Series manufacture of the LHC main. dipole magnets. Notes about the CERN. approach to industrial. production. C.Wyss & L.

Size: px
Start display at page:

Download "Series manufacture of the LHC main. dipole magnets. Notes about the CERN. approach to industrial. production. C.Wyss & L."

Transcription

1 Series manufacture of the LHC main dipole magnets Notes about the CERN approach to industrial production C.Wyss & L.Rossi / CERN SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 1

2 units, 8.3 T nominal field, 9 T ultimate field, 2 x 56 mm coil apertures, 15 m long, 28 t heavy Total value before cryostating: about 1BCHF (800 M$) Design and model work (1-m length) at CERN Full-length prototype collared coils made in industry (3 vendors) All prototype cold mass assembled at CERN Pre-series contracts for 3 x 30 cold masses Assembly of the first 2-4 pre-series cold masses / vendor at CERN, to train industry personnel Series contracts for 3 x 416 cold masses, after full testing of 2 preseries units/vendor and manufacture of 6-8 pre-series units/vendor SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 2

3 Highest magnet uniformity (10-4 ) necessary for best machine performance and simplest installation sequence in the tunnel For the pre-series, all main components were directly procured by CERN, providing thus the contractors qualification by CERN For series production, nearly all main components were directly procured by CERN (45 contracts, 4 inter- laboratory agreements - India, Russia, USA) Double source for critical items: SC cables, fine-blanked parts (collars and laminations) and corrector magnets All other CERN provided materials and components are from a single source Number of contracts minimized to achieve economies of scale and minimize the amount of CERN resources for close follow-up SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 3

4 Heavy tooling designed and procured by CERN, except for coil winding machines and coil curing presses Essential quality control equipment (coil e-module, geometrical, electrical, field quality) designed and supplied by CERN Maximum sharing of know-how among the CERN staff in charge of contract follow-up Implementation of Statistical Process Control (SPC) for the properties of materials, components, sub-assemblies and of the warm and cold tested magnets. Resident inspectors under CERN contract at the vendors premises SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 4

5 Responsibility for design and performance with CERN Responsibility for faultless assembly with the vendors Responsibility for operation and maintenance of the tooling with the owners of the tooling design Quality checks after completion of each main assembly step to intercept errors at the earliest moment and minimize the loss of added value Bonus (1% ) for magnets needing no more than three quenches to reach 9 T (reduced test time and hence cost for CERN) SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 5

6 Status on June 30, 2005 Dipole cold masses C.M.Contractual Sep-06 Jul-06 May-06 Mar-06 Jan-06 Nov-05 Sep-05 Jul-05 May-05 Mar-05 Jan-05 Nov-04 Sep-04 Jul-04 May-04 Mar-04 Jan-04 Nov-03 Sep-03 Jul-03 May-03 Mar-03 Jan-03 Nov-02 Sep-02 Jul-02 May-02 Mar-02 Jan-02 Nov-01 Sep-01 Jul-01 May-01 Mar-01 Jan SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN Collared coil accepted Just in time C.M. Delivered Years

7 Status on June 30, 2005: (71 %) collared coils accepted (61 %) cold masses delivered (51%) cryomagnets cold tested Rejected cold masses: for unsatisfactory quench performance - 10 for electrical failure (mostly quench heaters) - 2 for mechanical non-conformities SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 7

8 11 cold masses repaired without magnet disassembly 15 cold masses were disassembled (9 for quench performance, 6 for electrical failure) Out of the 26 rejected cold masses, 25 were repaired and only one was scrapped About 60% of the defaults could be clearly ascribed to assembly errors or to the non-respect of agreed procedures For the remaining 40 %, the responsibility was shared between CERN and the vendor The ramping up of series manufacture is the period were most errors occurred, because of the training of additional staff SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 8

Summary of Industrialization

Summary of Industrialization Summary of Industrialization Symposium Short list of highlights Summary of findings &discussions Conclusion 1 Time Agenda Industrialization Symposium at SFR 2005, status 4 July 2005, D.Proch Topics Speaker

More information

INDUSTRIAL CONTROLS FOR TEST SYSTEMS FROM SUPERCONDUCTING STRANDS TILL MAGNET FIDUCIALISATION IN THE TUNNEL FOR THE LHC PROJECT

INDUSTRIAL CONTROLS FOR TEST SYSTEMS FROM SUPERCONDUCTING STRANDS TILL MAGNET FIDUCIALISATION IN THE TUNNEL FOR THE LHC PROJECT INDUSTRIAL CONTROLS FOR TEST SYSTEMS FROM SUPERCONDUCTING STRANDS TILL MAGNET FIDUCIALISATION IN THE TUNNEL FOR THE LHC PROJECT ABSTRACT A. Rijllart, C. Charrondière, B. Khomenko, M. Marchesotti, E. Michel,

More information

Hardware Commissioning

Hardware Commissioning Hardware Commissioning an update the status of the documentation the report on the resources the programme of the coming year Roberto Saban on behalf of the Hardware Commissioning Working Group status

More information

LHC ARC DIPOLE STATUS REPORT

LHC ARC DIPOLE STATUS REPORT LHC ARC DIPOLE STATUS REPORT C.Wyss, CERN, Geneva, Switzerland # Abstract The LHC, a 7 Tev proton collider presently under construction at CERN, requires 1232 superconducting (SC) dipole magnets, featuring

More information

ELQA maintenance, diagnostics and data handling

ELQA maintenance, diagnostics and data handling ELQA maintenance, diagnostics and data handling Jaromir Ludwin The Henryk Niewodniczański Institute of Nuclear Physics Polish Academy of Sciences, Kraków Poland WP definition KE2058/TE KE2059/TE KE2060/TE

More information

Cryogenic Testing of Superconducting Corrector Magnets for the LHC Main Dipole

Cryogenic Testing of Superconducting Corrector Magnets for the LHC Main Dipole Cryogenic Testing of Superconducting Corrector Magnets for the LHC Main Dipole A.M. Puntambekar SC Tech Lab, AAMD Div. Raja Ramanna Centre For Advanced Technology, Indore Workshop on Cryogenic Science

More information

28/11/2016 Juan Carlos Perez TE-MSC-MDT Jose Ferradas TE-MSC-MDT

28/11/2016 Juan Carlos Perez TE-MSC-MDT Jose Ferradas TE-MSC-MDT TE-MSC-MDT 28/11/2016 Juan Carlos Perez Jose Ferradas TE-MSC-MDT TE-MSC-MDT Outline Description and status of the project Project TE3536 at Laboratory 927 Magnet Design and Technology (MDT) Main results

More information

Miljardkonferensen Procurement at CERN

Miljardkonferensen Procurement at CERN Miljardkonferensen Procurement at CERN 29 April 2015, Stockholm Anders Unnervik Procurement at CERN Introduction to CERN Procurement budget What does CERN buy? How? Procedures and Rules What is in it for

More information

CONSTRUCTION AND TESTING OF ARC DIPOLES AND QUADRUPOLES FOR THE RELATIVISTIC HEAVY ION COLLIDER (RHIC) AT BNL *

CONSTRUCTION AND TESTING OF ARC DIPOLES AND QUADRUPOLES FOR THE RELATIVISTIC HEAVY ION COLLIDER (RHIC) AT BNL * 996 IEEE. Personal use of this material is permitted. However, permission to reprint/republish this material for advertising or promotional purposes or for creating new collective works for resale or redistribution

More information

Standard ELQA measurements, ELQA for splice and proximity equipment consolidation

Standard ELQA measurements, ELQA for splice and proximity equipment consolidation Standard ELQA measurements, ELQA for splice and proximity equipment consolidation Piotr Jurkiewicz The Henryk Niewodniczański Institute of Nuclear Physics Polish Academy of Sciences, Kraków Poland ELQA

More information

Status of ATLAS & CMS Experiments

Status of ATLAS & CMS Experiments Status of ATLAS & CMS Experiments Atlas S.C. Magnet system Large Air-Core Toroids for µ Tracking 2Tesla Solenoid for inner Tracking (7*2.5m) ECAL & HCAL outside Solenoid Solenoid integrated in ECAL Barrel

More information

Residual Resistivity Ratio (RRR) Measurements of LHC Superconducting NbTi Cable Strands

Residual Resistivity Ratio (RRR) Measurements of LHC Superconducting NbTi Cable Strands EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 896 Residual Resistivity Ratio (RRR) Measurements of LHC Superconducting

More information

CHAPTER 7 MAIN MAGNETS IN THE ARCS

CHAPTER 7 MAIN MAGNETS IN THE ARCS CHAPTER 7 MAIN MAGNETS IN THE ARCS 7.1 OVERVIEW 7.1.1 Superconducting Technology for Accelerator Magnets The Large Hadron Collider relies heavily on superconducting magnets which are at the edge of the

More information

Physical Properties Measurement System (PPMS): Detailed specifications: Basic unit cryogen- free

Physical Properties Measurement System (PPMS): Detailed specifications: Basic unit cryogen- free Physical Properties Measurement System (PPMS): A Cryogen-free Physical Properties Measurement system that operates over a wider range of temperature and magnetic fields: fully automated/computer controlled

More information

The Superconducting Strand for the CMS Solenoid Conductor

The Superconducting Strand for the CMS Solenoid Conductor The Superconducting Strand for the CMS Solenoid Conductor B. Curé, B. Blau, D. Campi, L. F. Goodrich, I. L. Horvath, F. Kircher, R. Liikamaa, J. Seppälä, R. P. Smith, J. Teuho, and L. Vieillard Abstract-

More information

High Voltage Instrumentation Cables for the ITER Superconducting Magnet Systems

High Voltage Instrumentation Cables for the ITER Superconducting Magnet Systems High Voltage Instrumentation Cables for the ITER Superconducting Magnet Systems Summary for Call for Nominations 1. Background and scope ITER will be the world's largest experimental facility to demonstrate

More information

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension XFEL Cryo System Possible extension 1 st stage Project X Collaboration Meeting, FNAL September 8-9, 2010 (XFEL WP10 & WP13) Outline 2 XFEL accelerator structure TESLA technology Basic cryogenic parameters

More information

APAC 2007, Raja Ramanna Centre for Advanced Technology(RRCAT), Indore, India LHC STATUS. Lyndon Evans, CERN, Geneva, Switzerland

APAC 2007, Raja Ramanna Centre for Advanced Technology(RRCAT), Indore, India LHC STATUS. Lyndon Evans, CERN, Geneva, Switzerland LHC STATUS Lyndon Evans, CERN, Geneva, Switzerland Abstract The installation of the Large Hadron Collider at CERN is now approaching completion. Almost 1100 of the 1232 main bending magnets are installed

More information

LHC COMMISSIONING AT HIGHER ENERGY

LHC COMMISSIONING AT HIGHER ENERGY LHC COMMISSIONING AT HIGHER ENERGY P. Collier, F. Bordry, J. Wenninger, CERN, Geneva, Switzerland Abstract The LHC has just come to the end of its first Long Shutdown (LS1) and preparations are underway

More information

Slow Power Abort Check

Slow Power Abort Check Operation Methods Date: 27-11-2003 Slow Power Abort Check Prepared By Daniel Babu P, BARC, Mumbai Sridhar S, IGCAR, Kalpakkam Department of Atomic Energy, India Checked and Approved By Dr Vinod Chohan

More information

CERN-EC SUPPORT FOR SESAME MAGNETS

CERN-EC SUPPORT FOR SESAME MAGNETS 1. PUBLISHABLE SUMMARY CERN-EC SUPPORT FOR SESAME MAGNETS WP1 Project Management and Technical Coordination A complex preparation involving several CERN offices (Director-General, Legal service, Procurement

More information

Brett Parker, representing the

Brett Parker, representing the Compact Superconducting Magnet Solution for the 20 mr Crossing Angle Final Focus Brett Parker, representing the Brookhaven Superconducting Magnet Division Message: Progress continues on the compact superconducting

More information

Attitude Determination and Control Specifications

Attitude Determination and Control Specifications Attitude Determination and Control Specifications 1. SCOPE The attitude determination and control sub system will passively control the orientation of the two twin CubeSats. 1.1 General. This specification

More information

Status of the 12 GeV Upgrade and the SHMS R&D and PED Projects. Antje Bruell Hall C meeting, Jan Page 1

Status of the 12 GeV Upgrade and the SHMS R&D and PED Projects. Antje Bruell Hall C meeting, Jan Page 1 Status of the 12 GeV Upgrade and the SHMS R&D and PED Projects Antje Bruell Hall C meeting, Jan 26 2007 Page 1 Outline Status of the 12 GeV Upgrade New management structure Time lines Latest cost profile

More information

Who is Meyer Tool.! What US Manufacturing does for the economy.! Why support of basic science is important.!

Who is Meyer Tool.! What US Manufacturing does for the economy.! Why support of basic science is important.! Who is Meyer Tool. What US Manufacturing does for the economy. Why support of basic science is important. Why a strong US-industrial /US-laboratory partnership is important. One of two 500MHz Cryomodule

More information

European Organisation for Nuclear Research (CERN) QUACO PCP Lessons Learned so far.

European Organisation for Nuclear Research (CERN) QUACO PCP Lessons Learned so far. European Organisation for Nuclear Research (CERN) QUACO PCP Lessons Learned so far. Christophe Veys PCP expert CERN Procurement Service EAFIP-Prague 14 November 2017 1 7 PCP s and 5 PPI s BIG BANG L'Organisation

More information

THE CRYOGENIC SYSTEM OF TESLA

THE CRYOGENIC SYSTEM OF TESLA THE CRYOGENIC SYSTEM OF TESLA S. Wolff, DESY, Notkestr. 85, 22607 Hamburg, Germany for the TESLA collaboration Abstract TESLA, a 33 km long 500 GeV centre-of-mass energy superconducting linear collider

More information

Packaging of Cryogenic Components

Packaging of Cryogenic Components Packaging of Cryogenic Components William J. Schneider Senior Mechanical Engineer Emeritus November 19-23 2007 1 Packaging of Cryogenic Components Day one Introduction and Overview 2 What is important?

More information

ASG presentation and activities. Roberto Penco (consultant to ASG)

ASG presentation and activities. Roberto Penco (consultant to ASG) ASG presentation and activities Roberto Penco (consultant to ASG) CASTEL GROUP SIMA engineering + TECTUBI PARAMED X The near past: ACTIVITY SITE LHC Dipoles (30+386) Internal area (14000 m 2 ) LHC Corrector

More information

Versatile transceiver production and quality assurance

Versatile transceiver production and quality assurance Journal of Instrumentation OPEN ACCESS Versatile transceiver production and quality assurance To cite this article: L. Olantera et al Related content - Temperature characterization of versatile transceivers

More information

A new hybrid protection system for high-field superconducting magnets

A new hybrid protection system for high-field superconducting magnets A new hybrid protection system for high-field superconducting magnets Abstract E Ravaioli 1,2, V I Datskov 1, G Kirby 1, H H J ten Kate 1,2, and A P Verweij 1 1 CERN, Geneva, Switzerland 2 University of

More information

AUTOMATION OF 3D MEASUREMENTS FOR THE FINAL ASSEMBLY STEPS OF THE LHC DIPOLE MAGNETS

AUTOMATION OF 3D MEASUREMENTS FOR THE FINAL ASSEMBLY STEPS OF THE LHC DIPOLE MAGNETS IWAA2004, CERN, Geneva, 4-7 October 2004 AUTOMATION OF 3D MEASUREMENTS FOR THE FINAL ASSEMBLY STEPS OF THE LHC DIPOLE MAGNETS M. Bajko, R. Chamizo, C. Charrondiere, A. Kuzmin 1, CERN, 1211 Geneva 23, Switzerland

More information

Superconducting Magnets Quench Propagation and Protection

Superconducting Magnets Quench Propagation and Protection 1 Superconducting Magnets Quench Propagation and Protection Herman ten Kate CERN Accelerator School on Superconductivity for Accelerators, Erice 2013 2 1 Quench Protection, what for? Superconducting coil

More information

Herwig Schopper CERN 1211 Geneva 23, Switzerland. Introduction

Herwig Schopper CERN 1211 Geneva 23, Switzerland. Introduction THE LEP PROJECT - STATUS REPORT Herwig Schopper CERN 1211 Geneva 23, Switzerland Introduction LEP is an e + e - collider ring designed and optimized for 2 100 GeV. In an initial phase an energy of 2 55

More information

DRAWING PROCESS EXTERNAL DRAWINGS

DRAWING PROCESS EXTERNAL DRAWINGS CERN CH-1211 Geneva 23 Switzerland LHC Project Document No. CERN Div./Group or Supplier/Contractor Document No. the Large Hadron Collider project EDMS Document No. 103559 Date:1998-06-25 Quality Assurance

More information

Metrological Telecommunication System Development Project

Metrological Telecommunication System Development Project Philippines Metrological Telecommunication System Development Project 1. Project Profile and Japan s ODA Loan Report Date: March 2001 Field Survey: September 2000 The Philippines Manila Cebu Site Map:

More information

2008 JINST 3 S Powering and protection. Chapter Overview. 6.2 Powering circuits

2008 JINST 3 S Powering and protection. Chapter Overview. 6.2 Powering circuits Chapter 6 Powering and protection 6.1 Overview A very large number of superconducting and normal conducting magnets will be installed in the LHC, and most magnets of a given type in the same sector will

More information

IFJ PAN contribution to international projects

IFJ PAN contribution to international projects IFJ PAN contribution to international projects D. Bocian, A. Kotarba, J. Ludwin, M. Stodulski, J. Świerblewski, M. Wiencek IFJ PAN - ESS meeting Lund, 25 th June 2013 Kraków (Cracow) 700,000 inhabitants

More information

2008 JINST 3 S Magnets. Chapter Overview. 3.2 Superconducting cable

2008 JINST 3 S Magnets. Chapter Overview. 3.2 Superconducting cable Chapter 3 Magnets 3.1 Overview The Large Hadron Collider relies on superconducting magnets that are at the edge of present technology. Other large superconducting accelerators (Tevatron-FNAL, HERA-DESY

More information

Q2Q3D Specifications, Requirements and Scope

Q2Q3D Specifications, Requirements and Scope Q2Q3D Specifications, Requirements and Scope Paul Brindza 10/5/2016 Q2Q3D ERR Review October 12, 2016 1 Q2Q3D Outline Q2Q3 and Dipole Specifications Q2Q3D Status Q2Q3 and Dipole Contracts Scope of Work

More information

Physical Design of Superconducting Magnet for ADS Injection I

Physical Design of Superconducting Magnet for ADS Injection I Submitted to Chinese Physics C' Physical Design of Superconducting Magnet for ADS Injection I PENG Quan-ling( 彭全岭 ), WANG Bing( 王冰 ), CHEN Yuan( 陈沅 ) YANG Xiang-chen( 杨向臣 ) Institute of High Energy Physics,

More information

Impulse testing of coils and magnets: present experience and future plans

Impulse testing of coils and magnets: present experience and future plans Impulse testing of coils and magnets: present experience and future plans M. Marchevsky, E. Ravaioli, LBNL G. Ambrosio, FNAL M. Marchevsky 1 Impulse testing for LARP magnets Impulse testing is a key electrical

More information

EISCAT Scientific Association Technical Specification and Requirements for Antenna Unit V 2.0

EISCAT Scientific Association Technical Specification and Requirements for Antenna Unit V 2.0 EISCAT Scientific Association Technical Specification and s for Antenna Unit V 2.0 1. Technical Specification for Antenna Unit The EISCAT Scientific Association, also called "EISCAT" throughout this document,

More information

Robotics Market Update

Robotics Market Update Robotics Market Update The Outlook in North America Jeff Burnstein President Robotic Industries Association North American Economic Outlook The Great Recession of 2008-09 Financial meltdown in US caused

More information

Reliability studies for a superconducting driver for an ADS linac

Reliability studies for a superconducting driver for an ADS linac Mol, Belgium, 6-9 May 2007 Reliability studies for a superconducting driver for an ADS linac Paolo Pierini, Luciano Burgazzi Work supported by the EURATOM 6 framework program of the EC, under contract

More information

Motivation: ERL based e linac for LHeC

Motivation: ERL based e linac for LHeC Erk Jensen, for the LHeC team and the RF group ERL 2013, BINP, Novosibirsk, 09 Sep 2013 09 Sep 2013 1 Motivation: ERL based e linac for LHeC ( O. Brünings presentation) NB.: This is a 09 Sep 2013 2 Some

More information

HL-LHC Resources request

HL-LHC Resources request 1768040 1.0 VALID Date: 2017-02-01 Project/Activity: WP1 Title Position/ Project Management engineer As an Organization & Scheduling Support in the Engineering Department (EN), inside the Alignment, Coordination

More information

SECTION PANELBOARDS

SECTION PANELBOARDS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 24 16 PANELBOARDS SPEC WRITER NOTE: Delete between // --- // if not applicable to project. Also, delete any other item or paragraph not applicable in the section

More information

Brad Luke. Director Peddle Thorp Auckland

Brad Luke. Director Peddle Thorp Auckland Brad Luke Director Peddle Thorp Auckland Site Observation and Practical Completion Preparation PEDDLE THORP Introduction Architects Agreement for Services. Observation Work Plans. Auckland Council Quality

More information

R. Assmann, CERN/AB. for the Collimation Project 7/12/2007 LHC MAC RWA, LHC MAC 12/07

R. Assmann, CERN/AB. for the Collimation Project 7/12/2007 LHC MAC RWA, LHC MAC 12/07 Plan for Collimator Commissioning R. Assmann, CERN/AB 7/12/2007 for the Collimation Project LHC MAC RWA, LHC MAC 12/07 1) Installation Planning and Performance Reach Collimation is an performance-driven

More information

COMPARISON OF DIFFERENT MAGNETIC MEASUREMENT TECHNIQUES.

COMPARISON OF DIFFERENT MAGNETIC MEASUREMENT TECHNIQUES. COMPARISON OF DIFFERENT MAGNETIC MEASUREMENT TECHNIQUES. Isaac Vasserman, Shigemi Sasaki Argonne National Laboratory, Argonne, IL 60439, USA Abstract The magnetic measurement system at APS was upgraded.

More information

Manual: Distribution Substation Manual (DSM) Section D: Substation Drawing Revision List

Manual: Distribution Substation Manual (DSM) Section D: Substation Drawing Revision List Manual: Distribution Substation Manual (DSM) Section D: Substation Drawing Revision List Standard Number: HPC-5DA-07-0011-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer

More information

Betatron cleaning in IR3: results of FLUKA calculations. Fluka team

Betatron cleaning in IR3: results of FLUKA calculations. Fluka team Betatron cleaning in IR3: results of FLUKA calculations Fluka team R2E Meeting, July 17 th 2008 Goal of the study Verify the impact of the optional temporary functional move of the betatron cleaning to

More information

ALMA. ALMA Construction Status. Mark McKinnon. ALMA-NA Project Director/Manager September 28, 2011

ALMA. ALMA Construction Status. Mark McKinnon. ALMA-NA Project Director/Manager September 28, 2011 Construction Status Mark McKinnon -NA Project Director/Manager September 28, 2011 Antennas at AOS 18 antennas August 13, 2011 17 antennas August 6, 2011 Total of 44 antennas at the site (21NA, 13 EA, 10

More information

Magnets Y.C. Saxena Institute for Plasma Research. 1/16/2007 IPR Peer Review Jan

Magnets Y.C. Saxena Institute for Plasma Research. 1/16/2007 IPR Peer Review Jan Magnets Y.C. Saxena Institute for Plasma Research 1/16/2007 IPR Peer Review 15-17 Jan 2007 1 Magnet Development Program driven by Laboratory Scale Experiments ADITYA Tokamak SST-1 Tokamak 1/16/2007 IPR

More information

Plans for the ESS Linac. Steve Peggs, ESS for the ESS collaboration

Plans for the ESS Linac. Steve Peggs, ESS for the ESS collaboration Plans for the ESS Linac, ESS for the ESS collaboration 8 Work Packages Romuald Duperrier (30 years ago) Cristina Oyon Josu Eguia Work Packages in the Design Upgrade Mats Lindroos 1. Management Coordination

More information

Design of the magnets for the MAX IV project. Martin Johansson, Beam Dynamics meets Magnets-II workshop, Bad Zurzach, Dec.

Design of the magnets for the MAX IV project. Martin Johansson, Beam Dynamics meets Magnets-II workshop, Bad Zurzach, Dec. Design of the magnets for the MAX IV project Martin Johansson, Beam Dynamics meets Magnets-II workshop, Bad Zurzach, 01-04 Dec. 2014 MAX IV 3 GeV ring magnets key aspects: Relatively small magnet aperture

More information

Cryogenic Infrastructure for Testing of LHC Series Superconducting Magnets

Cryogenic Infrastructure for Testing of LHC Series Superconducting Magnets EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 793 Cryogenic Infrastructure for Testing of LHC Series Superconducting

More information

CERN (The European Laboratory for Particle Physics)

CERN (The European Laboratory for Particle Physics) 462 IEEE TRANSACTIONS ON INSTRUMENTATION AND MEASUREMENT, VOL. 48, NO. 2, APRIL 1999 The Measurement Challenge of the LHC Project Gunnar Fernqvist Abstract In 2005, CERN is planning to commission its next

More information

THE ELECTRICAL CIRCUITS IN THE LHC REFERENCE DATABASE

THE ELECTRICAL CIRCUITS IN THE LHC REFERENCE DATABASE CERN CH-1211 Geneva 23 Switzerland the Large Hadron Collider project Project Document No. CERN Div./Group or Supplier/Contractor Document No. AC-TCP EDMS Document No. 355662 Date: 2003-01-06 Engineering

More information

The High Luminosity LHC Project

The High Luminosity LHC Project The High Luminosity LHC Project Lucio Rossi CERN HL-LHC Project Leader LHC: il gigante E beam 0.3BR con 4 grandi occhi LHCb CMS ATLAS Explorazione della nuova frontiera con collisioni adroniche ALICE 2

More information

Cryogenic Operations at SLAC

Cryogenic Operations at SLAC Cryogenic Operations at SLAC J. G. Weisend II, A. Candia, W.W. Craddock, E. Thompson CryoOps 2006 5/30/2006 J. G. Weisend II 1 What Do We Do? Cryogenics at SLAC involve: Large scale He refrigerator operation

More information

A New Cryogenic Test Facility for Large and Heavy Superconducting Magnets

A New Cryogenic Test Facility for Large and Heavy Superconducting Magnets 2LPo2C-08 1 A New Cryogenic Test Facility for Large and Heavy Superconducting Magnets L. Serio, P. Schnizer, M. Arnaud, C. Bertone, E. Blanco, D. Calcoen, M. Charrondiere, E. J. Cho, G.-J. Coelingh, K.

More information

3.9 GHz System (AH1) XFEL WP46

3.9 GHz System (AH1) XFEL WP46 3.9 GHz System (AH1) XFEL WP46 14th European XFEL Machine Advisory Committee Meeting 02 May 2016 Paolo Pierini, INFN & DESY Elmar Vogel, DESY + INFN/DESY contributors PPT version 1 26/04/2016 Outline Status

More information

Power transformers. Shunt reactors Proven history for future success

Power transformers. Shunt reactors Proven history for future success Power transformers Shunt reactors Proven history for future success Shunt reactors an investment for today and for the future 2 Shunt reactors Improving power quality and reducing transmission costs Shunt

More information

Unit Transformers

Unit Transformers Unit 11.08 Transformers Prepared in Dec 1998 Second editing in march 2000 Learning objectives At the end of this unit you should be able to : 1. describe the structure and principle of operation of a basic

More information

Multipole Magnets with High Field Uniformity over Full Length for Super Separator Spectrometer

Multipole Magnets with High Field Uniformity over Full Length for Super Separator Spectrometer 1 Multipole Magnets with High Field Uniformity over Full Length for Super Separator Spectrometer S. Manikonda, R. Meinke, J. Nolen, V. Prince and G. Stelzer Abstract First few nested superconducting multipole

More information

Philippe Lebrun & Laurent Tavian, CERN

Philippe Lebrun & Laurent Tavian, CERN 7-11 July 2014 ICEC25 /ICMC 2014 Conference University of Twente, The Netherlands Philippe Lebrun & Laurent Tavian, CERN Ph. Lebrun & L. Tavian, ICEC25 Page 1 Contents Introduction: the European Strategy

More information

Recreation Facility Hours

Recreation Facility Hours NORMAL HOURS Recreation Facility Hours August 1, 2016 July 31, 2017 Last Revised: July 29, 2016 Effective Dates 2016: AUG 23 31, SEP 1 2, SEP 6 16, SEP 18 23, SEP 25 30, OCT 1 7, OCT 9 18, OCT 24 30, NOV

More information

Status and Future Perspective of the HIE-ISOLDE Project

Status and Future Perspective of the HIE-ISOLDE Project Status and Future Perspective of the HIE-ISOLDE Project International Particle Accelerator Conference, IPAC 12 New Orleans, Louisiana, USA, May 20-25, 2012 Yacine.Kadi@cern.ch OUTLINE Scope of HIE-ISOLDE

More information

SPECIFICATION FOR A 7.0 TESLA/400MM ROOM TEMPERATURE BORE MAGNET SYSTEM

SPECIFICATION FOR A 7.0 TESLA/400MM ROOM TEMPERATURE BORE MAGNET SYSTEM SPECIFICATION FOR A 7.0 TESLA/400MM ROOM TEMPERATURE BORE MAGNET SYSTEM Prepared by:- Magnex Scientific Limited The Magnet Technology Centre 6 Mead Road Oxford Industrial Park Yarnton, Oxford OX5 1QU,

More information

ELECTRONIC SYSTEMS FOR THE PROTECTION OF SUPERCONDUCTING ELEMENTS IN THE LHC

ELECTRONIC SYSTEMS FOR THE PROTECTION OF SUPERCONDUCTING ELEMENTS IN THE LHC EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 697 ELECTRONIC SYSTEMS FOR THE PROTECTION OF SUPERCONDUCTING ELEMENTS

More information

Information Warfare Research Project

Information Warfare Research Project SPACE AND NAVAL WARFARE COMMAND Information Warfare Research Project Charleston Defense Contractors Association 49th Small Business Industry Outreach Initiative 30 August 2018 Mr. Don Sallee SSC Atlantic

More information

ARotating Coil Array in Mono Bloc Printed Circuit Technology for Small Scale Harmonic Measurements

ARotating Coil Array in Mono Bloc Printed Circuit Technology for Small Scale Harmonic Measurements ARotating Coil Array in Mono Bloc Printed Circuit Technology for Small Scale Harmonic Measurements Olaf DUNKEL (Dep. TE MSC MM) On behalf of Rui DE OLIVEIRA (Dep. TE MPE EM) Lucette Gaborit, Ricardo Beltron

More information

Development of a charged-particle accumulator using an RF confinement method FA

Development of a charged-particle accumulator using an RF confinement method FA Development of a charged-particle accumulator using an RF confinement method FA4869-08-1-4075 Ryugo S. Hayano, University of Tokyo 1 Impact of the LHC accident This project, development of a charged-particle

More information

INNOVATIVE PERSPECTIVES FOR ELECTRICITY TRANSPORT

INNOVATIVE PERSPECTIVES FOR ELECTRICITY TRANSPORT INNOVATIVE PERSPECTIVES FOR ELECTRICITY TRANSPORT Jean-Maxime SAUGRAIN Corporate VP Technical Sharing Knowledge Across the Mediterranean Rabat Morocco May 9, 2013 Introduction to superconductors Superconductors

More information

The Superconducting Toroid for the New International AXion Observatory (IAXO)

The Superconducting Toroid for the New International AXion Observatory (IAXO) The Superconducting Toroid for the New International AXion Observatory (IAXO) I. Shilon, A. Dudarev, H. Silva, U. Wagner and H. H. J. ten Kate arxiv:1309.2117v1 [physics.ins-det] 9 Sep 2013 Abstract IAXO,

More information

Interfaces with MPS/PSS

Interfaces with MPS/PSS Interfaces with / European Spallation Source Accelerator Division TB, 16 November 2016, Lund, Sweden / interfaces 1/21 Outline 1 Introduction 2 3 4 Conclusions / interfaces 2/21 Outline 1 Introduction

More information

TECHNICAL SPECIFICATIONS. FOR AN MRBR 7.0 TESLA / 160mm ACTIVELY SHIELDED ROOM TEMPERATURE BORE MAGNET SYSTEM

TECHNICAL SPECIFICATIONS. FOR AN MRBR 7.0 TESLA / 160mm ACTIVELY SHIELDED ROOM TEMPERATURE BORE MAGNET SYSTEM TECHNICAL SPECIFICATIONS FOR AN MRBR 7.0 TESLA / 160mm ACTIVELY SHIELDED ROOM TEMPERATURE BORE MAGNET SYSTEM Prepared by:- Magnex Scientific Limited The Magnet Technology Centre 6 Mead Road Oxford Industrial

More information

SURFACE FINISH. A galvanized finish is MnDOT s standard on new traffic control signal poles, mast arms, transformer bases, and luminaire extensions.

SURFACE FINISH. A galvanized finish is MnDOT s standard on new traffic control signal poles, mast arms, transformer bases, and luminaire extensions. A galvanized finish is MnDOT s standard on new traffic control signal poles, mast arms, transformer bases, and luminaire extensions. The galvanized finish is highly abrasion resistant, however should the

More information

To produce more powerful and high-efficiency particle accelerator, efforts have

To produce more powerful and high-efficiency particle accelerator, efforts have Measuring Unloaded Quality Factor of Superconducting RF Cryomodule Jian Cong Zeng Department of Physics and Astronomy, State University of New York at Geneseo, Geneseo, NY 14454 Elvin Harms, Jr. Accelerator

More information

Conceptual Design of the LHC Interaction Region Upgrade Phase-I

Conceptual Design of the LHC Interaction Region Upgrade Phase-I EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 1163 Conceptual Design of the LHC Interaction Region Upgrade Phase-I

More information

Figure 1. TAMU1 dipole cross-section. Figure 2. Completed TAMU1 dipole and group that built it.

Figure 1. TAMU1 dipole cross-section. Figure 2. Completed TAMU1 dipole and group that built it. Testing of TAMU1 Dipole Team that built it: C. Battle, R. Blackburn, N. Diaczenko, T. Elliott, R. Gaedke, W. Henchel, E. Hill, M. Johnson, H. Kautzky, J. McIntyre, P. McIntyre, A. Sattarov Team that tested

More information

Broadband Current Probe Series Operation Manual

Broadband Current Probe Series Operation Manual Broadband Current Probe Series Operation Manual 1 TABLE OF CONTENTS INTRODUCTION 3 GENERAL INFORMATION 4 OPERATING INSTRUCTIONS 5 FORMULAS 6 MAINTENANCE 7 WARRANTY 8 2 INTRODUCTION CURRENT PROBE SPECIFICATIONS

More information

Cryogenics for Large Accelerators

Cryogenics for Large Accelerators Cryogenics for Large Accelerators Dr. Sergiy Putselyk Deutsches Elektronen-Synchrotron (DESY) MKS Division Notkestrasse 85 22607 Hamburg (Germany) Phone: +49 40 89983492 Fax: +49 40 89982858 E-Mail: Sergiy.Putselyk@desy.de

More information

Free-flying Satellite Inspector

Free-flying Satellite Inspector Approved for Public Release (OTR 2017-00263) Free-flying Satellite Inspector In-Space Non-Destructive Inspection Technology Workshop January 31-February 2, 2017 Johnson Space Center, Houston, Tx David

More information

Space and Missile Systems Center

Space and Missile Systems Center Space and Missile Systems Center Global Positioning Systems Directorate GPS Status & Modernization Progress: Service, Satellites, Control Segment, and Military GPS User Equipment 3 Nov 2016 Col Steve Whitney,

More information

Testing of the Toroidal Field Model Coil (TFMC)

Testing of the Toroidal Field Model Coil (TFMC) 1 CT/P 14 Testing of the Toroidal Field Model Coil (TFMC) E. Salpietro on behalf of the ITER-TFMC Team EFDA-CSU, Garching,, Germany ettore.salpietro@tech.efda.org Abstract The paper shortly describes the

More information

PWO Crystal ECAL. Ren-yuan Zhu California Institute of Technology May 19 th US CMS Collaboration Meeting, May 19, 2001 Ren-yuan Zhu, Caltech

PWO Crystal ECAL. Ren-yuan Zhu California Institute of Technology May 19 th US CMS Collaboration Meeting, May 19, 2001 Ren-yuan Zhu, Caltech PWO Crystal ECAL Ren-yuan Zhu California Institute of Technology May 19 th 2001 1 The Calorimeter Supermodule 36 supermodules in barrel, 4 Dees in endcaps. 1700 crystals/supermodule, 4000 crystals/dee

More information

Preliminary Design of the n2edm Coil System

Preliminary Design of the n2edm Coil System Preliminary Design of the n2edm Coil System Christopher Crawford, Philipp Schmidt-Wellenburg 2013-07-03 1 Introduction This report details progress towards the design of an electromagnetic coil package

More information

SPECIFICATIONS FOR A 4.7 TESLA/310MM BORE ACTIVELY SHIELDED MAGNET SYSTEM

SPECIFICATIONS FOR A 4.7 TESLA/310MM BORE ACTIVELY SHIELDED MAGNET SYSTEM SPECIFICATIONS FOR A 4.7 TESLA/310MM BORE ACTIVELY SHIELDED MAGNET SYSTEM Prepared by:- Magnex Scientific Limited The Magnet Technology Centre 6 Mead Road Oxford Industrial Park Yarnton, Oxford OX5 1QU,

More information

LHC: CONSTRUCTION AND COMMISSIONING STATUS

LHC: CONSTRUCTION AND COMMISSIONING STATUS LHC: CONSTRUCTION AND COMMISSIONING STATUS L. Evans, CERN, Geneva, Switzerland. Abstract The installation of the Large Hadron Collider at CERN is now approaching completion. All magnets are installed with

More information

New Superconducting Toroidal Magnet System for IAXO, the International AXion Observatory

New Superconducting Toroidal Magnet System for IAXO, the International AXion Observatory New Superconducting Toroidal Magnet System for IAXO, the International AXion Observatory I. Shilon, A. Dudarev, H. Silva, U. Wagner, and H. H. J. ten Kate European Organization for Nuclear Research (CERN),

More information

CERN PS, SL & ST Divisions

CERN PS, SL & ST Divisions EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH ORGANISATION EUROPÉENNE POUR LA RECHERCHE NUCLÉAIRE CERN PS, SL & ST Divisions CERN-PS-2002 CERN-SL-2002 CERN-ST-2002 1 st February 2002 TOWARDS A COMMON MONITORING

More information

HIGH MAGNETIC FIELD SUPERCONDUCTING MAGNETS FABRICATED IN BUDKER INP FOR SR GENERATION

HIGH MAGNETIC FIELD SUPERCONDUCTING MAGNETS FABRICATED IN BUDKER INP FOR SR GENERATION HIGH MAGNETIC FIELD SUPERCONDUCTING MAGNETS FABRICATED IN BUDKER INP FOR SR GENERATION K.V. Zolotarev *, A.M. Batrakov, S.V. Khruschev, G.N. Kulipanov, V.H. Lev, N.A. Mezentsev, E.G. Miginsky, V.A. Shkaruba,

More information

B262A. MATHEMATICS B (MEI) Paper 2 Section A (Foundation Tier) GENERAL CERTIFICATE OF SECONDARY EDUCATION. Wednesday 14 January 2009 Afternoon WARNING

B262A. MATHEMATICS B (MEI) Paper 2 Section A (Foundation Tier) GENERAL CERTIFICATE OF SECONDARY EDUCATION. Wednesday 14 January 2009 Afternoon WARNING F GENERAL CERTIFICATE OF SECONDARY EDUCATION MATHEMATICS B (MEI) Paper 2 Section A (Foundation Tier) B262A *CUP/T61563* Candidates answer on the question paper OCR Supplied Materials: None Other Materials

More information

KEYWORDS: LHC, helium cryogenics, superconductor, electrical feedbox, HTS current leads, busbar, magnet

KEYWORDS: LHC, helium cryogenics, superconductor, electrical feedbox, HTS current leads, busbar, magnet N EDMS 1035275 COMMISSIONING OF THE CRYOGENICS OF THE LHC LONG STRAIGHT SECTIONS A. Perin 1, J. Casas-Cubillos 1, S. Claudet 1, C. Darve 2, G. Ferlin 1, F. Millet 1, C. Parente 1, R. Rabehl 2, M. Soubiran

More information

Open To Buy (OTB) User Manual

Open To Buy (OTB) User Manual Open To Buy (OTB) User Manual Open to Buy Purpose... 3 Typical User and Workflow... 4 Open to Buy Definitions and Calculations... 5 Field Definitions... 5 Automatically Calculated OTB Fields... 5 Syntax

More information

AASHTO IDRRIM meeting

AASHTO IDRRIM meeting AASHTO IDRRIM meeting Marc TASSONE, IDRRIM Managing Director 2014 May 16 What about IDRRIM : Reference Partnership Institute for the community of public - private actors working for a shared interest :

More information