Designing For a Critical Load using a Spot Network
|
|
- Clifton Snow
- 6 years ago
- Views:
Transcription
1 This is a photographic template your photograph should fit precisely within this rectangle. Designing For a Critical Load using a Spot Network Tony Oruga, P.E. Product and Sales Manager Network Protectors 2007 Eaton Corporation. All rights reserved Eaton Corporation. All rights reserved.
2 Network Systems Who? When? What? How? Why? Where? 2 2
3 Network Systems Who knows what distribution network systems are? When? What? How? Why? Where? 3 3
4 Network Systems Who? When were they first used? What? How? 1882 DC networks Why? 1907 Memphis; AC network Where? 1921 Seattle 1922 NY; first system 4 4
5 When were they first used? 1922 Westinghouse Electric developed first Network System Union Electric in New York, now called Consolidated Edison. Con Ed - 25,000 Network Protectors on their system. 85% of Con Ed load supplied by Networks. Today Commercial areas of most major cities over 200,000 have network systems. Secondary Network voltages are 216, 480, and 600VAC 5 5
6 When were they first used? 6 6
7 Network Systems Who? When? What is a Network System? How? Why? Where? 7 7
8 What is a Network System? Alternative to traditional power distribution topologies Radial Primary Selective Secondary Selective Network System Spot Grid That s the way we have always done it 8 8
9 What is a Network System? Utility Substation Spot Network System Utility Substation Feeder Breaker Network Transformers Network Protector Network Breaker Fuse Cable Limiter Load Collector Bus *2 or more parallel feeders to a load supply allow uninterrupted power during contingency 9 9
10 What is a Network System? Grid Network System 10 10
11 What is a Network System? Grid Network System 3 Feeder Distributed
12 What is a Network System? Highest level of reliability for power distribution systems Most desirable for critical loads Two main topologies: Spot One dedicated customer Grid Several customers; i.e. City block 12 12
13 What is a Network System? Substation and Primary Feeders Nominal Voltages 4.16 kv to 34.5 kv Dedicated primary feeders- supply only network transformers 13 13
14 Network Systems Who? When? What? How does it work? Why? Where? 14 14
15 How does it work? Spot Network Fault on Primary side which causes breaker to open Spot Network - Fault on Primary Feeder Network Transformer Network protector Network breaker fuse Cable Limiters Collector Bus 15 15
16 How does it work? Spot Network Station Breaker opens which causes NP to open Spot Network - Station Breaker 1 is Opened Network Relay Trips Upon the Flow of Reverse Magnetizing Current of its Associated Network Transformer. Collector Bus 16 16
17 How does it work? Spot Network Station Breaker opens which causes NP to open Spot Network Continues operation at N-1 contingency Customer never experiences interruption of service Collector Bus 17 17
18 MPCV Relay Family Robust design for extreme temperatures (-40C to 125C).25 Thick Solid Brass Case Submersible Communication activated Advanced Safety Algorithms Only sequence based relay Replaces any Electro-Mechanical Network relay, solid state, or digital relays regardless of vintage or protector type. Specification preferred for foreign and domestic utilities 18 18
19 LV Secondary Network System Philosophy Underground Systems Reference Book, EEI T&D Committee (1957) Page 5-2: Operation is based on 3 principles: Westinghouse Electric Reference Book: Vol 3 Distribution Systems (1965) 1. The self-clearing of faults on the secondary grid either by burning-off faults or clearing by use of limiters. 2. Automatic opening of network protectors when a feeder breaker is opened or in event of a fault on a primary feeder cable or in a network transformer. 3. Automatic closing of network protectors to connect the network transformers to the secondary grid when the primary feeder is energized. 19 (Page 167) 19
20 Sample SLD 2-Unit Spot Network 20 20
21 Sample Network Floor Plan (Switchgear) 21 21
22 Sample SLD 3-Unit Spot Network 22 22
23 Sample Network Floor Plan (Switchgear) 23 23
24 Sample Profile Network view (submersible) Collector Bus Sudden Pressure Relay Visual Disconnect Visual Status Indicator Network Protector Network Transformer Source Bus Bulkhead *Throat or Wall mount Primary Disconnect Switch 24 24
25 Vault Vision Vault protection Family of sensors that seamlessly integrate into communication platform Multi-platform communication Heat detection systems 25 25
26 Today s Product Suite for Underground 26 26
27 How does it work? Spot Network Submersible model CM-52 shown Switchgear Line-Up 27 27
28 Network Systems Who? When? What? How? Why use a Network System? Where? 28 28
29 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage 29 29
30 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage Less transformer capacity is required 30 30
31 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage Less transformer capacity is required Lower peak loads on transformers - diversity of demand 31 31
32 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage Less transformer capacity is required Lower peak loads on transformers - diversity of demand Transformer losses are typically less 32 32
33 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage Less transformer capacity is required Lower peak loads on transformers - diversity of demand Transformer losses are typically less Protectors assure positive power into load 33 33
34 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage Less transformer capacity is required Lower peak loads on transformers - diversity of demand Transformer losses are typically less Protectors assure positive power into load System provides improved voltage regulation 34 34
35 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage Less transformer capacity is required Lower peak loads on transformers - diversity of demand Transformer losses are typically less Protectors assure positive power into load System provides improved voltage regulation Less voltage sag on Motor starting (up to 70% less than a radial system) 35 35
36 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage Less transformer capacity is required Lower peak loads on transformers - diversity of demand Transformer losses are typically less Protectors assure positive power into load System provides improved voltage regulation Less voltage sag on Motor starting (up to 70% less than a radial system) Automatic open and close operation 36 36
37 Advantages of Network System Design Outage on primary feeder does NOT cause customer outage Less transformer capacity is required Lower peak loads on transformers - diversity of demand Transformer losses are typically less Protectors assure positive power into load System provides improved voltage regulation Less voltage sag on Motor starting (up to 70% less than a radial system) Automatic open and close operation LV Network Customer outage rate Approaching zero Radial systems once every year. BEST SOLUTION FOR CRITICAL LOAD APPLICATIONS! 37 37
38 Number of Outages Reliability Design Considerations Spot Network Primary Selective Primary Loop Double-Ended Radial Investment Cost Radial Primary Selective Primary Loop Double-Ended Spot Network Costs associate with outages 38 38
39 Network Systems Who? When? What? How? Why? Where are they used today? 39 39
40 Where are they used today? 40 40
41 Where are they used today? *Selected example utilities 41 41
42 Where are they used today? Network Systems are also widely used in other parts of the world such as: Canada Asia and Asia Pacific Philippines Thailand South Korea Australia Latin America Central and South America Mexico Columbia Brazil Venezuela 42 42
43 Example Installations Electrical Room Installation Subsurface Vault Installation 43 43
44 Example Installations Platform installation Roof installation 44 44
45 Example Installations Detroit Edison Design 45 45
46 Example Installations Subsurface Vault Installation 46 46
47 Example Installations 3 Unit 480Y/277 V Spot Network- Seattle, WA- Building Vault 47 47
48 480V Spot Network Example (1-4 Feeders at kv) Load Estimation Study Maximum Short Term Peak Load: 1250 kva Continuous Average Load: 800 kva Minimum Baseline Load: 275 kva All above loading conditions at 0.87 Lagging PF 3 Standardized 480V Transformer Options 1000 kva (1200A) 1500 kva (1800A) 2500 kva (3000A) Network Unit Options 2-Unit through 6-Unit Spot Networks 48 48
49 Optimal Transformer / #-Unit Combination (N-1 Contingency)? 49 49
50 Transformer Calculations 50 50
51 Network Protector Selection 51 51
52 Network Protector Selection Rationale Choose 1000kVA 5% Impedance Transformers (125% Maximum Short Term = 1504A) 1600A NWP Rating Provides 133% Transformer Nameplate Overload Margin, a good fit. 1875A NWP 156% Rating also utilizes 1600:5 CTs but unnecessary higher amperage fuses. Select 1600A CM52 NWP for a 2-Unit 1000kVA Spot Network. Notice that a 2-Unit 1500kVA Spot would yield: Higher Transformer $, Higher NWP $ (4-Pole CM52), for undesired excess load capacity
53 IEEE Standards & References IEEE C Secondary Network Transformers Subway and Vault Type (Liquid Immersed) Requirements IEEE C Standard Requirement for Secondary Network Protectors EPRI Bronze Book Underground Distribution Systems Reference Book 53 53
54 Additional Network System Training Electrical Networks Systems Conference (ENSC) Annual Conference Guest Speakers and Vendor Trade Show 16 th Annual ENSC Tempe, AZ March 30 th to April 2 nd 2015 Troubleshooting Training (3-day)- covers all brands of NWPs Factory or Onsite Classes are available Greenwood Seminar to be held 2x per year, 4.0 CEU credits awarded NWP Engineer Application Training (2 days) Greenwood and On-Site 54 54
55 Questions? 55 55
How to maximize reliability using an alternative distribution system for critical loads
White Paper WP024001EN How to maximize reliability using an alternative distribution system for critical loads Executive summary The electric power industry has several different distribution topologies
More informationNotes 1: Introduction to Distribution Systems
Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission
More informationMV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer
PART 1: GENERAL 1.01 Transformer A. This section includes liquid filled, pad mounted distribution transformers with primary voltage of 12kV or 4.16kV (The University will determine primary voltage), with
More informationCourse 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC)
Name: Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC) 1. T F In three-phase four-wire delta systems rated 240/120 volts, sometimes
More informationPOWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS
POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS Juan Manuel Gers, PhD Protection coordination principles Relay coordination is the process of selecting settings that will assure that the relays
More informationProtection of Electrical Networks. Christophe Prévé
Protection of Electrical Networks Christophe Prévé This Page Intentionally Left Blank Protection of Electrical Networks This Page Intentionally Left Blank Protection of Electrical Networks Christophe Prévé
More informationTABLE OF CONTENT
Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES
More informationCONTENTS. 1. Introduction Generating Stations 9 40
CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific
More informationA Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants
A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants Martin Best and Stephanie Mercer, UC Synergetic, LLC Abstract Wind generating plants employ several
More informationDistribution/Substation Transformer
Distribution/Substation Transformer Type VFI, Vacuum Fault Interrupter Transformer Option Functional Specification Guide Functional specification for 15 kv, 25 kv, or 35 kv vacuum fault interrupter distribution/substation
More informationThis section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.
Basis of Design This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor. Background Information A Short Circuit and Coordination
More informationGrounding Recommendations for On Site Power Systems
Grounding Recommendations for On Site Power Systems Revised: February 23, 2017 2017 Cummins All Rights Reserved Course Objectives Participants will be able to: Explain grounding best practices and code
More informationOptimize Outage Management and Improve Underground System Reliability
SEL-8301 Underground Distribution Sensor Optimize Outage Management and Improve Underground System Reliability Line current measurement accuracy of 1.5 percent allows for more effective switching decisions
More informationNumbering System for Protective Devices, Control and Indication Devices for Power Systems
Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements
More informationEH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström
EH27401 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsn@ics.kth.se 1 Course map 2 Outline 1. Power System Topologies Transmission Grids vs Distribution grids Radial grids
More informationS&C Vista Underground Distribution Switchgear Outdoor Distribution
The offers superior overcurrent coordination. Among the features that provide excellent overcurrent coordination are unique coordinating speed tap and main time-current characteristic curves, which provide
More informationThree-Phase VFI Padmount Transformers. Double Duty in a Single Package. www. ElectricalPartManuals. com
Three-Phase VFI Padmount Transformers Double Duty in a Single Package The Compact,Lower-Cost,Versatile Solution to Power Distribution Save Money. Save Space. The Three-Phase VFI Padmount Transformer from
More informationUtility Interconnection and System Protection
Utility Interconnection and System Protection Alex Steselboim President, Advanced Power Technologies, Inc. Utility paralleling vs. isolated operation. Isochronous kw load sharing Reactive power (VAR) sharing
More informationWAVEFORM CORRECTOR (WAVEFORM CORRECTORS) REPLACES SURGE PROTECTION DEVICES (SPD) PREVIOUSLY KNOWN AS (TVSS)
WAVEFORM CORRECTOR (WAVEFORM CORRECTORS) REPLACES SURGE PROTECTION DEVICES (SPD) PREVIOUSLY KNOWN AS (TVSS) 1 PART 1: GENERAL This section describes materials and installation requirements for low voltage
More informationCutler-Hammer January 1999
Cutler-Hammer January 999 Index - System Design Systems nalysis Capacitors Protection/Coordination Grounding/Ground Fault Protection Power Quality Other Design Considerations Reference Data Description
More informationModule 10. Initiation Code RELIABILITY ACCOUNTABILITY
Module 10 Initiation Code 1 M10 Initiation Code This is not the Initiating cause code The Outage Initiation Codes describe where an Automatic Outage was initiated on the power system. Element-Initiated
More informationMV network design & devices selection EXERCISE BOOK
MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester
More informationConnection Impact Assessment Application
Connection Impact Assessment Application This form is for generators applying for Connection Impact Assessment (CIA) and for generators with a project size >10 kw. Please return the completed form by email,
More informationSubstation Preventive Maintenance
Substation Preventive Maintenance PROVINCIAL ELECTRICITY AUTHORITY 1 Presentation Contents 1) A kind of substation 2) Electrical equipment details of AIS substation 3) Electrical equipment details of GIS
More informationTexas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event
Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event
More informationDistribution System Development & Preliminary Studies
Distribution System Development & Preliminary Studies IEEE CED January 27, 2016 (second night) 2016 KBR, Inc. All Rights Reserved. Agenda Distribution System Development Modeling Data Studies Overview
More informationImpact Assessment Generator Form
Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project
More informationDistance Protection for Distribution Feeders. Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng.
Distance Protection for Distribution Feeders Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng. Why use distance protection for distribution feeders? Distance protection is mainly used for protecting
More informationPOWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE. Professor Akhtar Kalam Victoria University
POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE Professor Akhtar Kalam Victoria University The Problem Calculate & sketch the ZPS, NPS & PPS impedance networks. Calculate feeder faults. Calculate
More informationGE Ventilated Dry-Type Transformers. Secondary Substation Transformers - 5 and 15kV Class
GE Ventilated Dry-Type Transformers Secondary Substation Transformers - 5 and 15kV Class GE ventilated dry-type transformers are designed for indoor or outdoor applications in schools, hospitals, industrial
More informationHamdy Faramawy Senior Application Specialist ABB Sweden
Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy
More informationThe Importance of the Neutral-Grounding Resistor. Presented by: Jeff Glenney, P.Eng. and Don Selkirk, E.I.T.
The Importance of the Neutral-Grounding Resistor Presented by: Jeff Glenney, P.Eng. and Don Selkirk, E.I.T. Presentation Preview What is high-resistance grounding (HRG)? What is the purpose of HRG? Why
More informationTechnical T TECHNICAL. C o n t e n t s SPEEDFAX TM 2017
SPEEDFAX TM 2017 TSection C o n t e n t s Types of Power Distribution Systems T-2 T-4 Ground Fault Protection T-5 T-10 Overcurrent Protection and Coordination T-11 System Analysis T-12 Current Limiting
More informationSECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY SPEC WRITER NOTE: Delete between // -- // if not applicable to project. Also, delete any other item or
More informationTransformer Protection
Transformer Protection Transformer Protection Outline Fuses Protection Example Overcurrent Protection Differential Relaying Current Matching Phase Shift Compensation Tap Changing Under Load Magnetizing
More informationTable of Contents. Introduction... 1
Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...
More informationSmart Wires. Distributed Series Reactance for Grid Power Flow Control. IEEE PES Chapter Meeting - Jackson, MS August 8, 2012
Smart Wires Distributed Series Reactance for Grid Power Flow Control IEEE PES Chapter Meeting - Jackson, MS August 8, 2012 Jerry Melcher Director Program Management Smart Wires Inc. 2 Agenda Technology
More informationSubstation Testing and Commissioning: Power Transformer Through Fault Test
1 Substation Testing and Commissioning: Power Transformer Through Fault Test M. Talebi, Member, IEEE, Power Grid Engineering Y. Unludag Electric Power System Abstract This paper reviews the advantage of
More informationElectrical Arc Hazards
Arc Flash Analysis 1996-2009 ETAP Workshop Operation Notes Technology, 1996-2009 Inc. Operation Workshop Technology, Notes: Arc Inc. Flash Analysis Slide 1 Electrical Arc Hazards Electrical Arcs can occur
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationElectrical Protection System Design and Operation
ELEC9713 Industrial and Commercial Power Systems Electrical Protection System Design and Operation 1. Function of Electrical Protection Systems The three primary aims of overcurrent electrical protection
More informationModelling Parameters. Affect on DER Impact Study Results
Modelling Parameters Affect on DER Impact Study Results Agenda Distributed Energy Resources (DER) Impact Studies DER Challenge Study Steps Lessons Learned Modeling Reverse Power Transformer Configuration
More informationPRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75
PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion
More informationModern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions
1 Transmission transformers are important links in the bulk power system. They allow transfer of power from generation centers, up to the high-voltage grid, and to bulk electric substations for distribution
More informationMERALCO Standards: Electrical Design. Engr. Eduard Mercado Electrical Design Team
MERALCO Standards: Electrical Design Engr. Eduard Mercado Electrical Design Team Electrical Design Standards SERVICE VOLTAGES SECONDARY METERED - 240 V, 400 V, 460 V PRIMARY METERING -34.5 kv, 13.8 kv
More informationPJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016
PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 Prepared by System Planning Division Transmission Planning Department PJM 2016 Table of Contents Table of Contents Approval...6
More informationSHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP
SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP Kiran V. Natkar 1, Naveen Kumar 2 1 Student, M.E., Electrical Power System, MSS CET/ Dr. B.A.M. University, (India) 2 Electrical Power System,
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationIndustrial Electrician Level 3
Industrial Electrician Level 3 Industrial Electrician Unit: C1 Industrial Electrical Code I Level: Three Duration: 77 hours Theory: Practical: 77 hours 0 hours Overview: This unit is designed to provide
More informationFeeder Protection Challenges with High Penetration of Inverter Based Distributed Generation
Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Harag Margossian 1, Florin Capitanescu 2, Juergen Sachau 3 Interdisciplinary Centre for Security, Reliability
More informationMOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE
MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE Scott Storrar Contributors: Bill Hansen, Kyle Reddell, Tom McGrath Basic Mobile Sub Design Equipment mounted on semi-trailer Power transformer
More information1 INTRODUCTION 1.1 PRODUCT DESCRIPTION
GEK-00682D INTRODUCTION INTRODUCTION. PRODUCT DESCRIPTION The MDP Digital Time Overcurrent Relay is a digital, microprocessor based, nondirectional overcurrent relay that protects against phase-to-phase
More informationa) Determine the smallest, standard-sized circuit breaker that should be used to protect this branch circuit.
ECET4520 Exam II Sample Exam Problems Instructions: This exam is closed book, except for the reference booklet provided by your instructor and one (8.5 x11 ) sheet of handwritten notes that may not contain
More informationSECTION SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY
SECTION 16075 - SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide a short-circuit, component protection, flash
More informationThe NOVA Recloser shall be designed and tested in accordance with the following standards as applicable:
Reclosers NOVA Three-Phase Recloser Functional Specification Guide Functional specification for NOVA three-phase recloser 1. Scope This specification describes the features and ratings of the NOVA recloser.
More informationArc Flash Analysis Training
Arc Flash Analysis Training Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq An arc flash analysis study is
More informationE N G I N E E R I N G M A N U A L
1 1 1.0 PURPOSE The purpose of this document is to define policy and provide engineering guidelines for the AP operating companies (Monongahela Power Company, The Potomac Edison Company, and West Penn
More informationMODEL 421 Over/Under Motor Load Monitor
MODEL 421 Over/Under Motor Load Monitor Monitors True Motor Power (volts x current x power factor) Detects Motor Overload or Underload Operates on 120 or, Single-phase or 3-phase Built-in Trip and Restart
More informationAriadna Instruments. Power cable identifier & LV live network phase and feeder identifier
Ariadna Instruments Power cable identifier & LV live network phase and feeder identifier Cable identifiers Cable identifiers There are situations where it is necessary a correctly identification the distribution
More informationWESTERN UNDERGROUND COMMITTEE GUIDE 2.6 (2.6/00/0868)
WESTERN UNDERGROUND COMMITTEE GUIDE 2.6 (2.6/00/0868) THREE-PHASE SUBSURFACE UNDERGROUND COMMERCIAL DISTRIBUTION (UCD) TRANSFORMER NOTE: This "Guide" summarizes the opinions, recommendations, and practices
More informationARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS
The Electrical Power Engineers Qual-Tech Engineers, Inc. 201 Johnson Road Building #1 Suite 203 Houston, PA 15342-1300 Phone 724-873-9275 Fax 724-873-8910 www.qualtecheng.com ARC FLASH PPE GUIDELINES FOR
More informationRUDOLF Digital power analyzer. Advanced Version
RUDOLF Digital power analyzer Advanced Version Digital power analyzer Advanced Version Company Introduction Bridex Singapore Pte Ltd is founded in 1978 as a manufacturer of instruments transformer for
More informationLow Voltage Grid Monitoring
Smart Grid Gotland Subproject Power Quality Low Voltage Grid Monitoring EUW Amsterdam 2017-10-04 Why monitor the low voltage grid? Power outages have so far been identified only by customers, not acceptable
More informationBus Protection Fundamentals
Bus Protection Fundamentals Terrence Smith GE Grid Solutions 2017 Texas A&M Protective Relay Conference Bus Protection Requirements High bus fault currents due to large number of circuits connected: CT
More information2kVA EARTH TESTING CURRENT INJECTION SYSTEM 4046 / 4047 DATASHEET REDPHASE INSTRUMENTS
2kVA EARTH TESTING CURRENT INJECTION SYSTEM 4046 / 4047 DATASHEET REDPHASE INSTRUMENTS Contents Section Brief Description... 1 Where and why it is used... 1.1 Induced Measureable Parameters... 1.2 Hardware
More informationEE 741. Primary & Secondary Distribution Systems
EE 741 Primary & Secondary Distribution Systems Radial-Type Primary Feeder Most common, simplest and lowest cost Example of Overhead Primary Feeder Layout Example of Underground Primary Feeder Layout Radial-Type
More informationGridLiance Reliability Criteria
GridLiance Reliability Criteria Planning Department March 1, 2018 FOREWORD The GridLiance system is planned, designed, constructed, and operated to assure continuity of service during system disturbances
More informationUBC Technical Guidelines Section Edition Medium-Voltage Transformers Page 1 of 5
Page 1 of 5 1.0 GENERAL 1.1 Coordination Requirements.1 UBC Energy & Water Services.2 UBC Building Operations 1.2 Description.1 UBC requirements for Substation Transformers. 2.0 MATERIAL AND DESIGN REQUIREMENTS
More informationBusbars and lines are important elements
CHAPTER CHAPTER 23 Protection of Busbars and Lines 23.1 Busbar Protection 23.2 Protection of Lines 23.3 Time-Graded Overcurrent Protection 23.4 Differential Pilot-Wire Protection 23.5 Distance Protection
More informationWind Power Facility Technical Requirements CHANGE HISTORY
CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical
More informationECET 211 Electric Machines & Controls Lecture 3-1 (Part 1 of 2) Motor Transformers and Distribution Systems
ECET 211 Electric Machines & Controls Lecture 3-1 (Part 1 of 2) Motor Transformers and Distribution Systems Text Book: Electric Motors and Control Systems, by Frank D. Petruzella, published by McGraw Hill,
More informationCapstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:
Phone: (818) 734-5300 Fax: (818) 734-5320 Web: www.capstoneturbine.com Technical Reference Capstone MicroTurbine Electrical Installation 410009 Rev F (October 2013) Page 1 of 31 Capstone Turbine Corporation
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements
Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system
More informationPRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76
PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion
More informationMicrogrid Protection
Panel: Microgrid Research and Field Testing IEEE PES General Meeting, 4-8 June 7, Tampa, FL Microgrid Protection H. Nikkhajoei, Member, IEEE, R. H. Lasseter, Fellow, Abstract In general, a microgrid can
More informationDEVELOPMENT OF A TEST PROTOCOL FOR A 15 KV CLASS SOLID-STATE CURRENT LIMITER
DEVELOPMENT OF A TEST PROTOCOL FOR A 15 KV CLASS SOLID-STATE CURRENT LIMITER ABSTRACT Ashok Sundaram Electric Power Research Inc., USA asundara@epri.com The Solid-state Fault Current Limiter (SSFCL) is
More informationProtection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin
Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc. 770 565-1556 John@L-3.com 1 Protection Fundamentals By John Levine 2 Introductions Tools Outline Enervista Launchpad
More informationINSTALLATION INSTRUCTIONS FOR SYMCOM'S MODEL 777- MV ELECTRONIC OVERLOAD RELAY MEDIUM VOLTAGE
INSTALLATION INSTRUCTIONS FOR SYMCOM'S MODEL 777- MV ELECTRONIC OVERLOAD RELAY MEDIUM VOLTAGE BE SURE POWER IS DISCONNECTED PRIOR TO INSTALLATION! FOLLOW NATIONAL, STATE AND LOCAL CODES. READ THESE INSTRUCTIONS
More informationTopic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017
Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length
More informationAppendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS
Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS S1. Standard Interconnection Methods with Typical Circuit Configuration for Single or Multiple Units Note: The protection requirements
More informationJason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering
DLC s Brady IIB Project Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering Project Need In 2007, PJM and Duquesne Light Company (DLC) transmission
More informationSystem Protection and Control Subcommittee
Power Plant and Transmission System Protection Coordination Reverse Power (32), Negative Sequence Current (46), Inadvertent Energizing (50/27), Stator Ground Fault (59GN/27TH), Generator Differential (87G),
More informationUPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS
UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS 1 B. RAMESH, 2 K. P. VITTAL Student Member, IEEE, EEE Department, National Institute of Technology Karnataka,
More informationCause, Effect & Mitigation Strategies
WSU HANDS ON RELAY SCHOOL 2019 Arc Flash Fault Cause, Effect & Mitigation Strategies Joe Xavier, Technical Manager West Region Arc Flash Fault - Agenda What is an Arc Flash? Why and when does Arc Flash
More informationDeployment of Real-time State Estimator and Load Flow in BC Hydro DMS - Challenges and Opportunities
IEEE PES General Meeting, Vancouver, Canada, July 2013 Deployment of Real-time State Estimator and Load Flow in BC Hydro DMS - Challenges and Opportunities Djordje Atanackovic, BC Hydro Valentina Dabic,
More informationCompany Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System
Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels
More informationCHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses
CHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses 8.1 Introduction The present level of Transmission and Distribution (T & D) losses in Indian power system is estimated
More informationElectrical Description
History of this Document Rev. no.: Date: Description of change 0 First edition 2 2003-10-08 Section 3: The rated power of the transformer can be increased by 40% if they are equipped with 6 fans for forced
More informationMichigan State University Construction Standards SWITCHBOARDS, PANELBOARDS, AND CONTROL CENTERS PAGE
PAGE 262400-1 SECTION 262400 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationIPS INTELLIGENT PUMP STARTER. Integrated Tru-power electronic motor and pump protection
IPS INTELLIGENT PUMP STARTER With TM Smartstart Ø & Ø, 0/60 Hz, 20~600 VAC, /~00HP Integrated electronic pump protection overload Power metering and data logging options Motor Protection Key dealer yr.
More informationIntegrating Transmission and Distribution Engineering Eventualities
Integrating Transmission and Distribution Engineering Eventualities Task 1.1 G. T. Heydt, Arizona State University heydt@asu.edu PSERC Future Grid Initiative May 29, 2013 Innovative HVDC systems Two innovative
More informationTransmission Facilities Rating Methodology
Document title Transmission Facilities Rating Methodology Document number EGR-TRMC-00009 Applies to: Transmission Engineering, Transmission System Operations, and Transmission Planning- Progress Energy
More information7. INSPECTION AND TEST PROCEDURES
7.1 Switchgear and Switchboard Assemblies A. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. 2. Inspect physical and mechanical condition. 3. Inspect
More informationFeeder Protection From Over Load and Earth Fault Relay
Feeder Protection From Over Load and Earth Fault Relay Prof. Vaneela Pyla 1, Uma N. Bhimnath 2, Archana M. Bhosale 3, Apurva V. Khachane 4 Assistant Professor, Electrical Engineering Department, NBN Sinhgad
More informationLow Voltage Products & Systems. ABB Arc Guard System TM TVOC
Low Voltage Products & Systems ABB Arc Guard System TM TVOC Accidents can occur whenever electrical energy is generated or distributed... Short circuits in electrical installations can be a hazard. This
More informationNeed for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design
IEEE PES Transmission and Distribution Conference 2008 Panel Session Large Wind Plant Collector Design Wind Farm Collector System Grounding by Steven W. Saylors, P.E. Chief Electrical Engineer Vestas Americas
More informationA3-102 PCB ROGOWSKI COILS HIGH PRECISION LOW POWER SENSORS. Ljubomir A. Kojovic * Cooper Power Systems USA
21, rue d'artois, F-758 Paris http://www.cigre.org A3-12 Session 24 CIGRÉ PCB ROGOWSKI COILS HIGH PRECISION LOW POWER SENSORS Ljubomir A. Kojovic * Cooper Power Systems USA Summary-This paper presents
More informationVoltage Relays. Ensuring Reliable Protection for Electrical Systems against Voltage Faults. ISO 9001:2008 Certified.
Ensuring Reliable Protection for Electrical Systems against Voltage Faults Voltage Relays Inside the Catalogue Range Model Selection Specifications Technical Terms & Data ISO 9001:2008 Certified Delivering
More informationSingle Line Diagram of Substations
Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission lines are
More informationThyristorised Automatic Power Factor
Thyristorised Automatic Power Factor Correction with 7% D Tune Harmonics Suppression (Reactor/Filtering) System Power quality? In the present Low voltage (LV) industrial distribution system the power factor
More information