1 SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section DESCRIPTION OF REQUIREMENTS A. Types of Submittals: Submittal requirements specified in this Section include shop drawings, product data, samples, and miscellaneous workrelated submittals. Administrative submittals, project close-out, and record document submittals are specified elsewhere in Division 1. Specific requirements for work-related submittals (work of this Section) are specified in applicable sections for each unit of work. Submittal requirements are generally limited to "Product Confirmation" described hereafter, unless shop drawings, product data, samples, or other miscellaneous work-related submittal is specifically specified. Where specified, the following definitions define requirements: 1. Shop Drawings: Provide newly-prepared technical data specifically for this project, including drawings, diagrams, performance curves, data sheets, schedules, templates, patterns, reports, calculations, instructions, measurements, and similar information not in standard printed form, for general application to several projects. Do not reproduce Contract Documents as basis of shop drawings. 2. Product Data: Provide standard printed information on materials, products and systems; not specially prepared for this project, other than the designation, if selections from among available choices printed therein. Include manufacturer's standard printed recommendations for application and use, compliance with standards, applications of labels and seals, maintenance information, and special coordination requirements for installation.
2 3. Samples: Provide units identical with final condition of proposed materials or products for the work. Include "range" of samples (not less than 3 units) where unavoidable variations must be expected, and describe or identify variations between units of each set. Provide full set of optional samples where Architect's selection is required. Prepare samples to match Architects sample where so indicated. Include information with each sample to show generic description, source of product name and manufacturer, limitations, and compliance with standards. Samples are submitted for review and confirmation of color, pattern, texture, and "kind" by Architect. Color selections will not be made by the Architect until all samples requiring color selection have been received. Architect will not "test" samples (except as otherwise indicated ) for compliance with other requirements which are; therefore, the exclusive responsibility of the Contractor. Mock-ups are a special form of samples which are too large or otherwise inconvenient, for handling in specified manner, for transmittal of sample submittals. 4. Miscellaneous submittals related directly to the work (nonadministrative) include warranties, maintenance agreements, workmanship bonds, project photographs, survey data and reports, physical work records, quality testing and certifying reports, copies of industry standards, record drawings, field measurement data, operating and maintenance materials, overrun stock, and similar information, devices and materials applicable to the work, and not processed as shop drawings, product data, or samples. B. Intent: The Contract Documents define materials, products, fabrications and installations required; no departure from requirements of Contract Documents is permitted. The Architect's review of certain submittals is intended to be a preview of Contractor's proposed solution to work, which is specified by performance, rather than prescriptive terms, for which Contractor is allowed a choice of solutions among available options. The Architect will review and take appropriate action on shop drawings, product data, samples, and other submittals required by the Contract Documents. Such review shall be only for general conformance with the design concept and general compliance with the information given in the Contract Documents. It shall not include review of quantities, dimensions, weights or gauges, fabrication processes, construction methods, coordination with the work of other trades, or construction safety precautions, all of which are the sole responsibility of the Contractor. The Architect's review shall be conducted with reasonable promptness, consistent with sound professional practice. Review of a specific item shall not indicate acceptance of an assembly of
3 which the item is a component. The Architect shall not be required to review and shall not be responsible for any deviations from the Contract Documents not clearly noted by the Contractor, nor shall the Architect be required to review partial submissions of those for which submissions for correlated items have not been received PRODUCT CONFIRMATION AND SUBMITTAL SCHEDULE A. General: Following Notice of Award, and prior to signing Owner/Contractor Agreement, submit to the Architect a complete schedule of all materials, products and fabrications required by Contract Documents, naming the supplier, fabricator/manufacturer of each, and where applicable, identifying the manufacturer's product name and number for each item specified. This listing shall provide the Owner with confirmation of which products and materials, among available options allowed by Contract Requirements, will be utilized in the Work. For each item on which a submittal is required, provide approximate date upon which initial submittal will be presented to Architect for review. Utilize and maintain this schedule to coordinate submittal requirements and record Architect's action markings as defined herein. B. Form: Prepare product confirmation list and submittal schedule in same sequence as Specification Table of Contents; cross reference each item to corresponding Specification section. List generic work element, followed by exact product reference intended, for incorporation into the work and identify fabrication/manufacturer, and submittal dates in successive column format. Provide blank columns for action markings and resubmittal records. C. Product Review: For materials/products where no submittal requirements are identified within individual technical sections of the Project Manual, no additional submittals are required beyond confirmation listing. Comply with detailed requirements of Contract Documents GENERAL SUBMITTAL REQUIREMENTS A. Coordination and Sequencing: Coordinate preparation and processing of submittals, with performance of the Work, so that Work will not be delayed by submittals. B. Submittals: Provide submittal material of types indicated within individual technical sections of this manual. Do not allow required shop drawing copies to be used in connection with the Work without appropriate final "Action" markings by Architect.
4 1. Transmittal accompanying submittals shall identify the Project, Contract, subcontractor, fabricator or manufacturer, date submitted, and date of preparation. All submittals shall be numbered in consecutive sequence, and each sheet shall indicate the total number of sheets in each set. Submittal number shall consist of a specification division number, followed by sequential numeral, such as , which indicates the first mechanical submittal. Resubmittal would be identified as Submittal material shall have Contractor review stamp on each sheet of submitted material, stating they have reviewed submittal and found it to be in conformance with Contract Documents, signed and dated. Submittals received without Contractor's stamp will be returned "No Action Taken." 3. All submittals for all equipment in a given system, such as an air handling system, shall be submitted at one time and each complete, set in a separate binder. 4. When manufacturer's or fabricator's brochures, literature, and data sheets are submitted, the system or product specified shall be identified from other systems or products contained within preprinted information. All options to be included shall be clearly identified. 5. Submittals shall indicate types, gauges, style, finishes, etc., of all materials. Sufficient data shall be included to permit a detailed study of the product or system submitted. All submittals shall include installation instructions and ICBO reports where applicable. 6. Each submittal shall be marked to clearly indicate the use for which product, material, or procedure is being submitted for consideration. Each item submitted shall be marked for identification with the applicable page and paragraph number of the Specifications and/or the detail and sheet number of the Contract Drawings. 7. If submittal is a "substitute," it shall be submitted in conformance with requirements of Section 01600, and explanation given for substitution. 8. Piping, conduit, equipment, etc., submittals shall be accompanied with support/suspension information intended to be used for installation.
5
6 9. Ten (10) working days shall be allowed for Architect review, except attempt will be made to expedite submittals marked as "rush," provided all submittals are not marked "rush." Transmittals/submittals marked "rush" and sent by regular mail will not be given preferential attention. Contractor/suppliers letters will not be considered or acted on in lieu of manufacturer's printed information and/or instructions SPECIFIC-CATEGORY SUBMITTAL REQUIREMENTS A. General: Except as otherwise indicated in individual work sections, comply with requirements specified herein, for each indicated category of submittal. Provide and process repeat submittals if Architect's action marking indicates either "Revise and Resubmit" or "Rejected." Maintain field copies of all submittals for construction and coordination use. Maintain "Record Document" file on site for future transmittal to Owner at Project completion. B. Shop Drawings: Provide one (1) correctable translucent reproducible print and three (3) blue-line or black-line prints for Architect's review; reproducible and two (2) prints will be returned. Reproduce additional copies for field use as required. Comply with "Record Document" requirements of Section C. Product Data: Provide six (6) copies; four (4) copies will be returned. Comply with "Record Document" requirements of Section D. Samples: Provide preliminary submittal of a single set of samples for Architect's review and initial selection. Initial submittal is final submittal unless returned with "Action" which requires resubmittal. Submit two (2) sets of samples in final submittal; one (1) set will be returned. E. Inspection and Test Reports: Classify each as either "shop drawing" or "product data," depending upon whether report is uniquely prepared for project, or a standard publication of workmanship control testing at point of production, and process accordingly. F. Warranties: Refer to "Warranties and Bonds" section for specific general requirements on warranties, product/workmanship bonds, and maintenance agreements. In addition to copies desired for Contractor's use, furnish two (2) executed copies, except furnish two (2) additional (conformed) copies where required for maintenance manuals.
7 G. Standards: Where copy submittal is indicated, submit two (2) copies for Architect's and Owner's use. Where workmanship at project site and elsewhere is governed by standard, furnish additional copies to fabricators, installers, and others involved in performance of the Work. H. Close-out Submittals: Refer to "Close-out" sections for specific general requirements on submittal of closet information, materials, tools, and similar items. 1. Record Document Copies: Furnish one (1) reproducible set and two blueline sets. 2. Maintenance/Operating Manuals: Furnish two (3) bound copies. 3. Materials and Tools: Refer to individual work sections for required quantities of spare parts, extra and overrun stock, maintenance tools and devices, keys, and similar physical units to be submitted. 4. Shop Drawings and Product Data: Furnish one complete set of approved submittals. I. General Distribution: Provide additional distribution of submittals (not included in foregoing copy submittal requirements) to subcontractors, suppliers, fabricators, installers, governing authorities and others, as necessary for proper performance of the Work ACTION ON SUBMITTALS A. Architect's Action: Architect will review each submittal, mark with "Action," and where possible, return within ten (10) working days of receipt. Where submittal must be held for coordination, Contractor will be so advised without delay. Action markings shall be interpreted as follows: 1. "No Exception Taken": Work may proceed, provided it complies with Contract Documents. 2. "Make Corrections Noted": Work may proceed, provided it complies with notations and corrections on submittal, and with Contract Documents. 3. "Revise and Resubmit" or "Rejected": Do not proceed with work. Revise submittal in accordance with notations thereon, and resubmit without delay, to obtain a different action marking.
8 a. Do not permit submittals marked "Revise and Resubmit" to be used at the Project site, or elsewhere, where Work is in progress. 4. "Resubmit in Required Form" means that the submittal does not conform to the design concept, or meet requirements of the Contract Documents. B. Other Action: Where a submittal is primarily for information or record purposes, special processing or other activity, the submittal will be returned marked "Action Not Required." C. Architect's review of submittals in accordance with Article 4.2.7, the General Conditions, is not to be construed as authorization for additional work or additional cost. PART 2 - PRODUCTS Not Applicable PART 3 - EXECUTION 3.01 SUBMITTAL DELIVERY A. All submittals shall be transmitted to Architect in accordance with Contractor's Schedule of Submittals MOCK-UP SAMPLE CONSTRUCTION A Where sample construction is incorporated into the Work, location and extent will be determined at a pre-sample construction meeting attended by the Owner, Architect, Contractor, subcontractor, and all other supplier or parties involved in that particular mock-up sample. 1. All parties responsible for completion and testing of sample mockups shall be notified at least two (2) weeks in advance of presample construction meeting. 2. Initial submittals of Shop Drawings, Product Data and Samples, must be received by Owner prior to beginning of any sample construction. **END OF SECTION**
A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.
SECTION 01300 PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Requirements B. Submittal Procedures C. Specific Submittal Requirements D. Action on Submittals E. Repetitive Review 1.2 DESCRIPTION
More informationSECTION SUBMITTAL PROCEDURES
SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide submittals in accordance with the General Conditions as modified by the Supplementary Conditions,
More informationSECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
SECTION 01334 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Submit to the ENGINEER for review, such working drawings, shop drawings, test reports and data on materials and equipment
More informationEast Central College
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationTaylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES
SECTION 01340 SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED A. Contractor shall submit to the Architect/Engineer for review and exception, if any, such working
More informationA. Action Submittals: Written and graphic information that requires Engineer's responsive action.
SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationJEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia
BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners
More informationSection Meetings Section Material and Equipment. None Required
January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental
More informationA. Action Submittals: Written and graphic information that requires Architect's responsive action.
SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationDIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES
DIVISION 1 GENERAL REQUIREMENTS SECTION 01 33 00 PART 1 - GENERAL 1.1 SUMMARY A. This section includes administrative and procedural requirements for submittals required for performance of the work, including
More informationUCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationMISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration
SECTION 01 340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationDIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01300 - SUBMITTALS PART 1 - GENERAL 1.1 STIPULATIONS A. The section "Special Requirements" forms a part of this section by this reference thereto and shall have
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationSECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationSECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.1 DESCRIPTION A. This specification defines the general requirements and procedures for submittals. A submittal is information
More informationSECTION SUBMITTAL PROCEDURES
SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationUNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General
More informationTCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationSECTION SUBMITTAL PROCEDURES
SECTION 013300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply
More informationSECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationSECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
SECTION 01 33 23 - SHOP DRAWINGS, PRODUCT DATA, AND PART 1 - GENERAL 1.1 SUMMARY A. Products include, but are not limited to, the following construction submittals: 1. Shop Drawings. 2. Product Data. 3.
More informationSHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
SECTION 01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Shop drawings, manufacturer's catalog cuts, product data, samples, and attached Shop Drawing/ Catalog
More informationSECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.
SECTION 01300 - PART 1 - GENERAL 1.1 GENERAL A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. B. Unless otherwise noted, within 14 days after the date of commencement as stated in
More informationSECTION ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL 1.01 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Progress meetings. D. Construction progress schedule. E. Coordination drawings. SECTION 013000
More information2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS
PART 1 GENERAL 1.01 REQUIREMENTS INCLUDED SECTION 01 20 00 PROJECT MEETINGS A. Construction Manager shall schedule and administer pre-construction meeting, periodic progress meetings, and specially called
More informationAnswer: Qualification statement should be provided with the bid.
Little Diversified Architectural Consulting, Inc. 5815 Westpark Drive Charlotte, North Carolina 28217 Phone: 704-525-6350 Fax: 704-561-8700 Lincoln County Probation Renovation 208 N. Government Street
More information.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal
City of Winnipeg Brady Road Landfill Site Section 01300 New Entrance and Scale Facility Page 1 of 4 SUBMITTALS 1. SHOP DRAWINGS 1.1 General.1 Arrange for the preparation of clearly identified Shop Drawings
More informationSECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.
SECTION 01 3000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Submittals for review, information, and project closeout. D. Submittal procedures.
More informationPROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA
If project is not administered in PRISM, coordinate use of Exhibit 6 submittal schedule with this section. SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED
More informationSECTION SUBMITTAL PROCEDURES
SECTION 01 33 00 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes. 1. Submittal procedures. 2. Product data. 3. Shop drawings. 4. Samples. 5. Design data. 6. Test reports. 7. Certificates.
More informationSECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.
More informationINDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS:
INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS: 013300 SUBMITTAL PROCEDURES 018116 CONSTRUCTION WASTE MANAGEMENT DIVISION 2 EXISTING CONDITIONS: 023000 EARTHWORK
More informationSUBMITTAL PROCEDURES
SUBMITTAL PROCEDURES PART 1 GENERAL The ASPA Project Engineer (APE) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective
More informationSECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum
SECTION 013201 - SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum Pay Unit price breakdown) shall be developed and ultimately
More informationsubmittals 1s e c t i o n
Architectural Woodwork Standards submittals 1s e c t i o n SECTION 1 introductory Information Introduction...25 What to Expect...25 Purpose...25 Level of Detail...25 Approvals...25 Scheduling...25 The
More informationSTANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES
STANDARD SPECIFICATIONS SECTION 01330 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 DESCRIPTION A. Section includes general requirements and procedures related to preparation and transmittal of Submittals to
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018
SECTION 01 7839 - PROJECT RECORD DOCUMENTS GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationA. Section includes administrative and procedural requirements for project record documents, including the following:
SECTION 017839 - PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01
More information01100 SUMMARY OF WORK
Lambert..STL Airport Uve Animal Facility- World Trade Center- St. Louis, Missouri 01100 SUMMARY OF WORK PART 1.. DESCRIPTION a. General: The work to be completed consists of fabrication, deliver, and installation
More informationDWG, Inc. Coastal Carolina University State Project No. Consulting Engineers HTC Arena Lighting H17-N112-JM
SECTION 011000 SUMMARY PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Work covered by the Contract Documents. 2. Work under other contracts. 3. Use of premises. 4. Specification
More informationWorking Drawing Manual
Working Drawing Manual 2012 Table of Contents Section 1 Working Drawing Types... 1 1.1 General... 1 Section 2 Processing Steps... 1 2.1 Project Manager... 1 2.2 Engineering Document Unit... 2 2.3 Contractor...
More informationJacksonville District Master
-01 33 00 (April 2006) From USACE / NAVFAC / AFCESA UFGS UNIFIED FACILITIES GUIDE SPECIFICATIONS Revised thoughout - changes not indicated by CHG tags SECTION TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS
More informationSECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS
PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Record Documents. B. Operation and Maintenance Manuals. C. Warranties and bonds. 1.02 RELATED REQUIREMENTS SECTION 01 78 00 A. Section 01 30 00 - Administrative
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS *************************************************************************** SECTION
USACE / NAVFAC / AFCEC / NASA UFGS-01 33 00.05 20 (May 2014) Change 1-09/15 Change 2-12/15 Change 3-09/16 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 33 00.05 20
More informationWhat Are Submittals?
Introduction Overview of the Submittal Process Comparison of AIA with ConsensusDOCS Architect and Contractor Obligations FAR Requirements State Licensing Requirements 1 What Are Submittals? Submittals
More informationSECTION PROJECT MANAGEMENT AND COORDINATION
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationSECTION OPERATION AND MAINTENANCE DATA
SECTION 01787 OPERATION AND MAINTENANCE DATA PART 1 GENERAL 1.01 SUMMARY A. Compile product data and related information appropriate for OWNER's maintenance and operation of products furnished under Contract.
More informationSECTION 2 GENERAL REQUIREMENTS
SECTION 2 GENERAL REQUIREMENTS 2-1 ENGINEER REQUIRED: All plans and specifications for Improvements which are to be accepted for maintenance by the County and private, on-site drainage and grading shall
More informationConstruction Phase Project Management and Documentation
Construction Phase Project Management and Documentation Bill Mason CDM Smith Outline Design Bidding Construction Start-up & Closeout 2 DESIGN Design Preliminary Engineering Report Plans Specifications
More informationA. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationSubmittal Packages Detailed with Items and Reviewers
Submittal Packages Detailed with Items and Reviewers Tenochca Upgrades Project # 2351 San Diego State University 5500 Campanile Drive San Diego, CA 92182 Tel: 619-594-3740 Fax: 0054-096813-1 Tile Carpeting
More informationSUBCONTRACTORS PROCEDURES MANUAL EXHIBIT A.15 SAMPLE MANUAL ONLY FINAL MANUAL WILL BE CUSTOMIZED FOR GREAT WOLF LODGE
(Project) (Date) (Location) Turner Job # (TBD) Item No. 15 SUBCONTRACTORS PROCEDURES MANUAL EXHIBIT A.15 SAMPLE MANUAL ONLY FINAL MANUAL WILL BE CUSTOMIZED FOR GREAT WOLF LODGE (Location) TURNER CONTRACT
More informationBrad Luke. Director Peddle Thorp Auckland
Brad Luke Director Peddle Thorp Auckland Site Observation and Practical Completion Preparation PEDDLE THORP Introduction Architects Agreement for Services. Observation Work Plans. Auckland Council Quality
More information[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]
SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA PART I - GENERAL 1.1 SUMMARY A. Operation and Maintenance Data shall be submitted in appropriately-sized binders, with dividers, and organized by each
More informationKINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS
SECTION 01 3100 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,
More information***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)
DRAFT UFGS- 01 XX XX (FEB 2014) ------------------------ Drafting Activity: USACE UNIFIED FACILITIES GUIDE SPECIFICATION SECTION TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION 01 XX XX (FEB
More informationSECTION SUBMITTALS
SECTION 01300 SUBMITTALS PART 1- GENERAL 1.01 SCOPE OF WORK A. This Section specifies the general methods and requirements of submissions applicable to Shop Drawings, Product Data, Samples and Operations
More informationPROCEDURE FOR PROCESSING WORKING DRAWINGS
PROCEDURE FOR PROCESSING WORKING DRAWINGS MAY 2005 Procedure for Processing Working Drawings GENERAL: The procedure for the review and processing of working drawings provide for two primary types of drawings,
More informationREMARKS: The A.F.F. dimension noted on the drawings to the bottom of the grid is 15 0, this dimension should be 16 0.
SUBMITTAL REVIEW SENT VIA: REGULAR MAIL OVERNIGHT FAX HAND DELIVERY DIGITAL DELIVERY OTHER: TO: Rodrigo Gorgazzi / CannonDesign Steve Benesh / CannonDesign Tim Donlon / FROM: Steven Cooper CC: David Barnett
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 33 00 (May 2011) Change 9-08/17 ----------------------------- Preparing Activity: NASA Superseding UFGS-01 33 00 (February 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationWATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:
WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO-00111 Job No.: 16-7003 To Respondent of Record: ADDENDUM 2 July 5, 2017 This addendum, applicable to work referenced
More informationSection Project Closeout
Section 01700 - Project Closeout PART 1 GENERAL A. STIPULATIONS The section Special Requirements forms a part of this section by this reference thereto and shall have the same force and effect as if printed
More informationSAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO.
SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT Issued By: D. Anthony Rubin Date Issued: May 21, 2015 BID NO.: 15-7031 FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO.
More informationSubmittal Review SW Macadam Ave Suite 200 ATTENTION: Riley Tobin. Portland, OR RE: BSD Sunset High School
Submittal Review TO: Pavilion Construction DATE: 07.20.2015 JOB NO.: 1484P 4700 SW Macadam Ave Suite 200 ATTENTION: Riley Tobin Portland, OR 97239 RE: BSD Sunset High School Concession Stand/Interior Renovations
More informationAIA Continuing Education
AIA Continuing Education Hall & Company is a Registered Provider with the American Institute of Architects Continuing Education Systems. Credit earned based on the completion of this program will be reported
More informationThe Association of South African Quantity Surveyors Die Vereniging van Suid-Afrikaanse Bourekenaars PRELIMINARIES. Project. Employer.
The Association of South African Quantity Surveyors Die Vereniging van Suid-Afrikaanse Bourekenaars PRELIMINARIES Project Employer Contractor Contract Date File Code NOVEMBER 2007 EXPLANATORY NOTES AND
More informationREVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty
HOT AISLE CONTAINMENT SYSTEM (HACS) REVISION #1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. B. C. Drawings and general provisions of the Contract, including General and Supplementary. Conditions apply to
More informationPROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA
SECTION 01 78 00 CLOSE-OUT SUBMITTALS PART 1 - GENERAL 1.1 GUARANTEES A. Compile and submit guarantees, bonds, and service and maintenance contracts specified in the individual B. Guarantees from Subcontractors
More informationSANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS
SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS All plans for sanitary sewer main extensions, improvements and modifications
More informationSECTION III SUBMITTALS AND APPROVALS
SECTION III SUBMITTALS AND APPROVALS In order to expedite the approval process of new water distribution system and sanitary sewer collection system extensions, the Hilton Head No. 1 Public Service District
More information00-General Drawings. Doc. no.: NA-00-STS002
Gæðaskjal (GSK) GSK-1773 Date of issue: 24.11.2016 Revision no.:2.0 Responsible: Einar Friðgeir Björnsson Editor: Rafn Magnús Jónsson 00-General Drawings Doc. no.: NA-00-STS002 This standard technical
More informationThe GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document.
Enroll in GMFI Program Image Consultation Design Intent Document Preparation Preliminary Drawings Final Drawings Design Intent Document You are here. 1-2 Construction Documents Services performed by dealer
More information1. Land survey Work. 2. Civil and Structural engineering services.
SECTION 01050 FIELD ENGINEERING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification
More informationWorking Drawing Procedure
Working Drawing Procedure June 2007 Prepared by Structural Engineering & Construction Services 1.0 Working Drawing Procedure 1.1 General There are two primary types of working drawings, those requiring
More informationFAST TRACK WORKSHOP OBJECTIVES
1 FAST TRACKING FAST TRACK WORKSHOP OBJECTIVES TO UNDERSTAND: 1. WHY ARE CRITICAL PATH ( FAST TRACK ) DESIGN SUBMITTAL PACKAGES ALLOWED 2. WHEN IS FAST TRACK ALLOWED 3. WHEN IS THE CONTRACTOR ALLOWED TO
More information835 Gil Harbin Industrial Blvd Valdosta, GA 31601
QUALITY CONTROL PLAN NAVFAC SE PUBLIC WORKS MAYPORT FEAD MAYPORT 1966 BONHOMME RICHARD STREET MAYPORT NAVAL STATION FL 32228-0073 N69450-08-D-1781/0004 835 Gil Harbin Industrial Blvd Valdosta, GA 31601
More informationFacility Services Subgroup Preface for Divisions 21` through 28
Facility Services Subgroup Preface for Divisions 21` through 28 1.1 EXECUTIVE SUMMARY A. This document provides standards for the Consultants and Contractors producing mechanical and electrical design
More informationDesigner CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer
Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer Construction Documents 1.1 to 1.6 Create Submittal Log 1.1 Construction Docs Focus of this process is to transmit submittal
More informationTABLE OF CONTENTS. 1.0 Scope. 2.0 References. 3.0 Definitions. 4.0 Submission and Design Requirements. 5.0 Materials 5.1 General 5.
1.0 Scope 2.0 References 3.0 Definitions 4.0 Submission and Design Requirements 5.0 Materials 5.1 General 5.2 Marking 6.0 Equipment 7.0 Production 7.1 Steel Octagonal Poles 7.2 Base Plate 7.3 Top Cap 7.4
More informationSECTION LIGHTING PART 1- GENERAL
SECTION 16500 LIGHTING PART 1- GENERAL 1.01 WORK INCLUDED A. The Contractor shall provide all lighting fixtures, panelboards, labor, material, etc., in accordance with the preceding specifications, the
More information2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)
ATTACHMENT 5, CONTRACT 13, ADDENDUM 3 2017 CDM Smith 14955-109447 SECTION 01725 PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS) PART 1 GENERAL 1.01 DESCRIPTION A. The Owner and Contractor shall utilize the
More informationCITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT
CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS For EQUIPMENT FOR THE 2014 CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT WASTEWATER TREATMENT PLANT IMPROVEMENT PROJECT:
More informationMerrick Pet Care New Distribution Center Hereford, Texas
Merrick Pet Care New Distribution Center Hereford, Texas DATE: March 16, 2015 ARCHITECTURAL/ELECTRICAL ADDENDUM #6 FROM: TO: PROJECT: Lavin Associates, Architects Plan Holders of Record Merrick Pet Care,
More informationSPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work
2004 Specifications CSJ 0110-04-166 SPECIAL PROVISION 000--363 Description of Project, Scope of Contract and Sequence of Work 1. General. The work to be performed on this project consists of furnishing,
More informationAnticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days.
This addendum is hereby made part of the Request for Bid for the above-named project and shall be taken into consideration by all firms preparing a submittal on this project. Acknowledge receipt of this
More informationSECTION BASIC MECHANICAL REQUIREMENTS GENERAL BASIC MECHANICAL REQUIREMENTS PART RELATED DOCUMENTS
SECTION 15010 - BASIC MECHANICAL REQUIREMENTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Basic Requirements: Requirements of the Contract Forms, Conditions of the Contract, Specifications, Drawings, and
More informationB. Division-16 Basic Materials and Methods section apply to work specified in this section.
Section 16745 PREMISE CABLING SYSTEMS PART ONE GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification
More informationThis specification describes the general requirements for Engineering Services provided to Vale.
1/9 1.0 PURPOSE This specification describes the general requirements for Engineering Services provided to Vale. 2.0 GENERAL For the purposes of this document, the Engineering Consultant shall be referred
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-26 00 00.00 20 (July 2006) ------------------------------- Preparing Activity: NAVFAC Superseding UFGS-26 00 00.00 20 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationDESIGN REVIEW PROCESS AND APPLICATION
DESIGN REVIEW PROCESS AND APPLICATION Design review is the first step in the process of any construction project requiring permits. The Community Redevelopment Agency (CRA) Board is responsible for ensuring
More informationChapter 1 General Design Information
Chapter 1 General Information Introduction The primary aim in both designing and checking is to produce a structure that will safely carry the anticipated loads. The design team, consisting of the designers,
More informationSUBMITTAL REVIEW B Passenger Elevators Shop Drawings GCAN
SUBMITTAL REVIEW Submittal: No. 008 Spec Section: 14 2010 Passenger Elevators Reviewed By: Tripp Lewton, Comma-Q Architecture Date: May 17, 2012 Project: BPS Belgrade Elementary School Location: Belgrade,
More informationRecommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7)
Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Final Revision 2 AACE International Recommended Practice PS-24 Tracking
More informationEngineering Drawing System
LPR 7320.1 Effective Date: February 2, 2010 Expiration Date: February 2, 2015 Langley Research Center Engineering Drawing System National Aeronautics and Space Administration Responsible Office: Systems
More information-and- (the Artist ) maquette means the drawing or model, prepared by the Artist, of the proposed Art Work;
THIS AGREEMENT made in triplicate this th day of, 200 BETWEEN: CITY OF OTTAWA (the City -and- (the Artist WHEREAS the Council of the former City of Ottawa, an old municipality as defined in the City of
More informationDIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS
DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS PART 1 GENERAL 1.01 Scope of Work A. Provide material, accessories, tools, equipment and labor as required for the complete fabrication
More informationSUBMITTAL REVIEW Food Service Equipment Data Sheets GCAN. Notes: 1. See D-C Design comments. Submittal: No. 035.
SUBMITTAL REVIEW Submittal: No. 035.00 Spec Section: 11 4000 Food Service Equipment Reviewed By: Laura Landon, Comma-Q Architecture Date: July 23, 2012 Project: BPS Belgrade Elementary School Location:
More informationCity Plaza Energy Upgrades Timeline of Events Pella Window Cancellation
City Plaza Energy Upgrades Timeline of Events Pella Window Cancellation June 3, 2010 Pella asks what is needed for submittals. See Attachment #1. June 7, 2010 Pella (Matt Tison) confirms the receipt of
More informationADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030
ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO. 2018-008-COM.00030 To: Prospective Bidders of Record Date: December 17, 2018 The following changes, additions, revisions, and/or deletions
More information