1 G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G-1 T H E H A R B O U R C I T Y STANDARD LAYER NAMES SHEET 1 OF 3 G-1
2 LAYER LIST Name Description Colour Linetype G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G T H E H A R B O U R C I T Y STANDARD LAYER NAMES SHEET 2 OF 3 G-1A
3 LAYER LIST Name Description Colour Linetype G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G T H E H A R B O U R C I T Y STANDARD LAYER NAMES SHEET 3 OF 3 G-1B
4 STANDARD ABBREVIATIONS PIPE MATERIAL ABBREVIATIONS PIPING ABBREVIATIONS AC CMP CI CP CU DI HDPE PVC RC ST VC ASBESTOS CONCRETE CORRUGATED METAL PIPE CAST IRON CONCRETE PIPE COPPER DUCTILE IRON HIGH DENSITY POLYETHYLENE POLYVINYL CHLORIDE REINFORCED CONCRETE STEEL VITRIFIED CLAY COMPR F FIPT H MIPT COMPRESSION FITTING FLANGE FEMALE IRON PIPE THREAD HUB MALE PIPE PIPE THREAD GENERAL ABBREVIATIONS G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G-2 ASP CONC REQ'D TYP UNO ASPHALT CONCRETE NOT TO SCALE REQUIRED TYPICAL UNLESS NOTED OTHERWISE T H E H A R B O U R C I T Y STANDARD ABBREVIATIONS G-2
5 SYMBOL MATERIAL PROPOSED ASPHALT PAVEMENT AutoCAD PATTERN DOTS EXISTING ASPHALT PAVEMENT NO HATCH GRANULAR BASE GRAVEL GRANULAR SUB-BASE TRIANG UNDISTURBED EXISTING GROUND EARTH G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G-3 GRANULAR PIPE BEDDING DOTS IMPORTED GRANULAR BACKFILL HEX APPROVED NATIVE BACKFILL HOUND PIT RUN SAND AR-SAND DRAIN ROCK HONEY IMPORTED TOP SOIL CROSS CONCRETE AR-CONC METAL ANSI T H E H A R B O U R C I T Y STANDARD MATERIALS AND HATCH PATTERNS G-3
6 SHEET 1 OF 10 G-4
7 SHEET 2 OF 10 G-4A
8 SHEET 3 OF 10 G-4B
9 SHEET 4 OF 10 G-4C
10 SHEET 5 OF 10 G-4D
11 SHEET 6 OF 10 G-4E
12 SHEET 7 OF 10 G-4F
13 SHEET 8 OF 10 G-4G
14 SHEET 9 OF 10 G-4H
15 SHEET 10 OF 10 G-4I
16 POLE TYPE - FIELDS COG - Cobra / Galvanized COP - Cobra / Painted HCP - Heritage Cobra / Painted HPP - Heritage Post top / Painted MSP - Marine Style / Painted POG - Post top / Galvanized POT - Post top / Painted STLT# WATTAGE LAMP TYPE HEIGHT POLE TYPE TYPE LUMINAIRE MAKE Nad83(CSRS) Ground Level Coordinates NORTHING EASTING L1 L2 L3 L4 L5 L6 LAMP TYPE - FIELDS HPS - High Pressure Sodium I - Incandescent L - LED MH - Metal Halide MV - Mercury Vapour LUMINAIRE TYPE - FIELDS DGC - Drop Glass / Cobra FGC - Flat Glass / Cobra GLO - Globe HER - Heritage LAN - Lantern MSP - Marine Style TOP - Top Hat STREET LIGHT TABLE TO APPEAR ON STREET LIGHT OR ROAD DRAWINGS G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G-7 WC-19 & WC-19S RB-4L SIGN SCHEDULE SIGN QTY LOCATION 1 - NW CORNER VANCOUVER/TOWNSITE SW CORNER TOWNSITE/VANCOUVER WA-36L 1 - SOUTHEND OF BUST RAMP BACK TO BACK RB-4R RB-91 & WB-36L STA STA STA NW CORNER OF TOWNSITE/VANCOUVER TRAFFIC SIGN TABLE TO APPEAR ON TRAFFIC SIGNAGE AND PAINT MARKING DRAWINGS T H E H A R B O U R C I T Y STREET LIGHT TABLE AND TRAFFIC SIGN TABLE G-7
17 G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G T H E H A R B O U R C I T Y SURVEY CODE DESCRIPTIONS AND DESCRIPTION KEY SETS SHEET 1 OF 3 G-8
18 G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G T H E H A R B O U R C I T Y SURVEY CODE DESCRIPTIONS AND DESCRIPTION KEY SETS SHEET 2 OF 3 G-8A
19 G:\INFRASTRUCTURE PLANNING\STANDARDS & PRODUCTS\MOESS\EDITION NO11\FINAL DRAFT\FINAL DRAFT STANDARD CAD DRAWINGS\SECTION 1 DWGS\G T H E H A R B O U R C I T Y SURVEY CODE DESCRIPTIONS AND DESCRIPTION KEY SETS SHEET 3 OF 3 G-8B
FOR SERVICE BOXES IN CONCRETE DRIVEWAYS, SEE NOTE Min. COVER UNDER DITCHES. 600 Min. COVER
WOOD SERVICE MARKER STAKE (50 x 00) PAINTED BLUE PL mm FROM PROPERTY LINE STANDARD CONCRETE SERVICE BOX WITH EXTENSION AS REQ'D 00 FINISHED GROUND/ROAD SURFACE FOR SERVICE BOXES IN CONCRETE DRIVEWAYS,
More informationSTANDARD CATCH BASIN GUTTER LINE CB INLET FRAME & GRATE, GROUTED TO GRADE RINGS AS REQ'D CONCRETE CURB FINISHED GRADE ASPHALT MAX 50 MIN
CB INLET FRAME & GRATE, GROUTED TO GRADE RINGS AS REQ'D ASPHALT 20 GUTTER LINE CONCRETE CURB FINISHED GRADE PRECAST GRADE RINGS, 2 50 100 MAX PRECAST CB LID GROUT ALL AROUND CB LEAD, INSIDE & OUTSIDE OF
More informationAppendix C Construction Details
7172 Kennedy Road Warrenton, Virginia 20187 Appendix C Construction Details November 2017 TABLE OF CONTENTS THRUST BLOCKS Anchorage for 11 1/4 o, 22 1/2 o & 45 o Upper Vertical Bends... AV 01 Buttresses
More informationSECTION III STANDARD DRAWINGS ROYSE CITY GENERAL CONSTRUCTION NOTES & DETAILS
9. STANDARD DETAILS SECTION III STANDARD DRAWINGS ROYSE CITY GENERAL CONSTRUCTION NOTES & DETAILS j:\clerical\royse city\1-4086 general services\168-tech const standards review\tcss manual\2018 tcss manual\sec-9a
More informationWATER STRUCTURE LEGAL & SURVEY TOPOGRAPHY/GRADING LANDSCAPE/VEGETATION
REVISION IDENTIFIER DETAIL LABEL CALLOUT LABEL 1 SHEET ABANDONED ASBESTOS CEMENT BALK OF WALK BEGINNING OF CURVE BENCH MARK BUILDING CAPACITY CAST IRON CATCH BASIN CATCH BASIN MANHOLE CENTER LINE CERTIFICATE
More informationValley Road Main Replacement
Bonding Provided Construction Co., Construction, Construction, 5% 5% 5% 5% 5% 5% 5% acknowledged 2 - Bidder Acknowledges Receipt of Addendums there was only 1 Affadivit of Preferential Bidders Status not
More informationMemorandum. Mayor and Board of Aldermen. Benjamin Requet, Senior Planner. Date: February 21, Request for Water and Sewer Service for Clay Canvas
Memorandum To: From: Mayor and Board of Aldermen Benjamin Requet, Senior Planner February 21, 2017 Re: Request for Water and Sewer Service for Clay Canvas Please consider this request for granting water
More informationSTORM M ANHOLE FOR 42" PIPE AND SM ALLER JOB NO. SHEET NO. DATE MARCH 2015 OF MIN OF 3 CRSES MAX OF 5 CRSES 30"MAX 3 OR 3.5 PRECAST ECCENTIC CONC
01-APR-2015 13:33 = I:\MSV8i\Plotting\piblack.ptb V:\201001\\C\8x11_Howell_Det\stm_det01_8x11_st01.dgn TIME = MIN 3 CRSES MAX 5 CRSES 3 OR 3.5 PRECAST ECCENTIC CONC ID PIPE GRADE A CONC FILL 4" 8" 2-0"SUMP
More informationDIVISION A GENERAL AND DRAFTING ENGINEERING STANDARDS
CITY OF ALBANY DEPARTMENT OF PUBLIC WORKS DIVISION A GENERAL AND DRAFTING ENGINEERING STANDARDS Prepared By PUBLIC WORKS DEPARTMENT ALBANY, OREGON 97321 Telephone: (541) 917-7676 TABLE OF CONTENTS A 1.00
More informationRECORD DRAWINGS REVISED TO CONFORM TO CONSTRUCTION RECORDS PROVIDED BY CONTRACTOR GMG BY DATE 11/13 CRS NO.
CELL: (715) 803-8009 MABOSI@WISCONSINPUBLICSERVICE.COM CELL: (715) 573-7806 CHVIRCKS@WISCONSINPUBLICSERVICE.COM CALVIN.KLADE@FTR.COM DGAU@KRONENWETTER.COM SCOTT OLSEN (715) 302-1348 S REVISED TO CONFORM
More informationManhole or Catch Basin Type A & B Cone Sections Precast - Design F Manhole or Catch Basin Cover (Reducer Cone Section Precast) Design D
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (14-02) MANUAL: Standard
More informationCity of Regina Standard Construction Specification SECTION 2999 LISTING OF ROADWAY STANDARD DRAWINGS
City of Regina Standard Construction Specification SECTION 2999 LISTING OF ROADWAY STANDARD DRAWINGS R-1 Alternate Pavement Structures July/10 R-2 Typical Cross Sections for Asphaltic Concrete Pavements
More informationEXISTING TREE TO REMAIN (REFER TO LANDSCAPE PLAN) 500 TANCA STREET, SUITE #209 SAN JUAN, PUERTO RICO 00901 TEL 7877244144 FAX 7877244144 19'7" MAX SIDE POOL SETBACK 1000' MAX POOL SETBACK 1000'/ PROPOSED
More informationRiverside County Flood Control & Water Conservation District
10/11/2018 Page 1 of 10 ENGINEER'S ESTIMATE MAMCO, INC. dba ALABBASI G.J. GENTRY GENERAL ENGINEERING, INC. 1 MOBILIZATION L.S. 1 $100,000.00 $100,000.00 $48,000.00 $48,000.00 $88,580.77 $88,580.77 2 WATER
More information5/16" Flange nut. Bolt Keeper Plate (8" Sq. SYS.) (3) 1/2" x 3" Hex head connector zinc plated bolt w/ washers and nut. Anchor 3" sq. 7 Ga.
2 1/2" x 2 1/2" x 10 Ga. 6" 5" 4" Variable Slipbase (8" Sq. SYS.) 5/16 Corner Bolt W/ nut 5/16" Flange nut Stub Insert (8" Sq. SYS.) Bolt Keeper Plate (8" Sq. SYS.) (3) 1/2" x 3" Hex head connector zinc
More informationEXTERIOR BUILDING, ROOFING, AND SITE IMPROVEMENTS
CONTRACT NUMBER: IFB-8-B006 ARCHITECT / ENGINEER : HURST-ROSCHE, INC. NO. LINOIS 62203 (68) 398-0890 -7 E. RANDLE ST./ N. FRITZ ST. 402 CHERRY ST., 404-406 ST. LOUIS ST. 502-506 DEE ST. 50-505 PLUM ST.
More informationDECORATIVE. Prismasphere
78 DEORTIVE Prismasphere D EORTIVE Product atalog Prismasphere The Prismasphere Series is designed to complement exterior landscape and site architecture by bringing both historically significant and classic
More informationSIGN MOUNTED BEACON SIG-027-A SINGLE SIGN MOUNTED FLASHING BEACON INSTALLED ON ONE WOOD POST DETAIL "A-1"
1 1/2" x 60" Galvanized (thread both ends) Top Bolt See Detail "A-1" and Slotted Channel Parallel Conduit Clamp Warning Sign 3 Equal Bolt Spacings (3 places at 12" min. spacing) (1) 3/8"x 7" min. (4"x
More informationFord Water Meter Couplings & Accessories
Section H 2/2001 Ford Water Meter Couplings & Accessories The Ford Meter Box Co., Inc. 775 Manchester Avenue, P.O. Box 443, Wabash, Indiana, USA 46992-0443 Telephone: 260/563-3171 FAX: 1-800-826-3487 Overseas
More information10x12 FOUNDATION GUIDE 10x12 TRICO AND FLORA SHEDS
10x12 FOUNDATION GUIDE 10x12 TRICO AND FLORA SHEDS 10x12 WOOD SKID FLOOR FLOOR SYSTEM FOR 10x12 TRICO AND FLORA SHEDS RAW MATERIALS LIST: 2 (9) FLOOR FRAMING AND SHEATHING: 1) BAND BOARD 2 x 6 x 12 PRESSURE
More informationThe Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 8
September 2013 Page 1 of 8 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of air release chambers, flushout chambers, valve chambers, meter chambers
More informationOakdale Primary School, Peterborough Civil Engineering NBS Specification
Oakdale Primary School, Peterborough Civil Engineering NBS Specification Prepared for Hamson Barron Smith Revision Schedule 171046 Civil Engineering NBS Specification May 2017 Rev Date Details Prepared
More informationSYARIKAT BEKALAN AIR SELANGOR SDN BHD
NOTE : 1. FOR LEGEND, ABBREVIATION AND GENERAL NOTES SEE DRG. NO. SYA / STD / 001. 2. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED. 3. ACTUAL LENGTH OF PE COMMUNICATION PIPES SHALL BE DETERMINED ON
More informationStandard Plate 7036 is discontinued. It is replaced by Standard Plan Pedestrian Curb Ramp Details.
DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management & Technical Support, Design Support Section TRANSMITTAL LETTER NO. (12-02) MANUAL: Standard Plates DATED: May 11, 2012 SUBJECT: Standard
More informationMidwest Roadside Safety Facility
19'-11 1/2" 6083 239'-11 1/2" 73139 Impact 1100C 25 43 5/16" 1100 upstream from the upstream face of the first shear fender downstream of the joint between barrier nos. 7 and 8 Upstream End Downstream
More information2. Remove from the Standard Plate manual: Standard Plate Index, Sheets 1-4 of 4, Numerical Index of Standard Plates (August 31, 2012)
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management & Technical Support, Design Support Section TRANSMITTAL LETTER NO. (12-04) MANUAL: Standard
More informationItem 550 Chain Link Fence
Item Chain Link Fence 1. DESCRIPTION 2. MATERIALS Furnish, install, remove, repair, or replace chain link fence and gates. Furnish certification from the chain link fence materials manufacturer stating
More informationREGISTRATION EXAMINATION, JUNE 2008 DRAINLAYING ANSWER SCHEDULE
No. 9197 REGISTRATION EXAMINATION, JUNE 2008 DRAINLAYING ANSWER SCHEDULE Plumbers, Gasfitters and Drainlayers oard, 2008. All rights reserved. No part of this publication may be reproduced by any means
More informationSYARIKAT BEKALAN AIR SELANGOR SDN BHD
NOTE : 1. FOR LEGEND, ABBREVIATION AND GENERAL NOTES SEE DRG. NO. SYA / STD / 001. 2. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED. 3. ACTUAL LENGTH OF PE COMMUNICATION PIPES SHALL BE DETERMINED ON
More informationFord Couplings For Pipe And Tubing
Section J 6/2002 Ford Couplings For Pipe And Tubing The Ford Meter Box Co., Inc. 775 Manchester Avenue, P.O. Box 443, Wabash, Indiana, USA 46992-0443 Telephone: 260/563-3171 FAX: 1-800-826-3487 Overseas
More informationSECTION BASIC MATERIALS AND METHODS
SECTION 15050 BASIC MATERIALS AND METHODS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Pipe and Fittings. 1.02 RELATED SECTIONS A. Basic Mechanical Requirements: Section 15010. B. Supports, Anchors, and Seals:
More informationCurrent Standard Plates including Transmittal Letters are available on the web at:
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Project Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (15-03) MANUAL: Standard
More informationSUBJECT: Standard Plates 4132, 4155, Drainage Structures and Castings Info
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Project Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (18-01) MANUAL: Standard
More informationSPECIFICATION STEEL COUPLING MODEL 411
Sleeve Bolt Nut Follower Gasket 1/2 2 TWO BOLT 3 12 HIGH STRENGTH 2 12 SMALL O.D. 14 60 LARGE O.D. APPLICATIONS Typical Uses Joining plain-end pipe of same outside diameters Replace split or excessively
More informationCurrent Standard Plates including Transmittal Letters are available on the web at:
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Project Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (17-04) MANUAL: Standard
More informationROUTES: 65 SECTIONS: miles in length. THE FOLLOWING ITEMS AND APPROXIMATE QUANTITIES ARE INVOLVED:
ARKANSAS DEPARTMENT OF TRANSPORTATION CA0801 HWY. 110 - CLINTON (WIDENING) (S) FEDERAL AID PROJECT ACNHPP-0071(31) THE PURPOSE OF THIS PROJECT IS TO WIDEN HIGHWAY 65 IN VAN BUREN COUNTY. THIS PROJECT CONSISTS
More information2' x 3' Polymer Pull Box Cover 4'-0" 7'-0" 24" x 76" Access Opening 3'-6"
Scope.1 Precast Concrete Equipment Slab Box 8' x 10' x Pad with 4' x 7' x 3'- Box for 5-Way RAM Gas Switch, 2-Way, 3-Way, and 4-Way Pad-Mounted RAG Gas Switches, VFI 9, VFI 12, Bypass Switch, and 33 kv
More informationAllentown, PA - Plant Expansion Steel Pipe Spec. No. 671-S40 December 31, 2015
Steel DIVISION 15: MECHANICAL SECTION 15061: STEEL PIPE 1.0 GENERAL All materials shall be of high quality and as per the following specifications. 2.0 PRODUCTS 2.1 Specification CS-1 Service = (CA, VAC)
More informationSTANDARD BID ITEM NUMBERS
10701 TRAFFIC CONTROL LUMP SUM 10702 Traffic Control for Storm Sewer Installation LUMP SUM 10703 Traffic Control for Water Main Installation LUMP SUM 10704 Traffic Control for Sanitary Sewer Installation
More informationREPAIR CLAMP PARTS H fax: MULTIPLIER
REPAIR CLAMP PARTS Part Number Component Description Model Number Product Size List Price Unit V001 Neoprene Sheet Gasket AS All Sizes Square Inch V002 Waffle Pattern Gasket (NBR) AS All Sizes Square Inch
More informationTypical Drawings for Schools
0.85 1.7 0.85 3 3 0.6 3 3 0.85 1.7 0.85 0.3 4 4 1 1 2 2 0.425 0.425 0.425 0.425 1.2 2.4 1.2 0.6 0.6 4 4 1 1 3 3 0.4 0.6 0.3 0.3 3 3 4 4 0.4 4 4 1 1 2 2 Detail of (W 1.2 x 0.4 m) Detail of (W0.6 x 0.4 m)
More informationNORTH BEND WWTP 2018 CRITICAL IMPROVEMENTS CITY OFFICIALS. City Administrator BRENDEN ELWOOD TREVOR KOSTANICH ALAN GOTHELF. City Council.
NORTH BEND KING COUNTY WASHINGTON CITY OFFICIALS KENNETH G. HEARING Mayor LONDI LINDELL City Administrator BRENDEN ELWOOD TREVOR KOSTANICH ALAN GOTHELF City Council MARTIN VOLKEN MARK RIGOS, P.E. PUBLIC
More informationRSB-RCS/L SERIES The RSB-RCS/L Series rectangular shoebox is offered in a variety of lighting distributions with sharp cutoff to meet the challenging demands of today s site lighting projects. Fixture
More informationSUBJECT: Standard Plate Turf Establishment Areas (at Pipe Culvert Ends)
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (14-01) MANUAL: Standard
More informationSPECIFICATIONS FOR THE INSTALLATION OF CONDUIT SYSTEM(S) FOR STREETLIGHTS. 1 Definitions. 2 Scope of Work. 3 Extent of Work
SPECIFICATIONS FOR THE INSTALLATION OF CONDUIT SYSTEM(S) FOR STREETLIGHTS Section 1 Definitions 2 Scope of Work 3 Extent of Work 4 Inspection and Performance of Work 5 Trenching 6 Duct Installation 7 Backfilling
More information1. MATERIALS SHALL CONFORM TO THE FOLLOWING: a) STEEL REINFORCING - WIRE FABRIC (4x4) GALVANIZED - G G REINFORCING EARS TO BE EPOXY CO
1. MATERIALS SHALL CONFORM TO THE FOLLOWING: a) STEEL REINFORCING - WIRE FABRIC (4x4) GALVANIZED - G40.20-041G40.21-04 REINFORCING EARS TO BE EPOXY COATED - D3963/D3963M CEMENT - PORTLAND GU b) FINE AGGREGATE
More informationCONSTRUCTION SPECIFICATION FOR MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 407 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION TABLE OF CONTENTS 407.01
More informationINSTRUCTIONS: 1. Record the transmittal letter number, date, and subject on the transmittal record sheet located in the front of the manual.
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Technical Support Design Services Section TRANSMITTAL LETTER NO. (0-03) MANUAL: Standard Plates DATED: September
More informationSUBJECT: Standard Plate 9102 Turf Establishment Areas At Pipe Culvert Ends
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Project Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (17-03) MANUAL: Standard
More informationEngineering Department DRAWING STANDARD SPECIFICATIONS
DRAWING STANDARD SPECIFICATIONS June 2017 City of Surrey TABLE of CONTENTS Page i Page 1 INTRODUCTION... 1 1.1 Overview... 1 1.2 Measurements / Units... 1 1.3 Hardcopy and Digital Template... 1 2 DRAWING
More informationMH Table of Contents Standard Title/Scope Page Table of Contents SCE Public
MH Table of Contents Standard Title/Scope MH 300 MH 310 MH 318 MH 320 MH 325 MH 330 MH 335 MH 340 MH 350 Manholes Requirements MH 300.1 Manholes Requirements...........................................
More informationManholes Table of Contents
Standard MH 300 Title Manholes Requirements MH 300.1 Manholes Requirements Manholes Table of Contents Underground Structures Standards MH 310 MH 318 MH 320 MH 325 MH 330 MH 335 MH 340 MH 350 Precast Tub-Type
More informationSECTION 58 PRECAST CONCRETE BOX CULVERT. This work consists of furnishing and installing Pre-cast Concrete Box Culverts.
SECTION 58 PRECAST CONCRETE BOX CULVERT 58.1 DESCRIPTION A. General This work consists of furnishing and installing Pre-cast Concrete Box Culverts. B. Related Work Section 51 Section 52 Section 53 Section
More informationMSD STANDARD DRAWINGS LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT 700 WEST LIBERTY STREET LOUISVILLE, KENTUCKY
MSD M etr o p olitan S e w e r Di s t r ict STANDARD DRAWINGS LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT 700 WEST LIBERTY STREET LOUISVILLE, KENTUCKY 40203-1911 STANDARD DRAWINGS DIVISION
More informationSection. DEVELOPMENT STANDARDS City of Ellensburg ILLUMINATION STANDARDS
Section 8 City of Ellensburg ILLUMINATION STANDARDS Table of Contents STREET ILLUMINATION...3-5 GENERAL NOTES...3 INSTALLATION AND CONNECTIONS...3 MARKING...3 STAKING...3-4 TRENCH REQUIREMENTS...4 ILLUMINATION
More informationCl. I, Div. 1, Group B (with suffix GB), C, D Cl. I, Zone 1, Group IIB + H2
EVLS Hazard Gard A compact, affordable, explosionproof luminaire that has the best overall temperature performance ratings in its class! Eaton's Crouse-Hinds EVLS Hazard Gard is perfect as a general area
More informationSAUSALITO-MARIN CITY SANITARY DISTRICT MISCELLANEOUS UPGRADES PROJECT. Addendum No. 2
SAUSALITO-MARIN CITY SANITARY DISTRICT MISCELLANEOUS UPGRADES PROJECT Addendum No. 2 The following shall modify the Contract Documents. The work shall be accomplished in accordance with such modifications.
More informationCITY OF PITTSBURG ENGINEERING DEPARTMENT CONTRACT NO A WATER TREATEMENT PLANT CAPITAL IMPROVEMENTS PHASE 1A ADDENDUM #1 FENCE AND DITCH AUGUST
CITY OF PITTSBURG ENGINEERING DEPARTMENT CONTRACT NO. 2012-16A WATER TREATEMENT PLANT CAPITAL IMPROVEMENTS PHASE 1A ADDENDUM #1 FENCE AND DITCH AUGUST 2014 CHAIN LINK FENCE SPECIFICATIONS Chain link fence,
More informationBoardwalk Construction Guidelines
Boardwalk Construction Guidelines Acton Land Stewardship Committee Acton, Massachusetts 1 Rev. 2-2/9/2018 NOTICE TO AGENCIES OUTSIDE THE ACTON LAND STEWARDSHIP COMMITTEE THE BOARDWALK CONSTRUCTION GUIDELINES
More informationSPECIFICATIONS FOR THE INSTALLATION OF CONDUIT SYSTEMS IN RESIDENTIAL SUBDIVISIONS. Notification of Completed Conduit Sections
SPECIFICATIONS FOR THE INSTALLATION OF CONDUIT SYSTEMS IN RESIDENTIAL SUBDIVISIONS Section 1 Definitions 2 Scope of Work 3 Extent of Work 4 Inspection and Performance of Work 5 Trenching 6 Duct Installation
More informationREGIONAL TRANSIT AUTHORITY PUBLIC NOTICE. IFB Rail Expansion (Streetcar) Rampart Street. Addendum IV
REGIONAL TRANSIT AUTHORITY PUBLIC NOTICE IFB 2014-014 Rail Expansion (Streetcar) Rampart Street Addendum IV Acknowledge receipt of this addendum in the bid submission. This addendum is a part of the Contract
More informationGeneral Information. Ball Curb Valve
General Information 1. All Jones Curb Valves are manufactured in accordance with the AWWA Standard C-800-latest revision. 1. Copper Alloy CDA No. C83600 (85-5-5-5) 2. Copper Alloy CDA No. 89520 (Low Lead)
More informationTool 3-1 A2 Bushing 6 Check if the bushing supports (angle iron) are properly welded with the upper part of the structure pipes. welded bushing suppor
Rope Pump MANUFACTURING checklist for quality control A Welding General 1 Check if welding jigs are used for welding of the main parts (wheel, structure frame and bushings) 2 Check if the pump parts are
More informationSection H 02/2018 THE FORD METER BOX COMPANY, INC. CERTIFIED TO ISO 9001: Ford Water Meter Couplings and Accessories
DQS Inc. Section H 02/2018 THE FORD METER BOX COMPANY, INC. CERTIFIED TO ISO 9001:2015 10002505 Ford Water Meter Couplings and Accessories Contents Page Information ing System... 3 Pack Joint Connections
More informationInjection moulding. Introduction. Typical characteristics of injection moulded parts
Injection moulding Introduction Injection molding is generally used to produce thermoplastic polymers. It consists of heating of thermo plastic materials until it melts and then injecting into the steel
More informationPART 4 STANDARD DRAWINGS FOR CONSTRUCTION
4.0. INTRODUCTION PART 4 STANDARD DRAWINGS FOR CONSTRUCTION In this document, Ivins City adopts the most recent edition (currently 2007), including all amendments, of the APWA Utah Chapter s Manual of
More informationCity of Regina Standard Construction Specification SECTION 2660 CHAIN LINK FENCE
1.0 GENERAL 1.1 Scope 1.1.1 The work shall consist of supply and installing chain link fence, including braces and gates, as shown on the plans and specifications at the locations designated by the Engineer.
More informationSection COUPLINGS AND COUPLING ADAPTERS. This Section covers couplings and coupling adapters for ductile iron and steel pipe.
PART 1 GENERAL 1.01 SUMMARY Section 15155 This Section covers couplings and coupling adapters for ductile iron and steel pipe. 1.02 MEASUREMENT AND PAYMENT A. No separate payment for Work performed under
More informationThru Wall Floor Seals For New Installation
The O-Z/Gedney Thruwall and Floor Seals provide a positive means of sealing pipe, conduit or tube where they pass through a concrete foundation of a structure below grade or below ground water level or
More information24 X32 3 CAR GARAGE POLE BARN STYLE FRAME
24 X32 3 CAR GARAGE POLE BARN STYLE FRAME 3 ENTRY DOOR 2 WINDOWS, 1 @ EA. END 1-16 X8 GARAGE DOOR 1-9 X8 GARAGE DOOR 4 CONCRETE SLAB 10 WALLS 4/12 PITCH METAL ROOF METAL SIDING INDEX PAGE DESCRIPTION 1
More informationEVLP Low Profile Hazard Gard (H.I.D.) Luminaires
EVLP Low Profile (H.I.D.) Luminaires Medium and Cl. I, Div. 1, Groups B (GB suffix), C, D Cl. I, Zone 1, Groups IIB + H2 (with suffix GB), IIB, IIA Cl. II, Div. 1, Groups E, F, G; Class III Marine & Wet
More informationQUANTITY SURVEYS. Introduction
QUANTITY SURVEYS Introduction In engineering surveying, we often consider a route (road, sewer pipeline, channel, etc.) from three distinct perspectives. The plan view of route location is the same as
More informationPipe Restrainers series C Restrainers for use on IPEX Bionax AWWA CI OD C909 PVCO Pipe with MJ or Push-On Fittings
Pipe Restrainers series 1000 1000C Restrainers for use on IPEX Bionax AWWA CI OD C909 PVCO Pipe with MJ or Push-On Fittings INFORMATION Restrainers for restraining mechanical joint or push-on fittings
More informationGeneral Information...SA1-SA4
SECTION S INDEX Product Description Page Number General Information................................................................SA1-SA4 Type FSK Thruwall & Floor Seal For Conduit, Pipe or Tubing............................
More informationSTRUCTURES FOR SANITARY AND STORM SEWERS
SUDAS Standard Specifications Division 6 - Structures for Sanitary and Storm Sewers Section 600 - Structures for Sanitary and Storm Sewers STRUCTURES FOR SANITARY AND STORM SEWERS PART - GENERAL.0 SECTION
More informationSUPPLEMENTARY STANDARD DETAIL DRAWINGS
CITY OF MAPLE RIDGE DESIGN AND CONSTRUCTION DOCUMENTS Part 4 SUPPLEMENTARY STANDARD DETAIL DRAWINGS September 2015 Updated: October 2015 THIS PAGE INTENTIONALLY LEFT BLANK City of Maple Ridge Supplementary
More informationThis addendum forms a part of the Contract Documents dated: August 10, 2012.
Addendum # 1 Date Issued: August 28, 2012 Issued By: Project: Owner: Renker Eich Parks Architects 1609 Dr. Martin Luther King Street North St. Petersburg, Florida 33704 Ph# (727) 821-2986 Fax # (727) 896-4911
More informationA representative from Occupational Health is to be involved in the commissioning process to address any Respiratory Protection Program requirements.
SPEC-3017 1/8 1.0 PURPOSE This specification describes the minimum requirements for the installation of breathing air distribution systems (indoor and outdoor) up to the connection to the breathing air
More informationTesting. Material testing will be according to applicable AASHTO, ASTM or Department methods as specified.
907.01 Section 907. FENCING MATERIALS 907.01 General Requirements. Materials for use in fencing property, right-of-way and other installations must comply with this section. 907.02 Testing. Material testing
More informationSECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section
02760-1 of 5 SECTION 02760 STEEL LIGHTING STANDARDS 02760.01 GENERAL A. Description Steel lighting standards shall include, but not necessarily be limited to, furnishing and installing steel lighting poles,
More informationArchitect. Architect.
The The line line sketch sketch with with modified modified height height for for plinth plinth floor floor is is displayed. displayed. Open Open Architectural Architectural plan plan file, file, which
More informationSECTION UNDERGROUND POWER DUCT AND SUB-STRUCTURES. A. Section : Trenching, Backfilling, and Compacting
SECTION 33 71 19 UNDERGROUND POWER DUCT AND SUB-STRUCTURES PART 1 GENERAL 1.1 RELATED WORK A. Section 31 23 33: Trenching, Backfilling, and Compacting B. Section 32 01 00: Site Restoration and Rehabilitation
More informationModeling, Analyzing and Fabrication of Lifting SPRhook for Borewell Pipe
2014 IJEDR Volume 2, Issue 1 ISSN: 2321-9939 Modeling, Analyzing and Fabrication of Lifting SPRhook for Borewell Pipe 1 S.Prithiviraj, 2 S.Ravikumar 1 Post Graduate Student, 2 Assistant Professor Department
More informationINSTALLATION INSTRUCTIONS. March 2016 FOR FURTHER QUESTIONS, PLEASE CALL
March 2016 INSTALLATION INSTRUCTIONS FOR FURTHER QUESTIONS, PLEASE CALL 775 440 2025 JENSEN WATER RESOURCES 521 Dunn Circle, Sparks, NV 89431 JensenPumps.com Figure 1: This illustration shows a complete
More informationGENERAL NOTES ABBREVIATIONS DRAWING THEME STRUCTURAL DRAWING LIST SUBMITTALS S101 GENERAL NOTES SOUTH DYKE RIVERFRONT WALKWAY
GENERAL NOTES ABBREVIATIONS DRAWING THEME SUBMITTALS STRUCTURAL DRAWING LIST GENERAL NOTES S0 LETTERS OF ASSURANCE TENDER DOCUMENTS DESIGN BY CONTRACTORS TEMPORARY AND ANCILLARY WORKS AND SITE SAFETY FIELD
More informationRiverside County Flood Control & Water Conservation District
9/28/2016 Page 1 of 10 ENGINEER'S ESTIMATE MAMCO, INC. dba ALABBASI H & H GENERAL CONTRACTORS, INC. 1 MOBILIZATION L.S. 1 $50,000.00 $50,000.00 $106,571.00 $106,571.00 $180,000.00 $180,000.00 2 WATER CONTROL
More informationMoulding. Second Edition. Crawford. Roy J. 4CC%SMITHERS. A Smithers Group Company
Practical Guide to Rotational Moulding Second Edition Roy J. Crawford Mark P. Kearns 4CC%SMITHERS %))J R A P R A A Smithers Group Company Shawbury, Shrewsbury, Shropshire, SY4 4NR, United Kingdom Telephone:
More informationCity of Kitchener Infrastructure Services Department Engineering Services Division. CAD Standards for Engineering
City of Kitchener Infrastructure Services Department Engineering Services Division CAD Standards for Engineering Printed: October 29, 2012 Revision History Revision Description Date Layer revisions. June
More informationHigh Intensity Discharge Ballasts
CONTENTS High Intensity Discharge Ballasts Page No. 2 Mercury/Metal Halide Ballasts 3 Mercury/Metal Halide & Pulse Start Ballasts Available Models 4 Dimensions of Mercury/Metal Halide Ballasts 4 Wiring
More informationAdvanced Ground Investigation Techniques to Help Limit Risk or Examine Failure. Advanced Subsurface Investigations
Advanced Ground Investigation Techniques to Help Limit Risk or Examine Failure Overview Introduction What is geophysics? Why use it? Common Methods Seismic Ground Radar Electrical Case Studies Conclusion
More informationMUNICIPAL INFRASTRUCTURE
2440 MUNICIPAL INFRASTRUCTURE 100 50 90 90 1220 305 65 65 45 MUNICIPALITY OR SERVICE OARD Department of Municipal Affairs and Environment Hon., Minister 40 100 50 50 WHITE REFLECTIVE ACKGROUND 1. LETTERING
More informationSection XI - Drawings, Record Drawings and Valve Guides
Section XI - Drawings, Record Drawings and Valve Guides A. Introduction HRSD has in excess of 24,000 Record Drawings in an electronic form which are archived in a records management system based on the
More informationAssmann Corporation of America TANK INSTALLATION AND USE GUIDELINES FOR BULK STORAGE TANKS
Assmann Corporation of America TANK INSTALLATION AND USE GUIDELINES FOR BULK STORAGE TANKS General Information Assmann polyethylene storage tanks are manufactured to give you the toughest, most reliable
More informationSUBMITTAL LIST Note: See tab below for Samples and Instructions. Attach to end of Specification Section when complete.
REQUIREMENTS (indicate with an "") 011100 1.4 Detailed Construction Phasing Plan 011100 1.4 Sub-Surface Utility Location Plan 013100 1.3 Letter Designating Project Superintendent 013100 1.3 Construction
More informationMeter Box Access Solutions
Meter Box Access Solutions Table of Contents Meter Box Access Solutions Oval Meter Boxes Round Meter Boxes Rectangular Meter Boxes Meter Pits Adapter Rings Meter Lids Meter Covers, Plates and Lids Accessories
More informationMeasuring Pipes and Pipe Fittings
Measuring Pipes and Pipe Fittings by Larry Johnston When you repair or modify home plumbing, knowing the kind and size of pipe you need can save you time and trouble not to mention trips to the hardware
More informationSECTION PRECAST CONCRETE SECTIONAL MANHOLES
SECTION 02545 PRECAST CONCRETE SECTIONAL MANHOLES PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Precast reinforced concrete cylindrical sectional manholes, complete with openings, inserts, hardware,
More informationDISCONTINUED. LTV10 Series Composite Housing Accent. Specifications. Lightvault. Type: Job: Catalog number: Approvals: Fixture Options: / / /
Catalog number: Specifications 16J" (412.8 mm) 2B" (54.0 mm) Hubbell Lighting, Inc. / / / Fixture Optics Lamp Mode Option - order assembled with fixture See page 2 See page 3 L" (19.1 mm) 13J" (336.6 mm)
More informationSECTION MANHOLES
SECTION 02601 MANHOLES PART 1 GENERAL 1.01 SCOPE OF WORK A. WORK required under this section consists of all materials, accessories, equipment, tools, and labor required to install precast concrete standard
More informationMDOTProjectwise\Documents\Reference Documents\Traffic Reference\Statewide Special Details\Develop
500 460 MDOTProjectwise\Documents\Reference Documents\Traffic Reference\Statewide Special Details\Develop Check if Applicable TRAFFIC SIGNAL SPECIAL DETAILS INDEX/CHECKLIST *One completed checklist required