A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants

Size: px
Start display at page:

Download "A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants"

Transcription

1 A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants Martin Best and Stephanie Mercer, UC Synergetic, LLC Abstract Wind generating plants employ several distribution class circuits called collector feeders which enable the combined output of the wind turbine generators connected to them to be supplied to the bulk electric transmission system. The application and coordination of overcurrent protection systems for collector feeders at wind plants depends on several system characteristics, including collector feeder design, available fault currents, and the protective devices applied to the wind turbine generators. This paper provides a brief tutorial on the application and setting of overcurrent relays for collector feeders at wind plants and includes examples of typical calculations and coordination plots. Index Terms Collector Systems, Overcurrent Relays, Wind Farms, Wind Power. I. INTRODUCTION Large wind generating plants have become prevalent as green energy sources on the power system. A typical large wind generating plant may have wind turbine generators (WTGs), each rated at MVA connected to medium voltage distribution lines called collector feeders spread over a large area. Power from the WTGs is collected at medium voltage (typically 34.5 kv) and supplied to the main substation through the main collector feeder breakers. The relays applied to protect the collector feeder circuits must coordinate with the protective devices for faults at the individual WTGs without limiting the ability of the WTGs to provide power and effective voltage control for the system. This paper is intended to introduce novice engineers to the physical and electrical characteristics of collector feeders at wind electric plants and to provide a general method of overcurrent relay setting calculations and coordination for collector feeders at wind electric plants. II. WIND FARM COLLECTOR FEEDER CHARACTERISTICS Collector systems of large wind power plants normally have a radial configuration where the WTGs are connected together in a daisy-chain style, moving from the main feeder breaker at the collector substation to the farthest turbine. Collector feeders can therefore be thought of as radial distribution lines when all the generators are off-line and as multi-terminal subtransmission lines when one or more generators are on line. Figure 1 shows a one-line diagram of a wind electric power plant consisting of two collector feeder sections. As can be observed in this figure, the wind turbine generators on some collector feeders are simply connected one after the other down the length of a single circuit. However, some collector feeders may also have branch strings, which are connected by junction boxes. The junction boxes, in turn, have separable connectors (or elbows) that allow isolation of a feeder string to enable continuous operation of the remaining connected WTGs while maintenance or repair work is being performed. Collector feeder circuit operation exhibits both radial and network (looped) characteristics. When the WTGs are off-line they draw only the relatively low load current required by their station auxiliary equipment (lights, heaters, turbine gear motors, etc.). This station service current for the WTGs flows radially from the Collector Substation to the WTGs on the line, and system fault current flows exclusively from the Collector Substation to the fault location on the line or at a WTG. When the WTGs are on-line, their collective output current flows from the WTGs to the Collector Substation, and with multiple generation sources the collector feeder operates as a network. If a fault occurs on the line or at a WTG, most of the fault current comes from the Collector Substation, but a small component of the total fault current does come from any WTGs that are on line at the time of the fault.

2 sequence overcurrent elements can be also applied to provide additional protection or to satisfy coordination requirements that are unique to the installation. Non-directional overcurrent protection can often be applied for collector feeders because the fault current contribution from the collector substation is usually much greater than the contribution from the WTGs; however, if increased sensitivity is required to coordinate with individual WTG protective devices or to detect a fault on the low-voltage side of the WTG transformer, then directional overcurrent protection may be required at the collector feeder breaker. Fig. 1. Collector Feeder One-Line Diagram at a Wind Electric Power Plant. Therefore, relay protection schemes that are commonly applied for either radial or network distribution circuits may be considered. Non-directional overcurrent protection schemes have traditionally been applied for radial distribution line protection. Directional over-current protection schemes have traditionally been applied for protection of network or looped circuits, as well as directional distance relay protection schemes. Ideally, the protection schemes applied at the main feeder breakers at a wind electric power plant should provide primary protection for the collector feeder and backup protection for the step-up transformer at each WTG location. The inverse time-current characteristic of a time overcurrent relay can be selected to coordinate with the thermal damage curve of a line conductor or transformer as well as with overcurrent protective devices such as transformer fuses. Therefore, non-directional and directional overcurrent schemes are almost exclusively applied for collector feeder protection. 1) Non-Directional Overcurrent Protection Example The collector feeder in Figure 1 consists of eight 3.4 MW wind turbine generators. The full load current I FLA of all 8 Generators at 34.5 kv is: I FLA = 1000(8)(3.4 MVA) = 455 A ( 3)(34.5 kv) Since the relay is non-directional, the trip current setting of phase time overcurrent element 51P must be greater than or equal to 1.3 x I FLA for asynchronous generators and inverters, per NERC Standard PRC-025 (Generator Relay Loadability) [1]. Therefore, the 51P setting must be greater than or equal to: 1.3*(455) = 592 A The CT ratio on Feeder 4 is 1200:5 or 240:1. Therefore, dividing the desired trip setting by the current transformer ratio yields 592/240 = 2.47 A, secondary Therefore, the trip current setting for the 51P can be 2.47 A, secondary, if the relay can be set exactly, or rounded up to the nearest tenth to 2.5 A, secondary = 600 A, primary. Each WTG pad mount transformer in Figure 1 has a 3.35 MVA rating and is protected on the 34.5 kv side by a 100 A current limiting fuse in series with a 71 A expulsion type fuse. A current limiting fuse is typically connected in series with the expulsion fuse in cases where the available fault current exceeds the current interrupting rating of the expulsion fuse. The 51P relay must coordinate with the expulsion fuse at fault currents below the 1200 A interrupting rating of the fuse and with the current limiting fuse at fault currents above the expulsion fuse interrupting rating. A very inverse curve was selected to generally match the slope of the EXP and CLF curves over the range of fault currents. III. PROTECTION SCHEMES FOR WIND FARM COLLECTOR FEEDER CIRCUITS Overcurrent protection schemes for collector feeder circuits typically includes time delay and instantaneous phase and ground overcurrent elements. Definite time and negative An example of the resulting coordination appears in Figure 2. In Figure 2 the expulsion fuse (EXP) curve appears below both the transformer damage curve and the current limiting fuse (CLF) at fault currents lower than about 1200A. At fault currents above about 1200A the current limiting fuse (CLF) curve falls below the expulsion fuse curve and will clear the fault before the expulsion fuse can be damaged, thus protecting

3 the expulsion fuse. A very inverse curve was selected for the 51P to match the slope of the EXP/CLF curve combination. Both the EXP and CLF fuse curves fall below the feeder 4 51P relay curve so the 51P relay curve coordinates with both of the fuse curves. The 51P curve is well below the thermal damage curve of the smallest conductor or the feeder and will therefore trip the breaker for a fault before the conductor is damaged. The 600A trip current setting of the 51P is approximately 10 times the full load current rating of one wind turbine generator. It can be seen from Figure 2 that the high trip current setting provides little protection for individual wind turbine generator transformers. This is because the transformer thermal damage curve ends approximately where the 51P curve starts to operate. Therefore, even at a minimum time dial of 0.5, the relay is providing relatively poor back-up transformer protection for currents under 900 A. The phase instantaneous overcurrent relay 50P is typically set low enough to operate for a three-phase fault at the end of the collector feeder circuit but high enough to avoid operation for the inrush current caused by the eight WTG transformers when the collector feeder breaker is initially closed to energize the circuit. The maximum three-phase fault current available at the end of the collector feeder in Figure 1 is 10,375 A. To ensure that the 50P will operate positively for a fault at the end of the circuit, the relay may be set at 75-80% of the maximum current figure. For example, 0.8(10,375 A) = 8300 A. At the 240/1 CT ratio, the desired setting in secondary Amps would be A. Rounding up to the nearest Amp would yield a 50P setting of 35 = 8400 A, primary. Transformer inrush current upon initial energization is typically estimated to be times the nameplate rating of the transformer. If the combined inrush current of the 8 transformers is 12 x Ic, then the inrush current is 5382 A. This value is below the 8400 A 50P setting, so the 50P should not operate when the main collector feeder breaker is initially closed to energize the circuit. The 50P curve in Figure 2 appears as the vertical line at the end of the 51P curve at 8400 A. In cases where the calculated 50P setting is below the maximum expected GSU transformer inrush current, a dual level 50P scheme can be implemented in which the 50P element can be set to detect a feeder fault at the first WTG transformer on the feeder, based on 75-80% of the maximum fault current available at the high voltage side of the first WTG GSU transformer. A second phase overcurrent element can then be set to detect a fault at the farthest GSU on the circuit. The second 50P element can then be set with a definite time delay (usually in cycles) to ride out the transformer inrush current but avoid thermal damage to the cable at the end of the feeder. The combined nameplate current rating Ic of the 8 WTG transformers is: Ic = 8(3.35 MVA)(1000) = 449 A 1.732(34.5 kv)

4 Fig. 2. Non-Directional Phase Time-Overcurrent Coordination. Since the output current from the WTGs to the substation feeder breaker is essentially balanced, the trip current pickup of the neutral or residual ground time overcurrent (51N or 51G) element can be set relatively low, typically in the range of 10 30% of the phase time overcurrent (51P) setting. When selecting the 51G pickup setting, it is important to ensure that the pickup setting is high enough to coordinate with the expulsion fuse on the high voltage side of the WTG GSU transformers. For example, based on the 600 A 51P pickup current setting calculated previously, the 51G pickup setting could range from 60 A (10%) to 180 A (30%). However, the 71 Amp expulsion fuse on the high voltage side of the GSU transformer won t operate at currents below about 140 A, so the minimum 51G pickup setting should be at least 140 A to ensure proper coordination with the expulsion fuse.

5 Given the 240/1 CT ratio, a 0.6 = 144 A pickup setting for the 51G will be equivalent to 24% of the 51P pickup setting and will coordinate with the expulsion fuse. The curve type and time dial is then selected to coordinate with the expulsion fuse. An example of the resulting coordination between the Feeder F4 51G relay of Figure 1 and the high-side EXP fuses of the WTG 1 GSU transformer appears in Figure 3. In Figure 3 the 51G relay provides very good backup protection for the WTG GSU for single phase-to-ground faults because its setting is equal to just over twice the GSU full load current rating. The 51G coordinates with the EXP fuse at all values of fault current, but it coordinates with the CLF fuse only at current values above about 1200 A. This is acceptable, because the CLF was installed to blow before the EXP fuse for currents above 1200 A. Fig. 3. Non-Directional Ground Time-Overcurrent Coordination. The trip current pickup setting for the residual ground or neutral instantaneous overcurrent (50G or 50N) element is calculated much like that of the 50P. The 50G pickup for a collector feeder is typically set low enough to operate for a single phase to ground phase fault at the end of the feeder circuit but high enough to avoid operation for the combined

6 inrush current of the WTG transformers upon initial energization. The maximum single phase to ground fault current available at the end of the collector feeder in Figure 1 is 7175 Amps. Using the same 50P criterion of 75-80% of maximum fault current figure, an 80% setting for the 50G would be 24 = 5760 A, primary. This figure is just above the estimated 5382 A figure for combined GSU inrush, so the 5760 A 50G pickup setting should suffice. The 50G curve in Figure 3 appears as the vertical line at the end of the 51G curve at 5760 A. In cases where the calculated 50G setting is below the maximum expected GSU transformer inrush current, a dual level 50G protection scheme can be set based on the same criteria as the dual level 50P protection scheme described earlier. 2) Directional Overcurrent Protection Example A directional overcurrent relay can be set to operate for a fault in a particular direction, usually defined as forward or reverse. The forward trip direction for the relay could be defined as being in the direction from the substation bus towards the generators on the line. Conversely, the reverse direction could be defined as being in the direction from the WTG on the line towards the main substation bus. Consequently, the directional phase time overcurrent (67P) trip current pick-up can be set below the maximum output current of all the wind turbine generators when the trip direction is from the substation bus towards the WTG. However, the 67P trip current pick-up setting must be set above the combined wind turbine generator auxiliary load (heater and auxiliary equipment load with the wind turbine generators offline). The combined auxiliary load of all the WTGs on the circuit is typically less than 5% of the generating capacity of one WTG. Therefore, for coordination purposes, the 67P trip current setting can be based on the rating of a single wind turbine GSU transformer. For example, each wind turbine generator transformer in Figure 1 is rated at 3.35 MVA. The maximum nameplate current rating would therefore be: I FLA = 1000(3.35 MVA) = 56A ( 3)(34.5 KV) A typical phase time overcurrent setting for transformer protection would be 1.5 to 2.5 times the transformer nameplate rating, which would be equivalent to 84 to 140A, primary. However, the71 A expulsion fuse does not begin to melt until approximately 140 A; therefore the 67P trip current setting should be set above 140 A in order to coordinate with the EXP fuse. Therefore, the minimum trip current setting of the relay would be 0.6 = 144 A, primary, given the 1200/5 current transformer ratio. A curve type and time dial is then selected to coordinate with the expulsion fuse. Figure 4 shows the coordination between the wind turbine generator fuses and the 67P directional phase overcurrent relay.

7 Fig. 4. Directional Phase Time-Overcurrent Coordination. circuit. From Figure 4 above, it can be inferred that with the lower trip current setting, a more inverse time/current curve characteristic than the 51P could be selected whose slope more closely matches that of the expulsion fuse. The combination of the more inverse curve and the lower trip current setting enables the directional phase time overcurrent relay to provide excellent back-up protection for any of the wind turbine generators on the A 67P relay or the 67P element of an electronic multifunction relay usually determines the trip direction by comparing the line current with the system voltage; therefore, it is important to manage the protection system s response to an inadvertent loss of voltage on one or more phases, such as the loss of a VT secondary fuse. Most electronic relays have loss of potential logic which either blocks the 67P element or allows it to operate non-directionally. Non-directional

8 > REPLACE THIS LINE WITH YOUR PAPER IDENTIFICATION NUMBER (DOUBLE-CLICK HERE TO EDIT) < 8 operation of the 67P during a high generation condition could result in a needless trip of the main collector feeder breaker. Blocking the 67P element for loss of voltage and enabling a backup 51P element with a higher trip current setting would be one solution to the problem. It is also important to consider the effect of variable WTG generator loading conditions when applying directional overcurrent relays for collector feeder protection. Wind turbine generators with classifications of Type 3 and higher can supply or absorb appreciable amounts of reactive power. For example, when the WTGs are being operated in a voltage control mode they may absorb reactive power when they are lightly loaded to counter-act the effects of the capacitance of the collection system. Conversely, when it is necessary to raise the system voltage, the WTGs may be required to supply leading VARs to the system. While this capability enables the wind farm to help control and regulate the system voltage and power factor at the point of interconnection, the main power transformer or collector feeder relays may see a wide range of power factor angles, depending on the system dispatch requirements at the time. Jones and Bennett [2] described two occasions in which the 67P element of a collector feeder protection relay tripped when the VAR output of the Type 3 WTGs connected to the feeder brought the load current angle just inside the trip zone of the forward directional element. This can be seen in Figure 5 for Phase A. Their initial solution was simply to lower the line impedance angle setting used by the directional element from 50 0 to 35 0 to shift the forward trip zone away from the normal and emergency range of generator load current. If the relay is equipped with the load encroachment function, a second solution is to define the desired forward zone of fault protection using both directional control and load encroachment [2]. In this case, the maximum sensitivity angle of the positive sequence forward directional element can be set at the line impedance angle of 50 0 for directional control. Based on the first quadrant of an R-X plot, reverse load encroachment impedance characteristic angles can be set at 90 0 and 270 0, respectively, and the forward load encroachment characteristic angles can be set at 90 0 and 85 0, respectively. The forward and reverse load encroachment impedance settings can be set equivalent to % of the combined WTG capacity of the circuit. Alternatively, the forward and reverse load encroachment impedance settings can also be set on their minimum value [4]. The resulting relay trip zone under both directional control and load encroachment supervision on an R-X plot would therefore go from 85 0 in the first quadrant to in the fourth quadrant. Figure 6 shows the relay trip and non-trip zones as they would appear on the Phase A relay voltage and current axis of Figure 5. The effective relay trip zone under both load encroachment and the positive sequence forward directional element for the Phase A element in Figure 6 goes from 40 0 in the first quadrant through the 50-degrees lagging impedance angle of the line at in the fourth quadrant and ending at in the fourth quadrant. The combined directional and load encroachment settings will make the 67P element insensitive to both leading and lagging VAR flows from the WTGs to the transmission system. Figure 5: Phase A Directional Element Operation with WTGs Supplying Additional VARs for Voltage Support An additional margin of reliability can be provided by setting the line impedance angle as low as 10 0 to ensure proper directional element operation in the presence of large VAR flows (Chen, Shrestha, Ituzaro, and Fischer [2]). Figure 6: Phase A Element Operation with Directional and Load Encroachment Control In some electronic multi-function relays, negative sequence polarization techniques are used to control the operation of the 67P element. The negative sequence element settings used for directional control in typical protection applications may not provide reliable operation for directional protection of

9 > REPLACE THIS LINE WITH YOUR PAPER IDENTIFICATION NUMBER (DOUBLE-CLICK HERE TO EDIT) < 9 collector feeder circuits because the Type 4 turbines that are often installed on collector feeders generally produce very little negative sequence current during faults. Type 3 turbines may also provide little negative sequence current during faults when their response is being controlled by their electronic controls. Chen, Shrestha, Ituzaro, and Fischer [2] described an event in which a collector feeder breaker tripped correctly by 67P for a BCG line fault, but the 67P elements for both unfaulted collector feeders tripped incorrectly because the WTGs on the un-faulted feeders were not able to produce enough negative sequence current to enable the feeder relay to correctly determine the direction of the fault. The authors solution was to change the line impedance angle setting in all the relays to about In the negative sequence domain, lowering the line impedance angle to 10 0 enabled the relay to correctly calculate the fault current direction on both the faulted and un-faulted feeders. Additionally, lowering the line impedance angle to 10 0 moved the boundary angles of the positive sequence forward directional trip zone to and 280 0, respectively on an R-X diagram, or 80 0 and 260 0, respectively on a voltage/current axis such as that shown in Figure 5. The directional phase instantaneous overcurrent relay or element can be given the same pickup setting as the 50P because the collective inrush of the WTG transformers upon energization must still be considered. Some electronic multifunction relays have harmonic current blocking functions. In cases where the transformer inrush current exceeds the instantaneous trip current setting required to detect a fault at the end of the collector feeder circuit, harmonic current blocking can be used to inhibit the directional phase instantaneous overcurrent element from tripping for transformer inrush [4]. Similarly, the considerations discussed above for directional phase instantaneous overcurrent elements apply to directional neutral or ground instantaneous overcurrent element settings. Directional neutral or residual ground time overcurrent relays (67N or 67G) can also be applied for collector feeder protection. However, because the 67G (67N) must coordinate with the high-side fuse of the WTG step-up transformer, its minimum trip current setting will be the same as that of a 51N or 51G, and the resulting coordination would be the same as that shown in Figure 3. combined WTG load, will accommodate any change in generator loading conditions, and will generally provide excellent protection over the length of the collector feeder. However, because their minimum trip current pickup setting can be as much as 8 10 times higher than the rating of a single WTG on the circuit, non-directional phase time overcurrent elements may provide only limited backup overcurrent protection for individual WTG step-up transformers. Directional phase time overcurrent elements can be set below the combined WTG load to provide excellent collector feeder protection and backup overcurrent protection for individual WTG step-up transformers. Additional considerations are required in the selection of directional phase time overcurrent settings to ensure that the relay can accommodate any special generator loading conditions mandated by system voltage support requirements. Both directional and non-directional ground time overcurrent relays or elements in a multi-function relay can be set at a third or less of the combined generator load current but higher than the minimum operating current of the expulsion fuses protecting the WTG step-up transformer. Both directional and non-directional ground time overcurrent elements can provide excellent protection for the entire collector feeder as well as for individual WTG step-up transformers. Non-directional instantaneous overcurrent elements are generally set low enough to detect a fault at the end of the collector feeder but high enough to avoid misoperation for WTG GSU transformer inrush upon energization. Directional instantaneous overcurrent elements can either be set the same as their non-directional counterparts, or harmonic blocking control can be applied to enable them to operate for a fault at the end of a feeder without mis-operating for collective WTG transformer inrush. Additional contributions to the body of knowledge in the field of wind farm protection are made with every advance in wind turbine generator and protective relay technology. It is important for the protection engineer to design protection systems that are optimized to effectively address the specific protection requirements at hand. It is the authors hope that this paper will provide a knowledge base from which to start. IV. CONCLUSION The relay protection schemes applied to collector feeders at a wind electric power plant should provide primary protection for the collector feeder and backup protection for the step-up transformer at each WTG location. Several conclusions can be drawn from the foregoing discussion of overcurrent relay setting calculations and coordination for collector feeders. The first conclusion is that both non-directional and directional overcurrent relays or elements in a multi-function relay can be successfully applied and set to provide primary collector feeder protection and backup WTG transformer protection. Nondirectional phase time overcurrent elements are set above the

10 > REPLACE THIS LINE WITH YOUR PAPER IDENTIFICATION NUMBER (DOUBLE-CLICK HERE TO EDIT) < 10 REFERENCES Professional Engineer in the states of CA, DE, FL, GA, ME, NC, OH, PA, SC, TX, VA, and WA. [1] NERC Reliability Standard PRC-025-1: Generator Relay Loadability, July 17, 2014 [Online] Available: RC pdf [2] D. Jones and K. Bennett, Wind Farm Collector Protection Using Directional Overcurrent Elements, Transmission and Distribution Conference and Exposition (T&D), 2012 IEEE PES [Online] Available: [3] B.Chen, A. Shrestha, F.A. Ituzaro, and N. Fischer, Addressing Protection Challenges Associated With Type 3 and Type 4 Wind Turbine Generators, 40 th Annual Western Protective Relay Conference, October 2013 [Online] Available: /Technical%20Papers/6626_AddressingProtection_AS _ _Web2.pdf?v= [4] R. McDaniel, Phase Directional Overcurrent Settings recommendations for Wind Farm Applications Using the SEL-351S, SEL Application Guide AG Martin F. Best received a BS degree in Electrical Engineering from NC State University in 1976 and an MS degree in Electrical Engineering from the University of North Carolina at Charlotte in He joined Duke Energy in 1976 as a Junior Relay Engineer. He joined Duke Engineering & Services in 1995 as a Senior Engineer and served as the lead engineer on protection and control projects. Mr. Best moved to The Shaw Group in 2003 and then to Pike Electric/UC Synergetic in 2008 as a Consulting Engineer. At UC Synergetic he provides technical assistance and training to others on protective relay, control, and instrumentation issues including relay, control and instrumentation system design, determination of equipment requirements and application criteria, fault and coordination studies, power system disturbance analysis, and calculation of protective relay settings. Mr. Best became a Member (M) of IEEE in 1976 and a Senior Member (SM) in He is a working group chair in the Power System Relay Committee. He is a registered Stephanie Mercer received a BS degree in Electrical Engineering from Florida International University in 2008 and an MS degree in Electrical Engineering from the University of North Carolina at Charlotte in She joined Mitsubishi Heavy Industries in 2008 as a Junior Project Engineer. She worked with Florida Power and Light in 2012 as a Test Engineer for their smart meter grid project and with TYLin as a Project Engineer. Ms. Mora moved to UC Synergetic in 2014 as a Relay and Controls Engineer. At UC Synergetic she works on protective relay, control, and instrumentation issues including relay, control and instrumentation system design, determination of equipment requirements and application criteria, fault and coordination studies, power system disturbance analysis, and calculation of protective relay settings. Ms. Mora became a Member (M) of IEEE in She is an Engineer in Training currently registered for the Professional Engineer exam.

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination GSU Phase Overcurrent (51T), GSU Ground Overcurrent (51TG), and Breaker Failure (50BF) Protection NERC Protection Coordination Webinar Series

More information

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 Charles J. Mozina, Consultant Beckwith Electric Co., Inc. www.beckwithelectric.com I. Introduction During the 2003 blackout,

More information

1 INTRODUCTION 1.1 PRODUCT DESCRIPTION

1 INTRODUCTION 1.1 PRODUCT DESCRIPTION GEK-00682D INTRODUCTION INTRODUCTION. PRODUCT DESCRIPTION The MDP Digital Time Overcurrent Relay is a digital, microprocessor based, nondirectional overcurrent relay that protects against phase-to-phase

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Transmission System Phase Backup Protection

Transmission System Phase Backup Protection Reliability Guideline Transmission System Phase Backup Protection NERC System Protection and Control Subcommittee Draft for Planning Committee Approval June 2011 Table of Contents 1. Introduction and Need

More information

System Protection and Control Subcommittee

System Protection and Control Subcommittee Power Plant and Transmission System Protection Coordination Reverse Power (32), Negative Sequence Current (46), Inadvertent Energizing (50/27), Stator Ground Fault (59GN/27TH), Generator Differential (87G),

More information

Transformer Protection

Transformer Protection Transformer Protection Transformer Protection Outline Fuses Protection Example Overcurrent Protection Differential Relaying Current Matching Phase Shift Compensation Tap Changing Under Load Magnetizing

More information

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc. 770 565-1556 John@L-3.com 1 Protection Fundamentals By John Levine 2 Introductions Tools Outline Enervista Launchpad

More information

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 Prepared by System Planning Division Transmission Planning Department PJM 2016 Table of Contents Table of Contents Approval...6

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 PRC-025-1 Generator Relay Loadability A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities

More information

Catastrophic Relay Misoperations and Successful Relay Operation

Catastrophic Relay Misoperations and Successful Relay Operation Catastrophic Relay Misoperations and Successful Relay Operation Steve Turner (Beckwith Electric Co., Inc.) Introduction This paper provides detailed technical analysis of several catastrophic relay misoperations

More information

Power Plant and Transmission System Protection Coordination

Power Plant and Transmission System Protection Coordination Technical Reference Document Power Plant and Transmission System Protection Coordination NERC System Protection and Control Subcommittee Revision 1 July 2010 Table of Contents 1. Introduction... 1 1.1.

More information

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number:  Address: NORTH CAROLINA INTERCONNECTION REQUEST Utility: Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: An is considered complete when it provides all applicable and correct information

More information

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination Phase Distance (21) and Voltage-Controlled or Voltage-Restrained Overcurrent Protection (51V) NERC Protection Coordination Webinar Series June

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS Juan Manuel Gers, PhD Protection coordination principles Relay coordination is the process of selecting settings that will assure that the relays

More information

Focused Directional Overcurrent Elements (67P, Q and N) for DER Interconnection Protection

Focused Directional Overcurrent Elements (67P, Q and N) for DER Interconnection Protection Engineered Solutions for Power System Protection, Automaton and Control APPLICATION NOTE Focused Directional Overcurrent Elements (67P, Q and N) for DER Interconnection Protection 180622 Abstract This

More information

NERC Protection Coordination Webinar Series July 15, Jon Gardell

NERC Protection Coordination Webinar Series July 15, Jon Gardell Power Plant and Transmission System Protection Coordination Reverse Power (32), Negative Sequence Current (46), Inadvertent Energizing (50/27), Stator Ground Fault (59GN/27TH), Generator Differential (87G),

More information

Verifying Transformer Differential Compensation Settings

Verifying Transformer Differential Compensation Settings Verifying Transformer Differential Compensation Settings Edsel Atienza and Marion Cooper Schweitzer Engineering Laboratories, Inc. Presented at the 6th International Conference on Large Power Transformers

More information

Power Plant and Transmission System Protection Coordination Fundamentals

Power Plant and Transmission System Protection Coordination Fundamentals Power Plant and Transmission System Protection Coordination Fundamentals NERC Protection Coordination Webinar Series June 2, 2010 Jon Gardell Agenda 2 Objective Introduction to Protection Generator and

More information

Using a Multiple Analog Input Distance Relay as a DFR

Using a Multiple Analog Input Distance Relay as a DFR Using a Multiple Analog Input Distance Relay as a DFR Dennis Denison Senior Transmission Specialist Entergy Rich Hunt, M.S., P.E. Senior Field Application Engineer NxtPhase T&D Corporation Presented at

More information

PROTECTION of electricity distribution networks

PROTECTION of electricity distribution networks PROTECTION of electricity distribution networks Juan M. Gers and Edward J. Holmes The Institution of Electrical Engineers Contents Preface and acknowledgments x 1 Introduction 1 1.1 Basic principles of

More information

POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE. Professor Akhtar Kalam Victoria University

POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE. Professor Akhtar Kalam Victoria University POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE Professor Akhtar Kalam Victoria University The Problem Calculate & sketch the ZPS, NPS & PPS impedance networks. Calculate feeder faults. Calculate

More information

Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions

Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions PRC-001: System protection coordination PRC-019: Coordination with voltage regulating control

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

Power Plant and Transmission System Protection Coordination

Power Plant and Transmission System Protection Coordination Agenda Item 5.h Attachment 1 A Technical Reference Document Power Plant and Transmission System Protection Coordination Draft 6.9 November 19, 2009 NERC System Protection and Control Subcommittee November

More information

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event

More information

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS AND MEDIUM-SIZE FACILITIES (5,000-25,000KW) CONNECTED

More information

Improving Transformer Protection

Improving Transformer Protection Omaha, NB October 12, 2017 Improving Transformer Protection Wayne Hartmann VP, Customer Excellence Senior Member, IEEE Wayne Hartmann Senior VP, Customer Excellence Speaker Bio whartmann@beckwithelectric.com

More information

Electrical Protection System Design and Operation

Electrical Protection System Design and Operation ELEC9713 Industrial and Commercial Power Systems Electrical Protection System Design and Operation 1. Function of Electrical Protection Systems The three primary aims of overcurrent electrical protection

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

Setting and Verification of Generation Protection to Meet NERC Reliability Standards 1 Setting and Verification of Generation Protection to Meet NERC Reliability Standards Xiangmin Gao, Tom Ernst Douglas Rust, GE Energy Connections Dandsco LLC. Abstract NERC has recently published several

More information

Utility Interconnection and System Protection

Utility Interconnection and System Protection Utility Interconnection and System Protection Alex Steselboim President, Advanced Power Technologies, Inc. Utility paralleling vs. isolated operation. Isochronous kw load sharing Reactive power (VAR) sharing

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS Juan Manuel Gers, PhD Example - Single Line Example 1 - Data Calculate the following: 1. The three phase short circuit levels on busbars

More information

Generator Protection GENERATOR CONTROL AND PROTECTION

Generator Protection GENERATOR CONTROL AND PROTECTION Generator Protection Generator Protection Introduction Device Numbers Symmetrical Components Fault Current Behavior Generator Grounding Stator Phase Fault (87G) Field Ground Fault (64F) Stator Ground Fault

More information

9 Overcurrent Protection for Phase and Earth Faults

9 Overcurrent Protection for Phase and Earth Faults Overcurrent Protection for Phase and Earth Faults Introduction 9. Co-ordination procedure 9.2 Principles of time/current grading 9.3 Standard I.D.M.T. overcurrent relays 9.4 Combined I.D.M.T. and high

More information

UProtection Requirements. Ufor a Large scale Wind Park. Shyam Musunuri Siemens Energy

UProtection Requirements. Ufor a Large scale Wind Park. Shyam Musunuri Siemens Energy UProtection Requirements Ufor a Large scale Wind Park Shyam Musunuri Siemens Energy Abstract: In the past wind power plants typically had a small power rating when compared to the strength of the connected

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

PROTECTIVE RELAY MISOPERATIONS AND ANALYSIS

PROTECTIVE RELAY MISOPERATIONS AND ANALYSIS PROTECTIVE RELAY MISOPERATIONS AND ANALYSIS BY STEVE TURNER, Beckwith Electric Company, Inc. This paper provides detailed technical analysis of two relay misoperations and demonstrates how to prevent them

More information

Adaptive Relaying of Radial Distribution system with Distributed Generation

Adaptive Relaying of Radial Distribution system with Distributed Generation Adaptive Relaying of Radial Distribution system with Distributed Generation K.Vijetha M,Tech (Power Systems Engineering) National Institute of Technology-Warangal Warangal, INDIA. Email: vijetha258@gmail.com

More information

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy Interconnection Coordinator 1945

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities at a level to prevent unnecessary tripping

More information

How to maximize reliability using an alternative distribution system for critical loads

How to maximize reliability using an alternative distribution system for critical loads White Paper WP024001EN How to maximize reliability using an alternative distribution system for critical loads Executive summary The electric power industry has several different distribution topologies

More information

TABLE OF CONTENT

TABLE OF CONTENT Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES

More information

Distance Protection in Distribution Systems: How It Assists With Integrating Distributed Resources

Distance Protection in Distribution Systems: How It Assists With Integrating Distributed Resources 1 Distance Protection in Distribution Systems: How It Assists With Integrating Distributed Resources David Martin and Pankaj Sharma, Hydro One Networks Inc. Amy Sinclair and Dale Finney, Schweitzer Engineering

More information

Waterpower '97. Upgrading Hydroelectric Generator Protection Using Digital Technology

Waterpower '97. Upgrading Hydroelectric Generator Protection Using Digital Technology Waterpower '97 August 5 8, 1997 Atlanta, GA Upgrading Hydroelectric Generator Protection Using Digital Technology Charles J. Beckwith Electric Company 6190-118th Avenue North Largo, FL 33773-3724 U.S.A.

More information

Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security

Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security Steve Turner Senior Application Engineer Beckwith Electric Company Introduction Summarize conclusions from NERC

More information

2015 Relay School Bus Protection Mike Kockott March, 2015

2015 Relay School Bus Protection Mike Kockott March, 2015 2015 Relay School Bus Protection Mike Kockott March, 2015 History of Bus Protection Circulating current differential (1900s) High impedance differential (1940s) Percentage restrained differential (1960s)

More information

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS CONNECTED TO THE DISTRIBUTION SYSTEM ORANGE AND ROCKLAND

More information

Power Plant and Transmission System Protection Coordination of-field (40) and Out-of. of-step Protection (78)

Power Plant and Transmission System Protection Coordination of-field (40) and Out-of. of-step Protection (78) Power Plant and Transmission System Protection Coordination Loss-of of-field (40) and Out-of of-step Protection (78) System Protection and Control Subcommittee Protection Coordination Workshop Phoenix,

More information

Power System Protection Manual

Power System Protection Manual Power System Protection Manual Note: This manual is in the formative stage. Not all the experiments have been covered here though they are operational in the laboratory. When the full manual is ready,

More information

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements User s Guide General Most faults in power systems can be detected by applying

More information

U I. Time Overcurrent Relays. Basic equation. More or less approximates thermal fuse. » Allow coordination with fuses 9/24/2018 ECE525.

U I. Time Overcurrent Relays. Basic equation. More or less approximates thermal fuse. » Allow coordination with fuses 9/24/2018 ECE525. Time Overcurrent Relays More or less approximates thermal fuse» Allow coordination with fuses Direction of Current nduced Torque Restraining Spring Reset Position Time Dial Setting Disk Basic equation

More information

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition NERC System Protection and Control Subcommittee March 2016 NERC Report Title Report Date I Table

More information

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS 1 B. RAMESH, 2 K. P. VITTAL Student Member, IEEE, EEE Department, National Institute of Technology Karnataka,

More information

This webinar brought to you by The Relion Product Family Next Generation Protection and Control IEDs from ABB

This webinar brought to you by The Relion Product Family Next Generation Protection and Control IEDs from ABB This webinar brought to you by The Relion Product Family Next Generation Protection and Control IEDs from ABB Relion. Thinking beyond the box. Designed to seamlessly consolidate functions, Relion relays

More information

Protection of Electrical Networks. Christophe Prévé

Protection of Electrical Networks. Christophe Prévé Protection of Electrical Networks Christophe Prévé This Page Intentionally Left Blank Protection of Electrical Networks This Page Intentionally Left Blank Protection of Electrical Networks Christophe Prévé

More information

Substation Testing and Commissioning: Power Transformer Through Fault Test

Substation Testing and Commissioning: Power Transformer Through Fault Test 1 Substation Testing and Commissioning: Power Transformer Through Fault Test M. Talebi, Member, IEEE, Power Grid Engineering Y. Unludag Electric Power System Abstract This paper reviews the advantage of

More information

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria ReliabilityFirst Regional Criteria 1 Disturbance Monitoring and Reporting Criteria 1 A ReliabilityFirst Board of Directors approved good utility practice document which are not reliability standards. ReliabilityFirst

More information

Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection

Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection 133 1. Pilot wire differential relays (Device 87L) The pilot wire differential relay is a high-speed

More information

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY WN U-60 Attachment C to Schedule 152, Page 1 SCHEDULE 152 APPLICATION FOR INTERCONNECTING A GENERATING FACILITY TIER 2 OR TIER 3 This Application is considered complete when it provides all applicable

More information

DISTRIBUTION DEVICE COORDINATION

DISTRIBUTION DEVICE COORDINATION DISTRIBUTION DEVICE COORDINATION Kevin Damron & Calvin Howard Avista Utilities Presented March th, 08 At the 5 th Annual Hands-On Relay School Washington State University Pullman, Washington TABLE OF CONTENTS

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

Protection of a 138/34.5 kv transformer using SEL relay

Protection of a 138/34.5 kv transformer using SEL relay Scholars' Mine Masters Theses Student Theses and Dissertations Fall 2016 Protection of a 138/34.5 kv transformer using SEL 387-6 relay Aamani Lakkaraju Follow this and additional works at: http://scholarsmine.mst.edu/masters_theses

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network Preface p. iii Introduction and General Philosophies p. 1 Introduction p. 1 Classification of Relays p. 1 Analog/Digital/Numerical p. 2 Protective Relaying Systems and Their Design p. 2 Design Criteria

More information

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions 1 Transmission transformers are important links in the bulk power system. They allow transfer of power from generation centers, up to the high-voltage grid, and to bulk electric substations for distribution

More information

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Harag Margossian 1, Florin Capitanescu 2, Juergen Sachau 3 Interdisciplinary Centre for Security, Reliability

More information

The InterNational Electrical Testing Association Journal. BY STEVE TURNER, Beckwith Electric Company, Inc.

The InterNational Electrical Testing Association Journal. BY STEVE TURNER, Beckwith Electric Company, Inc. The InterNational Electrical Testing Association Journal FEATURE PROTECTION GUIDE 64S Theory, Application, and Commissioning of Generator 100 Percent Stator Ground Fault Protection Using Low Frequency

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

System Protection and Control Subcommittee

System Protection and Control Subcommittee Power Plant and Transmission System Protection Coordination Volts Per Hertz (24), Undervoltage (27), Overvoltage (59), and Under/Overfrequency (81) Protection System Protection and Control Subcommittee

More information

ENOSERV 2014 Relay & Protection Training Conference Course Descriptions

ENOSERV 2014 Relay & Protection Training Conference Course Descriptions ENOSERV 2014 Relay & Protection Training Conference Course Descriptions Day 1 Generation Protection/Motor Bus Transfer Generator Protection: 4 hours This session highlights MV generator protection and

More information

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements

More information

Implementation Plan Project Modifications to PRC Reliability Standard PRC-025-2

Implementation Plan Project Modifications to PRC Reliability Standard PRC-025-2 Project 2016-04 Modifications to PRC-025-1 Reliability Standard PRC-025-2 Applicable Standard PRC Generator Relay Loadability Requested Retirement PRC 025 1 Generator Relay Loadability Prerequisite Standard

More information

Harmonizing the Changing Resource Mix Keeping the Grid Together

Harmonizing the Changing Resource Mix Keeping the Grid Together Harmonizing the Changing Resource Mix Keeping the Grid Together Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 30, 2017 NERC-IEEE Memorandum of Understanding

More information

Pinhook 500kV Transformer Neutral CT Saturation

Pinhook 500kV Transformer Neutral CT Saturation Russell W. Patterson Tennessee Valley Authority Presented to the 9th Annual Fault and Disturbance Analysis Conference May 1-2, 26 Abstract This paper discusses the saturation of a 5kV neutral CT upon energization

More information

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products

More information

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document Bulk Electric System Definition Reference Document Version 2 April 2014 This technical reference was created by the Definition of Bulk Electric System drafting team to assist entities in applying the definition.

More information

Distance Element Performance Under Conditions of CT Saturation

Distance Element Performance Under Conditions of CT Saturation Distance Element Performance Under Conditions of CT Saturation Joe Mooney Schweitzer Engineering Laboratories, Inc. Published in the proceedings of the th Annual Georgia Tech Fault and Disturbance Analysis

More information

Protective Relays Digitrip 3000

Protective Relays Digitrip 3000 New Information Technical Data Effective: May 1999 Page 1 Applications Provides reliable 3-phase and ground overcurrent protection for all voltage levels. Primary feeder circuit protection Primary transformer

More information

Table of Contents. Introduction... 1

Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...

More information

NEW DESIGN OF GROUND FAULT PROTECTION

NEW DESIGN OF GROUND FAULT PROTECTION NEW DESIGN OF GROUND FAULT PROTECTION J. Blumschein*, Y. Yelgin* *SIEMENS AG, Germany, email: joerg.blumschein@siemens.com Keywords: Ground fault protection, directional element, faulted phase selection

More information

Alberta Interconnected Electric System Protection Standard

Alberta Interconnected Electric System Protection Standard Alberta Interconnected Electric System Protection Standard Revision 0 December 1, 2004 APEGGA Permit to Practice P-08200 Table of Contents Signature Page... 2 Table of Contents... 3 1.0 STAKEHOLDER REVIEW

More information

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies Application for A Sub-harmonic Protection Relay ERLPhase Power Technologies 1 Outline Introduction System Event at Xcel Energy Event Analysis Microprocessor based relay hardware architecture Sub harmonic

More information

Distance Relay Response to Transformer Energization: Problems and Solutions

Distance Relay Response to Transformer Energization: Problems and Solutions 1 Distance Relay Response to Transformer Energization: Problems and Solutions Joe Mooney, P.E. and Satish Samineni, Schweitzer Engineering Laboratories Abstract Modern distance relays use various filtering

More information

MV network design & devices selection EXERCISE BOOK

MV network design & devices selection EXERCISE BOOK MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester

More information

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES Purpose This section specifies the requirements for protective relays and control devices for Generation Entities interconnecting

More information

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla Power Plant and Transmission System Protection ti Coordination Loss-of-Field (40) and Out-of of-step Protection (78) NERC Protection Coordination Webinar Series June 30, 2010 Dr. Murty V.V.S. Yalla Disclaimer

More information

Testing Numerical Transformer Differential Relays

Testing Numerical Transformer Differential Relays Feature Testing Numerical Transformer Differential Relays Steve Turner Beckwith Electric Co., nc. ntroduction Numerical transformer differential relays require careful consideration as to how to test properly.

More information

Earth Fault Protection

Earth Fault Protection Earth Fault Protection Course No: E03-038 Credit: 3 PDH Velimir Lackovic, Char. Eng. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877) 322-4774

More information

889 Advanced Generator Protection Technical Note

889 Advanced Generator Protection Technical Note GE Grid Solutions 8 Series 889 Advanced Generator Protection Technical Note GE Publication Number: GET-20056 Copyright 2017 GE Multilin Inc. Overview The Multilin 889 is part of the 8 Series platform that

More information

2012 Grid of the Future Symposium. Impacts of the Decentralized Photovoltaic Energy Resources on the Grid

2012 Grid of the Future Symposium. Impacts of the Decentralized Photovoltaic Energy Resources on the Grid 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Impacts of the Decentralized Photovoltaic Energy Resources on the Grid B. ENAYATI, C.

More information

Back to the Basics Current Transformer (CT) Testing

Back to the Basics Current Transformer (CT) Testing Back to the Basics Current Transformer (CT) Testing As test equipment becomes more sophisticated with better features and accuracy, we risk turning our field personnel into test set operators instead of

More information

Preface...x Chapter 1 Electrical Fundamentals

Preface...x Chapter 1 Electrical Fundamentals Preface...x Chapter 1 Electrical Fundamentals Unit 1 Matter...3 Introduction...3 1.1 Matter...3 1.2 Atomic Theory...3 1.3 Law of Electrical Charges...4 1.4 Law of Atomic Charges...5 Negative Atomic Charge...5

More information

Unit 3 Magnetism...21 Introduction The Natural Magnet Magnetic Polarities Magnetic Compass...21

Unit 3 Magnetism...21 Introduction The Natural Magnet Magnetic Polarities Magnetic Compass...21 Chapter 1 Electrical Fundamentals Unit 1 Matter...3 Introduction...3 1.1 Matter...3 1.2 Atomic Theory...3 1.3 Law of Electrical Charges...4 1.4 Law of Atomic Charges...4 Negative Atomic Charge...4 Positive

More information

Time-current Coordination

Time-current Coordination 269 5.2.3.1 Time-current Coordination Time that is controlled by current magnitude permits discriminating faults at one location from another. There are three variables available to discriminate faults,

More information

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor. Basis of Design This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor. Background Information A Short Circuit and Coordination

More information

Forward to the Basics: Selected Topics in Distribution Protection

Forward to the Basics: Selected Topics in Distribution Protection Forward to the Basics: Selected Topics in Distribution Protection Lee Underwood and David Costello Schweitzer Engineering Laboratories, Inc. Presented at the IEEE Rural Electric Power Conference Orlando,

More information