1 ADDENDUM NUMBER ONE (1) For Occoquan Regional Park Jean R. Packard Center 1608 Room Exhibit Fabrication & Installation Addendum Date: Thursday, May 4, 2017 GENERAL: A. This addendum is hereby made a part of the Invitation to Bid for the above referenced project. The addendum shall become part of the Contract Documents and modify the bidding documents. B. Please note the addition of the attached page to the bid documents. This page was missing from the original bid document set and by inclusion with this addendum, is hereby incorporated into the project bid documents. C. Bidders should acknowledge receipt of this Addendum in the appropriate space on the bid form. D. This Addendum consists of EIGHT (8) pages of bidder questions and answers along with an attached document. BIDDER QUESTIONS AND ANSWERS: 1. Will the illustration/artwork required for the Floor Treatment be provided or is the procurement of this item the responsibility of the Fabricator? Addendum #1 Page 1 of 8

2 A: The flooring materials, installation, and final art are the responsibility of the flooring subcontractor. The artwork has been built to scale and will be provided. Any final adjustments for material thicknesses etc., are to be completed by floor subcontractor. 2. In what application/software and version and on which platform (MAC or PC) will the final high resolution production files be created? A: MAC, InDesign CC 2017 primarily (Illustrator and Photoshop may have been used as well). 3. Will all edits be complete or will the Fabricator be expected to do any or all final edits? A: Complete. Print-ready files will be 100% complete and no edits will be necessary during the fabrication phase. The fabricator will be responsible for providing the Illustrator templates so he has the right size and shape for his illustrations. 4. Will any photo retouching or compositing be required? If so, what percentage of the photos will require retouching? What type of retouching minor/medium spotting or major reconstruction/compositing? A: Files will be print-ready. No retouching will be necessary. 5. Will fonts be provided with the files or is it the Fabricator s responsibility to purchase all necessary fonts? A: All fonts will be provided and/or outlined. 6. Please provide a Graphic Elements List (Schedule) as an Excel document. Graphic Elements list to include all graphic elements identified using the approved numbering criteria, sizes and production methods. A: Please see drawings for graphics and specifications. A list has not been developed. 7. Please provide a detailed listing and description of all required custom illustrations needing procurement. A: See pg. 17. These topics and thumbnail sketches are approved. Further coordination should take place once an illustrator is brought on board. 8. Please verify the production method of the Chesapeake Bay Wall Shape. Drawing page 11 notes as an Applied Vinyl Map whereas page 22 notes as painted on wall. Which is the correct production method? Will you provide the art file? Will a dark border be required and provided as a separate file? A: The intent was painted. Art will be provided in vector format. Darker border shouldn t be necessary. Paint should be a shade darker to avoid requiring an outline. 9. On page 8 of the JRPOC 1608 Room Exhibits Project Manual document, Fabrication Scope and Services Overview, Item 1 Graphics, lists wall murals. Is this item still a requirement? If so, where is it located, what is the size and production method custom mural on-site by a muralist or custom mural reproduced as digitally printed wallpaper? Addendum #1 Page 2 of 8

3 A: This section of the Project Manual is a general overview outlining potential project needs. There are no applied graphic wall murals on this project. 10. The Project Closeout Scope Overview, page 11 of the JRPOC 1608 Room Exhibits Project Manual document does not include the Final Print/Production files. Is this an oversight? Will Final Production Files need to be included with the Close Out Package? A: Fabricator is responsible for packaging up (files, fonts, images ) the final files they used to go to print with and specify the installed final materials and finishes in the closeout package. 11. Regarding HPL graphics, is High Pressure Laminate required, or will PLI s equivalent acceptable? A: PLI is acceptable. 12. Are 11x17 color copy proofs and/or electronic pdf proofs acceptable? A: These are acceptable for drawings and FPO graphic proofs. Otherwise, samples should be submitted for each graphic material. 13. The bid package refers to the etched glass display in numerous places but the project drawings call for acrylic and 3-form. Has the glass been replaced by acrylic? A: Glass has been replaced with acrylic. However, the 1 st layer is GAR, which has a glass laminated surface for protection against scratches. 1 st layer is clear GAR, 2 nd and 3 rd are blue-colored 3-Form. 14. Project Manual Pg. 5 The itemized cost breakdown lists two entries on separate lines for glass rail graphics - Glass wave rail with laser etched and interpretive graphics on one line and Glass wave illustrations on another line. What are each of these - interpretive graphics and glass wave illustrations? A: Interpretive graphics are both the graphic glass etchings and the small rail caption graphics above. Illustrations were listed separately to account for hiring an illustrator. 15. Project Manual Pg. 5 in the middle of the list there is an entry for Floor Treatment. Is this the cost for just the painted lines on the floor as described on page 8 of the Project Drawing or does it include the flooring with installation, the artwork, and protective clear coats? A: The flooring materials, installation, and artwork, clearcoat, et. al. is all the scope of the flooring subcontractor. Initial artwork will be supplied by designer but may have to be slightly adjusted. 16. Project Manual Pg. 9 - Paragraph 1 in the middle of the page states that all freestanding units must withstand 100 lbs. of lateral force without tipping at 5 height. However, the Addendum #1 Page 3 of 8

4 Intro Panel shown on page 7 of the design Drawing is too narrow and on casters and will not meet this requirement. Is the anti-tipping requirement void? A: That is a portable unit on casters and is exempt from that requirement; however the fabricator needs to verify that it is stable enough to not pose a safety risk. 17. Project Manual Pg. 15 Graphic sample #4 is a print of the sails. Describe the requirements to print the sail fabric what is being printed on the fabric? Will a graphic file be provided? A: A PMS or color swatch will be provided for sampling. The printing technique is a solid field of color on the bottom layer and coming up the visible sides only. The color will be a light beige color. Anywhere there are sewn seams we would like the seaming to resemble sailmaking, designer to provide sample of the seaming required. The pattern on the sail will be achieved by lighting and the internal ribbing of the structure casting shadows. 18. Project Manual Pg. 20 Under Ceilings there is an entry stating the exhibit contractor is required to verify the ceilings are structurally sound to hang exhibits and equipment before accepting from GC. To accomplish this verification, the exhibit contractor will need to hire an independent structural engineer to review the GCs drawings and work. If the independent engineer determines the ceiling is not structurally sound, what is the corrective course of action? Will the GC s drawings be stamped by a structural engineer and the completed work inspected? A: All ceiling attachments are to the beams only (see pages 11,16 in package and attached drawings). This method has been approved by the architect. Also note the method of attaching the support cables to the sail frames. We estimate the entire assembly is no more than 200lbs, so stamped engineering drawings are not required. However, we are expecting the exhibit fabricator to inspect the existing conditions and make sure the hanging structure overhead is securely fastened and deemed safe. 19. Project Manual Pg. 20 Under Ceilings there is an entry requiring the exhibit contractor to coordinate the location of the hanging pipe(s) for fixtures used to suspend and light the sails. Is the GC responsible to install the pipes? Who supplies the pipe and makes the necessary modifications to accommodate the attachment to the building structure and hanging sails? A: See note above; the pipe and mounting hardware, along with installation, are in the exhibit fabricator s scope. Addendum #1 Page 4 of 8

5 20. Project Manual Pg. 20 Under Ceilings there is an entry requiring the exhibit contractor to coordinate sprinklers, HVAC, house lighting, and security with the GC. Is there any security in the exhibit contractors scope? A: None of the above is in the exhibit fabricator s scope, other than to coordinate installation of exhibit elements so there is no conflict. THE EXCEPTION is the 3 sprinkler heads that penetrate the sails. Those heads will need to be installed (see detail) after the sails are installed. This is in the exhibit fabricator s scope but will require a licensed sprinkler sub-contractor. 21. Project Manual Pg. 21 mid-page there is an entry stating EX Responsible for making sure integral lighting works with life safety systems. What is the extent of this requirement? A: We don t believe exhibits specified effect the building life safety requirement, fabricators to check with GC and make sure this is not required. Concern would be what happens to the fish tank if the power goes out. 22. Project Manual Pg. 22 Under Security at the top of the page it states EX Coordinate and security equipment or integration with the owner and GC. What security requirements are required? A: There are no specific security specifications for the exhibits, only coordination we could see if the GC is installing cameras, and we need to coordinate viewpoints. 23. Project Drawings this package contains the contact information for several vendors. Are other vendors permitted to bid on this project? A: Other vendors are permitted to bid, but in most cases, pricing, specifications, and design drawings are based on information from the specified vendors. Also note that in some cases, samples from the listed suppliers have been submitted and approved. Care should be exercised: if substituting vendors be absolutely sure all specs are met and no design changes are required. Any changes in materials may also involve re-submitting samples for approval. 24. Project Drawing Pgs. 12 & 13 These two pages have different quantities for the sprinkler heads. Will there be 3 or 4? A: There are three (3) heads that penetrate the sails. 25. Project Drawing Pg. 10 The note on the right side of the page specifies Moss Eco Poly Duck White for the sail fabric. Will the fabric color be one a standard Moss color or will it be a custom color? Will printing be required if yes, what is the nature of the print and will you provide the camera ready artwork. Addendum #1 Page 5 of 8

6 A: The fabric spec. has been submitted by Moss and approved. It is a standard Moss material. A solid color is requested and may require printing Moss. A color swatch can be provided. 26. Project Drawing Pg says the fish and tank accessories by others. The Aquarium Specifications box on page 26 lists a variety of equipment. Do we need to provide pricing for any of the tank equipment? A: The specifications and equipment were specified by the aquarium sub-contractor. All equipment and installation should be by them. The props noted on pg. 23 are to be provided by fabricator (spear, fish, and canoe base). 27. Project Drawing Pg. 26 is there a specific requirement for the material used to construct the fish tank (e.g., acrylic or glass)? A: That should be specified by the aquarium sub-contractor. 28. Project Drawing Pg. 30 How many artifacts require mounts? Weights and sizes? Mounted to the deck or back panel? A: See page 30 and 31 for artifacts and layouts. All artifact mounts are spider mounts from the rear. 29. On page 7 Item D says Content for AV (images, maps, illustrations, digital files and videos) Will be provided by owner Does this include all audio including bird sounds, river sounds other SFX and narration? A: No, all audio, SFX or voice over will be the responsibility of the exhibit fabricators AV Subcontractor. 30. If narration is to be provided by AV contractor, do they want the same narrator for each? Or might they want one man and one woman? If they are providing narrators, will they record the narration or will the AV contractor? A: Fabricator s AV Subcontractor will be responsible for hiring and implementing anything to do with narrating the films. Please price just using one voice for all four. 31. Who is providing scripts? Below is a list of tasks that I would think that we would include in our Quote, please verify that this is correct. Meet with client and get owner-provided materials Write treatments (include an attract screen) Write scripts Provide rough cut edits to scratch narration for approval Provide second rough cut (if needed) Provide narrator samples for selection Record narrator Addendum #1 Page 6 of 8

7 Provide caption files for approval Provide Fine cut for approval with captions Provide Master files A: The list of task outline above would be what is required for this project. Only other task for the AV Subcontractor would be to work with the Fabricator and client to verify the equipment specifications and make sure programs are running smoothly. 32. Aquarium - is acrylic acceptable for construction of the aquarium? It offers the following advantages; a. Better viewing properties: Most modern public displays are made using acrylic. Acrylic is clearer than glass it s the clearest material known. It also has a better light transmission level. Objects appear sharper and colors are more vibrant. Modern acrylic does not have a greenish tint and will not turn yellow. b. Strength: Acrylic is times stronger than glass of the same thickness, with better impact resistance. Because the joints are chemically bonded, not connected with an adhesive, they are also stronger visually more appealing. c. Refinishing: Acrylic scratches more easily than glass, but can be repaired/refinished to a like new condition. This includes scratches on the inside that can be repaired without having to remove livestock. Note that scratches are preventable with proper care and precautions. d. Better insulating properties: Acrylic will not conduct heat and cold as well as glass will, making it a better insulator. Acrylic aquariums will regulate and minimize temperature fluctuations better, giving you a more stable system. e. Weight: Acrylic is slightly less than half the weight of glass of the same thickness. This allows for easier moving and installation. A: Yes, acrylic is an acceptable substitution. 33. Artifacts - what is the availability of the artifacts for measuring by the mount maker? A: The artifacts will be made available for measuring. 34. Artifacts - Do you have a list with pictures? A: See pages 13 and 14th in the drawings package, these are all the artifacts. Artifacts to be mounted with rear spider mounts. Addendum #1 Page 7 of 8

8 Failure to register with NOVA Parks and/or failure to acknowledge addenda distributed to registered bidders could lead to bid disqualification. Project Addenda will be posted on the NOVA Parks website ( and ed to registered bidders. It is the bidder s responsibility to be aware of all addenda and acknowledge receipt of addenda on the Form of Proposal. ATTACHMENT: Details of lighting mount above Sculptural Element Addendum #1 Page 8 of 8

IFB PAINTING AT HAYDON ELEMENTARY ADDENDUM #1

IFB PAINTING AT HAYDON ELEMENTARY ADDENDUM #1 IFB 18-14 PAINTING AT HAYDON ELEMENTARY ADDENDUM #1 IFB MODIFICATIONS: BONDING REQUIREMENTS: Due to the complexity of the scope of work, MCPS is requiring bonding for this bid. The following bonds are

More information

Specifications: Other: sign in sheet

Specifications: Other: sign in sheet To: All Vendors Bidding on The College of New Jersey Nursing Simulation Lab Fit-Out Project From: Roselle Horodeski Finance & Business Services Date: July 29, 2015 ADDENDUM NO. 1 ISSUE DATE: July 29, 2015

More information

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Answer: Qualification statement should be provided with the bid.

Answer: Qualification statement should be provided with the bid. Little Diversified Architectural Consulting, Inc. 5815 Westpark Drive Charlotte, North Carolina 28217 Phone: 704-525-6350 Fax: 704-561-8700 Lincoln County Probation Renovation 208 N. Government Street

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

B. Samples: For color, letter style, and graphic representation required for each identification material and device.

B. Samples: For color, letter style, and graphic representation required for each identification material and device. PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

More information

CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO

CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO. 18-04 ADDENDUM NO. ONE DATE: September 07, 27 CLIENT / PROJECT: Chabot-Las Positas CCD Campus Master

More information

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO PAGE PROJECT NO. 0-0 0 0 0 0 0 DATE: PROJECT: GATEWAY STEM ATHLETICE FIELD ALTERATIONS GATEWAY STEM HIGH SCHOOL - ST. LOUIS PUBLIC SCHOOLS 0 MCRTEE AVENUE ST. LOUIS, MISSOURI 0 TO BID DOCUMENTS DATED DECEMBER,

More information

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 013300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply

More information

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty HOT AISLE CONTAINMENT SYSTEM (HACS) REVISION #1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. B. C. Drawings and general provisions of the Contract, including General and Supplementary. Conditions apply to

More information

QUALITY SCREENPRINTED PRODUCTS SINCE 1949 CUSTOM PRINTING. Signs Decals Nameplates Vehicle Decals and Magnetics

QUALITY SCREENPRINTED PRODUCTS SINCE 1949 CUSTOM PRINTING. Signs Decals Nameplates Vehicle Decals and Magnetics QUALITY SCREENPRINTED PRODUCTS SINCE 1949 CUSTOM PRINTING Signs Decals Nameplates Vehicle Decals and Magnetics 530 East Jamie Avenue La Habra, Ca 90631 Customer Service Order Desk (800) 903-3385 Fax (800)

More information

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Record Documents. B. Operation and Maintenance Manuals. C. Warranties and bonds. 1.02 RELATED REQUIREMENTS SECTION 01 78 00 A. Section 01 30 00 - Administrative

More information

CITY OF RICHMOND Notice of Public Opening. Contract: Richmond Speed Skating Oval Interior/ Exterior Signage Package

CITY OF RICHMOND Notice of Public Opening. Contract: Richmond Speed Skating Oval Interior/ Exterior Signage Package CITY OF RICHMOND CITY OF RICHMOND Notice of Public Opening Contract T.3263 Contract: Richmond Speed Skating Interior/ Exterior Signage Package Tenders have been issued for the Richmond Speed Skating Interior/

More information

Attached is Addendum No. 2 to SEPTA Sealed Bid APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House.

Attached is Addendum No. 2 to SEPTA Sealed Bid APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House. Dear Sir/Madam: Attached is Addendum No. 2 to SEPTA Sealed Bid 17-00222-APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House. The Bid due date and time is changed from Thursday, Nov.

More information

ADDENDUM NO. 02 July 31, 2012

ADDENDUM NO. 02 July 31, 2012 Post Point Wastewater Treatment Plant Improvements Owner: Engineer: GC/CM: City of Bellingham Carollo Engineers Mortenson Construction ADDENDUM NO. 02 July 31, 2012 THIS ADDENDUM MUST BE ACKNOWLEDGED ON

More information

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014 FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services ADDENDUM #4 December 5, 2014 This Addendum is issued to provide answers to questions from potential bidders

More information

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General

More information

Solid Surface Countertops

Solid Surface Countertops USE THIS SECTION FOR COUNTERTOPS. USE SECTION 06 61 16 FOR OTHER SOLID SURFACING APPLICATIONS INCLUDING WALL CLADDING AND MISCELLANEOUS FABRICATIONS. GENERAL NOTES TO SPECIFIER: THIS SPECIFICATION SECTION

More information

ADDENDUM No. 4 Page 1 of 8 (includes attachment)

ADDENDUM No. 4 Page 1 of 8 (includes attachment) ADDENDUM No. 4 Page 1 of 8 (includes attachment) Date Issued: November 27, 2017 Project: TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

digital graphics page 1 of 1

digital graphics page 1 of 1 page 1 of 1 digital graphics creating visual excitement Quality graphics contribute significantly to the impact of your exhibit. Vivid colors and sharp images attract attention, build traffic, and communicate

More information

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS) ATTACHMENT 5, CONTRACT 13, ADDENDUM 3 2017 CDM Smith 14955-109447 SECTION 01725 PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS) PART 1 GENERAL 1.01 DESCRIPTION A. The Owner and Contractor shall utilize the

More information

SECTION IDENTIFICATION FOR FIRE SUPPRESSION PIPING AND EQUIPMENT

SECTION IDENTIFICATION FOR FIRE SUPPRESSION PIPING AND EQUIPMENT SECTION 21 05 53 IDENTIFICATION FOR FIRE SUPPRESSION PIPING AND EQUIPMENT Display hidden notes to specifier. (Don't know how? Click Here) Copyright 2015-2015 ARCAT, Inc. - All rights reserved PART 1 GENERAL

More information

Construction Phase Project Management and Documentation

Construction Phase Project Management and Documentation Construction Phase Project Management and Documentation Bill Mason CDM Smith Outline Design Bidding Construction Start-up & Closeout 2 DESIGN Design Preliminary Engineering Report Plans Specifications

More information

ADDENDUM #1. April 29, 2009

ADDENDUM #1. April 29, 2009 April 29, 2009 Re: HACC, Central Pennsylvania s Community College Midtown 1 CCTA Phase 2 Solicitation # 09-17 From: Eastern pcm, LLC Construction Manager HACC 212 Locust Street, Suite 604 Harrisburg, PA

More information

SECTION IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

SECTION IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT SECTION 220553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT Henderson Engineers, Inc. PART 1 - GENERAL REQUIREMENTS 1.1 SUMMARY A. Extent of Plumbing work to be identified as required by this Section

More information

BOOTH CONSTRUCTION & DISPLAY REQUIREMENTS Huntington Convention Center Cleveland, Ohio February 7 9, 2018

BOOTH CONSTRUCTION & DISPLAY REQUIREMENTS Huntington Convention Center Cleveland, Ohio February 7 9, 2018 Linear, Corner and Perimeter Booths Linear booths, also called in line booths, are generally arranged in a straight line and have neighboring exhibitors on their immediate right and left, leaving only

More information

SECTION PROJECT COORDINATION VIA BIM

SECTION PROJECT COORDINATION VIA BIM SECTION 01 31 13 PROJECT COORDINATION VIA BIM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

SECTION FASCIA INTERIOR FRAMED SIGNS & DIRECTORIES

SECTION FASCIA INTERIOR FRAMED SIGNS & DIRECTORIES Corporate Office: ASI Signage Innovations. 8181 Jetstar Drive Dallas, Texas 76053 (214) 352-9140 voice (214) 352-9741 facsimile (800) 274-7732 www.asisignage.com marketing@asisignage.com GUIDE SPECIFICATION

More information

MINUTES OF MEETING. The following Questions were asked and answers were provided accordingly:

MINUTES OF MEETING. The following Questions were asked and answers were provided accordingly: MINUTES OF MEETING Meeting Date : July 15, 2014 Place : Greenwood Shop Main Conference Room Contract Title : Supply of Reworked T1 Trip Switch Brackets Proposal No. : T31BG14139 Present : TTC - A. Mckay

More information

REQUEST FOR QUOTATION INVITATION

REQUEST FOR QUOTATION INVITATION REQUEST FOR QUOTATION INVITATION DATE: July 15, 2010 DPS: REQUIREMENT: SUBJECT: Patricia Farina DPS Contract Administrator Email: Patricia.Farina@cityofchicago.org Telephone: 312-744-7660 Silver Halide

More information

TG Glazing Design-Build

TG Glazing Design-Build TG08.1 - Glazing Design-Build Question No. 0040 0041 0042 0043 Submission Date Question 7.14.2011 Is it acceptable to use 304 stainless in lieu of 316 where the material will be painted per 09 97 15? 7.14.2011

More information

Design Documents for Wayfinding

Design Documents for Wayfinding Design Documents for Wayfinding 11-11-08 FOR FHWA SUBMITTAL 1 2 3 4 5 6 7 8 9 1st AVENUE WEST 3rd AVENUE WEST A B C D E F G H I 15th STREET WEST 14th STREET WEST Historic 2nd AVENUE WEST BARCARROTA BOULEVARD

More information

SECTION WOOD DOORS

SECTION WOOD DOORS SECTION 08211 WOOD DOORS Notice to Vendors: CANV prefers to purchase products that contain tropical wood only if they are certified according to the guidelines of the Forest Stewardship Council (FSC).

More information

MTJ Outdoor Baggage Claim

MTJ Outdoor Baggage Claim MTJ Outdoor Baggage Claim 915 S. Tenth St. Montrose, CO 8101 p: (970) 29-1980 f: (970) 797-6811 www.motleyarc.com Drawings and Dimensions 1. ATTENTION ALL USERS OF THESE DRAWINGS, GENERAL CONTRACTORS,

More information

SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5. February 25, 2013

SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5. February 25, 2013 SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5 February 25, 2013 Owner: Architect: Administrative Office of the Courts 2860 Gateway Oaks Drive, Suite 400 Sacramento,

More information

East Central College

East Central College SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

ADDENDUM TO RFQ/P DOCUMENTS PROJECT # ADDENDUM: #01

ADDENDUM TO RFQ/P DOCUMENTS PROJECT # ADDENDUM: #01 ADDENDUM TO RFQ/P DOCUMENTS PROJECT #14-013 ADDENDUM: #01 Solano Community College District SCCD REQUEST FOR QUALIFICATIONS/PROPOSAL Project: HVAC & EMS Efficiency Project Implementation Date: 03/28/2014

More information

SECTION MECHANICAL IDENTIFICATION

SECTION MECHANICAL IDENTIFICATION Buebtel/Perlcins Community Learning Center GPD - 2001271.15 SECTION 15075 MECHANICAL IDENTIFICATION PART 1- GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General

More information

Guide Specification Section Interior Suspended Sliding Glass Doors

Guide Specification Section Interior Suspended Sliding Glass Doors Guide Specification Section 08 32 13 Interior Suspended Sliding Glass Doors SECTION 08 32 13 The Sliding Door Company s product combines operable sliding glass doors with stationary glazed panels to create

More information

State College Area School District

State College Area School District State College Area School District The following is a guideline for project design submittals to the Facility Committee of the State College Area School District. During the design process the committee

More information

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS:

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS: INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS: 013300 SUBMITTAL PROCEDURES 018116 CONSTRUCTION WASTE MANAGEMENT DIVISION 2 EXISTING CONDITIONS: 023000 EARTHWORK

More information

12560 W. Cedar Drive Lakewood, CO Barry Himmelman President

12560 W. Cedar Drive Lakewood, CO Barry Himmelman President Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 16-BS-2260 ADDENDUM NUMBER FOUR January 8, 2016 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM

More information

ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION

ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION July 6, 2011 City of Miami Fire Station #13 ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION This Addendum is issued to modify the previously issued Bidding and Contractual Documents,

More information

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017.

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017. !!! Addendum EXP Project No: MTA Project No: WIND-17-01 Project: Windsor Hall Renovations October 12, 2017 Addendum No: 3 The following information supplements and/or supersedes the bid documents. This

More information

Creative and file preparation guidelines

Creative and file preparation guidelines Creative and file preparation guidelines KODAK NEXPRESS OPAQUE WHITE DRY INK Expand your options The ability to add white ink into a design offers both practical and creative benefits. White ink improves

More information

Solicitation No.: The enclosed addendum amends the proposal documents for the above referenced Project.

Solicitation No.: The enclosed addendum amends the proposal documents for the above referenced Project. Date: June 30, 2017 Project: Ketchikan Shipyard Transfer Carts Solicitation No.: 18002 Addendum No. One TO ALL PLANHOLDERS: The enclosed addendum amends the proposal documents for the above referenced

More information

RHODE ISLAND TURNPIKE AND BRIDGE AUTHORITY P.O. Box East Shore Road Jamestown, Rhode Island Invitation to Bid Request for Proposals

RHODE ISLAND TURNPIKE AND BRIDGE AUTHORITY P.O. Box East Shore Road Jamestown, Rhode Island Invitation to Bid Request for Proposals RHODE ISLAND TURNPIKE AND BRIDGE AUTHORITY P.O. Box 437 1 East Shore Road Jamestown, Rhode Island 02835-0437 Invitation to Bid Request for Proposals Mototrbo Digital VHF Radio System Solicitation Number:

More information

Bid #3990DB - Two Way Motorola Radio System District Wide Upgrade

Bid #3990DB - Two Way Motorola Radio System District Wide Upgrade LAKE COUNTY SCHOOLS Leading our Children to Success Procurement Services 29529 CR 561 Tavares FL 32778 (352) 253-6760 Fax: (352) 253-6761 http://lake.k12.fl.us Superintendent: School Board Members: Susan

More information

PLAN SUBMITTAL REQUIREMENTS

PLAN SUBMITTAL REQUIREMENTS DEPARTMENT OF ECONOMIC AND COMMUNITY DEVELOPMENT BUILDING DIVISION PLAN SUBMITTAL REQUIREMENTS Residential and Commercial Projects Welcome to the South San Francisco Building Division. We are providing

More information

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals. SECTION 01300 PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Requirements B. Submittal Procedures C. Specific Submittal Requirements D. Action on Submittals E. Repetitive Review 1.2 DESCRIPTION

More information

Signs and Murals - Definitions:

Signs and Murals - Definitions: Signs and Murals - Definitions: Sign: Any device, structure, placard, surface, or fabric using graphics, letters, symbols, pictures, or sculptured matter designed to convey information visually and exposed

More information

Guide Specification Section Interior Aluminum Doors and Frames

Guide Specification Section Interior Aluminum Doors and Frames Guide Specification Section 08 11 16 Interior Aluminum Doors and Frames SECTION 08 11 16 The Sliding Door Company s door and frame system includes glazed swing doors, sidelights, transoms, and fixed panels

More information

Solid Surface Fabrications

Solid Surface Fabrications USE THIS SECTION F WALL CLADDING AND MISCELLANEOUS FABRICATIONS OTHER THAN COUNTERTOPS. USE SECTION 06 61 18 F COUNTERTOPS. GENERAL NOTES TO SPECIFIER: THIS SPECIFICATION SECTION HAS BEEN PREPARED TO ASSIST

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS DIVISION 1 - GENERAL REQUIREMENTS SECTION 01300 - SUBMITTALS PART 1 - GENERAL 1.1 STIPULATIONS A. The section "Special Requirements" forms a part of this section by this reference thereto and shall have

More information

SECTION IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

SECTION IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT SECTION 23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

Answer: Only to ChurchWoods, LLC.

Answer: Only to ChurchWoods, LLC. ADDENDUM ADDENDUM NO.: 3 DATE: 06/27/16 PROJECT: CHW ChurchWoods PROJECT ADDRESS: 4130 Old Post Road Charlestown, RI TO: All Bidders of Record: This Addendum forms a part of and modifies the bidding requirements

More information

SECTION D BIM COORDINATION DRAWINGS - CONTRACTORS

SECTION D BIM COORDINATION DRAWINGS - CONTRACTORS END OF SECTION 01 30 00 SECTION 01 31 21-3D BIM COORDINATION DRAWINGS - CONTRACTORS PART 1 - GENERAL 1.01 RELATED DOCUMENTS Attention is directed to Bidding and Contract Requirements, and to Division 1,

More information

November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT

November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y18-703-CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT REVISED BID OPENING DATE: DECEMBER 5, 2017 This addendum is hereby incorporated

More information

September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO C ADDENDUM NO.

September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO C ADDENDUM NO. Department of Public Works Transportation Division September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO. 17-11090-C ADDENDUM NO. 3 Dear Bidder: The

More information

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

A. Action Submittals: Written and graphic information that requires Architect's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

Facility Services Subgroup Preface for Divisions 21` through 28

Facility Services Subgroup Preface for Divisions 21` through 28 Facility Services Subgroup Preface for Divisions 21` through 28 1.1 EXECUTIVE SUMMARY A. This document provides standards for the Consultants and Contractors producing mechanical and electrical design

More information

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards] SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA PART I - GENERAL 1.1 SUMMARY A. Operation and Maintenance Data shall be submitted in appropriately-sized binders, with dividers, and organized by each

More information

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017.

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017. June 15, 2017 GS#108-281 Greene Hall Renovations University of Southern Mississippi Hattiesburg, Mississippi 00.910 ADDENDUM NO 1. This Addendum contains 6 pages and 21 pages of attachments for a total

More information

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form. McKee and Associates Architecture and Interior Design Addendum No. THREE Date: 12.11.17 Project: A NEW BUILDING FOR THE GREATER LIMESTONE COUNTY CHAMBER OF COMMERCE ATHENS, ALABAMA A3.1 GENERAL PROJECT

More information

Bid No. B14-02 Building 100 HVAC Improvements

Bid No. B14-02 Building 100 HVAC Improvements Bid No. B14-02 Building 100 HVAC Improvements Addendum No. 1 This Addendum No. 1 sets forth modifications to portions of the bid and contract documents for the above-referenced work described as: Building

More information

RENOVATION OF THE FARMERS MARKET Reference Number:

RENOVATION OF THE FARMERS MARKET Reference Number: RENOVATION OF THE FARMERS MARKET Reference Number: 13-098 A D D E N D U M NO. 1 The following shall form part of the tender documents issued by the City of Guelph s Purchasing Department, June, 2013. NOTE:

More information

1.01 NOTICE TO BIDDERS

1.01 NOTICE TO BIDDERS ADDENDUM NO. 1 1.01 NOTICE TO BIDDERS A. Date: 15 March 2013 B. From: Bahr Vermeer and Haecker Architects, Ltd. C. To: Prospective Bidders. D. Project: Lexington Public Schools Lexington Middle School

More information

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202 Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 May 24, 2017 ADDENDUM NUMBER: Three (3) TITLE: Construction Services for Arlington

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA If project is not administered in PRISM, coordinate use of Exhibit 6 submittal schedule with this section. SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED

More information

(Full legal name of business submitting the offer)

(Full legal name of business submitting the offer) Procurement Services Addendum # 1 Proposal Request Date Printed Date Issued Procurement Officer Phone E-Mail Address 18-CMG-B-012 April 16, 2018 April 16, 2018 Raymond Jenkins 843-566-8826 raymond_jenkins@

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 230553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Provisions of the Contract and of the Contract Documents apply to this Section. 1.2 SUBMITTALS A.

More information

Exhibit Space & Booth Layout Guidelines

Exhibit Space & Booth Layout Guidelines Exhibit Space & Booth Layout Guidelines Exhibit Space & Booth Display Rules The following display rules have been designed using the IAEE (International Association of Exhibitions and Events) guidelines

More information

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS SECTION 01300 SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections,

More information

SECTION BULLET- RESISTANT DOORS

SECTION BULLET- RESISTANT DOORS 1 SECTION 08 3950 BULLET- RESISTANT DOORS PART 1- GENERAL 1.01 SUMMARY A. This Section Includes: 1. Bullet- resistant steel door and frame systems. 2. Door hardware for bullet- resistant steel door and

More information

SUBMITTING A PRESS-READY COVER For Paperback Books with Perfect Binding, Plastic Comb, and Plastic Coil Binding

SUBMITTING A PRESS-READY COVER For Paperback Books with Perfect Binding, Plastic Comb, and Plastic Coil Binding For Paperback Books with Perfect Binding, Plastic Comb, and Plastic Coil Binding Press-Ready Material We will only accept a digital file for a press-ready cover. The file must be print-ready with no typesetting

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01 33 23 - SHOP DRAWINGS, PRODUCT DATA, AND PART 1 - GENERAL 1.1 SUMMARY A. Products include, but are not limited to, the following construction submittals: 1. Shop Drawings. 2. Product Data. 3.

More information

Addendum No. 1 page 1

Addendum No. 1 page 1 Addendum No. 1 page 1 Project: 2018 Interior Renovations Jeffersonville Township Public Library Jeffersonville Facility Jeffersonville, Indiana Project No.: 1723.01 Date: April 12, 2018 This addendum is

More information

Excavating, Backfilling, and Compaction for Utilities Piping (Plumbing).

Excavating, Backfilling, and Compaction for Utilities Piping (Plumbing). SECTION 15047 - IDENTIFICATION PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Identification including necessary accessories indicated on Construction Documents and specified in this section or as required

More information

Storage and Installation of welded LL Hollow Metal Door Frames in Steel Studs

Storage and Installation of welded LL Hollow Metal Door Frames in Steel Studs Storage and Installation of welded LL Hollow Metal Door Frames in Steel Studs Introduction This guide specification is intended to stress the necessary precautions and requirements for receipt, storage,

More information

ADDENDUM 1 and 2 September 29, 2017 Request for Proposals: Wi-Fi and Wireless Backhaul Replacement

ADDENDUM 1 and 2 September 29, 2017 Request for Proposals: Wi-Fi and Wireless Backhaul Replacement Following are the questions submitted on or before September 29, 2017, in accordance with RFP specifications. Responses to questions, clarifications of material, or corrections are indicated in green after

More information

ALL PLAN HOLDERS NANCY MAGER, NPSR ARCHITECTS, INC. DATE: November 29, Lea County General Service Building PROJECT NO: ADDENDUM NO: 1

ALL PLAN HOLDERS NANCY MAGER, NPSR ARCHITECTS, INC. DATE: November 29, Lea County General Service Building PROJECT NO: ADDENDUM NO: 1 A R C H I T E C T S, I n c. TO: ALL PLAN HOLDERS FROM: NANCY MAGER, NPSR ARCHITECTS, INC. DATE: November 29, 2018 PROJECT: Lea County General Service Building PROJECT NO: 18-142 ADDENDUM NO: 1 PAGES: 10

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/06/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/06/2017 SECTION 23 0553 - MECHANICAL SYSTEMS IDENTIFICATION GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION MECHANICAL IDENTIFICATION

SECTION MECHANICAL IDENTIFICATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions Specification Sections, apply to this Section. B. Related Sections:

More information

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER Approval Amendment Record Approval Date Version Description 03/05/2017 1 Initial issue PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 13 Table of Contents 1. Purpose...

More information

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

A. Action Submittals: Written and graphic information that requires Engineer's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SCI-FAB Product Specifications. Casework Section 1. Part 1 General

SCI-FAB Product Specifications. Casework Section 1. Part 1 General SCI-FAB Product Specifications Casework Section 1 Part 1 General 1.1 SCOPE OF WORK Includes all factory fabricated stainless steel casework as required by the project drawings. 1.2 TYPICAL INCLUSIONS A.

More information

Engineered construction creates a natural V shape in the lanyard which helps prevent ID card from twisting and turning when worn around the neck.

Engineered construction creates a natural V shape in the lanyard which helps prevent ID card from twisting and turning when worn around the neck. Engineered construction creates a natural V shape in the lanyard which helps prevent ID card from twisting and turning when worn around the neck. Standard Styles Cordlocks... allow the wearer to adjust

More information

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document.

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document. Enroll in GMFI Program Image Consultation Design Intent Document Preparation Preliminary Drawings Final Drawings Design Intent Document You are here. 1-2 Construction Documents Services performed by dealer

More information

BUILDING PLANS. BUILDING INSPECTIONS DEPARTMENT

BUILDING PLANS. BUILDING INSPECTIONS DEPARTMENT BUILDING PLANS BUILDING INSPECTIONS DEPARTMENT 507-537-6773 www.ci.marshall.mn.us This handout is intended only as a guide to the subject matter covered herein and is based in part on the 2015 Minnesota

More information

READING ARCHITECTURAL PLANS

READING ARCHITECTURAL PLANS READING ARCHITECTURAL PLANS ARCHITECTURAL DRAWINGS FOR A HOUSE Architectural drawings contain information about the size, shape, and location of all parts of the house ARCHITECTURAL DRAWINGS FOR A HOUSE

More information

Addendum to Description of Services for Building and Planning, Digital Design. The Association of of Consulting Engineers

Addendum to Description of Services for Building and Planning, Digital Design. The Association of of Consulting Engineers Addendum to Description of Services for Building and Planning, 2012 8.4 Digital Design 2016 The Association of of Consulting Engineers FRI and DANSKE ARK Addendum to Description of Services for Building

More information

ADDENDUM No. 1. ITB No Northside Interceptor Condition Assessment. Due: February 1, 2018 at 10:00 A.M. (Local Time)

ADDENDUM No. 1. ITB No Northside Interceptor Condition Assessment. Due: February 1, 2018 at 10:00 A.M. (Local Time) ADDENDUM No. 1 ITB No. 4521 Northside Interceptor Condition Assessment Due: February 1, 2018 at 10:00 A.M. (Local Time) The following changes, additions, and/or deletions shall be made to the Invitation

More information

Product Guide Specification

Product Guide Specification Shield Casework February 2014 3421 Merriam Lane Overland Park, Kansas 66203 Phone 913-744-2183 Fax 913-384-3477 Website www.shieldcasework.com E-mail info@shieldcasework.com Product Guide Specification

More information