Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering
|
|
- Erik Fowler
- 5 years ago
- Views:
Transcription
1 DLC s Brady IIB Project Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering
2 Project Need In 2007, PJM and Duquesne Light Company (DLC) transmission studies identified and confirmed a potential transmission system reliability issue a second contingency or N-2 thermal overload could occur in 2012 and a single contingency or N-1 thermal overloads could occur in 2022 Violation of DLC planning criteria DLC s Proposed 3-Part Transmission Solution: Construct new Brunot Island-Brady-Carson underground 345kV line Build a new 345/138kV substation at Brady Street Loop existing Carson-Oakland 138kV into the new substation & recable Transmission details of DLC s Brady Project shared at the PJM s August 2007 Transmission Expansion Advisory Committee meeting Three Baseline projects approved by PJM Board of Managers in October
3 Evolving System Need In 2011, changes in system conditions and projected demand resulted in a revised scope for the project Brady Street Substation was tabled Brunot Island Carson 345kV circuit still required Converting and re-cabling 69kV to 138kV circuits still required Project required in-service date adjusted to 6/1/2016 Transmission details shared at PJM s September 2011 Transmission Expansion Advisory Committee meeting In 2013, the need for 345kV shunt reactors was identified to address high voltage Shunt reactors planned for Brunot Island Substation and tapped from the Brunot Island-Carson 345kV circuit Transmission details shared at PJM s May 2013 Transmission Expansion Advisory Committee meeting 3
4 Brady IIB DLC s Brady Project was broken into multiple phases Phase I - ISD: 6/1/2012 Convert Forbes substation from 69kV to 138kV and two (2) 69kV High Pressure Fluid Filled (HPFF) circuits to 138kV Phase IIA - ISD: 6/1/2013 Establish a Carson-Oakland 138kV circuit utilizing former 69kV HPFF circuit Phase IIB - ISD: 6/1/2016 Establish Brunot Island-Carson 345kV (302) circuit Install two (2) 200MVAR, 345kV shunt reactors 4
5 Brady IIB Circuit Route Underground: 9 miles Overhead: 1.3 miles 5
6 High Pressure Fluid Filled (HPFF) Circuits DLC began using HPFF circuits in the 1950s Brady Project maximized the use of DLC s HPFF circuits Benefits of HPFF Utilization of existing infrastructure Proven track record at DLC Small footprint Ratings can be increased through oil circulation and forced cooling 6
7 High Pressure Fluid Filled (HPFF) Circuits Smart Pig A Smart Pig was used to test the HPFF pipe before recabling Common inspection tool in the oil and gas industry Uses magnetic flux leakage to identify corrosion or variations in the pipe wall thickness 7
8 Shunt Reactors Certain contingencies resulted in voltage above acceptable limits in future studies DLC Operations Center was experiencing high voltage during valley load periods Similar operational challenges across PJM territory Reactors sized and located to support voltage ranges across all demands Transient study performed to identify negative transient and harmonic conditions Determination for Independent Pole Operated (IPO) breakers to switch shunt reactors Control scheme employed to eliminate resonance condition when cable is de-energized and eliminate zero miss condition during energization Additional bus capacitance added to reduce Transient Recovery Voltage (TRV) 8
9 Shunt Reactors Transient Study Results Current Through Carson 345kV Breaker When Energizing Cable from Carson with Line Reactor In-Service ( Zero Miss ) Source: Transients Analysis for the Brunot Island to Carson 345 kv Cable Final Report Mitsubishi Electric Power Products, Inc., February
10 Shunt Reactors Transient Study Results Voltage on De-energized Brunot Island - Carson 345kV Circuit with Shunt Reactor In-Service Source: Transients Analysis for the Brunot Island to Carson 345 kv Cable Final Report Mitsubishi Electric Power Products, Inc., February
11 Shunt Reactors Transient Study Results Voltage Across the Shunt Reactor Circuit Breaker with Various TRV Control Capacitances when Interrupting Reactor-Limited Fault Source: Transients Analysis for the Brunot Island to Carson 345 kv Cable Final Report Mitsubishi Electric Power Products, Inc., February
12 Engineering and Construction Overview Engineering/Construction: 5 years June 2011 to 2016 Project Cost: $83.8M Brady IIB: $65M Shunt Reactors: $19M Over 31,600 Duquesne Light Hours Brady IIB - 17,900 Reactors - 13,700 12
13 Engineering and Construction Overview Brunot Island Substation 345kV Yard Expansion Carson Substation 345kV Yard Expansion Tecumseh Substation Establishment Major Equipment Installed (2) 345kV Shunt Reactors (6 single phase units) + 1 spare unit 143,000 Linear Feet of 2500MCM (HPFF) 345kV cable (7) 345kV Gang Operated Breakers (2) 345kV IPO Breakers 13
14 Shunt Reactor Design Core Design Slate Discs Rods for Clamping Stacked Core Source: GE/Alston Active Part Process Submittal, December,
15 Shunt Reactor Design Core Design Insulation Around Core Lowering Winding Around Core Lowering Top Yoke Source: GE/Alston Active Part Process Submittal, December,
16 Shunt Reactor Design Shipping Configurations 16
17 Shunt Reactor Design Assembly in Process 17
18 Brunot Island Substation Pre-Construction No kv Bus 18 No kv 350 MVA Auto. Arsenal (306) Collier (304) CS 186a No kv Bus 325 #3-345 kv Bus Arsenal (305) # kv Bus #2-138 kv Bus Forbes (Z-46) Legend 345 kv Equipment 138 kv Equipment 324 Arsenal (305) Arsenal (306) 320 Crescent (331) Brunot Island 345 kv Substation
19 Brunot Island Substation Pre-Construction 19
20 Brunot Island Substation Post Construction No kv Bus 20 No kv 350 MVA Auto. Arsenal (306) CS 186a No kv Bus 325 #3-345 kv Bus # kv Bus #4-345 kv Bus 200 MVAR Shunt Reactor Arsenal (305) Arsenal (306) Carson (302) Crescent (331) Brunot Island 345 kv Substation 330 Collier (304) Arsenal (305) #2-138 kv Bus Forbes (Z-46) Carson (302) Legend 345 kv Equipment 138 kv Equipment 341
21 Brunot Island Substation Post Construction 21
EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström
EH27401 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsn@ics.kth.se 1 Course map 2 Outline 1. Power System Topologies Transmission Grids vs Distribution grids Radial grids
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee August 11, 2016 2016 RTEP Window #3 Anticipated Scope and Timeline Anticipated 2016 RTEP Window #3 Anticipated 2016 RTEP Window #3
More informationCONTENTS. 1. Introduction Generating Stations 9 40
CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific
More informationTab 2 Voltage Stresses Switching Transients
Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles
More informationShunt Reactors. Global Top Energy, Machinery & Plant Solution Provider
Shunt Reactors Global Top Energy, Machinery & Plant Solution Provider Our Business Brief introduction of Hyosung Power & Industrial Systems PG While Hyosung is an established name for world-class electrical
More informationPhase Shifting Transformers. Presented by
Phase Shifting Transformers Presented by Phase Shifting Transformers (PST s) (a.k.a. Phase Angle Regulators) VS φ S P V V S = X L L X L sin( φ φ ) L S VL φ L PST s are power flow control devices between
More informationTraining Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch.
Training Title POWER TRANSFORMERS Training Duration 5 days Training Venue and Dates Power transformers 5 20-24 May $3,300 Abu Dhabi In any of the 5 star hotel. The exact venue will be informed soon. Training
More informationG. KOBET, I. GRANT, G. GOZA Tennessee Valley Authority USA. R. GIRGIS, M. ESPINDOLA ABB Corporation USA SUMMARY
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Assessment of the Impact of GMD on the TVA 500 kv Grid & Power Transformers Part II:
More informationECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control
ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections
More informationTransmission Facilities Rating Methodology for Florida
Document title Transmission Facilities Rating Methodology for Florida Document number EGR-TRMF-00001 Applies to: Transmission Engineering, Transmission System Operations, and Transmission Planning Duke
More informationHighgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES
Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why
More informationHVDC High Voltage Direct Current
HVDC High Voltage Direct Current Typical HVDC Station BACK TO BACK CONVERTER STATION MONO POLAR WITH GROUND RETURN PA Back to Back Converters indicates that the Rectifiers & Inverters are located in the
More informationFACILITY RATINGS METHOD TABLE OF CONTENTS
FACILITY RATINGS METHOD TABLE OF CONTENTS 1.0 PURPOSE... 2 2.0 SCOPE... 3 3.0 COMPLIANCE... 4 4.0 DEFINITIONS... 5 5.0 RESPONSIBILITIES... 7 6.0 PROCEDURE... 8 6.4 Generating Equipment Ratings... 9 6.5
More informationHIGH VOLTAGE CIRCUIT BREAKERS
HIGH VOLTAGE CIRCUIT BREAKERS Design and Applications Second Edition, Revised and Expanded RUBEN D. GARZON Square D Co. Smyrna, Tennessee MARCEL Ш D E К К E R MARCEL DEKKER, INC. NEW YORK BASEL CONTENTS
More informationPower System Studies
Power System Studies Laois Ballyragget Cable Feasibility Study PE667-F4-R3-1-3 ESBI Engineering Solutions Stephen Court, 18/21 St Stephen s Green, Dublin 2, Ireland Telephone+353-1-73 8 Fax+353-1-661 66
More informationCentral Hudson Gas & Electric Corporation. Transmission Planning Guidelines
Central Hudson Gas & Electric Corporation Transmission Planning Guidelines Version 4.0 March 16, 2016 Version 3.0 March 16, 2009 Version 2.0 August 01, 1988 Version 1.0 June 26, 1967 Table of Contents
More informationTRANSFORMER TECHNOLOGY GPT
Core-Form TRANSFORMER TECHNOLOGY GlobalPT Corporation performs research and engineering developments and co-ordination of works of technical partners in the field of technological progress and commercial
More informationESB National Grid Transmission Planning Criteria
ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and
More informationMidAmerican Energy Company 69 kv Facility Ratings Methodology
MidAmerican Energy Company 69 kv Facility Ratings Methodology Version 1.0 Issued by: Luke Erichsen Reviewed by: Tom Mielnik Last Reviewed: 8/29/2012 1 1.0 Scope: This document provides MidAmerican Energy
More informationCONSOLIDATED EDISON CO. OF NEW YORK, INC 4 IRVING PLACE NEW YORK, N.Y
CONSOLIDATED EDISON CO. OF NEW YORK, INC 4 IRVING PLACE NEW YORK, N.Y. 10003 EP 7000 5 JULY 2009 VOLTAGE SCHEDULE, CONTROL, AND OPERATION OF THE TRANSMISSION SYSTEM PURPOSE This specification describes
More informationEPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY
EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES COMPANY OVERVIEW EPS is a recognised company specialising in Electrical, Instrumentation, Structural, Mechanical and
More informationGreat Northern Transmission Line: Behind the (Electrical) Design
Great Northern Transmission Line: Behind the (Electrical) Design November 8, 2017 Christian Winter, P.E. Minnesota Power Sivasis Panigrahi, P.E. POWER Engineers, Inc. What is the Great Northern Transmission
More informationPOWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.
POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products
More informationNumbering System for Protective Devices, Control and Indication Devices for Power Systems
Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements
More informationFundamental Concepts of Dynamic Reactive Compensation. Outline
1 Fundamental Concepts of Dynamic Reactive Compensation and HVDC Transmission Brian K. Johnson University of Idaho b.k.johnson@ieee.org 2 Outline Objectives for this panel session Introduce Basic Concepts
More informationATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for Michigan s Eastern Upper and Northern Lower Peninsulas
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for
More informationChapter 7 Conclusion 7.1 General
Chapter 7 7.1 General The mechanical integrity of a transformer winding is challenged by several mechanisms. Many dielectric failures in transformers are direct results of reduced mechanical strength due
More informationNotes 1: Introduction to Distribution Systems
Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission
More informationTexas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event
Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event
More informationBasic Principles and Operation of Transformer
Basic Principles and Operation of Transformer CONSTRUCTIONAL ASPECTS Cores In order to enhance core s magnetic properties, it is constructed from an iron and silicon mixture (alloy). The magnetic core
More informationATTACHMENT - AESO FUNCTIONAL SPECIFICATION
ATTACHMENT - AESO FUNCTIONAL SPECIFICATION Functional Specification Revision History Revision Description of Revision By Date D1 For internal Comments Yaoyu Huang January 8, 2018 D2 For external Comments
More informationDEVELOPMENT OF A TEST PROTOCOL FOR A 15 KV CLASS SOLID-STATE CURRENT LIMITER
DEVELOPMENT OF A TEST PROTOCOL FOR A 15 KV CLASS SOLID-STATE CURRENT LIMITER ABSTRACT Ashok Sundaram Electric Power Research Inc., USA asundara@epri.com The Solid-state Fault Current Limiter (SSFCL) is
More informationProgress Report on Failures of High Voltage Bushings with Draw Leads By Jim McBride and Larry Coffeen, JMX Services / NEETRAC 7/26/2010
The Team: Jim McBride: IEEE Member Larry Coffeen: IEEE Senior Member President, JMX Services, Inc. Senior Research Engineer, NEETRAC BS EE Georgia Tech BS EE Georgia Tech Testing, DAQ, and Measurement
More informationLiquid-Filled Transformers
Liquid-Filled Transformers Custom Transformers at Standard Prices NIAGARA TRANSFORMER CORP. Induction Furnace Transformer Cycloconverter Rectifier Duty Transformer Arc Furnace Transformer Full Range of
More informationTransformer Protection
Transformer Protection Transformer Protection Outline Fuses Protection Example Overcurrent Protection Differential Relaying Current Matching Phase Shift Compensation Tap Changing Under Load Magnetizing
More informationTransformers TRANS FORM ERS
Transformers TRANS FORM ERS Meiden Transformers are standard design, standard quality. Our Factories on world-wide supply chain Since its founding in 1897 Meidensha Corporation has not only built up a
More informationMidAmerican Energy Company 100 kv and Above Facility Ratings Methodology
MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology For NERC Standard FAC-008 and FAC-009 Issued by: Dan Custer Reviewed by: Tom Mielnik Version 2.7 1 1.0 Scope: This document provides
More informationModelling Parameters. Affect on DER Impact Study Results
Modelling Parameters Affect on DER Impact Study Results Agenda Distributed Energy Resources (DER) Impact Studies DER Challenge Study Steps Lessons Learned Modeling Reverse Power Transformer Configuration
More informationValidation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit
Validation of a Power Transformer Model for Ferroresonance with System Tests on a 4 kv Circuit Charalambos Charalambous 1, Z.D. Wang 1, Jie Li 1, Mark Osborne 2 and Paul Jarman 2 Abstract-- National Grid
More informationField Instruction. Induced voltages can occur in overhead lines, underground cables, or in switchyards.
8.3 Induced Voltage Purpose The purpose of this instruction is to provide awareness of Electrostatic and Electromagnetic induced voltages and the method required to reduce or eliminate it. An induced voltage
More informationKansas City Power & Light Company. Transmission Facility Rating Methodology
Company Prepared by: KCP&L Transmission Planning December 6, 2017 Table of Contents 1. Purpose...4 2. Generator Rating Methodology...4 3....4 3.1. Equipment Rating Methodology...4 3.2. Items considered
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee March 9, 2017 2016/17 RTEP Long Term Proposal Window 2 2016/17 RTEP Long Term Proposal Window Timeline Window Opened: 11/1/2016 Window
More informationTransformer energisation after network blackout
Transformer energisation after network blackout Impact on network restoration and improvement of its process ABSTRACT According to ENTSO-E Network policy 5, responsibility for system restoration after
More informationModern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions
1 Transmission transformers are important links in the bulk power system. They allow transfer of power from generation centers, up to the high-voltage grid, and to bulk electric substations for distribution
More informationPomona, CA May 24 & 25, LTC Applications - Location, Series & Preventative Auto Transformers
Pomona, CA May 24 & 25, 2016 LTC Applications - Location, Series & Preventative Auto s siemens.com/answers Introduction Tap changer at active part Example of 3-phase tapchanger Page 2 Winding Configurations
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements
Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system
More informationR10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering)
R10 Set No. 1 Code No: R41023 1. a) Explain how arc is initiated and sustained in a circuit breaker when the CB controls separates. b) The following data refers to a 3-phase, 50 Hz generator: emf between
More informationDietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors
Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors May 11, 2010 Slide 1 Why phase-shifting transformers
More informationEffects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages
Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Waruna Chandrasena, Bruno Bisewski, and Jeff Carrara Abstract-- This paper describes several system
More informationACS 1000 Transformer Failure Investigation. Nathan Schachter, Peng
Investigation Nathan Schachter, Peng Objectives Learn what happened Explain why it happened Discuss solutions Suggest remedies so it does not happen again Prevention is the key to success 2 ACS 1000 VFD
More informationELECTRIC TRANSMISSION (ET) Guideline G0104
ELECTRIC TRANSMISSION (ET) ISSUING DEPARTMENT: ETM x ETEC ETPO ETTS EFFECTIVE DATE: 06-01-1997 DEPARTMENTS AFFECTED: ETM ETEC ETPO x ETTS REVIEW DATE: 01-01-1998 DEPARTMENT GROUP: ALL All All x All P E
More informationBE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %
BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and
More informationNumber: Prepared by: TABLE OF CONTENTS
Prepared by: C. J. McWhirter Issued by: D. J. Papadoulis Date: 30 August 2013 Page 1 of 19 TABLE OF CONTENTS Page 1 INTRODUCTION... 2 2 TRANSMISSION LINES... 2 3 TRANSFORMERS... 6 4 SHUNT REACTORS... 8
More informationFunctional Specification Revision History
Functional Specification Revision History Revision Description of Revision By Date V1D1 For Comments Yaoyu Huang October 27, 2016 V1 For Issuance Yaoyu Huang November 21, 2016 Section 5.3 updated Transformer
More informationPOWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009
POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 Nkosinathi Buthelezi Senior Consultant: Power Transformers and Reactors Presentation Content Standardization of Power
More informationQuanta Technology Advancing the Grid. Flexible AC Transmission System (FACTS) BGE Technology - Application Cases January 4, 2008 Q U A N T A SERVI CES
National Conference of State Legislatures The Forum for America s Ideas April 2011 National Association of Regulatory Utility Commissioners Q U A N T A SERVI CES Quanta Technology Advancing the Grid Flexible
More informationTransformer Technology Seminar What to consider at Design Reviews
Pomona CA, May 24-25, 2016 Transformer Technology Seminar Siemens AG Transformers siemens.com/answers Why to perform Design Review Meetings? To ensure both parties having the same understanding of the
More informationCONSULTANT PROCEDURES & DESIGN GUIDELINES Liquid-Filled Utility Transformers UNIVERSITY OF MISSOURI
GENERAL: The scope of this document is to provide instruction for the installation and testing of Medium Voltage, 3 Phase, Pad Mounted Transformers installed at the University of Missouri. Preferred transformers
More informationMonitoring Solutions For Power Transformers, Reactors, Bushings and Instrument Transformers
in cooperation with Monitoring Solutions For Power Transformers, Reactors, Bushings and Instrument Transformers BZ-MS/1 pazifik power Complete Transformer Monitoring System (TMS) ZVCM-1001 Bushing Monitoring
More informationSmart Wires. Distributed Series Reactance for Grid Power Flow Control. IEEE PES Chapter Meeting - Jackson, MS August 8, 2012
Smart Wires Distributed Series Reactance for Grid Power Flow Control IEEE PES Chapter Meeting - Jackson, MS August 8, 2012 Jerry Melcher Director Program Management Smart Wires Inc. 2 Agenda Technology
More information10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY
9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor
More informationAnalysis of a 405 km transmission line with series compensation
Analysis of a 405 km transmission line with series compensation by Dr. Rupert Gouws, North-West University This paper presents an investigative case study and energy efficiency analysis of the 405 km,
More informationMedium voltage circuit breaker technical guide
IEC 56-1987 - ANSI C37-06 1987 COMPARISON CONTENTS page 1 - Rated voltage 3 2 - Rated isolating level 3 3 - Rated voltage during normal running 4 4 - Allowable short time current 4 5 - Allowable current
More informationFixed Series Compensation
Fixed Series Compensation High-reliable turnkey services for fixed series compensation NR Electric Corporation The Fixed Series Compensation (FSC) solution is composed of NR's PCS-9570 FSC control and
More informationEVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION
EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION David TOPOLANEK Petr TOMAN Michal PTACEK Jaromir DVORAK Brno University of Technology - Czech
More informationEI HIGH VOLTAGE INSULATION TESTING POLICY
Network(s): Summary: ENGINEERING INSTRUCTION EI 09-0001 HIGH VOLTAGE INSULATION TESTING POLICY EPN, LPN, SPN This engineering instruction details the policy for the on-site insulation testing of new and
More informationArtificial Island Proposal Window
Artificial Island Proposal Window PJM TEAC Artificial Island Recommendation 6/16/2014 Artificial Island Timeline Past Timeline 9/13/2012 PJM discusses the trending Artificial Island operational issues
More informationSolving Customer Power Quality Problems Due to Voltage Magnification
PE-384-PWRD-0-11-1997 Solving Customer Power Quality Problems Due to Voltage Magnification R. A. Adams, Senior Member S. W. Middlekauff, Member Duke Power Company Charlotte, NC 28201 USA E. H. Camm, Member
More informationContinuous Monitoring on the SSE Networks Transmission System
10 th Universities High Voltage Network Colloquium 18 th - 19 th January 2017, GCU, Glasgow, Scotland Continuous Monitoring on the SSE Networks Transmission System The Need for Standards, Specifications
More informationInsulation Co-ordination For HVDC Station
Insulation Co-ordination For HVDC Station Insulation Co-ordination Definitions As per IEC 60071 Insulation Coordination is defined as selection of dielectric strength of equipment in relation to the operating
More informationBenefits of SFRA - Case Studies
6 th International Conference on Large Power Transformers- Modern Trends Benefits of SFRA - Case Studies B B Ahir Gujarat Energy Transmission Corporation Limited 1 Outline Condition Monitoring in GETCO
More informationBipole III Transmission Project
Bipole III Transmission Project Clean Environment Commission Public Hearings Fall 2012 System Planning Ronald Mazur BP III Keewantinoow Limestone Kettle Kelsey Jenpeg Grand Rapids OVERVIEW Transmission
More informationMOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE
MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE Scott Storrar Contributors: Bill Hansen, Kyle Reddell, Tom McGrath Basic Mobile Sub Design Equipment mounted on semi-trailer Power transformer
More informationTECHNOLOGIES FOR TOMORROW
TECHNOLOGIES FOR TOMORROW Development of large-capacity, 3-phase, 500kV that is disassembled for shipment and reassembled at the site 1. Introduction In order to maintain the quality verified by testing
More informationFGJTCFWP"KPUVKVWVG"QH"VGEJPQNQI[" FGRCTVOGPV"QH"GNGEVTKECN"GPIKPGGTKPI" VGG"246"JKIJ"XQNVCIG"GPIKPGGTKPI
FGJTFWP"KPUKWG"QH"GEJPQNQI[" FGRTOGP"QH"GNGETKEN"GPIKPGGTKPI" GG"46"JKIJ"XQNIG"GPIKPGGTKPI Resonant Transformers: The fig. (b) shows the equivalent circuit of a high voltage testing transformer (shown
More informationTransformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications
The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications Minnesota Power Systems Conference November 3 5, 2009 Earl Brown Heritage Center University of
More informationSub Regional RTEP Committee South
Sub Regional RTEP Committee South June 9, 2017 Subregional RTEP (SRRTEP) Meeting Format Update Response to stakeholder feedback Today s Presentation approach First Review (baseline and supplemental by
More informationBC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014
BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014 Expiry Year: 2018 APPROVED BY: Original signed by: Paul
More informationCoil Products Beginnings 1960 State of the Art. Customer partnership around the globe. Continuous innovation since 1900
Coil Products Coil Products Customer partnership around the globe More than 250,000 coil products delivered to more than 170 countries. More than 60 years of operational experience. 35,000 in Europe 13,000
More information2. Current interruption transients
1 2. Current interruption transients For circuit breakers or other switching facilities, transient voltages just after the current interruptions are of great concern with successful current breakings,
More informationFerroresonance Conditions Associated With a 13 kv Voltage Regulator During Back-feed Conditions
Ferroresonance Conditions Associated With a Voltage Regulator During Back-feed Conditions D. Shoup, J. Paserba, A. Mannarino Abstract-- This paper describes ferroresonance conditions for a feeder circuit
More informationSouthern Company Interconnection Requirements for Inverter-Based Generation
Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection
More informationSERVICE OFFERINGS FOR POWER SYSTEM STUDY & CONDITION MONITORING FOR STATIC EQUIPMENT
SERVICE OFFERINGS FOR POWER SYSTEM STUDY & CONDITION MONITORING FOR STATIC EQUIPMENT Page TABLE OF CONTENTS POWER SYSTEM STUDY: 5 DATA COLLECTION AND NETWORK MODELLING 5 LOAD FLOW STUDY 5 SHORT CIRCUIT
More informationNew HVDC Interaction between AC networks and HVDC Shunt Reactors on Jeju Converter Stations
New HVDC Interaction between AC networks 233 JPE 7-3-6 New HVDC Interaction between AC networks and HVDC Shunt Reactors on Jeju Converter Stations Chan-Ki Kim, Young-Hun Kwon * and Gil-Soo Jang ** KEPRI,
More informationCOPYRIGHTED MATERIAL. Index
Index Note: Bold italic type refers to entries in the Table of Contents, refers to a Standard Title and Reference number and # refers to a specific standard within the buff book 91, 40, 48* 100, 8, 22*,
More informationSingle Line Diagram of Substations
Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission lines are
More informationKNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers
KNOW MORE ABOUT THE TRANSFORMERS Glossary Transformers Ambient temperature The existing temperature of the atmosphere surrounding a transformer installation. Ampere The practical unit of electric current.
More informationHarmonics Issues that Limit Solar Photovoltaic Generation on Distribution Circuits
WREF 01 Paper # 048 Harmonics Issues that Limit Solar Photovoltaic Generation on Distribution Circuits Ketut Dartawan Ricardo Austria, Le Hui and Mark Suehiro* Pterra Consulting Maui Electric Company*
More informationReport on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL)
Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL) 1.0 Introduction: 1.1 DTL vide letter No. F.DTL/206/F.06/2015-16/Mgr(Bawana)/353 dated
More informationAmtrak s 138 kv Transmission System that supplies traction power to electric locomotives traveling on the
Word Count: 3039 Replacement of Amtrak s 138 KV Cable through the Baltimore Tunnels Raymond G. Verrelle, PE Amtrak Engineering Department 30 th St. Station, 4 th Floor South Fourth Floor, South Tower Philadelphia,
More informationDelayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines
Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines David K Olson Xcel Energy Minneapolis, MN Paul Nyombi Xcel Energy Minneapolis, MN Pratap G Mysore Pratap Consulting Services,
More informationROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT
ROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT Page 1 of 8 The document describes the current methodology used for developing facility ratings
More informationDYNAMIC PERFORMANCE OF THE EAGLE PASS BACK-TO-BACK HVDC LIGHT TIE. Å Petersson and A Edris ABB Power Systems AB, Sweden and EPRI,USA
DYNMI PERFORMNE OF THE EGLE PSS K-TO-K HVD LIGHT TIE Å Petersson and Edris Power Systems, Sweden and EPRI,US INTRODUTION Eagle Pass ack-to-ack (t) Tie is a Voltage Source converter (VS) -based tie interconnecting
More informationATC s Mackinac Back to Back. Summary
ATC s Mackinac Back to Back HVDC Project Update Michael B. Marz American Transmission Company Summary The Need For Flow Control at Mackinac Mackinac Flow Control Requirements Available Flow Control Technologies
More informationDesigning For a Critical Load using a Spot Network
This is a photographic template your photograph should fit precisely within this rectangle. Designing For a Critical Load using a Spot Network Tony Oruga, P.E. Product and Sales Manager Network Protectors
More informationMidAmerican Energy Company 100 kv and Above Facility Ratings Methodology
MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology For NERC Standard FAC-008-3 Version 3.4 1 Contents 1. Scope... 3 2. Establishment and Communication of Facility Ratings:... 3 2.1.
More informationEvaluation of coupling between dc and ac transmission lines on the same right-of-way: Parametric analysis and mitigation methods
Abstract: Evaluation of coupling between dc and ac transmission lines on the same right-of-way: Parametric analysis and mitigation methods Jingxuan (Joanne) Hu RBJ Engineering Corp. Winnipeg, MB, Canada
More informationMechanical Design. Brian Brinson Mechanical Design Manager.
Mechanical Design Brian Brinson Mechanical Design Manager brian.brinson@spx.com September 26, 2018 Agenda 1. Design Process 2. Pre-Approval Drawings Bid Drawings Preliminary Drawings 3. Approval Package
More informationITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/
ITC Holdings Planning Criteria Below 100 kv * Category: Planning Type: Policy Eff. Date/Rev. # 12/09/2015 000 Contents 1. Goal... 2 2. Steady State Voltage & Thermal Loading Criteria... 2 2.1. System Loading...
More informationHow to maximize reliability using an alternative distribution system for critical loads
White Paper WP024001EN How to maximize reliability using an alternative distribution system for critical loads Executive summary The electric power industry has several different distribution topologies
More information