State Radio Project. January Monthly Progress Report

Size: px
Start display at page:

Download "State Radio Project. January Monthly Progress Report"

Transcription

1 State Rad o Project State Radio Project January 2013 Monthly Progress Report

2 Project Goals Infrastructure Repair or replace critical components of Oregon s deteriorating state radio network and extend the useful life of the existing Oregon Department of Transportation and Oregon State Police wireless communications systems. Narrowbanding Comply with the approved Federal Communications Commission waiver deadline to transition state radios from wideband to narrowband transmission by Nov. 1, 2013, and position for future narrowbanding requirements. Consolidation Consolidate the ODOT and OSP wireless communications systems into a single unit and allow for shared efficiencies and integration between the four existing state systems. Interoperability Provide limited, local interoperability for public safety agencies and lay the foundation for expanded and improved interoperability in the future. Cover photo: Notice to proceed will be issued in early January for work at the Signal Tree site in Coos County. This view is to the southwest.

3 CONTENTS Project Map ii Project Update 1 Project Success 3 Project Progress by WBS 5 WBS 1.0 Project Management Summary 6 WBS 2.0 Narrowbanding 9 WBS 3.0 Microwave Modernization 11 WBS 4.0 Trunked radio System 14 WBS 5.0 Interoperability 16 WBS 6.0 Partnerships 17 WBS 7.0 Planning & Engineering 21 Staffing & Vendor Summary 25 Sites by County 29 Project Cost Summary 35 Estimated Project Cash Flow 36 The State Radio Project redesigned its Monthly Progress Report in December Project information previously contained in a separate Supplemental Operations Report is now combined into one monthly report, providing a more detailed and complete picture of the radio project s progress for a wider audience. January No. 28 Page i

4 Project Map Visit ODOT s Radio Project website at See previous progress reports and an interactive map at Page ii January No. 28

5 Project Update Two items that could challenge the State Radio Project s schedule emerged this month: specifications for antennas and contracts to purchase remaining office remote equipment. Radio project staff is working both issues to adhere to the timeline and mitigate delays. By month s end, mobile radio installations were wrapping up for the Oregon Department of Transportation s Maintenance Division vehicles, and Oregon State Police vehicle installations were back in full swing. The OSP installations will be completed in April. The project has received the necessary equipment for all of the trunking system Increment Zero (test bed) sites. Testing and installations will begin in late January, later than initially planned, to accommodate other priorities related to planning. Delaying the testing will not impact the original project schedule. Tests will begin with four of the planned eight sites and expand as the remaining sites come online in April. While the project is proceeding with the testing of the Increment Zero sites, it is pivoting the priority of delivery of two project components: microwave and the trunked radio system. The overall project schedule won t change, just what we do and when, said Radio Project Manager Dick Upton. We ll do more with the non-trunked sites in 2013 than we originally planned and push some of the work on the trunked sites back to the cusp of 2013 and into The project is well-prepared for acquisition of non-trunked radio sites, with the specifications and information needed to advance site construction in place. The acquisition and preparation of sites for the trunked radio sites, however, is challenged, and funding is uncertain. Therefore, it makes sense to defer the trunked radio sites to At the December meeting of the State Interoperability Executive Council, Major Projects Branch Manager Tom Lauer provided a status update of the radio project. He focused in particular on its This was a great job by all involved. Oregon Communications Plan, noting that we are using leads the way with this effort. a systematic and informed process to facilitate Bruce Richter, Region X coordinator, specific communication with SIEC members Department of Homeland Security and other stakeholders. The SIEC unanimously approved a draft legislative concept to modify House Bill 2101, and Yamhill County Commissioner Kathy George was very complimentary, thanking all members involved with developing the draft. Tom Lauer and his team have done a phenomenal job, said George. I can t thank you enough. Region X coordinator for the Department of Homeland Security Bruce Richter added his praises for the state s interoperability efforts, particularly the development of a smartphone application of the Oregon Regional Tactical Interoperability Communications Field Operations Guide, or TICFOG. This was a great job by all involved, said Richter. Oregon leads the way with this effort. Project communications remain a high-priority item for the management team. Having radio project staff housed in three separate locations presents a challenge, especially in ensuring the appropriate people are connected. We re going to be spending some time on internal staff dynamics and how to keep communication crisp and clear to keep the project moving, Upton said. January No. 28 Page 1

6 INFRASTRUCTURE Sites in construction in December include improvements at Wilson River in Tillamook County, Sillusi Butte in Benton County, Wash., and a solar installation at Nicolai in Clatsop County. We completed bid processes for Saddlebag in Lincoln County and Prospect in Marion County. Contracts have been awarded and notices to proceed will be issued in early January for work in Lincoln County at Cape Perpetua, Euchre Mountain, Table Mountain and Prairie Peak, as well as at Signal Tree in Coos County, Aldrich Mountain in Grant County, Mount Weston in Umatilla County, Herman Peak in Lane County, Hulse Ranch in Wasco County and Augspurger Mountain in Skamania County, Wash. NARROWBANDING With the exception of a few vehicles, ODOT Maintenance mobile radio installations will be complete in early January. OSP mobile radio installations will continue through February. Preparations for office remote radio installations are under way; installation of equipment is set to begin in January. Bids for the mountaintop antennas at several sites were let in December, and more are in the pipeline. Antenna work is expected to begin after the first of the year. CONSOLIDATION The State Radio User Group did not meet during December; however, staff continued to make progress toward finalizing the SRUG and cost model agreements by gaining three of the five required agency signatures. The radio project is collaborating with the other two agencies on gaining their acceptance and signatures. The 2013 SRUG meetings have been scheduled for the third Friday of each month. INTEROPERABILITY Coordination and planning work with the Office of Emergency Communications for broadband governance continued in December; results will be presented to the SIEC in February. This will support Oregon s strategic and operational planning for the FirstNet National Network. Preliminary work is under way for the State Implementation Grant that is anticipated to be released by FirstNet in early A rewrite of the current Statewide Communications Interoperability Plan will be integrated into this effort. The Oregon Regional TICFOG has been converted into an iphone app and is available from the itunes Store ( reference/oregon-efog). It will also be available soon for Android at the Google Apps Store. The Oregon efog app is an electronic reference of the TICFOG. The efog provides users search and information access features, Statewide Interoperability Coordinator Steve Noel updates the December meeting of the State Interoperability Executive Council. offering a content index with links to reference sections, tables, figures or images. Users can jump directly to regional quick references as well as add customizable bookmarks to develop their own personalized access to critical information for their territory. The efog can be downloaded and then taken to the field as an offline reference. Page 2 January No. 28

7 Project Success Repurposing radios as remote receivers means significant savings Substantial cost savings will be realized for the State Radio Project by repurposing single-band mobile radios from Oregon State Police and ODOT Maintenance Division vehicles as office remote receivers statewide. More than 200 Kenwood 5710 mobile radios are coming out of the radio users vehicles as the new Harris Unity mobiles are being installed. ODOT Maintenance has a couple, but it s mainly OSP that has the Kenwood mobile models being swapped out, said Chuck Kummer, ODOT s senior wireless system specialist for the radio project. In a parallel initiative, 110 offices around the state were scheduled to receive new Harris remote receivers as part of the office remote setup. It occurred to Kummer that a reuse of the Kenwoods was not only possible, but desirable. It just made sense: We don t need to buy expensive new radios we can use the equipment that s already paid for, he said. What the radio project calls an office remote is a base receiving station that brings in the signal from mountaintop repeaters in the area. In effect, the office remote is the means by which that office is added to the communications loop. In many cases, the office remote is simply a mobile radio with a power supply and several remote units attached that resemble a desktop phone. The Kenwood 5710 radios being replaced by the new Harris Unity mobile radios in OSP and ODOT vehicles can be repurposed as office remote receivers in some offices around the state. It just made sense: We don t need to buy expensive new radios we can use the equipment that s already paid for. The proposed office setup was going to be a new Unity mobile radio, Kummer said. So why not use what we already have? The Kenwoods operate with narrowband and are P25 compliant, so if we ever go that way, we re already all set. Project technicians are now set to rewire the Kenwood 5710 radios to convert them into remote receivers. There are instances in which the reconfigured Kenwoods won t work and it will be necessary to purchase new radios. But when they do fit, the radio project can save approximately $7,700 by not purchasing a new radio. With the approximately 75 Kenwoods targeted for reuse in various offices around the state, the reduction in project costs is estimated to be a little more than $550,000. Since more than 200 of the Kenwood models have been reclaimed, the project will have more than enough units to use as office remotes; surplus units can be sold to other agencies and public safety organizations. The repurposed radios have all of the required functionality of the originally selected model, being digital and P25 compliant. In fact, some Kenwood 5710 units have already been in use in Chuck Kummer, ODOT senior wireless system specialist some offices as remote receivers for years. They re fairly new radios with adequate capabilities, said Joe Messman, assistant radio project manager. They have sufficient functionality to operate in the offices, and they still have plenty of functional life ahead. January No. 28 Page 3

8 Both OSP and ODOT have been receptive to this idea of repurposing the Kenwood radios, mainly because of the cost savings. We discussed the ideas in many meetings, Messman said. They understand that the potential savings go far toward offsetting the budget shortfalls. For example, we ve needed to purchase special holsters, battery chargers and headset-microphones things that we anticipated at the beginning of the project but that have turned out to be needed in greater volume than originally estimated. In most offices, the radio equipment is installed out of sight in a back room or closet and has a remote desktop unit attached, so radio users rarely even see the receiver. It may not have the glossy, shining look of a new piece of equipment, he said. But it has the same capabilities to serve the users, so they won t notice a difference. Ultimately, repurposing these radios conserves public funds. Page 4 January No. 28

9 Project Progress by WBS The budget for the radio project in the biennium is $95.3 million. Work will continue into the next biennium for a total cost of $154.4 million. The work components necessary to launch the revised State Radio Project include project management, narrowbanding, microwave modernization, trunking, tactical interoperability and partner obligations. The budget and schedule for the project s active components are provided in the following pages of this report, which are based upon the work breakdown structure detailed in the State Radio Project s Project Management Plan Overall Project Engineering Narrowbanding Microwave Trunking Partnerships Dec. 31, 2012 Total Project Budget $209,991,920 Actual Expenditures $102,405,889 49% Forcast Expenditures $117,732,095 56% Total Budget Remaining $107,586,030 51% $107,586,030 52% $102,405,889 49% Current Expenditures OWIN expenditures account for $55.5 million of expenditures to date. In Millions January No. 28 Page 5

10 WBS 1.0 Project Management Summary Project management consists of those elements that are projectwide and affect all other WBS sections. Budget Expenditures For WBS 1.0 Project Management, 50 percent of the total budget has been expended to date. Total Section Budget $10,242,803 Actual Expenditures $5,139,972 50% Forcast Expenditures $6,154,343 60% Section Budget Remaining $5,102,831 50% $5,102,831 50% $5,139,972 50% Current Expenditures In Millions Activities and Progress Asset Management Progress continued in December on the development and rollout of the State Radio System s asset management and work order system. Three workshops were held during December with designated system administrators, frequency coordinators and ODOT/OSP Wireless Section lead workers to prepare each user group to interact with the software appropriately, as well as to identify any customization that may be required prior to deployment. Phase I rollout includes the deployment of the work order software; all Wireless Section technicians will attend training during February to learn how the work order system operates. Implementation staff, in conjunction with steering committee members, has identified March as the target to have Phase I operational. Subsequent phases will include lease tracking and management, inventory management and procurement management. Page 6 January No. 28

11 Change Management There are two types of change requests, administrative and formal. Administrative changes are those that do not affect the project s baseline scope, schedule or budget. Formal changes are those that affect those project baselines. During December, 26 change requests were processed and approved. To date, 135 changes have been approved: 45 were administrative and 90 were formal. November 2012 December 2012 Total to date Administrative Formal Total The following chart represents the value of the project s contingency budget at the end of the two most recent months. The change noted is due to approval of formal budget changes executed in December. November 2012 December 2012 Total Change Contingency budget end-of-month value $7,457,445 $8,301,737 + $844,292 Communications Management Communications staff provided the following project information/materials during December 2012: Produced redesigned December 2012 Monthly Progress Report Produced December 2012 Project Dashboard Produced December 2012 Key Project Facts sheet Produced and distributed quarterly Radio Users Update/newsletter Updated project website on Oregon.gov Distributed project information notices via GovDelivery Produced and published project feature story in Inside ODOT Reported on radio project activities to ODOT public affairs staff Distributed partner/stakeholder communication introducing project communications liaisons Finalized December 2012 Legislative Report Project management and staff also conducted the following outreach activities: Participation in and facilitation of the monthly Delivery Team meeting Participation in the quarterly State Interoperability Executive Council meeting Participation in the monthly Oregon Broadband Advisory Council meeting Participation in the weekly Oregon Public Safety Broadband Network conference call Participation in the weekly Emergency Response Interoperability Center / Public Safety Advisory Committee conference call January No. 28 Page 7

12 Quality Management Public Knowledge delivered its Quarterly Project Status and Improvement Report detailing activities from Oct. 1 through Dec. 31, Because a quarterly report was delivered, Public Knowledge did not issue new findings nor provide additional recommendations on previous findings. The project will provide the vendor with updates on the previous 14 findings already reported by the vendor. The following table details the findings addressed during November and December. November 2012 December 2012 Progress Total findings reported by Public Knowledge New Findings Positive no action required 0 0 +/- 0 Recommendations provided Previous Findings Additional recommendation provided Closed no further action required The following table is a snapshot of the issues, categorized by WBS section, managed by the project during December. Project management develops planned actions and target dates for resolving these issues. Until an issue has a target resolution date, it is not included in the planned for resolution count. Number of Active Issues Number Planned for Resolution Total Resolved 1.0 Project Management Narrowbanding Microwave Modernization Trunked Radio Interoperability Partnerships Planning and Design Total Page 8 January No. 28

13 WBS 2.0 Narrowbanding Narrowbanding includes work at mountaintop tower sites and at ODOT and OSP office sites. To meet the new federal narrowbanding deadine of Nov. 1, 2013, the radio project must install repeaters and make site improvements at the mountaintop tower sites and, at emergency communication offices statewide, install office controllers as well as deploy portable radios and mobile radios. Schedule Summary Budget Expenditures Dec. 31, 2012 For WBS 2.0 Narrowbanding, 56 percent of the total budget has been expended to date. Total Section Budget $31,571,907 Actual Expenditures $17,813,479 56% Forcast Expenditures $20,936,976 66% Section Budget Remaining $13,758,428 44% $13,758,428 44% $17,813,479 56% Current Expenditures In Millions January No. 28 Page 9

14 Activities and Progress 2.1 Narrowband Repeaters December 2012 Total to date Forecast Actual Forecast Actual Sites with repeaters installed Sites with antannas installed Staff worked to initiate the procurement process for antenna equipment associated with 23 highpriority locations. 2.2 Office Remotes December 2012 Total to date Forecast Actual Forecast Actual Radios installed Sites completed 110 sites Staff continued planning efforts for the upcoming installations, slated to begin in January. 2.3 Radio Deployment The radio deployment consists of two elements for both ODOT and OSP: training and deployment of mobile radio equipment, and training and deployment of handheld, portable radio units. The following table shows the number of units deployed in December and the total deployed to date. December 2012 Total to date ODOT Forecast Actual Forecast Actual Agency locations/crews completed Mobile radio deployment Portable radio deployment Employees trained NA 3 NA 966 OSP Agency locations/crews completed Mobile radio deployment Portable radio deployment Employees trained NA 23 NA Cut-Over Testing With the extension of the narrowband deadline, the project anticipates it will begin the cutover process in June Page 10 January No. 28

15 WBS 3.0 Microwave Modernization The microwave component of the radio project involves replacing old and outdated ODOT and OSP analog microwave with digital microwave and making associated site improvements. Microwave installation includes the acquisition, installation, implementation and optimization of the new digital microwave radios, antenna dishes, wave guide, routers and ancillary equipment to support both conventional and trunked radio systems. Network implementation consists of integrating routing, switching and monitoring equipment into the microwave system to move both voice and data messages over the digital microwave system. Improvements to towers, shelters, power supplies and other facilities required by the upgraded microwave and trunked radio systems are anticipated at most sites. New leases, permits and agreements will be obtained as needed. The budget for the biennium for this radio project component is $7.7 million for installation, $4.3 million for network implementation and $2.7 million for site work, for a total of $14.7 million. Work will continue into the next biennium for a total project cost of $54.8 million. Schedule Summary Dec. 31, 2012 Budget Expenditures For WBS 3.0 Microwave Modernization, 8 percent of the total budget has been expended to date $4,365,916 8% Total Section Budget $54,828,562 Actual Expenditures $4,365,916 8% Forcast Expenditures $7,775,955 14% Section Budget Remaining $50,462,646 92% $50,462,646 92% January No. 28 Page 11

16 Budget Expenditures (Cont.) Current Expenditures In Millions Activities and Progress 3.1 Microwave Installation and 3.2 Network Implementation The microwave installation phase includes those tasks involved in the installation of microwave equipment, from initiation to completion. Microwave installations may occur during a site s construction phase or after it has been completed. December 2012 Total to date Microwave Installation Complete Forecast Actual Forecast Actual Trunked test bed 11 sites Zone 1 core sites 31 sites Zone 2 Bend, trunked 6 sites 0 0 The project estimates Zone 3 Columbia River, trunked 9 sites 0 0 construction will take Zone 4 Willamette Valley, trunked 12 sites 1 1 place during the 2013 Zone 5 Interstate 84 corridor 44 sites 0 0 build season. Zone 6 U.S. 20 & 26 corridor 37 sites 0 0 Zone 7 Northwest Coast 31 sites 0 0 The project estimates Zone 8 Central Coast 21 sites 0 0 construction will take Zone 9 Southwest Coast 17 sites 0 0 place during the 2014 Zone 10 Southwest Interior 20 sites 0 0 build season. Zone 11 Oregon 140 corridor 11 sites 0 0 Page 12 January No. 28

17 3.3 Microwave Site Improvements The site improvement process includes three phases: pre-design, design and construction. The construction phase includes tasks completed from the acquisition of the building permit to the completion of site construction. Section 7.0 Planning and Engineering includes progress on the predesign and design phases of the site improvement process. December 2012 Total to date Site Improvements, Construction Complete Forecast Actual Forecast Actual Maintenance locations 10 sites Infill locations 30 sites Trunked test bed 11 sites Zone 1 core sites 31 sites Zone 2 Bend, trunked 6 sites 0 0 The project estimates Zone 3 Columbia River, trunked 9 sites 0 0 construction will take Zone 4 Willamette Valley, trunked 12 sites 0 0 place during the 2013 Zone 5 Interstate 84 corridor 44 sites 3 3 build season. Zone 6 U.S. 20 & 26 corridor 37 sites 1 1 Zone 7 Northwest Coast 31 sites 0 0 The project estimates Zone 8 Central Coast 21 sites 3 3 construction will take Zone 9 Southwest Coast 17 sites 1 1 place during the 2014 Zone 10 Southwest Interior 20 sites 0 0 build season. Zone 11 Oregon 140 corridor 11 sites 0 0 January No. 28 Page 13

18 WBS 4.0 Trunked radio System A trunked radio system is used to maximize available capacity in a two-way radio system. Because not everyone in a group talks at once and radio transmissions are usually short, a trunked computer can assign talk frequencies in a manner that allows multiple groups of users to share a small set of frequencies without hearing each other s conversations. This effectively compresses the voice signals and enhances the capacity of the system. The trunked system will allow local radio communications between public safety personnel; microwave will distribute those signals over a larger area, enabling distance and interagency communications. The budget for the trunked system portion of the radio project component is $7.9 million for repeaters, $1.1 million for switches and $2.3 million for dispatch consoles, for a total of $11.4 million, of which $8.2 million is projected to be used in the biennium. Schedule Summary Dec. 31, 2012 Budget Expenditures For WBS 4.0 Trunked Radio System, 0 percent of the total budget has been expended to date. $52, % Total Section Budget $11,428,008 Actual Expenditures $52,481 0% Forcast Expenditures $3,331,982 29% Section Budget Remaining $11,375, % $11,375, % Page 14 January No. 28

19 Budget Expenditures (Cont.) Current Expenditures In Millions Activities and Progress Development of the trunked radio system includes three categories of work: repeater and site control equipment, central trunking switches and dispatch consoles. The project continued efforts to prepare equipment for the implementation of Increment Zero, the project s trunked radio test bed. Section 7.0 Planning and Engineering also includes progress on the design efforts related to the trunked radio system. January No. 28 Page 15

20 WBS 5.0 Interoperability Improvements to state interoperability will be captured in this section. The State Interoperability Executive Council is currently heading statewide planning efforts to develop the overarching plan for interoperability in Oregon. Once the SIEC has finalized its plan, the project will initiate work on this effort. The project budget for this section is $2.3 million. No schedule information is currently available. See 7.5 Interoperability Design for progress related to other interoperability activities. Budget Expenditures No expenditures have been made related to interoperability to date. Activities and Progress No procurement, installation or implementation has been initiated for this work section. Page 16 January No. 28

21 WBS 6.0 Partnerships Partnerships were developed between the former OWIN program and local jurisdictions with the intent to reduce costs to both parties. These agreements created interdependency among participants for a functional system. The radio project has identified the partnership groups listed below as including sites that require work to meet the needs associated with these agreements. Schedule Summary Dec. 31, 2012 Budget Expenditures For WBS 6.0 Partnerships, 60 percent of the total budget has been expended to date. Total Section Budget $10,637,665 Actual Expenditures $6,364,861 60% Forcast Expenditures $8,207,987 77% Section Budget Remaining $4,272,804 40% $4,272,804 40% $6,364,861 60% Current Expenditures In Millions January No. 28 Page 17

22 Activities and Progress 6.1 OWIN Obligations For each partnership cluster, forecast and actual progress is reported for the month and for the project cumulatively through December. The following correspond to all tables in this section: Agreements: Umbrella and supplemental agreements executed in a given region. Design phase: Tasks completed from site planning through acquisition of the site building permit. Construction phase: Tasks completed from the acquisition of the building permit to the completion of site construction. Microwave installation phase: All tasks involved in the installation of microwave equipment, from initiation to completion. Microwave installations may occur during a site s construction phase or after it has been completed. Obligation complete: All work has been completed and associated quality reviews have been conducted and work approved. Quality reviews include those conducted by the partner(s), ODOT/OSP Wireless technicians and by representatives of the Oregon Office of Emergency Management Chemical Stockpile Emergency Preparedness Program December 2012 Total to date CSEPP Forecast Actual Forecast Actual Agreements complete Design phase complete Complete 1 1 Construction phase complete Microwave installation phase complete Obligations complete The expected completion date for construction efforts is January Due to weather constraints, the expected completion of microwave installations, and WBS section 6.1.1, is April Lincoln County December 2012 Total to date Lincoln County Forecast Actual Forecast Actual Agreements complete Complete 6 6 Design phase complete Complete 4 4 Construction phase complete Complete 3 3 Microwave installation phase complete Complete 4 4 Obligations complete The final component to complete this section of work is the installation of commercial power at one site. Currently the site is operational by way of back-up power. The expected completion date for WBS section is January Page 18 January No. 28

23 6.1.3 North Coast December 2012 Total to date North Coast Forecast Actual Forecast Actual Agreements complete Design phase complete Construction phase complete Microwave installation phase complete Obligations complete The expected completion date for WBS section is July North Valley December 2012 Total to date North Valley Forecast Actual Forecast Actual Agreements complete Design phase complete Complete 2 2 Construction phase complete Complete 2 2 Microwave installation phase complete Complete 2 2 Obligations complete The remaining agreement which will complete the work necessary for this obligation was slated to be executed during December; however, due to the holiday season, this agreement is expected in early January The revised completion date for WBS section is January Southwest Seven December 2012 Total to date Southwest Seven Forecast Actual Forecast Actual Agreements complete Design phase complete Complete 3 3 Construction phase complete Microwave installation phase complete Obligations complete The overarching agreement with the Southwest Seven was executed during December, delaying the start of construction for those remaining sites. The revised completion date for WBS section is May Klamath County December 2012 Total to date Klamath County Forecast Actual Forecast Actual Agreements complete Design phase complete Complete 3 3 Construction phase complete Microwave installation phase complete Obligations complete The radio project has adjusted the schedule for this section of work to the 2013 build season. This delay is, in part, a result of delays in executing necessary partner agreements and from site changes as requested by the U.S. Forest Service. The revised completion date for WBS section is September January No. 28 Page 19

24 6.1.7 Additional Partnerships December 2012 Total to date Additional Partnerships Forecast Actual Forecast Actual Agreements complete Design phase complete Construction phase complete Microwave installation phase complete Obligations complete The expected completion date for WBS section is June Future Partnerships These sections have been reserved for future partnership-related activities, should the need arise. 6.5 Strategic Technology Reserve Activities related to the deployment of the Strategic Technology Reserve have been completed. Operations of the reserve have been transferred to the ODOT/OSP Wireless Section. Development and implementation of associated intergovernmental agreements between ODOT and outside agencies are under way. These agreements will allow other agencies to use the reserve equipment for training or other non-emergency purposes. Page 20 January No. 28

25 WBS 7.0 Planning & Engineering The planning and engineering section of the work breakdown includes design and development activities associated with the previous WBS sections. Schedule Summary Dec. 31, 2012 Budget Expenditures For WBS 7.0 Planning and Engineering, 52 percent of the total budget has been expended. Total Section Budget $25,176,673 Actual Expenditures $13,164,615 52% Forcast Expenditures $15,820,288 63% Section Budget Remaining $12,012,058 48% $13,164,615 $12,012,058 52% 48% Current Expenditures In Millions January No. 28 Page 21

26 Activities and Progress 7.1 Statewide Planning These activities are captured under 7.5 Interoperability Design and 7.6 Partnership Development. 7.2 Narrowband Planning and Engineering Narrowbanding efforts will continue through summer 2013, in compliance with the radio project s revised narrowband deadline of Nov. 1, Currently, project staff continue to focus efforts on the deployment of narrowband radio equipment and on the further development of the project s narrowband cutover plan. 7.3 Microwave Modernization Engineering During December, two site-to-site microwave design proposals were completed. Staff also developed a draft priority deployment plan for the microwave system. Efforts continued to implement updates to the microwave design and the associated network diagram. Site improvements associated with the microwave modernization effort include pre-design and design phases. The following bullets detail the difference between the phases. Pre-design phase: Tasks completed from inception to approval by the Site Review Committee, the project s change review board. Design phase: Tasks completed from site planning through acquisition of the site building permit. The project estimates construction will take place during the 2013 build season for zones two through six, and during the 2014 season for zones seven through 11. December 2012 Total to date Pre-design Phase Complete Forecast Actual Forecast Actual Maintenance locations 10 sites Infill locations 30 sites Trunked test bed 11 sites Zone 1 core sites 31 sites Zone 2 Bend, trunked 8 sites Zone 3 Columbia River, trunked 9 sites Zone 4 Willamette Valley, trunked 12 sites Zone 5 Interstate 84 corridor 44 sites Zone 6 U.S. 20 & 26 corridor 37 sites Zone 7 Northwest Coast 31 sites Zone 8 Central Coast 21 sites Zone 9 Southwest Coast 17 sites Zone 10 Southwest Interior 20 sites Zone 11 Oregon 140 corridor 11 sites Page 22 January No. 28

27 December 2012 Total to date Design Phase Complete Forecast Actual Forecast Actual Maintenance locations 10 sites Infill locations 30 sites Trunked test bed 11 sites Zone 1 core sites 31 sites Zone 2 Bend, trunked 8 sites Zone 3 Columbia River, trunked 9 sites Zone 4 Willamette Valley, trunked 12 sites Zone 5 Interstate 84 corridor 44 sites Zone 6 U.S. 20 & 26 corridor 37 sites Zone 7 Northwest Coast 31 sites Zone 8 Central Coast 21 sites Zone 9 Southwest Coast 17 sites Zone 10 Southwest Interior 20 sites Zone 11 Oregon 140 corridor 11 sites During December, the project determined that it would hold all design development on sites in zones two, three and four until the trunked radio system design is complete. This resulted in a decrease in the cumulative actual totals for Pre-design Phase Complete and Design Phase Complete. Zones with a decrease in the pre-design phase are: Zone 2 Bend trunked, one site Zone 3 Columbia River trunked, six sites Zone 4 Willamette Valley trunked, eleven sites Zones with a decrease in the design phase complete are: Zone 4 Willamette Vally trunked, two sites 7.4 Trunked Radio System Engineering During December, the project revisited testing and staging acceptance of the Increment Zero equipment, finding that additional work was required. The installation schedule has been revised to begin at the end of January. Draft coverage requirements document was also circulated for review during December. 7.5 Interoperability Design The project has no update to report on the development of an interoperability design. Planning and development of the interoperability design continues to be in the hands of the SIEC. Once the SIEC has established a plan, the project will begin work to develop its implementation strategy. January No. 28 Page 23

28 7.6 Partnership Development Also see 6.0 Partnerships for progress on site-specific work related to previous OWIN obligations. The following bullets correspond to the table below: Agreements: Umbrella and supplemental agreements executed. Design phase: Tasks completed from site planning through acquisition of the site building permit. December 2012 Total to date All OWIN Obligations Forecast Actual Forecast Actual Agreements complete Design phase complete Page 24 January No. 28

29 Staffing & Vendor Summary Full-time state employees and contractors are working on the radio project throughout Oregon. In December, the project employed 26 full-time equivalent state positions Staffing Summary Contract Summary Including historic values of the previous OWIN program, the State Radio Project has spent $71,369,834 of the $121,145,211 currently available across the project s 15 contracts. This represents an overall expenditure of approximately 59 percent. $71,369,834 59% To date in the biennium, $39,865,561 has been spent. This represents 33 percent of the total contract amount available and approximately 44 percent of the contract amount available for the biennium. $49,775,377 41% Percentage of the total contract value expended to the total value of work available January No. 28 Page 25

30 Contract Summary By Vendor $64,700 $2,164,825 $15,743,049 $20,883,679 $951,175 $10,016,838 $11,049,170 $45,201,532 $2,919,347 $70,124 $5,248,028 $681,718 $145,820 $2,863,582 $3,141,625 ABN Engineering ABN Engineering provides supplemental architecture and engineering design services. Activities and Progress No deliverables were submitted during December. AECOM AECOM provides consulting services to the project in the selection and engagement of the radio system contractor (Harris) and provides project and quality management of the radio system. Activities and Progress Planned Actual Delivered draft trunked radio system coverage requirements 1 1 Reviewed and submitted comments on trunked radio system planning documents 3 3 Delivered microwave design proposals, site-to-site 2 2 Delivered revised microwave design proposals, site-to-site 2 2 Page 26 January No. 28

31 State Radio Project meeting attended Planned Actual Radio Vendor Progress Update meetings 3 3 Trunked Radio System Planning and Technical meetings 1 1 Increment Zero Status meetings 1 1 Microwave Update meetings 1 1 Site Review Committee meetings 3 3 Technology Collaboration meeting 3 3 Black & Veatch Black & Veatch provides professional services in connection with the planning, design, engineering and administration for all phases of the project. Activities and Progress Planned Actual NEPA evauations complete 4 2 Site surveys complete 2 2 Construction oversight visits complete 4 6 Harris Corp. Harris provides services, software and equipment for the design, installation and implementation of the project s radio system. Work products generated from these efforts are reported in sections 2.0 Narrowbanding and 7.0 Planning & Engineering. Activities and Progress State Radio Project meeting attended Planned Actual Radio Vendor Progress Update meetings 3 3 Trunked Radio System Planning and Technical meetings 1 1 Increment Zero Status meetings 1 1 HDR Engineering HDR Engineering provides contract management and coordination support services and information systems development support for the project. Activities and Progress Work products generated from these efforts are reported elsewhere in this report. HDR employees provided support in the following areas: Project schedule management, project mapping, environmental analysis and project delivery improvement Planned Actual Site Review Committee meetings 3 3 Technology Collaboration meeting 3 3 Legacy Wireless Legacy Wireless provides personnel resources capable of providing ongoing project management services for the project. Personnel acquired through this contract must have experience with design and construction of telecommunications sites, the implementation of a public safety radio system and the operations of a complex network of microwave systems to transport information. Activities and Progress January No. 28 Page 27

32 Work products generated from these efforts are reported elsewhere in this report. Legacy employees provided support in the following areas: Site project management design through construction Design team coordination State Radio Project meeting attended Planned Actual Increment Zero Status meetings 1 1 Technology Collaboration meeting 3 3 Site Review Committee meetings 3 3 Public Knowledge Public Knowledge provides independent quality management services for the project. Activities and Progress Planned Actual Quarterly Project Status and Improvement Report for Fourth Quarter SAIC SAIC Inc. provides personnel resources similar to those provided by Legacy Wireless. SAIC personnel must have experience with design and construction of telecommunications sites, the implementation of public safety radio systems and the operations of a complex network of microwave systems to transport information. Activities and Progress Work products generated from these efforts are reported elsewhere in this report. SAIC employees provided support in the following areas: Site project management design through construction State Radio Project meeting attended Planned Actual Increment Zero Status meetings 1 1 Technology Collaboration meeting 3 3 Site Review Committee meetings 3 3 Page 28 January No. 28

33 Sites by County For site-specific scope, schedule and budget, see the interactive map at Baker Baker City Maintenance Baker City Patrol Office Baker Scale Beaver Mountain M/W Beaver Ridge OSP Elkhorn Mountain M/W Halfway Hill Lime Hill M/W Lone Pine M/W Richland Maintenance Summit Point Whitney Sand Shed Benton Corvallis Maintenance M/W Mary s Peak M/W OSU Patrol Office Vineyard Hill Clackamas Brightwood Estacada Maintenance Goat Mountain Government Camp Maintenance Government Camp Patrol Office Lawnfield District Maintenance M/W Linhart Butte Milwaukie Maintenance M/W Mount Hood (Timberline) Mount Scott M/W (District 2B) PCC Patrol Office Pete s Mountain Portland Patrol Office Sand Shed (District 2C) Sandy Maintenance Suncrest M/W Clatsop Astoria Area Manager PM Astoria District Office 1 Astoria M/W Astoria Patrol Office Camp Rilea District 1 Bridge Crew Double Peak Humbug Maintenance Nicolai Mountain M/W OSP Seaside 911 Tillamook Head Warrenton M/W Warrenton Maintenance Wickiup Mountain M/W Columbia Clatskanie (County 911 Site) Clatskanie Maintenance Clatskanie Mountain Rainier M/W St Helens Patrol Office Coos Baldy Butte (Coos Bay) Bandon BPA Bennett Butte M/W Blue Ridge North Coos Bay Maintenance M/W Coos Bay Patrol Office Coquille Maintenance M/W Davis Slough Maintenance (Coos Bay) Four Mile Noah Butte Signal Tree (Ram Cell) Signal Tree M/W Crook Barnes Butte Grizzly Mountain M/W (Crook) Powell Butte Prineville Maintenance Prineville Patrol Office Curry Black Mound Bosley Butte Cape Blanco Cape Blanco (Curry) Carpenterville Curry Co Courthouse Edson Butte Gold Beach Maintenance (Hunters Creek) Gold Beach Patrol Office Grizzly Butte (Curry) Harbor Hill Iron Mountain Port Orford Maintenance Stone Butte January No. 28 Page 29

34 Sites by County (Cont.) Deschutes Awbrey Butte Bend District Office 10 Bend Maintenance M/W Bend Patrol Office Brothers Maintenance Hampton Butte La Pine Maintenance Long Butte Long Butte ODOT Mount Bachelor OSP East Headquarters Pine Mountain M/W Region 4 TOC (Bend) Sisters Maintenance Sugar Pine Wampus Butte Wanoga Butte Wanoga Sand Shed Douglas Boswell Springs Maintenance Canyonville Maintenance Chilcoot Mountain Cinnamon Butte Cougar Pass Dean Mountain Debris Hwy 38 Dean Mountain Rd Debris Hwy 38 Scottsburg Dodson Butte M/W Elkton Ridge Harness Mountain (LCSO) Harness Mountain M/W Lemolo Sand Shed Mount Nebo Mount Scott (Klamath) Red Butte Reedsport Maintenance Roman Nose Rose Hill Roseburg Maintenance (Shady) M/W Roseburg Patrol Office Roseburg Region 3 Office Scott Mountain (Douglas) Steamboat Maintenance Yellow Butte Gilliam Arlington Maintenance Arlington Patrol Office Condon Condon Maintenance Grant Aldrich Mountain Austin Maintenance Dixie Butte Fall Mountain M/W John Day M/W Airport John Day Maintenance/Canyon City John Day Patrol Office John Day Scale Tamarack Mountain Harney Beaty s Butte Burns Butte M/W Burns Maintenance Burns Patrol Office Devine Ridge M/W Jack Mountain King Mountain Steen s Mountain Stinkingwater Pass Sand Shed Hood River Cascade Locks Maintenance Cascade Locks POE Debris I-84 M/W Cascade Locks Hood River (CRITFC) Hood River 911 Middle Mountain (US Cellular) Parkdale Maintenance Jackson Ashland Maintenance Ashland POE Central Point Maintenance Halls Point Lincoln Maintenance Sand Shed Medford ODOT M/W Mount Ashland Mount Isabelle OSP SW Headquarters Prospect Maintenance Region 3 TOC (Central Point) Robinson Butte Roxy Ann Mountain M/W SCC/Central Point Dispatch/SW HQ Siskiyou Summit Fill Siskiyou Summit Sand Shed Page 30 January No. 28

35 Sites by County (Cont.) Soda Mountain M/W Starveout Mountain M/W Table Mountain (Jackson) White City Maintenance District M/W Jefferson Agency Plains Deer Ridge, DOC - Madras Gray Butte Madras Maintenance Madras Patrol Office Stephenson Josephine Cave Junction Maintenance Debris US 199 Road Closure Eight Dollar Fiddler Mountain Grants Pass Maintenance Grants Pass Patrol Office Onion Mountain Sexton Mountain M/W Klamath Applegate Butte Chemult Maintenance Chiloquin Maintenance Gilchrist Patrol Office Hamaker Mountain (KCSO) Hamaker Mountain ODOT Hogback Mountain Klamath Falls M/W Klamath Falls Maintenance Klamath Falls Patrol Office Klamath Falls POE Lake of the Woods Maintenance Medicine Mountain M/W Odell Butte Odell Lake Maintenance Pelican Butte Swan Lake Point Walker Mountain M/W (Klamath) Lake Adel Maintenance Adel Remote (Fish Rim) Alkalai Lake Maintenance M/W Black Cap Glass Butte M/W Grizzly Peak M/W (Lake) Lakeview Maintenance M/W Lakeview Patrol Office Picture Rock (DI) M/W Round Pass Silver Lake Maintenance Lane Bear Mountain Blanton Heights Buck Mountain M/W Dead Mountain Florence Maintenance Florence Patrol Office Glenada Ridge Glenwood Maintenance Goodwin Peak Herman Peak McKenzie Bridge Maintenance Mount Hagan Oakridge Maintenance Oakridge Patrol Office Prairie Peak M/W Springfield District Office M/W Springfield Patrol Office Table Rock (Lane) Veneta Maintenance Vida Walker Point (Lane) Wallace Butte Wolf Mountain (ATT) Wolf Mountain Lincoln Cape Perpetua Cape Perpetua (Lincoln) Euchre Mountain Lincoln County Newport Patrol Office Ona Beach Maintenance Rose Lodge Maintenance Saddlebag Table Mountain (Lincoln) Yaquina Head M/W Linn Albany Maintenance Albany Patrol Office Cascadia Green Peter Hoodoo Butte ATC January No. 28 Page 31

36 Sites by County (Cont.) LINN (Cont) Hoodoo Butte M/W McCully Mountain Santiam Junction Maintenance Scott Mountain Lookout (Linn) Snow Peak Sweet Home Maintenance Washburn Butte Malhuer Basque Maintenance Black Butte (Juntura) Blue Mountain Cottonwood Mountain M/W Farewell Bend POE Jordan Valley Maintenance Jordan Valley Patrol Office Juntura Maintenance Mahogany Mountain ODOT District 14 Office Ontario District Office 14 Ontario Maintenance M/W Ontario Patrol Office Pharmacy Hill Snake River, DOC - Ontario Succor Creek Summit Fill Vale Butte M/W Vale Maintenance Vale, District 14 Bridge Crew Marion ARC (Anderson Readiness Center) Capitol Mall Patrol Office Detroit Maintenance Halls Ridge ODOT T-Bldg M/W Oregon Depart of Forestry Oregon Emergency Management Oregon Motor Carrier HQ Oregon State Fire Marshall Prospect, Lower (Hill) M/W Prospect, Main M/W Region 2 TOC (Salem) Salem, Battery Room Salem, District 3 HQ Salem, District Office 3 Salem, Facilities Salem, Maintenance Salem, Material Lab Salem, OSP Office M/W Salem, Patrol Office Salem, PM & Sign Shop Salem, Radio, Bldg D Salem, Region 2 Electrical Bldg T Salem, Region 2 Stripping Salem, Region EOC/ HQ, Bldg B Salem, Repair Shop, Bldg M Salem, State Radio Project Salem, Transport Services Bldg K Salem, Wireless Bldg C State Fairgrounds State Penitentiary, DOC - Salem Wipper M/W Woodburn Maintenance Woodburn POE Morrow Black Mountain (OSP) Black Mountain M/W Boardman Gleason Peak Heppner Maintenance Heppner Patrol Office Jordan Butte Wilkinson Hill Multnomah 200 Market Ashforth Bldg (CRITFC HQ) Baldock Maintenance Barlow Maintenance M/W Council Crest Debris I-84 M/W Troutdale East Portland Maintenance Fremont Bridge M/W Interstate Bridge/Jantzen Beach Multnomah M/W System North Portland, Parkrose Maintenance Portland Bridge Office Portland Region 1 office Region 1 TOC (Portland) Sylvan District Office Maintenance M/W Troutdale District Office Troutdale Maintenance M/W Willatin Tank Polk Bald Mountain (Polk) Doane Creek Eagle Crest Grand Rhonde Maintenance Page 32 January No. 28

37 Sites by County (Cont.) Sherman Moro Maintenance Tillamook Cape Lookout (L190) Cape Meares Debris Field Hwy 6 Tillamook Neahkahnie Tillamook Clatsop Connection Tillamook DMV Maintenance M/W Tillamook Patrol Office Wilson River M/W Umatilla Bone Point Cabbage Hill (CTUIR) Cabbage Hill (US Cell) Cabbage Hill M/W Cold Springs Scalehouse Coombs Canyon Hermiston Maintenance Hermiston Patrol Office Lorenzen Rd (Exit 198) Meacham Maintenance Milton Freewater Patrol Office Mount Weston Mount Weston (Broadcast Building) Pendleton East Pendleton Justice Center Pendleton Maintenance M/W (IH) Pendleton Patrol Office Two Rivers, DOC - Umatilla Ukiah Maintenance Umatilla POE Umatilla Ridge Whitmore Rd Union Elgin Maintenance La Grande Maintenance M/W La Grande Patrol Office La Grande Scales Ladd Canyon Mount Emily M/W Mount Fanny Spout Springs Fill Wallowa Devil s Ridge Enterprise Maintenance Enterprise Patrol Office Flora Fill Station Howard Butte Mount Howard Wallowa Visitor Center Wasco Criterion Summit M/W Foremans Point Hulse Ranch M/W Kaser Maupin Maintenance Shaniko The Dalles East (US Cell) The Dalles Maintenance M/W The Dalles Patrol Office Tygh Ridge Warm Springs Maintenance Wasco Butte M/W Washington Banks Patrol Office Beaverton Area Manager PM Buxton Mountain M/W Cedar Hills Coffee Creek, DOC - Wilsonville Debris Field Hwy 6 Banks Manning Maintenance North Plains Patrol Office Round Top Tualatin Patrol Office Wheeler Keyes Mountain FTN Keyes Summit (Mitchell Remote) Mount Pisgah Rancharea Rock Spray Maintenance Yamhill Boulder Crest Chehalem Mountain M/W High Heaven McMinnville Maintenance Station McMinnville Patrol Office Mount Hebo M/W Mount Hebo South Point Newberg Maintenance January No. 28 Page 33

38 Sites by County (Cont.) Out-of-Oregon Augspurger Mountain M/W (CRITFC) Augspurger Mountain M/W (US Cell) Biddle Butte Golgotha Butte Golgotha Butte (BCES) Green Mountain Haystack Butte M/W Juniper (Klickitat) Megler (Chinook) Megler Bridge (Astoria) Roosevelt Mountain M/W Sheepy Ridge Sillusi Butte (BCES) Sillusi Butte Fill Skamania Mountain M/W Stacker Butte M/W Underwood Page 34 January No. 28

39 Project Cost Summary Original Budget 9/07/2011 Project Budget Revised Budget as of 12/31/12 Change in Budget through 12/31/12 Budget Biennium Budget Funds Spent through 12/31/2012 Balance Narrowbanding Repeaters 6,100,000 4,816,967 (1,283,033) 5,639,526 2,154,936 3,484,590 Office Remotes 2,000,000 1,990,450 (9,550) 1,990,450 32,685 1,957,765 Hand Helds/Portables 33,200,000 24,412,290 (8,787,710) 24,412,290 15,625,858 8,786,432 Cutover/Testing - 352, , , ,200 Site Work 6,600,000 - (6,600,000) Narrowbanding Subtotal 47,900,000 31,571,907 (16,328,093) 32,394,466 17,813,479 14,580,987 Microwave Modernization Purchase & Installation 29,300,000 12,985,000 (16,315,000) 7,672,955 96,295 7,576,659 Network 5,644,000 5,644,000 4,310,909 3,422, ,806 Site Improvements 38,950,000 36,199,562 (2,750,438) 2,721, ,517 1,873,751 Microwave Modernization Subtotal 68,250,000 54,828,562 (13,421,438) 14,705,132 4,365,916 10,339,216 Trunking Receivers 5,250,000 7,940,072 2,690,072 4,764,043 1,005 4,763,038 Switches 1,143,545 1,143,545 1,143,545 49,621 1,093,924 Consoles 1,400,000 2,344, ,391 2,344,391 1,855 2,342,536 Trunking Subtotal 6,650,000 11,428,008 4,778,008 8,251,979 52,481 8,199,498 Interoperability Procurement & Installation 2,300,000 2,300, Interoperability Subtotal 2,300,000 2,300, Partnerships Construction 10,400,000 10,637, ,665 9,885,313 6,364,861 3,520,452 Partnerships Subtotal 10,400,000 10,637, ,665 9,885,313 6,364,861 3,520,452 Engineering Narrowbanding 1,300,000 1,295,410 (4,590) 863,607 1,188,548 (324,942) Microwave Modernization 17,750,000 16,457,901 (1,292,099) 10,971,934 7,578,737 3,393,197 Trunking 1,850,000 6,114,062 4,264,062 6,114,062 2,572,333 3,541,729 Interoperability - 437, , , ,010 (553,710) Partnerships 872, , , , ,092 COPS Grant ,745 (536,745) Engineering Subtotal 25,176,673 4,276,673 18,968,236 13,164,615 5,803,621 Totals by Phase Narrowbanding 49,200,000 32,867,317 (16,332,683) 33,258,073 19,002,028 14,256,045 Microwave Modernization 86,000,000 71,286,463 (14,713,537) 25,677,066 12,213,026 13,464,040 Trunking 8,500,000 17,542,070 9,042,070 14,366,041 2,624,815 11,741,227 Interoperability 2,300,000 2,737, , ,300 1,259,382 (822,082) Partnerships 10,400,000 11,509,665 1,109,665 10,466,646 6,662,102 3,804,544 Subtotal 156,400, ,942,815 (20,457,185) 84,205,126 41,761,353 42,443,773 Project Management - 10,242,803 10,242,803 8,205,791 5,139,972 3,065,819 Contingency - 8,301,737 8,301,737 2,950,252-2,950,252 Total State Radio Project 156,400, ,487,356 (1,912,644) 95,361,169 46,901,325 48,459,844 Old OWIN Project Spending 45,000,000 49,256,733 4,256,733 Treasury Loan 8,000,000 6,247,831 (1,752,169) Total Old OWIN 53,000,000 55,504,564 2,504,564 Grand Total 209,400, ,991, ,920 January No. 28 Page 35

40 Estimated Project Cash Flow Page 36 January No. 28

Cover photo: Smoke from a nearby wildfire is visible from the Lime Hill radio site in Baker County. A crew from Summit Solutions Group was on site

Cover photo: Smoke from a nearby wildfire is visible from the Lime Hill radio site in Baker County. A crew from Summit Solutions Group was on site AUGUST 2015 MONTHLY PROGRESS REPORT Cover photo: Smoke from a nearby wildfire is visible from the Lime Hill radio site in Baker County. A crew from Summit Solutions Group was on site recently to tighten

More information

State Radio Project. July Monthly Progress Report

State Radio Project. July Monthly Progress Report State Rad o Project State Radio Project July 2013 Monthly Progress Report Project Goals Infrastructure Repair or replace critical components of Oregon s deteriorating state radio network and extend the

More information

Cover photo: Snow blanketed the State Radio Project s Mount Aldrich site in early November. The Grant County site sits at nearly 7,000 feet in

Cover photo: Snow blanketed the State Radio Project s Mount Aldrich site in early November. The Grant County site sits at nearly 7,000 feet in DECEMBER 2015 MONTHLY PROGRESS REPORT Cover photo: Snow blanketed the State Radio Project s Mount Aldrich site in early November. The Grant County site sits at nearly 7,000 feet in elevation. State Radio

More information

Cover photo: From the conference room between the Oregon State Police Northern Command Center and the Oregon Department of Transportation Northwest

Cover photo: From the conference room between the Oregon State Police Northern Command Center and the Oregon Department of Transportation Northwest NOVEMBER 2015 MONTHLY PROGRESS REPORT Cover photo: From the conference room between the Oregon State Police Northern Command Center and the Oregon Department of Transportation Northwest Transportation

More information

State Rad o Project STATE RADIO PROJECT. Monthly Progress Report. January 2015

State Rad o Project STATE RADIO PROJECT. Monthly Progress Report. January 2015 State Rad o Project STATE RADIO PROJECT January 2015 Monthly Progress Report PROJECT GOALS INFRASTRUCTURE Repair or replace critical components of Oregon s deteriorating state radio network and extend

More information

State Radio Project. January Monthly Progress Report

State Radio Project. January Monthly Progress Report State Rad o Project State Radio Project January 2014 Monthly Progress Report Project Goals Infrastructure Repair or replace critical components of Oregon s deteriorating state radio network and extend

More information

State Rad o Project STATE RADIO PROJECT. Monthly Progress Report. April 2015

State Rad o Project STATE RADIO PROJECT. Monthly Progress Report. April 2015 State Rad o Project STATE RADIO PROJECT April 2015 Monthly Progress Report PROJECT GOALS INFRASTRUCTURE Repair or replace critical components of Oregon s deteriorating state radio network and extend the

More information

State Radio Project. May Monthly Progress Report

State Radio Project. May Monthly Progress Report State Rad o Project State Radio Project May 2012 Monthly Progress Report PROject GOALS Infrastructure Repair or replace critical components of Oregon s deteriorating state radio network and extend the

More information

Sept 28, Mukhtar mook-tar Thakur

Sept 28, Mukhtar mook-tar Thakur MnDOT Office of Statewide Radio Communications (OSRC) Overview -Summary and ARMER Status Update Central Region Summit- Alexandria, MN Sept 28, 2016 Mukhtar mook-tar Thakur The Office of Statewide Radio

More information

OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT. Implementation Plan (Deliverable 13-A)

OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT. Implementation Plan (Deliverable 13-A) OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT Implementation Plan (Deliverable 13-A) Prepared by: Federal Engineering, Inc. 10600 Arrowhead Dr, Suite 160 Fairfax, VA 22030 703 359-8200 December

More information

Public Safety Interoperable Communications (PSIC)

Public Safety Interoperable Communications (PSIC) State of New Mexico Department of Information Technology 2013 National Association of State Chief Information Officers State IT Recognition Awards Public Safety Interoperable Communications (PSIC) Category:

More information

2 ESF 2 Communications. (includes Alert and Warning)

2 ESF 2 Communications. (includes Alert and Warning) 2 ESF 2 Communications (includes Alert and Warning) THIS PAGE LEFT BLANK INTENTIONALLY Table of Contents 1 Purpose... ESF 2-1 2 Scope... ESF 2-1 3 Roles and Responsibilities... ESF 2-2 3.1 Primary Agencies...

More information

EMERGENCY COMMUNICATIONS

EMERGENCY COMMUNICATIONS EMERGENCY COMMUNICATIONS FY2004-2010 1. BACKGROUND ISSUES The Emergency Communications element of the capital plan is comprised of three projects concerning emergency radio communications, computer aided

More information

Wyoming s Statewide Public-Safety Interoperable Radio Communications System WyoLink Frequently Asked Questions (FAQ)

Wyoming s Statewide Public-Safety Interoperable Radio Communications System WyoLink Frequently Asked Questions (FAQ) Wyoming s Statewide Public-Safety Interoperable Radio Communications System WyoLink Frequently Asked Questions (FAQ) Goals... 2 1. What is WyoLink supposed to accomplish?... 2 2. Who will oversee WyoLink

More information

OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT. Conceptual Design for Radio System, Revision 1 (November 30, 2006) (Deliverable 9-D)

OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT. Conceptual Design for Radio System, Revision 1 (November 30, 2006) (Deliverable 9-D) OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT Conceptual Design for Radio System, Revision 1 () (Deliverable 9-D) Prepared by: Federal Engineering, Inc. 10600 Arrowhead Drive, Suite 160 Fairfax,

More information

Radio Technology Overview. January 2011

Radio Technology Overview. January 2011 Radio Technology Overview January 2011 Presentation Objectives The objective of this presentation is to: Review terms as related to radio technology Review the challenges facing the City o FCC mandate

More information

Radio System Replacement Project

Radio System Replacement Project Radio System Replacement Project City Council Briefing December 6, 2017 William Finch, Chief Information Officer, Communication & Information Services Presentation Overview Background Procurement Process

More information

PALMETTO 800 History Project Cost

PALMETTO 800 History Project Cost PALMETTO 800 South Carolina has implemented the largest statewide emergency communications radio system in the nation. With over twenty thousand users, the system is available to federal, state, and local

More information

Statewide 800 MHz trunked radio system available for all emergency responders (local, State, Federal)

Statewide 800 MHz trunked radio system available for all emergency responders (local, State, Federal) Statewide 800 MHz trunked radio system available for all emergency responders (local, State, Federal) Goal: 95% in-street portable coverage based on a 3 watt portable radio Network infrastructure consisting

More information

Proposed Action Hutch Mountain Communications Site Coconino National Forest June 2016

Proposed Action Hutch Mountain Communications Site Coconino National Forest June 2016 Proposed Action Hutch Mountain Communications Site Coconino National Forest June 2016 PURPOSE AND NEED The proposed Hutch Mountain Communications Site project is part of a broader wireless industry strategy

More information

2-800 MHz CCCS Sys Extension

2-800 MHz CCCS Sys Extension 2-800 MHz CCCS Sys Extension 1. Program Area: PUBLIC PROTECTION 2. Identify agencies and departments involved. Sheriff-Coroner. 3. Is the Strategic Priority new or previously identified in an earlier Strategic

More information

9-800 MHz Countywide Coordinated Communications System (CCCS) Upgrade

9-800 MHz Countywide Coordinated Communications System (CCCS) Upgrade 9-800 MHz Countywide Coordinated Communications System (CCCS) Upgrade 1. Program Area: PUBLIC PROTECTION 2. Identify agencies and departments involved. Sheriff-Coroner 3. Is the Strategic Priority new

More information

Guide for Short Term Interoperability Revised June 24, 2009

Guide for Short Term Interoperability Revised June 24, 2009 Oregon State Interoperability Executive Council Guide for Short Term Interoperability Revised The Oregon State Interoperability Executive Council (SIEC) and the State of Oregon encourage Oregon s public

More information

Guide for Short Term Interoperability

Guide for Short Term Interoperability Oregon State Interoperability Executive Council Guide for Short Term Interoperability Adopted: by the SIEC Technical Committee The Oregon State Interoperability Executive Council (SIEC) and the State of

More information

ESF 2. Communications

ESF 2. Communications ESF 2 Communications This page left blank intentionally. 1 Introduction: Purpose and Scope ESF 2 organizes, establishes, and maintains the communications capabilities among appropriate agencies/entities

More information

Ernie B. McNeely, Township Manager Michael J. McGrath, Superintendent of Police Lower Merion Township Radio System Replacement DATE: June 25, 2014

Ernie B. McNeely, Township Manager Michael J. McGrath, Superintendent of Police Lower Merion Township Radio System Replacement DATE: June 25, 2014 EXHIBIT B TOWNSHIP OF LOWER MERION POLICE DEPARTMENT DEPARTMENTAL MEMORANDUM INTEGRITY PROFESSIONALISM RESPECT TO: FROM: SUBJECT: Ernie B. McNeely, Township Manager Michael J. McGrath, Superintendent of

More information

Public Safety Communications Commission

Public Safety Communications Commission Public Safety Communications Commission Report to Governor and Joint Transportation, Highways and Military Affairs Committee June 2017 Matthew H. Mead Governor Wyoming Public Safety Communications Commission

More information

IFERN / IFERN 2 Radio Base Stations for all Wisconsin MABAS Divisions/Counties

IFERN / IFERN 2 Radio Base Stations for all Wisconsin MABAS Divisions/Counties Project Name IFERN / IFERN 2 Radio Base Stations for all Wisconsin MABAS Divisions/Counties Sponsoring Agency MABAS Wisconsin - The Mutual Aid Box Alarm System (known as MABAS) Senate Bill SB 642 was approved

More information

TOPAZ Regional Wireless Cooperative (TRWC) Board of Directors

TOPAZ Regional Wireless Cooperative (TRWC) Board of Directors Date: September 6, 8 To: Through: From: Subject: TOPAZ Regional Wireless Cooperative (TRWC) Board of Directors Dale Shaw, TRWC Executive Director Randy Thompson Administrator Update Capital Projects )

More information

SERS primary mission was to design, purchase, build and operate a county-wide 800 MHz radio system along with supporting infrastructure and

SERS primary mission was to design, purchase, build and operate a county-wide 800 MHz radio system along with supporting infrastructure and * Established in 1999 * The Snohomish County Emergency Radio System SERS Mission SERS primary mission was to design, purchase, build and operate a county-wide 800 MHz radio system along with supporting

More information

Radio Communications Essentials. Module 9: Narrowbanding Pete Peterson

Radio Communications Essentials. Module 9: Narrowbanding Pete Peterson Radio Communications Essentials Module 9: Narrowbanding Pete Peterson 1 Topics Why is it Necessary? Who is Affected? Key Deadlines & Exceptions What are the Challenges? Sample Steps to Narrowband Frequently

More information

MINUTES REGULAR COMMISSION MEETING THE PORT OF PORTLAND January 9, 2008

MINUTES REGULAR COMMISSION MEETING THE PORT OF PORTLAND January 9, 2008 1 MINUTES REGULAR COMMISSION MEETING THE PORT OF PORTLAND January 9, 2008 In response to due notice, the regular meeting of the Commissioners of the Port of Portland was held at 9:00 a.m. in the Commission

More information

Attachment C to Modification # 6 to VA HSMM. Schedule of Fees

Attachment C to Modification # 6 to VA HSMM. Schedule of Fees Task A. Perform radio asset inventory, needs assessment, and project expected growth. B. Document existing radio frequency authorizations. Devise a frequency reuse strategy. Determine the capacity of the

More information

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017 NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP 697-16-016 July 28, 2017 Reference is made to the Request for Proposal (RFP) to Service Providers for Nevada Shared Radio Replacement Project, upon

More information

2 ESF 2 Communications

2 ESF 2 Communications 2 ESF 2 Communications THIS PAGE LEFT BLANK INTENTIONALLY ESF 2 Communications Table of Contents 1 Purpose and Scope... ESF 2-1 2 Policies and Agreements... ESF 2-1 3 Situation and Assumptions... ESF 2-1

More information

Public Safety Radio Communications System Update. Presented by Steve Streiffert Assistant Director, IT Solutions May 10, 2011

Public Safety Radio Communications System Update. Presented by Steve Streiffert Assistant Director, IT Solutions May 10, 2011 Public Safety Radio Communications System Update Presented by Steve Streiffert Assistant Director, IT Solutions May 10, 2011 Purpose Review state of the current radio system Council to consider M&C P11234

More information

Resolution Authorizing Expenditure Appropriations to Purchase Radio Equipment and Facilitate Infrastructure R56 Grounding Work

Resolution Authorizing Expenditure Appropriations to Purchase Radio Equipment and Facilitate Infrastructure R56 Grounding Work CITY OF MARTINEZ CITY COUNCIL AGENDA March 21, 2012 TO: FROM: SUBJECT: Mayor and City Council Gary D. Peterson, Chief of Police Resolution Authorizing Expenditure Appropriations to Purchase Radio Equipment

More information

EVALUATING AN ADAPTIVE SIGNAL CONTROL SYSTEM IN GRESHAM. James M. Peters, P.E., P.T.O.E., Jay McCoy, P.E., Robert Bertini, Ph.D., P.E.

EVALUATING AN ADAPTIVE SIGNAL CONTROL SYSTEM IN GRESHAM. James M. Peters, P.E., P.T.O.E., Jay McCoy, P.E., Robert Bertini, Ph.D., P.E. EVALUATING AN ADAPTIVE SIGNAL CONTROL SYSTEM IN GRESHAM James M. Peters, P.E., P.T.O.E., Jay McCoy, P.E., Robert Bertini, Ph.D., P.E. ABSTRACT Cities and Counties are faced with increasing traffic congestion

More information

EXHIBIT 2 Page 1 of 5 Reasonable Necessity for Eminent Domain Action Tuttle Property Final Report PREPARED JANUARY 2018 FOR BROWARD COUNTY, FLORIDA MissionCriticalPartners.com State College Office 690

More information

INTERNAL AUDIT DIVISION CLERK OF THE CIRCUIT COURT

INTERNAL AUDIT DIVISION CLERK OF THE CIRCUIT COURT INTERNAL AUDIT DIVISION CLERK OF THE CIRCUIT COURT AUDIT OF EMERGENCY COMMUNICATIONS DEPARTMENT INTERGOVERNMENTAL RADIO PROGRAM Ken Burke, CPA* Clerk of the Circuit Court Ex Officio County Auditor Robert

More information

Columbia Communications District Request for Information New Radio Communications System

Columbia Communications District Request for Information New Radio Communications System Columbia 9-1-1 Communications District Request for Information New Radio Communications System Submission Deadline January 2, 2018 1 1 Overview 1.1 Introduction The Columbia 911Communications District

More information

SUBJECT: MARIN EMERGENCY RADIO AUTHORITY (MERA) NEXT GENERATION

SUBJECT: MARIN EMERGENCY RADIO AUTHORITY (MERA) NEXT GENERATION STAFF REPORT MEETING DATE: August 20, 2013 TO: City Council 75 Rowland Way #200 Novato, CA 94945-3232 (415) 899-8900 FAX (415) 899-8213 www.novato.org FROM: James Berg, Chief of Police SUBJECT: MARIN EMERGENCY

More information

Current Systems. 1 of 6

Current Systems. 1 of 6 Current Systems Overview Radio communications within the State of California s adult correctional institutions are vital to the daily safety and security of the institution, staff, inmates, visitors, and

More information

The Professional Consulting Services Communications Consultant E-911. Design Alternatives

The Professional Consulting Services Communications Consultant E-911. Design Alternatives The Communications Consultant E-911 Sullivan County, New York April 21, 2010 Table of Contents 1. OVERVIEW... 4 2. TECHNOLOGY OPTIONS... 5 2.1 Analog Conventional... 5 2.2 Project 25 Conventional... 5

More information

CACFP After School Meal & Snack Programs Schools with 50% Free and Reduced Eligibility

CACFP After School Meal & Snack Programs Schools with 50% Free and Reduced Eligibility CACFP After School Meal & Snack Programs Schools with 50% Free and Reduced Eligibility BAKER BAKER SCH DIST 05J Brooklyn Elementary School 0.6226 BAKER BAKER SCH DIST 05J Haines Elementary School 0.5309

More information

SAN DIEGO COUNTY MUTUAL AID RADIO PLAN

SAN DIEGO COUNTY MUTUAL AID RADIO PLAN ATTACHMENT A SAN DIEGO COUNTY MUTUAL AID RADIO PLAN 1.1 General Mutual aid channels are a critical part of San Diego County's radio system requirements. The San Diego County Mutual Aid Radio Plan will

More information

Public Safety Radio System. August 6, 2018

Public Safety Radio System. August 6, 2018 Public Safety Radio System August 6, 2018 Project overview Phase I Needs Assessment Coverage Capacity Resiliency & Redundancy Interoperability Encryption Phase II RFP Development Response Review Selection

More information

Business Plan Summary

Business Plan Summary Owner: 2012-2016 Business Plan Summary Program Corporate, Operational & Council Services Service grouping Corporate Services Service Type Internal Service Mike Bushby Division Manager Fleet Services and

More information

STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah

STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah I. Introduction STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah The Bureau of Land Management s (BLM) St. George Field Office (SGFO) requires

More information

Pennsylvania STARNet NASCIO Awards Information Communications Technology Innovation Commonwealth of Pennsylvania

Pennsylvania STARNet NASCIO Awards Information Communications Technology Innovation Commonwealth of Pennsylvania Information Communications Technology Innovation Commonwealth of Pennsylvania Executive Summary In the mid-1990s, the Commonwealth of Pennsylvania faced the prospect of replacing an aging analog radio

More information

CACFP Tiering Schools with >50% Free and Reduced Eligibility Data Collected : 10/31/2006 Effective March 1, 2007 to February 28, 2008

CACFP Tiering Schools with >50% Free and Reduced Eligibility Data Collected : 10/31/2006 Effective March 1, 2007 to February 28, 2008 CACFP Tiering Schools with >50% Free and Reduced Eligibility Data Collected : 10/31/2006 Effective March 1, 2007 to February 28, 2008 BAKER BURNT RIVER SCH DIST 30J Burnt River School BAKER HUNTINGTON

More information

January 11, 2012 #

January 11, 2012 # Suite 1250 999 West Hastings Street Vancouver BC CANADA V6C 2W2 Tel: 1.778.724.4700 Fax: 1.604.558.7400 January 11, 2012 #2012-02 Midas Gold Outlines Initial Work Plan & Budget for its Golden Meadows Project,

More information

Paul Levesque, Executive Assistant Cornelia Glenn, Recording Secretary

Paul Levesque, Executive Assistant Cornelia Glenn, Recording Secretary Page 1 COMMISSIONERS PRESENT: STAFF PRESENT: Ken Burdick, Chairperson Gina Mulford, Vice Chairperson Jerry Dove, Commissioner Paul Levesque, Executive Assistant Cornelia Glenn, Recording Secretary STAFF

More information

Communications Interoperability- Current Status

Communications Interoperability- Current Status Communications Interoperability- Current Status Stephen Mitchell Abstract Over the past decade, the public-safety community in partnership with local, state, and federal agencies have worked to develop

More information

TRAINING BULLETIN. EFFECTIVE DATE: 05/06 DOC NO: TB198 CROSS REF: Communications Checklists

TRAINING BULLETIN. EFFECTIVE DATE: 05/06 DOC NO: TB198 CROSS REF: Communications Checklists INTRODUCTION Communications Support 131 (CS131) is an important asset of the District and plays a significant role in the county and region. The unit has many communications assets, including radios on

More information

Eaton County Public Safety Radio System Recommendation

Eaton County Public Safety Radio System Recommendation Eaton County Public Safety Radio System Recommendation AUGUST 1, 2017 EATON COUNTY CENTRAL DISPATCH RADIO SYSTEM ADVISORY WORKGROUP TABLE OF CONTENTS Executive Summary... 3 Overview of the Radio System

More information

MEMA Narrowbanding Planning Primer

MEMA Narrowbanding Planning Primer 1. The State of Maine is required to narrowband its public safety communications radios, as are all county and local governments, in accordance with the Federal Communications Commission (FCC) mandate,

More information

Narrow-banding What It Means to Public Safety Webinar

Narrow-banding What It Means to Public Safety Webinar Narrow-banding What It Means to Public Safety Webinar Rick Mulvihill Director Presenters Charlie Stephenson Director of Outreach and Technology Assistance Robert Rhoads Office of Emergency Communications,

More information

The Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250)

The Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250) The Office of the Finance and Purchasing Manager Telephone : (250) 352-8204 Fax : (250) 352-6594 REQUEST FOR PREQUALIFICATIONS RADIO COMMUNICATIONS INFRASTRUCTURE UPGRADE CONTRACTOR SERVICES 2018-PRQ-01

More information

[LLOR L DP0000.LXSSH X.HAG ] Notice of Availability of the Draft Resource Management Plan/Environmental

[LLOR L DP0000.LXSSH X.HAG ] Notice of Availability of the Draft Resource Management Plan/Environmental This document is scheduled to be published in the Federal Register on 10/05/2018 and available online at https://federalregister.gov/d/2018-21629, and on govinfo.gov 4310-33 DEPARTMENT OF THE INTERIOR

More information

Interoperable Communication Sustainment

Interoperable Communication Sustainment Georgia Emergency Management Agency Homeland Security Interoperable Communication Sustainment Nick Brown Statewide Interoperable Communication Coordinator (SWIC) April 7 2015 What drives our Interoperability

More information

ESF 2. Communications

ESF 2. Communications ESF 2 Communications This page left blank intentionally. 1 Introduction: Purpose and Scope ESF 2 organizes, establishes, and maintains the communications capabilities among appropriate agencies/entities

More information

BEFORE THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES COUNTY, OREGON * * * *

BEFORE THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES COUNTY, OREGON * * * * REVIEWED LEGAL COUNSEL For Recording Stamp Only BEFORE THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES COUNTY, OREGON An Ordinance Amending Deschutes County Code Title 18 to Provide a Definition of Agricultural

More information

PLANNING DIVISION COMMUNITY & NEIGHBORHOODS DEPARTMENT

PLANNING DIVISION COMMUNITY & NEIGHBORHOODS DEPARTMENT Staff Report PLANNING DIVISION COMMUNITY & NEIGHBORHOODS DEPARTMENT To: Salt Lake City Administrative Hearing Officer From: Casey Stewart; 801-535-6260 Date: Re: September 22, 2017 (for September 28 Administrative

More information

ANNUAL REPORT 60 YEARS OF SERVICE

ANNUAL REPORT 60 YEARS OF SERVICE 60 YEARS 2016 ANNUAL REPORT 60 YEARS OF SERVICE In 1956, a group of ten educators gathered together to form a credit union with the idea that together, they were stronger. Today, that group has grown into

More information

III. APPROVAL OF MINUTES: December 8 th, 2009 M/S Williams/Iverson to accept as submitted. All ayes.

III. APPROVAL OF MINUTES: December 8 th, 2009 M/S Williams/Iverson to accept as submitted. All ayes. MINUTES FOR A MEETING OF THE ASHLAND FOREST LANDS COMMISSION Tuesday, January 12th, 2010 5:30PM to 7:30PM Siskiyou Room, Community Development Building 51 Winburn Way I. CALL TO ORDER: 5:30 PM II. INTRODUCTIONS

More information

MEMBERS ABSENT Buffalo Grove Fire Department, Rolling Meadows Fire Department.

MEMBERS ABSENT Buffalo Grove Fire Department, Rolling Meadows Fire Department. MINUTES OF THE REGULAR MEETING OF THE EXECUTIVE COMMITTEE OF THE NORTHWEST CENTRAL DISPATCH SYSTEM, HELD IN THE MOUNT PROSPECT VILLAGE HALL, MOUNT PROSPECT, COOK COUNTY, ILLINOIS, ON THURSDAY, MARCH 21,

More information

I-5 Bridge Replacement Project

I-5 Bridge Replacement Project I-5 Bridge Replacement Project Joint Interim Committee on Interstate 5 Bridge Replacement Oregon State Capitol Salem, Oregon January 14, 2014 Matthew Garrett, Director Oregon Department of Transportation

More information

Small Cell Infrastructure in Denver

Small Cell Infrastructure in Denver September 2017 Small Cell Infrastructure in Denver The City and County of Denver is receiving growing numbers of requests from wireless providers and wireless infrastructure companies to construct small

More information

Ingham County Request for Proposals Public Safety Radio System Project Manager and Consulting Services Packet #120-18

Ingham County Request for Proposals Public Safety Radio System Project Manager and Consulting Services Packet #120-18 Ingham County Request for Proposals Public Safety Radio System Project Manager and Consulting Services Packet #120-18 ADDENDUM NO. 1 The following clarifications, modifications and/or revisions to the

More information

SHARED COMMUNICATIONS 40,000 8,500 SERVICES FOR OHIO PUBLIC

SHARED COMMUNICATIONS 40,000 8,500 SERVICES FOR OHIO PUBLIC MARCS TODAY Statewide, robust, stable platform STATE OF OHIO MARCSIP Business Plan/Rollout May 9, 2012 Ohio APCO/NENA Combined Chapter Business Meeting Over 40,000 radios activated Originally designed

More information

Steven W. Jennings, CIO Harris County ITC

Steven W. Jennings, CIO Harris County ITC Steven W. Jennings, CIO Harris County ITC Harris County operates an 800 MHz Motorola Multi-cast SmartZone Regional Radio System that supports 33,000 users in 512 departments in the region, covering nine

More information

Missouri FY 10 Interoperable Grant Guideline Definition and Examples of Eligible Procurement

Missouri FY 10 Interoperable Grant Guideline Definition and Examples of Eligible Procurement Missouri FY 10 Interoperable Grant Guideline Definition and Examples of Eligible Procurement Missouri grant guidelines for interoperable communications equipment are changing for fiscal year 2010. Based

More information

Amateur Radio Emergency Communications Interoperability Plan

Amateur Radio Emergency Communications Interoperability Plan Amateur Radio Emergency Communications Interoperability Plan Washington State Regional Homeland Security Coordination District IV Clark County Cowlitz County Skamania County Wahkiakum County v1.0 adopted:

More information

HOUSE COMMITTEE ON VETERANS AND EMERGENCY PREPAREDNESS

HOUSE COMMITTEE ON VETERANS AND EMERGENCY PREPAREDNESS HOUSE COMMITTEE ON VETERANS AND EMERGENCY PREPAREDNESS MAY 16, 2017 TESTIMONY BY JOHN CORE, OREGON SECTION AMERICAN RADIO RELAY LEAGUE ON THE AMATEUR RADIO EMERGENCY SERVICE PURPOSE: REVIEW POSSIBLE POLICIES

More information

Oregon 2016 Row by Row Experience ~ Home Sweet Home ~

Oregon 2016 Row by Row Experience ~ Home Sweet Home ~ Bolts To Blocks 133 Broadalbin SW Albany, OR 97321 541-704-0386 The Quilt Loft 405 1st Ave. W Albany, OR 97321 541-928-7242 Aloha Sewing & Vacuum 18335 SW TV Hwy Aloha, OR 97003 503-649-6050 Sew Creative

More information

Allied Radio Matrix for Emergency Response (ARMER) Standards, Protocols, Procedures

Allied Radio Matrix for Emergency Response (ARMER) Standards, Protocols, Procedures Allied Radio Matrix for Emergency Response (ARMER) Standards, Protocols, Procedures Document Section: 3 Interoperability Standards Status: Complete Sub Section: State Procedure Title: 800 MHz Statewide

More information

Narrowbanding and Public Safety Communications

Narrowbanding and Public Safety Communications Narrowbanding and Public Safety Communications Introduction and Overview Jay Sexton Georgia Tech Research Institute Introductions What equipment is used on every call by every public safety responder?

More information

Orange County Sheriff s Department. Jo Ann Galisky Assistant Sheriff

Orange County Sheriff s Department. Jo Ann Galisky Assistant Sheriff Orange County Sheriff s Department Jo Ann Galisky Assistant Sheriff Orange County Demographics 798 Square Miles 34 cities 42 Miles of coastline Population- 2,978,800 2 nd largest county in California in

More information

Federal Partnership for Interoperable Communications

Federal Partnership for Interoperable Communications Federal Partnership for Interoperable Communications Overview, Interoperability Efforts, and P25 Alaska Interoperability Communications Summit July 2006 The (FPIC) serves as a coordination body to address

More information

Datacasting for Public Safety Access to Enhanced Technology via Public Television

Datacasting for Public Safety Access to Enhanced Technology via Public Television Datacasting for Public Safety Access to Enhanced Technology via Public Television Thursday, January 17, 2019 2:00 3:30 PM Eastern Time Zone Conference Line: (510) 227-1018 Conference ID: 446 1830 Screen

More information

Joint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building

Joint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building Joint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building City of Tacoma Steve Victor, Deputy City Attorney 253-591-5638 svictor@ci.tacoma.wa.us Pierce

More information

The work under the Environment under Review subprogramme focuses on strengthening the interface between science, policy and governance by bridging

The work under the Environment under Review subprogramme focuses on strengthening the interface between science, policy and governance by bridging The work under the Environment under Review subprogramme focuses on strengthening the interface between science, policy and governance by bridging the gap between the producers and users of environmental

More information

Follow the Yellow Brick Road

Follow the Yellow Brick Road NDCEE National Defense Center for Environmental Excellence National Defense Center for Environmental Excellence TRANSFERRING TECHNOLOGY SOLUTIONS Supporting Readiness, Sustainability, and Transformation

More information

This page is intentionally left blank

This page is intentionally left blank This page is intentionally left blank This page is intentionally left blank MnDOT Metro District Fact Sheet Mpls./St. Paul District Offices: Roseville-Water's Edge (HQ), Golden Valley, Oakdale mndot.gov/metro/

More information

Quiet Recreation on BLM-Managed Lands in Southwest Utah: Economic Contribution Prepared for The Pew Charitable Trusts July 2017

Quiet Recreation on BLM-Managed Lands in Southwest Utah: Economic Contribution Prepared for The Pew Charitable Trusts July 2017 Quiet Recreation on BLM-Managed Lands in Southwest Utah: Economic Contribution 2015 Prepared for The Pew Charitable Trusts July 2017 This page left intentionally blank CONTACT Kristin Lee, Austin Rempel,

More information

POSITION DESCRIPTION

POSITION DESCRIPTION State of Michigan Civil Service Commission Capitol Commons Center, P.O. Box 30002 Lansing, MI 48909 Position Code 1. RACCTCHE POSITIO DESCRIPTIO This position description serves as the official classification

More information

West Region Wildfire Council Meeting Minutes 8/9/12

West Region Wildfire Council Meeting Minutes 8/9/12 West Region Wildfire Council Meeting Minutes 8/9/12 Meeting Attendance Name Agency Email 1 Tom Austin Log Hill Fire Toma67@aol.com 2 Chris Barth Montrose Interagency Fire cbarth@blm.gov 3 Lilia Colter

More information

Prepared for the House Committee on Veterans and Emergency Preparedness. Workgroup On Amateur Radio. Representative Bill Post, Chair

Prepared for the House Committee on Veterans and Emergency Preparedness. Workgroup On Amateur Radio. Representative Bill Post, Chair Prepared for the House Committee on Veterans and Emergency Preparedness Workgroup On Amateur Radio Representative Bill Post, Chair By John Core, ARRL Oregon Section Manager May 16, 2017 Workgroup Purpose:

More information

Metrological Telecommunication System Development Project

Metrological Telecommunication System Development Project Philippines Metrological Telecommunication System Development Project 1. Project Profile and Japan s ODA Loan Report Date: March 2001 Field Survey: September 2000 The Philippines Manila Cebu Site Map:

More information

3 4 1: 2: SAFECOM : 4: 5: 6: 7: IP

3 4 1: 2: SAFECOM : 4: 5: 6: 7: IP Texas Radio Communications Interoperability Plan 1 TABLE OF CONTENTS Introduction... 3 Levels of Interoperability... 4 Figure 1: Six Levels of Interoperability... 4 Figure 2: SAFECOM Interoperability Continuum...

More information

The Public Safety Committee will be briefed on the Modernization of Dallas' Radio Network on Monday, November 1, 2010.

The Public Safety Committee will be briefed on the Modernization of Dallas' Radio Network on Monday, November 1, 2010. Memorandum CITY OF DALLAS Date: October 29, 2010 To: Mayor Pro Tem Dwaine Caraway, Chair and Members of the Public Safety Committee Subject: Modernization of Dallas' Radio Network The Public Safety Committee

More information

DAS Solutions. Delivering coverage and capacity in today s challenging environments

DAS Solutions. Delivering coverage and capacity in today s challenging environments DAS Solutions Delivering coverage and capacity in today s challenging environments Wireless subscribers expect clear coverage Partner with an industry leader With a diverse offering of communications sites

More information

This Call for Qualifications does not require the preparation of a design proposal.

This Call for Qualifications does not require the preparation of a design proposal. EDMS# 211137 I. Introduction This Call for Qualifications invites professional artists, or artist team, to participate in a two-stage selection process to develop an original, public art work for Port

More information

MERA NEXT GENERATION SYSTEM SUMMARY PROJECT DESCRIPTION IN ADVANCE OF CEQA SUBSEQUENT ENVIRONMENTAL IMPACT REPORT (SEIR)

MERA NEXT GENERATION SYSTEM SUMMARY PROJECT DESCRIPTION IN ADVANCE OF CEQA SUBSEQUENT ENVIRONMENTAL IMPACT REPORT (SEIR) PROJECT SPONSOR AND LEAD AGENCY MERA NEXT GENERATION SYSTEM SUMMARY PROJECT DESCRIPTION IN ADVANCE OF CEQA SUBSEQUENT ENVIRONMENTAL IMPACT REPORT (SEIR) The Marin Emergency Radio Authority (MERA) is a

More information

Oregon Annual Social Indicators Survey (OASIS), 2005 Codebook (from SPSS)

Oregon Annual Social Indicators Survey (OASIS), 2005 Codebook (from SPSS) Oregon Annual Social Indicators Survey (OASIS), 2005 Codebook (from SPSS) List of variables on the working file Name (Position) Label respnum$ (1) Respondent number Print Format: F9 Write Format: F9 time$

More information

City of Laguna Hills Application for a Conditional Use Permit Project Information and Justification

City of Laguna Hills Application for a Conditional Use Permit Project Information and Justification Authorized Agent for Verizon Wireless City of Laguna Hills Application for a Conditional Use Permit Project Information and Justification With current efforts underway to establish the required infrastructure

More information

[LLNVW00000.L GN0000.LVEMF X. Notice of Intent to Prepare an Environmental Impact Statement for the Proposed

[LLNVW00000.L GN0000.LVEMF X. Notice of Intent to Prepare an Environmental Impact Statement for the Proposed This document is scheduled to be published in the Federal Register on 03/04/2016 and available online at http://federalregister.gov/a/2016-04806, and on FDsys.gov 4310-HC DEPARTMENT OF THE INTERIOR Bureau

More information

CONCEPTS TO OPERATIONS, INC.

CONCEPTS TO OPERATIONS, INC. CHANNEL 16 PROJECT Presented by CONCEPTS TO OPERATIONS, INC. E-mail: cto@concepts2ops.com Web Site: www.concepts2ops.com APCO International Annual Conference Denver, Colorado Professionals Putting Good

More information

MAKING THE CALL ON A NATIONAL PUBLIC SAFETY WIRELESS NETWORK

MAKING THE CALL ON A NATIONAL PUBLIC SAFETY WIRELESS NETWORK MAKING THE CALL ON A NATIONAL PUBLIC SAFETY WIRELESS NETWORK A white paper from L.R. Kimball May 2010 866.375.6812 info@lrkimball.com www.lrkimball.com ARchitecture Engineering Communications technology

More information