1 IFB PAINTING AT HAYDON ELEMENTARY ADDENDUM #1 IFB MODIFICATIONS: BONDING REQUIREMENTS: Due to the complexity of the scope of work, MCPS is requiring bonding for this bid. The following bonds are required: 1. Bid Bond 5% of bid 2. Performance Bond 100% of bid 3. Payment Bond 100% of bid MINIMUM REQUIREMENTS: Bid Bond in the amount of 5% of your bid. Awarded firm must demonstrate successful experience in painting of similar scope, size, and cost. Prior to start of work, the awarded firm shall provide a valid certificate of insurance and performance and payment bonds (100%) in the full amount of the contract price. Class A license is required for this project if the cost exceeds $100,000. Exhibit A Paint Areas: A new Exhibit A is attached change to rooms to be painted and not painted. Exhibit F Design and Paint Requirements: A new Exhibit F is attached to include page 8 for the Gym requirements Attachment 6 Pricing Schedule: Please disregard previous Attachment 6 and replace with Attachment 6 in this document this adds a line for pricing for Alternate Space Stage in the Cafeteria IFB CLARIFICATIONS: 1. When is the anticipated start date? Start date will be the end of the school year for students, around June 15, The work should be completed by August 13, 2018 with punch-out completed by August 20, What are the colors for the Cafeteria and Gym? The paint colors are not known for these two areas. The vendor is expected to color match the white, blue and black paint for these areas. In the Gym, there is one wall in Exhibit F that does include the Regale Blue wall SW In the Cafeteria, what is being painted? The walls up to and including the black trim are being color matched and painted, the doors and frames are being painted as well as the blue on the pillars. Vendors are NOT painting the ceiling, or panels. The two (2) rooms to the side of the stage shown in the walk-through are being painted as well. Conduits are being painted. 4. For the Alternate pricing for the Stage, what is being painted? The walls but not behind the cage on the left of the stage and the back climbing wall may or may not come down and will be discussed upon award. 5. What is being painted in the gym? The vendor will be expected to color match three walls with the existing color. Vendors are not expected to move the bleachers as they are bolted to the wall/floor. Vendors will paint Addendum 1 IFB
2 ADDENDUM #1 IFB PAINTING AT HAYDON ELEMENTARY to the top of the bleachers. Vendors will ONLY paint up to the rafters and stop, no rafters or tectum boards will be painted. The gym office will be painted. The mural will NOT be painted over. 6. What are we doing with existing murals? Existing murals are going to stay, the vendor will need to paint around them. The murals should be blocked off; the vendor is not expected to paint to mural edges. 7. Will the student/teacher art on walls in classrooms and hallways be removed? Yes, teachers will be informed that all items affixed to the walls should be removed in preparation for the work listed in this contract. 8. Will vendors paint the natural wood doors? No, vendors will not paint any of the natural wood doors 9. In bathrooms within classrooms, what will be painted? Vendor will be required to paint all walls not covered with FRP within the restrooms located inside classrooms. 10. For the round sunken room in the middle of the school, what needs to occur there? Vendors will be removing the carpet from the walls on the inside and outside of that room. The orange ceiling will be painted. The wood baseboard will be removed and replaced with the new base cove. Inside this room, the blue carpet will stay, including the blue carpet that goes slightly up the wall in the front of the room. 11. What will happen to accordion doors? Accordion doors are to be left as-is and not be painted or removed. 12. Can vendors have employees work in shifts? Yes, please notate this on the bid response. MCPS will make sure that the building is accessible to complete this work within the timeframe specified. 13. Should the vendor paint the expansion joints? No, these do not need to be painted. 14. What should vendors to for the wire molds and cords? Vendors will need to cut around wire molds and any other items permanently affixed to the walls. Projectors and the like will be bagged for the vendors before the work begins. 15. With regards to the outside painting, what is included? Vendors will only paint the exterior doors and lintels for any window that has a lintel. All anodized aluminum will NOT be painted. 16. Exhibit F shows specific artwork, is the vendor expected to paint the items, such as the birds in in the library? No the art done by others will not be part of this bid. Vendors are required to paint the design in the hallway, but not the birds in the library, Haydon Hawk in the gym, etc. ADDENDUM ATTACHMENTS: Attached Exhibit A Attached Exhibit F Attached Attachment 6 Revised Pricing Schedule Attached MANDATORY Pre-Bid Meeting Sign-In Sheet Addendum 1 IFB
3 ADDENDUM #1 IFB PAINTING AT HAYDON ELEMENTARY ATTACHMENT 6 PRICING SCHEDULE REVISED *Vendors shall remove previous Attachment 6 Pricing Schedule and replace with this form. Responses not submitted on this Attachment 6 will be found non-responsive. *The bid prices shall be for a Turnkey-all inclusive (labor, materials, equipment, overhead, bid bond, etc.) project. No additional charges will be allowed. Pricing is firm fixed. Firms submitting a bid acknowledge the scope of work, terms and conditions and completion deadlines. Haydon Elementary School *Preparation Cost: $ *Painting Cost: $ Total Contract Cost: $ (Not including price for Alternate area) *Price for Alternate Area in Cafeteria: $ Estimated Time for Completion: Proposed Start Date: Notes/Comments: *If awarded, the Bidder is prepared to provide the required Insurance and Performance and Payment Bonds. Company Authorized Signature Date Print Name Title Addendum 1 IFB
4
5 MANASSAS CITY PUBLIC SCHOOLS R.C. Haydon Elementary School 9075 Park Avenue Manassas VA, JULY 24, 2017
6 Haydon Elementary School FOCUS AREAS FOCUS AREAS LIBRARY / MEDIA CENTER GYM CORRIDORS SW 7607 SANTORINI BLUE SW 7663 MONORAIL SILVER
7 Haydon Elementary School GENERAL NOTES FLOOR PLAN IS NOT TO SCALE AND CONDITIONS/FLOORPLAN MAY VARY ON SITE. FLOORPLAN IS SHOWN FOR LAYOUT PLANNING / PRICING PURPOSES ONLY. CONTRACTOR IS RESPONSIBLE FOR VERIFYING ALL FIELD CONDITIONS AND DIMENSIONS, INCLUDING CEILING HEIGHTS. CONTRACTOR IS RESPONSIBLE FOR CONFIRMING ALL QUANTITIES AND OVERAGE AS REQUIRED BY MCPS. BEFORE PROCEEDING WITH HIS WORK, THE CONTRACTOR SHALL CAREFULLY INSPECT ALL SURFACES TO BE PAINTED OR FINISHED AND SHALL NOTIFY MCPS OF ANY DEFECTS, IMPROPER MATERIALS, WORKMANSHIP OR OTHER CONDITION WHICH IN HIS OPINON WILL AFFECT THE SATISFACTORY COMPLETION AND PERMANENCY OF HIS WORK. THE ABSENCE OF ANY SUCH NOTIFICATION WILL BE CONSTRUED AS AN ACCEPTANCE BY THE CONTRACTOR OF ALL SUCH SURFACES. USE PRODUCTS OF SAME MANUFACTURER FURNISHING FIRST OR PRIMER SEALER COATS OF THE PARTICULAR SURFACE FOR SUCCEEDING COATS, EXCEPT WHERE METAL PRIMER IS USED. TYPICAL WALL COLOR U. N. O. SHERWIN WILLIAMS SW 7011 NATURAL CHOICE EXTRA. COLORS AND TYPES OF PAINT NOT LISTED OR INDICATED WILL BE SELECTED BY ARCHITECT. THE VARIOUS SURFACES SHALL BE PAINTED OR FINISHED WITH A MINIMUM OF ONE (1) PRIMER COAT AND (2) FINISH COATS. ADDITIONAL PRIMER AND FINISH COATS SHALL BE PROVIDED IF REQUIRED TO COVER MATERIAL UNIFORMLY AND COMPLETELY. ALL DRYWALL SURFACES SHALL BE PRIMED & PREPARED TO RECEIVE WALL FINISH. ALL SCRATCHES, CRACKS, HOLES OR SIMILAR DEFECTS SHALL BE PROPERLY CUT OUT AND FILLED WITH SPACKLING COMPOUND, OR OTHER PATCHING MATERIAL AS MAY BE REQUIRED. PATCHED PORTIONS OF DRYWALL SHALL BE GIVEN A COAT OF PRIMER-SEALER IN ADDITION TO ALL OTHER SPECIAL COATS. WALL SHALL BE EGGSHELL FINISHED, ROLLED. ACCESS DOORS, BUCKS AND OTHER METAL WORK SHALL BE SEMI-GLOSS FINISH AND SAME COLOR AS WALL IN WHICH THEY OCCUR. IF ADJACENT SURFACE IS FINISHED IN WALLCOVERING, MATCH COLOR AS CLOSELY AS POSSIBLE. CEILING AND SOFFIT FINISH FLAT TYPICALLY. ALL METAL ITEMS SCHEDULED FOR PAINTED FINISH (I.E. DOOR FRAMES, DOORS, RAILING, HVAC ENCLOSURES) SHALL BE PAINTED WITH A DTM PAINT. COLOR TO BE SAME AS ADJACENT SURFACES UNLESS OTHERWISE NOTED. SW 7607 SANTORINI BLUE AT COMPLETION OF WORK, ALL SUB-CONTRACTORS SHALL REMOVE FROM THE PREMISES ANY DEBRIS CAUSED BY HIS WORK. SUB-CONTRACTOR TO PACK & LABEL ALL ATTIC STOCK. OWNER TO PROVIDE LOCATION FOR SUB-CONTRACTOR TO DELIVER ATTIC STOCK TO BE STORED. MIN 5% OR 1 GALLON BUCKET (WHICHEVER IS GREATER) OF ALL COLORS AND PRODUCTS INSTALLED. FLAME SPREAD RATINGS FOR ALL INTERIOR FINISHES SHALL BE CLASS A. PROVIDE WRITTEN CONFIRMATION OF FLAME SPREAD TESTING TO BUILDING AND FIRE DEPARTMENTS. SW 7663 MONORAIL SILVER
8 Haydon Elementary School ALL PAINT COLORS TO BE USED TYP. WALL PAINT UNLESS OTHERWISE NOTED Benjamin Moore DOOR TRIM & DOOR PAINT ACCENT COLOR AT CORRIDORS ACCENT COLOR AT GYM ACCENT COLOR AT LIBRARY ACCENT COLOR AT LIBRARY ACCENT COLOR AT GYM WALL BASE COLOR SHALL BE AS CLOSE AS POSSIBLE TO DOOR TRIM COLOR JOHNSONITE 83 MIDNIGHT ACCENT COLOR AT CORRIDORS ACCENT COLOR AT LIBRARY ACCENT COLOR AT GYM ACCENT COLOR AT LIBRARY AT CLINIC: (SEE CLINIC PROTECTIVE WALL PAINT SHEET) OPTION 1 COLOR MATCH EXISTING BLUE & THEN GET PAINT IN SAME COLOR FAMILY, BUT A FEW SHADES DARKER IN HARMONY INTERIOR LATEX OPTION 2 SW 7011 NATURAL CHOICE IN PAINT SHIELD MICROBICIDAL INTERIOR LATEX PAINT SW 7607 SANTORINI BLUE SW 7663 MONORAIL SILVER
9 Haydon Elementary School SCHOOL CORRIDORS CONCEPT SKETCH SW 7663 MONORAIL SILVER
10 Haydon Elementary School SCHOOL CORRIDORS CONCEPT SKETCH
11 Haydon Elementary School MEDIA CENTER/LIBRARY SW 7607 SANTORINI BLUE BIRD & CLOUD WALL FILM IS OPTIONAL SW 7663 MONORAIL SILVER
12 Haydon Elementary School GYM ADD SCHOOL NAME PAINT RECTANGULAR BOX & STRIPES, SCHOOL LOGO TO BE APPLIED AFTER PAINTING COMPLETE SW 7607 SANTORINI BLUE PAINT WALL ACCENT COLOR:
13
14
PAINTING PAINTING
09920 - PAINTING 09920-1 PART ONE: GENERAL PAINTING 1.1 Description 1.1.1 Work of this Section, as shown or specified, shall be provided by the Interior Contractor and shall be in accordance with the requirements
More informationCOMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION. SPECIFICATIONS FOR Interior Painting CONTRACT
COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION SPECIFICATIONS FOR Interior Painting CONTRACT AT ENGINEERING DISTRICT 8-0 2140 HERR STREET HARRISBURG, PA. 17103 CONTACTS: Mike Miller 717-787-6408
More informationDecember 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions
December 31, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y16-721-MM / ADDENDUM No. 1 ORANGE COUNTY CONVENTION CENTER PHASE III VALENCIA BALLROOM RENOVATION Bid Opening Date: January 12, 2016
More informationSECTION PAINTS AND COATINGS. a. Section Submittal Procedures: Requirements for submittals.
SECTION 09900 PART 1 GENERAL 1. SUMMARY: a. Section includes surface preparation and field application of paints and other coatings. 2. SUBMITTALS: a. Section 01330 - Submittal Procedures: Requirements
More informationPROJECT LOCATION BOZEMAN HIGH SCHOOL. ELECTRICAL ENGINEER: Van Dykken Engineering 37 Spanish Peak Drive Bozeman, MT Phone:
DRAWING INDEX GENERAL C. PROJECT COVER G-WING A/V IMPROVEMENTS.0 AREA PLAN ST FLOOR SOUTH. TYP. PROJECTOR MOUNTING & PROJECTOR NOTES.2 G-WING TECHNOLOGY CABINET ELEVATIONS.3 G-WING WIRING DIAGRAM.4 G-WING
More informationFAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014
FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services ADDENDUM #4 December 5, 2014 This Addendum is issued to provide answers to questions from potential bidders
More informationB. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.
McKee and Associates Architecture and Interior Design Addendum No. THREE Date: 12.11.17 Project: A NEW BUILDING FOR THE GREATER LIMESTONE COUNTY CHAMBER OF COMMERCE ATHENS, ALABAMA A3.1 GENERAL PROJECT
More informationA. Section includes surface preparation and the application of paint systems on the following exterior substrates: 1. Steel.
SECTION 099113 - EXTERIOR PAINTING PART 1 - GENERAL 1.1 SUMMARY A. Section includes surface preparation and the application of paint systems on the following exterior substrates: 1. Steel. B. Related Requirements:
More informationBid No. B14-02 Building 100 HVAC Improvements
Bid No. B14-02 Building 100 HVAC Improvements Addendum No. 1 This Addendum No. 1 sets forth modifications to portions of the bid and contract documents for the above-referenced work described as: Building
More informationADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC.
ADDENDUM NO. 2 PROJECT: OWNER: ENGINEER / ARCHITECT: PROJECT LOCATION: Saginaw County Community Mental Health Authority Germania Club Renovation Phase 2 Saginaw County Community Mental Health Authority
More informationEXTERIOR PAINTING
SECTION 099113 - EXTERIOR PAINTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationCielito Lindo de Tubac Home Owners Association PAINTING POLICIES AND PROCEDURES
Cielito Lindo de Tubac Home Owners Association PAINTING POLICIES AND PROCEDURES The CC&Rs for Cielito Lindo de Tubac HOA address exterior repainting only briefly under Article 3.1(A), (B) and (E). As this
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 099123 - INTERIOR PAINTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationAttached is Addendum No. 2 to SEPTA Sealed Bid APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House.
Dear Sir/Madam: Attached is Addendum No. 2 to SEPTA Sealed Bid 17-00222-APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House. The Bid due date and time is changed from Thursday, Nov.
More informationSECTION PAINTS AND COATINGS
SECTION 09 90 00 PAINTS AND COATINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Surface preparation. B. Field application of paints and other coatings. 1.2 RELATED SECTIONS A. Division 05 - Metal Fabrications.
More informationADDENDUM 1 and 2 September 29, 2017 Request for Proposals: Wi-Fi and Wireless Backhaul Replacement
Following are the questions submitted on or before September 29, 2017, in accordance with RFP specifications. Responses to questions, clarifications of material, or corrections are indicated in green after
More informationTEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION PLAQUE, SERVICE AWARD PUBLICATION
TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION TXDOT 080-78-36* AMENDED: NOVEMBER 2004** PLAQUE, SERVICE AWARD PUBLICATION This specification is a product of the Texas Department of Transportation
More informationSECTION PAINTING
SECTION 09900 PAINTING PART 1 - GENERAL 1.1 SECTION INCLUDES A. This Section includes surface preparation, painting, and finishing of new and existing wood, interior and exterior surfaces including the
More informationA. Section includes surface preparation and the application of paint systems on exterior substrates.
SECTION 09 91 13 - EXTERIOR PAINTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More information1. Labels: Do not paint over UL, FMG, or other code-required labels or equipment name, identification, performance rating, or nomenclature plates.
SECTION 09 9100 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationSPECIFICATIONS PROPOSAL & BID DOCUMENT
Cerro Gordo County Department of Public Health LEAD-BASED PAINT HAZARD CONTROL PROGRAM IALHB0628-16 SPECIFICATIONS PROPOSAL & BID DOCUMENT Property: 13 N Monroe Tenant s Relocating: Yes No Lead Based Paint
More informationITEM DESCRIPTION BIDDER CODE NO. UNIT COST UNIT COST 1 GALLON 5 GALLON
BID ON: PAINT AND SUPPLIES - AS NEED UNTIL 1/31/19 BID NO: 18-11 OPENED: FEBRUARY 20, 2018 @ 2:00PM 1 Oil Base Exterior House Paint Mobile Paint Mfg. 1408 $21.50 Acrylic Latex Exterior Gloss House Paint
More informationADDENDUM NUMBER ONE (1) For. Occoquan Regional Park Jean R. Packard Center 1608 Room Exhibit Fabrication & Installation
ADDENDUM NUMBER ONE (1) For Occoquan Regional Park Jean R. Packard Center 1608 Room Exhibit Fabrication & Installation Addendum Date: Thursday, May 4, 2017 GENERAL: A. This addendum is hereby made a part
More informationMatt Morgan Assistant Superintendent of Support Services. Kristine Johnston Director of Purchasing. Date: July 30, 2015
To: Matt Morgan Assistant Superintendent of Support Services From: Kristine Johnston Director of Purchasing Date: July 30, 2015 Re: Paint and Miscellaneous Supplies Annual Contract #15-06-4488 The following
More informationSYLVAN WAY LIBRARY FIRE DOORS REQUEST FOR BID
SYLVAN WAY LIBRARY FIRE DOORS REQUEST FOR BID Kitsap Regional Library is currently seeking quotes for replacement and installation of fire rated frames, doors and hardware at the Sylvan Way branch. There
More informationA. Section includes surface preparation and the application of paint systems on the following exterior substrates: 1. Steel and iron.
Farmington, Missouri Project Number M1801~01 PART 1 ~GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationPAINT, PUTTY, AND CAULKING MATERIALS FORM. Date. General Contractor. Painting Sub-Contractor. Project Number. Project Name.
SECTION 09902 PAINT, PUTTY, AND CAULKING MATERIALS FORM Date General Contractor Painting Sub-Contractor Project Number Project Name Project Address Paint, putty, and caulking materials as specified are
More informationBid No :01 Exterior Roynon Elementary & La Verne Heights (Alternate #1) SCOPE OF WORK
Part I. General 1.01 General Conditions SCOPE OF WORK A. The contractor shall provide all paint, labor, tools and supplies to perform a complete repaint of all exterior/interior surfaces of the building,
More informationAddendum #1 - Bid Package #
Addendum #1 - Bid Package #6929-08 Project Name: Lincoln Public Schools District Office 5901 O Street Lincoln, NE Project No.: 11065 Issued: September 18, 2012 This Addendum is issued by Hampton Construction
More informationSECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More information12560 W. Cedar Drive Lakewood, CO Barry Himmelman President
Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 16-BS-2260 ADDENDUM NUMBER FOUR January 8, 2016 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM
More informationB. Division-16 Basic Materials and Methods section apply to work specified in this section.
Section 16745 PREMISE CABLING SYSTEMS PART ONE GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification
More informationThe School District of Palm Beach County Project Name SDPBC Project No. SECTION ( ) SIGNAGE PART 1 GENERAL 1.1 RELATED DOCUMENTS
PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 10441 (10 14 00) SIGNAGE A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division-1 specification section,
More informationSECTION EXTERIOR PAINTING PART 1 - GENERAL
13414.01 EXTERIOR PAINTING 099113-1 SECTION 099113 - EXTERIOR PAINTING 1.1 SUMMARY PART 1 - GENERAL A. Section includes surface preparation and the application of paint systems on the following exterior
More informationCSI Section DMI Light Gage Structural Steel Framing Systems. Blocking Fire Rated Pre-cut (Proprietary) Furring Wall Preservative Treated
DMI Database CCF5IF9HGLPD-QB (4,88) $14,775.00 CSI Section 05400 DMI Light Gage Structural Steel Framing Systems Angle Framing Bridging Channel Flat Strapping Furring Clip Angle Soffit/Fascia/Deck Framing
More informationHousing and Neighborhood Services of Rock Hill SCOPE OF WORK BID TAB. Job # BID-CDBG #16
Housing and Neighborhood Services of Rock Hill SCOPE OF WORK BID TAB Job # BID-CDBG #16 Bid is to be turn-key, including all applicable code requirements, materials, labor, City Business License permits,
More informationITEM NO. DESCRIPTION BIDDER CODE NO. UNIT COST UNIT COST 1 GALLON 5 GALLON. 1 Oil Base Exterior House Paint Glidden Profess 2516 $22.
BID ON: PAINT AND SUPPLIES BID NO: 10-135 OPENED: DECEMBER 3, 2010 @ 2:00 PM 1 Oil Base Exterior House Paint Glidden Profess 2516 $22.00 Acrylic Latex Exterior Gloss House Paint 2 Super White Glidden Profess
More informationCLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017.
June 15, 2017 GS#108-281 Greene Hall Renovations University of Southern Mississippi Hattiesburg, Mississippi 00.910 ADDENDUM NO 1. This Addendum contains 6 pages and 21 pages of attachments for a total
More informationINSTALLATION INSTRUCTIONS FOR PLASCORE F5075 FRAME WALL
INSTALLATION INSTRUCTIONS FOR PLASCORE F5075 FRAME WALL The following information is provided by Plascore, Inc., as a general guideline for the installation of the F5075 Frame Wall System. This information
More informationGRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO
PAGE PROJECT NO. 0-0 0 0 0 0 0 DATE: PROJECT: GATEWAY STEM ATHLETICE FIELD ALTERATIONS GATEWAY STEM HIGH SCHOOL - ST. LOUIS PUBLIC SCHOOLS 0 MCRTEE AVENUE ST. LOUIS, MISSOURI 0 TO BID DOCUMENTS DATED DECEMBER,
More informationSECTION SIGNAGE
SECTION 10 14 00 SIGNAGE PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division-1 specification section, apply
More informationMontclair, NJ ADDENDUM NO. 1 Issue Date: May 15, 2017
Montclair, NJ 0704 ADDENDUM NO. Issue Date: May 5, 207 Request for Proposal # 294 Building 47 West Renovation- Phase 6a Number of Pages: 2 plus 5 sketches Date of Original Bidding Documents: April 26,
More informationSECTION PROJECT MANAGEMENT AND COORDINATION
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationAgenda. Interior Painting Exterior Painting Typical Problems Low VOC Paints
Painting 101 Agenda Interior Painting Exterior Painting Typical Problems Low VOC Paints Interior Painting Flat Requires less prep (spot patch & prime) Less durable Eggshell More durable than flat Requires
More informationSECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
SECTION 01 33 23 - SHOP DRAWINGS, PRODUCT DATA, AND PART 1 - GENERAL 1.1 SUMMARY A. Products include, but are not limited to, the following construction submittals: 1. Shop Drawings. 2. Product Data. 3.
More informationCHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO
CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO. 18-04 ADDENDUM NO. ONE DATE: September 07, 27 CLIENT / PROJECT: Chabot-Las Positas CCD Campus Master
More information1.01 NOTICE TO BIDDERS
ADDENDUM NO. 1 1.01 NOTICE TO BIDDERS A. Date: 15 March 2013 B. From: Bahr Vermeer and Haecker Architects, Ltd. C. To: Prospective Bidders. D. Project: Lexington Public Schools Lexington Middle School
More informationPRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB
SECTION 09 9123 - INTERIOR PAINTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationID0.1 PALO VERDE 8000 WEST US HIGHWAY 290 AUSTIN, TX SHEET INDEX: CONTACT INFORMATION: DISCLOSURES: DOCUMENT GENERAL NOTES:
CONTACT INFORMATION: SHEET INDEX: DISCLOSURES: DOCUMENT GENERAL NOTES: CLIENT ARDENT RESIDENTIAL 5453 BURNET RD. SUITE 203 AUSTIN, TX 78756 ARCHITECT DAVIES COLLABORATIVE 5453 BURNET RD. SUITE 202 AUSTIN,
More informationTELEPHONE: (215) Addendum No. 1
THE SCHOOL DISTRICT OF PHILADELPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, Third Floor - Suite 371 Philadelphia, PA 19130-4015 TELEPHONE: (215) 400-4730 Addendum No.
More informationTG Glazing Design-Build
TG08.1 - Glazing Design-Build Question No. 0040 0041 0042 0043 Submission Date Question 7.14.2011 Is it acceptable to use 304 stainless in lieu of 316 where the material will be painted per 09 97 15? 7.14.2011
More informationHOENER ASSOCIATES INC. ARCHITECTS
HOENER ASSOCIATES INC. ARCHITECTS BRUCE D. DELL MARK REUTHER ADDENDUM NO. 1 PROJECT 15-22C RENOVATION AND SITE WORK AT: BUILDING B DDRB OF ST. CHARLES DEVELOPMENT DISABILITIES RESOURCE BOARD ST. CHARLES,
More informationFebruary 18, Re: Zephyr Lakes Amenity Center Zephyrhills, Florida
February 18, 2019 Re: Zephyr Lakes Amenity Center Zephyrhills, Florida These are the responses to the RFIs received by 2:00 PM on Monday, February 11, 2019. All items that are not answered in the following
More informationApproval Process: Houses Painted without approved colors/arb:
Approval Process: When you are ready to repaint your house from the original paint color selected by Kennedy Homes, you must still submit an ARB Form to the management community or the Board naming the
More informationAmendment to Bid #1 Minor Office Renovations B /30/2018 No
Project Name: Bid #: Extend Bid Opening Date and Time: Public Construction Bond Required: Pre-Bid Meeting (mandatory): Procurement Services Drive, Columbia, SC 0 Phone: 0-0-0 Web: www.riverbanks.org/procurement
More informationINDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS:
INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS: 013300 SUBMITTAL PROCEDURES 018116 CONSTRUCTION WASTE MANAGEMENT DIVISION 2 EXISTING CONDITIONS: 023000 EARTHWORK
More informationPainting Lesson Two: Choosing the Right Paint. Facilitator Guide
Painting Lesson Two: Choosing the Right Paint Facilitator Guide Building Basics was paid for under an EL Civics grant from the U. S. Department of Education administered by the Virginia Department of Education.
More informationADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS
ADDENDUM NO. TWO To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS Prepared By: ARCHITECT Bhide & Hall Architects, P.A. 1329-C Kingsley
More informationSt. Monica Food Pantry
St. Monica Food Pantry 26 5113-1 ELECTRICAL WORK DIVISION 26 SECTION 265113 INTERIOR LIGHTING FIXTURES PART 1. GENERAL 1.1 WORK INCLUDES A. Extent, location, and details of interior lighting fixture work
More informationMINUTES OF MEETING. The following Questions were asked and answers were provided accordingly:
MINUTES OF MEETING Meeting Date : July 15, 2014 Place : Greenwood Shop Main Conference Room Contract Title : Supply of Reworked T1 Trip Switch Brackets Proposal No. : T31BG14139 Present : TTC - A. Mckay
More informationJEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia
BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners
More informationMerrick Pet Care New Distribution Center Hereford, Texas
Merrick Pet Care New Distribution Center Hereford, Texas DATE: March 16, 2015 ARCHITECTURAL/ELECTRICAL ADDENDUM #6 FROM: TO: PROJECT: Lavin Associates, Architects Plan Holders of Record Merrick Pet Care,
More informationADDENDUM NO. 1 November 10, 2016
COUER D ALENE CITY HALL PROJECT NO. 2016-009 REMODEL AND ADDITION COEUR D ALENE, IDAHO ADDENDUM NO. 1 November 10, 2016 This addendum is hereby incorporated into and is an integral part of the bidding
More informationA. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationSERIES 300 SINGLE HUNG WITH FIN WINDOW INSTALLATION
IMPORTANT INFORMATION: WHETHER IT BE LOCATION OR INSTALLATION TYPE, NOT ALL WINDOW TYPES CAN BE INSTALLED IN ALL AREAS OR WALL CONDITIONS. CONSULT YOUR LOCAL BUILDING CODE DEPARTMENT FOR ANY REGULATIONS
More information(Full legal name of business submitting the offer)
Procurement Services Addendum # 1 Proposal Request Date Printed Date Issued Procurement Officer Phone E-Mail Address 18-CMG-B-012 April 16, 2018 April 16, 2018 Raymond Jenkins 843-566-8826 raymond_jenkins@
More informationA. This Section includes surface preparation and the application of paint systems on the following substrates:
SECTION 09900 - PAINTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply
More informationREQUEST FOR QUOTATION INVITATION
REQUEST FOR QUOTATION INVITATION DATE: July 15, 2010 DPS: REQUIREMENT: SUBJECT: Patricia Farina DPS Contract Administrator Email: Patricia.Farina@cityofchicago.org Telephone: 312-744-7660 Silver Halide
More informationSection Meetings Section Material and Equipment. None Required
January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental
More informationSECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.
More informationINVITATION TO TENDER ITT No. PS FIRE HALL 5 + HOUSING CONSTRUCTION. ADDENDUM No. 2 and AMENDMENT No. 2
FINANCE, RISK AND BUSINESS PLANNING Supply Chain Management May 17, 2016 INVITATION TO TENDER ITT No. PS20160468 FIRE HALL 5 + HOUSING CONSTRUCTION ADDENDUM No. 2 and AMENDMENT No. 2 RE: Various additions
More informationVERTICAL STILE ABOVE HORIZONTAL TRIM VERTICAL STILE BELOW COVE BASE ADHESIVE. 1" [25.4mm] BASE DETAIL
Please Read All sheet will be provided in stock sizes for field cutting. All trims will be provided in 8-0 stock lengths for field cutting. CEILING TRIM 1" [25.4mm] Acrovyn Interiors vinyl acrylic wall
More informationTELEPHONE: (215) Addendum No Cooling Plant Replacement SDP Contracts No. B-080C, B-081C and B-082 of 2017/18
THE SCHOOL DISTRICT OF PHILADELPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, 3 rd Floor Suite 371 Philadelphia, PA 19130 TELEPHONE: (215) 400-4730 Addendum No. 001 Subject:
More informationEMMEGI ARCHITECTURAL FENCING MASTER SPECIFICATION SECTION METAL FENCING, GATES & RAILING SYSTEM PART 1 GENERAL
EMMEGI ARCHITECTURAL FENCING MASTER SPECIFICATION SECTION 05720 METAL FENCING, GATES & RAILING SYSTEM PART 1 GENERAL EMMEGI ARCHITECTURAL FENCING is a high quality steel fencing system comprised of a hybrid
More informationMTJ Outdoor Baggage Claim
MTJ Outdoor Baggage Claim 915 S. Tenth St. Montrose, CO 8101 p: (970) 29-1980 f: (970) 797-6811 www.motleyarc.com Drawings and Dimensions 1. ATTENTION ALL USERS OF THESE DRAWINGS, GENERAL CONTRACTORS,
More informationB. Samples: For each exposed product and for each color and texture specified.
SECTION 095113 -ACOUSTICAL PANEL CEILINGS PART 1- GENERAL 1.1 SUMMARY Section includes acoustical panels and exposed suspension systems for ceilings. Work is limited to modification of existing acoustical
More informationADDENDUM No. 4 Page 1 of 8 (includes attachment)
ADDENDUM No. 4 Page 1 of 8 (includes attachment) Date Issued: November 27, 2017 Project: TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J
More informationPlease read through the entire document before starting your installation process to better understand what is required.
1 P a g e How s It Hanging? Step-by-Step Guide for Hanging your Wallpaper Walls Republic offers a richer and wider selection of designs, textures and colours than ever before found in the wallpaper world,
More informationSpecifications: Other: sign in sheet
To: All Vendors Bidding on The College of New Jersey Nursing Simulation Lab Fit-Out Project From: Roselle Horodeski Finance & Business Services Date: July 29, 2015 ADDENDUM NO. 1 ISSUE DATE: July 29, 2015
More informationSECTION SUBMITTAL PROCEDURES
SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationNovember 30, Courtney Wilton Portland Public Schools 501 North Dixon Portland, OR 97227
November 30, 2016 Courtney Wilton Portland Public Schools 501 North Dixon Portland, OR 97227 Via email: Regarding: cwilton@pps.net Lead Paint Condition Assessment Abernethy Elementary School 2421 SE Orange
More informationSERIES 300 SINGLE HUNG WINDOW INSTALLATION
IMPORTANT INFORMATION: WHETHER IT BE LOCATION OR INSTALLATION TYPE, NOT ALL WINDOW TYPES CAN BE INSTALLED IN ALL AREAS OR WALL CONDITIONS. CONSULT YOUR LOCAL BUILDING CODE DEPARTMENT FOR ANY REGULATIONS
More informationGENERAL INSTALLATION GUIDE: WARRANTY: PRODUCT INFORMATION T F
GENERAL INSTALLATION GUIDE: Unless otherwise indicated, all Seven Oaks M.U. Architectural Products materials are to be used for decorative purposes only. All products must be installed using ample amount
More informationIf the address on this form is different than the address of the building, submit a written explanation.
ILLINOIS DEPARTMENT OF PUBLIC HEALTH AHERA THREE YEAR REINSPECTION ASBESTOS ABATEMENT PROGRAM SCHOOL INFORMATION FORM SECTION I NAME OF SCHOOL DISTRICT: CHICAGO SCHOOL DIST 299 SCHOOL ID NUMBER: 14-016-2990-2311
More informationRENOVATION TO STUDENT SERVICES/HOUSING FROM HOSPITAL DAKOTA STATE UNIVERSITY MADISON, SOUTH DAKOTA
RENOVATION TO STUDENT SERVICES/HOUSING FROM HOSPITAL DAKOTA STATE UNIVERSITY MADISON, SOUTH DAKOTA KOCH HAZARD ARCHITECTS ADDENDUM DATE:. SCOPE OF THIS ADDENDUM: The following becomes a part of the original
More informationACORNWIRE.COM MESH PARTITIONS DIVISION 10 - SPECIALTIES WIRE MESH PARTITION FOLDING GATE
acorn WIRE ACORNWIRE.COM MESH PARTITIONS DIVISION 10 - SPECIALTIES 10 22 13 WIRE MESH PARTITION 10 22 16 FOLDING GATE GUIDE Page 4 / 5 No. 130A All wire type for normal industrial use. 7, 8, 9, 10 and
More informationname (h) phone (m) phone time zone door style* *required finish* *required designer
name (h) phone (m) phone email guide time zone door style* finish* designer Eastern *required *required Central Mountain Pacific before you begin video Please be sure to view the CliqStudios How to Measure
More informationADDENDUM #1. April 29, 2009
April 29, 2009 Re: HACC, Central Pennsylvania s Community College Midtown 1 CCTA Phase 2 Solicitation # 09-17 From: Eastern pcm, LLC Construction Manager HACC 212 Locust Street, Suite 604 Harrisburg, PA
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 2
SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 2 PROJECT: June Jordan School for Equity DATE: April 17, 2017 Security Cameras & Science Classrooms Improvements Project
More informationCONVEYANCE PIPELINE AND PUMP STATION
SCOPE OF WORK CONVEYANCE PIPELINE AND PUMP STATION The purpose of this scope of work is to provide engineering services to revise and complete the design of the RUWAP pipeline and 5th Avenue Pump Station
More informationSECTION WOOD DOORS
SECTION 08211 WOOD DOORS Notice to Vendors: CANV prefers to purchase products that contain tropical wood only if they are certified according to the guidelines of the Forest Stewardship Council (FSC).
More informationAnswer: Only to ChurchWoods, LLC.
ADDENDUM ADDENDUM NO.: 3 DATE: 06/27/16 PROJECT: CHW ChurchWoods PROJECT ADDRESS: 4130 Old Post Road Charlestown, RI TO: All Bidders of Record: This Addendum forms a part of and modifies the bidding requirements
More informationCITY OF PITTSBURG ENGINEERING DEPARTMENT CONTRACT NO A WATER TREATEMENT PLANT CAPITAL IMPROVEMENTS PHASE 1A ADDENDUM #1 FENCE AND DITCH AUGUST
CITY OF PITTSBURG ENGINEERING DEPARTMENT CONTRACT NO. 2012-16A WATER TREATEMENT PLANT CAPITAL IMPROVEMENTS PHASE 1A ADDENDUM #1 FENCE AND DITCH AUGUST 2014 CHAIN LINK FENCE SPECIFICATIONS Chain link fence,
More informationSustainably made in the United States. Doors Make the Difference. stilechoice.com
Sustainably made in the United States Doors Make the Difference stilechoice.com Just What You Want Let s cut to the chase: At IHS Door Company we do one thing, and we do it really well. We make MDF stile
More informationState College of Florida Building 11_Music Interior Painting
State College of Florida Building 11_Music Interior Painting Project No. 2-18-1-20 IFB # FAC2018-3 March 16, 2018 Scope of Work The scope is an important key to a successful job and describes the tasks
More informationADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.
ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO. PS 061 SEVEN SPRINGS WASTEWATER TREATMENT FACILITY IMPROVEMENTS PASCO COUNTY,
More informationSECTION SUBMITTAL PROCEDURES
SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide submittals in accordance with the General Conditions as modified by the Supplementary Conditions,
More informationArchitectural Design Process
Architectural Design Process Custom Residential A. Schematic Design Phase Pre-Design Meeting Site Analysis Site Survey Conceptual Design & Project Scope Design Program Guideline Project Team Formation
More informationChapter 22 - Cabinets & Vanities
Chapter 22 - Cabinets & Vanities Contents Chapter 22 - Cabinets & Vanities... 22-1 Timing & Prerequisites... 22-2 Cabinets... 22-3 Cabinet Layout... 22-3 Wall Cabinets... 22-4 Assemble the Wall Units...
More informationCall your Lumber Liquidators Store #233, at (707) to pay for your materials.
Call your Lumber Liquidators Store #233, at (707) 324-3630 to pay for your materials. S.W. Contractors CA lic #879074 822 Alhambra Ave Unit #1 Martinez, CA 94553 Phone (510) 436-7211 Fax (925) 229-8800
More information