Fault Locating at Pacific Gas and Electric Company

Size: px
Start display at page:

Download "Fault Locating at Pacific Gas and Electric Company"

Transcription

1 Fault Locating at Pacific Gas and Electric Company i-pcgrid 2015 Scott Hayes

2

3

4 Relay Targets were the earliest fault location devices.

5

6 Light Beam Oscillographs and later Digital Fault Recorders

7

8 Microprocessor Relays Microprocessor based protective relays were an off shoot of digital fault locator research. Since 1990 PG&E has actively used MP relays to provide fault locations. Improved customer reliability. Reduced patrol costs. 50 mile line. Foot patrol or $1000 per hour helicopter?

9 Fault Location Algorithms Takagi Method Improved Takagi Method Enhanced Improved Takagi Method Variation of Ohms Law. R = V/I

10 Typical relay calculated fault display Event: AG T Location: Frequency: 60.0 Targets: INST ZONE1 EN G 50 V1 Mem: / 58 Early efforts relied on dial up modems, sharing existing phone lines or in some cases installing terminal printers in substations for line personnel to access relay calculated fault locations.

11

12 Relay Calculated Fault Locations All modern relays can calculate fault locations and output the information to SCADA. Why would engineers need to get involved? Can fault locations be successfully done on distribution circuits?

13 Factors Affecting Fault Location Accuracy 1. 3 phase faults are relatively accurate on two terminal lines. 2. Ground faults are the most inaccurate due to several factors. 3. Load current and fault current mixed together decreases accuracy. 4. Untransposed lines decrease accuracy. 5. Tapped lines decreases accuracy both for three terminal transmission lines or tapped load or generation stations. 6. PG&E standard transformer connections for distribution banks make fault locations less accurate for ground faults than at almost all other utilities. 7. Mixed conductor size on a circuit decreases accuracy. 8. Double circuiting decreases accuracy. 9. Paralleled conductor decreases accuracy. 10.Series cap banks decrease accuracy. 11.Wood pole construction decreases accuracy by increasing fault ground fault resistance.

14 PG&E System Topology PG&E 115 kv and 60/70 kv Transmission Lines often have taps, multiple wire sizes and multiple sources. Our standard distribution transformers (115/12 kv or 60/12 kv) are connected:

15 PG&E Transmission Circuit Miles /70 kv 115 kv 230 kv 500 kv

16 Average Circuit Outage Rate Series /70 kv 115 kv 230 kv 500 kv

17 Number of Fault Location Provided

18 Fault Type and Voltage Distribution 2014 Faults by Voltage 500 kv, 3.1% 230 kv, 10.1% 60 kv, 45.3% 115 kv, 34.0% 500 kv 230 kv 115 kv 70 kv, 7.5% 70 kv 60 kv

19 Travelling Waves Travelling wave fault location(twfl) shows the most promise for improved accuracy but is not widely applied. PG&E had a travelling wave fault locator in the 1970 s. Required a comm tech, variable frequency generator and amplifier. Applied on 230 kv s Created our own TWFL system using GOES clocks and voltage inputs. Applied on 500 kv s - Applied several commercial TWFL equipment using current inputs on EHV system TWFL is now integrated into some line relays.

20 Conclusions Fault Locations Improve Service Reliability and Decrease Patrol Costs. Due to PG&E Transmission Topology, Engineer Calculated Fault Locations are Preferred. PG&E System Protection is Committed to Providing Fault Locations 24/7/365. Challenge: Maintaining Reliable Remote Relay Access with Changing NERC CIP Requirements.

Module 9. Fault Type Form 4.X RELIABILITY ACCOUNTABILITY

Module 9. Fault Type Form 4.X RELIABILITY ACCOUNTABILITY Module 9 Fault Type Form 4.X 1 M9 Fault Type The descriptor of the fault, if any, associated with each Automatic Outage of an Element. 1. No fault 2. Phase-to-phase fault (P-P) 3. Single phase-to-ground

More information

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY Module 10 Initiation Code 1 M10 Initiation Code This is not the Initiating cause code The Outage Initiation Codes describe where an Automatic Outage was initiated on the power system. Element-Initiated

More information

Distance Protection for Distribution Feeders. Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng.

Distance Protection for Distribution Feeders. Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng. Distance Protection for Distribution Feeders Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng. Why use distance protection for distribution feeders? Distance protection is mainly used for protecting

More information

Wires Down Improvement Program at Pacific Gas and Electric

Wires Down Improvement Program at Pacific Gas and Electric Wires Down Improvement Program at Pacific Gas and Electric Scott Hayes, Damon Thayer, Shawn Holder and Emili Scaief Pacific Gas and Electric Presented at the Western Protective Relay Conference 2015 Abstract

More information

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS S1. Standard Interconnection Methods with Typical Circuit Configuration for Single or Multiple Units Note: The protection requirements

More information

ELECTRIC TRANSMISSION (ET) Guideline G0104

ELECTRIC TRANSMISSION (ET) Guideline G0104 ELECTRIC TRANSMISSION (ET) ISSUING DEPARTMENT: ETM x ETEC ETPO ETTS EFFECTIVE DATE: 06-01-1997 DEPARTMENTS AFFECTED: ETM ETEC ETPO x ETTS REVIEW DATE: 01-01-1998 DEPARTMENT GROUP: ALL All All x All P E

More information

Traveling Wave Fault Location Experience at Bonneville Power Administration

Traveling Wave Fault Location Experience at Bonneville Power Administration Traveling Wave Fault Location Experience at Bonneville Power Administration Armando Guzmán, Veselin Skendzic, and Mangapathirao V. Mynam, Stephen Marx, Brian K. Johnson Abstract-- Faults in power transmission

More information

Smart Wires. Distributed Series Reactance for Grid Power Flow Control. IEEE PES Chapter Meeting - Jackson, MS August 8, 2012

Smart Wires. Distributed Series Reactance for Grid Power Flow Control. IEEE PES Chapter Meeting - Jackson, MS August 8, 2012 Smart Wires Distributed Series Reactance for Grid Power Flow Control IEEE PES Chapter Meeting - Jackson, MS August 8, 2012 Jerry Melcher Director Program Management Smart Wires Inc. 2 Agenda Technology

More information

Distribution Fault Location

Distribution Fault Location Distribution Fault Location 1. Introduction The objective of our project is to create an integrated fault locating system that accurate locates faults in real-time. The system will be available for users

More information

GridLiance Reliability Criteria

GridLiance Reliability Criteria GridLiance Reliability Criteria Planning Department March 1, 2018 FOREWORD The GridLiance system is planned, designed, constructed, and operated to assure continuity of service during system disturbances

More information

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event

More information

DOUBLE-ENDED FAULT LOCATORS

DOUBLE-ENDED FAULT LOCATORS The InterNational Electrical Testing Association Journal FEATURE END-TO-END TESTING OF DOUBLE-ENDED FAULT LOCATORS BY STEVE TURNER, Beckwith Electric Company, Inc.. www.netaworld.org FOR HIGH VOLTAGE,

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

Implementation of Automatic Under Voltage Load Shedding Program in Entergy System

Implementation of Automatic Under Voltage Load Shedding Program in Entergy System Implementation of Automatic Under Voltage Load Shedding Program in Entergy System Sharma Kolluri, IEEE Fellow Manager, Transmission Planning Entergy Services, Inc. Presentation at i-pcgrid Workshop San

More information

FAULT LOCATING USING VOLTAGE AND CURRENT MEASUREMENTS

FAULT LOCATING USING VOLTAGE AND CURRENT MEASUREMENTS The BEST Group THE BUFFALO ENERGY SCIENCE AND TECHNOLOGY GROUP -Winter Lecture Series FAULT LOCATING USING VOLTAGE AND CURRENT MEASUREMENTS Presented by: Syed Khundmir T Department of Electrical Engineering

More information

Locating Faults by the Traveling Waves They Launch

Locating Faults by the Traveling Waves They Launch Locating Faults by the Traveling Waves They Launch Edmund O. Schweitzer, III, Armando Guzmán, Venkat Mynam, Veselin Skendzic, and Bogdan Kasztenny Schweitzer Engineering Laboratories, Inc. Stephen Marx

More information

Transmission Availability Data System Definitions

Transmission Availability Data System Definitions Table of Contents Transmission Availability Data System Definitions February 1, 2018 1 of 31 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents

More information

Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan

Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan Mark Hackney October 5-8, 2009 Amman, Jordan Energy Control Center Layout 2 Energy Control

More information

Distance Relay Response to Transformer Energization: Problems and Solutions

Distance Relay Response to Transformer Energization: Problems and Solutions 1 Distance Relay Response to Transformer Energization: Problems and Solutions Joe Mooney, P.E. and Satish Samineni, Schweitzer Engineering Laboratories Abstract Modern distance relays use various filtering

More information

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length

More information

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch.

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch. Training Title POWER TRANSFORMERS Training Duration 5 days Training Venue and Dates Power transformers 5 20-24 May $3,300 Abu Dhabi In any of the 5 star hotel. The exact venue will be informed soon. Training

More information

Increased Reliability of EHV Systems through Station Switchable Spare Transformer and Shunt Reactor Design and Operation

Increased Reliability of EHV Systems through Station Switchable Spare Transformer and Shunt Reactor Design and Operation 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2015 Grid of the Future Symposium Increased Reliability of EHV Systems through Station Switchable Spare Transformer and

More information

ANALYSIS OF A FLASHOVER OPERATION ON TWO 138KV TRANSMISSION LINES

ANALYSIS OF A FLASHOVER OPERATION ON TWO 138KV TRANSMISSION LINES ANALYSIS OF A FLASHOVER OPERATION ON TWO 138KV TRANSMISSION LINES Authors: Joe Perez, P.E.: SynchroGrid, College Station, Texas Hung Ming Chou, SynchroGrid, College Station, Texas Mike McMillan, Bryan

More information

Breaker Pole Scatter and Its Effect on Quadrilateral Ground Distance Protection

Breaker Pole Scatter and Its Effect on Quadrilateral Ground Distance Protection Breaker Pole Scatter and Its Effect on Quadrilateral Ground Distance Protection James Ryan Florida Power & Light Company Arun Shrestha and Thanh-Xuan Nguyen Schweitzer Engineering Laboratories, Inc. 25

More information

Our Cyber Security History and Future

Our Cyber Security History and Future Our Cyber Security History and Future Trustworthy Cyber Infrastructure for the Power Grid April 3, 2015 Edmund O. Schweitzer III, Ph.D. President, Schweitzer Engineering Laboratories, Inc. Copyright SEL

More information

Summary of Relaying Reviews Reporting

Summary of Relaying Reviews Reporting Revised Attachment B (Agenda Item 6) Summary of Relaying Reviews -- 12-31-04 Reporting This form shall be used without modification to provide a summary of relaying reviews performed by each Transmisission

More information

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements User s Guide General Most faults in power systems can be detected by applying

More information

GPS Timing In Substations: Past, Present, & Future

GPS Timing In Substations: Past, Present, & Future GPS Timing In Substations: Past, Present, & Future NASPI Working Group March 23, 2017 Patrick Hawks Robert Orndorff Kyle Thomas Dominion Virginia Power Dr. Yilu Liu Dao Zhou University of Tennessee Current

More information

Application of DFA Technology for Improved Reliability and Operations

Application of DFA Technology for Improved Reliability and Operations Application of DFA Technology for Improved Reliability and Operations IEEE/IAS Rural Electric Power Conference Columbus, Ohio, 24 April 2017 Robert A. Peterson, P.E., Director Control Center and Emergency

More information

Phasor Measurements for Blackout Prevention

Phasor Measurements for Blackout Prevention Phasor Measurements for Blackout Prevention Anjan Bose Washington State University Pullman, WA, USA i-pcgrid 2013 San Francisco, CA March 26-28, 2013 Monitoring the Power Grid (SCADA) Visualization Tables

More information

Data Isolation Cards. 2-Wire HDSL/56KBS Isolation Card P Wire HDSL/56KBS Isolation Card P30050

Data Isolation Cards. 2-Wire HDSL/56KBS Isolation Card P Wire HDSL/56KBS Isolation Card P30050 Data Isolation Cards 2-Wire HDSL/56KBS Isolation Card P30076 4-Wire HDSL/56KBS Isolation Card P30050 Printed in USA 12/11 T0331 Rev. A Table of Contents Page 1.0 SCOPE 2 2.0 PRODUCT OVERVIEW 2 2.1 System

More information

SynchroPhasor use at OG&E. Austin D. White P.E. Steven E. Chisholm Oklahoma Gas & Electric

SynchroPhasor use at OG&E. Austin D. White P.E. Steven E. Chisholm Oklahoma Gas & Electric SynchroPhasor use at OG&E Austin D. White P.E. Steven E. Chisholm Oklahoma Gas & Electric Outline Hardware/Software Overview Current Deployment Status Use at OG&E Problems Solved & Interesting Findings

More information

Synchrophasors for Validation of Distance Relay Settings: Real Time Digital Simulation and Field Results

Synchrophasors for Validation of Distance Relay Settings: Real Time Digital Simulation and Field Results 1 Synchrophasors for Validation of Distance s: Real Time Digital Simulation and Field Results Brian K. Johnson, Sal Jadid Abstract This paper proposes a method to measure transmission line parameters for

More information

RELAY LOADABILITY CHALLENGES EXPERIENCED IN LONG LINES. Authors: Seunghwa Lee P.E., SynchroGrid, College Station, Texas 77845

RELAY LOADABILITY CHALLENGES EXPERIENCED IN LONG LINES. Authors: Seunghwa Lee P.E., SynchroGrid, College Station, Texas 77845 RELAY LOADABILITY CHALLENGES EXPERIENCED IN LONG LINES Authors: Seunghwa Lee P.E., SynchroGrid, College Station, Texas 77845 Joe Perez P.E., SynchroGrid, College Station, Texas 77802 Presented before the

More information

TADS Data Reporting Training TADS Data Reporting Training November, 2017

TADS Data Reporting Training TADS Data Reporting Training November, 2017 TADS Data Reporting Training 2017 TADS Data Reporting Training November, 2017 Agenda Day 1 Day 2 What is TADS TADS Mechanics Accessing the portal Checklist Inventory Outage and Event report Lunch Coding

More information

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T-18

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T-18 BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T-18 LIVE LINE PERMITS, ASSURANCE OF NO RECLOSE PERMITS AND CAUTION TAGS Supersedes OO 1T-18 issued 13 October 2010 Review Year: 2019 Original signed by:

More information

Single Earthed Neutral and Multi Earthed Neutral. Single Earthed Neutral and Multi Earthed Neutral: Multi Grounded Neutral System (MEN):

Single Earthed Neutral and Multi Earthed Neutral. Single Earthed Neutral and Multi Earthed Neutral: Multi Grounded Neutral System (MEN): Single Earthed Neutral and Multi Earthed Neutral. SEPTEMBER 6, 2011 5 COMMENTS Single Earthed Neutral and Multi Earthed Neutral: In Distribution System Three Phase load is unbalance and non linear so The

More information

Event Analysis Tutorial

Event Analysis Tutorial 1 Event Analysis Tutorial Part 1: Problem Statements David Costello, Schweitzer Engineering Laboratories, Inc. Abstract Event reports have been an invaluable feature in microprocessor-based relays since

More information

A New Use for Fault Indicators SEL Revolutionizes Distribution System Protection. Steve T. Watt, Shankar V. Achanta, and Peter Selejan

A New Use for Fault Indicators SEL Revolutionizes Distribution System Protection. Steve T. Watt, Shankar V. Achanta, and Peter Selejan A New Use for Fault Indicators SEL Revolutionizes Distribution System Protection Steve T. Watt, Shankar V. Achanta, and Peter Selejan 2017 by Schweitzer Engineering Laboratories, Inc. All rights reserved.

More information

Transmission Availability Data Systems Frequently Asked Questions

Transmission Availability Data Systems Frequently Asked Questions Transmission Availability Data Systems Frequently Asked Questions March 2016 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary... iv Chapter 1 TADS Inventory Related Questions...1

More information

Advanced Fault Analysis System (or AFAS) for Distribution Power Systems

Advanced Fault Analysis System (or AFAS) for Distribution Power Systems Advanced Fault Analysis System (or AFAS) for Distribution Power Systems Laurentiu Nastac 1, Paul Wang 1, Om Nayak 2, Raluca Lascu 3, Thomas Walker 4, Douglas Fitchett 4, and Soorya Kuloor 5 1 Concurrent

More information

System Ratings, Limits and Real-Time Monitoring. Presented to: Operating Committee April 21, 2016

System Ratings, Limits and Real-Time Monitoring. Presented to: Operating Committee April 21, 2016 System Ratings, Limits and Real-Time Monitoring Presented to: Operating Committee April 21, 2016 Thermal Facility Ratings In New England Summer ratings (April 1 to October 31) Winter ratings (November

More information

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 % BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and

More information

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination GSU Phase Overcurrent (51T), GSU Ground Overcurrent (51TG), and Breaker Failure (50BF) Protection NERC Protection Coordination Webinar Series

More information

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines Central Hudson Gas & Electric Corporation Transmission Planning Guidelines Version 4.0 March 16, 2016 Version 3.0 March 16, 2009 Version 2.0 August 01, 1988 Version 1.0 June 26, 1967 Table of Contents

More information

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies Application for A Sub-harmonic Protection Relay ERLPhase Power Technologies 1 Outline Introduction System Event at Xcel Energy Event Analysis Microprocessor based relay hardware architecture Sub harmonic

More information

Premier Event Sponsor 4RF Gold Sponsor ECI The Elastic Network

Premier Event Sponsor 4RF Gold Sponsor ECI The Elastic Network REGION 10 2018 TECHNICAL CONFERENCE October 11 & 12, 2018 Courtyard Sacramento Cal Expo Sacramento, CA Premier Event Sponsor 4RF Gold Sponsor ECI The Elastic Network Thursday, October 11, 2018 7:00AM 5:00PM

More information

Digital Line Protection System

Digital Line Protection System Digital Line Protection System! Microprocessor Based Protection, Control and Monitoring System! Waveform Sampling! Proven Protection! Economical! Ease of Retrofit 1 DLP-D D Enhancements ASCII SUBSET Three

More information

Phase Angle Monitoring:

Phase Angle Monitoring: Phase Angle Monitoring: Industry Experience Following the 2011 Pacific Southwest Outage Recommendation 27 Ryan D. Quint, PhD, PE NERC SMS Coordinator NASPI Work Group Meeting October 2016 Background Purpose:

More information

Automated Phase Identification System for Power Distribution Systems

Automated Phase Identification System for Power Distribution Systems Automated Phase Identification System for Power Distribution Systems A Revised Final Report Submitted to Dr. Miu and the Senior Design Project Committee of the Electrical and Computer Engineering Department

More information

QUESTIONNAIRE ON FAULT LOCATION SYSTEMS

QUESTIONNAIRE ON FAULT LOCATION SYSTEMS For WG B5.52 Analysis and comparison of fault location systems in substation automation systems The objective of this questionnaire is to obtain information of nowadays fault location systems used by the

More information

Power System Fundamentals

Power System Fundamentals Power System Fundamentals Relay Applications PJM State & Member Training Dept. Objectives At the end of this presentation the Student will be able to: Describe the purpose of protective relays Identify

More information

IMPLEMENTATION OF ADVANCED DISTRIBUTION AUTOMATION IN U.S.A. UTILITIES

IMPLEMENTATION OF ADVANCED DISTRIBUTION AUTOMATION IN U.S.A. UTILITIES IMPLEMENTATION OF ADVANCED DISTRIBUTION AUTOMATION IN U.S.A. UTILITIES (Summary) N S Markushevich and A P Berman, C J Jensen, J C Clemmer Utility Consulting International, JEA, OG&E Electric Services,

More information

CP CU1. Coupling unit for line and ground testing

CP CU1. Coupling unit for line and ground testing CP CU1 Coupling unit for line and ground testing Line and ground test system CPC 100 The CPC 100 is a multifunctional test set for primary assets. When combined with the CP CU1 it covers the following

More information

Summary Paper for C IEEE Guide for Application of Digital Line Current Differential Relays Using Digital Communication

Summary Paper for C IEEE Guide for Application of Digital Line Current Differential Relays Using Digital Communication Summary Paper for C37.243 IEEE Guide for Application of Digital Line Current Differential Relays Using Digital Communication Participants At the time this draft was completed, the D32 Working Group had

More information

THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF RUSSEL D. JOHNSON

THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF RUSSEL D. JOHNSON THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF RUSSEL D. JOHNSON PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE d/b/a EVERSOURCE ENERGY RELIABILITY ENHANCEMENT

More information

Power System Protection. Dr. Lionel R. Orama Exclusa, PE Week 9

Power System Protection. Dr. Lionel R. Orama Exclusa, PE Week 9 Power System Protection Dr. Lionel R. Orama Exclusa, PE Week 9 Pilot Relaying Communication channels & signals Pilot wire schemes Opposed voltage Circulating current Blocking schemes Directional comparison

More information

Commercial Deployments of Line Current Differential Protection (LCDP) Using Broadband Power Line Carrier (B-PLC) Technology

Commercial Deployments of Line Current Differential Protection (LCDP) Using Broadband Power Line Carrier (B-PLC) Technology Commercial Deployments of Line Current Differential Protection (LCDP) Using Broadband Power Line Carrier (B-PLC) Technology Nachum Sadan - Amperion Inc. Abstract Line current differential protection (LCDP)

More information

SWITCHGEAR PROTECTION AND POWER SYSTEMS BY SUNIL S. RAO DOWNLOAD EBOOK : SWITCHGEAR PROTECTION AND POWER SYSTEMS BY SUNIL S.

SWITCHGEAR PROTECTION AND POWER SYSTEMS BY SUNIL S. RAO DOWNLOAD EBOOK : SWITCHGEAR PROTECTION AND POWER SYSTEMS BY SUNIL S. SWITCHGEAR PROTECTION AND POWER SYSTEMS BY SUNIL S. RAO DOWNLOAD EBOOK : SWITCHGEAR PROTECTION AND POWER SYSTEMS BY Click link bellow and free register to download ebook: SWITCHGEAR PROTECTION AND POWER

More information

Fault Localization using Wavelet Transforms in 132kV Transmission Lines

Fault Localization using Wavelet Transforms in 132kV Transmission Lines ENGINEER - Vo). XXXXII, No. 04, pp. [95-104], 2009 The Institution of Engineers, Sri Lanka Fault Localization using Wavelet Transforms in 132kV Transmission Lines J.V.U.P. Jayatunga, P.S.N. De Silva and

More information

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System WHO SHOULD FILE THIS SUBMITTAL: Anyone in the final stages of interconnecting a Generation System with Nodak Electric Cooperative, Inc. This submittal shall be completed and provided to Nodak Electric

More information

Estimation of Fault Resistance from Fault Recording Data. Daniel Wong & Michael Tong 2014-November-5

Estimation of Fault Resistance from Fault Recording Data. Daniel Wong & Michael Tong 2014-November-5 Estimation of Fault Resistance from Fault Recording Data Daniel Wong & Michael Tong 2014-November-5 Agenda Project Background & Introduction Fault Resistance & Effect Estimation Algorithm Estimation Results

More information

Use of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation Data Files

Use of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation Data Files 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Use of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation

More information

Končar TMS - Bushing monitoring

Končar TMS - Bushing monitoring Končar TMS - Bushing monitoring Many recent studies have shown that bushing failure is one of the most common causes of transformer failure. Thus need for bushing diagnostic and monitoring system has risen.

More information

Distance Protection: Why Have We Started With a Circle, Does It Matter, and What Else Is Out There? What Is a Distance Protection Element?

Distance Protection: Why Have We Started With a Circle, Does It Matter, and What Else Is Out There? What Is a Distance Protection Element? Distance Protection: Why Have We Started With a Circle, Does It Matter, and What Else Is Out There? Edmund O. Schweitzer, III and Bogdan Kasztenny Schweitzer Engineering Laboratories Copyright SEL 2017

More information

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006 October 25, 2006 Document name Category MODEL POWER SYSTEM TESTING GUIDE ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy ( ) Guideline ( x ) Report or other ( ) Charter Document date

More information

Module 11a. Initiating Cause Code Form 4.X RELIABILITY ACCOUNTABILITY

Module 11a. Initiating Cause Code Form 4.X RELIABILITY ACCOUNTABILITY Module 11a Initiating Cause Code Form 4.X 1 M11 Initiating and Sustained Cause Codes An Initiating Cause Code that describes the initiating cause of the outage. A Sustained Cause Code that describes the

More information

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line Vince Leung March 27, 2017 Reviewed by Johnny Nguyen Table of Contents Background 2 Objective 3 Base Case Assumptions

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS Juan Manuel Gers, PhD Example - Single Line Example 1 - Data Calculate the following: 1. The three phase short circuit levels on busbars

More information

Line Protection Roy Moxley Siemens USA

Line Protection Roy Moxley Siemens USA Line Protection Roy Moxley Siemens USA Unrestricted Siemens AG 2017 siemens.com/digitalgrid What is a Railroad s Biggest Asset? Rolling Stock Share-holders Relationships Shipping Contracts Employees (Engineers)

More information

Substation Testing and Commissioning: Power Transformer Through Fault Test

Substation Testing and Commissioning: Power Transformer Through Fault Test 1 Substation Testing and Commissioning: Power Transformer Through Fault Test M. Talebi, Member, IEEE, Power Grid Engineering Y. Unludag Electric Power System Abstract This paper reviews the advantage of

More information

Industrial and Commercial Power Systems Topic 7 EARTHING

Industrial and Commercial Power Systems Topic 7 EARTHING The University of New South Wales School of Electrical Engineering and Telecommunications Industrial and Commercial Power Systems Topic 7 EARTHING 1 INTRODUCTION Advantages of earthing (grounding): Limitation

More information

No. SSIEC-SEW SHINSUNG. Solid Insulation Eco Load Break Switch (SILO) SILO SERIES 15kV, 27kV 400A, 630A

No. SSIEC-SEW SHINSUNG. Solid Insulation Eco Load Break Switch (SILO) SILO SERIES 15kV, 27kV 400A, 630A SHINSUNG Solid Insulation Eco Load Break Switch (SILO) SILO SERIES 15kV, 27kV 400A, 630A Enhanced Self Healing System General SILO is 3 phase, solid insulated load break switch (LBS) and vacuum interruption

More information

Instrument Transformer Services (ITS) Voltage / Potential Transformer Reclassification

Instrument Transformer Services (ITS) Voltage / Potential Transformer Reclassification Instrument Transformer Services (ITS) Voltage / Potential Transformer Reclassification Schneider Electric Instrument Transformer Services VT/PT Reclassification 1 CONTENTS PURPOSE OF THIS DOCUMENT 3 EXECUTIVE

More information

TEAMS Competition 2014

TEAMS Competition 2014 TEAMS Competition 2014 Engineering Digital Relays for Smart Electrical Grids Introduction W hen people talk about the national power grid, they are actually describing three power grids that are connected

More information

The Advantages and Application of Three Winding Transformers

The Advantages and Application of Three Winding Transformers The Advantages and Application of Three Winding Transformers MSc, CEng, FIEE, FIMechE, FIPENZ Principal, Sinclair Knight Merz Abstract Although seldom used in Australia and New Zealand, three winding transformers

More information

Using smart grid sensors and advanced software applications as an asset management tool at Hydro Ottawa

Using smart grid sensors and advanced software applications as an asset management tool at Hydro Ottawa 24th International Conference & Exhibition on Electricity Distribution (CIRED) 12-15 June 2017 Session 1: Network components Using smart grid sensors and advanced software applications as an asset management

More information

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS Ljubomir KOJOVIC Cooper Power Systems - U.S.A. Lkojovic@cooperpower.com INTRODUCTION In steel facilities that use Electric Arc Furnaces (EAFs) to manufacture

More information

Overvoltage Protection

Overvoltage Protection Overvoltage Protection S T U D E N T M A N U A L March 31, 2005 2 STUDENT TRAINING MANUAL Prerequisites: Single-Phase Transformer Load Checks Objectives: From memory, you will be able to describe the electrical

More information

Phase Rolling and the Impacts on Protection

Phase Rolling and the Impacts on Protection Phase Rolling and the Impacts on Protection Denglin (Dennis) Tang Burns & McDonnell 1700 West Loop South, Houston, TX 77027 Office: (713) 622-0227 Fax: (713) 622-0224 dtang@burnsmcd.com Abstract: During

More information

AC Transmission Line Model Parameter Validation

AC Transmission Line Model Parameter Validation AC Transmission Line Model Parameter Validation A report to the Line Protection Subcommittee of the Power System Relay Committee of the IEEE Power & Energy Society Prepared by working group D6 Sept 2014

More information

Protection Challenges for Transmission Lines with Long Taps

Protection Challenges for Transmission Lines with Long Taps Protection Challenges for Transmission Lines with Long Taps Jenny Patten, Majida Malki, Quanta Technology, Matt Jones, American Transmission Co. Abstract Tapped transmission lines are quite common as they

More information

Self Healing Single Phase Looped Network AUTOMATED RECONFIGURATION FOR POWER OUTAGE MANAGEMENT. Team Members

Self Healing Single Phase Looped Network AUTOMATED RECONFIGURATION FOR POWER OUTAGE MANAGEMENT. Team Members Self Healing Single Phase Looped Network AUTOMATED RECONFIGURATION FOR POWER OUTAGE MANAGEMENT Team Members Lamine Bassene Damel Goddard Oluwabunkunmi Olusanya Chibuzo Ononiwu Luan Watson TABLE OF CONTENTS

More information

Partial Discharge, Survey or Monitor?

Partial Discharge, Survey or Monitor? July 2014 Partial Discharge, Survey or Monitor? 24-7 Partial Discharge monitoring is the ultimate tool for finding insulation weaknesses before they fail. Introduction It s well established that Partial

More information

GIS Data Assessment for DMS and Smart Grid Implementation

GIS Data Assessment for DMS and Smart Grid Implementation GIS Data Assessment for DMS and Smart Grid Implementation John Dirkman, P.E. Telvent Esri EGUG 11 October 2011 11/3/2011 1 Agenda 1. Determining your Distribution Management System and Smart Grid Drivers

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Hamdy Faramawy Senior Application Specialist ABB Sweden

Hamdy Faramawy Senior Application Specialist ABB Sweden Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy

More information

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE The following is PG&E's procedure for pre-energization inspections. For PG&E to provide the Load

More information

AEP s 765kV Transmission Line Model Validation for Short Circuit and System Studies. T. YANG, Q. QIU, Z. CAMPBELL American Electric Power USA

AEP s 765kV Transmission Line Model Validation for Short Circuit and System Studies. T. YANG, Q. QIU, Z. CAMPBELL American Electric Power USA 1, rue d Artois, F-75008 PARI CIGRE U National Committee http : //www.cigre.org 015 Grid of the Future ymposium AEP s 765kV Transmission Line Model Validation for hort Circuit and ystem tudies T. YANG,

More information

S&C Vista Underground Distribution Switchgear Outdoor Distribution

S&C Vista Underground Distribution Switchgear Outdoor Distribution The offers superior overcurrent coordination. Among the features that provide excellent overcurrent coordination are unique coordinating speed tap and main time-current characteristic curves, which provide

More information

Transmission System Phase Backup Protection

Transmission System Phase Backup Protection Reliability Guideline Transmission System Phase Backup Protection NERC System Protection and Control Subcommittee Draft for Planning Committee Approval June 2011 Table of Contents 1. Introduction and Need

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS Juan Manuel Gers, PhD Protection coordination principles Relay coordination is the process of selecting settings that will assure that the relays

More information

Wireless InterOp Architecture and Design. Robert Burchard

Wireless InterOp Architecture and Design. Robert Burchard Wireless InterOp Architecture and Design Robert Burchard Agenda Smart Grid Concepts Use Cases Architectural & Design Overview & Considerations Network Overview (BH, WWAN, WLAN, WHAN) Coverage and Capacity

More information

Protection & Control Journal

Protection & Control Journal Protection & Control Journal August 2007 Redundancy Considerations in MV Distribution Systems Application of Phasor Measurement Units for Disturbance Recording Status on the First IEC61850-Based Protection

More information

Utility Interconnection and System Protection

Utility Interconnection and System Protection Utility Interconnection and System Protection Alex Steselboim President, Advanced Power Technologies, Inc. Utility paralleling vs. isolated operation. Isochronous kw load sharing Reactive power (VAR) sharing

More information

PG&E 500 kv Series-Compensated Transmission Line Relay Replacement: Design Requirements and RTDS Testing

PG&E 500 kv Series-Compensated Transmission Line Relay Replacement: Design Requirements and RTDS Testing PG&E 500 kv Series-Compensated Transmission Line Relay Replacement: Design Requirements and RTDS Testing Davis Erwin, Monica Anderson, and Rafael Pineda Pacific Gas and Electric Company Demetrios A. Tziouvaras

More information

Dynamic Model Of 400 Kv Line With Distance Relay. Director Research, The MRPC Company, Hyderabad, India 2

Dynamic Model Of 400 Kv Line With Distance Relay. Director Research, The MRPC Company, Hyderabad, India 2 Dynamic Model Of 400 Kv Line With Distance Relay Ramleela Khare 1, Dr Filipe Rodrigues E Melo 2 1 Director Research, The MRPC Company, Hyderabad, India 2 Assoc. Professor Commerce, St. Xavier s College

More information

TRANSMISSION AND SUBSTATIONS RESEARCH AREA

TRANSMISSION AND SUBSTATIONS RESEARCH AREA TRANSMISSION AND SUBSTATIONS RESEARCH AREA VISION The core vision of the Transmission and Substations Area is: Extract the Maximum from Existing Assets and Construct High-Performance New Assets The Life

More information

Education & Training

Education & Training Distribution System Operator Certificate This program provides you with a proficient working knowledge in modern electric power distribution systems. These four classes are designed to walk students through

More information

Designing For a Critical Load using a Spot Network

Designing For a Critical Load using a Spot Network This is a photographic template your photograph should fit precisely within this rectangle. Designing For a Critical Load using a Spot Network Tony Oruga, P.E. Product and Sales Manager Network Protectors

More information