Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah

Size: px
Start display at page:

Download "Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah"

Transcription

1 Sediment Transport Workshop, Utah State University, 1 August 2017 Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah I. Goals for learning and discussion: A. Learn to use HEC-RAS, by building a working steady state model B. Learn the relation among model inputs, model-derived outputs, and actual field conditions C. After this session, students will be able to construct a basic HEC model and will be ready to learn how to tackle more complicated modeling scenarios. II. Activity: After eating lunch, we will walk along the channel and identify the locations of channel crosssections and bed material counts. Your observations will be useful when you return to the class room and build the model. Background: Summit Creek is a small tributary of the Bear River that drains part of the Bear River Range. Mack Park is a 13-ac tract that was deeded to Smithfield city in Originally, the area was referred to as the Grove because of the trees, willows, and shrubbery (Smithfield Historical Society, 2001). The map of the park from 1934 depicted a heavily wooded area around the stream. The stream was shown approximately at the same location as it is today. The present landscape of the park was created in the late 1970s following numerous complaints about rowdy parties and misuse. Diseased and dead trees were removed. Unsightly underbrush and willows were cleared away from the creek banks. The city crews graded some of the areas and riprapped the banks of the creek. New trees and grass were planted where needed. The completed project cost about $10,000 (Smithfield Historical Society, 2001). Comparison of the location of today s channel with that of 1934 indicates that some degree of realignment occurred during these construction activities. Stream flow The USGS operated gaging station between 1961 and 1979 approximately 4 mi upstream from the park (Fig. 1) where the drainage basin area is 11.6 mi 2. The mean annual flow for this period was 19.8 ft 3 /s and varied over a three-fold range between 8.1 and 29.1 ft 3 /s (Fig. 2). The largest flood of the gaging period was 302 ft 3 /s and occurred May 23, This flood was approximately 15 times larger than the mean annual flow. The 2-yr recurrence flood is approximately 145 ft 3 /s, which is approximately 7 times larger than the mean annual flow. Flood frequency analysis indicates that the 1.5-yr recurrence flood at the gage is approximately 76 ft 3 /s and that the 2-yr recurrence flood is 149 ft 3 /s (Fig. 3).

2 Stream flow through the park has two origins: natural flood flows generated from the watershed and base flows derived from irrigation return flows from canals. There are three diversions of stream flow between the USGS gage and Mack Park (Photo 1), and most base flows are diverted from the stream. The base flows that you observe are primarily derived from water that is not diverted and flow that enters the stream from the Logan, Hyde Park, and Smithfield Canal originally diverted from the Logan River. In contrast, flood flows are typically derived from the Summit Creek watershed, because they occur at a time when diversions are minimal. There is no regular measurement of stream flow in the park. We have developed a stage-discharge rating relation. Over a stage range of approximately 1.8 ft, discharge varies between approximately 0 and 129 ft 3 /s (Fig. 4). Geomorphology The water surface slope through the park is between and , depending on the stage at which measurements are made (Fig. 5). The reach within 30 m upstream from the lower concrete bridge is the steepest part of the profile. The bed material of the channel is highly variable, because many blocks or rip rap have now fallen into the channel and contribute to hydraulic roughness. Thus, we completed two bed material counts (Fig. 6) that were isolated to specific bars in the park, located in Figure 7. In addition, we completed one surface material count that averaged bed material of the entire channel between cross-sections 8 and 18, one surface material count from Canyon Road to Middle Bridge (Fig.7), one surface material count that averaged the reach between the middle and downstream bridges, and one count that characterized the average bed material size upstream from Canyon Road. We also completed one subsurface bed material count at gravel bar 2 in the park. Since bed material size, bed material organization, bank material, and plan form all contribute to hydraulic roughness, you should observe channel conditions as you walk around. Examine the example cross-sections shown in Figure 8 and note the edges of the active bed, bank material, and the sloping grassy surfaces of the park. You will need to identify the edges of the bank when building your HEC-RAS model and so your field notes will be useful later today. HEC-RAS modeling exercise When you return to the classroom, you are to build a HEC-RAS model of Summit Creek between cross-sections 1 and 18. The cross-section data, including the distance between cross-sections, are included in an Excel file.

3 Summit Creek, Smithfield, Utah Photo 1. Diversion on Summit Creek, about 0.7miles upstream from Mack Park. July 8, 2008 (~ 2.62 ft 3 /s) June 8, 2009 (~ 130 ft 3 /s) August 4, 2009 Photo 2. Stream character upstream from Mack Park

4 Summit Creek, Smithfield, Utah June 8, 2009 (~ 130 ft 3 /s) August 4, 2009 July 8, 2008 (~ 2.62 ft 3 /s) Photo 3. Stream character in Mack Park. July 8, 2008 (~ 2.62 ft 3 /s) August 4, 2009 Photo 4. Change of river bed in Mack Park.

5

6

7

8

9

10

11

12 Figure 8 Example cross-sections, Summit Creek at Mack Park 99 Summit Creek XS-1 Elevation, in meters, above an arbitrary datum Distance from left endpoint, in meters, from an arbitrary datum a) 99 Summit Creek XS-2 Elevation, in meters, above an arbitrary datum Distance from left endpoint, in meters, from an arbitrary datum b)

13 100 Summit Creek XS-11 Elevation, in meters, above an arbitrary datum Distance from left endpoint, in meters, from an arbitrary datum c) 100 Summit Creek XS-12 Elevation, in meters, above an arbitrary datum Distance from left endpoint, in meters, from an arbitrary datum d)

14 101 Summit Creek XS-17 Elevation, in meters, above an arbitrary datum Distance from left endpoint, in meters, from an arbitrary datum e) 101 Summit Creek XS-18 Elevation, in meters, above an arbitrary datum Distance from left endpoint, in meters, from an arbitrary datum f)

15 Day 2 RAS Exercise - Summit Creek The goal of this exercise is to construct and calibrate a working RAS model of the Mack Park section of Summit Creek. Then you will use it to estimate water surface elevations for a wide range of discharges. These instructions assume a basic knowledge of HEC- RAS. Step 1 CREATE A NEW PROJECT - Create a new project by clicking <File> <New Project> - Choose an existing folder or create a new one by clicking the <Create Folder> button - Enter a Title and a File Name and hit <OK> The program will create the new project in English units. - Click <options> <unit system> and select SI units for our metric data. Step 2 ENTER AND EDIT GEOMETRIC DATA - Begin entering geometry data by clicking <Edit> <Geometric Data> - Then, in the new window, click <File> <New Geometry Data> - Enter a Title and click <OK> - In the empty geometry data window, click the River Reach tool and draw in a simple channel, ending with a double click: a straight line will do. When you double click, a box will appear. Enter a River name and a Reach name. Choose something creative like Summit Creek for the river name and Mack Park for the reach name, then click OK. - Next, click the Cross Section tool and choose <Options> <Add a new Cross Section> - In the box that appears, enter the river station for the section that will be entered. Remember that HEC requires that the lowest river station number be at the downstream end and that station numbers increase in the upstream direction. The input data for your cross sections are contained in the posted Excel spreadsheet. Data includes; station and elevation points (cross section data from left to right when looking downstream), bank stations (left and right), and downstream reach lengths for the left overbank (LOB), channel, and right overbank (ROB). You will also need to guess at a Manning s n for your channel and overbank areas. You will adjust the n value later in the exercise, when you calibrate the model. Contraction and expansion coefficients can be set to 0.1 and 0.3 respectively. After entering your cross section data, click <apply data>, and the plot of your data will be updated with your changes. When you are satisfied with your cross section, begin entering data for the next section by clicking <options> <Add new Cross Section>, and repeat the procedure outlined above. When all section data has been entered, close the cross section editor. You should see that the sections have been added to the schematic plot of the river. Save the geometry data by clicking <File> <Save Geometry Data> and giving it a name. Close the geometric data window

16 Step 3 ENTER AND EDIT STEADY FLOW DATA - Begin entering steady flow data by clicking <edit> <Steady Flow Data>. - Enter the number of profiles (discharges in cfs) that are to be entered. To begin with, choose 3 profiles. - Enter the 3 calibration discharges of cms ( cfs), cms (38.5 cfs), and cms (2.62 cfs), into the table by the station number. - Enter the profile names by clicking <options> <edit profile names> and entering a descriptive name for each profile, then click OK. - Now click the Reach Boundary Conditions button. We will use a known water surface boundary condition, so click that button and enter the known water surfaces for the downstream section into the box for each of our 3 calibration discharges, and click OK. Click OK to close the boundary condition editor. - Next, we will enter the surveyed water surface elevations from the Excel spreadsheet. While still working in the steady flow data editor, click <Options> <Observed WS>. A new box will open that allows water surface elevations to be entered for each river station. Enter the data into the proper row and click OK. Save the steady flow data by clicking <File> <Save Flow Data>, entering a name for the steady flow data, and clicking OK. Close the steady flow data editor. Your HEC model is now ready to run. Step 4 RUN THE MODEL To run the model, click <Run> <Steady Flow Analysis>. In the steady flow analysis window, make sure the subcritical radio button is selected, and then click the large COMPUTE button. If everything works, you should see a quick-moving blue computation bar and then the program will show you a short message about the model run. Click the Close button. The model run is now complete. You can examine your results in many ways. Begin by clicking on the tool buttons for View cross sections and View profiles. In these windows, click <options> <variables>, and turn on the observed water surface elevations by clicking the appropriate box. Take a look at the long profile and several cross sections and compare your water surface elevations to the surveyed elevations. How well do your computed water surface elevations match the surveys?? Do you need to calibrate? Step 5 CALIBRATE YOUR MODEL For each of the flows of 2.62 ft 3 /s, 38.5 ft 3 /s, and 129 ft 3 /s, compare your predicted water surface slope with the actual water surface measured in the field. To calibrate your model, you can vary n values to obtain better agreement between the computed and the surveyed WSEL. Increasing n values will raise the computed water surface: decreasing n will lower it. Try to adjust the n values to get your modeled values to match the surveys. You can do this one section at a time, using different values for n at each section, or you can use the same value for all sections. We will discuss the relative merits of each method in class. When you are satisfied with your model, make sure your geometry file is saved. You can add additional discharges to the model by adding more profiles to the steady flow editor and specifying a discharge. We will also show you another roughness method. At this point, we will get the group together and discuss your results.

17 HOMEWORK (I) Determine the capacity of the channel before flows inundate areas used by the public. Using the flood frequency plot, determine the frequency of this inundation. (II) With your calibrated RAS model, extract an output table that includes shear stress in the channel (Shear Chan). RAS will report values for each section for each of the three flows. You also have grain size information in Figure 6. The critical Shields Number * c c ( s 1) gd can be used to estimate the onset of sediment motion. If one uses the median size of the gravel portion of the surface grain size for each bar, a reasonable value of critical Shields Number is * c 0.03 You have all the pieces. Estimate the discharge at which sediment begins moving on the two bars. (s = ρ s /ρ = 2.65; ρ = 1,000 kg/m 3, and g = 9.81 m/s 2 ). Make sure you have RAS report shear in N/m 2 ). We will discuss the results in the morning. [Spoiler alert: you are unlikely to find a definitive answer to this problem!]

CE 365K Exercise 2: HEC-RAS Modeling Spring 2014 Hydraulic Engineering Design

CE 365K Exercise 2: HEC-RAS Modeling Spring 2014 Hydraulic Engineering Design CE 365K Exercise 2: HEC-RAS Modeling Spring 2014 Hydraulic Engineering Design This exercise was prepared by Fernando R. Salas and David R. Maidment Introduction In this exercise, we will learn how to setup

More information

The Basics. HECRAS Basis Input. Geometry Data - the basics. Geometry Data. Flow Data. Perform Hydraulic Computations. Viewing the Output

The Basics. HECRAS Basis Input. Geometry Data - the basics. Geometry Data. Flow Data. Perform Hydraulic Computations. Viewing the Output The Basics HECRAS Basis Input Geometry Data. Flow Data. Perform Hydraulic Computations by G. Parodi WRS ITC The Netherlands Viewing the Output ITC Faculty of Geo-Information Science and Earth Observation

More information

Example Application C H A P T E R 4. Contents

Example Application C H A P T E R 4. Contents C H A P T E R 4 Example Application This chapter provides an example application of how to perform steady flow water surface profile calculations with HEC-RAS. The user is taken through a step-by-step

More information

Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections

Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections v. 9.1 WMS 9.1 Tutorial Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections Modify cross sections in an HEC-RAS model to use surveyed cross section data Objectives Build a basic HEC-RAS

More information

Floodplain Modeling 101. Presentation Goals

Floodplain Modeling 101. Presentation Goals Floodplain Modeling 101 Presenter: Joseph L. Miller, P.E., CFM 2016 INAFSM Conference Presentation Goals Introduction to Indiana s and FEMA s floodplain modeling technical requirements for riverine modeling

More information

Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections

Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections WMS 10.1 Tutorial Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections Modify cross sections in an HEC-RAS model to use surveyed cross section data v. 10.1 Objectives Build a basic HEC-RAS

More information

Stream Design: From GEOPAK to HEC-Ras

Stream Design: From GEOPAK to HEC-Ras 10 Stream Design: From GEOPAK to HEC-Ras OBJECTIVES Provide you with a general understanding of GEOPAK Cross Section Reports and their capability to generate geometric information for the HecRas program.

More information

Iowa Bridge Sensor Demonstration Project Phase I and Phase II Executive Summary Report. Floodplain Management Services Silver Jackets Pilot Study

Iowa Bridge Sensor Demonstration Project Phase I and Phase II Executive Summary Report. Floodplain Management Services Silver Jackets Pilot Study Iowa Bridge Sensor Demonstration Project Phase I and Phase II Executive Summary Report Floodplain Management Services Silver Jackets Pilot Study Final Report AUGUST 2016 Iowa Bridge Sensor Demonstration

More information

APPENDIX I FLOODPLAIN ANALYSIS

APPENDIX I FLOODPLAIN ANALYSIS APPENDIX I FLOODPLAIN ANALYSIS TECHNICAL MEMORANDUM Date: June 11, 2014 To: Bibiana Alvarez and Ryan Lee Sawyer, Analytical Environmental Services From: Melanie Carr, MS, PE, Tarick Abu- Aly, MS, PE, Rafael

More information

GEO-SLOPE International Ltd, Calgary, Alberta, Canada Relief Well Spacing

GEO-SLOPE International Ltd, Calgary, Alberta, Canada   Relief Well Spacing 1 Introduction Relief Well Spacing Relief wells are commonly installed on the downstream side of an earth dam to control the seepage and pore-pressures (e.g. levee; Figure 1). A key design requirement

More information

North Carolina No-Rise Guidance Document

North Carolina No-Rise Guidance Document North Carolina No-Rise Guidance Document June 4, 2015 Atlanta, GA Dan Brubaker, PE, CFM NFIP Engineer (919) 825-2300 Dan.Brubaker@ncdps.gov Purpose Provide guidance for No-Rise preparation Engineers Provide

More information

URBAN DRAINAGE AND FLOOD CONTROL DISTRICT

URBAN DRAINAGE AND FLOOD CONTROL DISTRICT URBAN DRAINAGE AND FLOOD CONTROL DISTRICT Digital Flood Hazard Area Delineation (DFHAD) Guidelines July 2009 Prepared by 720 South Colorado Boulevard Suite 410 S Denver, Colorado 80246 phone (303) 757-3655

More information

2.5 Design of Channels

2.5 Design of Channels 2.6 Design of Open Channels Open channels have uses in urban stormwater drainage urban sanitary-sewer systems irrigation delivery systems In the next few lectures, we'll discuss the design procedure for

More information

Topographic Maps. Contour Lines

Topographic Maps. Contour Lines Topographic Maps Our first task today will consist of locating ourselves with the help of a topographic map. GPS units that can tell you the location of any Dunkin' Donuts within a five mile radius. Paper

More information

3 Table of Contents. Introduction. Installing and Activating... 8 Getting Updates Basic Working Procedures

3 Table of Contents. Introduction. Installing and Activating... 8 Getting Updates Basic Working Procedures User's Guide 3 Table of Contents 1. Introduction 5 1.1 Installing and Activating... 8 1.2 Getting Updates... 9 2. 11 2.1 What To Do First... 13 2.2 Starting a New Project... 14 2.3 Setting Up Your Model...

More information

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges 50.24 Culverts, Bridges and Culvert Bridges Type, Size and Location (T, S & L) Plans shall be required for all Bridges, Culvert Bridges and Culverts of eight-foot (8') clear span or greater as follows:

More information

FLOOD ESTIMATE FROM POSSIBLE DAM BREAK SCENARIO OF SUN KOSI LAND SLIDE DAM, NEPAL. O. P. GUPTA Director Central Water Commission

FLOOD ESTIMATE FROM POSSIBLE DAM BREAK SCENARIO OF SUN KOSI LAND SLIDE DAM, NEPAL. O. P. GUPTA Director Central Water Commission FLOOD ESTIMATE FROM POSSIBLE DAM BREAK SCENARIO OF SUN KOSI LAND SLIDE DAM, NEPAL by O. P. GUPTA Director Central Water Commission Introduction Landslide dams are natural phenomenon that poses a major

More information

MAJOR GRADING PLAN CHECKLIST

MAJOR GRADING PLAN CHECKLIST MAJOR GRADING PLAN CHECKLIST PUBLIC WORKS DEPARTMENT / ENGINEERING DIVISION 8130 Allison Avenue, La Mesa, CA 91942 Phone: (619) 667-1166 Fax: (619) 667-1380 Grading plans shall address both rough grading

More information

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated

More information

Re: Survey of constructed cross section per Restoration Framework on Wind River, Fremont County, WY

Re: Survey of constructed cross section per Restoration Framework on Wind River, Fremont County, WY 1-11-17 LeClair Irrigation District 1418 Cowboy Lane Riverton, WY 82501 (307) 856-4018 Re: Survey of constructed cross section per Restoration Framework on Wind River, Fremont County, WY Dear Mr. Hoelzen,

More information

Loy Gulch, Paint Pony, East Fork Paint Pony LOMR

Loy Gulch, Paint Pony, East Fork Paint Pony LOMR Loy Gulch, Paint Pony, East Fork Paint Pony LOMR Woodland Park, CO Prepared by: Michael Baker International 165 S. Union Blvd, Suite 200 Lakewood, CO 80226 TABLE OF CONTENTS I. INTRODUCTION... 2 1.1 Purpose...

More information

APPENDIX E - FLOODPLAIN INFORMATION

APPENDIX E - FLOODPLAIN INFORMATION CITY OF WOODLAND PARK STORMWATER MASTER PLAN - Floodplain Information APPENDIX E - FLOODPLAIN INFORMATION E1 - Floodplain Information TABLE OF CONTENTS I. INTRODUCTION... 2 Loy Gulch, Paint Pony, East

More information

SCOUR: EVALUATION AND RIPRAP. John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

SCOUR: EVALUATION AND RIPRAP. John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch SCOUR: EVALUATION AND RIPRAP John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch IMPORTANCE OF SCOUR The most common cause of bridge failures is from floods scouring bed material from around

More information

COPYRIGHTED MATERIAL. Contours and Form DEFINITION

COPYRIGHTED MATERIAL. Contours and Form DEFINITION 1 DEFINITION A clear understanding of what a contour represents is fundamental to the grading process. Technically defined, a contour is an imaginary line that connects all points of equal elevation above

More information

List of Figures. List of Forms

List of Figures. List of Forms City of Columbia Engineering Regulations PART 1: SUBMISSION OF PLANS Table of Contents Paragraph Description Page No. 1.1 General 1-1 1.2 Engineer s Report 1-1 1.3 Plans 1-3 1.4 Revisions to Approved Plan

More information

Flood Hazard Area Delineation Guidelines MOSER & ASSOCIATES ENGINEERING ICON ENGINEERING URBAN DRAINAGE AND FLOOD CONTROL DISTRICT

Flood Hazard Area Delineation Guidelines MOSER & ASSOCIATES ENGINEERING ICON ENGINEERING URBAN DRAINAGE AND FLOOD CONTROL DISTRICT Flood Hazard Area Delineation Guidelines MOSER & ASSOCIATES ENGINEERING ICON ENGINEERING URBAN DRAINAGE AND FLOOD CONTROL DISTRICT Flood Hazard Area Delineation (FHAD) Guidelines Contents Section Page

More information

Floods On The Minnesota River Planning For St. Peter

Floods On The Minnesota River Planning For St. Peter Floods On The Minnesota River Planning For St. Peter Group Members Section: A B C D E In this lab, we will make a flood hazard map for the city of St. Peter. We will use the 100-year flood as the design

More information

RE: Engineered Riffle Concepts for Sodom Dam Removal Grade Control Elements

RE: Engineered Riffle Concepts for Sodom Dam Removal Grade Control Elements November 19, 2009 Ms. Melissa Jundt NOAA Fisheries Hydropower Division 1201 NE Lloyd Boulevard, Suite 1100 Portland, Oregon 97232 RE: Engineered Riffle Concepts for Sodom Dam Removal Grade Control Elements

More information

CHAPTER 11 SURVEY CADD

CHAPTER 11 SURVEY CADD CHAPTER 11 SURVEY CADD Chapter Contents Sec. 11.01 Sec. 11.02 Sec. 11.03 Sec. 11.04 Sec. 11.05 Sec. 11.06 Sec. 11.07 Sec. 11.08 Sec. 11.09 Sec. 11.10 General Description of Survey File Contents of Survey

More information

Date Requested, 200_ Work Order No. Funding source Name of project Project limits: Purpose of the project

Date Requested, 200_ Work Order No. Funding source Name of project Project limits: Purpose of the project Bureau of Engineering SURVEY DIVISION REQUEST FOR TOPOGRAPHIC SURVEY Date Requested, 200_ Work Order No. Funding source Name of project Project limits: Purpose of the project Caltrans involvement (must

More information

ENVI.2030L Topographic Maps and Profiles

ENVI.2030L Topographic Maps and Profiles Name ENVI.2030L Topographic Maps and Profiles I. Introduction A map is a miniature representation of a portion of the earth's surface as it appears from above. The environmental scientist uses maps as

More information

APPENDIX K DEPARTMENT OF PLANNING AND CODE ENFORCEMENT SUBDIVISION APPLICATION CENTER SUBMITTAL CHECKLIST

APPENDIX K DEPARTMENT OF PLANNING AND CODE ENFORCEMENT SUBDIVISION APPLICATION CENTER SUBMITTAL CHECKLIST VI-K -1 of 8 APPENDIX K DEPARTMENT OF PLANNING AND CODE ENFORCEMENT SUBDIVISION APPLICATION CENTER SUBMITTAL CHECKLIST Final Submittal Major Subdivision Project Name Subdivision Number Location (Street

More information

Digital Flood Hazard Area Delineation (DFHAD) Guidelines

Digital Flood Hazard Area Delineation (DFHAD) Guidelines Digital Flood Hazard Area Delineation (DFHAD) Guidelines Contents Section Page Acronyms and Abbreviations Abbreviations and Acronyms... iii Revise Descriptions... iv 1.0 Introduction and Purpose... 1 1.1

More information

Town of Westlake Construction Plans Review Checklist

Town of Westlake Construction Plans Review Checklist CONSTRUCTION PLANS CONTENTS All Drawings 24 x 36 Cover Sheet Final Plat Site Plan Demolition Plan Utility Plan Drainage Area Map and Calculations Paving Plan & Profile Sheets Storm Drain Plan & Profile

More information

Technical Memorandum ECO-7

Technical Memorandum ECO-7 To: Woody Frossard, TRWD From: Bob Brashear, CDM This document is released for the purpose of interim review under the authority of Robert Brashear, P.E., TX license 80771 on 21-Mar-2005. It is not to

More information

Sheet Metal OverviewChapter1:

Sheet Metal OverviewChapter1: Sheet Metal OverviewChapter1: Chapter 1 This chapter describes the terminology, design methods, and fundamental tools used in the design of sheet metal parts. Building upon these foundational elements

More information

Digital Letter of Map Change (DLOMC) Guidelines May 2010

Digital Letter of Map Change (DLOMC) Guidelines May 2010 Digital Letter of Map Change (DLOMC) Guidelines May 2010 Prepared for: Urban Drainage and Flood Control District 2450 West 26th Avenue, Suite 156B Denver, CO 80211 Prepared by: 8100 South Akron Street,

More information

Sheet Metal OverviewChapter1:

Sheet Metal OverviewChapter1: Sheet Metal OverviewChapter1: Chapter 1 This chapter describes the terminology, design methods, and fundamental tools used in the design of sheet metal parts. Building upon these foundational elements

More information

AutoCAD 2016 for Civil Engineering Applications

AutoCAD 2016 for Civil Engineering Applications Introduction to AutoCAD 2016 for Civil Engineering Applications Learning to use AutoCAD for Civil Engineering Projects Nighat Yasmin Ph.D. SDC P U B L I C AT I O N S Better Textbooks. Lower Prices. www.sdcpublications.com

More information

SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS

SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS 101 General 102 Submittal Requirements A. Initial Submittal B. Second Submittal 103 Plan Requirements A. Subdivisions B. Site Plans 104 Approval of

More information

Week 15. Mechanical Waves

Week 15. Mechanical Waves Chapter 15 Week 15. Mechanical Waves 15.1 Lecture - Mechanical Waves In this lesson, we will study mechanical waves in the form of a standing wave on a vibrating string. Because it is the last week of

More information

PART XIII: HYDRAULIC/ HYDROLOGY SURVEYS

PART XIII: HYDRAULIC/ HYDROLOGY SURVEYS PART XIII: HYDRAULIC/ HYDROLOGY SURVEYS 13.1 Purpose and Scope Hydraulic surveys are required for flow analysis to determine bridge and culvert design characteristics. A hydraulic survey is usually but

More information

RRR Design & Modeling with the FDOT Civil 3D State Kit

RRR Design & Modeling with the FDOT Civil 3D State Kit RRR Design & Modeling with the FDOT Civil 3D State Kit Mike Racca - CADD Applications Development Specialist Production Support Office CADD 605 Suwannee St - MS 40, Tallahassee, Florida 32399 Session Objectives:

More information

1. Working with Bathymetry

1. Working with Bathymetry 1. Working with Bathymetry The CMS setup for Shark River Inlet provides a succinct example for illustrating a number of methods and SMS tools that can be applied to most engineering projects. The area

More information

Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02

Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02 Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02 1. INTRODUCTION This standard is written to provide the professional surveyor (Surveyor) and the client with a guideline for producing

More information

TO: FROM SUBJECT: SRBA Jon Albright Technical Memorandum on Hydrologic Yields PROJECT: Sulphur River Basin Feasibility Study DATE: 08/26/2014 CC:

TO: FROM SUBJECT: SRBA Jon Albright Technical Memorandum on Hydrologic Yields PROJECT: Sulphur River Basin Feasibility Study DATE: 08/26/2014 CC: 593 Summerhill Rd Texarkana, Texas 7553 93-838-8533 fax 93-832-47 TO: FROM SUBJECT: PROJECT: SRBA Jon Albright Technical Memorandum on Hydrologic Yields Sulphur River Basin Feasibility Study DATE: 8/26/214

More information

PRE-LAB for: Introduction to Aerial Photographs and Topographic maps (Ch. 3)

PRE-LAB for: Introduction to Aerial Photographs and Topographic maps (Ch. 3) GEOLOGY 306 Laboratory Instructor: TERRY J. BOROUGHS NAME: PRE-LAB for: Introduction to Aerial Photographs and Topographic maps (Ch. 3) For this assignment you will require: a calculator and metric ruler.

More information

Terrain Modeling with ArcView GIS

Terrain Modeling with ArcView GIS What You Will Need: A Pentium class PC with 32 MB of RAM (minimum) and 100 MB of free hard drive space, ArcView GIS 3.1 or higher and WinZip or an equivalent program, and an Internet connection. Data and/or

More information

Basic Surveying. Kabul, Afghanistan February 2011

Basic Surveying. Kabul, Afghanistan February 2011 Basic Surveying Kabul, Afghanistan February 2011 1 This watershed rehabilitation and restoration training was prepared by the U.S. Department of Agriculture (USDA) team of Jon Fripp (Civil Engineer USDA/NRCS),

More information

Pilot Project Ross Valley Watershed Geomorphology GIS Database Final Report August 30, 2010

Pilot Project Ross Valley Watershed Geomorphology GIS Database Final Report August 30, 2010 Pilot Project Ross Valley Watershed Geomorphology GIS Database Final Report August 30, 2010 Prepared by: Gerhard Epke 2010 Watershed Intern (831) 332-1324 24 Bolinas Ave San Anselmo, CA 94960 Supervised

More information

Introduction to Aerial Photographs and Topographic maps (Chapter 3)

Introduction to Aerial Photographs and Topographic maps (Chapter 3) GEOLOGY 306 Laboratory Instructor: TERRY J. BOROUGHS NAME: Introduction to Aerial Photographs and Topographic maps (Chapter 3) For this assignment you will require: a calculator and metric ruler. Objectives:

More information

Survey Data and TOPO Checklist

Survey Data and TOPO Checklist Checklists Survey Data and TOPO Preliminary Plan Field Review Plans o Field Review Erosion Control Right-of-Way and Utility Meeting Plans Final Plan Field Review Plans Methods of Plan Markups Plan-in-Hand

More information

Information for File # RMM

Information for File # RMM Information for File # 3-4-RMM Applicant:, L.P. Corps Contact: Ryan Malterud Address: 8 Fifth Street East, St. Paul, Minnesota 56 E-Mail: Ryan.M.Malterud@usace.army.mil Phone: (65) 9-586 Primary County:

More information

SWAN LAKE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT 1

SWAN LAKE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT 1 SWAN LAKE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT 1 1. General Description Figure 1 provides a map of the Swan Lake Watershed. The watershed is characterized by two major parallel

More information

Basic Recording. Start --> Programs --> Panopto --> Panopto Recorder. Logging In

Basic Recording. Start --> Programs --> Panopto --> Panopto Recorder. Logging In Basic Recording Logging In Presenters are able to log into the Recorder with their credentials and record video, audio, PowerPoint presentations and also add Screen Capture functionality. NOTE: If using

More information

Comparison of Flow Characteristics at Rectangular and Trapezoidal Channel Junctions

Comparison of Flow Characteristics at Rectangular and Trapezoidal Channel Junctions Journal of Physics: Conference Series Comparison of Flow Characteristics at Rectangular and Channel Junctions To cite this article: Ajay Kumar Pandey and Rakesh Mishra 202 J. Phys.: Conf. Ser. 364 024

More information

Civil Engineering Hydraulics. Backwater Profile

Civil Engineering Hydraulics. Backwater Profile Civil Engineering Hydraulics God put me on this earth to accomplish a certain number of things. Right now I am so far behind that I will never die. Last class, we derived an expression for the change in

More information

MAPPING YOUR STREAM. TIME REQUIRED 50 minutes in Field 50 minutes in Classroom 50 minutes Homework

MAPPING YOUR STREAM. TIME REQUIRED 50 minutes in Field 50 minutes in Classroom 50 minutes Homework OUR MAPPING YOUR STREAM STREAM ACTIVITY SUMMARY Students will draft a cross-sectional profile of the stream and measure the velocity of the current. They will use both of these to calculate the discharge

More information

Presented By: Todd Ward Project Manager

Presented By: Todd Ward Project Manager Presented By: Todd Ward Project Manager Mailing Address All submittals for LOMRs and CLOMRs Harris County should be directed to Harris County Flood Control District. Submittals can be mailed or hand-delivered

More information

Moving Man Introduction Motion in 1 Direction

Moving Man Introduction Motion in 1 Direction Moving Man Introduction Motion in 1 Direction Go to http://www.colorado.edu/physics/phet and Click on Play with Sims On the left hand side, click physics, and find The Moving Man simulation (they re listed

More information

ENSC 470/894 Lab 3 Version 6.0 (Nov. 19, 2015)

ENSC 470/894 Lab 3 Version 6.0 (Nov. 19, 2015) ENSC 470/894 Lab 3 Version 6.0 (Nov. 19, 2015) Purpose The purpose of the lab is (i) To measure the spot size and profile of the He-Ne laser beam and a laser pointer laser beam. (ii) To create a beam expander

More information

Estimated Time Required to Complete: 45 minutes

Estimated Time Required to Complete: 45 minutes Estimated Time Required to Complete: 45 minutes This is the first in a series of incremental skill building exercises which explore sheet metal punch ifeatures. Subsequent exercises will address: placing

More information

Administered through the: Colorado Plateau Cooperative Ecosystem Studies Unit Cooperative Agreement Number P14AC00921

Administered through the: Colorado Plateau Cooperative Ecosystem Studies Unit Cooperative Agreement Number P14AC00921 Award Number: P14AC01154 Project Number: USUCP-74 CFDA #: 15.945 Park/NPS Unit: Big Bend National Park/Rio Grande Wild and Scenic River Title of Project: Monitoring geomorphic condition and sediment transport

More information

Profiling River Surface Velocities and Volume Flow Estmation with Bistatic UHF RiverSonde Radar

Profiling River Surface Velocities and Volume Flow Estmation with Bistatic UHF RiverSonde Radar Profiling River Surface Velocities and Volume Flow Estmation with Bistatic UHF RiverSonde Radar Don Barrick Ralph Cheng Cal Teague Jeff Gartner Pete Lilleboe U.S. Geological Survey CODAR Ocean Sensors,

More information

B-PERMIT PLAN CHECK MANUAL

B-PERMIT PLAN CHECK MANUAL B-PERMIT PLAN CHECK MANUAL 5. SEWER PLANS Sewer Plans are usually submitted in conjunction with Street Plans to meet the requirements of conditions imposed on a Planning or Zoning action. In some cases

More information

This Land Surveying course has been developed by. Failure & Damage Analysis, Inc.

This Land Surveying course has been developed by. Failure & Damage Analysis, Inc. This Land Surveying course has been developed by Failure & Damage Analysis, Inc. www.discountpdh.com www.pepdh.com Bridge Surveying SURVEYS Bridge surveying is necessary to locate a site, obtain information

More information

CONCEPT REVIEW GUIDELINES

CONCEPT REVIEW GUIDELINES Department of Planning & Community Development @ Jefferson Station 1526 E. Forrest Avenue Suite 100 East Point, GA 30344 404.270.7212 (Phone) 404.765.2784 (Fax) www.eastpointcity.org CONCEPT REVIEW GUIDELINES

More information

Authorized Agent: City of Manassas Check List Attached: Contact: Address: Phone Number: Fax Number: Developer s Name: Phone Number:

Authorized Agent: City of Manassas Check List Attached: Contact:   Address: Phone Number: Fax Number: Developer s Name: Phone Number: CITY OF MANASSAS DEPARTMENT OF COMMUNITY DEVELOPMENT DEVELOPMENT SERVICES DIVISION 9027 Center Street Room 201 Manassas, Virginia, 20110 Phone: 703-257-8278 Fax: 703-257-5831 Application Date: APPLICANT

More information

Appendix B. Argonaut-SL Principles of Operation

Appendix B. Argonaut-SL Principles of Operation Appendix B. Argonaut-SL Principles of Operation SonTek/YSI, Inc. This Argonaut-SL System Manual appendix provides an introduction to the operating principles of the SonTek/YSI Argonaut Side-Looking (SL)

More information

DESIGN OF IRRIGATION CHANNELS IN MOHAMMARA AKKAR MOHAFAZA

DESIGN OF IRRIGATION CHANNELS IN MOHAMMARA AKKAR MOHAFAZA DESIGN OF IRRIGATION CHANNELS IN MOHAMMARA AKKAR MOHAFAZA VOLUME 1 DETAILED DESIGN DRAWINGS JULY, 2017 X= 293500 Y=39500 X= 293000 X= 292500 X= 292000 X= 291500 X= 291000 X= 290500 PROPOSED IRRIGATION

More information

Existing and Design Profiles

Existing and Design Profiles NOTES Module 09 Existing and Design Profiles In this module, you learn how to work with profiles in AutoCAD Civil 3D. You create and modify profiles and profile views, edit profile geometry, and use styles

More information

Lab #4 Topographic Maps and Aerial Photographs

Lab #4 Topographic Maps and Aerial Photographs Lab #4 Topographic Maps and Aerial Photographs Purpose To familiarize you with using topographic maps. Visualizing the shape of landforms from topographic maps is an essential skill in geology. Proficiency

More information

BACKGROUND INFORMATION

BACKGROUND INFORMATION Build an Island INTRODUCTION For this assignment, you will be creating a topographic map and three-dimensional model of a fictional island that you have designed. You will start by exploring some basic

More information

Survey Aspects of Automated Machine Control. The Changing Role of the Construction Surveyor / Inspector/Grader

Survey Aspects of Automated Machine Control. The Changing Role of the Construction Surveyor / Inspector/Grader Survey Aspects of Automated Machine Control The Changing Role of the Construction Surveyor / Inspector/Grader Charlie Brown, PE, PLS NCDOT State Location & Surveys Engineer AASHTO TIG AMG Work Group The

More information

Introduction to Aerial Photographs and Topographic maps (Chapter 7, 9 th edition) or (chapter 3, 8 th edition)

Introduction to Aerial Photographs and Topographic maps (Chapter 7, 9 th edition) or (chapter 3, 8 th edition) GEOLOGY 306 Laboratory Instructor: TERRY J. BOROUGHS NAME: Introduction to Aerial Photographs and Topographic maps (Chapter 7, 9 th edition) or (chapter 3, 8 th edition) For this assignment you will require:

More information

Site Plan/Building Permit Review

Site Plan/Building Permit Review Part 6 Site Plan/Building Permit Review 1.6.01 When Site Plan Review Applies 1.6.02 Optional Pre- Application Site Plan/Building Permit Review (hereafter referred to as Site Plan Review) shall be required

More information

High Precision Positioning Unit 1: Accuracy, Precision, and Error Student Exercise

High Precision Positioning Unit 1: Accuracy, Precision, and Error Student Exercise High Precision Positioning Unit 1: Accuracy, Precision, and Error Student Exercise Ian Lauer and Ben Crosby (Idaho State University) This assignment follows the Unit 1 introductory presentation and lecture.

More information

CVE 372 HYDROMECHANICS OPEN CHANNEL FLOW II

CVE 372 HYDROMECHANICS OPEN CHANNEL FLOW II CVE 372 HYDROMECHANICS OPEN CHANNEL FLOW II Dr. Bertuğ Akıntuğ Department of Civil Engineering Middle East Technical University Northern Cyprus Campus CVE 372 Hydromechanics 1/68 Overview 3.4 Rapidly Varied

More information

Fall 2001 Whooping Crane Migrational Survey Protocol Implementation Report

Fall 2001 Whooping Crane Migrational Survey Protocol Implementation Report Fall 2001 Whooping Crane Migrational Survey Protocol Implementation Report Prepared by Executive Director s Office For Committee s of the Platte River Cooperative Agreement June 5, 2002 I. Introduction

More information

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360)

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 Email: cdd@ci.tumwater.wa.us WATER-SEWER-STREET-STORM (IN CITY) Submittal Checklist TUM - RCVD BY DATE STAMP APPLICANT INFORMATION

More information

Module 2: Mapping Topic 3 Content: Topographic Maps Presentation Notes. Topographic Maps

Module 2: Mapping Topic 3 Content: Topographic Maps Presentation Notes. Topographic Maps Topographic Maps 1 Take a few moments to study the map shown here of Isolation Peak, Colorado. What land features do you notice? Do you thinking hiking through this area would be easy? Did you see the

More information

Gradient and Rate of Change

Gradient and Rate of Change Name: 1. Base your answer(s) to the following question(s) on the topographic map shown below. Letters A, B, C, and D represent locations on Earth s surface. The symbol marks the highest elevation on Patty

More information

Analysis of Reference Tidal Channel Plan Form For the Montezuma Wetlands Restoration Project

Analysis of Reference Tidal Channel Plan Form For the Montezuma Wetlands Restoration Project Analysis of Reference Tidal Channel Plan Form For the Montezuma Wetlands Restoration Project Sarah Pearce, Geomorphologist Joshua N. Collins, Project Manager Contribution No. 80 May, 2004 ACKNOWLEDGEMENTS

More information

Advanced Excel. Table of Contents. Lesson 3 Solver

Advanced Excel. Table of Contents. Lesson 3 Solver Advanced Excel Lesson 3 Solver Pre-reqs/Technical Skills Office for Engineers Module Basic computer use Expectations Read lesson material Implement steps in software while reading through lesson material

More information

Town of Apex, North Carolina

Town of Apex, North Carolina POND DRAINAGE PLAN APPLICATION Town of Apex, North Carolina POND DRAINAGE PLAN APPLICATION: Applications are due by 12:00 pm on the first business day of each month. Please see the Minor Site Plan Schedule

More information

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST YES* GENERAL SUBMISSION ITEMS Does the submission include: 1. Thirteen (13) copies of completed Application Form? 2. Thirteen (13) copies of the Preliminary

More information

MINOR SUBDIVISION. [ ] [ ] [ ] [ ] B. Dimensions, bearings and curve data for all property lines and easements.

MINOR SUBDIVISION. [ ] [ ] [ ] [ ] B. Dimensions, bearings and curve data for all property lines and easements. MINOR SUBDIVISION 190-69. Minor subdivisions. In addition to the requirements indicated in 190-67 (SEE BELOW), the information below shall be shown on the plans for all minor subdivision applications.

More information

Step It Up a Rung from AutoCAD Designs to AutoCAD Electrical

Step It Up a Rung from AutoCAD Designs to AutoCAD Electrical Step It Up a Rung from AutoCAD Designs to AutoCAD Electrical Todd Schmoock Synergis Technologies MA4762-L: AutoCAD Electrical has proven to be easy for creating electrical controls system designs. It has

More information

Town of Skowhegan Application For Development Review

Town of Skowhegan Application For Development Review Town of Skowhegan Application For Development Review Return to: Skowhegan Planning Office 225 Water St., Skowhegan, ME 04976 (207) 474-6904 skowcodesec@skowhegan.org To be filled in by Staff: Project Name:

More information

1. The topographic map below shows a depression contour line on Earth's surface.

1. The topographic map below shows a depression contour line on Earth's surface. 1. The topographic map below shows a depression contour line on Earth's surface. Points A, B, C, and D represent surface locations. Contour line elevations are in feet. Which profile best shows the topography

More information

CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION:

CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION: CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION: LOG NO.: LEGEND REVIEW REVIEWED BY DATE / - Requirement satisfied 1 O Requirement not satisfied 2?

More information

Secondary Consolidation (Creep)

Secondary Consolidation (Creep) Secondary Consolidation Tutorial 11-1 Secondary Consolidation (Creep) When a load is applied to a low permeability soil (clay), you will see a period of primary consolidation as excess pore pressures dissipate.

More information

Compensatory Mitigation Monitoring Report Aquatic Habitat Improvement City of Montrose Whitewater Park, Montrose County, Colorado March 6, 2014

Compensatory Mitigation Monitoring Report Aquatic Habitat Improvement City of Montrose Whitewater Park, Montrose County, Colorado March 6, 2014 Compensatory Mitigation Monitoring Report Aquatic Habitat Improvement City of Montrose Whitewater Park, Montrose County, Colorado March 6, 2014 i. Project Overview 1. USACE # # SPK 2013 00851 2. Permittee:

More information

ATTACHMENT H TACOMA HYDROELECTRIC PROJECT DESCRIPTION OF PROJECT FEATURES

ATTACHMENT H TACOMA HYDROELECTRIC PROJECT DESCRIPTION OF PROJECT FEATURES ATTACHMENT H TACOMA HYDROELECTRIC PROJECT DESCRIPTION OF PROJECT FEATURES The Tacoma Hydroelectric Project is located about 20 miles north of Durango, Colorado, on a high intermountain plateau west of

More information

Phone: Gold SW, Suite 111 Fax:

Phone: Gold SW, Suite 111 Fax: Phone: 505-843-7643 610 Gold SW, Suite 111 Fax: 505-246-2232 Albuquerque, New Mexico, 87102 Web: WaterBank.com vember 30, 2010 John D. Armijo, Thomas Armijo William J. Gurule Contact: John D. Armijo P.O.

More information

DIGITAL RESISTANCE METER

DIGITAL RESISTANCE METER 1 P a g e M A N 1 7 0 MILLER 400D DIGITAL RESISTANCE METER USER S MANUAL Revised May 19, 2014 2 P a g e M A N 1 7 0 CONTENTS Page Section 1: Description 3 Section 2: How to Take Resistance Readings Manually

More information

SURVEYING 1 CE 215 CHAPTER -3-

SURVEYING 1 CE 215 CHAPTER -3- Civil Engineering Department SURVEYING 1 CE 215 CHAPTER -3- PROFILE AND CROSS SECTION LEVELING 1 2 1 3 4 2 5 6 3 7 8 4 9 10 5 11 12 6 13 14 7 15 16 8 17 18 9 19 20 10 21 22 11 23 24 12 25 26 13 27 28 14

More information

1 MUNICIPAL INFRASTRUCTURE

1 MUNICIPAL INFRASTRUCTURE Engineering Design Criteria & Standard Drawings Page 5 1 MUNICIPAL INFRASTRUCTURE 1.1 Drawing & Submission Requirements 1.1.1 General This section discusses the requirements for the submission of engineering

More information

Determining the Dynamic Characteristics of a Process

Determining the Dynamic Characteristics of a Process Exercise 5-1 Determining the Dynamic Characteristics of a Process EXERCISE OBJECTIVE In this exercise, you will determine the dynamic characteristics of a process. DISCUSSION OUTLINE The Discussion of

More information

Appendix N: Data Capture Guidelines Summary of Changes

Appendix N: Data Capture Guidelines Summary of Changes Appendix N: Data Capture Guidelines Summary of Changes The following Summary of Changes details revisions of Appendix N subsequent to the initial publication of the Draft Appendix N in April 2004. These

More information