ALMA. ALMA Construction Status. Mark McKinnon. ALMA-NA Project Director/Manager September 28, 2011

Size: px
Start display at page:

Download "ALMA. ALMA Construction Status. Mark McKinnon. ALMA-NA Project Director/Manager September 28, 2011"

Transcription

1 Construction Status Mark McKinnon -NA Project Director/Manager September 28, 2011

2 Antennas at AOS 18 antennas August 13, antennas August 6, 2011 Total of 44 antennas at the site (21NA, 13 EA, 10 EU) Total of 27 antennas accepted (16 NA, 8 EA, 3 EU) ANASAC, September 28-29,

3 Vertex Antennas 21 Vertex antennas in Chile 16 of these accepted 5 most recent antennas fully accepted in 30 weeks; demonstrates ability to deliver antennas at targeted rate of 1 every 6 weeks 5 in various stages of assembly at the SEF: DV17: Servo & HVAC testing completed. Pointing underway DV18: Panel installation, photogrammetry, & electrical work complete. Servo & HVAC testing underway. DV19: Installation of platforms, servo cabinet, & HVAC complete. BUS assembled & mated to Invar cone. Panel installation underway. DV20: pedestal on foundation since August 12 DV21: arrived at SEF on September 10. To be installed on foundation this week. ANASAC, September 28-29,

4 EU Antennas 10 antennas in Chile; 7 assembled 3 antennas conditionally accepted 3 accepted in 14.5 weeks (1 every 4.8 weeks) 4 assembled and in various stages of vendor tests (AEM4-AEM7) 2 in assembly (AEM8 & AEM9) 1 on antenna pad (AEM11). 4 in transit. ANASAC, September 28-29,

5 EA Antennas All 4 12m antennas conditionally accepted 7m antennas (9 of 12 in Chile) 4 antennas conditionally accepted (CM04 on July 28) 2 undergoing tests (CM05 & CM06) 3 undergoing final adjustments & servo tests (CM07-CM09) Remaining three 7m in transit from Japan (CM10-CM12). ANASAC, September 28-29,

6 Operations Support Facility NA antennas EA antennas EU antennas OSF Technical Building Antenna acceptance testing ANASAC, September 28-29,

7 Optical Pointing Telescope 2 prototype OPTs used to verify pointing performance of first 9 NA antennas. Now used for EU antennas. 2 (of 6) production units now used at AIV and by NA Routine performance not at required level due to temperaturedependent image drift. Could delay antenna acceptances Existing and revised designs under evaluation by consultant Motion essentially eliminated by reducing OPT heat load Final report nearing completion Production to resume after completion of successful review in October. ANASAC, September 28-29,

8 Nutator Chopping secondary used for total power measurements Delayed due to issues with servo control of secondary and stiffness of mirror back plate ASIAA improved structural stiffness Unit #1 in Green Bank for servo optimization Test Readiness Review to be held in late September; user documents written Residual torque measurements underway in Taiwan Delta-CDR scheduled for early October Then ship nutator unit #1 from Taiwan to Chile for engineering tests 5 Hz, 500 throw ANASAC, September 28-29,

9 Site AOS Roads Total road distance to be built under AOS roads contract is ~67km. 33.9km (51%) of roads have been completed; overall, 89% complete AOS Utilities Rough cut of roads to all stations complete Compaction, grading, and finishing underway. Roads & utilities delayed by ~2 months due to bad weather Roads to be complete December 2011 Utilities work estimated at 45% complete Trenching and cable installation for central cluster completed Expect pads for Extended Array to be available by end of September Utilities to be complete March 2012 Permanent power supply (EU) to be operational in November ANASAC, September 28-29,

10 AOS Utilities Installation Photo Credit: NRAO/AUI/NSF, Carlos Padilla Acknowledgement: General Dynamics C4 Systems ANASAC, September 28-29,

11 AOS Roads & Utilities ANASAC, September 28-29,

12 Front Ends 26 FEs (12 EA, 10 NA, 4 EU) in Chile 4 in transit (1 EA, 1 NA, 2 EU) FEICs can deliver 1 FE per month FE component delivery on schedule Initial suite of frequency bands Band 3: GHz Band 6: GHz Band 7: GHz Band 9: GHz Assembled FE in cryostat ANASAC, September 28-29,

13 Front End Service Vehicle - I FESVs (2) are used to transport FEs to/from AOS antennas/osf FESV1 In-house acceptance (PAI) for FESV1 held in Taiwan on June Shipped to Chile on July 5. Arrived August 16. On site acceptance (PAS) held at OSF on August Recommended for conditional acceptance Conditions include documentation & operator training FESV press release at FESV2 PAI scheduled for October 7 Expected arrival in Chile in November; PAS in December ANASAC, September 28-29,

14 FESV - II ANASAC, September 28-29,

15 FESV - III Vertex Melco-12 AEM Melco-7 ANASAC, September 28-29,

16 Front End Handling Vehicle Custom cart (3) designed to move FEs between the FESV and antennas Designed and fabricated in Chile Prototype delivered to OSF for FESV PAS on August 29 Minor modifications needed to maneuver in receiver cabin of EU antenna (6 weeks) ANASAC, September 28-29,

17 Backend Completed installation and testing of final stage of central local oscillator article (CLOA) in August Brings CLOA to full complement for 66 antennas & 4 sub-arrays Final PAS held on September 23 All backend deliverables completed in September ANASAC, September 28-29,

18 Correlator 3 correlator quadrants at AOS Quadrants 1 & 2 in routine use by AIV & CSV PAS for Q3 completed in September 2010 Q4 remains at the NTC in Charlottesville to be used for software tests by computing IPT PAI completed September 6 Operational at AOS in July 2012 Correlator for Atacama Compact Array (ACA) is installed and tested. Acceptance completed January 2011 ANASAC, September 28-29,

19 Computing Correlator software testing achieved full data rate of 60 MB/s. Version R8.1 of the Software was released in early July for routine use by CSV CIPT s annual CDR (for R9.0) held in Santiago on July 4-8 Testing of the single board computer (SBC) for the antennas was done at the OSF and AOS in support of the SBC final procurement. Procurement made CASA V3.1 released. Addresses speed/performance issues Testing of CASA parallel imaging on new computer cluster improved processing speed by a factor of 8. (with EVLA) First version of the Dynamic Scheduling Algorithm agreed with science operations and implemented ANASAC, September 28-29,

20 Changes in Project Personnel Gary Parks is new JAO Project Manager (PM) With JPL since Most recently flight system manager for Phoenix Mars Lander. Previously PM for Herschel and Planck space missions Technical background in RF, remote sensing, and VLBI Michael Thorburn became new Head of the Department of Engineering (ADE) in July Was Director of Engineering for Antenna Subsystems at Loral. Previously PM for the Cassini Radio Science Program at JPL. Rich Lacasse became new lead of the NA Correlator IPT in August With AUI/NRAO since Senior Engineer in IPT since Art Symmes became new lead for the NA Antenna IPT in February NRAO civil/structural engineer on GBT and antennas. Was IPT deputy lead. ANASAC, September 28-29,

21 Schedule High Level View ITEM EXPECTED* OCCURRED Phase closure with 3 antennas at AOS Nov 2009 Nov 2009 Start commissioning and science verification Nov 2009 Jan antennas in array Aug 2010 Sep 2010 First call for proposals Dec 2010 Mar 2011 Central cluster stations complete Mar 2011 May antennas in array Feb 2011 Aug 2011 Start early science (16 antennas) Jul 2011 Sep 2011 inauguration (50 antennas) Jan 2013 Mar antennas in service Jul 2013 Sep 2013 Critical path: EU antennas & FEs, and antenna integration & verification * Expected dates as presented to ANASAC Sep 2010 ANASAC, September 28-29,

22 Budget: NA Contingency Contingency for North America $15.79M balance at end of July % of the uncommitted NA budget Liens on NA contingency (as of August 2011) From pending change requests total $6.52M Not all CRs will be approved, but more can develop Sum of weighted risks from recent update to risk register is $5.72M Financial situation for EU is similar ANASAC, September 28-29,

23 Development operations plan and budget makes provisions for future developments to enhance s capabilities. Actions to organize development: Development management plan written (under revision). Addresses: Proposal evaluation & measures to avoid NRAO conflict of interest Program management (budget, schedule, design reviews, acceptance) Development workshop held in Charlottesville on March Good NA community participation, e.g. SMA, CARMA, HIA, NRL Call for proposals for development studies to be issued soon Other Executives sponsoring similar activities JAO and Executives completed development principles document to describe how development activities will be coordinated. ANASAC, September 28-29,

24 The Atacama Large Millimeter/submillimeter Array (), an international astronomy facility, is a partnership among Europe, North America and East Asia in cooperation with the Republic of Chile. is funded in Europe by the European Organization for Astronomical Research in the Southern Hemisphere (ESO), in North America by the U.S. National Science Foundation (NSF) in cooperation with the National Research Council of Canada (NRC) and the National Science Council of Taiwan (NSC) and in Japan by the National Institutes of Natural Sciences (NINS) in cooperation with the Academia Sinica (AS) in Taiwan. construction and operations are led on behalf of Europe by ESO, on behalf of North America by the National Radio Astronomy Observatory (NRAO), which is managed by Associated Universities, Inc. (AUI) and on behalf of East Asia by the National Astronomical Observatory of Japan (NAOJ). The Joint Observatory (JAO) provides the unified leadership and management of the construction, commissioning and operation of. ANASAC, September 28-29,

ANASAC, September 20, 2012

ANASAC, September 20, 2012 ANASAC, September 20, 2012 Construction Mark McKinnon Atacama Large Millimeter/submillimeter Array Karl G. Jansky Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array Antennas

More information

Atacama Large Millimeter Array Project Status. M. Tarenghi ALMA Director

Atacama Large Millimeter Array Project Status. M. Tarenghi ALMA Director Atacama Large Millimeter Array Project Status M. Tarenghi ALMA Director Atacama Large Millimeter Array Specifications Partners: US (NSF)+Canada (NRC) - ESO+Spain - Chile 64 12-m antennas, at 5000 m altitude

More information

What is CASA? Rachel Friesen. North American ALMA Science Center. Victoria BC, January 18, 2011 ALMA Software Tutorial 1

What is CASA? Rachel Friesen. North American ALMA Science Center. Victoria BC, January 18, 2011 ALMA Software Tutorial 1 What is CASA? Rachel Friesen North American ALMA Science Center Victoria BC, January 18, 2011 ALMA Software Tutorial 1 Outline Introduction and Current Status General tools and tasks CASA in use! CASA

More information

Technical Considerations: Nuts and Bolts Project Planning and Technical Justification

Technical Considerations: Nuts and Bolts Project Planning and Technical Justification Technical Considerations: Nuts and Bolts Project Planning and Technical Justification Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long

More information

ALMA Interferometer and Band 7 Cartridge

ALMA Interferometer and Band 7 Cartridge ALMA Interferometer and Band 7 Cartridge B7 Cartridge designed, assembled and tested by: S. Mahieu, D. Maier (mixer team lead), B. Lazareff (now at IPAG) G. Celestin, J. Chalain, D. Geoffroy, F. Laslaz,

More information

Computing IPT. B.E. Glendenning (NRAO) J. Ibsen (JAO) G. Kosugi (NAOJ) G. Raffi (ESO) Computing IPT ALMA Annual External Review October

Computing IPT. B.E. Glendenning (NRAO) J. Ibsen (JAO) G. Kosugi (NAOJ) G. Raffi (ESO) Computing IPT ALMA Annual External Review October Computing IPT B.E. Glendenning (NRAO) J. Ibsen (JAO) G. Kosugi (NAOJ) G. Raffi (ESO) Computing IPT ALMA Annual External Review 25-28 October 2010 1 Outline Overall Status Software Development Organization

More information

REDUCTION OF ALMA DATA USING CASA SOFTWARE

REDUCTION OF ALMA DATA USING CASA SOFTWARE REDUCTION OF ALMA DATA USING CASA SOFTWARE Student: Nguyen Tran Hoang Supervisor: Pham Tuan Anh Hanoi, September - 2016 1 CONTENS Introduction Interferometry Scientific Target M100 Calibration Imaging

More information

The Atacama Large Millimeter/submillimeter Array: Current Status. Alison Peck Deputy Project Scientist Joint ALMA Office

The Atacama Large Millimeter/submillimeter Array: Current Status. Alison Peck Deputy Project Scientist Joint ALMA Office The Atacama Large Millimeter/submillimeter Array: Current Status Alison Peck Deputy Project Scientist Joint ALMA Office Overview International project to build & operate a large (up to 80- antennas) millimeter/submm

More information

Introduction to Radio Interferometry Anand Crossley Alison Peck, Jim Braatz, Ashley Bemis (NRAO)

Introduction to Radio Interferometry Anand Crossley Alison Peck, Jim Braatz, Ashley Bemis (NRAO) Introduction to Radio Interferometry Anand Crossley Alison Peck, Jim Braatz, Ashley Bemis (NRAO) Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope

More information

ALMA Band-1: Key Components, Cartridge Design, and Test Plan

ALMA Band-1: Key Components, Cartridge Design, and Test Plan ALMA Band-1: Key Components, Cartridge Design, and Test Plan Yuh-Jing Hwang, Chau-Ching Chiong, Yue-Fang Kuo, Ted Huang, Doug Henke, Marian Pospieszalski, Nicolas Reyes, Ciska Kemper, and Paul Ho ASIAA,

More information

ALMA Technology and. N.D. Whyborn ALMA AIV Lead Engineer

ALMA Technology and. N.D. Whyborn ALMA AIV Lead Engineer ALMA Technology and RFI Mitigation Strategies N.D. Whyborn ALMA AIV Lead Engineer nwhyborn@alma.cl CORF meeting, Santiago, 10-11 August 2009 CORF meeting, Santiago, 10-11 August 2009 ALMA System Block

More information

Introduction to Radio Interferometry Sabrina Stierwalt Alison Peck, Jim Braatz, Ashley Bemis

Introduction to Radio Interferometry Sabrina Stierwalt Alison Peck, Jim Braatz, Ashley Bemis Introduction to Radio Interferometry Sabrina Stierwalt Alison Peck, Jim Braatz, Ashley Bemis Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very

More information

Radio Interferometers Around the World. Amy J. Mioduszewski (NRAO)

Radio Interferometers Around the World. Amy J. Mioduszewski (NRAO) Radio Interferometers Around the World Amy J. Mioduszewski (NRAO) A somewhat biased view of current interferometers Limited to telescopes that exist or are in the process of being built (i.e., I am not

More information

VLA EXPANSION PROJECT MANAGEMENT PLAN. Version 1.0 September 2001

VLA EXPANSION PROJECT MANAGEMENT PLAN. Version 1.0 September 2001 VLA EXPANSION PROJECT MANAGEMENT PLAN Table of Contents Version 1.0 September 2001 I. OVERVIEW... 1 1.1 Introduction... 1 1.2 Objectives and Scope... 1 1.2.1 Scientific Objectives... 1 1.2.2 Technical

More information

ALMA Assembly, Integration and Verification: Overview and Work Plan

ALMA Assembly, Integration and Verification: Overview and Work Plan SYSE.85.01.00.00-001-A-PLA 2005-03-12 Prepared By: Name(s) and Signature(s) Rick Murowinski, with numerous contributors Organization JAO Page: 2 of 22 Change Record Version Date Affected Paras Reason 0.4

More information

The ALMA Front End. Hans Rudolf

The ALMA Front End. Hans Rudolf The ALMA Front End Hans Rudolf European Southern Observatory, ALMA, Karl-Schwarzschild-Straße 2, 85748 Garching, Germany, +49-89-3200 6397, hrudolf@eso.org Abstract The Atacama Large Millimeter Array (ALMA)

More information

~ Toward Future ~ Discussion triggered by Masao Saito

~ Toward Future ~ Discussion triggered by Masao Saito NRO 45m Telescope ~ Toward Future ~ Discussion triggered by Masao Saito NRO (draft) Mission Science Providing Cutting-edge g Science Capabilities Education Educate Next Generation Astronomers Public Outreach

More information

Planning ALMA Observations

Planning ALMA Observations Planning Observations Atacama Large mm/sub-mm Array Mark Lacy North American Science Center Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very

More information

ASTRO 6525 Lecture #18:! (Sub-)Millimeter Interferometry I!! October 27, 2015!

ASTRO 6525 Lecture #18:! (Sub-)Millimeter Interferometry I!! October 27, 2015! ASTRO 6525 Lecture #18:! (Sub-)Millimeter Interferometry I!! October 27, 2015! Dominik A. Riechers Find me at office SSB 220 E-mail: dr@astro.cornell.edu Schedule for this Section Today: Introduction to

More information

Time and Frequency Distribution Overview and Issues Rob Selina

Time and Frequency Distribution Overview and Issues Rob Selina Time and Frequency Distribution Overview and Issues Rob Selina Atacama Large Millimeter/submillimeter Array Karl G. Jansky Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array

More information

ACA; Atacama Compact Array

ACA; Atacama Compact Array ACA; Atacama Compact Array Ryohei Kawabe, ALMA-J Project Scientist & East Asian ARC Manager ALMA-J Office NAOJ 1 Array Configuration of ALMA 12-m Array ACA The ACA System 7m Array; Twelve (12) 7-meter

More information

Quarterly Status Update (QSU) January March 2010

Quarterly Status Update (QSU) January March 2010 Quarterly Status Update (QSU) January March 2010 Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array Primer The structure

More information

Integration of Band 5 receivers at ALMA/JAO. Giorgio Siringo Senior RF Engineer & FrontEnd Technical Lead - JAO on behalf of the B5 integration team

Integration of Band 5 receivers at ALMA/JAO. Giorgio Siringo Senior RF Engineer & FrontEnd Technical Lead - JAO on behalf of the B5 integration team Integration of Band 5 receivers at ALMA/JAO Giorgio Siringo Senior RF Engineer & FrontEnd Technical Lead - JAO on behalf of the B5 integration team Who is Who B5 Management ESO Project Manager: Pavel Yagoubov

More information

Evolution of the Capabilities of the ALMA Array

Evolution of the Capabilities of the ALMA Array Evolution of the Capabilities of the ALMA Array This note provides an outline of how we plan to build up the scientific capabilities of the array from the start of Early Science through to Full Operations.

More information

Current status of ASTE for submm VLBI

Current status of ASTE for submm VLBI Current status of ASTE for submm VLBI Mareki Honma (VERA/NAOJ) + ASTE submm-vlbi team member (T. Oyama, T. Hara, K. Hada, H. Nagai, T. Bushimata, S. Suzuki, N. Kawaguchi, Y. Kohno, H. Ezawa, H. Iwashita

More information

Phasing ALMA for (sub)mm-vlbi Observations

Phasing ALMA for (sub)mm-vlbi Observations Phasing ALMA for (sub)mm-vlbi Observations Enabling an Event Horizon Telescope A proposal for consideration by the ALMA Board Submitted by a collaboration including: MIT Haystack Observatory Harvard-Smithsonian

More information

Developments in Expanding the Event Horizon Telescope: Phased ALMA and South Pole Telescope

Developments in Expanding the Event Horizon Telescope: Phased ALMA and South Pole Telescope The 8 th East Asia VLBI Workshop 2015, Sapporo, Japan, 8-10 July 2015 Developments in Expanding the Event Horizon Telescope: Phased ALMA and South Pole Telescope Jan Wagner on behalf of European and Korean

More information

Technologies for Radio Astronomy Mark Bowen Acting Theme Leader Technologies for Radio Astronomy October 2012 CSIRO ASTRONOMY AND SPACE SCIENCE

Technologies for Radio Astronomy Mark Bowen Acting Theme Leader Technologies for Radio Astronomy October 2012 CSIRO ASTRONOMY AND SPACE SCIENCE Technologies for Radio Astronomy Mark Bowen Acting Theme Leader Technologies for Radio Astronomy October 2012 CSIRO ASTRONOMY AND SPACE SCIENCE Outline Current Projects CABB ATCA C/X Upgrade FAST Parkes

More information

Planning (VLA) observations

Planning (VLA) observations Planning () observations 14 th Synthesis Imaging Workshop (May 2014) Loránt Sjouwerman National Radio Astronomy Observatory (Socorro, NM) Atacama Large Millimeter/submillimeter Array Karl G. Jansky Very

More information

EVLA Memo 105. Phase coherence of the EVLA radio telescope

EVLA Memo 105. Phase coherence of the EVLA radio telescope EVLA Memo 105 Phase coherence of the EVLA radio telescope Steven Durand, James Jackson, and Keith Morris National Radio Astronomy Observatory, 1003 Lopezville Road, Socorro, NM, USA 87801 ABSTRACT The

More information

ESO/ALBiUS activities in ALMA imaging with CASA

ESO/ALBiUS activities in ALMA imaging with CASA ESO/ALBiUS activities in ALMA imaging with CASA Dirk Petry (ESO), August 2010 Outline ALMA Overview ALMA CALIM challenges CASA status Ongoing work at ESO 1 ALMA Overview The Atacama Large Mm/sub-mm Array

More information

Table 5.1 Specifications for The Evaluation Receivers (33-45?) GHz HFET amplifier GHz SIS mixer GHz (HFET amp covers GHz)

Table 5.1 Specifications for The Evaluation Receivers (33-45?) GHz HFET amplifier GHz SIS mixer GHz (HFET amp covers GHz) MMA Project Book, Chapter 5 Section 1 Evaluation Receivers John Payne Graham Moorey Last changed 1999-May-2 Revision History: 1998-11-18: Major revision 1999-05-02: Minor specification changes in Table

More information

EVLA Project Book, Chapter 4 4 Antennas and Feeds. Jim Ruff, Ed Szpindor, S. Srikanth Last changed 2002-Feb-28

EVLA Project Book, Chapter 4 4 Antennas and Feeds. Jim Ruff, Ed Szpindor, S. Srikanth Last changed 2002-Feb-28 EVLA Project Book, Chapter 4 4 Antennas and Feeds Jim Ruff, Ed Szpindor, S. Srikanth Last changed 2002-Feb-28 Revision History: 2002-Feb-28, Rev C Add paragraph on RFI; identify cable, tubing, and ducting

More information

More Radio Astronomy

More Radio Astronomy More Radio Astronomy Radio Telescopes - Basic Design A radio telescope is composed of: - a radio reflector (the dish) - an antenna referred to as the feed on to which the radiation is focused - a radio

More information

Performance Highlights of the ALMA Correlators

Performance Highlights of the ALMA Correlators Performance Highlights of the ALMA Correlators Alain Baudry 1a,b, Richard Lacasse c, Ray Escoffier c, John Webber c, Joseph Greenberg c, Laurence Platt c, Robert Treacy c, Alejandro F. Saez d, Philippe

More information

PLATO Preliminary Requirements Review Technical Report

PLATO Preliminary Requirements Review Technical Report PLATO Preliminary Requirements Review Technical Report Prepared by Review Team Reference SRE-F/2013.075/ Issue 1 Revision 1 Date of Issue 16/12/2013 Status Issued Document Type Distribution Title Issue

More information

IYAS 2015 NOEMA. the NOrthern Extended Millimeter Array. K.F. Schuster - IRAM

IYAS 2015 NOEMA. the NOrthern Extended Millimeter Array. K.F. Schuster - IRAM NOEMA IYAS 2015 the NOrthern Extended Millimeter Array K.F. Schuster - IRAM IRAM Organization Founded 1978 CNRS (France) MPG (Germany), ING (Spain) joins 1989 HQ Grenoble Admin., Technical Dev. (75 (~70

More information

The North America Array

The North America Array The North America Array Technology Development and the Realization of the SKA-High Steven T. Myers & Jim Ulvestad NRAO 15 Oct 2009 USSKA Consortium Meeting Pasadena, CA The North America Array is... Technology

More information

ALMA Band 1. Charles Cunningham and Stéphane Claude. IRMMW-THZ 2005, Williamsburg. IRMMW-THZ 2005, Williamsburg

ALMA Band 1. Charles Cunningham and Stéphane Claude. IRMMW-THZ 2005, Williamsburg. IRMMW-THZ 2005, Williamsburg ALMA Band 1 Charles Cunningham and Stéphane Claude Canadian Users - ALMA Canadian LRP 2010 The Atacama Large Millimetre Array is the top priority in LRP2000 The Atacama Large Millimetre Array (ALMA) is

More information

PROJECT CHARTER. (DRAFT Version 1.0, 16-AUG-07)

PROJECT CHARTER. (DRAFT Version 1.0, 16-AUG-07) PROJECT CHARTER (DRAFT Version 1.0, 16-AUG-07) PROJECT NAME Next Generation, Common User NRAO Pulsar Backend (AKA Scott Ransom s Dream Pulsar Machine ) PROJECT PERSONNEL Project Sponsor Scott Ransom Project

More information

EVLA Science Operations: the Array Science Center. Claire Chandler NRAO/Socorro

EVLA Science Operations: the Array Science Center. Claire Chandler NRAO/Socorro EVLA Science Operations: the Array Science Center Claire Chandler NRAO/Socorro SAGE meeting Socorro, May 22-23, 2007 The need for an Array Science Center 2 The VLA/VLBA currently supply users with raw

More information

Technologies for Radio Astronomy

Technologies for Radio Astronomy Technologies for Radio Astronomy CSIRO Astronomy and Space Science Alex Dunning in lieu of Tasso Tzioumis Facilities Program Director Technologies June 2017 Directions for ATNF Engineering (Update since

More information

Metrological Telecommunication System Development Project

Metrological Telecommunication System Development Project Philippines Metrological Telecommunication System Development Project 1. Project Profile and Japan s ODA Loan Report Date: March 2001 Field Survey: September 2000 The Philippines Manila Cebu Site Map:

More information

Preliminary Design Phase Activities, Priorities and Opportunities

Preliminary Design Phase Activities, Priorities and Opportunities Preliminary Design Phase Activities, Priorities and Opportunities Massively multiplexed spectroscopy with MSE: Science, Project and Vision Kei Szeto MSE Project Office 28 February, 2019 Outline Overview

More information

Longer baselines and how it impacts the ALMA Central LO

Longer baselines and how it impacts the ALMA Central LO Longer baselines and how it impacts the ALMA Central LO 1 C. Jacques - NRAO October 3-4-5 2017 ALMA LBW Quick overview of current system Getting the data back is not the problem (digital transmission),

More information

ALMA and how to use it. Edwige Chapillon On behalf of the IRAM ARC node

ALMA and how to use it. Edwige Chapillon On behalf of the IRAM ARC node ALMA and how to use it Edwige Chapillon On behalf of the IRAM ARC node ALMA and how to use it I- The ALMA observatory II- The ARC nodes III- The PI experience ALMA Atacama Large Millimeter/Submillimeter

More information

UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July 27, Secure Energy for America

UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July 27, Secure Energy for America RPSEA 09121-3300 3300-05 05 Autonomous Inspection of Subsea Facilities Phase I Final Presentation / Phase II Status Report UDW Technology Conference Dan McLeod / John Jacobson Lockheed Martin MS2 July

More information

Imaging and Calibration Algorithms for EVLA, e-merlin and ALMA. Robert Laing ESO

Imaging and Calibration Algorithms for EVLA, e-merlin and ALMA. Robert Laing ESO Imaging and Calibration Algorithms for EVLA, e-merlin and ALMA Socorro, April 3 2008 Workshop details Oxford, 2008 Dec 1-3 Sponsored by Radionet and the University of Oxford 56 participants http://astrowiki.physics.ox.ac.uk/cgi-bin/twiki/view/algorithms2008/webhome

More information

Space Technology FY 2013

Space Technology FY 2013 Space Technology FY 2013 Dr. Mason Peck, Office of the Chief Technologist ASEB April 4, 2012 O f f i c e o f t h e C h i e f T e c h n o l o g i s t Technology at NASA NASA pursues breakthrough technologies

More information

High Speed Data Transmission and Processing Systems for e-vlbi Observations

High Speed Data Transmission and Processing Systems for e-vlbi Observations High Speed Data Transmission and Processing Systems for e-vlbi Observations Yasuhiro Koyama, Tetsuro Kondo, and Junichi Nakajima Communications Research Laboratory, Kashima Space Research Center 893-1

More information

ANN-MS. Active GPS antenna. Data Sheet. Abstract

ANN-MS. Active GPS antenna. Data Sheet. Abstract ANN-MS Active GPS antenna Data Sheet Abstract The ANN active GPS antenna with integrated low-noise amplifier (LNA) is the perfect match to the u-blox GPS receivers. 48 x 40 x 13 mm www.u-blox.com Document

More information

Space and Missile Systems Center

Space and Missile Systems Center Space and Missile Systems Center Global Positioning Systems Directorate GPS Status & Modernization Progress: Service, Satellites, Control Segment, and Military GPS User Equipment 3 Nov 2016 Col Steve Whitney,

More information

1. INTRODUCTION 2. GENERAL CONCEPT V. 3 (p.1 of 7) / Color: No / Format: Letter / Date: 5/30/2016 8:36:41 PM

1. INTRODUCTION 2. GENERAL CONCEPT V. 3 (p.1 of 7) / Color: No / Format: Letter / Date: 5/30/2016 8:36:41 PM An ultra-broadband optical system for ALMA Band 2+3 V. Tapia a, R. Nesti b, A. González c, I. Barrueto d, F. P. Mena* d, N. Reyes d, F. Villa e, F. Cuttaia e, P. Yagoubov f. a Astronomy Department, Universidad

More information

Analysis of European Architectures for Space Exploration

Analysis of European Architectures for Space Exploration Analysis of European Architectures for Space Exploration 9 th International Conference on Exploration and Utilisation of the Moon 22 26 October, Sorrento 1 Exploration Goals Extend access and a sustainable

More information

Observing Modes and Real Time Processing

Observing Modes and Real Time Processing 2010-11-30 Observing with ALMA 1, Observing Modes and Real Time Processing R. Lucas November 30, 2010 Outline 2010-11-30 Observing with ALMA 2, Observing Modes Interferometry Modes Interferometry Calibrations

More information

Electronics Division Technical Note No Modular Analysis Software for the ALMA Front End Test and Measurement System

Electronics Division Technical Note No Modular Analysis Software for the ALMA Front End Test and Measurement System Electronics Division Technical Note No. 221 Modular Analysis Software for the ALMA Front End Test and Measurement System Aaron Beaudoin- NRAO Technology Center Summer Intern Abstract: A new software library

More information

The Australian SKA Pathfinder Project. ASKAP Digital Signal Processing Systems System Description & Overview of Industry Opportunities

The Australian SKA Pathfinder Project. ASKAP Digital Signal Processing Systems System Description & Overview of Industry Opportunities The Australian SKA Pathfinder Project ASKAP Digital Signal Processing Systems System Description & Overview of Industry Opportunities This paper describes the delivery of the digital signal processing

More information

ANN-MS. active GPS antenna. Data Sheet. locate, communicate, accelerate. Abstract

ANN-MS. active GPS antenna. Data Sheet. locate, communicate, accelerate. Abstract locate, communicate, accelerate ANN-MS active GPS antenna Data Sheet Abstract The ANN active GPS antenna with integrated low-noise amplifier (LNA) is the perfect match to the u-blox GPS receivers. 48 x

More information

Juan Carlos Guzman (on behalf of the ASKAP Computing Team) ASKAP Control Software Group Lead ICALEPCS 2011, October 2011, Grenoble, France

Juan Carlos Guzman (on behalf of the ASKAP Computing Team) ASKAP Control Software Group Lead ICALEPCS 2011, October 2011, Grenoble, France Status of ASKAP Monitoring and Control System Juan Carlos Guzman (on behalf of the ASKAP Computing Team) ASKAP Control Software Group Lead ICALEPCS 2011, 10 14 October 2011, Grenoble, France What is ASKAP?

More information

Recreation Facility Hours

Recreation Facility Hours NORMAL HOURS Recreation Facility Hours August 1, 2016 July 31, 2017 Last Revised: July 29, 2016 Effective Dates 2016: AUG 23 31, SEP 1 2, SEP 6 16, SEP 18 23, SEP 25 30, OCT 1 7, OCT 9 18, OCT 24 30, NOV

More information

The Second Health Information Technology Summit

The Second Health Information Technology Summit The Second Health Information Technology Summit Shared HIT/HIPAA Issues: The National Provider Identifier and the Impact on Payers, Health Plans and Clearinghouses Session 5.05 Tom Polhemus Principal Operations

More information

Test Methods and Standards for RF Based Emergency Equipment

Test Methods and Standards for RF Based Emergency Equipment Test Methods and Standards for RF Based Emergency Equipment Precision Indoor Personnel Location and Tracking for Emergency Responders International Technology Workshop August 1-, 011 Kate Remley, William

More information

Performance of H Maser During the EOC Week 29 July to 03 August

Performance of H Maser During the EOC Week 29 July to 03 August Performance of H Maser During the EOC Week 29 July to 03 August ALMA Technical Note Number: 6 Status: FINAL Prepared by: Organization: Date: Anthony Remijan (EOC Program Scientist for Extension and Optimization

More information

Optical Telescope Design Study Results

Optical Telescope Design Study Results Optical Telescope Design Study Results 10 th International LISA Symposium Jeff Livas 20 May 2014 See also poster #19: Shannon Sankar UF and GSFC Telescope Design for a Space-based Gravitational-wave Mission

More information

CFHT and Subaru Wide Field Camera

CFHT and Subaru Wide Field Camera CFHT and Subaru Wide Field Camera WIRCam and Beyond: OIR instrumentation plan of ASIAA Chi-Hung Yan Institute of Astronomy and Astrophysics, Academia Sinica Canada France Hawaii Telescope 3.6 m telescope

More information

TECHNOLOGICAL DEVELOPMENTS AT IGN INSTRUMENTATION AND TECHNOLOGICAL DEVELOPMENTS AT THE IGN

TECHNOLOGICAL DEVELOPMENTS AT IGN INSTRUMENTATION AND TECHNOLOGICAL DEVELOPMENTS AT THE IGN INSTRUMENTATION AND TECHNOLOGICAL DEVELOPMENTS AT THE IGN Yebes Observatory is a Fundamental Geodetic Station where Astronomical, Geodetic and Geophysical techniques are combined. Yebes, Guadalajara, Spain

More information

Attitude Determination and Control Specifications

Attitude Determination and Control Specifications Attitude Determination and Control Specifications 1. SCOPE The attitude determination and control sub system will passively control the orientation of the two twin CubeSats. 1.1 General. This specification

More information

ESO Industry Information Day. The UK Experience. 26 March 2015, Trinity College, Dublin

ESO Industry Information Day. The UK Experience. 26 March 2015, Trinity College, Dublin ESO Industry Information Day The UK Experience 26 March 2015, Trinity College, Dublin Dr Colin Vincent (Head, Astronomy Division; STFC ESO Council Member, Chair ESO Finance Committee) Funding Mechanism

More information

TrigNet: The South African Network of Continuously Operating GNSS Base Stations

TrigNet: The South African Network of Continuously Operating GNSS Base Stations TrigNet: The South African Network of Continuously Operating GNSS Base Stations R Wonnacott ESESA User Need Workshop Thread 2: Status of Current GNSS Applications in South Africa Somerset West 2 March

More information

ANTENNAS. ALMA Project Book, Chapter 4. Jeffrey Kingsley and Jaap Baars Last revised 2002-JAN-12

ANTENNAS. ALMA Project Book, Chapter 4. Jeffrey Kingsley and Jaap Baars Last revised 2002-JAN-12 ALMA Project Book, Chapter 4 ANTENNAS Jeffrey Kingsley and Jaap Baars Last revised 2002-JAN-12 4 ANTENNAS... 2 4.1 INTRODUCTION... 3 4.2 SPECIFICATIONS AND REQUIREMENTS... 4 4.2.1 Operating Environment...

More information

NASA Space Exploration 1 st Year Report

NASA Space Exploration 1 st Year Report Exploration Systems Mission Directorate NASA Space Exploration 1 st Year Report Rear Admiral Craig E. Steidle (Ret.) Associate Administrator January 31, 2005 The Vision for Space Exploration THE FUNDAMENTAL

More information

1. SMOS Status 1.1 Payload 1.2 Platform 1.3 Satellite 1.4 Launcher 1.5 FOS 1.6 DPGS 2. Other Developments 3. Future (Near & Far) 4.

1. SMOS Status 1.1 Payload 1.2 Platform 1.3 Satellite 1.4 Launcher 1.5 FOS 1.6 DPGS 2. Other Developments 3. Future (Near & Far) 4. 1. SMOS Status 1.1 Payload 1.2 Platform 1.3 Satellite 1.4 Launcher 1.5 FOS 1.6 DPGS 2. Other Developments 3. Future (Near & Far) 4. Schedule 1 1.1 Payload General: Structural / Thermal Model test campaigns

More information

SEPTEMBER PROJECT REPORT VLA PROJECT. October 15, 1976

SEPTEMBER PROJECT REPORT VLA PROJECT. October 15, 1976 ;iii--\. 'NATIONAL RADIO ASTRONOMY OBSERVATORY SEPTEMBER PROJECT REPORT VLA PROJECT October 15, 1976 NATIONAL RADIO ASTRONOMY OBSERVATORY MONTHLY PROGRESS REPORT VLA PROJECT September 1976 SITE AND WYE

More information

HPS Upgrade Proposal

HPS Upgrade Proposal HPS Upgrade Proposal HPS collaboration July 20, 2017 Analysis of the HPS engineering run data showed worse than expected reach in both the bump hunt and the vertexing searches. These reach discrepancies

More information

Specifications for the GBT spectrometer

Specifications for the GBT spectrometer GBT memo No. 292 Specifications for the GBT spectrometer Authors: D. Anish Roshi 1, Green Bank Scientific Staff, J. Richard Fisher 2, John Ford 1 Affiliation: 1 NRAO, Green Bank, WV 24944. 2 NRAO, Charlottesville,

More information

TROPOSPHERIC CHARACTERISATION OF SKA SITES

TROPOSPHERIC CHARACTERISATION OF SKA SITES TROPOSPHERIC CHARACTERISATION OF SKA SITES Document number... WP3 040.020.000 R 001 Revision... 2 Author... R.P. Millenaar Date... 2011 02 09 Status... Approved for release Name Designation Affiliation

More information

German Receiver for Astronomy at THz Frequencies

German Receiver for Astronomy at THz Frequencies German Receiver for Astronomy at THz Frequencies ATM 1-5 THz, 14 km altitude German SOFIA workshop 28,02.2011 Page 1 GREAT - the Consortium GREAT, L#1 & L#2 channels PI-Instrument funded and developed

More information

Ku-Band Receiver System for SHAO

Ku-Band Receiver System for SHAO Ku-Band Receiver System for SHAO Overview Brent Willoughby July 2014 Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array

More information

Miniature Deployable High Gain Antenna for CubeSats

Miniature Deployable High Gain Antenna for CubeSats Phantom Works Miniature Deployable High Gain Antenna for CubeSats Charles S. Scott MacGillivray Office: (714) 372-1617 e-mail: charles.s.macgillivray@boeing.com Mobile: (714) 392-9095 e-mail: zserfv23@gmail.com

More information

Agilent 8761A/B Microwave Switches

Agilent 8761A/B Microwave Switches Agilent 8761A/B Microwave Switches Product Overview Product Description The Agilent Technologies 8761A and 8761B are single-pole, double-throw coaxial switches with excellent electrical and mechanical

More information

Helioseismic Magnetic Imager Program at LMSAL

Helioseismic Magnetic Imager Program at LMSAL Helioseismic Magnetic Imager Program at LMSAL Contract PY-2223 Progress Report for December 2002 Introduction This is the third monthly progress report for the HMI program at LMSAL. We/LMSAL are collaborators

More information

Users Expectations from the ALMA Software

Users Expectations from the ALMA Software Users Expectations from the ALMA Software Leonardo Testi INAF Osservatorio Astrofisico di Arcetri ALMA Software: the users view Current status and goals Observation Preparation Science Pipeline Data Reduction

More information

A Feasibility Study of Techniques for Interplanetary Microspacecraft Communications

A Feasibility Study of Techniques for Interplanetary Microspacecraft Communications 1 A Feasibility Study of Techniques for Interplanetary Microspacecraft Communications By: G. James Wells Dr. Robert Zee University of Toronto Institute for Aerospace Studies Space Flight Laboratory August

More information

VLBI2010: In search of Sub-mm Accuracy

VLBI2010: In search of Sub-mm Accuracy VLBI2010: In search of Sub-mm Accuracy Bill Petrachenko, Nov 6, 2007, University of New Brunswick What is VLBI2010? VLBI2010 is an effort by the International VLBI Service for Geodesy and Astrometry (IVS)

More information

Relative Navigation, Timing & Data. Communications for CubeSat Clusters. Nestor Voronka, Tyrel Newton

Relative Navigation, Timing & Data. Communications for CubeSat Clusters. Nestor Voronka, Tyrel Newton Relative Navigation, Timing & Data Communications for CubeSat Clusters Nestor Voronka, Tyrel Newton Tethers Unlimited, Inc. 11711 N. Creek Pkwy S., Suite D113 Bothell, WA 98011 425-486-0100x678 voronka@tethers.com

More information

Series manufacture of the LHC main. dipole magnets. Notes about the CERN. approach to industrial. production. C.Wyss & L.

Series manufacture of the LHC main. dipole magnets. Notes about the CERN. approach to industrial. production. C.Wyss & L. Series manufacture of the LHC main dipole magnets Notes about the CERN approach to industrial production C.Wyss & L.Rossi / CERN SCRF05-12 July 2005 L.Rossi & C.Wyss - CERN 1 1232 +16 units, 8.3 T nominal

More information

OPTICS OF SINGLE BEAM, DUAL BEAM & ARRAY RECEIVERS ON LARGE TELESCOPES J A M E S W L A M B, C A L T E C H

OPTICS OF SINGLE BEAM, DUAL BEAM & ARRAY RECEIVERS ON LARGE TELESCOPES J A M E S W L A M B, C A L T E C H OPTICS OF SINGLE BEAM, DUAL BEAM & ARRAY RECEIVERS ON LARGE TELESCOPES J A M E S W L A M B, C A L T E C H OUTLINE Antenna optics Aberrations Diffraction Single feeds Types of feed Bandwidth Imaging feeds

More information

Figure 1 Photo of an Upgraded Low Band Receiver

Figure 1 Photo of an Upgraded Low Band Receiver NATIONAL RADIO ASTRONOMY OBSERVATORY SOCORRO, NEW MEXICO EVLA TECHNICAL REPORT #175 LOW BAND RECEIVER PERFORMANCE SEPTMBER 27, 2013 S.DURAND, P.HARDEN Upgraded low band receivers, figure 1, were installed

More information

Wide-Band Two-Stage GaAs LNA for Radio Astronomy

Wide-Band Two-Stage GaAs LNA for Radio Astronomy Progress In Electromagnetics Research C, Vol. 56, 119 124, 215 Wide-Band Two-Stage GaAs LNA for Radio Astronomy Jim Kulyk 1,GeWu 2, Leonid Belostotski 2, *, and James W. Haslett 2 Abstract This paper presents

More information

Brushless Servo Motor Drives xdrive Series

Brushless Servo Motor Drives xdrive Series Brushless Servo Motor Drives xdrive Series All-Digital, AC-Input, Velocity or Torque Control Allied Motion s xdrive servo drives are precision, all-digital DSP-based servo drive amplifiers capable of supplying

More information

mm/sub-mm interferometry Vincent Pietu IRAM Material from Melanie Krips, Michael Bremer, Frederic Gueth

mm/sub-mm interferometry Vincent Pietu IRAM Material from Melanie Krips, Michael Bremer, Frederic Gueth mm/sub-mm interferometry Vincent Pietu IRAM Material from Melanie Krips, Michael Bremer, Frederic Gueth Motivation Rotation lines Quantification of angular momentum. Example for a linear molecule: rotational

More information

Information Warfare Research Project

Information Warfare Research Project SPACE AND NAVAL WARFARE COMMAND Information Warfare Research Project Charleston Defense Contractors Association 49th Small Business Industry Outreach Initiative 30 August 2018 Mr. Don Sallee SSC Atlantic

More information

NASA s Detailed Response to the James Webb Space Telescope Independent Comprehensive Review Panel Report

NASA s Detailed Response to the James Webb Space Telescope Independent Comprehensive Review Panel Report NASA s Detailed Response to the James Webb Space Telescope Independent Comprehensive Review Panel Report NASA appreciates the insightful recommendations of the Independent Comprehensive Review Panel (ICRP)

More information

National Aeronautics and Space Administration Jet Propulsion Laboratory California Institute of Technology

National Aeronautics and Space Administration Jet Propulsion Laboratory California Institute of Technology QuikSCAT Mission Status QuikSCAT Follow-on Mission 2 QuikSCAT instrument and spacecraft are healthy, but aging June 19, 2009 will be the 10 year launch anniversary We ve had two significant anomalies during

More information

Data Digitization & Transmission Session Moderator: Chris Langley

Data Digitization & Transmission Session Moderator: Chris Langley Data Digitization & Transmission Session Moderator: Chris Langley Atacama Large Millimeter/submillimeter Array Karl G. Jansky Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array

More information

New Thrust in Indian Space Programme

New Thrust in Indian Space Programme New Thrust in Indian Space Programme A Glance Dr. M Annadurai Director, ISRO Satellite Centre International Technical Meet on Quality Assurance Jan 2018 Vision: Harness space technology for national development

More information

Feasibility Analysis for a Manned Mars Free-Return Mission in 2018

Feasibility Analysis for a Manned Mars Free-Return Mission in 2018 Feasibility Analysis for a Manned Mars Free-Return Mission in 2018 Inspiration Mars Dennis Tito, Taber MacCallum, John Carrico, 8 May, 2013 Authors Dennis A. Tito Inspiration Mars Foundation Grant Anderson

More information

VLA Lowband. Frazer Owen

VLA Lowband. Frazer Owen VLA Lowband Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array What is VLA Lowband? 54-86 MHz + 230-470 MHz: Two uncooled

More information

Prime Focus Imaging Spectrograph

Prime Focus Imaging Spectrograph Prime Focus Imaging Spectrograph Status 8 of 9 collimator and 6 of 9 camera lenses received (including all lenses) Slitmask mechanism assembled and wired, waveplate mechanism assembled Structure in fabrication

More information

Summary of the Second ALMA Phasing Project (APP) Commissioning and Science Verification Mission: 2015 March 24-30

Summary of the Second ALMA Phasing Project (APP) Commissioning and Science Verification Mission: 2015 March 24-30 Summary of the Second ALMA Phasing Project (APP) Commissioning and Science Verification Mission: 2015 March 24-30 ALMA Technical Note: Number 17 Status: Final Prepared by: Organization Date L. D. Matthews

More information