3.9 GHz System (AH1) XFEL WP46

Size: px
Start display at page:

Download "3.9 GHz System (AH1) XFEL WP46"

Transcription

1 3.9 GHz System (AH1) XFEL WP46 14th European XFEL Machine Advisory Committee Meeting 02 May 2016 Paolo Pierini, INFN & DESY Elmar Vogel, DESY + INFN/DESY contributors PPT version 1 26/04/2016

2 Outline Status presented at Nov 2015 MAC Operational experience during injector commissioning Spare module preparation Plans for R&D at CW for upgrades

3 WP46: 3.9 GHz System STATUS PRESENTED AT LAST MAC

4 Status at 13 th MAC (11/15) and report Module installed & visited by MAC in the Injector Waiting for first cooldown and RF characterization 1 cavity tested with tuner, magshield, coupler at AMTF MAC Report As the 3.9 GHz module has not been tested before installation, maybe some extra commissioning time needs to be scheduled. The commissioning team is well aware that the 3.9 GHz module has not been tested before installation. It is very appropriate to cool down as soon as possible to find out if any problem exists with this and other parts of the beamline.

5 WP46: 3.9 GHz System MODULE ASSEMBLY AND INSTALLATION

6 Timeplan presented at 12 th MAC Meeting Cavity Preparation CR String Assembly (2 Wks) Module Assembly (7 Wks) Installation, technical commissioning (8 Wks) P. Pierini, 14th XFEL MAC Meeting 12 th MAC 02/May/2016

7 14 weeks from cavities to tunnel Status and plans for the 3.9 GHz section of XFEL Module assembly timeline Where When Activity CLEAN ROOM (3 wks) ROLL-OUT AREA ON GIRDER (2 wks) ROLL-OUT AREA SUSPENDED (2 wks) CANTILEVER (4 wks) FLOOR SUPPORT (3 wks) WK25 WK26 WK27 WK28 WK29 WK30 WK31 WK32 WK33 WK34 WK35 WK36 WK37 WK38 WK39 Clean room preparation, last coupler installed on cavities String installation start. Cavity connections Finish installation. String Roll-out Partial magnetic shield installation and tuner installation, T sensors 2 phase line welds, T sensor installation completion, tuner motor Suspension from cold mass, completion of magnetic shield, alignment End of string alignment (2 pass and final survey), transfer to cantilever, preparation of 2K thermal sinking (HOM, motor), HOM notch filter tuning Weld of the magnet package current leads, weld of the warmup circuit RF cables, completion mag shield, HOM thermal sinks, installation of coupler cones, cable thermalization, start assembly of 4K shield parts Finalization of 4K/80K shields and MLI blankets Vessel roll-on, post bracket/suspension of the Cold Mass on the Vacuum Vessel, longitudinal pre-alignment of CM to VV, transfer to floor supports CM to VV alignment, start of coupler installation Finish coupler installation on one side, install coupler vacuum pump line Coupler side two, coupler vacuum, beam vacuum & leak check Transport to Tunnel

8 Major Assembly Milestones July September

9 Activities in between

10 Final Preparation stages in tunnel November th MAC Assembly WG distribution Injector String Integration Dec 10: Start cooldown Dec 15, cavity pre-tuning Dec 16, calibration: AH1 Ready 50 kw LLRF & Klystron calibration on load

11 WP46: 3.9 GHz System MODULE RF COMMISSIONING

12 Cavity vertical tests at INFN/LASA First cavity vertical test 26-Sep-14 and last 11-Feb-2015

13 RF Commissioning in Tunnel Infrastructure aspects, workload of main linac module testing activities and schedule delays made it impossible to perform an integral test of the module before tunnel installation The module was installed in tunnel without cryogenic and RF testing Tunnel environment is not the most favorable for precise RF measurements activities Few RF power meters with respect to AMTF, though a few not initially foreseen were implemented (e.g. HOM power readings, not preent in the main linac) The positive aspect is that all subcomponents were in their final configuration and driven by the XFEL control system Smooth transition from characterization to operation

14 Main characterization checklist Cavity performances, up to quench limit - done Phase alignment and QL tuning - done Beam-based calibrations - done HOM thermal stability studies - done Cryogenic performance assessment - done Preserving (and improving) beam quality ongoing Characterization of the RF power distribution skipped (for schedule reason)

15 First operation at nominal gradient on Day 1 18 December 2015 Operation with no beam First rough calibration Nominal pulse structure Fill Time: 750 us Flat Top: 650 us Gradient well above nominal 40 MV of VS voltage First quench > 45 MV Cavity phasing missing and QL values not yet tuned LLRF in FB mode

16 Beam Based calibration: Cavity Phases Cavity transient, QL determination and phase calibration January 2016, on beam Beam transients Phase Calibrations Preliminary to : Phase Tuning QL tuning Large initial cavity phase spread WG assembled in tunnel, no cal. 160 Beam induced cavity gradient changes After operation of a few stub tuners Tune with 3-stub tuners WG Spacers

17 QL tuning & Phase alignment 1 February 2016, AH1 moved 1 ms after the beam Allow injector commissioning while aligning cavity phases Individual maps of 3-stub tuner positions QL-Phase region Case of design in range of tuner QL-Phase region Case of design outside range of tuner WG spacers installed on 3 cavities

18 Started regular operation in injector 10 February 2016 QL aligned well within the 10% requirement Phases within February 2016 Back on beam Moved to -180 (wrt on-crest), calibration with beam energy

19 Quench Gradients & HOM performance Cavity Q0 is 2E9 (VT measure) Qt is 1E10 (VT calib) Cav QH1 QH2 C1 7.29E E+11 C2 1.14E E+10 C3 8.70E E+11 C4 1.91E E+11 C5 3.18E E+11 C6 8.32E E+11 C7 1.36E E+10 C8 4.50E E+15 C1 HOM1 suboptimal tuning C4 HOM1 detuned (cavity Q0) Stable thermal behavior Cav Max Gradient Tunnel Limit VT Gradient C MV/m Quench 21.0 MV/m C MV/m Power 20.0 MV/m C MV/m Quench 20.8 MV/m C Mv/m Power 22.0 MV/m C Mv/m Quench 21.0 MV/m C Mv/m Power 19.6 MV/m C Mv/m Quench 20.0 MV/m C Mv/m Power 21.8 MV/m Tunnel measurement much less accurate WG distribution assumed uniform (3x3dB+loss)

20 Temperature stability at highest SP In spite of the large peak fundamental mode power leaking out of two HOM1 couplers temperatures are extremely stable Levels at 20 MV Three CERNOX sensors are at each HOM can end (flange, tophat and inner antenna base) and connected to technical interlock system 40 MV Never triggered

21 Cryogenic aspects Static loads of individual component in the injector circuit cannot be individually assessed, only global measurements can be done Including end and feed box and both modules However, using data from components assessed in AMTF MKS estimates 2 K: 4-7 W 5/8 K: N/A problems with flowmeters 40/80 K: approx 95 W Overall, performance similar to 1.3 GHz modules Somewhat expected, same concept, same # penetrations Well within capabilities of cryocapabilities at injector

22 First confirmation of linearization effect TDS diagnostic not yet available at injector 12 April 2015 transmission of full train with acceptable losses in the after last dipole to beam dump not possible without AH1 AH1=0 MV AH1=10 MV

23 WP46: 3.9 GHz System SPARE INJECTOR MODULE PLANS

24 Spares components 5 cavities for spare module presently at DESY 2 from previous series production 3 from the second series of 10 cavities 5 more cavities tested, expected before end May/mid June Last 2 cavities of the second series delayed Vessel integration non-conformities: Repair Module (CM and VV) at DESY Several other components already have been procured in quantities for 2 modules and are already in stock either at DESY, INFN or FNAL Couplers, magnet, magnetic shields, PU and HOMs, beam line flange transitions, vacuum line, waveguides, etc.

25 Spare module activities String assembly and module installation scheduled to start in September, after tunnel closure and DESY Clean Room maintenance Increased manpower availability for all operations with the end of tunnel assemblies Adaptation of the module support rail for XATB1 in AMTF ongoing (BINP procurement) Ready before end of 2016 Testing in nominal XFEL pulsed conditions in early 2017 XATB1 already equipped with RF (single cavity tests) Planning ongoing for tests in CW performances Two companies exploring 3.9 GHz 1 kw

26 WP46: 3.9 GHz System CONCLUSIONS

27 Summary RF commissioning of the 3.9 GHz module in the tunnel was a great success Achieved performances above nominal during the early injector commissioning stages in December 2015, with the AH1 pulse shifted in time from the beam Module in regular operation with beam since January 2016 Final verification will be achieved with TDS The second spare module is well proceeding towards assembly & testing An extended test scope for CW testing with SSA is being discussed, in view of the possible future high duty cycle upgrades of the XFEL facility

28 WP46: 3.9 GHz System THANKS! Acknowledgements INFN M.Bertucci, M. Bonezzi, A.Bosotti, JF.Chen, M.Chiodini, M.Fusetti, C.Maiano, P.Michelato, L.Monaco, M.Moretti, C.Pagani, R.Paparella, D. Sertore DESY Too many people from MIN, MKS 1, MKS 3, MHF-SL, MPL, MSK, etc. And especially the whole BKR team FNAL Elvin Harms and the ACC39 team Most photos courtesy of D. Nölle/Ettore Zanon S.p.A.

29 After final round of Beam Based Calibration After LLRF final calibration with beam induced transients an asymmetry of the WG distribution is apparent (left/right arms of the distribution system Confirmation requires dedicated measurements of WG distribution at high power Directional Couplers) Odd-numbered Even-numbered Regular closed loop operation, at 20 MV setpoint Requires RF cables disconnection to LLRF panel & several accessess with measurement equipment Did not proceed as module performances are reached with margins!

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES LARGE SCALE TESTING OF SRF CAVITIES AND MODULES Jacek Swierblewski IFJ PAN Krakow IKC for the XFEL Introduction IFJ PAN 2 Institute of Nuclear Physics (IFJ) located in Kraków, Poland was founded in 1955

More information

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM FOR THE EUROPEAN XFEL Julien Branlard, for the LLRF team TALK OVERVIEW 2 Introduction Brief reminder about the XFEL LLRF system Commissioning goals

More information

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium Performance of Superconducting Cavities for the European XFEL Detlef Reschke DESY for the EU-XFEL Accelerator Consortium Outline 2 European XFEL Linear Accelerator Cavity Production Vertical Acceptance

More information

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY Status of the European XFEL Accelerator Construction Project Reinhard Brinkmann, DESY European XFEL Introduction Some specifications Photon energy 0.3-24 kev Pulse duration ~ 10-100 fs Pulse energy few

More information

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY Low-Level RF S. Simrock, DESY Outline Scope of LLRF System Work Breakdown for XFEL LLRF Design for the VUV-FEL Cost, Personpower and Schedule RF Systems for XFEL RF Gun Injector 3rd harmonic cavity Main

More information

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension XFEL Cryo System Possible extension 1 st stage Project X Collaboration Meeting, FNAL September 8-9, 2010 (XFEL WP10 & WP13) Outline 2 XFEL accelerator structure TESLA technology Basic cryogenic parameters

More information

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Approval: Originator: Tor Raubenheimer, Physics Support Lead Date Approved Approver: Marc Ross, Cryogenic System Manager Approver: Jose Chan,

More information

LLRF Operation and Performance of the European XFEL. An overview

LLRF Operation and Performance of the European XFEL. An overview LLRF Operation and Performance of the European XFEL. An overview Mathieu Omet LLRF, Barcelona, 16.10.2017 Contents > Introduction > LLRF commissioning > Energy Reach > LLRF performance > Summary / Outlook

More information

Validation of the superconducting 3.9 GHz cavity package for the European X-ray Free Electron Laser

Validation of the superconducting 3.9 GHz cavity package for the European X-ray Free Electron Laser PHYSICAL REVIEW ACCELERATORS AND BEAMS 2, 425 (217) Validation of the superconducting 3.9 GHz cavity package for the European X-ray Free Electron Laser C. G. Maiano, * J. Branlard, M. Hüning, K. Jensch,

More information

To produce more powerful and high-efficiency particle accelerator, efforts have

To produce more powerful and high-efficiency particle accelerator, efforts have Measuring Unloaded Quality Factor of Superconducting RF Cryomodule Jian Cong Zeng Department of Physics and Astronomy, State University of New York at Geneseo, Geneseo, NY 14454 Elvin Harms, Jr. Accelerator

More information

Vibration studies of a superconducting accelerating

Vibration studies of a superconducting accelerating Vibration studies of a superconducting accelerating module at room temperature and at 4.5 K Ramila Amirikas, Alessandro Bertolini, Wilhelm Bialowons Vibration studies on a Type III cryomodule at room temperature

More information

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Overview ALICE (Accelerators and Lasers In Combined Experiments)

More information

THE CRYOGENIC SYSTEM OF TESLA

THE CRYOGENIC SYSTEM OF TESLA THE CRYOGENIC SYSTEM OF TESLA S. Wolff, DESY, Notkestr. 85, 22607 Hamburg, Germany for the TESLA collaboration Abstract TESLA, a 33 km long 500 GeV centre-of-mass energy superconducting linear collider

More information

Cryogenics for Large Accelerators

Cryogenics for Large Accelerators Cryogenics for Large Accelerators Dr. Sergiy Putselyk Deutsches Elektronen-Synchrotron (DESY) MKS Division Notkestrasse 85 22607 Hamburg (Germany) Phone: +49 40 89983492 Fax: +49 40 89982858 E-Mail: Sergiy.Putselyk@desy.de

More information

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY Abstract HIGH POWER COUPLER FOR THE TESLA TEST FACILITY W.-D. Moeller * for the TESLA Collaboration, Deutsches Elektronen-Synchrotron DESY, D-22603 Hamburg, Germany The TeV Energy Superconducting Linear

More information

Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience

Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience Lars Hagge, Benno List SLAC, 31.03.2014 Agenda > Introduction: Collaborative Engineering > Collaborative Design &

More information

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY -

DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY - DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY - F. Peauger, C. Arcambal, F. Ardellier, S. Berry, P. Bosland, A. Bouygues, E. Cenni, JP. Charrier, G. Devanz, F. Eozénou,

More information

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University Overview of ERL Projects: SRF Issues and Challenges Matthias Liepe Cornell University Overview of ERL projects: SRF issues and challenges Slide 1 Outline Introduction: SRF for ERLs What makes it special

More information

R.Bachimanchi, IPAC, May 2015, Richmond, VA

R.Bachimanchi, IPAC, May 2015, Richmond, VA 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

3.9 GHz Deflecting Mode Cavity

3.9 GHz Deflecting Mode Cavity 3.9 GHz Deflecting Mode Cavity Timothy W. Koeth July 12, 2005 History of 3.9 GHz DMC Cavity Simulations The Other Modes concern and modeling R/Q Wake Field Simulations Design: OM couplers Testing: Vertical

More information

FLASH. FLASH Training: RF Gun. FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously. Siegfried Schreiber, DESY

FLASH. FLASH Training: RF Gun. FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously. Siegfried Schreiber, DESY FLASH Training: RF Gun FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously Siegfried Schreiber, DESY FLASH Training DESY 17-Mar-2017 FLASH1 RF Gun History RF Guns operated

More information

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE M. Liepe, S. Belomestnykh, E. Chojnacki, Z. Conway, V. Medjidzade, H. Padamsee, P. Quigley, J. Sears, V. Shemelin, V. Veshcherevich,

More information

ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II

ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II G. Wu 1, A. Grassellino, E. Harms, N. Solyak, A. Romanenko, C. Ginsburg, R. Stanek Fermi National Accelerator Laboratory, Batavia,

More information

Borut Baricevic. Libera LLRF. 17 September 2009

Borut Baricevic. Libera LLRF. 17 September 2009 Borut Baricevic Libera LLRF borut.baricevic@i-tech.si 17 September 2009 Outline Libera LLRF introduction Libera LLRF system topology Signal processing structure GUI and signal acquisition RF system diagnostics

More information

High Power Couplers for TTF - FEL

High Power Couplers for TTF - FEL High Power Couplers for TTF - FEL 1. Requirements for High Power Couplers on superconducting Cavities 2. Characteristics of pulsed couplers 3. Standing wave pattern in the coaxial coupler line 4. Advantages

More information

Work Package Status Report

Work Package Status Report Work Package Status Report Date: August 2018 Work Package: WP5 Elliptical cavities and cryomodules Author: Pierre Bosland, Roger Ruber, Daniele Sertore, Mike Ellis, Christine Darve 1. Accomplishments by

More information

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT G. Olry, J-L. Biarrotte, S. Blivet, S. Bousson, C. Commeaux, C. Joly, T. Junquera, J. Lesrel, E. Roy,

More information

Status of berlinpro and BESSY II Installation of SSA. Helmholtz-Zentrum Berlin for materials and energy (HZB)

Status of berlinpro and BESSY II Installation of SSA. Helmholtz-Zentrum Berlin for materials and energy (HZB) Status of berlinpro and BESSY II Installation of SSA Wolfgang Anders, Helmholtz-Zentrum Berlin for materials and energy (HZB) 19th ESLS-RF Meeting 30.9.-1.10.2015 MaxLab outline BERLinPro Status building

More information

Status and Future Perspective of the HIE-ISOLDE Project

Status and Future Perspective of the HIE-ISOLDE Project Status and Future Perspective of the HIE-ISOLDE Project International Particle Accelerator Conference, IPAC 12 New Orleans, Louisiana, USA, May 20-25, 2012 Yacine.Kadi@cern.ch OUTLINE Scope of HIE-ISOLDE

More information

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS J. Teichert, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A.

More information

Advance on High Power Couplers for SC Accelerators

Advance on High Power Couplers for SC Accelerators Advance on High Power Couplers for SC Accelerators Eiji Kako (KEK, Japan) IAS conference at Hong Kong for High Energy Physics, 2017, January 23th Eiji KAKO (KEK, Japan) IAS at Hong Kong, 2017 Jan. 23 1

More information

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF Y. Yamamoto #, H. Hayano, E. Kako, T. Matsumoto, S. Michizono, T. Miura, S. Noguchi, M. Satoh, T. Shishidio, K. Watanabe, KEK, Tsukuba,

More information

3.9 GHz work at Fermilab

3.9 GHz work at Fermilab 3.9 GHz work at Fermilab + CKM 13-cell cavity Engineering and designing W.-D. Moeller Desy, MHF-sl Protocol of the meeting about 3 rd harmonic cavities during the TESLA collaboration meeting at DESY on

More information

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ERL 09 8 th 12 th June 2009 ALICE Accelerators and Lasers In Combined Experiments Brief Description ALICE Superconducting

More information

Status and Plans for the 805 MHz Box Cavity MuCool RF Workshop III 07/07/09 Al Moretti

Status and Plans for the 805 MHz Box Cavity MuCool RF Workshop III 07/07/09 Al Moretti Status and Plans for the 805 MHz Box Cavity MuCool RF Workshop III 07/07/09 Al Moretti 7/6/2009 1 Outline : Description of the Box cavity Concept. Box Cavity Summary Plans. HFSS Models of orthogonal and

More information

Current Status of cerl Injector Cryomodule

Current Status of cerl Injector Cryomodule Current Status of cerl Injector Cryomodule E. Kako, Y. Kondo, S. Noguchi, T. Shishido, K. Watanabe, Y. Yamamoto (KEK, Japan) 1 Outline Overview of Injector Cryomodule 2-cell Cavities HOM RF Feedthroughs

More information

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute CEBAF waveguide absorbers R. Rimmer for JLab SRF Institute Outline Original CEBAF HOM absorbers Modified CEBAF loads for FEL New materials for replacement loads High power loads for next generation FELs

More information

Motivation: ERL based e linac for LHeC

Motivation: ERL based e linac for LHeC Erk Jensen, for the LHeC team and the RF group ERL 2013, BINP, Novosibirsk, 09 Sep 2013 09 Sep 2013 1 Motivation: ERL based e linac for LHeC ( O. Brünings presentation) NB.: This is a 09 Sep 2013 2 Some

More information

H. Weise, Deutsches Elektronen-Synchrotron, Hamburg, Germany for the XFEL Group

H. Weise, Deutsches Elektronen-Synchrotron, Hamburg, Germany for the XFEL Group 7+(7(6/$;)(/352-(&7 H. Weise, Deutsches Elektronen-Synchrotron, Hamburg, Germany for the XFEL Group $EVWUDFW The overall layout of the X-Ray FEL to be built in international collaboration at DESY will

More information

Hardware Commissioning

Hardware Commissioning Hardware Commissioning an update the status of the documentation the report on the resources the programme of the coming year Roberto Saban on behalf of the Hardware Commissioning Working Group status

More information

RF System LSD Work. William Merz

RF System LSD Work. William Merz RF System LSD Work William Merz LSD Re-Baseline Review Jefferson Lab Thomas Jefferson National Accelerator Facility Page 1 Outline What I will talk about 12 GEV RF power system installation and commissioning

More information

Snowmass WG5: Superconducting Cavities and Couplers (Draft August 12, 2005 Rong-Li Geng) Topic 1: Cavity Shape

Snowmass WG5: Superconducting Cavities and Couplers (Draft August 12, 2005 Rong-Li Geng) Topic 1: Cavity Shape Snowmass WG5: Superconducting Cavities and Couplers (Draft August 12, 2005 Rong-Li Geng) Topic 1: Cavity Shape Overview The cavity shape determines the fundamental mode as well as the higher order modes

More information

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY G. Devanz, D. Braud, M. Desmons, Y. Gasser, E. Jacques, O. Piquet, J. Plouin, J.- P. Poupeau, D. Roudier, P. Sahuquet, CEA-Saclay,

More information

KEK ERL CRYOMODULE DEVELOPMENT

KEK ERL CRYOMODULE DEVELOPMENT KEK ERL CRYOMODULE DEVELOPMENT H. Sakai*, T. Furuya, E. Kako, S. Noguchi, M. Sato, S. Sakanaka, T. Shishido, T. Takahashi, K. Umemori, K. Watanabe and Y. Yamamoto KEK, 1-1, Oho, Tsukuba, Ibaraki, 305-0801,

More information

Superstructures; First Cold Test and Future Applications

Superstructures; First Cold Test and Future Applications Superstructures; First Cold Test and Future Applications DESY: C. Albrecht, V. Ayvazyan, R. Bandelmann, T. Büttner, P. Castro, S. Choroba, J. Eschke, B. Faatz, A. Gössel, K. Honkavaara, B. Horst, J. Iversen,

More information

CEBAF Overview June 4, 2010

CEBAF Overview June 4, 2010 CEBAF Overview June 4, 2010 Yan Wang Deputy Group Leader of the Operations Group Outline CEBAF Timeline Machine Overview Injector Linear Accelerators Recirculation Arcs Extraction Systems Beam Specifications

More information

LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC. Marc Ross 13 January 2014

LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC. Marc Ross 13 January 2014 LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC Marc Ross 13 January 2014 What are the technical and practical limits for DF? 1st limit: Heat load at 2K for each cryomodule

More information

SLHiPP-2, Catania, Italy. A cryogenic system for the MYRRHA linac. Nicolas Chevalier, Tomas Junquera

SLHiPP-2, Catania, Italy. A cryogenic system for the MYRRHA linac. Nicolas Chevalier, Tomas Junquera SLHiPP-2, Catania, Italy A cryogenic system for the MYRRHA linac Nicolas Chevalier, Tomas Junquera 04.05.2012 Outline 1 ) Cryogenic system requirements : heat loads 2 ) Temperature optimization, possible

More information

Main Injector Cavity Simulation and Optimization for Project X

Main Injector Cavity Simulation and Optimization for Project X Main Injector Cavity Simulation and Optimization for Project X Liling Xiao Advanced Computations Group Beam Physics Department Accelerator Research Division Status Meeting, April 7, 2011 Outline Background

More information

A few results [2,3] obtained with the individual cavities inside their horizontal cryostats are summarized in Table I and a typical Q o

A few results [2,3] obtained with the individual cavities inside their horizontal cryostats are summarized in Table I and a typical Q o Particle Accelerators, 1990, Vol. 29, pp. 47-52 Reprints available directly from the publisher Photocopying permitted by license only 1990 Gordon and Breach, Science Publishers, Inc. Printed in the United

More information

Software Design Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 16, 2009

Software Design Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 16, 2009 Software Design Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 16, 2009 Copyright 2009 by Zheqiao Geng. Any change of this document should be agreed by

More information

Experience with 3.9 GHz cavity HOM couplers

Experience with 3.9 GHz cavity HOM couplers Cornell University, October 11-13, 2010 Experience with 3.9 GHz cavity HOM couplers T. Khabiboulline, N. Solyak, FNAL. 3.9 GHz cavity general parameters Third harmonic cavity (3.9GHz) was proposed to compensate

More information

TESLA RF POWER COUPLERS DEVELOPMENT AT DESY.

TESLA RF POWER COUPLERS DEVELOPMENT AT DESY. TESLA RF POWER COUPLERS DEVELOPMENT AT DESY. Dwersteg B., Kostin D., Lalayan M., Martens C., Möller W.-D., DESY, D-22603 Hamburg, Germany. Abstract Different RF power couplers for the TESLA Test Facility

More information

Industrialization of E-XFEL string and module assembly at CEA- Saclay. Preparation work Lessons learnt Cost reduction

Industrialization of E-XFEL string and module assembly at CEA- Saclay. Preparation work Lessons learnt Cost reduction Industrialization of E-XFEL string and module assembly at CEA- Saclay Preparation work Lessons learnt Cost reduction / /201 C. Madec 1 CEA contribution CEA contributes to the E-XFEL Cold Linac construction

More information

Tuning systems for superconducting cavities at Saclay

Tuning systems for superconducting cavities at Saclay Tuning systems for superconducting cavities at Saclay 1 MACSE: 1990: tuner in LHe bath at 1.8K TTF: 1995 tuner at 1.8K in the insulating vacuum SOLEIL: 1999 tuner at 4 K in the insulating vacuum Super-3HC:

More information

FAST RF KICKER DESIGN

FAST RF KICKER DESIGN FAST RF KICKER DESIGN David Alesini LNF-INFN, Frascati, Rome, Italy ICFA Mini-Workshop on Deflecting/Crabbing Cavity Applications in Accelerators, Shanghai, April 23-25, 2008 FAST STRIPLINE INJECTION KICKERS

More information

RF Design of Normal Conducting Deflecting Cavity

RF Design of Normal Conducting Deflecting Cavity RF Design of Normal Conducting Deflecting Cavity Valery Dolgashev (SLAC), Geoff Waldschmidt, Ali Nassiri (Argonne National Laboratory, Advanced Photon Source) 48th ICFA Advanced Beam Dynamics Workshop

More information

Packaging of Cryogenic Components

Packaging of Cryogenic Components Packaging of Cryogenic Components William J. Schneider Senior Mechanical Engineer Emeritus November 19-23 2007 1 Packaging of Cryogenic Components Day one Introduction and Overview 2 What is important?

More information

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University ESS RF Development at Uppsala University Roger Ruber for the FREIA team Uppsala University ESS-UU Collaboration 2009 ESS and UU start discussion on 704 MHz RF development proposal for ESS dedicated test

More information

two pairs of dipole steering windings that t inside the quadrupole yoke an RF beam position monitor (BPM) consisting of a pill box RF cavity,

two pairs of dipole steering windings that t inside the quadrupole yoke an RF beam position monitor (BPM) consisting of a pill box RF cavity, Chapter 6 Quadrupole Package The quadrupole package is shown in Fig. 6.1. It consists of a superferric quadrupole doublet powered in series enclosed in a stainless steel vessel and cooled by 4 K LHe; two

More information

Report of working group 5

Report of working group 5 Report of working group 5 Materials Cavity design Cavity Fabrication Preparatioin & Testing Power coupler HOM coupler Beam line absorber Tuner Fundamental R&D items Most important R&D items 500 GeV parameters

More information

A 3 GHz SRF reduced-β Cavity for the S-DALINAC

A 3 GHz SRF reduced-β Cavity for the S-DALINAC A 3 GHz SRF reduced-β Cavity for the S-DALINAC D. Bazyl*, W.F.O. Müller, H. De Gersem Gefördert durch die DFG im Rahmen des GRK 2128 20.11.2018 M.Sc. Dmitry Bazyl TU Darmstadt TEMF Upgrade of the Capture

More information

SPOKE CRYOMODULES CONCEPTUAL DESIGNS FOR ESS & MYRRHA

SPOKE CRYOMODULES CONCEPTUAL DESIGNS FOR ESS & MYRRHA SPOKE CRYOMODULES CONCEPTUAL DESIGNS FOR ESS & MYRRHA Hervé Saugnac- IPNO SLHIPP-2 - Catania- 3&4 May 2012 ESS 72 MeV Baseline of the Spoke linac: 10 cryomodules, each one containing 2 double Spoke β=0.5

More information

PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC

PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC F. Peauger, C. Arcambal, S. Berry, N. Berton, P. Bosland, E. Cenni, J.P. Charrier, G. Devanz, F. Eozenou, F. Gougnaud,

More information

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF Project X Cavity RF and mechanical design T. Khabiboulline, FNAL/TD/SRF TTC meeting on CW-SRF, 2013 Project X Cavity RF and mechanical design T 1 High ß Low ß 0.5 HWR SSR1 SSR2 0 1 10 100 1 10 3 1 10 4

More information

Software Requirements Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 06, 2009

Software Requirements Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 06, 2009 Software Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 06, 2009 Copyright 2009 by Zheqiao Geng. Any change of this document should be agreed by the development

More information

SNS CRYOMODULE PERFORMANCE*

SNS CRYOMODULE PERFORMANCE* SNS CRYOMODULE PERFORMANCE* J. Preble*, I. E. Campisi, E. Daly, G. K. Davis, J. R. Delayen, M. Drury, C. Grenoble, J. Hogan, L. King, P. Kneisel, J. Mammosser, T. Powers, M. Stirbet, H. Wang, T. Whitlatch,

More information

Commissioning of Advanced Virgo

Commissioning of Advanced Virgo Commissioning of Advanced Virgo VSR1 VSR4 VSR5/6/7? Bas Swinkels, European Gravitational Observatory on behalf of the Virgo Collaboration GWADW Takayama, 26/05/2014 B. Swinkels Adv. Virgo Commissioning

More information

Initial Beam Phasing of the SRF Cavities in LCLS-II

Initial Beam Phasing of the SRF Cavities in LCLS-II Introduction Initial Beam Phasing of the SRF Cavities in LCLS-II P. Emma Nov. 28, 2016 One of the more challenging aspects of commissioning the LCLS-II accelerator is in the initial phasing of the SRF

More information

THE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING CAVITY

THE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING CAVITY Presented at the 1999 Particle Accelerator Conference, New York City, NY, USA, March 29 April 2 CLNS 99/1614 / SRF 990407-03 THE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING

More information

5.5 SNS Superconducting Linac

5.5 SNS Superconducting Linac JP0150514 ICANS - XV 15 th Meeting of the International Collaboration on Advanced Neutron Sources November 6-9, 2000 Tsukuba, Japan Ronald M. Sundelin Jefferson Lab* 5.5 SNS Superconducting Linac 12000

More information

Attosecond Diagnostics of Muti GeV Electron Beams Using W Band Deflectors

Attosecond Diagnostics of Muti GeV Electron Beams Using W Band Deflectors Attosecond Diagnostics of Muti GeV Electron Beams Using W Band Deflectors V.A. Dolgashev, P. Emma, M. Dal Forno, A. Novokhatski, S. Weathersby SLAC National Accelerator Laboratory FEIS 2: Femtosecond Electron

More information

Liquid Helium Heat Load Within the Cornell Mark II Cryostat

Liquid Helium Heat Load Within the Cornell Mark II Cryostat SRF 990615-07 Liquid Helium Heat Load Within the Cornell Mark II Cryostat E. Chojnacki, S. Belomestnykh, and J. Sears Floyd R. Newman Laboratory of Nuclear Studies Cornell University, Ithaca, New York

More information

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW*

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW* Presented at the 13th International Workshop on RF Superconductivity, Beijing, China, 2007 SRF 071120-04 OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW* S. Belomestnykh #, CLASSE, Cornell

More information

Cavity development for TESLA

Cavity development for TESLA Cavity development for TESLA Lutz.Lilje@desy.de DESY -FDET- Cavity basics History: Limitations and solutions»material inclusions»weld defects»field emission»increased surface resistance at high field Performance

More information

INFN School on Electron Accelerators. Cryomodule Design & Cryogenics

INFN School on Electron Accelerators. Cryomodule Design & Cryogenics INFN School on Electron Accelerators 12-14 September 2007, INFN Sezione di Pisa Lecture 7a Cryomodule Design & Cryogenics Carlo Pagani University of Milano INFN Milano-LASA & GDE The ILC technology choice

More information

LC Technology Hans Weise / DESY

LC Technology Hans Weise / DESY LC Technology Hans Weise / DESY All you need is... Luminosity! L σ 2 N e x σ y σ y σ x L n b f rep Re-writing reflects the LC choices... L P E b c. m. N e σ σ x y... beam power... bunch population... Ac-to-beam

More information

HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK

HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK E. Kako #, H. Hayano, S. Noguchi, T. Shishido, K. Watanabe and Y. Yamamoto KEK, Tsukuba, Ibaraki, 305-0801, Japan Abstract An input coupler,

More information

System Integration of the TPS. J.R. Chen NSRRC, Hsinchu

System Integration of the TPS. J.R. Chen NSRRC, Hsinchu System Integration of the TPS J.R. Chen NSRRC, Hsinchu OUTLINE I. Main features of the TPS II. Major concerns and intersystem effects of an advanced synchrotron light source III. Subsystems and intersystem

More information

J. Jacob: Status of the ESRF RF upgrade

J. Jacob: Status of the ESRF RF upgrade 17th ESLS RF Meeting 2013 HZB BESSY 18th 19th September Status of the ESRF RF upgrade J. Jacob J.-M. Mercier V. Serrière M. Langlois G. Gautier [CINEL] 1 RF upgrade phase 1 until 2015 - reminder Replacement

More information

Third Harmonic Cavity Status

Third Harmonic Cavity Status Third Harmonic Cavity Status General parameters Cavity design Main coupler calculation HOM analysis and HOM coupler design Lorentz Forces and Stress analysis Summary General parameters Third harmonic cavity

More information

RENASCENCE * PERFORMANCE AND PROBLEMS ON FIRST TEST Feedthrough leaks sub 70 K. End group quenching

RENASCENCE * PERFORMANCE AND PROBLEMS ON FIRST TEST Feedthrough leaks sub 70 K. End group quenching Proceedings of SRF27, Peking Univ., Beijing, China PERFORMANCE OF THE CEBAF PROTOTYPE CRYOMODULE RENASCENCE * C. E. Reece, E. F. Daly, G. K. Davis, M. Drury, W. R. Hicks, J. Preble, H. Wang # Jefferson

More information

Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay. Abstract

Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay. Abstract SRF Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay Abstract This report presents the piezo tuner developed at Saclay in the framework of CARE/SRF.

More information

3 General layout of the XFEL Facility

3 General layout of the XFEL Facility 3 General layout of the XFEL Facility 3.1 Introduction The present chapter provides an overview of the whole European X-Ray Free-Electron Laser (XFEL) Facility layout, enumerating its main components and

More information

LEP Couplers..a Troubled Story of a Success. HPC2002, Jefferson Lab, October 30 th, 2002 R. Losito, CERN 1

LEP Couplers..a Troubled Story of a Success. HPC2002, Jefferson Lab, October 30 th, 2002 R. Losito, CERN 1 LEP Couplers..a Troubled Story of a Success HPC2002, Jefferson Lab, October 30 th, 2002 R. Losito, CERN 1 1 Overview & development: specifications, problems, solutions Operation: field equalization, trip

More information

A Study of Magnetic Shielding Performance of a Fermilab International Linear Collider Superconducting RF Cavity Cryomodule

A Study of Magnetic Shielding Performance of a Fermilab International Linear Collider Superconducting RF Cavity Cryomodule A Study of Magnetic Shielding Performance of a Fermilab International Linear Collider Superconducting RF Cavity Cryomodule Anthony C. Crawford Fermilab Technical Div. / SRF Development Dept. acc52@fnal.gov

More information

Ku-Band Receiver System for SHAO

Ku-Band Receiver System for SHAO Ku-Band Receiver System for SHAO Overview Brent Willoughby July 2014 Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array

More information

QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER*

QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER* QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER* P.N. Prakash and A.Roy Nuclear Science Centre, P.O.Box 10502, New Delhi 110 067, INDIA and K.W.Shepard Physics Division, Argonne National Laboratory,

More information

Status of superconducting module development suitable for cw operation: ELBE cryostats

Status of superconducting module development suitable for cw operation: ELBE cryostats Status of superconducting module development suitable for cw operation: ELBE cryostats, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A. Winter Forschungszentrum

More information

Roman Pots. Marco Oriunno SLAC, PPA. M.Oriunno, SLAC

Roman Pots. Marco Oriunno SLAC, PPA. M.Oriunno, SLAC Roman Pots Marco Oriunno SLAC, PPA The Roman Pot technique 1. The Roman Pot, an historically successful technique for near beam physics: ISR, SPS, TEVATRON, RICH, DESY 2. A CERN in-house technology: ISR,

More information

TESLA Quad Package With BPM

TESLA Quad Package With BPM TESLA Quad Package With BPM H. Brueck, DESY Zeuthen, January 22, 2004 Technology Working Group 1 Topics The TESLA Quadrupole Package Status of Components Magnet Feedthroughs HTc Leads BPM Test in ACC6

More information

Status Alcator C-Mod Engineering Systems. DoE Quarterly Review October 27, 2005

Status Alcator C-Mod Engineering Systems. DoE Quarterly Review October 27, 2005 Status Alcator C-Mod Engineering Systems DoE Quarterly Review October 27, 2005 1 Outline Run campaign Up-to-Air Machine Status Lower Hybrid Cryopump Tungsten Tiles Schedule/Plans 2 FY2005 Run Campaign

More information

overview of cryomodules for proton accelerators

overview of cryomodules for proton accelerators overview of cryomodules for proton accelerators Paolo Pierini INFN Sezione di Milano Laboratorio Acceleratori e Superconduttività Applicata Paolo.Pierini@mi.infn.it 19 March 2009 Bilbao outline discuss

More information

LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE

LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE M. P. Kelly, Z. A. Conway, S. M. Gerbick, M. Kedzie, T. C. Reid, R. C. Murphy, B. Mustapha, S.H. Kim, P. N. Ostroumov, Argonne National Laboratory,

More information

Performance of the TTF Photoinjector Laser System

Performance of the TTF Photoinjector Laser System Performance of the TTF Photoinjector Laser System S. Schreiber, DESY Laser Issues for Electron Photoinjectors, October 23-25, 22, Stanford, California, USA & I. Will, A. Liero, W. Sandner, MBI Berlin Overview

More information

Superconducting RF cavities activities for the MAX project

Superconducting RF cavities activities for the MAX project 1 Superconducting RF cavities activities for the MAX project OECD-NEA TCADS-2 Workshop Nantes, 22 May 2013 Marouan El Yakoubi, CNRS / IPNO 2 Contents 352 MHz spoke Cryomodule design 700 MHz test area 700

More information

DESIGN AND BEAM DYNAMICS STUDIES OF A MULTI-ION LINAC INJECTOR FOR THE JLEIC ION COMPLEX

DESIGN AND BEAM DYNAMICS STUDIES OF A MULTI-ION LINAC INJECTOR FOR THE JLEIC ION COMPLEX DESIGN AND BEAM DYNAMICS STUDIES OF A MULTI-ION LINAC INJECTOR FOR THE JLEIC ION COMPLEX Speaker: P.N. Ostroumov Contributors: A. Plastun, B. Mustapha and Z. Conway HB2016, July 7, 2016, Malmö, Sweden

More information

Proposal of test setup

Proposal of test setup Proposal of test setup Status of the study The Compact Linear collider (CLIC) study is a site independent feasibility study aiming at the development of a realistic technology at an affordable cost for

More information

Superconducting RF System. Heung-Sik Kang

Superconducting RF System. Heung-Sik Kang Design of PLS-II Superconducting RF System Heung-Sik Kang On behalf of PLS-II RF group Pohang Accelerator Laboratory Content 1. Introduction 2. Physics design 3. Cryomodules 4. Cryogenic system 5. High

More information