Monthly Progress Report April 2004

Size: px
Start display at page:

Download "Monthly Progress Report April 2004"

Transcription

1 Heliosiesmic & Magnetic Imager Contract #: PY-2223 Cage Code: Total Pages: 7 Monthly Progress Report April 2004 Lockheed Martin Space Systems Company Advanced Technology Center Lockheed Martin Solar & Astrophysics Laboratory (LMSAL) 3251 Hanover Street, Palo Alto, CA

2 Table of Contents 1.0 Introduction Summary Schedule and Milestones Major Activities During March Filters and Optics Mechanical Mechanisms Electrical Software I&T Thermal Major Sub-contracts CCD e2v Camera Electronics - RAL Michelson LightMachinery Structure Vision Composites Planned Activities For May Design Updates Resource Requirements Issues/Concerns...7 Page 2 of 7

3 1.0 Introduction This is the monthly progress report for the month of April 2004 of the HMI program for the progress undertaken by LMSAL under the phase C/D/E contract with Stanford. The LMSAL team is in collaboration with Stanford University on the HMI/SDO solar physics investigation being led by Professor Phil Scherrer of Stanford University. 2.0 Summary April showers bring May flowers and will hopefully hold true for HMI. The RAL team has been working very hard at getting the CCD that was received from e2v up and running with the SECCHI camera. A first photo has been received, the team will learn more in May about the performance of the waveform generator. Some other highlights this month include: the shutter life test began, the performance of the Michelson interferometer beam-splitter was excellent, the mini-brass HEB assembly was completed, the structure contract was placed, the 1553 portion of the spacecraft interface was received, and a EEE parts and materials and process control board was held. The HMI team continues to hold weekly SDO Project and instrument telecons, weekly HMI-specific telecons, nearly weekly CCD camera system telecons, weekly telecons with LightMachinery, weekly HMI status meetings, and a constant stream of internal technical meetings. 3.0 Schedule and Milestones An updated detailed schedule is submitted at the end of each month. Shown below are some key program milestones and activities, with an emphasis on those that will occur in the near term and have recently occurred. Milestone Date Notes Begin shutter test End Mar 04 Completed (started) Michelson Performance April Attended (in Canada) Review Structure Kick-off meeting April 13 Completed Review e2v data May 6-13 Review RAL progress May 6-13 IFWG May Michelson CDR June 22 Receive SM Structure Sept 04 Structure order in process HMI CDR Nov 04 (at LM) Deliver HMI to S/C Nov 06 Launch Apr 08 * Five year baseline mission * Page 3 of 7

4 4.0 Major Activities During March 4.1 Filters and Optics The primary and secondary lens quotes were reviewed with the suppliers and one supplier, Janos, overlooked some of the requirements and chose to retract their proposal and no bid. A birefringence specification was added to the drawing, a revision released and sent to the chosen supplier, Coastal Optics. A revised quotation is expected. The ISS and BDS beam-splitter drawings and statement of work were released. The request for quote and drawing package is being sent to Lightmachinery. All of the Lyot filter elements have been placed on ordered. The focus block and calibration lens drawings were released. 4.2 Mechanical The CCD orientation has been resolved. There will be two board layouts for HMI and one will be designated in common with AIA. The detector board layout drawing is being reviewed and the connector panel design is progressing. A concept design for the shielding of the flex cable is being generated. A peer review will be scheduled to complete a request for action from the Mission PDR (the date has not been set, yet). The radiation analysis model was completed and the first cases are being analyzed. The Michelson mount drawings were released and work is progressing on the oven housing drawings. The oven pre-amp layout and cover drawings are in check. Alignment mechanism drawings are progressing. The ISS mirror mount is near completion and good progress is being made on the ISS beam-splitter mount and bi-cell sensor mount. HMI welcomed a new team member, Satyam Dave, to start work in detailing the alignment mechanism. 4.3 Mechanisms The shutter life test has begun! The shutter thermal test data and the test procedure were reviewed. A couple modifications to the test program were implemented and the test started. The focus/cal wheel drawings were completed and sent to the supplier for comments. Mechanism drive electronics were requested for the mechanism testing: the schedule is being reviewed to decide on quantities and board type. 4.4 Electrical The mini-brass electronics box enclosure was received and the development bridgeboard and motherboard assembly was completed. The brass box was assembled with the interconnect board and testing has begun. The over controller out-line drawing is complete and the parts stress analysis is progressing. The HEB enclosure design has gone from a single cover to multiple covers for each board. The design is commonly used on other LM programs and simplifies the box assembly and individual board access. It also resolved the concern for connector alignment challenges. Now the board outline drawings can continue. The Page 4 of 7

5 connector pin-outs for the spacecraft simulator were submitted to the SDO team. Lastly, a common buy plan with the SDO team has been implemented. 4.5 Software The 1553 portion of the spacecraft simulator was received, integrated and tested. There was an issue in sending commands, but it was resolved and the simulator is running with the LMSAL EGSE. The SDO team members that performed the installation also provided some training of ASIST for the HMI/AIA team. The ground systems PDR was attended and several items were discussed. The independent verification and validation (IVV) matrix was reviewed and a survey on critical function tests was requested. A security plan needs to be in place by CDR and the format control document was reviewed. In the meantime, a significant milestone was achieved: the kernel and SUROM software was loaded onto the RAD6000 board. The QHSS code peer review action items were completed and the CVS control is running. The acceptance test software for the EGSE core software is running, now individual instruments will be added. 4.6 I&T Most of the hardware ordered for chamber retrofit has arrived and is being integrated. Instrument package alignment and test planning meetings have begun. 4.7 Thermal The oven thermal analysis shows that the secondary cover over the Michelsons is necessary and heater sizing and sensor locations are being determined. The front window analysis is progressing. Rose has returned and will be resuming the optics package and front window analysis. 4.8 Major Sub-contracts CCD e2v Three batches of flight CCDs have started processing. Everyone is patiently awaiting tested results of the two engineering units, which are due eminently. E2v is working to resolve a charge transfer variance across the CCD. Several team members will visit e2v in May Camera Electronics - RAL RAL has been working very hard at getting the CCD received from e2v running with the SECCHI camera. They have built a test CCD interface board and the layout is progressing at LMSAL for the flight board. The test board was completed and the CCD plugged in and we have lift off. Page 5 of 7

6 First Picture with Camera Michelson LightMachinery LightMachinery is continuing with testing of the engineering test unit beam-splitter. A preliminary test report has been received and test results looks great. They have also continued assembly on the mechanical test model and are near finished with test procedures. The CDR is now schedule for June 22 at LMSAL Structure Vision Composites The contracted was placed and a kick-off meeting was held. Work has begun on the detailed design of the structure. 5.0 Planned Activities For May 1. Continue the procurement for the optical elements. 2. Continue to work with the AIA team to organize LMSAL personnel for both programs in an optimal manner. 3. Continue work on mechanical and electrical drawings and detailed design. 4. On a routine (mostly weekly) basis continue to participate in telecons with the complete SDO group, the combined HMI/AIA-Project specific telecons, CCD Working Group telecons, Light Machinery telecons, BAE telecons; and to conduct HMI team meetings as well as specific meetings on Electronics/ Software, Filters, and Mechanical topics. 6.0 Design Updates As previously mentioned the CCD printed circuit board and housing layout design trade study has been resolved with two board layout designs. This allows for the shortest cable lengths and more simplified cable routing. The design is maturing. Also, the HEB cover design was reviewed and a multiple cover design selected to simplify assembly. Page 6 of 7

7 7.0 Resource Requirements The project has decided that an acoustics test is required and the mass simulator must meet the contamination requirements of the ICD as flight. The monthly mass and power status reports are provided as separate files. 8.0 Issues/Concerns Now that AIA has finished with the PDR, more attention has been given to HMI, common designs are progressing. Waiting test results of the CCD. Waiting test results of the camera performance testing with the CCD. The existing version of the SMCSLite chip that is used in the CEB and in the Camera Interface board needs to undergo radiation testing to verify it is acceptable, and we need to keep on top of whether the newer version of this chip will be available in time for our programs. Page 7 of 7

8 John Miles Allocation Basic Mass Margin LMSAL Doc. # HMI00157K Components Mass (kg) # Mass/Unit Status/Basis Notes ICD Allocation HMI Electronics Box (HEB) Estimate includes 0.2 kg for fasteners 25% HMI Optics Package (HOP) Estimate includes 0.2 kg for fasteners 66% HMI Harness (Harness) Estimate Presumes length of 4 meters 9% 6.39 Total 71 Revision History (Most Recent = Current) 06-May Apr Mar Nov Oct-03 5-Sep-03 7-Aug Jul Jun May Apr Mar-03 Proposal HMI Monthly Mass Report HOP design maturity growth (0.4 kg net decrease): Detector Assy, Focus Wheels, ISS Sensor, Structure HOP design maturity growth (0.67 kg net increase): CEB, ISS, Detector Assy, Telescope, Oven, Structure Design maturity growth, front door design and oven design HOP increase reflects larger/heavier CEBs and enlarged structure assy. HEB increase reflects complete modeling of the HEB structure and shielding on power section. Allocation expected to increase to 71 kg with the approval of CCR-30 but that is not reflected in this report. Harness Mass doubled in accordance with new SDO estimate of Harness length (changed from 2 to 4 meters). HEB and HOP Estimates unchanged from last month. Estimate unchanged from last month. Allocation increased 2 kg per CCR-016, see SDO doc 464-SYS-SPEC-0007B_SDO Mass Budget.xls, dated 12 August 2003 NOTE: SDO doc 464-SYS-SPEC-0007B should show 17 kg for the HEB and 35.3 kg for the HOP vs. 16 and 36.3 respectively. Includes 2.6 kg increase (unapproved) to bring the CCD shielding to 1.5 cm Al equivalent in all directions. No CEB increase included. Unchanged from last month, trade 5a verbally approved by SDO, presume allocation will increase soon. This report does not include possible mass increases currently being discussed in various Camera Electronics Box options. Unchanged from last month, trade 5a verbally approved by SDO, presume allocation will increase soon. HEB value reflects the 2 kg increase from reliability Trade "5a", no change to the Harness or OP from last month Updated names of components, no changes in mass estimates or allocations 53.2 kg Allocation made by SDO Project Office - D. Ward Estimate = 55 kg

9 HMI Monthly Power Report John Miles LMSAL Doc. # HMI00158J # Estimate Power /unit (W) Nominal / Operations Mode Estimated Power (W) Allocated Power (W) Power Margin (W) # Estimate Power /unit (W) Eclipse Mode Estimated Allocated Power (W) Power (W) Power Margin (W) # Estimate Power /unit (W) Orbit Raising Mode Estimated Allocated Power (W) Power (W) Power Margin (W) # Estimate Power /unit (W) Launch Mode Estimated Allocated Power (W) Power (W) Power Margin (W) TBD TBD TBD TBD Revision History (Most Recent = Current) 05-May-04 Updated estimates for camera I/F (including second FPGA), HRI, limb tracker, PZT driver, PCI/bridge/1553, and housekeeping boards in HEB. Added estimates for limb tracker pre-amp, PZT, and mechanisms in HOP. Overall nominal ops power dropped by 1.8 W. 09-Apr-04 Estimate unchanged from last month. Detailed power reassessment is to be carried out this month. 17-Nov-03 Estimate unchanged from last month. For reference, Allocations and Margins shown in green italics are those proposed in CCR Oct-03 Estimate unchanged from last month. 05-Sep-03 Estimate unchanged from last month. Allocations for Nominal/Operations and Eclipse Mode have increased 1 Watt (in each mode) per CCR-016, see 464-SYS-SPEC-0008A_SDO Power Budget, dated 12 August Jul-03 This report, prepared for Aug. 2003, is unchanged from May 2003, Received verbal approval of preferred reliability CCR, presume allocation will increase accordingly This report does not include possible power increases currently being discussed in various Camera Electronics Box options. 10-Jul-03 Unchanged from May 2003, received verbal approval of preferred reliability, presume allocation will increase accordingly This report does not include possible power increases currently being discussed in various Camera Electronics Box options. 04-Jun-03 Unchanged from May 2003, received verbal approval of preferred reliability, presume allocation will increase accordingly 09-May-03 Increased Operations and Eclipse Power by 1 Watt to reflect "preferred" reliability configuration of the HEB 04-Apr-03 Increased Nominal Power allocation by 1 Watt per D. Ward telecon. Added allocation columns for all modes. For the Orbit Injection Mode have presumed survival heaters and initial CCD decontam heaters only. For the Launch Mode have presumed all HMI power and heaters are off until Orbit Injection Mode begins. Estimates same as HMI SCR presentation. 26-Mar-03 Added allocations, considering revising thermal so that all numbers in one spot - D. Ward

Helioseismic Magnetic Imager Program at LMSAL

Helioseismic Magnetic Imager Program at LMSAL Helioseismic Magnetic Imager Program at LMSAL Contract PY-2223 Progress Report for December 2002 Introduction This is the third monthly progress report for the HMI program at LMSAL. We/LMSAL are collaborators

More information

Solar Dynamics Observatory

Solar Dynamics Observatory Solar Dynamics Observatory Solar Dynamics Observatory System Concept Review Helioseismic and Magnetic Imager Draft Presentation 21 March 2003 Hansen Experimental Physics Laboratory Stanford, CA Lockheed

More information

Solar Dynamics Observatory. Solar Dynamics Observatory. System Concept Review Helioseismic and Magnetic Imager

Solar Dynamics Observatory. Solar Dynamics Observatory. System Concept Review Helioseismic and Magnetic Imager Solar Dynamics Observatory Solar Dynamics Observatory System Concept Review Helioseismic and Magnetic Imager Presenters: P. Scherrer R. Bush L. Springer Stanford University Hansen Experimental Physics

More information

Prime Focus Imaging Spectrograph

Prime Focus Imaging Spectrograph Prime Focus Imaging Spectrograph Status 8 of 9 collimator and 6 of 9 camera lenses received (including all lenses) Slitmask mechanism assembled and wired, waveplate mechanism assembled Structure in fabrication

More information

Optical Telescope Design Study Results

Optical Telescope Design Study Results Optical Telescope Design Study Results 10 th International LISA Symposium Jeff Livas 20 May 2014 See also poster #19: Shannon Sankar UF and GSFC Telescope Design for a Space-based Gravitational-wave Mission

More information

Overall Technical Status

Overall Technical Status NOMAD Science Working Team meeting 4 Overall Technical Status ESA/ESRIN, 13-14 September 2012 1 Overview General status & Overview Optical design Mechanical design Electronic design Firmware/Software Breadboards

More information

PLATO Preliminary Requirements Review Technical Report

PLATO Preliminary Requirements Review Technical Report PLATO Preliminary Requirements Review Technical Report Prepared by Review Team Reference SRE-F/2013.075/ Issue 1 Revision 1 Date of Issue 16/12/2013 Status Issued Document Type Distribution Title Issue

More information

GLAST Large Area Telescope: Planning Meeting March 10, 2004 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6

GLAST Large Area Telescope: Planning Meeting March 10, 2004 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Planning Meeting March 10, 2004 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6 David J. Thompson Thomas E. Johnson NASA Goddard Space

More information

A 1m Resolution Camera For Small Satellites

A 1m Resolution Camera For Small Satellites A 1m Resolution Camera For Small Satellites Paper SSC06-X-5 Presenter: Jeremy Curtis 1 Introduction TopSat launched October 2005 carrying RAL s 2.5m GSD camera into a 686km orbit Built and operated by

More information

DISC Experiment Overview & On-Orbit Performance Results

DISC Experiment Overview & On-Orbit Performance Results DISC Experiment Overview & On-Orbit Performance Results Andrew Nicholas, Ted Finne, Ivan Galysh Naval Research Laboratory 4555 Overlook Ave., Washington, DC 20375; 202-767-2441 andrew.nicholas@nrl.navy.mil

More information

Phoenix. A 3U CubeSat to Study Urban Heat Islands. Sarah Rogers - Project Manager NASA Space Grant Symposium April 14, 2018

Phoenix. A 3U CubeSat to Study Urban Heat Islands. Sarah Rogers - Project Manager NASA Space Grant Symposium April 14, 2018 Phoenix A 3U CubeSat to Study Urban Heat Islands Sarah Rogers - Project Manager NASA Space Grant Symposium April 14, 2018 Phoenix Overview Undergraduate-led 3U CubeSat to study Urban Heat Islands through

More information

CRITICAL DESIGN REVIEW

CRITICAL DESIGN REVIEW STUDENTS SPACE ASSOCIATION THE FACULTY OF POWER AND AERONAUTICAL ENGINEERING WARSAW UNIVERSITY OF TECHNOLOGY CRITICAL DESIGN REVIEW November 2016 Issue no. 1 Changes Date Changes Pages/Section Responsible

More information

National Aeronautics and Space Administration Jet Propulsion Laboratory California Institute of Technology

National Aeronautics and Space Administration Jet Propulsion Laboratory California Institute of Technology QuikSCAT Mission Status QuikSCAT Follow-on Mission 2 QuikSCAT instrument and spacecraft are healthy, but aging June 19, 2009 will be the 10 year launch anniversary We ve had two significant anomalies during

More information

In the summer of 2002, Sub-Orbital Technologies developed a low-altitude

In the summer of 2002, Sub-Orbital Technologies developed a low-altitude 1.0 Introduction In the summer of 2002, Sub-Orbital Technologies developed a low-altitude CanSat satellite at The University of Texas at Austin. At the end of the project, team members came to the conclusion

More information

1. Description This section describes the procedures to install the GNIRS onto a side looking port on the Gemini 8M telescope.

1. Description This section describes the procedures to install the GNIRS onto a side looking port on the Gemini 8M telescope. 4.3 Instrument Installation & Removal 4.3.1. Installing Instrument on Side Looking Port 1. Description This section describes the procedures to install the GNIRS onto a side looking port on the Gemini

More information

SIMBOL-X. Peter Lechner MPI-HLL Project Review Schloss Ringberg, science background. mission. telescope.

SIMBOL-X. Peter Lechner MPI-HLL Project Review Schloss Ringberg, science background. mission. telescope. SIMBOL-X Peter Lechner MPI-HLL Project Review Schloss Ringberg, 24.04.07 science background mission telescope detector payload low energy detector science background science targets black holes astrophysics

More information

NIRCam Instrument Overview

NIRCam Instrument Overview NIRCam Instrument Overview Larry G. Burriesci Lockheed Martin Advanced Technology Center 3251 Hanover St., Palo Alto, CA 94304 ABSTRACT The Near Infrared (NIRCam) instrument for NASA s James Webb Space

More information

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Technical Proposal. Part 3B Product Development Plan

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Technical Proposal. Part 3B Product Development Plan ARTES Competitiveness & Growth Full Proposal Requirements for the Content of the Technical Proposal Part 3B Statement of Applicability and Proposal Submission Requirements Applicable Domain(s) Space Segment

More information

Payload Configuration, Integration and Testing of the Deformable Mirror Demonstration Mission (DeMi) CubeSat

Payload Configuration, Integration and Testing of the Deformable Mirror Demonstration Mission (DeMi) CubeSat SSC18-VIII-05 Payload Configuration, Integration and Testing of the Deformable Mirror Demonstration Mission (DeMi) CubeSat Jennifer Gubner Wellesley College, Massachusetts Institute of Technology 21 Wellesley

More information

PWO Crystal ECAL. Ren-yuan Zhu California Institute of Technology May 19 th US CMS Collaboration Meeting, May 19, 2001 Ren-yuan Zhu, Caltech

PWO Crystal ECAL. Ren-yuan Zhu California Institute of Technology May 19 th US CMS Collaboration Meeting, May 19, 2001 Ren-yuan Zhu, Caltech PWO Crystal ECAL Ren-yuan Zhu California Institute of Technology May 19 th 2001 1 The Calorimeter Supermodule 36 supermodules in barrel, 4 Dees in endcaps. 1700 crystals/supermodule, 4000 crystals/dee

More information

Proposal Smart Vision Sensors for Entomologically Inspired Micro Aerial Vehicles Daniel Black. Advisor: Dr. Reid Harrison

Proposal Smart Vision Sensors for Entomologically Inspired Micro Aerial Vehicles Daniel Black. Advisor: Dr. Reid Harrison Proposal Smart Vision Sensors for Entomologically Inspired Micro Aerial Vehicles Daniel Black Advisor: Dr. Reid Harrison Introduction Impressive digital imaging technology has become commonplace in our

More information

YamSat. YamSat Introduction. YamSat Team Albert Lin (NSPO) Yamsat website

YamSat. YamSat Introduction. YamSat Team Albert Lin (NSPO) Yamsat website Introduction Team Albert Lin (NSPO) Yamsat website http://www.nspo.gov.tw Major Characteristics Mission: Y: Young, developed by young people. A: Amateur Radio Communication M: Micro-spectrometer payload

More information

Spacecraft to Science Instrument Data Interface Control Document. Dwg. No

Spacecraft to Science Instrument Data Interface Control Document. Dwg. No Rev. ECO Description Checked Approval Date 01 Initial Release for S/C negotiation RFGoeke 4 Oct.02 Spacecraft to Science Instrument Data Interface Control Document Dwg. No. 43-03001 Revision 01 4 October

More information

ISUAL Test Plans and Procedures

ISUAL Test Plans and Procedures UCB Dwg. No: 8823-W7 Rev: A ISUAL Test Plans and Procedures Prepared by: H. Heetderks Approved by: S. Mende Revision History Rev Description By Date A Initial version containing summary material from dwg

More information

GLAST Large Area Telescope:

GLAST Large Area Telescope: DRAFT Rev 1 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software Overview W.B.S 4.1.7 Gunther Haller Stanford Linear Accelerator Center Manager,

More information

RADIOMETRIC PERFORMANCE OF THE CRIS INSTRUMENT FOR JPSS-1

RADIOMETRIC PERFORMANCE OF THE CRIS INSTRUMENT FOR JPSS-1 Place image here (10 x 3.5 ) RADIOMETRIC PERFORMANCE OF THE CRIS INSTRUMENT FOR JPSS-1 RONALD GLUMB, LAWRENCE SUWINSKI, STEVEN WELLS, REBECCA MALLOY CALCON Technical Conference Logan, UT August 22-25,

More information

OPAL Optical Profiling of the Atmospheric Limb

OPAL Optical Profiling of the Atmospheric Limb OPAL Optical Profiling of the Atmospheric Limb Alan Marchant Chad Fish Erik Stromberg Charles Swenson Jim Peterson OPAL STEADE Mission Storm Time Energy & Dynamics Explorers NASA Mission of Opportunity

More information

ANASAC, September 20, 2012

ANASAC, September 20, 2012 ANASAC, September 20, 2012 Construction Mark McKinnon Atacama Large Millimeter/submillimeter Array Karl G. Jansky Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array Antennas

More information

HASP Payload Specification and Integration Plan

HASP Payload Specification and Integration Plan Payload Title: High Altitude Tracking Solar Survey (HATS 2.0) Payload Class: Small Large (circle one) Payload ID: 09 Institution: Contact Name: Arizona State University Elizabeth Dyer Contact Phone: 6025702298

More information

Commissioning of Advanced Virgo

Commissioning of Advanced Virgo Commissioning of Advanced Virgo VSR1 VSR4 VSR5/6/7? Bas Swinkels, European Gravitational Observatory on behalf of the Virgo Collaboration GWADW Takayama, 26/05/2014 B. Swinkels Adv. Virgo Commissioning

More information

DOCUMENT CHANGE NOTICE (DCN) SHEET 1 OF 1

DOCUMENT CHANGE NOTICE (DCN) SHEET 1 OF 1 LAT Project Office SLAC DCN No. LAT-XR-00418-1 DOCUMENT CHANGE NOTICE (DCN) SHEET 1 OF 1 ORIGINATOR: Warren Davis PHONE: 650-926-4349 DATE: 11/26/01 CHANGE TITLE: Initial Release of Tracker Level III Specification

More information

A LATERAL SENSOR FOR THE ALIGNMENT OF TWO FORMATION-FLYING SATELLITES

A LATERAL SENSOR FOR THE ALIGNMENT OF TWO FORMATION-FLYING SATELLITES A LATERAL SENSOR FOR THE ALIGNMENT OF TWO FORMATION-FLYING SATELLITES S. Roose (1), Y. Stockman (1), Z. Sodnik (2) (1) Centre Spatial de Liège, Belgium (2) European Space Agency - ESA/ESTEC slide 1 Outline

More information

APPROVAL SHEET. TITLE : Prime Focus Image Spectrograph (PFIS) ICD of the Southern African Large Telescope (SALT)

APPROVAL SHEET. TITLE : Prime Focus Image Spectrograph (PFIS) ICD of the Southern African Large Telescope (SALT) APPROVAL SHEET TITLE : Prime Focus Image Spectrograph (PFIS) ICD of the Southern African Large Telescope (SALT) DOCUMENT NUMBER : 1520AS0002 ISSUE: 3 SYNOPSIS : This document describes the Interface between

More information

PREPARED BY: I. Miller DATE: 2004 May 23 CO-OWNERS REVISED DATE OF ISSUE/CHANGED PAGES

PREPARED BY: I. Miller DATE: 2004 May 23 CO-OWNERS REVISED DATE OF ISSUE/CHANGED PAGES Page 1 of 30 LIGHTMACHINERY TEST REPORT LQT 30.11-1 TITLE: HMI Michelson Interferometer Test Report Serial Number 1 - Wideband FSR INSTRUCTION OWNER HMI Project Manager PREPARED BY: I. Miller DATE: 2004

More information

The Application of SE Methodologies to the design and development of a Space Telescope

The Application of SE Methodologies to the design and development of a Space Telescope SWISSED15 The Application of SE Methodologies to the design and development of a Space Telescope Mike Johnson CSEP, Systems Engineering Teamleader at RUAG Space Overview / Aim / Agenda Aim: That you and

More information

CYGNSS Mission Update

CYGNSS Mission Update International Ocean Vector Wind Science Team Meeting Portland, OR 19-21 May 2015 CYGNSS Mission Update Chris Ruf (1) CYGNSS Principal Investigator Paul Chang (2), Maria Paola Clarizia (1), Scott Gleason

More information

Conceptual Structural Design

Conceptual Structural Design Conceptual Structural Design Description: This document contains information about the conceptual structural design in order to let the other participants in the CubeSat project get an idea of the structural

More information

EMI/EMC. GLAST Large Area Telescope. LAT Pre-Shipment Review. Gamma-ray Large Area Space Telescope. Neil Johnson NRL. Michael Lovellette NRL

EMI/EMC. GLAST Large Area Telescope. LAT Pre-Shipment Review. Gamma-ray Large Area Space Telescope. Neil Johnson NRL. Michael Lovellette NRL GLAST Large Area Telescope Gamma-ray Large Area Space Telescope LAT Pre-Shipment Review EMI/EMC EMI/EMC 1 Neil Johnson NRL Michael Lovellette NRL Stanford Linear Accelerator Center Purpose / Contents Demonstrate

More information

EPS Bridge Low-Cost Satellite

EPS Bridge Low-Cost Satellite EPS Bridge Low-Cost Satellite Results of a Concept Study being performed for Dr. Hendrik Lübberstedt OHB-System AG OpSE Workshop Walberberg 8th November 2005 EPS Bridge Key System Requirements Minimum

More information

Small Satellites: The Execution and Launch of a GPS Radio Occultation Instrument in a 6U Nanosatellite

Small Satellites: The Execution and Launch of a GPS Radio Occultation Instrument in a 6U Nanosatellite Small Satellites: The Execution and Launch of a GPS Radio Occultation Instrument in a 6U Nanosatellite Dave Williamson Director, Strategic Programs Tyvak Tyvak: Satellite Solutions for Multiple Organizations

More information

UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July 27, Secure Energy for America

UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July 27, Secure Energy for America RPSEA 09121-3300 3300-05 05 Autonomous Inspection of Subsea Facilities Phase I Final Presentation / Phase II Status Report UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July

More information

Rochester Institute of Technology. Wildfire Airborne Sensor Program (WASP) Project Overview

Rochester Institute of Technology. Wildfire Airborne Sensor Program (WASP) Project Overview Rochester Institute of Technology Wildfire Airborne Sensor Program (WASP) Project Overview Introduction The following slides describe a program underway at RIT The sensor system described herein is being

More information

INTRODUCTION The validity of dissertation Object of investigation Subject of investigation The purpose: of the tasks The novelty:

INTRODUCTION The validity of dissertation Object of investigation Subject of investigation The purpose: of the tasks The novelty: INTRODUCTION The validity of dissertation. According to the federal target program "Maintenance, development and use of the GLONASS system for 2012-2020 years the following challenges were determined:

More information

Greg Mandt. AMS 90 th Annual Meeting 6th Annual Symposium on Future National Operational Environmental Satellite Systems NPOESS and GOES R

Greg Mandt. AMS 90 th Annual Meeting 6th Annual Symposium on Future National Operational Environmental Satellite Systems NPOESS and GOES R An Overview of the GOES R Program Greg Mandt System Program Director AMS 90 th Annual Meeting 6th Annual Symposium on Future National Operational Environmental Satellite Systems NPOESS and GOES R January19

More information

Holography Transmitter Design Bill Shillue 2000-Oct-03

Holography Transmitter Design Bill Shillue 2000-Oct-03 Holography Transmitter Design Bill Shillue 2000-Oct-03 Planned Photonic Reference Distribution for Test Interferometer The transmitter for the holography receiver is made up mostly of parts that are already

More information

Satellite Testing. Prepared by. A.Kaviyarasu Assistant Professor Department of Aerospace Engineering Madras Institute Of Technology Chromepet, Chennai

Satellite Testing. Prepared by. A.Kaviyarasu Assistant Professor Department of Aerospace Engineering Madras Institute Of Technology Chromepet, Chennai Satellite Testing Prepared by A.Kaviyarasu Assistant Professor Department of Aerospace Engineering Madras Institute Of Technology Chromepet, Chennai @copyright Solar Panel Deployment Test Spacecraft operating

More information

1. SMOS Status 1.1 Payload 1.2 Platform 1.3 Satellite 1.4 Launcher 1.5 FOS 1.6 DPGS 2. Other Developments 3. Future (Near & Far) 4.

1. SMOS Status 1.1 Payload 1.2 Platform 1.3 Satellite 1.4 Launcher 1.5 FOS 1.6 DPGS 2. Other Developments 3. Future (Near & Far) 4. 1. SMOS Status 1.1 Payload 1.2 Platform 1.3 Satellite 1.4 Launcher 1.5 FOS 1.6 DPGS 2. Other Developments 3. Future (Near & Far) 4. Schedule 1 1.1 Payload General: Structural / Thermal Model test campaigns

More information

Astrophysics. Paul Hertz Director, Astrophysics Division Science Mission

Astrophysics. Paul Hertz Director, Astrophysics Division Science Mission National Aeronautics and Space Administration Astrophysics Large Mission Concept Studies Kick Off AAS 227th Meeting Kissimmee, Florida January 6, 2016 Paul Hertz Director, Astrophysics Division Science

More information

Industry Day of the Copernicus Sentinel-5 and Jason-CS Projects

Industry Day of the Copernicus Sentinel-5 and Jason-CS Projects Industry Day of the Copernicus Sentinel-5 and Jason-CS Projects With the present announcement, the European Space Agency and Astrium GmbH Satellites (Germany) inform the EMITS Users (European Companies

More information

PREPARED BY: I. Miller DATE: 2004 May 23 CO-OWNERS REVISED DATE OF ISSUE/CHANGED PAGES

PREPARED BY: I. Miller DATE: 2004 May 23 CO-OWNERS REVISED DATE OF ISSUE/CHANGED PAGES Page 1 of 30 LIGHTMACHINERY TEST REPORT LQT 30.11-2 TITLE: HMI Michelson Interferometer Test Report Serial Number 2 - Narrowband FSR INSTRUCTION OWNER HMI Project Manager PREPARED BY: I. Miller DATE: 2004

More information

MONS Field Monitor. System Definition Phase. Design Report

MONS Field Monitor. System Definition Phase. Design Report Field Monitor System Definition Phase Design Report _AUS_PL_RP_0002(1) Issue 1 11 April 2001 Prepared by Date11 April 2001 Chris Boshuizen and Leigh Pfitzner Checked by Date11 April 2001 Tim Bedding Approved

More information

Airbus DS ESA Phase-0 L5 Spacecraft/Orbital Concept Overview. Emanuele Monchieri 6 th March 2017

Airbus DS ESA Phase-0 L5 Spacecraft/Orbital Concept Overview. Emanuele Monchieri 6 th March 2017 Airbus DS ESA Phase-0 L5 Spacecraft/Orbital Concept Overview Emanuele Monchieri 6 th March 2017 Airbus DS ESA Phase-0 L5 Spacecraft/Orbital Concept Overview Contents L5 Mission Outline Mission Concept

More information

Mission Goals. Brandi Casey (Project Manager)

Mission Goals. Brandi Casey (Project Manager) Mission Goals Brandi Casey (Project Manager) 1 What is it? TREADS NanoSat (TREADS-N) Testbed for Responsive Experiments And Demonstrations in Space (TREADS) TREADS is a 'full-service' technology demonstration

More information

PREPARED BY: I. Miller DATE: 2004 May 23 CO-OWNERS REVISED DATE OF ISSUE/CHANGED PAGES

PREPARED BY: I. Miller DATE: 2004 May 23 CO-OWNERS REVISED DATE OF ISSUE/CHANGED PAGES Page 1 of 34 LIGHTMACHINERY TEST REPORT LQT 30.11-3 TITLE: HMI Michelson Interferometer Test Report Serial Number 3 wide band FSR INSTRUCTION OWNER HMI Project Manager PREPARED BY: I. Miller DATE: 2004

More information

Pin photodiode Quality Assurance Procedure

Pin photodiode Quality Assurance Procedure GENEVE, SUISSE GENEVA, SWITZERLAND ORGANISATION EUROPEENE POUR LA RECHERCHE NUCLEAIRE EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Laboratoire Européen pour la Physique des Particules European Laboratory

More information

Space Technology FY 2013

Space Technology FY 2013 Space Technology FY 2013 Dr. Mason Peck, Office of the Chief Technologist ASEB April 4, 2012 O f f i c e o f t h e C h i e f T e c h n o l o g i s t Technology at NASA NASA pursues breakthrough technologies

More information

Selecting an image sensor for the EJSM VIS/NIR camera systems

Selecting an image sensor for the EJSM VIS/NIR camera systems Selecting an image sensor for the EJSM VIS/NIR camera systems presented by Harald Michaelis (DLR-PF) Folie 1 EJSM- Jan. 18th 2010; ESTEC What for a detector/sensor we shall chose for EJSM? Vortragstitel

More information

NASA s X2000 Program - an Institutional Approach to Enabling Smaller Spacecraft

NASA s X2000 Program - an Institutional Approach to Enabling Smaller Spacecraft NASA s X2000 Program - an Institutional Approach to Enabling Smaller Spacecraft Dr. Leslie J. Deutsch and Chris Salvo Advanced Flight Systems Program Jet Propulsion Laboratory California Institute of Technology

More information

CubeSat Proximity Operations Demonstration (CPOD) Mission Update Cal Poly CubeSat Workshop San Luis Obispo, CA

CubeSat Proximity Operations Demonstration (CPOD) Mission Update Cal Poly CubeSat Workshop San Luis Obispo, CA CubeSat Proximity Operations Demonstration (CPOD) Mission Update Cal Poly CubeSat Workshop San Luis Obispo, CA 04-22-2015 Austin Williams VP, Space Vehicles ConOps Overview - Designed to Maximize Mission

More information

Coronal and heliospheric imaging instrumentation development at RAL Space

Coronal and heliospheric imaging instrumentation development at RAL Space Coronal and heliospheric imaging instrumentation development at RAL Space JA Davies, CJ Eyles, DK Griffin, RA Harrison, KF Middleton, AG Richards, JK Rogers, SJ Tappin, IAJ Tosh, NR Waltham Heritage (1)

More information

ALMA Interferometer and Band 7 Cartridge

ALMA Interferometer and Band 7 Cartridge ALMA Interferometer and Band 7 Cartridge B7 Cartridge designed, assembled and tested by: S. Mahieu, D. Maier (mixer team lead), B. Lazareff (now at IPAG) G. Celestin, J. Chalain, D. Geoffroy, F. Laslaz,

More information

CCD Procurement Specification EUV Imaging Spectrometer

CCD Procurement Specification EUV Imaging Spectrometer Solar-B EIS * CCD Procurement Specification EUV Imaging Spectrometer Title CCD Procurement specification Doc ID MSSL/SLB-EIS/SP/02 ver 2.0 Author Chris McFee Date 25 March 2001 Ver 2.0 Page 2 of 10 Contents

More information

The Virtual Spacecraft Reference Facility

The Virtual Spacecraft Reference Facility The Virtual Spacecraft M.Schön, M.Arcioni, D.Temperanza, K.Hjortnaes Michael.Schoen@esa.int On-Board Software Systems Section 1 Agenda Why? What? How? When? 2 The Virtual Spacecraft architecture view EuroSim

More information

Issue 1.0. Date 2 th June Signature and Date. Document Prepared By: Document Approved By: Document Released By: Signature and Date

Issue 1.0. Date 2 th June Signature and Date. Document Prepared By: Document Approved By: Document Released By: Signature and Date Document Title Document Number Deliverable Items List 1.1D070G Issue 1.0 Date 2 th June 2004 Document Prepared By: Document Approved By: Document Released By: David Lunney Mark Casali David Lunney Signature

More information

Hosted Payload Interface Guide for Proposers CII for Earth Science Instruments Overview. Randy Regan NASA CII Team Chief Engineer

Hosted Payload Interface Guide for Proposers CII for Earth Science Instruments Overview. Randy Regan NASA CII Team Chief Engineer Hosted Payload Interface Guide for Proposers CII for Earth Science Instruments Overview Randy Regan NASA CII Team Chief Engineer CII Overview Agenda CII Purpose and Goal Approach Workshop #3 Purpose and

More information

Aquarius Project, Spacecraft, Instrument and Data Processing Status

Aquarius Project, Spacecraft, Instrument and Data Processing Status Aquarius Project, Spacecraft, Instrument and Data Processing Status Gene Carl Feldman, Joel Gales, Liang Hong, Norman Kuring, Tommy Owens, Fred Patt, Alicia Scott, John Wilding Cal-Val Virtual Workshop

More information

Utilizing Commercial DSLR for High Resolution Earth Observation Satellite

Utilizing Commercial DSLR for High Resolution Earth Observation Satellite SSC18-XII-03 Utilizing Commercial DSLR for High Resolution Earth Observation Satellite Nobutada Sako Canon Electronics Inc. 3-5-10, Shibakoen, Minato-ku, Tokyo 105-0011, Japan; +81-3-6910-1105 sako.nobutada@canon-elec.co.jp

More information

Status of ATLAS & CMS Experiments

Status of ATLAS & CMS Experiments Status of ATLAS & CMS Experiments Atlas S.C. Magnet system Large Air-Core Toroids for µ Tracking 2Tesla Solenoid for inner Tracking (7*2.5m) ECAL & HCAL outside Solenoid Solenoid integrated in ECAL Barrel

More information

ABSTRACT INTRODUCTION

ABSTRACT INTRODUCTION COMPASS-1 PICOSATELLITE: STRUCTURES & MECHANISMS Marco Hammer, Robert Klotz, Ali Aydinlioglu Astronautical Department University of Applied Sciences Aachen Hohenstaufenallee 6, 52064 Aachen, Germany Phone:

More information

Constellation Systems Division

Constellation Systems Division Lunar National Aeronautics and Exploration Space Administration www.nasa.gov Constellation Systems Division Introduction The Constellation Program was formed to achieve the objectives of maintaining American

More information

Satellite Technology for Future Applications

Satellite Technology for Future Applications Satellite Technology for Future Applications WSRF Panel n 4 Dubai, 3 March 2010 Guy Perez VP Telecom Satellites Programs 1 Commercial in confidence / All rights reserved, 2010, Thales Alenia Space Content

More information

Power modeling and budgeting design and validation with in-orbit data of two commercial LEO satellites

Power modeling and budgeting design and validation with in-orbit data of two commercial LEO satellites SSC17-X-08 Power modeling and budgeting design and validation with in-orbit data of two commercial LEO satellites Alan Kharsansky Satellogic Av. Raul Scalabrini Ortiz 3333 piso 2, Argentina; +5401152190100

More information

Massport Capital Programs Enterprise Schedule Management. Primavera Schedule Toolkit Design. January 2018 Version 1.0

Massport Capital Programs Enterprise Schedule Management. Primavera Schedule Toolkit Design. January 2018 Version 1.0 Massport Capital Programs Enterprise Schedule Management Primavera Schedule Toolkit Design January 2018 Version 1.0 Contents 1.0 INTRODUCTION 2 1.1 DISCLAIMER 3 2.0 TOOLKIT SCHEDULE COMPONENTS 4 2.1 SCHEDULE

More information

Typical Project Life Cycle

Typical Project Life Cycle Typical Project Life Cycle D. KANIPE 1/29/2015 Contract Initiation VISION REQUEST FOR INFORMATION REQUEST FOR PROPOSAL SOURCE EVALUATION BOARD RFI RFP Proposals Evaluated Companies Respond Companies Submit

More information

The Nemo Bus: A Third Generation Nanosatellite Bus for Earth Monitoring and Observation

The Nemo Bus: A Third Generation Nanosatellite Bus for Earth Monitoring and Observation The Nemo Bus: A Third Generation Nanosatellite Bus for Earth Monitoring and Observation FREDDY M. PRANAJAYA Manager, Advanced Systems Group S P A C E F L I G H T L A B O R A T O R Y University of Toronto

More information

RAX: The Radio Aurora explorer

RAX: The Radio Aurora explorer RAX: Matt Bennett University of Michigan CubeSat Workshop Cal Poly, San Luis Obispo April 22 nd, 2009 Background Sponsored by National Science Foundation University of Michigan and SRI International Collaboration

More information

From concept to launch of remote sensing satellites

From concept to launch of remote sensing satellites ENMAP Summer School on Remote Sensing Data Analysis From concept to launch of remote sensing satellites Roland Doerffer Retired from Helmholtz Zentrum Geesthacht Institute of Coastal Research Now: Brockmann

More information

ALMA. ALMA Construction Status. Mark McKinnon. ALMA-NA Project Director/Manager September 28, 2011

ALMA. ALMA Construction Status. Mark McKinnon. ALMA-NA Project Director/Manager September 28, 2011 Construction Status Mark McKinnon -NA Project Director/Manager September 28, 2011 Antennas at AOS 18 antennas August 13, 2011 17 antennas August 6, 2011 Total of 44 antennas at the site (21NA, 13 EA, 10

More information

SWOT PROJECT STATUS T. LAFON. SDT Toulouse 7 JULY SWOT Status

SWOT PROJECT STATUS T. LAFON. SDT Toulouse 7 JULY SWOT Status SWOT PROJECT STATUS T. LAFON SDT Toulouse 7 JULY 2015 1 ITEM System Satellite RFU/ DUPLEXER NADIR Ku DORIS Mission ground segment (SDS) MAJOR PHASE B ACTIVITIES OVERVIEW Status System engineering & architecture,

More information

Ku-Band Receiver System for SHAO

Ku-Band Receiver System for SHAO Ku-Band Receiver System for SHAO Overview Brent Willoughby July 2014 Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array

More information

Virgo status and commissioning results

Virgo status and commissioning results Virgo status and commissioning results L. Di Fiore for the Virgo Collaboration 5th LISA Symposium 13 july 2004 VIRGO is an French-Italian collaboration for Gravitational Wave research with a 3 km long

More information

Series manufacture of the LHC main. dipole magnets. Notes about the CERN. approach to industrial. production. C.Wyss & L.

Series manufacture of the LHC main. dipole magnets. Notes about the CERN. approach to industrial. production. C.Wyss & L. Series manufacture of the LHC main dipole magnets Notes about the CERN approach to industrial production C.Wyss & L.Rossi / CERN SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 1 1232 +16 units, 8.3 T nominal

More information

Current Status of Hayabusa2. Yuichi Tsuda, Project Manager, Hayabusa2 Project Japan Aerospace Exploration Agency

Current Status of Hayabusa2. Yuichi Tsuda, Project Manager, Hayabusa2 Project Japan Aerospace Exploration Agency Current Status of Hayabusa2 Yuichi Tsuda, Project Manager, Hayabusa2 Project Japan Aerospace Exploration Agency Small Body Assessment Group 18th Meeting, Jan.18, 2018 Present Status of Hayabusa2 (as of

More information

Orbicraft Pro Complete CubeSat kit based on Raspberry-Pi

Orbicraft Pro Complete CubeSat kit based on Raspberry-Pi Orbicraft Pro Complete CubeSat kit based on Raspberry-Pi (source IAA-AAS-CU-17-10-05) Speaker: Roman Zharkikh Authors: Roman Zharkikh Zaynulla Zhumaev Alexander Purikov Veronica Shteyngardt Anton Sivkov

More information

SPS Chapter Research Award Interim Report

SPS Chapter Research Award Interim Report SPS Chapter Research Award Interim Report Project Title Name of School Construction of a Watt Balance to Redefine the Kilogram University of Maryland, College Park SPS Chapter Number 4155 Total Amount

More information

Instrument Characteristics

Instrument Characteristics II Workshop Instrument Characteristics Marco Romoli Torino, 12-13 dicembre 2012 In order to meet the requirements: Coronal Imaging Wavelength range Spatial Resolution Field-of-view VL: 580-640 nm UV: 121.6

More information

Hardware Commissioning

Hardware Commissioning Hardware Commissioning an update the status of the documentation the report on the resources the programme of the coming year Roberto Saban on behalf of the Hardware Commissioning Working Group status

More information

Rome, Changing of the Requirements and Astrofein s Business Models for Cubesat Deployer

Rome, Changing of the Requirements and Astrofein s Business Models for Cubesat Deployer Rome, 07.12.2017 4 th IAA Conference on University Satellite Missions and Cubesat Workshop Changing of the Requirements and Astrofein s Business Models for Cubesat Deployer Stephan Roemer Head of Space

More information

SPACE. (Some space topics are also listed under Mechatronic topics)

SPACE. (Some space topics are also listed under Mechatronic topics) SPACE (Some space topics are also listed under Mechatronic topics) Dr Xiaofeng Wu Rm N314, Bldg J11; ph. 9036 7053, Xiaofeng.wu@sydney.edu.au Part I SPACE ENGINEERING 1. Vision based satellite formation

More information

Figure 1. Proposed Mission Operations Functions. Key Performance Parameters Success criteria of an amateur communicator on board of Moon-exploration

Figure 1. Proposed Mission Operations Functions. Key Performance Parameters Success criteria of an amateur communicator on board of Moon-exploration Title: CubeSat amateur laser communicator with Earth to Moon orbit data link capability Primary Point of Contact (POC) & email: oregu.nijuniku@jaxa.jp Co-authors: Oleg Nizhnik Organization: JAXA Need Available

More information

The Colorado Student Space Weather Experiment (CSSWE) On-Orbit Performance

The Colorado Student Space Weather Experiment (CSSWE) On-Orbit Performance The Colorado Student Space Weather Experiment (CSSWE) On-Orbit Performance David Gerhardt 1, Scott Palo 1, Xinlin Li 1,2, Lauren Blum 1,2, Quintin Schiller 1,2, and Rick Kohnert 2 1 University of Colorado

More information

NASA s Detailed Response to the James Webb Space Telescope Independent Comprehensive Review Panel Report

NASA s Detailed Response to the James Webb Space Telescope Independent Comprehensive Review Panel Report NASA s Detailed Response to the James Webb Space Telescope Independent Comprehensive Review Panel Report NASA appreciates the insightful recommendations of the Independent Comprehensive Review Panel (ICRP)

More information

Optimization of coupling between Adaptive Optics and Single Mode Fibers ---

Optimization of coupling between Adaptive Optics and Single Mode Fibers --- Optimization of coupling between Adaptive Optics and Single Mode Fibers --- Non common path aberrations compensation through dithering K. Saab 1, V. Michau 1, C. Petit 1, N. Vedrenne 1, P. Bério 2, M.

More information

Advanced Electrical Bus (ALBus) CubeSat Technology Demonstration Mission

Advanced Electrical Bus (ALBus) CubeSat Technology Demonstration Mission Advanced Electrical Bus (ALBus) CubeSat Technology Demonstration Mission April 2015 David Avanesian, EPS Lead Tyler Burba, Software Lead 1 Outline Introduction Systems Engineering Electrical Power System

More information

DTIC il ELECTED 00HD IN FILE COP ( II 'O T1 T Final Report. Contract No. N K for. Multifilter Spectrometer (FEB)

DTIC il ELECTED 00HD IN FILE COP ( II 'O T1 T Final Report. Contract No. N K for. Multifilter Spectrometer (FEB) IN FILE COP ( t'- rm -mm Final Report for Multifilter Spectrometer (FEB) for Microwave Atmospheric Sounder Contract No. N00014-86.K-02368 by Dr. Charlesm L. Croakey Communications and Space Sciences Laboratory

More information

Uranus Exploration Challenges

Uranus Exploration Challenges Uranus Exploration Challenges Steve Matousek Workshop on the Study of Icy Giant Planet (2014) July 30, 2014 (c) 2014 California Institute of Technology. Government sponsorship acknowledged. JPL URS clearance

More information

Use of the Deep Impact HRI Instrument to Observe Exoplanets Via Microlensing

Use of the Deep Impact HRI Instrument to Observe Exoplanets Via Microlensing Use of the Deep Impact HRI Instrument to Observe Exoplanets Via Microlensing 16 th International Conference on Gravitational Microlensing Steve Wissler [1] David Bennett [2] Tim Larson [1] [1] Jet Propulsion

More information

CRaTER Short Form Functional Test Procedure in Thermal/Vacuum. Dwg. No

CRaTER Short Form Functional Test Procedure in Thermal/Vacuum. Dwg. No Rev. ECO Description Author Approved Date 01 32-248 Use for SN2 Thermal-Vacuum testing RFGoeke 9/27/07 CRaTER Short Form Functional Test Procedure in Thermal/Vacuum Dwg. No. 32-06003.0201 Revision 01 September

More information

Michigan Multipurpose MiniSat M-Cubed. Kiril Dontchev Summer CubeSat Workshop: 8/9/09

Michigan Multipurpose MiniSat M-Cubed. Kiril Dontchev Summer CubeSat Workshop: 8/9/09 Michigan Multipurpose MiniSat M-Cubed Kiril Dontchev Summer CubeSat Workshop: 8/9/09 Michigan NanoSat Pipeline Inputs Outputs U of M Ideas Innovative technology Entrepreneurial thought Science Papers Flight

More information

Compact High Resolution Imaging Spectrometer (CHRIS) siraelectro-optics

Compact High Resolution Imaging Spectrometer (CHRIS) siraelectro-optics Compact High Resolution Imaging Spectrometer (CHRIS) Mike Cutter (Mike_Cutter@siraeo.co.uk) Summary CHRIS Instrument Design Instrument Specification & Performance Operating Modes Calibration Plan Data

More information