Construction Systems for Building and Civil works adopted in Hong Kong Presented by Raymond W M Wong Division of Building Science & Technology City University of Hong Kong The presentation

More information

Fundamentals III CHAPTER PROJECT EXERCISE

Fundamentals III CHAPTER PROJECT EXERCISE CHAPTER 4 Fundamentals III PROJECT EXERCISE This project exercise provides point-by-point instructions for setting up the drawing with layers and then creating the objects shown in Figure P4 1. FIGURE

More information

Mechanical Drawing. Unit 2 Study Guide for Chapters 6-10

Mechanical Drawing. Unit 2 Study Guide for Chapters 6-10 Mechanical Drawing Unit 2 Study Guide for Chapters 6-10 Chapter 6 Multiview Drawing Section 6.1 Understanding Orthographic Projection A. Technical Drawing: How can a technical drawing give more accurate

More information

Ohio Department of Transportation Office of Roadway Engineering January 18, 2013

Ohio Department of Transportation Office of Roadway Engineering January 18, 2013 Ohio Department of Transportation Office of Roadway Engineering January 18, 2013 To: Holders of the Traffic Standard Construction Drawings (SCDs) and Plan Insert Sheets (PISs) As of January 18, 2013, eighteen

More information

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20 Design Manual Chapter 5 - Roadway Design 5G - PCC Pavement Joints 5G-2 Types of Joints A. Jointing PCC pavement joints are necessary primarily to control the location of cracks that occur from natural

More information

NEW SINGLE FAMILY HOMES

NEW SINGLE FAMILY HOMES NEW SINGLE FAMILY HOMES Your submission must include the following to be accepted as a complete application: 1 copy of the deed and / or purchase and sales agreement if you have owned the property less

More information

TURNPIKE DESIGN HANDBOOK (TDH) PLANS PRODUCTION PART 3

TURNPIKE DESIGN HANDBOOK (TDH) PLANS PRODUCTION PART 3 TURNPIKE DESIGN HANDBOOK (TDH) PLANS PRODUCTION PART 3 FLORIDA S TURNPIKE ENTERPRISE PRODUCTION DESIGN DEPARTMENT OCOEE, FL January 2018 Introduction As part of the Turnpike s continuing quality enhancement

More information