The Italy - Malta interconnection. Morris Brenna

Size: px
Start display at page:

Download "The Italy - Malta interconnection. Morris Brenna"

Transcription

1 The Italy - Malta interconnection

2 Introduction The Republic of Malta has an area of 316 km2 and a population of about 410 thousands with an energy annual consumption of about 2.3 TWh. The Maltese electric network was an isolated system with a peak load around 424 MW while the power reserve margins shrunk below N-1 condition (in terms of power plants), relieved by the incumbent crisis, but still demanding prompt investments on the electric energy supply side. Moreover, some of the existing steam plants have been decommissioned both for ageing reasons and environmental compliances. As an alternative/integration to commissioning new small scale fossilfuel-fired generation plants, has been identified in an electrical submarine interconnection with the Italian grid to provide improvements in terms of security of supply, power quality; economic savings; possible integration of wind farms; CO2 and air pollutants emissions reduction.

3 Introduction Sicily has an area of km2 and a population of about 5 millions with an energy annual consumption of about 22 TWh (6.4 % of Italy s annual consumption). In 2008 in Sicily the electric demand was satisfied by local energy generation. The energy demand of the island was supplied by thermal plants (93%), hydro plants (3%) and renewable plants, mainly wind plants (4%). Currently, the average power requested by the loads is around 2,100 MW and the total installed power is so shared: 5,434 MW from thermal power plants 1,677 MW from wind farms 1,204 MW from photoviltaic generators Since 1973 the energy balance in Sicily has been always positive, with an average surplus of 5%. Up to a few years ago, the island was connected to the Italian national network by a 400kV singlecircuit submarine link. Currently, a new double-circuit 400 kv submarine cable line (Sorgente-Rizziconi) is in operation and connect the Sicily with the Italian mainland. The Sicilian primary network 380kV and 220 kv, operated in meshed way in all the substations of the network, can ensure the highest level of security during the normal operation of the transmission grid. The 150 kv network is operated partially in meshed way and partially in radial way. The dispatching is carried-out in compliance with the (N-1) static and dynamic security criterion.

4 Introduction The establishment of a link between Malta and Italy was the key step in the strategic reorientation of the Maltese energy system. This interconnection has unique regulatory features, since it is a "unilateral" public interconnection, ie realized, owned and operated by only one of the transmission operator (Enemalta), which has required special solutions for authorization processes and for capacity management. The project, which is part of the European Energy Program for Recovery (EEPR), as a public utility project, was partly funded by the European Union, which made available 100 million euros for its implementation (about half of the total cost of the project). Now this electrical connection is fully in the so-called Trans-European Energy Networks (TEN-E).

5 Introduction Three technical solutions are currently available for undersea transmission of electric power: AC (synchronous) links DC, line commutated (DC-LCC) DC, voltage source (DC-VSC) All three solutions are in principle applicable to the Malta Sicily link Performances, shortcomings and costs of these techniques differ widely. Factors to be considered for a comparison can be qualitatively outlined

6 Advantages of the Malta Sicily interconnection More stable power supply of the Maltese electrical system Lower electricity price in Malta Decommissioning of older thermal power plants with environmental benefits Flexible use of non-programmable renewable energies, especially wind power, in Sicily

7 The challenge Long submarine connection (about 120 km), maximum water depth: 160 m

8 Technical alternatives 132 kv transmission grid voltage in Malta 220 kv transmission grid voltage in Sicily AC LCC 100 kv VSC 200 kv DC

9 Comparison between AC and DC solutions AC Link capacity Power transmission limits Power transmission control Cables Transmission losses Substations Reactive power exchange with network Passive receiving network supply / blackstart capability Redundancy (upon loss of a cable) Stations Costs Cables (capital, for equal crosssection) Cables (laying) Reliability / availability (*) Dependent on cable ampacity and cable length Angular stability Requires external means. Only depends on dispatching if no parallel links exist Highest (extra joule losses due to skin effect and reactive current, plus dielectric losses) Minimum (less than 0.3% of rated power for each station ) Limited due to extensive shunt compensation (>95%) Possible, limited by voltage stability 3-Core cables: none(*) (requires 2nd cable) Single-core cables: 100% if fourth (spare) cable provided Minimal (standard devices), shunt reactors only extra cost Maximum (3 phase conductors, single-core cables also require Cu armour) Maximum for single-core cables; minimum for 3-core (possibly with shorter laying stretches) Higher DC-LCC DC-VSC Only dependent on cable ampacity (virtually unlimited length) AC short-circuit power at terminals Controllable (10-100)% of rated power. System frequency constraints if no parallel links exist Lower than AC (minimum with sea return or with use of EHVDC ) ( )% of rated power for each station Limited, if AC filter/capacitor switching is performed Not available Monopolar: none (requires 2nd cable) Bipolar: 50% if sea return electrodes available Maximum (large footprint, extensive AC filters); sea return also requires electrodes Minimum for monopolar with sea return or IMR(***) (only 1 cable). Otherwise 2 cables needed Minimum for monopolar or bundled laying None Controllable (0-100)% of rated power. System frequency constraints if no parallel links exist Lower than AC Maximum (( )% of rated power for each station) Controllable in amplitude and sign (subject to capability limits) Possible, limited by voltage stability (**) None (requires 2nd couple of cables) Significant, comparable with LCC Lower than AC due to higher part count (spares needed) Difficult, theoretically possible at reduced power. Further study needed. (**) Application under study. (***) IMR: Integrated Metallic Return. Comparable to bipolar (or external metallic-return monopolar) LCC, always 2 cables Minimum for bundled laying Further experience required (Comparable to LCC?)

10 Comparison between AC and DC solutions Steady-state performance assessment of HVDC links, either LCC or VSC, is quite straightforward and is usually performed by DC equipment manufacturers Working out the operating envelope of AC cable interconnections is more involved, and usually done at Utilities engineering level Extensive system impact studies are required in both cases, with regard to voltage/angular stability, insulation coordination, harmonics etc.

11 Power losses

12 Normalized costs

13 Normalized costs/mw

14 AC solution issues One of the most conspicuous features of HV and EHV cable lines (CLs) is shunt capacitance, times that of overhead lines (OHLs); series inductance is smaller (30 to 70% of OHLs depending on cable spacing) As a result, Surge Impedance Loading (SIL) of CLs is several times the apparent power transmitted at thermal limit (i.e. ampacity) HV/EHV CLs thus have a substantial reactive power surplus in any operating condition

15 Reactive power issues Reduction of maximum transmissible real power and/or of allowable cable length between compensating stations Underexcited operation of nearby generators Step voltage change at the energizing bus following line switching-on/off Voltage rise at the open receiving end, upon line switching-on, or load rejection Line-charging current must not exceed rated line-charging breaking current of circuit breakers (CBs)

16 Reactive power issues "System" effects are catered for by judicious application inductive shunt compensation of Oil-immersed shunt reactors are robust, well-proven devices without moving parts Theoretically, to reduce the charging current hunt compensation should be installed at intermediate locations along the CL. This is not possible in submarine links: shunt reactors are installed at the terminals of the cable line

17 Final choice After many studies, the final transmission system chosen for the Malta Italy interconnection is an AC 220 kv cable line The rated power is 200 MW, but the system is prearranged for a second cable line This interconnection started its commercial operation in April 2015 It is the longest HVAC submarine cable in the world The Italian connection is located in Ragusa, in the south-east of Sicily The Maltese connection is located in Maghtab, in north Malta

18 Single-line diagram of the final Sicily-Malta interconnection

19 Ragusa terminal station The Italian connection has been realized in an existing HV substation

20 Ragusa terminal station

21 Maghtab terminal station In Magthab has been realized a new substation that provide the connection with the Maltese HV system through 220/132 kv autotransformers. Maghtab station is located nearby the Maltese landing point of the Malta-Sicily interconnector. Due to proximity to the shore, all the equipment, including autotransformers, shunt reactors and 230 kv / 132 kv switchgears, have been installed indoor.

22 Main submarine cable parameters ( km) Main conductor 630 mm2, Cu Insulaton XLPE, 24 mm Water-blocking tape Semiconductng water-swellable tape Metallic sheath Lead alloy ½C, 3 mm, 29 ka for 1 s Polyethylene sheath Semiconductng PE, 2.6 mm Steel armor 1 layer, 120 GSWA wires x 5.6 mm Ø Nominal current 655 A (249 MVA) Overloadability 1 h 1,113 A (170%) Maximum operatng voltage 245 kv Basic impulse insulaton level (BIL) 1,050 kv DC resistance Ω/km AC resistance Ω/km Line inductance 0.42 mh/km Line capacitance F/km Positve sequence resistance Ω/km Positve sequence reactance 0.13 Ω/km External diameter 239 mm

23 Submarine cable Copper conductor Semiconductie watertggt compound Semiconductor screen XLPE Insulaton Semiconductor screen Pgase identier tape Watertggt ribbon Lead sgeatg Polyetgylene sgeatg Optcal iber cable Semiconductor iller Filler Semiconductor reinforcement ribbon Galianized steel wire reinforcement Polypropylene bandage Polypropylene yarn

24 Submarine cable

25 Land cable Aluminum conductor Semiconductor layer XLPE insulaton Semiconductor layer Hygroscopic layer Aluminum Sgeatg Polyetgylene Sgeatg

26 Main land cable parameters (19.1 km) Main conductor 1000 mm2, Al Insulaton XLPE, 19.1 mm Water-blocking tape Semiconductng water-swellable tape Metallic sheath Aluminium 1.2 mm, 50 ka for 0.5 s Polyethylene sheath HDPE, 4 mm Nominal current 763 A Overloadability 1 h 1,144 A (150%) Maximum operatng voltage 245 kv Basic impulse insulaton level (BIL) 1,050 kv DC resistance Ω/km AC resistance Ω/km Line inductance mh/km Line capacitance F/km Positve sequence resistance Ω/km Positve sequence reactance Ω/km External diameter mm

27 Shunt reactors Ragusa substation: 1 constant 220 Mvar SR directly connected to the 220 kv cable Maghtab substation 1 variable Mvar SR with on-load tap changer connected to the 220 kv cable 1 variable Mvar SR with on-load tap changer connected to the 220 kv busbars through a circuit breaker, therefore it can be disconnected

28 Maximum active transmissible power = = 1 Pc = surge impedance loading Sz = power at ampacity K" = cable propagation constant L = cable length

29 Capability curves

30 Capability curves Delivered active and reactive power in Malta, with attendant receiving end voltage at Maghtab busbars; 230 kv voltage in Ragusa, for different values of total inductive shunt compensation in Maghtab (from left to right, 240, 180, 120, 60 Mvar)

31 Transmission losses Actual value Percent value Overall transmission losses calculated for all operating points comprised inside the capability curve related to 120 Mvar shunt compensation in Maghtab. 230 kv voltage in Ragusa.

32 Power flows Half power By adjusting ATR tap and reactor it is possible to set the active and reactive power flows in the Maghtab substation at the desired values Full power

33 Final tests Final tests on the Malta-Sicily link started in January 2015; the link started commercial operation in April 2015; besides conventional high voltage tests, special tests have been carried out, in order to assess the impedance of the submarine cable line at 50 Hz and higher frequencies. Results, summarized in this figure, show that the first resonant frequency is about 375 Hz (around 7th harmonic); impedance magnitude at first resonant frequency is about 180.

34 Cable energization Current at the Sicilian (sending) end of the link during cable energization

35 Cable energization Phase to ground voltages in Maghtab substation during cable energization

36 Protection system The new 220 kv connection has a fully redundant monitoring, control and protection system in each substation, in order to ensure adequate safety margins for the operation of the two interconnected electrical networks. Given the importance of the new connection and terminal apparatuses, the protection system can detect the different types of failure that may occur on both the connecting cable and the electrical stations. More in detail, each of the different types of failure that may affect the interconnection system must be detected by at least two protections, based on different operating principles. A fault on the 220 kv cable or on the compensation inductors connected to the end of the cable must be eliminated in the base time by opening the line circuit breakers at the end of the HV cable (at Ragusa and Maghtab substations).

37 Protection system

38 Protection system To ensure the priority of one of the two protection systems, by automatically transferring (without delay) the control signal to the other in case of failure, both protectors use 24/48 optical fiber connection. Dielectric central element Grooied core in tgermoplastc material optcal ibers buffering Bandage witg syntgetc tapes Black polyetgylene sgeatg Aramid yarns Bandage witg syntgetc tapes Black polyetgylene sgeatg

39 Conclusions The new 220 kv AC cable connection between Sicily and Malta, with its 100 km (about km), represents the longest AC submarine interconnection in the world. The realization of the work has allowed for a more stable power supply to the Maltese electrical system and a lower cost of electricity while decreasing the environmental impact produced by the old Maltese power plants. In addition, there is a more flexible management of the Sicilian electricity production plant, favoring in particular the dispatching of non-programmable renewable sources, especially with regard to wind generation. However, it is necessary to point out some possible criticalities that may arise in the setting of the island of frequency of the Sicilian electrical system, especially in the event of a sudden trip of the new Sicily-Malta connection. These criticisms are partially resolved thanks to the new Sorgente-Rizziconi link.

40 Tgank you for your atenton

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

A cost effective hybrid HVDC transmission system with high performance in DC line fault handling

A cost effective hybrid HVDC transmission system with high performance in DC line fault handling 2, rue d Artois, F-758 PARIS B4-7 CIGRE 28 http : //www.cigre.org A cost effective hybrid HVDC transmission system with high performance in DC line fault handling Mats Andersson, Xiaobo ang and ing-jiang

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

HVDC Transmission. Michael Muhr. Institute of High Voltage Engineering and System Performance Graz University of Technology Austria P A S S I O N

HVDC Transmission. Michael Muhr. Institute of High Voltage Engineering and System Performance Graz University of Technology Austria P A S S I O N S C I E N C E P A S S I O N T E C H N O L O G Y HVDC Transmission Michael Muhr Graz University of Technology Austria www.tugraz.at 1 Definition HV High Voltage AC Voltage > 60kV 220kV DC Voltage > 60kV

More information

Fatima Michael college of Engineering and Technology

Fatima Michael college of Engineering and Technology Fatima Michael college of Engineering and Technology DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING EE2303 TRANSMISSION AND DISTRIBUTION SEM: V Question bank UNIT I INTRODUCTION 1. What is the electric

More information

Coil Products Beginnings 1960 State of the Art. Customer partnership around the globe. Continuous innovation since 1900

Coil Products Beginnings 1960 State of the Art. Customer partnership around the globe. Continuous innovation since 1900 Coil Products Coil Products Customer partnership around the globe More than 250,000 coil products delivered to more than 170 countries. More than 60 years of operational experience. 35,000 in Europe 13,000

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Transmission of Electrical Energy

Transmission of Electrical Energy Transmission of Electrical Energy Electrical energy is carries by conductors such as overhead transmission lines and underground cables. The conductors are usually aluminum cable steel reinforced (ACSR),

More information

HVDC High Voltage Direct Current

HVDC High Voltage Direct Current HVDC High Voltage Direct Current Typical HVDC Station BACK TO BACK CONVERTER STATION MONO POLAR WITH GROUND RETURN PA Back to Back Converters indicates that the Rectifiers & Inverters are located in the

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for Michigan s Eastern Upper and Northern Lower Peninsulas

ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for Michigan s Eastern Upper and Northern Lower Peninsulas 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

Experience with Connecting Offshore Wind Farms to the Grid

Experience with Connecting Offshore Wind Farms to the Grid Oct.26-28, 2011, Thailand PL-22 CIGRE-AORC 2011 www.cigre-aorc.com Experience with Connecting Offshore Wind Farms to the Grid J. FINN 1, A. SHAFIU 1,P. GLAUBITZ 2, J. LOTTES 2, P. RUDENKO 2, M: STEGER

More information

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter 1 Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter Nee, Staffan Norrga, Remus Teodorescu ISBN-10: 1118851560

More information

High Voltage DC Transmission 2

High Voltage DC Transmission 2 High Voltage DC Transmission 2 1.0 Introduction Interconnecting HVDC within an AC system requires conversion from AC to DC and inversion from DC to AC. We refer to the circuits which provide conversion

More information

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation Course ELEC0014 - Introduction to electric power and energy systems Additional exercises with answers December 2017 Exercise A1 Consider the system represented in the figure below. The four transmission

More information

USE OF HVDC MULTI TERMINAL OPTIONS FOR FUTURE UPGRADE OF THE NATIONAL GRID

USE OF HVDC MULTI TERMINAL OPTIONS FOR FUTURE UPGRADE OF THE NATIONAL GRID USE OF HVDC MULTI TERMINAL OPTIONS FOR FUTURE UPGRADE OF THE NATIONAL GRID JOS ARRILLAGA Emeritus Professor, FIEE, FIEEE, MNZM 2/77 HINAU STREET, RICCARTON CHRISTCHURCH ARRILLJ@ELEC.CANTERBURY.AC.NZ TELEPHONE

More information

ATC s Mackinac Back to Back. Summary

ATC s Mackinac Back to Back. Summary ATC s Mackinac Back to Back HVDC Project Update Michael B. Marz American Transmission Company Summary The Need For Flow Control at Mackinac Mackinac Flow Control Requirements Available Flow Control Technologies

More information

Facilitating Bulk Wind Power Integration Using LCC HVDC

Facilitating Bulk Wind Power Integration Using LCC HVDC 21, rue d Artois, F-758 PARIS CIGRE US National Committee http : //www.cigre.org 213 Grid of the Future Symposium Facilitating Bulk Wind Power Integration Using LCC HVDC A. HERNANDEZ * R.MAJUMDER W. GALLI

More information

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations Case Study 1 Power System Planning and Design: Power Plant, Transmission Lines, and Substations Lindsay Thompson, 5203120 Presented to Riadh Habash ELG 4125 11/10/2013 1.0 ABSTRACT A power plant delivers

More information

Lecturer: Dr. J B E AL-ATRASH No. of Pages: 4

Lecturer: Dr. J B E AL-ATRASH No. of Pages: 4 Philadelphia University Faculty of Engineering Dept. of Electrical Engineering Student Name: Student Number: Final Exam Course Title: Design of T&D System Date: 15 th June 2016 Course No: 610 515/650511

More information

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections

More information

ELECTRICAL POWER ENGINEERING

ELECTRICAL POWER ENGINEERING Introduction This trainer has been designed to provide students with a fully comprehensive knowledge in Electrical Power Engineering systems. The trainer is composed of a set of modules for the simulation

More information

1400 MW New Zealand HVDC Upgrade: Introducing Power Modulation Controls and Round Power Mode

1400 MW New Zealand HVDC Upgrade: Introducing Power Modulation Controls and Round Power Mode 1400 MW New Zealand HVDC Upgrade: Introducing Power Modulation Controls and Mode Simon P. Teeuwsen Network Consulting Siemens AG Erlangen, Germany simonp.teeuwsen@siemens.com Abstract The existing HVDC

More information

SYSTEM STUDIES for HVDC

SYSTEM STUDIES for HVDC INTRODUCTION The design of HVDC requires Careful study coordination, which must be achieved in compliance with the Owner s requirements. To achieve these objectives, number of highly interactive system

More information

Technologies data base and technological innovation needs up to 2050

Technologies data base and technological innovation needs up to 2050 Session IV : Long-term grid development Technology and operations Technologies data base and technological innovation needs up to 2050 Eric Peirano, Technofi Work Package leader e-highway2050 I Final Conference

More information

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors May 11, 2010 Slide 1 Why phase-shifting transformers

More information

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY 9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor

More information

Should we transform our lines to HVDC?

Should we transform our lines to HVDC? Should we transform our lines to HVDC? HVDC versushvac Gaurav Dabhi 1, Nishit Sanghvi 2, Pinkesh Patel 3 1 Electrical Eng., G.H. Patel college of Eng. & Tech., dabhi60@gmail.com 2 Electrical Eng., G.H.

More information

HV AC TESTING OF SUPER-LONG CABLES

HV AC TESTING OF SUPER-LONG CABLES HV AC TESTING OF SUPER-LONG CABLES Stefan SCHIERIG, (Germany), schierig@highvolt.de Peter COORS, (Germany), coors@highvolt.de Wolfgang HAUSCHILD, IEC, CIGRE, (Germany), hauschild@highvolt.de ABSTRACT The

More information

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Level 6 Graduate Diploma in Engineering Electrical Energy Systems 9210-114 Level 6 Graduate Diploma in Engineering Electrical Energy Systems Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler,

More information

A new control scheme for an HVDC transmission link with capacitorcommutated converters having the inverter operating with constant alternating voltage

A new control scheme for an HVDC transmission link with capacitorcommutated converters having the inverter operating with constant alternating voltage 21, rue d Artois, F-758 PARIS B4_16_212 CIGRE 212 http : //www.cigre.org A new control scheme for an HVDC transmission link with capacitorcommutated converters having the inverter operating with constant

More information

Electrical Power Systems

Electrical Power Systems Electrical Power Systems CONCEPT, THEORY AND PRACTICE SECOND EDITION SUBIR RAY Professor MVJ College of Engineering Bangalore PHI Learning Pfcte tofm Delhi-110092 2014 Preface xv Preface to the First Edition

More information

CONTENTS. 1. Introduction Generating Stations 9 40

CONTENTS. 1. Introduction Generating Stations 9 40 CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific

More information

Joe Warner, Electric Power Industry Conference (EPIC), November 15, 2016 Advances in Grid Equipment Transmission Shunt Compensation

Joe Warner, Electric Power Industry Conference (EPIC), November 15, 2016 Advances in Grid Equipment Transmission Shunt Compensation Joe Warner, Electric Power Industry Conference (EPIC), November 15, 2016 Advances in Grid Equipment Transmission Shunt Compensation Slide 1 Excerpt from the BoA BoA: Book of Acronyms MSC/MSR: Mechanically

More information

Harmonic resonances due to transmission-system cables

Harmonic resonances due to transmission-system cables International Conference on Renewable Energies and Power Quality (ICREPQ 14) Cordoba (Spain), 8 th to 1 th April, 214 Renewable Energy and Power Quality Journal (RE&PQJ) ISSN 2172-38 X, No.12, April 214

More information

Determination of Optimal Account and Location of Series Compensation and SVS for an AC Transmission System

Determination of Optimal Account and Location of Series Compensation and SVS for an AC Transmission System ISSN (e): 2250 3005 Vol, 04 Issue, 5 May 2014 International Journal of Computational Engineering Research (IJCER) Determination of Optimal Account and Location of Series Compensation and SVS for an AC

More information

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products

More information

Zambezi (previously Caprivi) Link HVDC Interconnector: Review of Operational Performance in the First Five Years

Zambezi (previously Caprivi) Link HVDC Interconnector: Review of Operational Performance in the First Five Years 21, rue d Artois, F-758 PARIS B4-18 CIGRE 216 http : //www.cigre.org Zambezi (previously Caprivi) Link HVDC Interconnector: Review of Operational Performance in the First Five Years T G MAGG, Power System

More information

Voltage Source Converter Modelling

Voltage Source Converter Modelling Voltage Source Converter Modelling Introduction The AC/DC converters in Ipsa represent either voltage source converters (VSC) or line commutated converters (LCC). A single converter component is used to

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org B4-112 AORC Technical meeting 214 HVDC Circuit Breakers for HVDC Grid Applications K. Tahata, S. Ka, S. Tokoyoda, K. Kamei, K. Kikuchi, D. Yoshida, Y. Kono, R. Yamamoto, H. Ito Mitsubishi

More information

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM SWITCHING OVERVOLTAGES IN A 4-KV CABLE SYSTEM Mustafa Kizilcay University of Siegen Siegen, Germany kizilcay@uni-siegen.de Abstract This paper deals with the computation of switching overvoltages in a

More information

Introduction to HVDC in GB. Ian Cowan Simulation Engineer 12 March 2018

Introduction to HVDC in GB. Ian Cowan Simulation Engineer 12 March 2018 Introduction to HVDC in GB Ian Cowan Simulation Engineer 12 March 2018 Contents 1) History of Electricity Networks 2) Overview of HVDC 3) Existing Schemes 4) Future Schemes 5) Regulation and Ownership

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

Application of SVCs to Satisfy Reactive Power Needs of Power Systems

Application of SVCs to Satisfy Reactive Power Needs of Power Systems 1 Application of SVCs to Satisfy Reactive Power Needs of Power Systems H. K. Tyll, Senior Member, IEEE Abstract In the early days of power transmission problems like voltage deviation during load changes

More information

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009 Lab 1 Objectives In this lab, our objective is to simulate a simple single machine infinite bus configuration using the PowerWorld Simulator software. We design a local generator system (a synchronous

More information

ELECTRICAL POWER TRANSMISSION TRAINER

ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER This training system has been designed to provide the students with a fully comprehensive knowledge in Electrical Power Engineering

More information

Impact Assessment Generator Form

Impact Assessment Generator Form Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project

More information

Index. b back-flashover 245 biomass 207 breakers 74 buchholz protection 235 busbar sectionalizer 193 business enterprises 18

Index. b back-flashover 245 biomass 207 breakers 74 buchholz protection 235 busbar sectionalizer 193 business enterprises 18 331 Index a activity plan 318 agricultural enterprise 21 annual increase factor 12 annuity factor 44, 156 annuity method 38 ANSI code numbers 237 arrester, protection level 245 assessment of losses 38

More information

Analysis of a 405 km transmission line with series compensation

Analysis of a 405 km transmission line with series compensation Analysis of a 405 km transmission line with series compensation by Dr. Rupert Gouws, North-West University This paper presents an investigative case study and energy efficiency analysis of the 405 km,

More information

Power transmission systems for offshore wind farms: Technical-economic analysis 1. Abstract

Power transmission systems for offshore wind farms: Technical-economic analysis 1. Abstract Power transmission systems for offshore wind farms: Technical-economic analysis 1 Abstract Several studies claim that wind power will play a major role in the energy supply of the European Union, forecasting

More information

Single Line Diagram of Substations

Single Line Diagram of Substations Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission lines are

More information

An Integrated Transformer-Shunt Reactor Operation Device for The Connection of Off-Shore Wind-Farms

An Integrated Transformer-Shunt Reactor Operation Device for The Connection of Off-Shore Wind-Farms An Integrated Transformer-Shunt Reactor Operation Device for The Connection of Off-Shore Wind-Farms C. Bruzzese, F. Ielpo, S. Lauria F. Palone, M. Rebolini Dept. of Astronautical, Electrical, and Energy

More information

DC utilization of existing LVAC distribution cables

DC utilization of existing LVAC distribution cables DC utilization of existing LVAC distribution cables D. Antoniou, A. Tzimas and S. M. Rowland The University of Manchester School of Electrical and Electronic Engineering M13 9PL, UK Abstract Low Voltage

More information

Fundamental Concepts of Dynamic Reactive Compensation. Outline

Fundamental Concepts of Dynamic Reactive Compensation. Outline 1 Fundamental Concepts of Dynamic Reactive Compensation and HVDC Transmission Brian K. Johnson University of Idaho b.k.johnson@ieee.org 2 Outline Objectives for this panel session Introduce Basic Concepts

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH Requirements for Offshore Grid Connections in the Grid of TenneT TSO GmbH Bernecker Straße 70, 95448 Bayreuth Updated: 5th October 2010 1/10 Requirements for Offshore Grid Connections in the Grid of TenneT

More information

Digital Fault Recorder Deployment at HVDC Converter Stations

Digital Fault Recorder Deployment at HVDC Converter Stations Digital Fault Recorder Deployment at HVDC Converter Stations On line continuous monitoring at HVDC Converter Stations is an important asset in determining overall system performance and an essential diagnostic

More information

Overview of Actuation Thrust

Overview of Actuation Thrust Overview of Actuation Thrust Fred Wang Thrust Leader, UTK Professor ECE 620 CURENT Course September 13, 2017 Actuation in CURENT Wide Area Control of Power Power Grid Grid Measurement &Monitoring HVDC

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

New HVDC Interaction between AC networks and HVDC Shunt Reactors on Jeju Converter Stations

New HVDC Interaction between AC networks and HVDC Shunt Reactors on Jeju Converter Stations New HVDC Interaction between AC networks 233 JPE 7-3-6 New HVDC Interaction between AC networks and HVDC Shunt Reactors on Jeju Converter Stations Chan-Ki Kim, Young-Hun Kwon * and Gil-Soo Jang ** KEPRI,

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller This paper deals with the general problem of utilizing of renewable energy sources to generate electric

More information

HVDC Solutions for Integration of the Renewable Energy Resources

HVDC Solutions for Integration of the Renewable Energy Resources HVDC Solutions for Integration of the Renewable Energy Resources Comparison of Technical Alternatives and System Configurations Marcus Haeusler Energy Management, Large Transmission Solutions Siemens AG

More information

Tab 2 Voltage Stresses Switching Transients

Tab 2 Voltage Stresses Switching Transients Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles

More information

Insulation Co-ordination For HVDC Station

Insulation Co-ordination For HVDC Station Insulation Co-ordination For HVDC Station Insulation Co-ordination Definitions As per IEC 60071 Insulation Coordination is defined as selection of dielectric strength of equipment in relation to the operating

More information

High Voltage DC Transmission Prof. Dr. S. N. Singh Department of Electrical Engineering Indian Institute of Technology, Kanpur

High Voltage DC Transmission Prof. Dr. S. N. Singh Department of Electrical Engineering Indian Institute of Technology, Kanpur High Voltage DC Transmission Prof. Dr. S. N. Singh Department of Electrical Engineering Indian Institute of Technology, Kanpur Module No. # 01 Lecture No. # 02 Comparison of HVAC and HVDC Systems Welcome

More information

ELEMENTS OF FACTS CONTROLLERS

ELEMENTS OF FACTS CONTROLLERS 1 ELEMENTS OF FACTS CONTROLLERS Rajiv K. Varma Associate Professor Hydro One Chair in Power Systems Engineering University of Western Ontario London, ON, CANADA rkvarma@uwo.ca POWER SYSTEMS - Where are

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0 DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Hamdy Faramawy Senior Application Specialist ABB Sweden

Hamdy Faramawy Senior Application Specialist ABB Sweden Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy

More information

EE 740 Transmission Lines

EE 740 Transmission Lines EE 740 Transmission Lines 1 High Voltage Power Lines (overhead) Common voltages in north America: 138, 230, 345, 500, 765 kv Bundled conductors are used in extra-high voltage lines Stranded instead of

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014 Constant Terminal Voltage Working Group Meeting 4 19 th September 014 Overview Options summary System under investigation Options analysis Discussion Options Option 1 Constant Terminal Voltage controlled

More information

MV network design & devices selection EXERCISE BOOK

MV network design & devices selection EXERCISE BOOK MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester

More information

EE 741. Primary & Secondary Distribution Systems

EE 741. Primary & Secondary Distribution Systems EE 741 Primary & Secondary Distribution Systems Radial-Type Primary Feeder Most common, simplest and lowest cost Example of Overhead Primary Feeder Layout Example of Underground Primary Feeder Layout Radial-Type

More information

Roll No. :... Invigilator s Signature :.. CS/B.TECH(EE)/SEM-5/EE-502/ POWER SYSTEM-I. Time Allotted : 3 Hours Full Marks : 70

Roll No. :... Invigilator s Signature :.. CS/B.TECH(EE)/SEM-5/EE-502/ POWER SYSTEM-I. Time Allotted : 3 Hours Full Marks : 70 Name : Roll No. :.... Invigilator s Signature :.. CS/B.TECH(EE)/SEM-5/EE-502/2011-12 2011 POWER SYSTEM-I Time Allotted : 3 Hours Full Marks : 70 The figures in the margin indicate full marks. Candidates

More information

The University of Nottingham

The University of Nottingham The University of Nottingham Power Electronic Converters for HVDC Applications Prof Pat Wheeler Power Electronics, Machines and Control (PEMC) Group UNIVERSITY OF NOTTINGHAM, UK Email pat.wheeler@nottingham.ac.uk

More information

Exercises on overhead power lines (and underground cables)

Exercises on overhead power lines (and underground cables) Exercises on overhead power lines (and underground cables) 1 From the laws of Electromagnetism it can be shown that l c = 1 v 2 where v is the speed of propagation of electromagnetic waves in the environment

More information

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider Shunt Reactors Global Top Energy, Machinery & Plant Solution Provider Our Business Brief introduction of Hyosung Power & Industrial Systems PG While Hyosung is an established name for world-class electrical

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

UProtection Requirements. Ufor a Large scale Wind Park. Shyam Musunuri Siemens Energy

UProtection Requirements. Ufor a Large scale Wind Park. Shyam Musunuri Siemens Energy UProtection Requirements Ufor a Large scale Wind Park Shyam Musunuri Siemens Energy Abstract: In the past wind power plants typically had a small power rating when compared to the strength of the connected

More information

Overview of Actuation Thrust

Overview of Actuation Thrust Overview of Actuation Thrust Fred Wang Thrust Leader, UTK Professor Prepared for CURENT Course September 4, 2013 Actuation in CURENT Wide Area Control of Power Power Grid Grid Measurement &Monitoring HVDC

More information

HVDC CAPACITOR COMMUTATED CONVERTERS IN WEAK NETWORKS GUNNAR PERSSON, VICTOR F LESCALE, ALF PERSSON ABB AB, HVDC SWEDEN

HVDC CAPACITOR COMMUTATED CONVERTERS IN WEAK NETWORKS GUNNAR PERSSON, VICTOR F LESCALE, ALF PERSSON ABB AB, HVDC SWEDEN HVDC CAPACITOR COMMUTATED CONVERTERS IN WEAK NETWORKS GUNNAR PERSSON, VICTOR F LESCALE, ALF PERSSON ABB AB, HVDC SWEDEN Summary Capacitor Commutated Converters (CCC) were introduced to the HVDC market

More information

Unit 2. Single Line Diagram of Substations

Unit 2. Single Line Diagram of Substations Unit 2 Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission

More information

Influence of Wind Generators in Voltage Dips

Influence of Wind Generators in Voltage Dips Influence of Wind Generators in Voltage Dips E. Belenguer, N. Aparicio, J.L. Gandía, S. Añó 2 Department of Industrial Engineering and Design Universitat Jaume I Campus de Riu Sec, E-27 Castelló (Spain)

More information

ELEC Transmission i and

ELEC Transmission i and ELEC-1104 Lecture 5: Transmission i and Distribution ib ti Power System Layout Transmission and Distribution The transmission system is to transmit a large amount of energy from the power stations s to

More information

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Code No: R3 R1 Set No: 1 III B.Tech. II Semester Supplementary Examinations, January -14 POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Max Marks: 75 Answer any FIVE Questions

More information

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering DLC s Brady IIB Project Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering Project Need In 2007, PJM and Duquesne Light Company (DLC) transmission

More information

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL Basically the HVDC transmission consists in the basic case of two convertor stations which are connected to each other by a transmission link consisting of an overhead

More information

Bipole III Transmission Project

Bipole III Transmission Project Bipole III Transmission Project Clean Environment Commission Public Hearings Fall 2012 System Planning Ronald Mazur BP III Keewantinoow Limestone Kettle Kelsey Jenpeg Grand Rapids OVERVIEW Transmission

More information

EE 340 Transmission Lines. Spring 2012

EE 340 Transmission Lines. Spring 2012 EE 340 Transmission Lines Spring 2012 Physical Characteristics Overhead lines An overhead transmission line usually consists of three conductors or bundles of conductors containing the three phases of

More information

Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping

Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping P. Mestas, M. C. Tavares Abstract. The optimization of the grounding neutral reactor is a common practice

More information

Power System Studies

Power System Studies Power System Studies Laois Ballyragget Cable Feasibility Study PE667-F4-R3-1-3 ESBI Engineering Solutions Stephen Court, 18/21 St Stephen s Green, Dublin 2, Ireland Telephone+353-1-73 8 Fax+353-1-661 66

More information

ENGINEERING ACADEMY X V

ENGINEERING ACADEMY X V 1. Two incandescent bulbs of rating 230, 100 W and 230, 500 W are connected in parallel across the mains. As a result, what will happen? a) 100 W bulb will glow brighter b) 500 W bulb will glow brighter

More information

EL 403 MODEL TEST PAPER - 1 POWER SYSTEMS. Time: Three Hours Maximum Marks: 100

EL 403 MODEL TEST PAPER - 1 POWER SYSTEMS. Time: Three Hours Maximum Marks: 100 POWER SYSTEMS Time: Three Hours Maximum Marks: 0 Answer five questions, taking ANY TWO from Group A, any two from Group B and all from Group C. All parts of a question (a, b, etc. ) should be answered

More information

Quanta Technology Advancing the Grid. Flexible AC Transmission System (FACTS) BGE Technology - Application Cases January 4, 2008 Q U A N T A SERVI CES

Quanta Technology Advancing the Grid. Flexible AC Transmission System (FACTS) BGE Technology - Application Cases January 4, 2008 Q U A N T A SERVI CES National Conference of State Legislatures The Forum for America s Ideas April 2011 National Association of Regulatory Utility Commissioners Q U A N T A SERVI CES Quanta Technology Advancing the Grid Flexible

More information

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/ ITC Holdings Planning Criteria Below 100 kv * Category: Planning Type: Policy Eff. Date/Rev. # 12/09/2015 000 Contents 1. Goal... 2 2. Steady State Voltage & Thermal Loading Criteria... 2 2.1. System Loading...

More information

Designing Of Distributed Power-Flow Controller

Designing Of Distributed Power-Flow Controller IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) ISSN: 2278-1676 Volume 2, Issue 5 (Sep-Oct. 2012), PP 01-09 Designing Of Distributed Power-Flow Controller 1 R. Lokeswar Reddy (M.Tech),

More information