Construction Phase Project Management and Documentation

Size: px
Start display at page:

Download "Construction Phase Project Management and Documentation"

Transcription

1 Construction Phase Project Management and Documentation Bill Mason CDM Smith

2 Outline Design Bidding Construction Start-up & Closeout 2

3 DESIGN

4 Design Preliminary Engineering Report Plans Specifications 4

5 Design Preliminary Engineering Report Serves as basis for design Explains purpose of project Defines scope of work Plans Specifications 5

6 Design Preliminary Engineering Report Plans Pictorial representation of project Schematics Maps Plan and Profile Views Standard or Project Specific Details Broken down by structure or discipline Specifications 6

7 Design Preliminary Engineering Report Plans Specifications Provides detailed requirements of materials, equipment, installation, and testing Division 0 Often Termed front end Division 1 General Requirements Divisions 2 through 17 Technical Requirements 7

8 Section RAS Pumps Section Aluminum Grating Section Cast-In-Place Concrete Section Ductile Iron Pipe

9 BIDDING

10 Bidding Prequalification Plan Distribution Pre-Bid Meeting Bid Form Bid Opening Award 10

11 Bidding Prequalification Using an impartial system to identify suitable contractors Plan Distribution Pre-Bid Meeting Bid Form Bid Opening Award 11

12 Bidding Prequalification Plan Distribution Distribution of plans and specifications to plan rooms Notifying potential contractors and subcontractors of project Pre-Bid Meeting Bid Form Bid Opening Award 12

13 Bidding Prequalification Plan Distribution Pre-Bid Meeting Meeting with interested contractors, subcontractors, and suppliers Explain scope of project and answer questions Bid Form Bid Opening Award 13

14 Bidding Prequalification Plan Distribution Pre-Bid Meeting Bid Form Lump Sum Unit Price Items Allowances & Alternates Bid Opening Award 14

15 Bidding Prequalification Plan Distribution Pre-Bid Meeting Bid Form Bid Opening Minimum of three bids required to open Additional documentation required (i.e. DBE participation) Award 15

16 Bidding Prequalification Plan Distribution Pre-Bid Meeting Bid Form Bid Opening Award Typically given to lower, responsible bidder 16

17 CONSTRUCTION

18 Construction Roles of Stakeholders Meetings Shop Drawings and RFIs Schedule Financials 18

19 Construction OWNER CONTRACTOR ENGINEER 19

20 Construction OWNER Dictating Scope of Project Setting up Financing Compliance with Local, State, and Federal Regulations Operations & Maintenance of Facility once Complete 20

21 Construction ENGINEER Inspection of Construction for Compliance with Construction Documents Coordination of Independent Testing Labs Interpretation of Construction Documents Review of Contractors Schedule and Payments Assist in Facility Start-up 21

22 Construction CONTRACTOR Construction of Project Hiring and Management of Subcontractors Procurement of Equipment and Materials Maintaining Schedule and Budget Start-up and Testing of Equipment 22

23 Construction Roles of Stakeholders State and Local Agencies (Funding Agencies) Independent Testing Labs Equipment Suppliers and Representatives Meetings Shop Drawings and RFIs Schedule Financials 23

24 Construction Roles of Stakeholders Meetings Pre-Construction Meeting Monthly Progress Coordination Meetings Start-up Meetings Shop Drawings and RFIs Schedule Financials 24

25 Construction Roles of Stakeholders Meetings Pre-Construction Meeting Review Project Scope Establish Project Proceedures Shop Drawings and RFIs Schedule Financials 25

26 Construction Roles of Stakeholders Meetings Monthly Progress Review Work Performed (Past 30 days/next 30 days) Discuss Coordination Items Review Schedule and Change Items Other Items as Necessary Shop Drawings and RFIs Schedule Financials 26

27 Construction Roles of Stakeholders Meetings Coordination Meetings Usually Held on Weekly Basis Discuss How Construction Will Impact Plant/System Operations Shop Drawings and RFIs Schedule Financials 27

28 Construction Roles of Stakeholders Meetings Start-up Meetings Review Details of Bringing New Equipment Online Discuss Testing and Training Requirements Shop Drawings and RFIs Schedule Financials 28

29 Construction Roles of Stakeholders Meetings Shop Drawings and RFIs Link between Design and Construction Details what the Contractor will Build/Install Ensures Compliance with Specifications and Drawings Prepared by Contractor and Submitted to Engineer Schedule Financials 29

30 Submittals vary in shape, size, and color Shop Drawings Working Drawings Product Data Samples Certificates Operations & Maintenance (O&M) Manuals

31 Shop Drawing Submittals Specific to a piece of equipment or building material Custom-prepared by manufacturer or vendor Nuts & bolts -oriented Fabrication drawings Erection/installation drawings Setting/mounting diagrams Actual shop manufacturing instructions Wiring diagrams Factory test reports Performance curves Project reference data

32 Working Drawing Submittals Specific to an area or process, or to a procedure for executing the work in accordance with the contract documents Installation drawings for piping Electrical conduit or duct bank layouts Equipment anchoring & support

33 Product Data Submittals Standard, prepared data from manufacturers Often termed catalog cuts Generic information-related Manufacturer s specifications Photographs Quality control procedures Standard warranties Available options and accessories

34 Sample Submittals Physical examples of the work Desired by the Engineer for visual verification of materials of construction, method of construction, color selection, or size Samples may range from pipe coupons to storage tank color sets

35 Certification Submittals Documentation of compliance with specifications or standards Confirmation proper equipment and/or system installation Validation of completed testing/pre-commissioning Examples include: Certificate of Installation, Certificate of Manufacture, Certificate of Compliance

36 Submittal Requirements Usually identified in Specification Section Addresses Contractor Responsibilities for: Certifying the accuracy Tracking (numbering the submittal) Number of submittals Content of submittals Point of contact and mailing address for delivery of submittals Addresses Engineer Responsibilities for: Time of review Disposition of review

37 Submittal Reviews Review and approval by the Engineer does not permit any departure from the Contract (Executed) Documents Review and approval by the Engineer does not relieve the Contractor of responsibility for details, dimensions, materials, etc. Review and approval by the Engineer does not authorize changes to the Contract (Executed) Documents, only Change Orders do

38 Recommended Submittal Handling Subcontractor Owner Contractor RPR Manufacturer/ Vendor Engineer

39 Submittal Tracking (Log) Construction Project Administration, 7 th Edition, Edward Fisk, copyright 2003, Prentice Hall

40 Construction Roles of Stakeholders Meetings Shop Drawings and RFIs Schedule Details Sequence and Duration of Work Items Financials 40

41 Construction Roles of Stakeholders Meetings Shop Drawings and RFIs Schedule Financials Applications for Payment Change Orders Work Change Directives 41

42 START UP & CLOSEOUT

43 Start Up and Closeout Manufacturer Checkout Equipment Testing Operator Training O&M Manuals Spare Parts Warranties Record Drawings Punchlists 43

44 Questions?

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide submittals in accordance with the General Conditions as modified by the Supplementary Conditions,

More information

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

A. Action Submittals: Written and graphic information that requires Engineer's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.

More information

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals. SECTION 01300 PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Requirements B. Submittal Procedures C. Specific Submittal Requirements D. Action on Submittals E. Repetitive Review 1.2 DESCRIPTION

More information

SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Progress meetings. D. Construction progress schedule. E. Coordination drawings. SECTION 013000

More information

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Record Documents. B. Operation and Maintenance Manuals. C. Warranties and bonds. 1.02 RELATED REQUIREMENTS SECTION 01 78 00 A. Section 01 30 00 - Administrative

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS PART 1 GENERAL 1.01 REQUIREMENTS INCLUDED SECTION 01 20 00 PROJECT MEETINGS A. Construction Manager shall schedule and administer pre-construction meeting, periodic progress meetings, and specially called

More information

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners

More information

SECTION PROJECT MANAGEMENT AND COORDINATION

SECTION PROJECT MANAGEMENT AND COORDINATION SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS) ATTACHMENT 5, CONTRACT 13, ADDENDUM 3 2017 CDM Smith 14955-109447 SECTION 01725 PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS) PART 1 GENERAL 1.01 DESCRIPTION A. The Owner and Contractor shall utilize the

More information

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES STANDARD SPECIFICATIONS SECTION 01330 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 DESCRIPTION A. Section includes general requirements and procedures related to preparation and transmittal of Submittals to

More information

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

A. Action Submittals: Written and graphic information that requires Architect's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

CONVEYANCE PIPELINE AND PUMP STATION

CONVEYANCE PIPELINE AND PUMP STATION SCOPE OF WORK CONVEYANCE PIPELINE AND PUMP STATION The purpose of this scope of work is to provide engineering services to revise and complete the design of the RUWAP pipeline and 5th Avenue Pump Station

More information

East Central College

East Central College SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01 33 00 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes. 1. Submittal procedures. 2. Product data. 3. Shop drawings. 4. Samples. 5. Design data. 6. Test reports. 7. Certificates.

More information

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS SECTION 01300 SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections,

More information

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer Construction Documents 1.1 to 1.6 Create Submittal Log 1.1 Construction Docs Focus of this process is to transmit submittal

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 013300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply

More information

Section Meetings Section Material and Equipment. None Required

Section Meetings Section Material and Equipment. None Required January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental

More information

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General

More information

This specification describes the general requirements for Engineering Services provided to Vale.

This specification describes the general requirements for Engineering Services provided to Vale. 1/9 1.0 PURPOSE This specification describes the general requirements for Engineering Services provided to Vale. 2.0 GENERAL For the purposes of this document, the Engineering Consultant shall be referred

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.1 DESCRIPTION A. This specification defines the general requirements and procedures for submittals. A submittal is information

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES SECTION 01340 SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED A. Contractor shall submit to the Architect/Engineer for review and exception, if any, such working

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01334 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Submit to the ENGINEER for review, such working drawings, shop drawings, test reports and data on materials and equipment

More information

SECTION SUBMITTALS

SECTION SUBMITTALS SECTION 01300 SUBMITTALS PART 1- GENERAL 1.01 SCOPE OF WORK A. This Section specifies the general methods and requirements of submissions applicable to Shop Drawings, Product Data, Samples and Operations

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01 33 23 - SHOP DRAWINGS, PRODUCT DATA, AND PART 1 - GENERAL 1.1 SUMMARY A. Products include, but are not limited to, the following construction submittals: 1. Shop Drawings. 2. Product Data. 3.

More information

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

SECTION OPERATION AND MAINTENANCE DATA

SECTION OPERATION AND MAINTENANCE DATA SECTION 01787 OPERATION AND MAINTENANCE DATA PART 1 GENERAL 1.01 SUMMARY A. Compile product data and related information appropriate for OWNER's maintenance and operation of products furnished under Contract.

More information

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA SECTION 01 78 00 CLOSE-OUT SUBMITTALS PART 1 - GENERAL 1.1 GUARANTEES A. Compile and submit guarantees, bonds, and service and maintenance contracts specified in the individual B. Guarantees from Subcontractors

More information

A. Section includes administrative and procedural requirements for project record documents, including the following:

A. Section includes administrative and procedural requirements for project record documents, including the following: SECTION 017839 - PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01

More information

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal City of Winnipeg Brady Road Landfill Site Section 01300 New Entrance and Scale Facility Page 1 of 4 SUBMITTALS 1. SHOP DRAWINGS 1.1 General.1 Arrange for the preparation of clearly identified Shop Drawings

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA If project is not administered in PRISM, coordinate use of Exhibit 6 submittal schedule with this section. SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED

More information

Answer: Qualification statement should be provided with the bid.

Answer: Qualification statement should be provided with the bid. Little Diversified Architectural Consulting, Inc. 5815 Westpark Drive Charlotte, North Carolina 28217 Phone: 704-525-6350 Fax: 704-561-8700 Lincoln County Probation Renovation 208 N. Government Street

More information

Vanderbilt University Standard Specification Revised 2/6/08

Vanderbilt University Standard Specification Revised 2/6/08 SECTION 01 78 23 OPERATION AND MAINTENANCE DATA PART 1 GENERAL 1.01 RELATED SECTIONS A. Section 01 77 00 Closeout Procedures B. Section 01 78 39 Project Record Documents 1.02 SUMMARY A. This section provides

More information

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION 01 3100 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

SUBMITTAL PROCEDURES

SUBMITTAL PROCEDURES SUBMITTAL PROCEDURES PART 1 GENERAL The ASPA Project Engineer (APE) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective

More information

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty HOT AISLE CONTAINMENT SYSTEM (HACS) REVISION #1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. B. C. Drawings and general provisions of the Contract, including General and Supplementary. Conditions apply to

More information

Heat Exchanger Construction Checklist

Heat Exchanger Construction Checklist Heat Exchanger Checklist Project: Pump tag: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist

More information

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. SECTION 01300 - PART 1 - GENERAL 1.1 GENERAL A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. B. Unless otherwise noted, within 14 days after the date of commencement as stated in

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS DIVISION 1 - GENERAL REQUIREMENTS SECTION 01300 - SUBMITTALS PART 1 - GENERAL 1.1 STIPULATIONS A. The section "Special Requirements" forms a part of this section by this reference thereto and shall have

More information

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.: WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO-00111 Job No.: 16-7003 To Respondent of Record: ADDENDUM 2 July 5, 2017 This addendum, applicable to work referenced

More information

Bidders for the Oak Brook Park District Family Locker Room Renovation

Bidders for the Oak Brook Park District Family Locker Room Renovation BIDDING & CONTRACT REQUIREMENTS Document 00901 Addendum No. 1 Date: June 1, 2017 From: To: Wight Construction Services, Inc. 2500 Frontage Road Darien, IL 60561 Bidders for the Oak Brook Park District

More information

Architectural Design Process

Architectural Design Process Architectural Design Process Custom Residential A. Schematic Design Phase Pre-Design Meeting Site Analysis Site Survey Conceptual Design & Project Scope Design Program Guideline Project Team Formation

More information

TABLE OF CONTENTS. 1.0 Scope. 2.0 References. 3.0 Definitions. 4.0 Submission and Design Requirements. 5.0 Materials 5.1 General 5.

TABLE OF CONTENTS. 1.0 Scope. 2.0 References. 3.0 Definitions. 4.0 Submission and Design Requirements. 5.0 Materials 5.1 General 5. 1.0 Scope 2.0 References 3.0 Definitions 4.0 Submission and Design Requirements 5.0 Materials 5.1 General 5.2 Marking 6.0 Equipment 7.0 Production 7.1 Steel Octagonal Poles 7.2 Base Plate 7.3 Top Cap 7.4

More information

SECTION III SUBMITTALS AND APPROVALS

SECTION III SUBMITTALS AND APPROVALS SECTION III SUBMITTALS AND APPROVALS In order to expedite the approval process of new water distribution system and sanitary sewer collection system extensions, the Hilton Head No. 1 Public Service District

More information

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS:

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS: INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS: 013300 SUBMITTAL PROCEDURES 018116 CONSTRUCTION WASTE MANAGEMENT DIVISION 2 EXISTING CONDITIONS: 023000 EARTHWORK

More information

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Shop drawings, manufacturer's catalog cuts, product data, samples, and attached Shop Drawing/ Catalog

More information

SPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work

SPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work 2004 Specifications CSJ 0110-04-166 SPECIAL PROVISION 000--363 Description of Project, Scope of Contract and Sequence of Work 1. General. The work to be performed on this project consists of furnishing,

More information

SECTION PROJECT COORDINATION VIA BIM

SECTION PROJECT COORDINATION VIA BIM SECTION 01 31 13 PROJECT COORDINATION VIA BIM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

SUBMITTAL LIST Note: See tab below for Samples and Instructions. Attach to end of Specification Section when complete.

SUBMITTAL LIST Note: See tab below for Samples and Instructions. Attach to end of Specification Section when complete. REQUIREMENTS (indicate with an "") 011100 1.4 Detailed Construction Phasing Plan 011100 1.4 Sub-Surface Utility Location Plan 013100 1.3 Letter Designating Project Superintendent 013100 1.3 Construction

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018 SECTION 01 7839 - PROJECT RECORD DOCUMENTS GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

01100 SUMMARY OF WORK

01100 SUMMARY OF WORK Lambert..STL Airport Uve Animal Facility- World Trade Center- St. Louis, Missouri 01100 SUMMARY OF WORK PART 1.. DESCRIPTION a. General: The work to be completed consists of fabrication, deliver, and installation

More information

PMA ONLINE TRAINING. Commercial Drawings. One Hour Continuing Education

PMA ONLINE TRAINING. Commercial Drawings. One Hour Continuing Education PMA ONLINE TRAINING Commercial Drawings One Hour Continuing Education PMA training disclaimer The information provided in this document is intended for use as a guideline and is not intended as, nor does

More information

Jacksonville District Master

Jacksonville District Master -01 33 00 (April 2006) From USACE / NAVFAC / AFCESA UFGS UNIFIED FACILITIES GUIDE SPECIFICATIONS Revised thoughout - changes not indicated by CHG tags SECTION TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS

More information

CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES

CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES FINAL DESIGN, BID PHASE, AND CONSTRUCTION SERVICES BACKGROUND ARCADIS U.S., Inc. (ARCADIS)

More information

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum SECTION 013201 - SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum Pay Unit price breakdown) shall be developed and ultimately

More information

This specification describes the minimum technical requirements for drawings, as applicable to all disciplines.

This specification describes the minimum technical requirements for drawings, as applicable to all disciplines. SPEC-0800 1/5 1.0 PURPOSE This specification describes the minimum technical requirements for drawings, as applicable to all disciplines. 2.0 VALE DRAWING TYPE DEFINITIONS Engineering Drawings Engineering

More information

SECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section

SECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section 02760-1 of 5 SECTION 02760 STEEL LIGHTING STANDARDS 02760.01 GENERAL A. Description Steel lighting standards shall include, but not necessarily be limited to, furnishing and installing steel lighting poles,

More information

Facility Services Subgroup Preface for Divisions 21` through 28

Facility Services Subgroup Preface for Divisions 21` through 28 Facility Services Subgroup Preface for Divisions 21` through 28 1.1 EXECUTIVE SUMMARY A. This document provides standards for the Consultants and Contractors producing mechanical and electrical design

More information

Work Type Definition and Submittal Requirements Work Type: Subsurface Utility Engineering (SUE)

Work Type Definition and Submittal Requirements Work Type: Subsurface Utility Engineering (SUE) MUST be qualified under Minnesota Department of Transportation Prequalification Program - Work Type 15.1 Subsurface Utility Engineering The first section, Work Type Definition, provides a detailed explanation

More information

DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS

DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS PART 1 GENERAL 1.01 Scope of Work A. Provide material, accessories, tools, equipment and labor as required for the complete fabrication

More information

DWG, Inc. Coastal Carolina University State Project No. Consulting Engineers HTC Arena Lighting H17-N112-JM

DWG, Inc. Coastal Carolina University State Project No. Consulting Engineers HTC Arena Lighting H17-N112-JM SECTION 011000 SUMMARY PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Work covered by the Contract Documents. 2. Work under other contracts. 3. Use of premises. 4. Specification

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES DIVISION 1 GENERAL REQUIREMENTS SECTION 01 33 00 PART 1 - GENERAL 1.1 SUMMARY A. This section includes administrative and procedural requirements for submittals required for performance of the work, including

More information

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014) DRAFT UFGS- 01 XX XX (FEB 2014) ------------------------ Drafting Activity: USACE UNIFIED FACILITIES GUIDE SPECIFICATION SECTION TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION 01 XX XX (FEB

More information

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards] SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA PART I - GENERAL 1.1 SUMMARY A. Operation and Maintenance Data shall be submitted in appropriately-sized binders, with dividers, and organized by each

More information

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030 ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO. 2018-008-COM.00030 To: Prospective Bidders of Record Date: January 8, 2019 The following changes, additions, revisions, and/or deletions

More information

Scope of Services. Project management tasks are estimated based upon anticipated project duration of 52 weeks.

Scope of Services. Project management tasks are estimated based upon anticipated project duration of 52 weeks. Scope of Services Project Understanding The City of Sparks (City) has also requested the HDR Engineering, Inc. (HDR) provided limited shop drawing review and periodic observation during construction and

More information

i. Shoring layout. ii. Shoring sections and details (including anchor details, if required).

i. Shoring layout. ii. Shoring sections and details (including anchor details, if required). 1. Design NOC 1.1 Shoring Design NOC: b. Required Drawings (DLTM COORDINATES) i. Shoring layout. ii. Shoring sections and details (including anchor details, if required). 1. Shoring Works NOC should be

More information

GE018: Interpretation of Engineering Drawings

GE018: Interpretation of Engineering Drawings GE018: Interpretation of Engineering Drawings GE018 Rev.001 CMCT COURSE OUTLINE Page 1 of 5 Training Description: This course, developed out of best practice recommendations and extensive industry experience,

More information

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents. SECTION 01 3000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Submittals for review, information, and project closeout. D. Submittal procedures.

More information

Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7)

Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7) Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Final Revision 2 AACE International Recommended Practice PS-24 Tracking

More information

Bid No. B14-02 Building 100 HVAC Improvements

Bid No. B14-02 Building 100 HVAC Improvements Bid No. B14-02 Building 100 HVAC Improvements Addendum No. 1 This Addendum No. 1 sets forth modifications to portions of the bid and contract documents for the above-referenced work described as: Building

More information

Booster Pumping Station 115 Booster Pump Procurement

Booster Pumping Station 115 Booster Pump Procurement Madison Water Utility Tom Heikkinen General Manager 119 E. Olin Avenue Alan L. Larson PE, BCEE Principal Engineer Madison, Wisconsin 53713 Telephone: 608 266-4653 FAX: 608 266-4426 email: allarson@cityofmadison.com

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-11 47 00 (August 2017) ----------------------------- Preparing Activity: USACE Superseding UFGS-11 47 00 (February 2009) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

Proposal PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y. Baker, MT P.O. Box 846

Proposal PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y. Baker, MT P.O. Box 846 PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y Proposal P.O. Box 846 Baker, MT 59313 P R E C A S T R E I N F O R C E D C O N C R E T E B O X C U L V E R T F O R W E S T M O

More information

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017 NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP 697-16-016 July 28, 2017 Reference is made to the Request for Proposal (RFP) to Service Providers for Nevada Shared Radio Replacement Project, upon

More information

Efficient Tactics of Project Management

Efficient Tactics of Project Management Ohio Structure Steel & Architectural Metals Association Efficient Tactics of Project Management Friday, June 23, 2017 Mark V. Holland, P.E. Chief Engineer Paxton & Veirling Steel Co. How to get paid. This

More information

September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO C ADDENDUM NO.

September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO C ADDENDUM NO. Department of Public Works Transportation Division September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO. 17-11090-C ADDENDUM NO. 3 Dear Bidder: The

More information

SECTION METAL FABRICATIONS

SECTION METAL FABRICATIONS SECTION 05100 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for metal fabrications, including minimum requirements for fabricator, and galvanizing. 1.02 REFERENCE STANDARDS A. ASTM

More information

James W. Moore, PE / Brandon D. Enevold, PE / Kjersten E. Kuhta, PE Dylan J. Cunningham, PE / Jacob L. Deering, PE / Joel R.

James W. Moore, PE / Brandon D. Enevold, PE / Kjersten E. Kuhta, PE Dylan J. Cunningham, PE / Jacob L. Deering, PE / Joel R. ADDENDUM NO. 1 October 21, 2016 PROJECT: CWU CAMPUS GENERATOR PROJECT #: CWU Project No. 12238-02 The additions, clarifications and corrections contained herein shall be made to the Project Manual, Drawings

More information

SECTION CONSTRUCTION PHOTOGRAPHS AND VIDEO RECORDING

SECTION CONSTRUCTION PHOTOGRAPHS AND VIDEO RECORDING SECTION 01321 CONSTRUCTION PHOTOGRAPHS AND VIDEO RECORDING PART 1 GENERAL 1.01 SUMMARY A. Employ a competent photographer to take construction record photographs for preconstruction conditions, periodically

More information

BIM Introduction. Building Information Management Definitions, Applications and general information. Betty Bezos

BIM Introduction. Building Information Management Definitions, Applications and general information. Betty Bezos BIM Introduction Building Information Management Definitions, Applications and general information Betty Bezos betty@bezos.com 9/1/2017 1 9/1/2017 2 Innovations in BIM 3D Design: 3D visualizations allow

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS *************************************************************************** SECTION

UNIFIED FACILITIES GUIDE SPECIFICATIONS *************************************************************************** SECTION USACE / NAVFAC / AFCEC / NASA UFGS-01 33 00.05 20 (May 2014) Change 1-09/15 Change 2-12/15 Change 3-09/16 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 33 00.05 20

More information

BUILDING PLANS. BUILDING INSPECTIONS DEPARTMENT

BUILDING PLANS. BUILDING INSPECTIONS DEPARTMENT BUILDING PLANS BUILDING INSPECTIONS DEPARTMENT 507-537-6773 www.ci.marshall.mn.us This handout is intended only as a guide to the subject matter covered herein and is based in part on the 2015 Minnesota

More information

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS For EQUIPMENT FOR THE 2014 CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT WASTEWATER TREATMENT PLANT IMPROVEMENT PROJECT:

More information

CITY OF TOMBALL. Section FIRE HYDRANTS 1.01 SECTION INCLUDES. A. Fire hydrants. B. Adjustment of fire hydrants and gate valves.

CITY OF TOMBALL. Section FIRE HYDRANTS 1.01 SECTION INCLUDES. A. Fire hydrants. B. Adjustment of fire hydrants and gate valves. Section 02520 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Fire hydrants. B. Adjustment of fire hydrants and gate valves. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment is on a unit price basis

More information

SECTION BASIC MATERIALS AND METHODS. A. The requirements of the General Conditions and Supplementary Conditions apply to all Work herein.

SECTION BASIC MATERIALS AND METHODS. A. The requirements of the General Conditions and Supplementary Conditions apply to all Work herein. SECTION 230500 BASIC MATERIALS AND METHODS PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. The requirements of the General Conditions and Supplementary Conditions apply to all Work herein. B. The Contract

More information

May 15, 2012 Hugh Anderson Legal Counsel to the Engineers Joint Contract Documents Committee

May 15, 2012 Hugh Anderson Legal Counsel to the Engineers Joint Contract Documents Committee Shop Drawings: Contractual and Legal Issues May 15, 2012 Hugh Anderson Legal Counsel to the Engineers Joint Contract Documents Committee Shop Drawings Defined CSI definition: Drawings that illustrate a

More information

Working Drawing Manual

Working Drawing Manual Working Drawing Manual 2012 Table of Contents Section 1 Working Drawing Types... 1 1.1 General... 1 Section 2 Processing Steps... 1 2.1 Project Manager... 1 2.2 Engineering Document Unit... 2 2.3 Contractor...

More information

Technical Specifications: Supply of Seamless Grade TP304L Pipe and Grade WP304L Pipework Fittings to the ITER Organization (IO).

Technical Specifications: Supply of Seamless Grade TP304L Pipe and Grade WP304L Pipework Fittings to the ITER Organization (IO). IDM UID: R22L3M ver 1.4 Technical Specifications: Supply of Seamless Grade TP304L Pipe and Grade WP304L Pipework Fittings to the ITER Organization (IO). Contents 1 Terms and Acronyms... 3 2 Background...

More information

WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) CITY OF CARTERSVILLE

WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) CITY OF CARTERSVILLE WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) ADDENDUM NO.1 ADDENDUM NO. 1 DATE: OCTOBER 16, 2018 To BID, CONTRACT, BONDS AND SPECIFICATIONS FOR CONSTRUCTING WATER TREATMENT PLANT FILTERS REHABILITATION

More information

Pledge of Allegiance Staff Introduction Bid Package Submittal Sign-In Sheet and Project Scope Q&A Process Anticipated Date Sequence General Project

Pledge of Allegiance Staff Introduction Bid Package Submittal Sign-In Sheet and Project Scope Q&A Process Anticipated Date Sequence General Project Pledge of Allegiance Staff Introduction Bid Package Submittal Sign-In Sheet and Project Scope Q&A Process Anticipated Date Sequence General Project Overview Procedures, Protocol, and General Contract Requirements

More information