1 RENOVATION OF THE FARMERS MARKET Reference Number: A D D E N D U M NO. 1 The following shall form part of the tender documents issued by the City of Guelph s Purchasing Department, June, NOTE: the acknowledgement of this addendum must be indicated on FT2R DELETE ADD Pages FT1 FT5 Pages FT1R FT5R (attached) DRAWINGS AND ANY RELATED INFORMATION The bidder shall verify that these Contract documents are complete and assume responsibility to view/download/print the drawings, specifications and any related information not sent with this document. You are required to go to the City s website where under the description of this contract you will find links to the drawings, specifications and any related information not sent with this document. Shortages shall be reported to the Engineer immediately. It will be your responsibility to make sure that when you print any drawings/sketches/etc that they are printed to scale. The following addition, deletions and amendments are hereby made a part of the Specifications and Drawings for the above referenced Contract. ADD the following drawings SKA-01 Vestibule ADM-1 Existing Ground Floor Plan ADM-2 Ground Floor Plan ADM-3 Ground Floor Plan Plumbing ADE-1 Part Ground Floor ADE-2 Alternate Price ADE-3 Part Ground Floor/Alternate Price ADE-4 Part Ground Floor/Alternate Price ADE-5 Alternate Price D-1 Island Millwork Detail 1
2 CLARIFICATION Q1: Does the ceiling get painted? A1: No the ceiling does not get painted. Q2: Who is responsible for digging out the trench for the sanitary? A2: The mechanical contractor is responsible for digging out the trench and is to be included in the tender GC is responsible to patch the concrete as required. Q3: Who is responsible for the roof venting for the mechanical? A3: The Mechanical contractor is to provide the roof vents and the GC is to have the roofing company put them in. Q4: How man RFP panels are provided to the contractor? A4: As per the drawings there are 175 provided to the contractor including fasteners and dividing connections. ARCHITECTURAL SPECIFICATIONS Specification Section Interior Specialties 1.1 Page 2; item 2.2. (List and Description of Product). Add to read: Approved alternates;.1 Stanley Magic Access Operator visible application..2 Dor-o-matic Benchmark Swing operator..3 SW100 By Besam Specification Section Painting 2.1 A note to be added that the interior brick veneer walls have been blasted by the owner and that portion of the surface preparation is not to be included in the contractors base bid. The patching of the brick veneer walls only will also be completed by the owner and not to be included in the contractors base bid. 2
3 ARCHITECTURAL DRAWINGS Reference Drawing SP-1 Site Plan 1.1 Remove the note on parking stalls 4 parking 2.75 m each c/w new painted parking lines. 1.2 Revise the note on the building from Existing and Addition)Area:1073 sqm to Existing building Area: 1040 sqm) 1.3 Remove the zoning requirements for the Designated accessible parking space size. Reference Drawing A-110 Floor Plan 2.1 Provide separate price for replacing the existing doors and frames for doors # 1, 2 in Vestibule 101 and doors 3 and 4 in Vestibule 102. Refer to SKA-01 attached for details. Item 3.0 Reference Drawing A-111 Floor Finish Plan 3.1 Remove the integral cove base for the both entrance Vestibules 101 and 102. Item 4.0 Reference Drawing A-401 Elevation and Miscellaneous Details 4.1 Include the noted new H.M. doors and frames c/w tempered safety glass in Separate Price. Item 5.0 Reference Drawing A-601 Schedules 5.1 Door and Frame Schedule: Provide a Separate Price as instructed in the Bid Form for replacing the existing doors and frames with new painted H.M. doors and frames c/ w tempered Safety Glass, for Doors # 1,2,3, Door and Frame Schedule: Provide a Separate Price as instructed in the Bid Form for providing Automatic Door Operator and Push Buttons for Doors # 3, and 4. Refer to Specification Section Interior Specialties for the approved Barrier Free Door Operator s Manufacturers. 5.3 Door Hardware Schedule: Provide as Separate Price for providing the new hardware for Doors # 1,2,3,4. Hardware to include: - Panic Device by: Von Duprin - Hinges by: Stanley Hinge Company - Closer by: Sargent - Kick Plate by: Sargent - Weather strips by: Sargent - Threshold by: Sargent 5.4 Refer to SKA-01 attached for details. 3
4 Item 6.0 Reference Drawing A-110 Floor Plan optional millwork and detail D To include Formica laminate countertop and the box is constructed from white melamine. The detail shows an example of a 2 section. To be in large sections as per the floor plan. Item 7.0 Reference Drawing A-111 Floor Finish Plan Saw Cutting 7.1 Note 8 to read All the required saw cutting in the existing concrete floor for drainage and end post partition insertion into floor to be completed by the Owner. Contractor is to provide pouring/patching of concrete flooring, and to prepare the floor to accept the new epoxy (Stonclad GS with Stontec System) finish. MECHANICAL (FOR YOUR REFERENCE TO BE INCLUDED IN MECHANICAL TENDER ) Reference Drawing M-101 and Attached Sketch ADM Revise floor plan to keep existing Office Area. 1.2 Revise Alternate Price for existing washrooms to remove and reinstall existing exhaust fans only. The removal and reinstallation of plumbing fixtures to be base bid. 1.3 Revise existing 3" diameter sanitary piping running through Units to be capped and abandoned in place. Refer to sketch ADM-1. Reference Drawing M-201 and Attached Sketch ADM Delete Alternate Price note for existing washrooms. Reinstallation of existing plumbing fixtures to be base bid. 2.2 Revise 1½" diameter sanitary piping serving S-1 in Unit 23 to suit revised floor plan as per ADM Delete items A and B in General Notes in their entirety. Item 3.0 Reference Drawing M-202 and Attached Sketch ADM Revise 1½" diameter hot and cold water piping serving S-1 in Unit 10 to be a rough-in only for future sink. Do NOT include fixtures for this unit. 3.2 Revise existing ½" diameter hot and cold water piping serving S-1 in Unit 23 to suit revised floor plan as per sketch ADM-3. Item 4.0 Reference Drawing M Revise item S-1 in plumbing fixture schedule as follows: Fixture manufacturer model: Glacier Bay W-GB No alternates. Fixture description: Single compartment, self-rimming vanity, vitreous china, integral overflow, undercoated, clamps. 4
5 Overall sizes: 514 mm x 434 mm x 184 mm (20¼" x 17⅞" x 7¼"). Home Depot product number: Item 5.0 Reference Drawing M Delete item 25 from Part A of mechanical specification in its entirety. 5.2 Delete item 26 for Part A of mechanical specification in its entirety. 5.3 Revise item 6 from Part B of mechanical specification to include CPVC (Flow Guard) and PEX-a (Wirsbo/Uponor) as acceptable materials for domestic water piping in lieu of type L copper pipe. CPVC and PEX-a piping must meet the same inside dimensions of the equivalent trade size of type L copper pipe. If CPVC or PEX-a have a smaller inside diameter than type L copper, the next trade size larger must be used. 5.4 Revise item 6 from Part B of mechanical specification to include System 15 PVC as acceptable material for above grade sanitary and vent piping. ELECTRICAL Reference Drawing E101 and Attached Sketches ADE-1 and ADE In existing Office and Washroom Areas, revise devices and associated notes as per sketch ADE Add alternate price plan as per sketch ADE-2. Reference Drawing E201 and Attached Sketch ADE In Office 103, revise fixture type as per sketch ADE Add alternate price plan as per sketch ADE Revise note #2 to read: Note not used. 2.4 Add fixture type F8 to light fixture schedule as per sketch ADE-3. Item 3.0 Reference Drawing E301 and Attached Sketch ADE On Office 103, Meeting Room 105, and existing Washroom Area, revise devices as per sketch ADE Add alternate price plan as per sketch ADE Revise notes #6 and #8 to read: Note not used. 3.4 Revise note10 to read: Indicates Data rack. Item 4.0 Reference Drawing E401 and Attached Sketch ADE-5 5
6 4.1 In fire alarm systems specification section, delete item # Add identified pricing section to electrical specification as per sketch ADE-5. End of Addendum #1. 6
Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017.
!!! Addendum EXP Project No: MTA Project No: WIND-17-01 Project: Windsor Hall Renovations October 12, 2017 Addendum No: 3 The following information supplements and/or supersedes the bid documents. This
More informationADDENDUM #1. April 29, 2009
April 29, 2009 Re: HACC, Central Pennsylvania s Community College Midtown 1 CCTA Phase 2 Solicitation # 09-17 From: Eastern pcm, LLC Construction Manager HACC 212 Locust Street, Suite 604 Harrisburg, PA
More informationADDENDUM NOTICE INTERIOR RENOVATIONS AT THE BATHURST CLARK RESOURCE LIBRARY, 900 CLARK AVENUE WEST, VAUGHAN, ON
The City of Vaughan Procurement Services Department 2141 Major Mackenzie Drive Vaughan, ON L6A 1T1 Tel (905) 832-8555 ADDENDUM NOTICE ADDENDUM NO. 3 Total of (5) page BID NO. T18-003 DESCRIPTION: INTERIOR
More informationHIA AIR CARGO HAMILTON ADDENDUM #3. Addendum No. A03 (Architectural) o Text 1 page o SK-10a o SK-10b o SK-11
HIA AIR CARGO HAMILTON ADDENDUM # (This Addendum consists of six () pages) Cover sheet Schedule time lines for Architectural Precast, Miscellaneous Metals, Insulated Metal Panels, Roofing and Aluminum
More informationARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI)
ARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI) PROJECT: Villa Joseph Marie High School - Auditorium Addition ARCHITECTS PROJECT NO: 2339 ASI NO: 001 DATE OF ISSUANCE: 12/5/2017 TO: Twining Construction Co.
More informationBidding Trades shall bring this Addendum to the attention of all sub-trades and suppliers from whom they may be receiving quotations.
Addendum No. 3 Re / Objet: Phase Two Espanola High School Redevelopment Project 147 Spruce Street Espanola, ON YBA Project No.: 1323 `The following information, amendments and revisions shall constitute
More informationRENOVATION TO STUDENT SERVICES/HOUSING FROM HOSPITAL DAKOTA STATE UNIVERSITY MADISON, SOUTH DAKOTA
RENOVATION TO STUDENT SERVICES/HOUSING FROM HOSPITAL DAKOTA STATE UNIVERSITY MADISON, SOUTH DAKOTA KOCH HAZARD ARCHITECTS ADDENDUM DATE:. SCOPE OF THIS ADDENDUM: The following becomes a part of the original
More informationADDENDUM NO. 2. The Bid Opening has not changed it remains December 8, 2016 AT 1:30 P.M.
ADDENDUM NO. TO: PLANS AND SPECIFICATIONS FOR STATE OF MISSOURI Health Center Renovation Missouri School for the Blind NO. E60-0 The Bid Opening has not changed it remains December 8, 06 AT :30 P.M. GENERAL
More informationHAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA
HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: 08012.00 SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA ADDENDUM NUMBER 1 to the BID SET August 10, 2009 General This Addendum will become part
More informationIntroduction. Classifications of piping: Industrial. Residential (i.e., plumbing) Carries liquids and gases used in the manufacture of products
Plumbing Plans Introduction Classifications of piping: Industrial Carries liquids and gases used in the manufacture of products Residential (i.e., plumbing) Carries fresh water, gas, liquid, solid waste
More informationADDENDUM #2 September 12, 2018
Physical Plant Services Project Management 1000 Rim Drive Phone: (970) 247-7523 Fax: (970) 247-7555 Project No. 2007-130P18 Whalen Gymnasium Expansion and Renovation for Exercise Science Request for Qualifications
More informationDecember 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions
December 31, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y16-721-MM / ADDENDUM No. 1 ORANGE COUNTY CONVENTION CENTER PHASE III VALENCIA BALLROOM RENOVATION Bid Opening Date: January 12, 2016
More informationADDENDUM No. 4 Page 1 of 8 (includes attachment)
ADDENDUM No. 4 Page 1 of 8 (includes attachment) Date Issued: November 27, 2017 Project: TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J
More informationGRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO
PAGE PROJECT NO. 0-0 0 0 0 0 0 DATE: PROJECT: GATEWAY STEM ATHLETICE FIELD ALTERATIONS GATEWAY STEM HIGH SCHOOL - ST. LOUIS PUBLIC SCHOOLS 0 MCRTEE AVENUE ST. LOUIS, MISSOURI 0 TO BID DOCUMENTS DATED DECEMBER,
More informationNotre Dame High Addition/Renovation Addendum 3 Page 1
School Notre Dame High Addition/Renovation Addendum 3 Page 1 PROJECT: Notre Dame High School Addition/ Renovation Calgary. Alberta DATE November 15, 2012 ADDENDUM NO. 3 Attachment pages Addendum: Page(s)
More informationMarshall Truck Station Laboratory Addition Project No. TZ MnDOT
Marshall Truck Station Laboratory Addition Project No. TZ-91523 MnDOT 13-6574 ADDENDUM NUMBER 2 DATED September 19, 2013 Marshall Truck Station Laboratory Addition Project No. TZ-91523 MnDOT 13-6574 Architect:
More informationADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC.
ADDENDUM NO. 2 PROJECT: OWNER: ENGINEER / ARCHITECT: PROJECT LOCATION: Saginaw County Community Mental Health Authority Germania Club Renovation Phase 2 Saginaw County Community Mental Health Authority
More informationADDENDUM THREE SPECIFICATIONS. Vincennes University Renovations of the Curtis G. Shake Learning Resources Center
ADDENDUM THREE Addendum Three (AD.03) to the drawings and specifications prepared by Gibraltar Design for Curtis G. Shake Learning Resources Center for Vincennes University, Vincennes, Indiana. All Contractors
More information12560 W. Cedar Drive Lakewood, CO Barry Himmelman President
Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 16-BS-2260 ADDENDUM NUMBER FOUR January 8, 2016 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM
More informationWayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009
ADDENDUM NO 2 OWNER: Wayne State University DATE: January 4 th, 2019 PROJECT: NM Project Number: 18113.0 ARCHITECT: ENGINEER: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009 IMEG 26200 Town
More informationAnswer: Only to ChurchWoods, LLC.
ADDENDUM ADDENDUM NO.: 3 DATE: 06/27/16 PROJECT: CHW ChurchWoods PROJECT ADDRESS: 4130 Old Post Road Charlestown, RI TO: All Bidders of Record: This Addendum forms a part of and modifies the bidding requirements
More informationSUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5. February 25, 2013
SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5 February 25, 2013 Owner: Architect: Administrative Office of the Courts 2860 Gateway Oaks Drive, Suite 400 Sacramento,
More informationKidsAbility Guelph Hub Renovation ADDENDUM #2 Project No.:
KidsAbility Guelph Hub Renovation ADDENDUM #2 This Addendum amends and forms part of the Bidding and Contract Documents for the above Project as follows: CLARIFICATIONS Q1. Is it possible to set up a secondary
More informationCS2.0 COVER SHEET VOL. 2
ARCHITECT GEORGE CROMWELL ELEMENTARY SCHOOL REVITALIZATION 525 Wellham Avenue Glen Burnie, Maryland 21061 OWNER ANNE ARUNDEL COUNTY PUBLIC SCHOOLS 9034 FT. SMALLWOOD ROAD PASADENA, MARYLAND 21122 tel:
More informationThe following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents, Inquiry No. 17-WDI-031.
ADDENDUM NO. 2 April 11, 2017 Page 1 The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents,. These Exhibits are re-issued in their entirety, unless
More informationADDENDUM NO. 1 November 10, 2016
COUER D ALENE CITY HALL PROJECT NO. 2016-009 REMODEL AND ADDITION COEUR D ALENE, IDAHO ADDENDUM NO. 1 November 10, 2016 This addendum is hereby incorporated into and is an integral part of the bidding
More informationADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION
July 6, 2011 City of Miami Fire Station #13 ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION This Addendum is issued to modify the previously issued Bidding and Contractual Documents,
More information1.01 NOTICE TO BIDDERS
ADDENDUM NO. 1 1.01 NOTICE TO BIDDERS A. Date: 15 March 2013 B. From: Bahr Vermeer and Haecker Architects, Ltd. C. To: Prospective Bidders. D. Project: Lexington Public Schools Lexington Middle School
More informationDIVISION Hardware
FORMAT 1. Technical specifications content and numbering system shall be based on the most current CSI Master Format. BASIS OF DESIGN 1. APSU design standards shall not replace fully developed, project
More informationAddendum #1 - Bid Package #
Addendum #1 - Bid Package #6929-08 Project Name: Lincoln Public Schools District Office 5901 O Street Lincoln, NE Project No.: 11065 Issued: September 18, 2012 This Addendum is issued by Hampton Construction
More informationCHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT
1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department August 11, 2010 Addendum No. 2 INVITATION FOR BID NO.: 11-07 Industrial Technology Center, Buildings 1400/1600
More information.2 Section Steel Doors and Frames.1 Item 1.6 Delete for ten (10) years respectively. and replace with for two (2) years respectively.
École Secondaire Publique Odyssée New Childcare Centre, Site and Interior Renovations Conseil scolaire public du Nord-Est de l Ontario Project No. 1819 SECTION 00 54 13 ADDENDUM NO. 2 Issued July 4, 2018
More informationResidential Construction Checklist Single and Two Family Construction
DATE: _ Building Inspection Submittal Requirements Residential Construction Checklist Single and Two Family Construction Submit a City of Big Spring Permit Application, checklist, and 3 complete hard copy
More informationSpecifications: Other: sign in sheet
To: All Vendors Bidding on The College of New Jersey Nursing Simulation Lab Fit-Out Project From: Roselle Horodeski Finance & Business Services Date: July 29, 2015 ADDENDUM NO. 1 ISSUE DATE: July 29, 2015
More informationMSU Barnard Hall 105 Cleanroom Installation PPA # Page 1
ADDENDUM NUMBER 1 DATE: February 10, 2017 PROJECT: MSU Barnard Hall Room 105 Cleanroom Installation PPA# 16-0002 (Consulting Design Solutions, Inc. Project # 1613) BID DATE: February 23, 2017 2:00 PM,
More informationPOST BID ADDENDUM TWO
POST BID ADDENDUM TWO DATE: March 4, 2016 PROJECT: Ingham County Human Services Building Renovation Packet No. 96-15 PROJECT #: 14-614 This Addendum is issued for the purpose of modifying and/or clarifying
More informationHAMMEL ASSOCIATES ARCHITECTS, LLC 2 5 E A S T G R A N T S T R E E T, S U I T E L A N C A S T E R, P E N N S Y L V A N I A
CHL ASSOCIATES ARCHITECTURE 1 5 7 0 R I V E R R O A D, M A R I E T T A, P E N N S Y L V A N I A 1 7 5 4 7 HAMMEL ASSOCIATES ARCHITECTS, LLC 2 5 E A S T G R A N T S T R E E T, S U I T E 1 0 2 L A N C A
More informationTELEPHONE: (215) Addendum No. 1
THE SCHOOL DISTRICT OF PHILADELPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, Third Floor - Suite 371 Philadelphia, PA 19130-4015 TELEPHONE: (215) 400-4730 Addendum No.
More informationMontclair, NJ ADDENDUM NO. 1 Issue Date: May 15, 2017
Montclair, NJ 0704 ADDENDUM NO. Issue Date: May 5, 207 Request for Proposal # 294 Building 47 West Renovation- Phase 6a Number of Pages: 2 plus 5 sketches Date of Original Bidding Documents: April 26,
More informationCHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT
1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department October 25, 2010 Addendum No. 09.R INVITATION FOR BID NO.: 11-05 Modernization of Classroom Building 300 Chabot
More informationCity of St. Charles School District New Addition and Renovation at George M. Null Elementary School 435 Yale Boulevard St. Charles, Missouri 63301
City of St. Charles School District 435 Yale Boulevard St. Charles, Missouri 6330 ADDENDUM #2 Date: April 03, 209 Prepared or: City of St. Charles School District Project Number: 709 Architect: Dickinson
More informationA. This Section includes plumbing fixtures and related components.
SECTION 224200 PLUMBING FIXTURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationNovember 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT
November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y18-703-CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT REVISED BID OPENING DATE: DECEMBER 5, 2017 This addendum is hereby incorporated
More informationCHAPTER 5 ARCHITECTURE
CHAPTER 5 ARCHITECTURE 5.1 GENERAL... 4 5.2 CONCEPT/PROJECT DEFINITION DESIGN (30%) SUBMITTAL REQUIREMENTS... 4 5.2.1 DESIGN ANALYSIS... 4 5.2.1.1 Design Criteria... 4 5.2.1.2 Narratives... 4 5.2.1.2.1
More informationCabinet Planning Guide
Cabinet Planning Guide After all the thinking, dreaming and planning, the time has come to get started. The following workbook will assist you with the information you need to start the process. Complete
More informationADDENDUM NO. 4 November 15, Page 1
ADDENDUM NO. 4 November 15, 201 8 Page 1 PROJECT MANUAL FOR CONSTRUCTION OF HVAC REPLACEMENT FOR NORTH OCONEE HIGH SCHOOL FOR OCONEE COUNTY SCHOOLS WATKINSVILLE, GEORGIA DATED: SEPTEMBER 14, 2018 CUNNINGHAM,
More informationThe following information supplements and/or supersedes the bid documents issued on July 10, 2017.
Addendum No. 02 ADDENDUM Pages 2 Project No. 1706 Date: July 21, 2017 Project: West End Lofts 44 MacDonald Street, Arnprior, ON The following information supplements and/or supersedes the bid documents
More informationCHAPMAN GRIFFIN LANIER SUSSENBACH ARCHITECTS, INC. ARCHITECT S ADDENDUM NO. 06
CGLS A R C H I T E C T S CHAPMAN GRIFFIN LANIER SUSSENBACH ARCHITECTS, INC. 2500 Cumberland Parkway Suite 350 Atlanta, Georgia 30339 404.733.5493 (voice) 404.733.6804 (fax) www.cglsarchitects.com ARCHITECT
More information2. All work and materials shall be in full accordance with Local and State ordinance and with any prevailing rules and regulations.
General Conditions: 1. Deliver all food service equipment as specified herein, including that which is reasonably inferred, with all related items necessary to complete work shown on contract drawings
More informationADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016
ADDENDUM NO. 1 DATE: MARCH 1, 2016 PROJECT: ARCHITECT: TO: 2017 BAND ADDITION, ROOF REPLACEMENT AND AIR-CONDITIONING WORK ROCK FALLS HIGH SCHOOL 101 12 TH STREET ROCK FALLS, IL 61071 BCA PROJECT NO. 1620
More informationChuck Caesar. VIA: /Webposting April 27, 2017
VIA: Email/Webposting April 27, 2017 O Haver Contractors 12831 O Connor Road San Antonio, TX 78233 Telephone 210-590-2889 Fax 210/657-5888 Attn: John Zamoyski, Project Manager Email johnz@ohcltd.net John
More informationNIAGARA REGIONAL HOUSING MZE FILE NO
M A C D O N A L D Z U B E R E C E N S S L E N A rch it ects I nc. NRH NEW DEVELOPMENT PROJECT 527 CARLTON ST., ST. CATHARINES, ONTARIO NIAGARA REGIONAL HOUSING MZE FILE NO. 16-44 Project No. 16-44 April
More informationBIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D
HOSKINS ARCHITECTURE, LLC 1721 4 th AVENUE NORTH, SUITE 101 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 7 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS
More informationFinish Hardware. Contents. Section 10
Section 10 Finish Hardware Contents 10.0.0 Introduction to contents 10.1.0 Door hinges (types and illustrations) 10.2.0 Locksets and latchset configurations and functions 10.3.0 Heavy-duty mortise cases,
More informationADDENDUM ADDENDUM NO.: 01 PROJECT NO.: CONTRACT NO.: DATE OF ISSUE: January 12, 2018
ADDENDUM ADDENDUM NO.: 0 PROJECT NAME: Williams Park Fieldhouse PROJECT NO.: 320 CONTRACT NO.: C593 DATE OF ISSUE: January 2, 208 NOTICE OF CHANGES, MODIFICATIONS, OR CLARIFICATIONS TO CONTRACT DOCUMENTS
More informationSECTION PROJECT COORDINATION VIA BIM
SECTION 01 31 13 PROJECT COORDINATION VIA BIM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationADDENDUM #01. PROJECT: Saint Mary s University Student Centre Reorganization PROJECT N o : DATE:
ADDENDUM #01 PROJECT: Saint Mary s University Student Centre Reorganization PROJECT N o : 2018-04600 DATE: 2018.04.27 This Addendum shall be considered part of the specifications for the construction of
More information(Full legal name of business submitting the offer)
Procurement Services Addendum # 1 Proposal Request Date Printed Date Issued Procurement Officer Phone E-Mail Address 18-CMG-B-012 April 16, 2018 April 16, 2018 Raymond Jenkins 843-566-8826 raymond_jenkins@
More information.1 Comply with the General Conditions of the Contract, Supplementary General Conditions and the requirements of Division 1.
PAGE 1 PART 1 GENERAL 1.1 REFERENCE.1 Comply with the General Conditions of the Contract, Supplementary General Conditions and the requirements of Division 1. 1.2 RELATED WORK SPECIFIED ELSEWHERE.1 Installation
More informationB. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.
McKee and Associates Architecture and Interior Design Addendum No. THREE Date: 12.11.17 Project: A NEW BUILDING FOR THE GREATER LIMESTONE COUNTY CHAMBER OF COMMERCE ATHENS, ALABAMA A3.1 GENERAL PROJECT
More informationDivision 08. Openings
Division 08. Openings 08 10 00. Doors and Frames 08 11 00. Metal Doors and Frames 1. All fire rated doors shall be metal. 2. Contractors shall remove all rating labels from doors/frames that are not installed
More informationWALKS AND SIDEWALKS REQUIREMENTS:
DOUBLE PARKING STALLS DIAGONAL PARKING STALLS EXTERIOR ROUTES OF TRAVEL: From accessible parking spaces, provide most practical direct accessible route of travel to all building entrances and exteriorground
More informationThis is being reviewed, additional comment to follow Marmoleum tile has been removed and replaced with a biobased VCT.
Dr. Checks Comment Responses Review: 100% Building Package B Review Project: (G168476) Ft. Gillem, Enclave Force Protection Latest Update: 03-03-2010 8:30 am 1. 3079320 We will coordinate and add to the
More informationHOENER ASSOCIATES INC. ARCHITECTS
HOENER ASSOCIATES INC. ARCHITECTS BRUCE D. DELL MARK REUTHER ADDENDUM NO. 1 PROJECT 15-22C RENOVATION AND SITE WORK AT: BUILDING B DDRB OF ST. CHARLES DEVELOPMENT DISABILITIES RESOURCE BOARD ST. CHARLES,
More informationMusic Area Casework General 1.01 Summary Related Sections Definitions Qualifications and Quality Assurance
1.00 General 1.01 Summary Music Area Casework A. This section includes the following Scope of Work as referred to in the plans: 1. Thermally Fused Laminate manufactured casework, for use in music areas,
More informationNEW SEVICE CENTER BOB HART CHEVROLET. 495 S. 7th St. E:\RE Smith New Logo.jpg VINITA, OK RE SMITH BOB HART CHEVROLET NEW SERVICE CENTER
NEW SEVICE CENTER VINITA, OK 70 9 S. 7th St. VINITA, OK 70 06 W. 2nd St., Joplin, MO 680 Phone: 7-62- Fax: 7-782-678 GENERAL G0.0 COVER CIVIL C.0 SITE DEMO C. SITE PLAN C.2 GRADING PLAN (FORTHCOMING) ARCHITECTURAL
More informationDimension Below are the critical settings in AutoCAD. Other software should follow the same settings.
8.1 Drawing Standard 8.1.1 Introduction This drawing standard applies to all building drawings being prepared for the University of Calgary (UCalgary) by external consultants or vendors and internal staff
More informationADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030
ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO. 2018-008-COM.00030 To: Prospective Bidders of Record Date: January 8, 2019 The following changes, additions, revisions, and/or deletions
More informationDOCUMENT NARRATIVE PETSMART # 3131 GREEN VALLEY SAHUARITA, ARIZONA Construction Change Directive #1 (CCD-1) / September 22, 2017
These documents, indicated as Construction Change Directive #1 with a delta - 1, supersede the previous issue and should be inserted into the Construction Documents. The tags in the column indicate which
More informationSECTION PLUMBING FIXTURES
SECTION 224000 - PLUMBING FIXTURES PART 1 - GENERAL 1.1 SUMMARY A. This Section includes 1. Faucets for lavatories and sinks. 2. Flushometers. 3. Toilet seats. 4. Protective shielding guards. 5. Fixture
More informationFAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014
FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services ADDENDUM #4 December 5, 2014 This Addendum is issued to provide answers to questions from potential bidders
More information1.1 The Bid Date has changed to October 4, The time and place will remain the same.
Addendum Number Four To The Drawings and Specifications for Pleasant Valley Elementary School Wichita, Kansas Issued: Wednesday Wichita Unified School District # 259 Project No. 12-25077 HANNEY & ASSOCIATES
More informationExcavating, Backfilling, and Compaction for Utilities Piping (Plumbing).
SECTION 15047 - IDENTIFICATION PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Identification including necessary accessories indicated on Construction Documents and specified in this section or as required
More informationFebruary 18, Re: Zephyr Lakes Amenity Center Zephyrhills, Florida
February 18, 2019 Re: Zephyr Lakes Amenity Center Zephyrhills, Florida These are the responses to the RFIs received by 2:00 PM on Monday, February 11, 2019. All items that are not answered in the following
More informationD. Product Certificates: Signed by manufacturers of casework certifying that products furnished comply with requirements.
SECTION 12356 - CASEWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,
More informationADDENDUM TO THE CONTRACT. for the GLACIER FIRE STATION KITCHEN AND CLASSROOM RENOVATION. Contract No. E16-181
ADDENDUM TO THE CONTRACT for the ENGINEERING DEPARTMENT GLACIER FIRE STATION KITCHEN AND CLASSROOM RENOVATION Contract No. E6-8 ADDENDUM NO.: ONE CURRENT DEADLINE FOR BIDS: May 9, 206 PREVIOUS ADDENDA:
More informationREVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty
HOT AISLE CONTAINMENT SYSTEM (HACS) REVISION #1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. B. C. Drawings and general provisions of the Contract, including General and Supplementary. Conditions apply to
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM SOTA-AAS HIGH SCHOOL MODERNIZATION ADDENDUM NO. 2
SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM SOTA-AAS HIGH SCHOOL MODERNIZATION ADDENDUM NO. 2 Owner: San Francisco Unified School District Date: Dec. 10, 2014 135 Van Ness Avenue
More informationTO: All Recipients Date: March 20, 2015
CITY OF VALDEZ Project Title: Valdez Museum, Library, Elementary School roof replacements Project No.: 15-310-4250, 15-310-4260, 15-310-9513 Contract No.: 1214 TO: All Recipients Date: March 20, 2015 SUBJECT:
More information1. Name the horizontal member that rests on the foundation wall to support other wood members.
Student Name: Teacher: Date: District: Rowan Assessment: 9_12 T and I IC62 - Drafting - Architr II Test 1 Description: Unit C - Floorplans - Test 3 (ALL) Form: 501 1. Name the horizontal member that rests
More informationResidential Room Addition / Remodel Submittal Requirement Checklist
City of Elko Building Department 1753 College Avenue Elko, Nevada 89801 (775) 777-7220 fax (775) 777-7229 Residential Room Addition / Remodel Submittal Requirement Checklist TWO COMPLETE SETS OF PROPERLY
More informationHilton Americas Guestroom Conversion (19th Fl.) Invitation to Bid
DATE: February 9, 28 SUBECT: Letter of Clarification #2 RE: TO: Hilton Americas Guestroom Conversion (19th Fl.) Invitation to Bid All Prospective Bidders ( HFC ) issues this Letter of Clarification regarding
More informationStantec Architecture Inc South Flores Street Suite 201 San Antonio TX Tel: (210) Fax: (210)
Stantec Architecture Inc. 1344 South Flores Street Suite 201 San Antonio TX 78204-1672 Tel: (210) 223-9588 Fax: (210) 223-9589 ADDENDUM #1 07/11/2014 TO PLANS AND SPECIFICATIONS FOR RENOVATION AND ADDITION
More informationCompany. Signed: Date:
ADDENDUM No. 1 For: Please acknowledge receipt of this Addendum No. 1 Sign and return by fax to 856-424-1688: Company Signed: BURLINGTON TOWNSHIP BOARD OF EDUCATION RENOVATIONS TO B, C & H WING GANG TOILET
More informationADDENDUM NO. 3, March 14, 2017 A.B.C. No
ADDENDUM NO. 3, March 14, 2017 A.B.C. No. 2017044 RE: UM Harman Hall Mechanical Renovation Montevallo, Alabama 35115 Architect s job no. 2747 FROM: TurnerBatson 1950 Stonegate Drive, Suite 200 Birmingham,
More informationSECTION IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
SECTION 220553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT Henderson Engineers, Inc. PART 1 - GENERAL REQUIREMENTS 1.1 SUMMARY A. Extent of Plumbing work to be identified as required by this Section
More informationPROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic
GENERAL SITE PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS Scope of work narrative Building code review Description of construction Documentation on drawings as List of applicable
More informationINSTALLATION SHOP DRAWINGS FOR MINNEAPOLIS, MN
MINNEAPOLIS, MN 2-0- 2-- General Notes Abbreviations Deviations from Architectural Specifications Deviations from Architectural Drawings ALUM. = ALUMINUM B.O. = BY OTHERS CONT. = CONTINUOUS. = CLEARANCE
More information404 Doors, Doorways, and Gates
404 Doors, Doorways, and Gates 404.2 Manual Doors, Doorways, and Manual Gates. Manual doors and doorways and manual gates intended for user passage shall comply with 404.2. 404.2.2 Double-Leaf Doors and
More informationAddendum Number: 1 WT White HS Additions and Renovations, Dallas ISD
Addendum #1 July 9, 2018 Addendum Number: 1 Project: WT White HS Additions and Renovations, Dallas ISD Bid Package: BP#215 Project Number: 1719 - ORG 021 The following items modify the plans and specifications
More information" BASE CABINET
INSTALLATION GUIDE INSTALLATION GUIDE Before You Begin Installing Your Kitchen Cabinets 1. Read through installation guide to understand all steps and gather tools needed. 2. Verify that all of the hardware,
More informationMODEL SETUP FOR RENOVATION PROJECTS INSTRUCTIONS AND TUTORIALS
MODEL SETUP FOR RENOVATION PROJECTS INSTRUCTIONS AND TUTORIALS WHAT S INSIDE INTRODUCTION 1 PART ONE LAYERS AND CLASSES FOR RENOVATION PROJECT 1 OVERVIEW 1 SETTING UP LAYERS AND CLASSES 1 CREATING OBJECT
More informationChapter 22 - Cabinets & Vanities
Chapter 22 - Cabinets & Vanities Contents Chapter 22 - Cabinets & Vanities... 22-1 Timing & Prerequisites... 22-2 Cabinets... 22-3 Cabinet Layout... 22-3 Wall Cabinets... 22-4 Assemble the Wall Units...
More informationPriority 3 - Toilet Rooms
The ADA Checklist for Readily Achievable Barrier Removal Priority 3 - Toilet Rooms Project Building Location Date Surveyors Contact Information When toilet rooms are open to the public they should be accessible
More informationADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.
ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO. PS 061 SEVEN SPRINGS WASTEWATER TREATMENT FACILITY IMPROVEMENTS PASCO COUNTY,
More informationCSP PSYCHIATRIC SERVICES UNIT SECTION IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
SECTION 23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe Markers. 2. Valve Tags. 3. Equipment Nameplates. 4. Underground Marking Tape. 5. Duct
More informationShay Cab - Floor & Roof
Shay Cab - Floor & Roof Nelson Riedel Nelson@NelsonsLocomotive.com Initial: 1/20/04 Last Revised: 06/06/2004 Cab Floor: A cab floor was made at the same time as the tender floor. I was unhappy with some
More informationUniversity of Houston Master Construction Specifications Insert Project Name SECTION MECHANICAL SCOPE OF WORK PART 1 - GENERAL
SECTION 23 00 10 - MECHANICAL SCOPE OF WORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements", and Section 23 01
More informationTHE CHURCH OF J ESUS CHRIST OF LATTER-DAY SAINTS BISHOPS' STOREHOUSE THE CHURCH OF OF LATTER-DAY SAINTS HOME STORAGE CENTER BISHOPS' STOREHOUSE
231 THE CHURCH OF J ESUS CHRIST OF LATTER-DAY SAINTS BISHOPS' THE CHURCH OF BISHOPS' HOURS Monday-Friday P.M. - X:00 A.M. X:00 Saturday P.M. - X:00 A.M. X:00 J ESUS CHRIST OF LATTER-DAY SAINTS HOME STORAGE
More informationThis addendum forms a part of the Contract Documents dated: August 10, 2012.
Addendum # 1 Date Issued: August 28, 2012 Issued By: Project: Owner: Renker Eich Parks Architects 1609 Dr. Martin Luther King Street North St. Petersburg, Florida 33704 Ph# (727) 821-2986 Fax # (727) 896-4911
More information