GEO-SLOPE International Ltd, Calgary, Alberta, Canada Relief Well Spacing

Size: px
Start display at page:

Download "GEO-SLOPE International Ltd, Calgary, Alberta, Canada Relief Well Spacing"

Transcription

1 1 Introduction Relief Well Spacing Relief wells are commonly installed on the downstream side of an earth dam to control the seepage and pore-pressures (e.g. levee; Figure 1). A key design requirement for problems of this type is the required well spacing. Reservior Wells Natural outlet gulley 13 m 7 m 7 m Figure 1 Schematic of problem The plan view option in SEEP/W can be used to explore the relative effect of well spacing on the seepage and pore-pressures. The term relative is used here because the plan view simulation is not a true 3- dimensional analysis. The plan view analysis is ideally used to simulate the flow in confined aquifers; however, the problem shown in Figure 1 lends itself reasonably well to this type of analysis if a simplifying assumption is made that the levee acts as a confining unit and the foundation soils act as an aquifer. Consequently, the plan view simulation can provide some useful information at considerably less cost in comparison to a true 3D analysis. This example demonstrates how the SEEP/W plan view analysis can be used for this purpose. 2 Problem description Figure 1 illustrates a case involving a 1 m thick foundation layer. The total head in the reservoir is 13 m assuming that the datum is located at the bottom of the foundation layer. The far-field total head some distance down-slope of the levee is being controlled at 7 m by a natural stream which acts as a seepage outlet. For the purpose of this example, it is assumed that pumping maintains the water level at 7 m in the relief wells; the same elevation as the water in the outlet gulley. SEEP/W Example File: Relief well spacing.docx Page 1 of 9

2 3 SEEP/W plan view definition Reservior Wells 13 m 7 m 7 m Distance - m Figure 2 Plan view of SEEP/W configuration Figure 2 shows the SEEP/W finite element mesh in plan-view. The mesh comprises a single region 5 m along the levee with a line drawn along the toe (Draw Line). The mesh is generated along the line (Draw Mesh (select the line) Generate mesh along line) and points are added at equally spaced intervals (Draw Points). As will be demonstrated, the points and the line (actually line segments after the points are added) are necessary for the specification of the boundary conditions. To use the Plan view in SEEP/W, it is necessary to represent the original ground surface (i.e. before the levee was built) by specifying the x-y-z coordinates of three locations. SEEP/W Example File: Relief well spacing.docx Page 2 of 9

3 The plan view option is selected using the Set Units and Scale command. After the Plan view is selected, a Generate button appears. Clicking on the Generate button brings up the dialog box shown in Figure 3. Figure 3 Plan view dialog box for mesh thickness generation Points #1 and #2 define the left side of the plan view mesh and correspond to the position on the upstream toe of the levee. Point #3 defines the lower-right corner of the plan view mesh and corresponds to the position along the stream. The z-coordinate is considered to be the elevation of the ground surface; that is, the top of the foundation layer. The ground surface is everywhere at the same elevation. Clicking on the Generate button generates the appropriate thickness for all the elements in the mesh. The reservoir is represented with a total head (H) boundary condition on the left equal to 13 m. The water level in the outlet gulley is represented with H = 7 m. Three different scenarios are then investigated: 1. Without drainage: the case of having drainage controls is used as a basis for interpretation; 2. Collection trench: a drainage trench is simulated by applying H = 7 m to the line along the downstream toe, and, 3. Variably spaced relief wells: the effect of relief wells is explored using a well spacing of 5 m, 25 m, 1 m, and 5 m. For this illustrative example, the hydraulic conductivity has been set to 1 m/day, a value chosen simply for convenient discussion purposes. It is important to recognize that in a Plan view analysis only the specified saturated conductivity is used. Specifying the K as a constant is consequently adequate in a Plan view analysis no K function is required. SEEP/W Example File: Relief well spacing.docx Page 3 of 9

4 4 Results and Discussion 4.1 Without drainage The total quantity of seepage through the foundation is 6 m 3 /day without any drainage measures, as shown by the two flux sections in Figure 4. The flux quantity Q can be verified by a simple calculation because the gradient and cross-sectional area of the foundation are constant: 13 7 Q k dh / dl A (1) (5)(1).12(5) 6 5 m 3 /day. The equal spacing of the contours in Figure 4 is reflective of the constant gradient Distance - m m³/days 6 m³/days Figure 4 Flow situation with no wells 5 Collection trench The installation of a free draining collection trench would permit the water level to be maintained at an elevation of about 7 m. Essentially the same flow system would develop if the wells were spaced closely. This case and the previous case could both be simulated using a 2-dimensional analysis. Figure 5 shows the total head contours and fluxes at two sections. There is no flow beyond the trench, as indicated by the lack of head contours, for two reasons: 1) all of the seepage from the reservoir is collected by the trench; and 2) the water elevation in the trench is the same as the outlet gulley (i.e. there is no flow from the outlet gulley towards the trench). The total flow quantity is now twice the value reported previously because the gradient has doubled: (13-7) / 25 =.24. It is interesting to note that by installing the seepage control features the amount of seepage increases. SEEP/W Example File: Relief well spacing.docx Page 4 of 9

5 Distance - m m³/days 5.182e-13 m³/days Figure 5 Flow with an open collection trench 6 Variably spaced relief wells The effect of relief wells of variable spacing can be explored by applying H = 7 m at the well locations (i.e. Points) for the cases of: 5, 25, 1 and 5 m spacing. The resulting fluxes at two locations and the total head contours are shown in Figure 6 through Figure 9, respectively. SEEP/W Example File: Relief well spacing.docx Page 5 of 9

6 m³/days m³/days Figure 6 Flow with 5 m well spacing m³/days m³/days Figure 7 Flow with 25 m well spacing SEEP/W Example File: Relief well spacing.docx Page 6 of 9

7 14.96 m³/days m³/days Figure 8 Flow with 1 m well spacing m³/days m³/days Figure 9 Flow with 5 m well spacing The sum of the two flux sections in each of the cases is 12 m 3 /day. The difference between the two flux sections is the amount captured by the wells. This can be verified by using the View Results Information SEEP/W Example File: Relief well spacing.docx Page 7 of 9

8 command and clicking on the Point at the well. This will give the amount of flow out of the system at the well. The amount depicted by the right most flux section is the amount of flow that bypasses the wells. If this amount is taken as a percentage of the total 12 m 3 /day, the results are as follows: Spacing - m Percent passing wells trench. 7 Commentary It is interesting to note that even a wide spacing between the relief wells has a significant impact on the amount of flow through the foundation. However, the pore-pressure profile between the drains (along the bottom of the model) is hardly affected. Figure 1 shows the pore-pressure for a profile though the drain and at the middle between two drains when the spacing is 5 m. Conversely, the pressure profiles are nearly identical when the spacing is 5 m as shown in Figure 11 the only difference is right at the well. 3 2 Pressure Head (m) Middle : days Top : days X (m) Figure 1 Pressure profiles with a 5 m spacing SEEP/W Example File: Relief well spacing.docx Page 8 of 9

9 3 2 Pressure Head (m) Middle : days Top : days X (m) Figure 11 Pressure profiles with a 5 m spacing Perhaps the most significant observation is that with a 5 m spacing the results are very close to the trenchcase. The implication is that a conventional 2D vertical section analysis would be a realistic representation of the actual conditions in the field. Such a conventional 2D analysis could of course capture more of the complexity of a cross-section such as flow through the levee itself. The results of the plan view analysis are best viewed as relative values for various spacing. Actual seepage quantities would be better represented by a conventional 2D analysis. 8 Concluding remark This example shows how SEEP/W can be used to approximate the effect of relief well spacing along a linear structure such as a levee or irrigation canal. SEEP/W Example File: Relief well spacing.docx Page 9 of 9

AutoCAD 2016 for Civil Engineering Applications

AutoCAD 2016 for Civil Engineering Applications Introduction to AutoCAD 2016 for Civil Engineering Applications Learning to use AutoCAD for Civil Engineering Projects Nighat Yasmin Ph.D. SDC P U B L I C AT I O N S Better Textbooks. Lower Prices. www.sdcpublications.com

More information

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated

More information

SURVEYING 1 CE 215 CHAPTER -3-

SURVEYING 1 CE 215 CHAPTER -3- Civil Engineering Department SURVEYING 1 CE 215 CHAPTER -3- PROFILE AND CROSS SECTION LEVELING 1 2 1 3 4 2 5 6 3 7 8 4 9 10 5 11 12 6 13 14 7 15 16 8 17 18 9 19 20 10 21 22 11 23 24 12 25 26 13 27 28 14

More information

RRR Design & Modeling with the FDOT Civil 3D State Kit

RRR Design & Modeling with the FDOT Civil 3D State Kit RRR Design & Modeling with the FDOT Civil 3D State Kit Mike Racca - CADD Applications Development Specialist Production Support Office CADD 605 Suwannee St - MS 40, Tallahassee, Florida 32399 Session Objectives:

More information

The Basics. HECRAS Basis Input. Geometry Data - the basics. Geometry Data. Flow Data. Perform Hydraulic Computations. Viewing the Output

The Basics. HECRAS Basis Input. Geometry Data - the basics. Geometry Data. Flow Data. Perform Hydraulic Computations. Viewing the Output The Basics HECRAS Basis Input Geometry Data. Flow Data. Perform Hydraulic Computations by G. Parodi WRS ITC The Netherlands Viewing the Output ITC Faculty of Geo-Information Science and Earth Observation

More information

Should We Upgrade to Phase 2 6.0?

Should We Upgrade to Phase 2 6.0? Should We Upgrade to Phase 2 6.0? Rocscience has released version 6.0 of Phase 2, the popular two-dimensional finite element program for analyzing and designing surface and underground excavations in rock

More information

Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah

Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah Sediment Transport Workshop, Utah State University, 1 August 2017 Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah I. Goals for learning and discussion:

More information

Lab #4 Topographic Maps and Aerial Photographs

Lab #4 Topographic Maps and Aerial Photographs Lab #4 Topographic Maps and Aerial Photographs Purpose To familiarize you with using topographic maps. Visualizing the shape of landforms from topographic maps is an essential skill in geology. Proficiency

More information

Existing and proposed contours at 1-foot intervals. The fill and/or excavation quantities in cubic yards.

Existing and proposed contours at 1-foot intervals. The fill and/or excavation quantities in cubic yards. PLAN REQUIREMENTS The plans for street design shall conform to the requirements of Sections 3 and 4. The following requirements shall also be shown on the plans where applicable. Road and Storm Plans:

More information

LONGITUDINAL PROFILE COMPLETION

LONGITUDINAL PROFILE COMPLETION LONGITUDINAL PROFILE COMPLETION Vertical alignment of the ditch bottom determine using cross-sections plot (refer to fig. 0630) according to the chainage direction: ditch bottom on right side... dotted

More information

Town of Westlake Construction Plans Review Checklist

Town of Westlake Construction Plans Review Checklist CONSTRUCTION PLANS CONTENTS All Drawings 24 x 36 Cover Sheet Final Plat Site Plan Demolition Plan Utility Plan Drainage Area Map and Calculations Paving Plan & Profile Sheets Storm Drain Plan & Profile

More information

COPYRIGHTED MATERIAL. Contours and Form DEFINITION

COPYRIGHTED MATERIAL. Contours and Form DEFINITION 1 DEFINITION A clear understanding of what a contour represents is fundamental to the grading process. Technically defined, a contour is an imaginary line that connects all points of equal elevation above

More information

Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections

Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections v. 9.1 WMS 9.1 Tutorial Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections Modify cross sections in an HEC-RAS model to use surveyed cross section data Objectives Build a basic HEC-RAS

More information

ENVI.2030L Topographic Maps and Profiles

ENVI.2030L Topographic Maps and Profiles Name ENVI.2030L Topographic Maps and Profiles I. Introduction A map is a miniature representation of a portion of the earth's surface as it appears from above. The environmental scientist uses maps as

More information

CONTOURS SURVEYING 1 CE 215 CHAPTER -3- Ishik University / Sulaimani Civil Engineering Department 12/7/2017. Ishik University / Sulaimani

CONTOURS SURVEYING 1 CE 215 CHAPTER -3- Ishik University / Sulaimani Civil Engineering Department 12/7/2017. Ishik University / Sulaimani Civil Engineering Department SURVEYING 1 CE 215 CHAPTER -3- CONTOURS 1 2 1 3 4 2 PURPOSE OF CONTOURING Contour survey is carried out at the starting of any engineering project such as a road, a railway,

More information

Introduction to Aerial Photographs and Topographic maps (Chapter 3)

Introduction to Aerial Photographs and Topographic maps (Chapter 3) GEOLOGY 306 Laboratory Instructor: TERRY J. BOROUGHS NAME: Introduction to Aerial Photographs and Topographic maps (Chapter 3) For this assignment you will require: a calculator and metric ruler. Objectives:

More information

SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS

SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS 101 General 102 Submittal Requirements A. Initial Submittal B. Second Submittal 103 Plan Requirements A. Subdivisions B. Site Plans 104 Approval of

More information

List of Figures. List of Forms

List of Figures. List of Forms City of Columbia Engineering Regulations PART 1: SUBMISSION OF PLANS Table of Contents Paragraph Description Page No. 1.1 General 1-1 1.2 Engineer s Report 1-1 1.3 Plans 1-3 1.4 Revisions to Approved Plan

More information

PRE-LAB for: Introduction to Aerial Photographs and Topographic maps (Ch. 3)

PRE-LAB for: Introduction to Aerial Photographs and Topographic maps (Ch. 3) GEOLOGY 306 Laboratory Instructor: TERRY J. BOROUGHS NAME: PRE-LAB for: Introduction to Aerial Photographs and Topographic maps (Ch. 3) For this assignment you will require: a calculator and metric ruler.

More information

Topographic Maps. Contour Lines

Topographic Maps. Contour Lines Topographic Maps Our first task today will consist of locating ourselves with the help of a topographic map. GPS units that can tell you the location of any Dunkin' Donuts within a five mile radius. Paper

More information

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422 B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422 422.1 GENERAL The work under these tender items consists of the fabrication and installation in open cut of precast reinforced

More information

Shoe Box Activity Constructing a Topographic Map

Shoe Box Activity Constructing a Topographic Map Shoe Box Activity Constructing a Topographic Map Background Information All maps are models of some feature of the real world. The kind of map oen used by scientists is called a contour or topographic

More information

Module 2: Mapping Topic 3 Content: Topographic Maps Presentation Notes. Topographic Maps

Module 2: Mapping Topic 3 Content: Topographic Maps Presentation Notes. Topographic Maps Topographic Maps 1 Take a few moments to study the map shown here of Isolation Peak, Colorado. What land features do you notice? Do you thinking hiking through this area would be easy? Did you see the

More information

Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections

Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections WMS 10.1 Tutorial Hydraulics and Floodplain Modeling Managing HEC-RAS Cross Sections Modify cross sections in an HEC-RAS model to use surveyed cross section data v. 10.1 Objectives Build a basic HEC-RAS

More information

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360)

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 Email: cdd@ci.tumwater.wa.us WATER-SEWER-STREET-STORM (IN CITY) Submittal Checklist TUM - RCVD BY DATE STAMP APPLICANT INFORMATION

More information

Stream Design: From GEOPAK to HEC-Ras

Stream Design: From GEOPAK to HEC-Ras 10 Stream Design: From GEOPAK to HEC-Ras OBJECTIVES Provide you with a general understanding of GEOPAK Cross Section Reports and their capability to generate geometric information for the HecRas program.

More information

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges 50.24 Culverts, Bridges and Culvert Bridges Type, Size and Location (T, S & L) Plans shall be required for all Bridges, Culvert Bridges and Culverts of eight-foot (8') clear span or greater as follows:

More information

Corridors. To create a corridor you must have an alignment (baseline), a profile (existing or proposed), and an assembly.

Corridors. To create a corridor you must have an alignment (baseline), a profile (existing or proposed), and an assembly. Corridors To create a corridor you must have an alignment (baseline), a profile (existing or proposed), and an assembly. Alignments You have 2 choices in defining an alignment: (1) Alignments > Create

More information

-f/d-b '') o, q&r{laniels, Advisor. 20rt. lmage Processing of Petrographic and SEM lmages. By James Gonsiewski. The Ohio State University

-f/d-b '') o, q&r{laniels, Advisor. 20rt. lmage Processing of Petrographic and SEM lmages. By James Gonsiewski. The Ohio State University lmage Processing of Petrographic and SEM lmages Senior Thesis Submitted in partial fulfillment of the requirements for the Bachelor of Science Degree At The Ohio State Universitv By By James Gonsiewski

More information

CHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN

CHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN N/A Waiver (1) Four (4) copies of application form. (2) Fifteen (15) copies of plan (3) Subdivision/site plan application fee & professional review escrow deposit (4) Variance application fee & professional

More information

1.1 GENERAL RECORD DRAWING REQUIREMENTS

1.1 GENERAL RECORD DRAWING REQUIREMENTS Page 1 of 5 VILLAGE OF ROMEOVILLE RECORD DRAWINGS CHECKLIST PART I GENERAL Record drawings are required to provide a means of schematic verification that the intent of the approved engineering design has

More information

Introduction to Aerial Photographs and Topographic maps (Chapter 7, 9 th edition) or (chapter 3, 8 th edition)

Introduction to Aerial Photographs and Topographic maps (Chapter 7, 9 th edition) or (chapter 3, 8 th edition) GEOLOGY 306 Laboratory Instructor: TERRY J. BOROUGHS NAME: Introduction to Aerial Photographs and Topographic maps (Chapter 7, 9 th edition) or (chapter 3, 8 th edition) For this assignment you will require:

More information

B17. Sewer Site Plans BULLETIN

B17. Sewer Site Plans BULLETIN BULLETIN B17 Revised 5/2/2016 Sewer Site Plans Public Works This bulletin is designed to assist you in submitting the required documentation for sewer site plans to the Pierce County Sewer Division in

More information

BACKGROUND INFORMATION

BACKGROUND INFORMATION Build an Island INTRODUCTION For this assignment, you will be creating a topographic map and three-dimensional model of a fictional island that you have designed. You will start by exploring some basic

More information

Display and Draw Features

Display and Draw Features CHAPTER 7 Display and Draw Features 7.1 Overview Feature / Function Tool Display or draw DTM features, such as contours, triangles, lattices, voids, islands, etc. DTM Menu Bar Load > DTM Features GEOPAK

More information

Anne Arundel County Dept. of Inspections and Permits Water Sewer Plan Checklist

Anne Arundel County Dept. of Inspections and Permits Water Sewer Plan Checklist Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated

More information

Engineering Surveying -1 CE212 Contouring Lectures. Lecture 2016, November 29 th Muhammad Noman

Engineering Surveying -1 CE212 Contouring Lectures. Lecture 2016, November 29 th Muhammad Noman Engineering Surveying -1 CE212 Contouring Lectures Lecture 2016, November 29 th Muhammad Noman Contour An Imaginary line on the ground surface joining the points of equal elevation is known as contour.

More information

URBAN DRAINAGE AND FLOOD CONTROL DISTRICT

URBAN DRAINAGE AND FLOOD CONTROL DISTRICT URBAN DRAINAGE AND FLOOD CONTROL DISTRICT Digital Flood Hazard Area Delineation (DFHAD) Guidelines July 2009 Prepared by 720 South Colorado Boulevard Suite 410 S Denver, Colorado 80246 phone (303) 757-3655

More information

Levee Risk Assessments

Levee Risk Assessments Levee Risk Assessments Overview of the USACE Semi-Qualitative Risk Assessment Process for Levees Michael Kynett, PE Levee Safety Program Manager Sacramento District, USACE Levee State-of-the-Practice Symposium

More information

ACSA PLAN REVIEW CHECKLIST (Guideline Only) (4) Standard water and sewer general plan notes (attached).

ACSA PLAN REVIEW CHECKLIST (Guideline Only) (4) Standard water and sewer general plan notes (attached). ACSA PLAN REVIEW CHECKLIST (Guideline Only) Revised: December 3, 2015 General (1) Proper Title (2) Vicinity map on first sheet. (3) Date and latest plan revision. (4) Standard water and sewer general plan

More information

Module 6 : Design of Retaining Structures. Lecture 30 : Dewatering [ Section 30.1 : Introduction ]

Module 6 : Design of Retaining Structures. Lecture 30 : Dewatering [ Section 30.1 : Introduction ] Lecture 30 : Dewatering [ Section 30.1 : Introduction ] Objectives In this section you will learn the following Introduction Lecture 30 : Dewatering [ Section 30.1 : Introduction ] Introduction Dewatering

More information

Determining the Dynamic Characteristics of a Process

Determining the Dynamic Characteristics of a Process Exercise 5-1 Determining the Dynamic Characteristics of a Process EXERCISE OBJECTIVE In this exercise, you will determine the dynamic characteristics of a process. DISCUSSION OUTLINE The Discussion of

More information

Corridors To create a corridor you must have an alignment (baseline), a profile (existing or proposed), and an assembly.

Corridors To create a corridor you must have an alignment (baseline), a profile (existing or proposed), and an assembly. Corridors 2018-2019 To create a corridor you must have an alignment (baseline), a profile (existing or proposed), and an assembly. Alignments You have 2 choices in defining an alignment from scratch: (1)

More information

PRELIMINARY PLAT CHECK LIST

PRELIMINARY PLAT CHECK LIST Name of Proposed Subdivision: The following items must be included with the initial submittal of a Preliminary Plat: Application, filled out completely Project Narrative Pre-application Conference Report

More information

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for preparation

More information

Training Manual The Installation of Siphonic Pipework

Training Manual The Installation of Siphonic Pipework Training Manual The Installation of Siphonic Pipework The Engineered Rainwater Solution Training Manual: The Installation of Siphonic Pipework o Overview of Principals of Siphonic Drainage o Interpreting

More information

Example Application C H A P T E R 4. Contents

Example Application C H A P T E R 4. Contents C H A P T E R 4 Example Application This chapter provides an example application of how to perform steady flow water surface profile calculations with HEC-RAS. The user is taken through a step-by-step

More information

Grease Interceptor Design Checklist

Grease Interceptor Design Checklist CHECKLIST C2 Revised 5/2/2016 Grease Interceptor Design Checklist Public Works DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling private

More information

Conceptual, Preliminary and Final Site Plan Review in Holladay City

Conceptual, Preliminary and Final Site Plan Review in Holladay City Conceptual, Preliminary and Final Site Plan Review in Holladay City The City of Holladay incorporated in December, 1999 and adopted its own zoning ordinance in May, 2000. All land use decisions are made

More information

Surveying & Measurement. Detail Survey Topographic Surveying

Surveying & Measurement. Detail Survey Topographic Surveying Surveying & Measurement Detail Survey Topographic Surveying Introduction Mapping surveys are made to determine the relief of the earth s surface and locate critical points on it. to determine the locations

More information

AutoCAD Civil 3D 2009 ESSENTIALS

AutoCAD Civil 3D 2009 ESSENTIALS AutoCAD Civil 3D 2009 ESSENTIALS SDC PUBLICATIONS Schroff Development Corporation www.schroff.com Better Textbooks. Lower Prices. Alignments and Profiles Section 2: Profiles In this section you learn how

More information

Oil-Water Separator Design Checklist

Oil-Water Separator Design Checklist CHECKLIST C3 Revised 5/2/2016 Oil-Water Separator Design Checklist DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling private oil-water

More information

CITY OF MUSKEGO DRAFTING STANDARDS

CITY OF MUSKEGO DRAFTING STANDARDS CITY OF MUSKEGO DRAFTING STANDARDS GENERAL - These standards apply to all plans. 1. Plans must be prepared on sheets measuring 36 inch across and 22 inch to 24 inch high unless otherwise specified under

More information

Interaction of Soil and Seepage Barrier Cracks under Seepage Flow

Interaction of Soil and Seepage Barrier Cracks under Seepage Flow Utah State University DigitalCommons@USU All Graduate Plan B and other Reports Graduate Studies 5-29 Interaction of Soil and Seepage Barrier Cracks under Seepage Flow Justin Whitmer Utah State University

More information

MAJOR GRADING PLAN CHECKLIST

MAJOR GRADING PLAN CHECKLIST MAJOR GRADING PLAN CHECKLIST PUBLIC WORKS DEPARTMENT / ENGINEERING DIVISION 8130 Allison Avenue, La Mesa, CA 91942 Phone: (619) 667-1166 Fax: (619) 667-1380 Grading plans shall address both rough grading

More information

Role of BIM. in Plumbing System -K Chandrakanth and M Vinay Kumar. Abstract. 3 Dimension. Introduction: Collaborative Design:

Role of BIM. in Plumbing System -K Chandrakanth and M Vinay Kumar. Abstract. 3 Dimension. Introduction: Collaborative Design: Role of BIM in Plumbing System -K Chandrakanth and M Vinay Kumar Abstract As we look at the plumbing industry, especially in the building sector from design stage to operation & maintenance, huge amount

More information

Expanding the Frontiers of Geotechnical Engineering

Expanding the Frontiers of Geotechnical Engineering Expanding the Frontiers of Geotechnical Engineering Software development is not an exact science. When a new version of a Rocscience program is being planned, what are the decisions that have to be made

More information

NALYSIS OF STABILIZING SLOPES USING VERTICAL PILES

NALYSIS OF STABILIZING SLOPES USING VERTICAL PILES NALYSIS OF STABILIZING SLOPES USING VERTICAL PILES Mahmoud S. Abdelbaki: Lecturer, Gehan E. Abdelrahman: Lecturer, Youssef G. Youssef :Assis.Lecturer, Civil Eng. Dep., Faculty of Eng., Cairo University,

More information

Earth Sciences 089G Short Practical Assignment #4 Working in Three Dimensions

Earth Sciences 089G Short Practical Assignment #4 Working in Three Dimensions Earth Sciences 089G Short Practical Assignment #4 Working in Three Dimensions Introduction Maps are 2-D representations of 3-D features, the developers of topographic maps needed to devise a method for

More information

Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02

Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02 Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02 1. INTRODUCTION This standard is written to provide the professional surveyor (Surveyor) and the client with a guideline for producing

More information

Ohio Department of Transportation, VBA Documentation

Ohio Department of Transportation, VBA Documentation Contents 1.1 Current Versions... 2 1.2 Overview... 3 1.3 Supporting Files and Standards... 4 1.3.1 ODOT_Drainage.cel... 4 1.3.2 ODOT2013.ddb... 5 1.4 ODOT_StormSewerPlan2013.mvba... 6 1.4.1 Mode: Place

More information

CONCEPT REVIEW GUIDELINES

CONCEPT REVIEW GUIDELINES Department of Planning & Community Development @ Jefferson Station 1526 E. Forrest Avenue Suite 100 East Point, GA 30344 404.270.7212 (Phone) 404.765.2784 (Fax) www.eastpointcity.org CONCEPT REVIEW GUIDELINES

More information

APPENDIX I FLOODPLAIN ANALYSIS

APPENDIX I FLOODPLAIN ANALYSIS APPENDIX I FLOODPLAIN ANALYSIS TECHNICAL MEMORANDUM Date: June 11, 2014 To: Bibiana Alvarez and Ryan Lee Sawyer, Analytical Environmental Services From: Melanie Carr, MS, PE, Tarick Abu- Aly, MS, PE, Rafael

More information

Secondary Consolidation (Creep)

Secondary Consolidation (Creep) Secondary Consolidation Tutorial 11-1 Secondary Consolidation (Creep) When a load is applied to a low permeability soil (clay), you will see a period of primary consolidation as excess pore pressures dissipate.

More information

Advance Concrete. Tutorial

Advance Concrete. Tutorial Advance Concrete Tutorial Table of contents About this tutorial... 9 How to use this guide... 10 Lesson 1: Creating a building grid... 11 Step 1: Create a default building grid... 11 Step 2: Set the distances

More information

REVIEW TOPICS CEEN 2320 FINAL EXAM

REVIEW TOPICS CEEN 2320 FINAL EXAM REVIEW TOPICS CEEN 2320 FINAL EXAM Be familiar with all materials covered in class, your class handouts and the notes you took in class, your homework assignments, test questions, formulas, tables, figures.

More information

Homework 4: Understanding Graphs [based on the Chauffe & Jefferies (2007)]

Homework 4: Understanding Graphs [based on the Chauffe & Jefferies (2007)] 3 September 2008 MAR 110 HW4 -Graphs 1 Homework 4: Understanding Graphs [based on the Chauffe & Jefferies (2007)] The term "datum" refers to one unit of information. The plural of datum is "data." In science

More information

NAME: PERIOD: DATE: LAB PARTNERS: LAB #6 DRAWING A CONTOUR MAP FROM A THREE DIMENSIONAL MODEL

NAME: PERIOD: DATE: LAB PARTNERS: LAB #6 DRAWING A CONTOUR MAP FROM A THREE DIMENSIONAL MODEL NAME: PERIOD: DATE: LAB PARTNERS: LAB #6 DRAWING A CONTOUR MAP FROM A THREE DIMENSIONAL MODEL INTRODUCTION Since land distances and elevations on the earth's surface can be very great it is necessary to

More information

HEADS Pro: The Simplest & Versatile software for Highway engg.&

HEADS Pro: The Simplest & Versatile software for Highway engg.& HEADS Pro: The Simplest & Versatile software for Highway engg.& design with special features for low cost rual & hill roads, tunnels, road widening, strengthening, profile correction, pavement design,

More information

Slope analysis & Grading. Earth shape and earthwork Topographic map Slope form Slope analysis Grading

Slope analysis & Grading. Earth shape and earthwork Topographic map Slope form Slope analysis Grading 6 Slope analysis & Grading Earth shape and earthwork Topographic map Slope form Slope analysis Grading 81 Topographic Map Topographic Contour map Topographic contour map are composed of a series of line

More information

3. DESIGN SPECIFICATIONS

3. DESIGN SPECIFICATIONS Schedule H to Bylaw 7452, Subdivision Bylaw Page 10 3. DESIGN SPECIFICATIONS 3.1 General 3.1.1 The Design Specifications apply to the design of sanitary sewers, storm drains, waterworks, roadways, and

More information

CHAPTER 3 MARGINAL INFORMATION AND SYMBOLS

CHAPTER 3 MARGINAL INFORMATION AND SYMBOLS CHAPTER 3 MARGINAL INFORMATION AND SYMBOLS A map could be compared to any piece of equipment, in that before it is placed into operation the user must read the instructions. It is important that you, as

More information

Drafting: A Hands-on Experience

Drafting: A Hands-on Experience Steve Webb Field Support Applications Engineer Drafting: A Hands-on Experience Solid Edge University 2014 May 12-14, Atlanta, GA, USA SOLID EDGE UNIVERSITY 2014 Re-imagine What s Possible #SEU14 Agenda

More information

Fig. 9 Different weld positions. There are five basic types of common joints. They are

Fig. 9 Different weld positions. There are five basic types of common joints. They are c) Vertical - On the wall d) Horizontal - On the wall Fig. 9 Different weld positions 7.0 TYPES OF JOINTS There are five basic types of common joints. They are Butt joint Lap joint T joint Corner joint,

More information

Re: Survey of constructed cross section per Restoration Framework on Wind River, Fremont County, WY

Re: Survey of constructed cross section per Restoration Framework on Wind River, Fremont County, WY 1-11-17 LeClair Irrigation District 1418 Cowboy Lane Riverton, WY 82501 (307) 856-4018 Re: Survey of constructed cross section per Restoration Framework on Wind River, Fremont County, WY Dear Mr. Hoelzen,

More information

TEMScripts Auto Image Measurement (Pattern) Manual. TEMScripts LLC. Last updated: 12/5/2016

TEMScripts Auto Image Measurement (Pattern) Manual. TEMScripts LLC. Last updated: 12/5/2016 TEMScripts Auto Image Measurement (Pattern) Manual TEMScripts LLC. Last updated: 2/5/206 Close Digital Micrograph TS EasyMetro Installation Copy following files to \\Gatan\DigitalMicrograph\PlugIns (normally

More information

Confidence Intervals. Class 23. November 29, 2011

Confidence Intervals. Class 23. November 29, 2011 Confidence Intervals Class 23 November 29, 2011 Last Time When sampling from a population in which 30% of individuals share a certain characteristic, we identified the reasonably likely values for the

More information

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST YES* GENERAL SUBMISSION ITEMS Does the submission include: 1. Thirteen (13) copies of completed Application Form? 2. Thirteen (13) copies of the Preliminary

More information

EMP Finite-element Time-domain Electromagnetics

EMP Finite-element Time-domain Electromagnetics EMP Finite-element Time-domain Electromagnetics Field Precision Copyright 2002 PO Box 13595 Albuquerque, New Mexico 87192 U.S.A. Telephone: 505-220-3975 FAX: 505-294-0222 E Mail: techinfo@fieldp.com Internet:

More information

Durham Model Aquifer- Pumping test March 23, 2018

Durham Model Aquifer- Pumping test March 23, 2018 Durham Model Aquifer- Pumping test March 23, 2018 Analysis using MLU for Windows General setup A discussion in the LinkedIn group "Hydrogeology Forum" introduces the DMA pumping test. The aquifer is man-made

More information

QUANTITY SURVEYS. Introduction

QUANTITY SURVEYS. Introduction QUANTITY SURVEYS Introduction In engineering surveying, we often consider a route (road, sewer pipeline, channel, etc.) from three distinct perspectives. The plan view of route location is the same as

More information

TESTING EQUIPMENT SHEAR STRENGTH PARAMETERS SOIL. established in 1972

TESTING EQUIPMENT SHEAR STRENGTH PARAMETERS SOIL.   established in 1972 SOIL www.alfatestusa.com established in 1972 SOIL Used to perform large range of Triaxial tests on soil samples to determine the strength parameters and the mechanical properties. Capable of performing:

More information

1. The topographic map below shows a depression contour line on Earth's surface.

1. The topographic map below shows a depression contour line on Earth's surface. 1. The topographic map below shows a depression contour line on Earth's surface. Points A, B, C, and D represent surface locations. Contour line elevations are in feet. Which profile best shows the topography

More information

Drip System Simulation Programme (DSSP), Water Technology Centre, TNAU

Drip System Simulation Programme (DSSP), Water Technology Centre, TNAU DECISION SUPPORT SYSTEM FOR DESIGN OF DRIP SUBUNITS WITH TAPERED PIPES IN NON-UNIFORM SLOPES V.Ravikumar, Associate Professor, WTC, TNAU, Coimbatore Designing of drip irrigation system with desired uniformity

More information

SUBMITTAL REQUIREMENTS FOR USE PROCESS III OR PROCESS IV

SUBMITTAL REQUIREMENTS FOR USE PROCESS III OR PROCESS IV COMMUNITY DEVELOPMENT DEPARTMENT 33325 8 th Avenue South Federal Way WA 98003 253-835-2607; Fax 253-835-2609 www.cityoffederalway.com SUBMITTAL REQUIREMENTS FOR USE PROCESS III OR PROCESS IV USE PROCESS

More information

Landscaping Tutorial

Landscaping Tutorial Landscaping Tutorial This tutorial describes how to use Home Designer Essentials s Terrain Tools. In it, you will learn how to add elevation information to your terrain, how to create terrain features,

More information

MSD STANDARD DRAWINGS LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT 700 WEST LIBERTY STREET LOUISVILLE, KENTUCKY

MSD STANDARD DRAWINGS LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT 700 WEST LIBERTY STREET LOUISVILLE, KENTUCKY MSD M etr o p olitan S e w e r Di s t r ict STANDARD DRAWINGS LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT 700 WEST LIBERTY STREET LOUISVILLE, KENTUCKY 40203-1911 STANDARD DRAWINGS DIVISION

More information

Promontory Architectural Review Committee

Promontory Architectural Review Committee Promontory Architectural Review Committee Design Review Application Purpose The Design Review Process and Application have been established to insure that a proposed project is compatible with historical,

More information

APPENDIX B: DETAIL DRAWINGS OF SELECTED IMPROVEMENT TECHNIQUES

APPENDIX B: DETAIL DRAWINGS OF SELECTED IMPROVEMENT TECHNIQUES APPENDIX B: DETAIL DRAWINGS OF SELECTED IMPROVEMENT TECHNIQUES This appendix provides schematic drawings (not to scale) that illustrate the materials, form, and construction of selected improvement techniques.

More information

7. Consider the following common offset gather collected with GPR.

7. Consider the following common offset gather collected with GPR. Questions: GPR 1. Which of the following statements is incorrect when considering skin depth in GPR a. Skin depth is the distance at which the signal amplitude has decreased by a factor of 1/e b. Skin

More information

SABAT CONSULTING GROUP PAYDIRT 4 TRAINING MANUAL. Support Numbers: SABAT: / GTCO / PAYDIRT:

SABAT CONSULTING GROUP PAYDIRT 4 TRAINING MANUAL. Support Numbers: SABAT: / GTCO / PAYDIRT: SABAT CONSULTING GROUP PAYDIRT 4 TRAINING MANUAL Support Numbers: SABAT: 905-850-9633 / GTCO 800-344-4723 / PAYDIRT: 800-235-4972 Digitizer Setup Codes: / QR: S + 0+1 / SW: S + 0+ 1 PAYDIRT OTHER SUPPORT:

More information

Leveling. Double-Rodded Leveling. Illustrative Problem. Double-Rodded Leveling 8/17/2014

Leveling. Double-Rodded Leveling. Illustrative Problem. Double-Rodded Leveling 8/17/2014 Double-Rodded Leveling Double-Rodded Leveling A method of determining the differences in elevation between points by employing two level routes simultaneously Two turning points are established such that

More information

Important Considerations For Graphical Representations Of Data

Important Considerations For Graphical Representations Of Data This document will help you identify important considerations when using graphs (also called charts) to represent your data. First, it is crucial to understand how to create good graphs. Then, an overview

More information

8/17/2014. Process of directly or indirectly measuring vertical distances to determine the elevation of points or their differences in elevation

8/17/2014. Process of directly or indirectly measuring vertical distances to determine the elevation of points or their differences in elevation Process of directly or indirectly measuring vertical distances to determine the elevation of points or their differences in elevation Leveling results are used: To design highways, railroads, canals, sewers,

More information

Survey Data and TOPO Checklist

Survey Data and TOPO Checklist Checklists Survey Data and TOPO Preliminary Plan Field Review Plans o Field Review Erosion Control Right-of-Way and Utility Meeting Plans Final Plan Field Review Plans Methods of Plan Markups Plan-in-Hand

More information

Contour An imaginary line on the ground surface joining the points of equal elevation is known as contour.

Contour An imaginary line on the ground surface joining the points of equal elevation is known as contour. Contour An imaginary line on the ground surface joining the points of equal elevation is known as contour. In other words, contour is a line in which the ground surface is intersected by a level surface

More information

B-PERMIT PLAN CHECK MANUAL

B-PERMIT PLAN CHECK MANUAL B-PERMIT PLAN CHECK MANUAL 5. SEWER PLANS Sewer Plans are usually submitted in conjunction with Street Plans to meet the requirements of conditions imposed on a Planning or Zoning action. In some cases

More information

TUTORIAL #1. Initial ft ss, psia Initial bubble point pressure, psia 800. Water-oil contact, ft ss. Porosity, percent 20

TUTORIAL #1. Initial ft ss, psia Initial bubble point pressure, psia 800. Water-oil contact, ft ss. Porosity, percent 20 TUTORIAL #1 This is a 40 acre pilot test of a 5-spot pattern (10 acre well spacing) for CO2 injection in a good quality sandstone formation with a net thickness of 75 ft. Due to the small areal size the

More information

Contact Us : E Surveying Solutions AMR #7, Circular ring Road Nandini Layout Bangalore Karnataka, India. Phone:

Contact Us : E Surveying Solutions AMR #7, Circular ring Road Nandini Layout Bangalore Karnataka, India. Phone: E Surveying Solutions work towards bring the survey community together and utilize your engineering and our software skills to deliver effective services, by introducing cutting edge technology at an affordable

More information

Basic Surveying. Kabul, Afghanistan February 2011

Basic Surveying. Kabul, Afghanistan February 2011 Basic Surveying Kabul, Afghanistan February 2011 1 This watershed rehabilitation and restoration training was prepared by the U.S. Department of Agriculture (USDA) team of Jon Fripp (Civil Engineer USDA/NRCS),

More information