1 NOVEMBER 2015 MONTHLY PROGRESS REPORT

2

3 Cover photo: From the conference room between the Oregon State Police Northern Command Center and the Oregon Department of Transportation Northwest Transportation Operations Center, the console cutover team coordinates each dispatch center switch to the new Pantel console and logging recorder system. From left are Eric Vargas (ODOT), Nathan Renner (Pantel), Mat McDonald (Pantel), Richard Wilson (ODOT), Kurt Chandler (ODOT), Lisa Strader (ODOT) and Nancy Hall (AECOM).

4 State Radio Project MONTHLY PROGRESS REPORT PROJECT AND GOALS UPDATE In October, the State Radio Project console project team began the carefully planned cutover process for the Oregon Department of Transportation and Oregon State Police dispatch centers. The team switched over one center at a time to the new Pantel console system to ensure the system functioned correctly before moving on to the next. Dispatcher training on the new system occurred before each cutover. Every dispatch center received a detailed individual cutover plan with two implementation teams, one at the dispatch center and one at the Oregon Military Department s Anderson Readiness Center in Salem, which houses the backroom equipment. Each plan includes ODOT Wireless Communications Section technicians on site to move the consoles into position and troubleshoot any issues and a technician on call around the clock during the 48-hour cutover period. On Oct. 6, the console project team kicked off the cutover process at ODOT s Transportation Management Operations Center in Portland. The dispatchers easily integrated into the new system with very few problems, said Brent Atkinson, TMOC incidence response supervisor. They were able to get used to the system before it went live, and the feedback I received from them after cutover was mostly positive. By all accounts the transition went smoothly at TMOC. One minor holdup involved the phone company and the process of transferring phone lines, but the rest of the process went as planned. The dispatchers at TMOC appeared to move from the old Gold Elite to the Pantel system so seamlessly that from my viewpoint you could hardly tell that anything had happened, said Lisa Strader, ODOT State Radio Project assistant manager. Three more dispatch centers switched over by the end of the month: OSP Northern Command Center, OSP Southern Command Center and ODOT s Southern Transportation Operations Center. Pantel staff was onsite during each cutover to answer questions and resolve minor issues. A couple bigger issues also surfaced, and Pantel is working on solutions. One issue involves the instant replay recorder. If a dispatcher is listening to a recorded call, it overrides a new incoming call. Dispatchers need other audio to get through even when they are listening to a recording. Another issue concerns network usage with the logging recorder. We talk about network usage a lot for all the different pieces of the project because there is only so much bandwidth available, Strader said. For a period of time on one day, the logging recorders used double the expected bandwidth. It hasn t occurred since, but we are closely monitoring network usage. Team members suspect it could be because two officer-involved shootings occurred during that week and staff played back the recordings, which could have overloaded the system. But because we don t know exactly what happened, the project team is testing to see if it can be replicated. Other small modifications to the system could make dispatchers jobs easier and more efficient. Some are punch list items that Pantel is under contract to fix, and some are things that ODOT Wireless can adjust. The console team will prioritize the list of possible improvements and accommodate as many as possible. INFRASTRUCTURE I n October, work continued on several sites, including Applegate Butte and Medicine Mountain in Klamath County and Sugar Pine in Deschutes County. The project issued notice to proceed for Santiam Junction in Linn County and Wilson River in Tillamook County. At Applegate Butte crews installed the roof on the new concrete shelter. Medicine Mountain work included tree removal for a clear microwave path, and Sugar Pine received a new HVAC system, and interior electrical and November 2015 No. 62 Page 1

5 MONTHLY PROGRESS REPORT State Radio Project grounding improvements. Medicine Mountain reached substantial completion in October along with Adel Remote, Picture Rock and Round Pass. The Snow Peak site in Linn County was decommissioned, which involved the removal of fencing, the tower and foundation, and the propane foundation. Crews salvaged the 500-gallon propane tan, and performed backfill and restoration of the site. NARROWBANDING T he radio project met the required Federal Communications Commission mandate to transition to narrowband operations ahead of the November 2013 deadline. Work on several narrowbandingrelated items, including antenna installations, office remotes and power system upgrades, and construction of a number of infill sites will continue through CONSOLIDATION T he radio project goal to consolidate the ODOT and OSP wireless communications systems into a single unit and allow for shared efficiencies and integration between the existing state systems is complete. OSP staff, communications sites and communications systems were consolidated with ODOT as of July 1, The work to transfer the OSP sites to ODOT is complete. INTEROPERABILITY T he State Interoperability Executive Council Technical Committee reviewed applications from public safety radio system entities for use of the radio project s budgeted interoperability funds. The committee is preparing recommendations and will present them to the SIEC at the November quarterly meeting. The Oregon Department of Justice is reviewing the request for proposals for a statewide interoperability survey. PROJECT PROGRESS The total budget for the radio project is $229,991,920. Less expenditures from the previous biennia and those expended by the Oregon Wireless Interoperability Network program, or OWIN, the remaining budget is $175.1 million. The work components necessary to launch the revised State Radio Project include project management, narrowbanding, microwave modernization, trunking, tactical interoperability and partner obligations. The budget and schedule for the project s active components are provided in the State Radio Project monthly dashboard; supplemental information in this report is based upon the work breakdown structure detailed in the State Radio Project s Project Management Plan. WBS 1.0 PROJECT MANAGEMENT SUMMARY Project management consists of those elements that are projectwide and affect all other WBS sections. For WBS 1.0 Project Management, 96 percent of the total budget has been expended to date. Page 2 November 2015 No. 62

6 State Radio Project MONTHLY PROGRESS REPORT ASSET MANAGEMENT Microwave equipment was delivered from the warehouse during October for Adel Remote, Applegate Butte, Bear Mountain, Burns Butte, Burns Maintenance, Cabbage Hill, Elkhorn, Halfway Hill, Hoodoo Butte ATC, Howard Butte, Klamath Falls, Lime Hill, Picture Rock, Round Pass, Table Mountain Jackson, Tillamook Head and Wampus Butte. Low-band radio equipment was delivered from the warehouse for Grizzly Mountain and Stephenson. Asset management staff continues to work with the radio project s Finance and Financial Services staff to reconcile site expenditures. The asset management team is working to move the majority of the State Radio Project warehouse inventory to ODOT buildings in Salem by Dec. 1. Staff continues to work closely with ODOT Surplus to recycle and surplus decommissioned equipment that has been returned from sites. CHANGE MANAGEMENT There are two types of change requests, administrative and formal. Administrative changes are those that do not affect the project s baseline scope, schedule or budget. Formal changes are those that affect those project baselines. During October, 11 change requests were processed and approved. September 2015 October 2015 Total to date Administrative Formal Total The following table represents the value of the project s contingency budget at the end of the two most recent months. The change noted is due to approval of formal budget changes executed in October. September 2015 October 2015 Total Change Contingency budget, end-of-month value $3,944,197 $2,761,190 $(1,183,007) COMMUNICATIONS MANAGEMENT Communications staff provided the following project information/materials during October: Produced October 2015 Monthly Progress Report Produced October 2015 Project Dashboard Produced October 2015 Key Project Facts sheet Updated project website on Oregon.gov November 2015 No. 62 Page 3

7 MONTHLY PROGRESS REPORT State Radio Project Distributed project information notices via GovDelivery Provided update on radio project activities to ODOT public affairs staff QUALITY MANAGEMENT The following table is a snapshot of the past two Quarterly Project Status and Improvement Reports issued by Public Knowledge. Second quarter 2015 Third quarter 2015 Overall risk the project will not meet scope, budget or timing goals High High Total number of risks identified during the review period 13 5 Total number of high-rated risks identified during the review period 2 0 In addition to reporting risk findings, Public Knowledge evaluates 35 quality standards each quarter, which are also ranked as high, medium or low risks. The following table is a summation of those ratings. Second quarter 2015 Third quarter 2015 Standards rated as high risk 17% 0% Standards rated as moderate risk 66% 71% Standards rated as low risk 17% 29% The following table is a snapshot of the issues, categorized by WBS section, managed by the project during October. Project management develops planned actions and target dates for resolving these issues. Until an issue has a target resolution date, it is not included in the planned for resolution count. Number of active issues Number planned for resolution Total resolved 1.0 Project Management Narrowbanding Microwave Modernization Trunked Radio Interoperability Partnerships Planning and Engineering Total Page 4 November 2015 No. 62

8 State Radio Project MONTHLY PROGRESS REPORT WBS 2.0 NARROWBANDING The narrowbanding component of the radio project involves two primary work efforts. First is to transition ODOT and OSP radio operations to narrowband mode, which the radio project completed in August 2013 in advance of the revised federal deadline of Nov. 1, The second effort includes implementing equipment upgrades, beyond those required for narrowband operation, to mountaintop tower sites and office locations throughout the state. For WBS 2.0 Narrowbanding, 98 percent of the total budget has been expended to date. The radio deployment section of work (WBS 2.3) consists of two primary elements: training and deployment of mobile radio equipment, and training and deployment of handheld, portable radio units. Recipients of this equipment include ODOT and OSP employees, along with select groups with the Oregon Department of Corrections and the Oregon Office of Emergency Management, as identified by the agency. The radio deployment effort is complete. The project s effort to complete closeout work for the radio deployment, including final reconciliation of all work, is ongoing. WBS 3.0 MICROWAVE MODERNIZATION The microwave component of the radio project involves replacing old and outdated ODOT and OSP analog microwave with digital microwave and making associated site improvements. Microwave installation includes the acquisition, installation, implementation and optimization of the new digital microwave radios, antenna dishes, wave guide, routers and ancillary equipment to support both conventional and trunked radio systems. Network implementation consists of integrating routing, switching and monitoring equipment into the microwave system to move both voice and data messages over the digital microwave system. Improvements to towers, shelters, power supplies and other facilities required by the upgraded microwave and trunked radio systems are anticipated at most sites. New leases, permits and agreements will be obtained as needed. The budget for this project component, totaling $51.6 million, is comprised of $19 million for installation, $5.6 million for network implementation, $25.7 million for site work and $1.3 million for wireless infrastructure management system implementation. For WBS 3.0 Microwave Modernization, 73 percent of the total budget has been expended to date. INSTALLATION AND IMPLEMENTATION The project is tracking the implementation of the microwave network in two ways: by individual sites and by individual hops. A microwave hop connects two sites to each other. In most cases, a November 2015 No. 62 Page 5

9 MONTHLY PROGRESS REPORT State Radio Project single site will require equipment sets to support multiple hops. The microwave network is established by connecting the hops together. The radio project will report a site as microwave installation complete when all equipment needed to support all hops has been installed at the site. The project will report a microwave hop complete when equipment connecting two sites has been installed. SITE IMPROVEMENTS The site improvement process includes three phases: pre-design, design and construction. Pre-design phase: Tasks completed from inception to approval by the Site Review Committee, the project s change review board. Pre-design scoping activities at all sites are complete; however, radio project staff will revisit sites as necessary to address any needs that may arise during the design process. Design phase: Tasks completed from site planning through acquisition of the site building permit. Construction phase: Tasks completed from the acquisition of the building permit to the completion of site construction. WIRELESS INFRASTRUCTURE MANAGEMENT SYSTEM The wireless infrastructure management system, previously referred to as the network management system, will provide monitoring, alarming and control capabilities for system components and associated equipment. WBS 4.0 TRUNKED RADIO SYSTEM A trunked radio system is used to maximize available capacity in a two-way radio system. Because not everyone in a group talks at once and radio transmissions are usually short, a trunked computer can assign talk frequencies in a manner that allows multiple groups of users to share a small set of frequencies without hearing each other s conversations. This effectively compresses the voice signals and enhances the capacity of the system. The trunked system will allow local radio communications between public safety personnel; microwave will distribute those signals over a larger area, enabling distance and interagency communications. The $27.2 million budget for the trunked radio system includes five primary work efforts: procurement and installation of trunked radio repeaters for $15 million, switches for $2.1 million, dispatch consoles for $4.9 million, testing and training for $3.6 million and VHF integration for $1.6 million. For WBS 4.0 Trunked Radio System, 69 percent of the total budget has been expended to date. Development of the trunked radio system includes three categories of work: repeater and site control equipment, central trunking switches and dispatch consoles. Section 7.0 Planning and Engineering also includes progress on the design efforts related to the trunked radio system. Repeaters and site control equipment installations are underway. Central trunking switches have been installed at dispatch centers in Salem and Bend. Dispatch consoles were installed at four of the six dispatch centers. Page 6 November 2015 No. 62

10 State Radio Project MONTHLY PROGRESS REPORT WBS 5.0 INTEROPERABILITY Improvements to state interoperability will be captured in this section. The State Interoperability Executive Council is currently heading statewide planning efforts to develop the overarching plan for interoperability in Oregon. Once the SIEC has finalized its plan, the project will initiate work on this effort. The project budget for this section is $2.3 million. For WBS 5.0 Interoperability, 1 percent of the total budget has been expended to date. The SIEC Technical Committee reviewed applications from local public safety agencies for use of interoperability funds. Funding recommendations will be presented to the SIEC at the November meeting. WBS 6.0 PARTNERSHIPS Partnerships were developed between the former OWIN program and local jurisdictions with the intent to reduce costs to both parties. These agreements created interdependency among participants for a functional system. The radio project has identified the partnership groups listed below as including sites that require work to meet the needs associated with these agreements: Chemical Stockpile Emergency Preparedness Program (CSEPP) (WBS 6.1.1) Lincoln County (WBS 6.1.2) North Coast (WBS 6.1.3) North Valley (WBS 6.1.4) Southwest Seven (WBS 6.1.5) Klamath County (WBS 6.1.6) Additional partnerships (WBS 6.1.7) For WBS 6.0 Partnerships, 93 percent of the total budget has been expended to date. OWIN OBLIGATIONS All partnership work is complete with the exception of Klamath County. The work in Klamath County is progressing. All partnership obligations in this network are scheduled to be completed in mid-december, weather permitting. Agreements: Umbrella and supplemental agreements executed in a given region. Design phase: Tasks completed from site planning through acquisition of the site building permit. Construction phase: Tasks completed from the acquisition of the building permit to the completion of site construction. November 2015 No. 62 Page 7

11 MONTHLY PROGRESS REPORT State Radio Project Microwave installation phase: All tasks involved in the installation of microwave equipment, from initiation to completion. Microwave installations may occur during a site s construction phase or after it has been completed. Obligation complete: All work has been completed and associated quality reviews have been conducted and work approved. Quality reviews include those conducted by the partner(s), Wireless Communications Section technicians and by representatives of OEM. STRATEGIC TECHNOLOGY RESERVE Activities related to the deployment of the Strategic Technology Reserve (WBS 6.5) have been completed. Operations have been transferred to the Wireless Communications Section. WBS 7.0 PLANNING & ENGINEERING The planning and engineering section of the work breakdown includes design and development activities associated with the previous WBS sections. For WBS 7.0 Planning and Engineering, 94 percent of the total budget has been expended. Statewide Planning activities (WBS 7.1) are captured under 7.5 Interoperability Design. The project has completed all narrowband planning (WBS 7.2) efforts and has transitioned ODOT and OSP radios to operate in narrowband mode. The microwave design (WBS 7.3) is considered substantially complete. Small adjustments continue to be made in response to needs identified during the site acquisition and construction processes. Coordination of microwave implementation is well underway. Development on the radio project s trunked radio system (WBS 7.4) design is ongoing. Interoperability design (WBS 7.5) will be accomplished largely by local public safety agencies, in coordination with the project, that are awarded interoperability funds through an application process and approved by the State Interoperability Executive Council. Partnership development (WBS 7.6) is complete. WBS 8.0 INTEGRATION TRAINING This section of work was developed and incorporated into the project budget during February It includes limited funding for training activities for Wireless Communications Section technicians and stakeholders. Activities related to integration training began in the third quarter of 2014 and will extend into For WBS 8.0 Integration Training, 39 percent of the total budget has been expended to date. No training activities took place during October. Page 8 November 2015 No. 62

12 State Radio Project MONTHLY PROGRESS REPORT STAFFING SUMMARY Full-time state employees and contractors are working on the radio project throughout Oregon. In October, the project employed 16 full-time equivalent state positions Number of Jobs State Radio Project Employees Site Development Staff (B&V) Contractors (SAIC, Legacy, HDR) Radio Staff (Harris & AECOM) November 2015 No. 62 Page 9

13 MONTHLY PROGRESS REPORT State Radio Project CONTRACT SUMMARY Including historic values of the previous OWIN program, the State Radio Project has spent $141,816,130 of the $179,748,937 currently available across the project s 16 contracts. This represents an overall expenditure of approximately 79 percent. To date in the biennium, $8,675,586 has been spent. This represents 5 percent of the total contract amount available and approximately 19 percent of the contract amount available for the biennium. CONTRACT SUMMARY BY VENDOR Expended Before 6/30/2011 Expended After 6/30/2011 Available Balance (10/31/2015) Contract amount available ABN Engineering $0 $580,309 $81,866 $662,175 AECOM $294,656 $4,547,625 $537,942 $5,380,224 Aviat $9,456,115 $12,316,767 $ 9,961,570 $31,734,452 Black & Veatch $6,168,224 $5,687,067 $11,284,089 $23,139,379 CSGI $951,175 $0 $0 $951,175 Federal Engineering $7,932,754 $703,111 $1,380,972 $10,016,838 GDIT $3,750,794 $6,417,793 $841,644 $11,010,231 Harris $0 $51,555,336 $6,468,959 $58,024,295 HDR $261,091 $3,689,925 $45,947 $3,996,963 JLA Consulting $0 $70,124 $0 $70,124 Legacy Wireless $1,656,972 $4,142,064 $1,014,537 $6,813,573 Misc. small contracts $1,032,273 $11,146,784 $2,957,361 $15,136,638 OBEC $0 $141,045 $4,775 $145,820 Pantel International $0 $2,890,391 $1,309,058 $4,199,449 Public Knowledge $0 $1,802,460 $1,061,123 $2,863,582 SAIC $0 $4,621,056 $982,965 $5,604,020 Total $31,504,273 $110,311,857 $37,932,808 $179,748,937 18% 61% 21% Page 10 November 2015 No. 62

14 State Radio Project MONTHLY PROGRESS REPORT PROJECT COST SUMMARY Original Budget 09/07/2011 Rebaselined Budget 9/30/2013 Prior Budget Changes as of 09/30/2015 Current Month Budget Changes as of 10/31/2015 Current Budget as of 10/31/2015 Funds Spent through 10/31/2015 Balance Narrowbanding Repeaters 6,100,000 4,415, , ,748,786 4,719,353 29,433 Office Remotes 2,000,000 2,116,600 (915,549.00) - 1,201, , ,478 Hand Helds/Portables 33,200,000 25,742, , ,658,708 26,485, ,051 Cutover/Testing - 300,000 (69,295.00) - 230, ,705 - Narrowbanding Subtotal 41,300,000 32,574, ,921-32,839,250 32,301, ,961 Microwave Modernization Purchase & Installation 29,300,000 17,568,049 1,470,072-19,038,121 12,702,127 6,335,995 Network 5,498, ,454-5,608,446 5,199, ,172 Site Improvements 45,550,000 25,150,000 (704,907) 1,208,194 25,725,287 19,845,753 5,879,533 Network Management System 1,386,984 (141,984) 1,245,000 82,338 1,162,662 Training & Equipment Acquisition 500,000 (500,000) Microwave Modernization Subtotal 74,850,000 50,104, ,635 51,616,854 37,829,492 13,787,361 Trunking Receivers 5,250,000 14,803, ,938-15,049,388 12,697,339 2,352,049 Switches 2,403,062 (288,813) - 2,114,249 2,114,248 1 Consoles 1,400,000 3,941, ,105-4,933,651 3,049,383 1,884,268 Testing & Training 4,193,867 (576,250) - 3,617, ,469 3,064,149 VHF Integration 1,500,000 70,013-1,570, ,938 1,222,076 Trunking Subtotal 6,650,000 26,841, ,993-27,284,918 18,762,376 8,522,542 Interoperability Procurement & Installation 2,300,000 2,300,000 2,300,000 30,415 2,269,585 Interoperability Subtotal 2,300,000 2,300, ,300,000 30,415 2,269,585 Partnerships Construction 10,400,000 10,469,802-10,469,802 9,743, ,391 Partnerships Subtotal 10,400,000 10,469, ,469,802 9,743, ,391 Engineering Narrowbanding 1,300,000 1,532, ,339 (46,125) 1,817,986 1,817, Microwave Modernization 17,750,000 18,468,867 1,088,268 17,099 19,574,234 19,106, ,254 Trunking 1,850,000 9,299, , ,951 10,232,752 8,571,262 1,661,489 Interoperability - 3,064,792 (1,431,054) (259,630) 1,374,107 1,374,107 - Partnerships 410,155 (50,270) (51) 359, ,835 - Engineering Subtotal 20,900,000 32,775, , ,245 33,358,913 31,229,669 2,129,244 Integration Training Integration Training 500,000 (350,000) - 150,000 58,931 91,069 Integration Training Subtotal - 500,000 (350,000) - 150,000 58,931 91,069 Totals by Phase Narrowbanding 42,600,000 34,107, ,260 (46,125) 34,657,236 34,118, ,461 Microwave Modernization 92,600,000 68,572,892 1,320,903 1,297,293 71,191,088 56,936,472 14,254,616 Trunking 8,500,000 36,141, , ,951 37,517,669 27,333,638 10,184,031 Interoperability 2,300,000 5,364,792 (1,431,054) (259,630) 3,674,107 1,404,523 2,269,585 Partnerships 10,400,000 10,879,957 (50,270) (51) 10,829,637 10,103, ,391 Integration Training - 500,000 (350,000) - 150,000 58,931 91,069 Phase Subtotal 156,400, ,566, ,255 1,562, ,019, ,955,583 28,064,154 Project Management - 15,069,054 (343,837) (379,431) 14,345,785 13,729, ,063 Project Contingency Reserve - 3,852,259 91,938 (1,183,007) 2,761,190-2,761,190 Total State Radio Project 156,400, ,487, , ,126, ,685,306 31,441,407 Old OWIN Project Spending 45,000,000 49,256,733 (639,356) - 48,617,377 48,617,377 - Treasury Loan 8,000,000 6,247,831 6,247,831 6,247,831 - Total Old OWIN 53,000,000 55,504,564 (639,356) - 54,865,208 54,865,208 - Grand Total 209,400, ,991, ,991, ,550,513 31,441,407 November 2015 No. 62 Page 11

15 MONTHLY PROGRESS REPORT State Radio Project ESTIMATED PROJECT CASH FLOW $180 $160 $140 $120 Dollars in Millions $100 $80 $60 $40 $20 $0 Project Management Engineering Contingency Narrowbanding Microwave Modernization Trunking Interoperability Partnerships Page 12 November 2015 No. 62

Cover photo: Snow blanketed the State Radio Project s Mount Aldrich site in early November. The Grant County site sits at nearly 7,000 feet in

Cover photo: Snow blanketed the State Radio Project s Mount Aldrich site in early November. The Grant County site sits at nearly 7,000 feet in DECEMBER 2015 MONTHLY PROGRESS REPORT Cover photo: Snow blanketed the State Radio Project s Mount Aldrich site in early November. The Grant County site sits at nearly 7,000 feet in elevation. State Radio

More information

Cover photo: Smoke from a nearby wildfire is visible from the Lime Hill radio site in Baker County. A crew from Summit Solutions Group was on site

Cover photo: Smoke from a nearby wildfire is visible from the Lime Hill radio site in Baker County. A crew from Summit Solutions Group was on site AUGUST 2015 MONTHLY PROGRESS REPORT Cover photo: Smoke from a nearby wildfire is visible from the Lime Hill radio site in Baker County. A crew from Summit Solutions Group was on site recently to tighten

More information

State Rad o Project STATE RADIO PROJECT. Monthly Progress Report. January 2015

State Rad o Project STATE RADIO PROJECT. Monthly Progress Report. January 2015 State Rad o Project STATE RADIO PROJECT January 2015 Monthly Progress Report PROJECT GOALS INFRASTRUCTURE Repair or replace critical components of Oregon s deteriorating state radio network and extend

More information

State Rad o Project STATE RADIO PROJECT. Monthly Progress Report. April 2015

State Rad o Project STATE RADIO PROJECT. Monthly Progress Report. April 2015 State Rad o Project STATE RADIO PROJECT April 2015 Monthly Progress Report PROJECT GOALS INFRASTRUCTURE Repair or replace critical components of Oregon s deteriorating state radio network and extend the

More information

State Radio Project. January Monthly Progress Report

State Radio Project. January Monthly Progress Report State Rad o Project State Radio Project January 2014 Monthly Progress Report Project Goals Infrastructure Repair or replace critical components of Oregon s deteriorating state radio network and extend

More information

Public Safety Interoperable Communications (PSIC)

Public Safety Interoperable Communications (PSIC) State of New Mexico Department of Information Technology 2013 National Association of State Chief Information Officers State IT Recognition Awards Public Safety Interoperable Communications (PSIC) Category:

More information

State Radio Project. July Monthly Progress Report

State Radio Project. July Monthly Progress Report State Rad o Project State Radio Project July 2013 Monthly Progress Report Project Goals Infrastructure Repair or replace critical components of Oregon s deteriorating state radio network and extend the

More information

Wyoming s Statewide Public-Safety Interoperable Radio Communications System WyoLink Frequently Asked Questions (FAQ)

Wyoming s Statewide Public-Safety Interoperable Radio Communications System WyoLink Frequently Asked Questions (FAQ) Wyoming s Statewide Public-Safety Interoperable Radio Communications System WyoLink Frequently Asked Questions (FAQ) Goals... 2 1. What is WyoLink supposed to accomplish?... 2 2. Who will oversee WyoLink

More information

OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT. Conceptual Design for Radio System, Revision 1 (November 30, 2006) (Deliverable 9-D)

OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT. Conceptual Design for Radio System, Revision 1 (November 30, 2006) (Deliverable 9-D) OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT Conceptual Design for Radio System, Revision 1 () (Deliverable 9-D) Prepared by: Federal Engineering, Inc. 10600 Arrowhead Drive, Suite 160 Fairfax,

More information

Sept 28, Mukhtar mook-tar Thakur

Sept 28, Mukhtar mook-tar Thakur MnDOT Office of Statewide Radio Communications (OSRC) Overview -Summary and ARMER Status Update Central Region Summit- Alexandria, MN Sept 28, 2016 Mukhtar mook-tar Thakur The Office of Statewide Radio

More information

2-800 MHz CCCS Sys Extension

2-800 MHz CCCS Sys Extension 2-800 MHz CCCS Sys Extension 1. Program Area: PUBLIC PROTECTION 2. Identify agencies and departments involved. Sheriff-Coroner. 3. Is the Strategic Priority new or previously identified in an earlier Strategic

More information

State Radio Project. January Monthly Progress Report

State Radio Project. January Monthly Progress Report State Rad o Project State Radio Project January 2013 Monthly Progress Report Project Goals Infrastructure Repair or replace critical components of Oregon s deteriorating state radio network and extend

More information

Statewide 800 MHz trunked radio system available for all emergency responders (local, State, Federal)

Statewide 800 MHz trunked radio system available for all emergency responders (local, State, Federal) Statewide 800 MHz trunked radio system available for all emergency responders (local, State, Federal) Goal: 95% in-street portable coverage based on a 3 watt portable radio Network infrastructure consisting

More information

SUBJECT: MARIN EMERGENCY RADIO AUTHORITY (MERA) NEXT GENERATION

SUBJECT: MARIN EMERGENCY RADIO AUTHORITY (MERA) NEXT GENERATION STAFF REPORT MEETING DATE: August 20, 2013 TO: City Council 75 Rowland Way #200 Novato, CA 94945-3232 (415) 899-8900 FAX (415) 899-8213 www.novato.org FROM: James Berg, Chief of Police SUBJECT: MARIN EMERGENCY

More information

9-800 MHz Countywide Coordinated Communications System (CCCS) Upgrade

9-800 MHz Countywide Coordinated Communications System (CCCS) Upgrade 9-800 MHz Countywide Coordinated Communications System (CCCS) Upgrade 1. Program Area: PUBLIC PROTECTION 2. Identify agencies and departments involved. Sheriff-Coroner 3. Is the Strategic Priority new

More information

PALMETTO 800 History Project Cost

PALMETTO 800 History Project Cost PALMETTO 800 South Carolina has implemented the largest statewide emergency communications radio system in the nation. With over twenty thousand users, the system is available to federal, state, and local

More information

EMERGENCY COMMUNICATIONS

EMERGENCY COMMUNICATIONS EMERGENCY COMMUNICATIONS FY2004-2010 1. BACKGROUND ISSUES The Emergency Communications element of the capital plan is comprised of three projects concerning emergency radio communications, computer aided

More information

IFERN / IFERN 2 Radio Base Stations for all Wisconsin MABAS Divisions/Counties

IFERN / IFERN 2 Radio Base Stations for all Wisconsin MABAS Divisions/Counties Project Name IFERN / IFERN 2 Radio Base Stations for all Wisconsin MABAS Divisions/Counties Sponsoring Agency MABAS Wisconsin - The Mutual Aid Box Alarm System (known as MABAS) Senate Bill SB 642 was approved

More information

Guide for Short Term Interoperability

Guide for Short Term Interoperability Oregon State Interoperability Executive Council Guide for Short Term Interoperability Adopted: by the SIEC Technical Committee The Oregon State Interoperability Executive Council (SIEC) and the State of

More information

Radio Technology Overview. January 2011

Radio Technology Overview. January 2011 Radio Technology Overview January 2011 Presentation Objectives The objective of this presentation is to: Review terms as related to radio technology Review the challenges facing the City o FCC mandate

More information

Communications Interoperability- Current Status

Communications Interoperability- Current Status Communications Interoperability- Current Status Stephen Mitchell Abstract Over the past decade, the public-safety community in partnership with local, state, and federal agencies have worked to develop

More information

Radio System Replacement Project

Radio System Replacement Project Radio System Replacement Project City Council Briefing December 6, 2017 William Finch, Chief Information Officer, Communication & Information Services Presentation Overview Background Procurement Process

More information

Guide for Short Term Interoperability Revised June 24, 2009

Guide for Short Term Interoperability Revised June 24, 2009 Oregon State Interoperability Executive Council Guide for Short Term Interoperability Revised The Oregon State Interoperability Executive Council (SIEC) and the State of Oregon encourage Oregon s public

More information

Narrowbanding and Public Safety Communications

Narrowbanding and Public Safety Communications Narrowbanding and Public Safety Communications Introduction and Overview Jay Sexton Georgia Tech Research Institute Introductions What equipment is used on every call by every public safety responder?

More information

OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT. Implementation Plan (Deliverable 13-A)

OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT. Implementation Plan (Deliverable 13-A) OREGON WIRELESS INTEROPERABILITY NETWORK (OWIN) PROJECT Implementation Plan (Deliverable 13-A) Prepared by: Federal Engineering, Inc. 10600 Arrowhead Dr, Suite 160 Fairfax, VA 22030 703 359-8200 December

More information

MEMA Narrowbanding Planning Primer

MEMA Narrowbanding Planning Primer 1. The State of Maine is required to narrowband its public safety communications radios, as are all county and local governments, in accordance with the Federal Communications Commission (FCC) mandate,

More information

MOTOBRIDGE IP Interoperable Solution

MOTOBRIDGE IP Interoperable Solution MOTOBRIDGE IP Interoperable Solution BRIDGING THE COMMUNICATIONS GAP Statewide, regional and local now public safety organizations can make the connection without replacing their existing radio systems

More information

2 ESF 2 Communications

2 ESF 2 Communications 2 ESF 2 Communications THIS PAGE LEFT BLANK INTENTIONALLY ESF 2 Communications Table of Contents 1 Purpose and Scope... ESF 2-1 2 Policies and Agreements... ESF 2-1 3 Situation and Assumptions... ESF 2-1

More information

Pennsylvania STARNet NASCIO Awards Information Communications Technology Innovation Commonwealth of Pennsylvania

Pennsylvania STARNet NASCIO Awards Information Communications Technology Innovation Commonwealth of Pennsylvania Information Communications Technology Innovation Commonwealth of Pennsylvania Executive Summary In the mid-1990s, the Commonwealth of Pennsylvania faced the prospect of replacing an aging analog radio

More information

Current Systems. 1 of 6

Current Systems. 1 of 6 Current Systems Overview Radio communications within the State of California s adult correctional institutions are vital to the daily safety and security of the institution, staff, inmates, visitors, and

More information

CONCEPTS TO OPERATIONS, INC.

CONCEPTS TO OPERATIONS, INC. CHANNEL 16 PROJECT Presented by CONCEPTS TO OPERATIONS, INC. E-mail: cto@concepts2ops.com Web Site: www.concepts2ops.com APCO International Annual Conference Denver, Colorado Professionals Putting Good

More information

SHARED COMMUNICATIONS 40,000 8,500 SERVICES FOR OHIO PUBLIC

SHARED COMMUNICATIONS 40,000 8,500 SERVICES FOR OHIO PUBLIC MARCS TODAY Statewide, robust, stable platform STATE OF OHIO MARCSIP Business Plan/Rollout May 9, 2012 Ohio APCO/NENA Combined Chapter Business Meeting Over 40,000 radios activated Originally designed

More information

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017 NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP 697-16-016 July 28, 2017 Reference is made to the Request for Proposal (RFP) to Service Providers for Nevada Shared Radio Replacement Project, upon

More information

INTERNAL AUDIT DIVISION CLERK OF THE CIRCUIT COURT

INTERNAL AUDIT DIVISION CLERK OF THE CIRCUIT COURT INTERNAL AUDIT DIVISION CLERK OF THE CIRCUIT COURT AUDIT OF EMERGENCY COMMUNICATIONS DEPARTMENT INTERGOVERNMENTAL RADIO PROGRAM Ken Burke, CPA* Clerk of the Circuit Court Ex Officio County Auditor Robert

More information

Business Plan Summary

Business Plan Summary Owner: 2012-2016 Business Plan Summary Program Corporate, Operational & Council Services Service grouping Corporate Services Service Type Internal Service Mike Bushby Division Manager Fleet Services and

More information

Capability Statement. Brisbane. Dalby. Mackay. Moranbah

Capability Statement. Brisbane. Dalby. Mackay. Moranbah Capability Statement Brisbane Dalby Mackay Moranbah Who we are RCS Telecommunications was created in 2013 through the merger of Queensland Communications and Networking (QCN) and Radio Communications Solutions

More information

ATLAS. P25 Systems. LMR communications made simple.

ATLAS. P25 Systems. LMR communications made simple. P25 Systems LMR communications made simple. We make your critical communication system safe and simple to use. IS THE MOST MODERN & FLEXIBLE P25 SYSTEM Our patented Latitude technology makes the P25 application

More information

Public Safety Communications Commission

Public Safety Communications Commission Public Safety Communications Commission Report to Governor and Joint Transportation, Highways and Military Affairs Committee June 2017 Matthew H. Mead Governor Wyoming Public Safety Communications Commission

More information

MARIN COUNTY ON BEHALF OF MARIN EMERGENCY RADIO AUTHORITY (MERA) RADIO COMMUNICATIONS SYSTEM

MARIN COUNTY ON BEHALF OF MARIN EMERGENCY RADIO AUTHORITY (MERA) RADIO COMMUNICATIONS SYSTEM MARIN COUNTY ON BEHALF OF MARIN EMERGENCY RADIO AUTHORITY (MERA) RADIO COMMUNICATIONS SYSTEM REQUEST FOR PROPOSALS EXECUTIVE SUMMARY When Marin County calls 911, your dispatcher sends help with a Motorola

More information

Radio Communications Essentials. Module 9: Narrowbanding Pete Peterson

Radio Communications Essentials. Module 9: Narrowbanding Pete Peterson Radio Communications Essentials Module 9: Narrowbanding Pete Peterson 1 Topics Why is it Necessary? Who is Affected? Key Deadlines & Exceptions What are the Challenges? Sample Steps to Narrowband Frequently

More information

Ernie B. McNeely, Township Manager Michael J. McGrath, Superintendent of Police Lower Merion Township Radio System Replacement DATE: June 25, 2014

Ernie B. McNeely, Township Manager Michael J. McGrath, Superintendent of Police Lower Merion Township Radio System Replacement DATE: June 25, 2014 EXHIBIT B TOWNSHIP OF LOWER MERION POLICE DEPARTMENT DEPARTMENTAL MEMORANDUM INTEGRITY PROFESSIONALISM RESPECT TO: FROM: SUBJECT: Ernie B. McNeely, Township Manager Michael J. McGrath, Superintendent of

More information

SAN DIEGO COUNTY MUTUAL AID RADIO PLAN

SAN DIEGO COUNTY MUTUAL AID RADIO PLAN ATTACHMENT A SAN DIEGO COUNTY MUTUAL AID RADIO PLAN 1.1 General Mutual aid channels are a critical part of San Diego County's radio system requirements. The San Diego County Mutual Aid Radio Plan will

More information

BUTLER COUNTY RADIO RFP RESPONSES TO VENDOR QUESTIONS. Butler County 700 MHz, P25 Public Safety Radio Network Issued July 8, 2016

BUTLER COUNTY RADIO RFP RESPONSES TO VENDOR QUESTIONS. Butler County 700 MHz, P25 Public Safety Radio Network Issued July 8, 2016 County of Butler, Pennsylvania Request for Proposals 700 MHz, Project 25 Public Safety Radio Network BUTLER COUNTY RADIO RFP RESPONSES TO VENDOR QUESTIONS Request for Proposal: Butler County 700 MHz, P25

More information

Broward County Consolidated Communication Committee. Updates. April 20, 2017

Broward County Consolidated Communication Committee. Updates. April 20, 2017 Broward County Consolidated Communication Committee Updates April 20, 2017 Action Plan for Recommendations from Assessment Report (Fitch & Assoc. Report) The high level action plan was provided to City

More information

The Professional Consulting Services Communications Consultant E-911. Design Alternatives

The Professional Consulting Services Communications Consultant E-911. Design Alternatives The Communications Consultant E-911 Sullivan County, New York April 21, 2010 Table of Contents 1. OVERVIEW... 4 2. TECHNOLOGY OPTIONS... 5 2.1 Analog Conventional... 5 2.2 Project 25 Conventional... 5

More information

Resolution Authorizing Expenditure Appropriations to Purchase Radio Equipment and Facilitate Infrastructure R56 Grounding Work

Resolution Authorizing Expenditure Appropriations to Purchase Radio Equipment and Facilitate Infrastructure R56 Grounding Work CITY OF MARTINEZ CITY COUNCIL AGENDA March 21, 2012 TO: FROM: SUBJECT: Mayor and City Council Gary D. Peterson, Chief of Police Resolution Authorizing Expenditure Appropriations to Purchase Radio Equipment

More information

MERA NEXT GENERATION SYSTEM SUMMARY PROJECT DESCRIPTION IN ADVANCE OF CEQA SUBSEQUENT ENVIRONMENTAL IMPACT REPORT (SEIR)

MERA NEXT GENERATION SYSTEM SUMMARY PROJECT DESCRIPTION IN ADVANCE OF CEQA SUBSEQUENT ENVIRONMENTAL IMPACT REPORT (SEIR) PROJECT SPONSOR AND LEAD AGENCY MERA NEXT GENERATION SYSTEM SUMMARY PROJECT DESCRIPTION IN ADVANCE OF CEQA SUBSEQUENT ENVIRONMENTAL IMPACT REPORT (SEIR) The Marin Emergency Radio Authority (MERA) is a

More information

WASHINGTON COUNTY-WIDE Digital Trunked P25 Phase 2 Interoperable EMERGENCY RADIO, PAGING & SYSTEM for sheriff, police, fire

WASHINGTON COUNTY-WIDE Digital Trunked P25 Phase 2 Interoperable EMERGENCY RADIO, PAGING & SYSTEM for sheriff, police, fire 2018-2019 WASHINGTON COUNTY-WIDE Digital Trunked P25 Phase 2 Interoperable EMERGENCY RADIO, PAGING & 9-1-1 SYSTEM for sheriff, police, fire departments ems first responders & ambulance Operating from a

More information

Allied Radio Matrix for Emergency Response (ARMER) Standards, Protocols, Procedures

Allied Radio Matrix for Emergency Response (ARMER) Standards, Protocols, Procedures Allied Radio Matrix for Emergency Response (ARMER) Standards, Protocols, Procedures Document Section: 3 Interoperability Standards Status: Complete Sub Section: State Procedure Title: 800 MHz Statewide

More information

Appointments are available the first two weeks of June 2001 (06/04/01 06/15/01) from 9:00 a.m. to 4:00 p.m.

Appointments are available the first two weeks of June 2001 (06/04/01 06/15/01) from 9:00 a.m. to 4:00 p.m. ATTN: Potential Land Mobile Radio Systems Integrators The Commonwealth of Virginia will be issuing a Request for Proposal in the near future to establish a Contract with a Systems Integrator to upgrade

More information

REPORT TO MAYOR AND COUNCIL

REPORT TO MAYOR AND COUNCIL AGENDA ITEM NO. 3.j REPORT TO MAYOR AND COUNCIL TO THE HONORABLE MAYOR AND COUNCIL DATE: July 24, 2012 SUBJECT: ADOPT RESOLUTION NO. 12-62 APPROVING A SEVEN-YEAR CAPITAL LEASE AGREEMENT WITH MOTOROLA SOLUTIONS,

More information

DESCRIPTION OF INTENDED SINGLE SOURCE PURCHASE (PUR 7776)

DESCRIPTION OF INTENDED SINGLE SOURCE PURCHASE (PUR 7776) DESCRIPTION OF INTENDED SINGLE SOURCE PURCHASE (PUR 7776) AGENCY Department of Management Services TITLE Mutual Aid Communication Microwave Short description of the commodity or service desired: Microwave

More information

Chester County Voice Radio Project Monthly Status Webinar Meeting. 1 April :00 to 14:20

Chester County Voice Radio Project Monthly Status Webinar Meeting. 1 April :00 to 14:20 1 April 2015 14:00 to 14:20 Agenda The Agenda for the meeting was reviewed and encompassed: Construction Status Leasing Status Technical Overview Schedule Review Two Week Look-Ahead Additional items for

More information

Public Safety Radio Communications System Update. Presented by Steve Streiffert Assistant Director, IT Solutions May 10, 2011

Public Safety Radio Communications System Update. Presented by Steve Streiffert Assistant Director, IT Solutions May 10, 2011 Public Safety Radio Communications System Update Presented by Steve Streiffert Assistant Director, IT Solutions May 10, 2011 Purpose Review state of the current radio system Council to consider M&C P11234

More information

Motorola Deployable Solutions

Motorola Deployable Solutions Motorola Deployable Solutions Fully integrated site solution on wheels for rapid response to additional capacity, additional coverage, or disaster recovery. Rapid Response Advanced planning, preparation,

More information

Rulemaking Hearing Rules of the Tennessee Department of Health Bureau of Health Licensure and Regulation Division of Emergency Medical Services

Rulemaking Hearing Rules of the Tennessee Department of Health Bureau of Health Licensure and Regulation Division of Emergency Medical Services Rulemaking Hearing Rules of the Tennessee Department of Health Bureau of Health Licensure and Regulation Division of Emergency Medical Services Chapter 1200-12-01 General Rules Amendments of Rules Subparagraph

More information

SARASOTA COUNTY GOVERNMENT

SARASOTA COUNTY GOVERNMENT SARASOTA COUNTY GOVERNMENT Emergency Services TO: Sarasota County Commission THROUGH: Thomas A. Harmer, County Administrator FROM: Richard Collins, Director of Emergency Services Jerry Wheeler, Manager,

More information

SERS primary mission was to design, purchase, build and operate a county-wide 800 MHz radio system along with supporting infrastructure and

SERS primary mission was to design, purchase, build and operate a county-wide 800 MHz radio system along with supporting infrastructure and * Established in 1999 * The Snohomish County Emergency Radio System SERS Mission SERS primary mission was to design, purchase, build and operate a county-wide 800 MHz radio system along with supporting

More information

Glossary of Terms Black Sky Event: Blue Sky Operations: Federal Communications Commission (FCC): Grey Sky Operations:

Glossary of Terms Black Sky Event: Blue Sky Operations: Federal Communications Commission (FCC): Grey Sky Operations: Glossary of Terms The following is a list of terms commonly used in the electric utility industry regarding utility communications systems and emergency response. The purpose of this document is to provide

More information

The Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250)

The Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250) The Office of the Finance and Purchasing Manager Telephone : (250) 352-8204 Fax : (250) 352-6594 REQUEST FOR PREQUALIFICATIONS RADIO COMMUNICATIONS INFRASTRUCTURE UPGRADE CONTRACTOR SERVICES 2018-PRQ-01

More information

LOUDON COUNTY ARES EMERGENCY OPERATIONS PLAN

LOUDON COUNTY ARES EMERGENCY OPERATIONS PLAN LOUDON COUNTY ARES EMERGENCY OPERATIONS PLAN MARCH 2008 I. INTRODUCTION A. Amateur Radio Service LOUDON COUNTY, TENNESSEE AMATEUR RADIO EMERGENCY SERVICE EMERGENCY OPERATIONS PLAN The Amateur Radio Service

More information

Santa Barbara County Operational Area Interoperable Communications Study Final Report. June 25, 2012

Santa Barbara County Operational Area Interoperable Communications Study Final Report. June 25, 2012 Santa Barbara County Operational Area Interoperable Communications Study Final Report June 25, 2012 Agenda Review Project Goals and Status Provide Overview of Current Systems Discuss Assessment Findings

More information

FINAL REPORT SUBMITTED JUNE 2017 TO: SHENANDOAH COUNTY, VIRGINIA

FINAL REPORT SUBMITTED JUNE 2017 TO: SHENANDOAH COUNTY, VIRGINIA Radio System Needs Assessment FINAL REPORT SUBMITTED JUNE 2017 TO: SHENANDOAH COUNTY, VIRGINIA TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 1. INTRODUCTION... 6 2. METHODOLOGY... 6 2.1. INITIAL MEETING...

More information

Interoperable Communication Sustainment

Interoperable Communication Sustainment Georgia Emergency Management Agency Homeland Security Interoperable Communication Sustainment Nick Brown Statewide Interoperable Communication Coordinator (SWIC) April 7 2015 What drives our Interoperability

More information

You Think You ve Got Problems?

You Think You ve Got Problems? You Think You ve Got Problems? How One County Addressed a Lack of Channels, Site-Acquisition Headaches, Political Opposition, and Funding Issues to Build a New Radio Network By Ray Duncan and Brian Nordlund

More information

Textron Reports Second Quarter 2014 Income from Continuing Operations of $0.51 per Share, up 27.5%; Revenues up 23.5%

Textron Reports Second Quarter 2014 Income from Continuing Operations of $0.51 per Share, up 27.5%; Revenues up 23.5% Textron Reports Second Quarter 2014 Income from Continuing Operations of $0.51 per Share, up 27.5%; Revenues up 23.5% 07/16/2014 PROVIDENCE, R.I.--(BUSINESS WIRE)-- Textron Inc. (NYSE: TXT) today reported

More information

Eaton County Public Safety Radio System Recommendation

Eaton County Public Safety Radio System Recommendation Eaton County Public Safety Radio System Recommendation AUGUST 1, 2017 EATON COUNTY CENTRAL DISPATCH RADIO SYSTEM ADVISORY WORKGROUP TABLE OF CONTENTS Executive Summary... 3 Overview of the Radio System

More information

UNCLASSIFIED R-1 Shopping List Item No. 127 Page 1 of 1

UNCLASSIFIED R-1 Shopping List Item No. 127 Page 1 of 1 Exhibit R-2, RDT&E Budget Item Justification Date February 2004 R-1 Item Nomenclature: Defense Technology Analysis (DTA), 0605798S Total PE Cost 6.625 5.035 7.279 5.393 5.498 5.672 5.771 Project 1: DOD

More information

Public Safety Radio Communications

Public Safety Radio Communications Public Safety Radio Communications Dare County, North Carolina September 18, 2006 INDEPENDENT PROFESSIONAL QUALITY DRIVEN EXPERIENCED User Organizations Sheriff County Fire Departments County EMS Departments

More information

RADIO COMMUNICATIONS DEGRADATION & INTEROPERABILITY OR CAN YOU HEAR ME NOW? Presenter: Jon Bromberg (W1JDB) Eastside Fire & Rescue COML/COMT

RADIO COMMUNICATIONS DEGRADATION & INTEROPERABILITY OR CAN YOU HEAR ME NOW? Presenter: Jon Bromberg (W1JDB) Eastside Fire & Rescue COML/COMT RADIO COMMUNICATIONS DEGRADATION & INTEROPERABILITY OR CAN YOU HEAR ME NOW? Presenter: Jon Bromberg (W1JDB) Eastside Fire & Rescue COML/COMT COMMUNICATIONS FAILURES Not IF but WHEN Three primary levels

More information

2016 Smart Cities Survey Summary Report of Survey Results

2016 Smart Cities Survey Summary Report of Survey Results Introduction 2016 Smart Cities Survey Summary Report of Survey Results In 2016, the International City/County Management Association (ICMA) conducted a survey in partnership with the Smart Cities Council

More information

CSP DIGITAL TRUNKED AND RADIO SYSTEM QUESTION AND ANSWERS UPDATED 7/30/2018

CSP DIGITAL TRUNKED AND RADIO SYSTEM QUESTION AND ANSWERS UPDATED 7/30/2018 1.3 Current Radio Systems General Question Can the Klein ISD verify if the repeater frequency pairs used at the high schools and intermediate schools would be available for the system if they can be relicensed

More information

Joint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building

Joint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building Joint System Owners Customer Information Meeting Thursday, December 7, 2017 Environmental Service Building City of Tacoma Steve Victor, Deputy City Attorney 253-591-5638 svictor@ci.tacoma.wa.us Pierce

More information

TOPAZ Regional Wireless Cooperative (TRWC) Board of Directors

TOPAZ Regional Wireless Cooperative (TRWC) Board of Directors Date: September 6, 8 To: Through: From: Subject: TOPAZ Regional Wireless Cooperative (TRWC) Board of Directors Dale Shaw, TRWC Executive Director Randy Thompson Administrator Update Capital Projects )

More information

MOTOROLA SOLUTIONS 2017 K-12 EDUCATION INDUSTRY SURVEY REPORT SURVEY REPORT 2017 SCHOOL COMMUNICATIONS

MOTOROLA SOLUTIONS 2017 K-12 EDUCATION INDUSTRY SURVEY REPORT SURVEY REPORT 2017 SCHOOL COMMUNICATIONS MOTOROLA SOLUTIONS 2017 K-12 EDUCATION INDUSTRY SURVEY REPORT SURVEY REPORT 2017 SCHOOL COMMUNICATIONS THE POWER OF UNIFIED SCHOOL COMMUNICATIONS We look to our nation s schools as an oasis of learning,

More information

JOB ANNOUNCEMENT. Whitman County Communications Systems Manager

JOB ANNOUNCEMENT. Whitman County Communications Systems Manager JOB ANNOUNCEMENT POSITION: Department: Whitman County Communications Systems Manager Emergency Management Salary Range: $60,000 to 99,000 DOQ : plus Benefits (medical, vision, and dental, PERS) TO APPLY

More information

WHEREVER THE CALL TAKES YOU

WHEREVER THE CALL TAKES YOU CONTACT your TELSTRA ACCOUNT EXECUTIVE CALL 1300 TELSTRA (1300 835 787) telstra.com/enterprise telstra managed Radio networks march 2012 WHEREVER THE CALL TAKES YOU things you need to know This document

More information

DCC Trunked Radio System Proposer Questions and Answers, rev 2 September 28, 2011

DCC Trunked Radio System Proposer Questions and Answers, rev 2 September 28, 2011 Proposer questions are in Times New Roman plain text. Answers to proposer questions are in Times New Roman italics. General Q1. RFP Extension. Due to the large number of Buildings requiring In-Building

More information

State Radio Project. May Monthly Progress Report

State Radio Project. May Monthly Progress Report State Rad o Project State Radio Project May 2012 Monthly Progress Report PROject GOALS Infrastructure Repair or replace critical components of Oregon s deteriorating state radio network and extend the

More information

Textron Reports Third Quarter 2014 Income from Continuing Operations of $0.57 per Share, up 62.9%; Revenues up 18.1%

Textron Reports Third Quarter 2014 Income from Continuing Operations of $0.57 per Share, up 62.9%; Revenues up 18.1% Textron Reports Third Quarter Income from Continuing Operations of $0.57 per Share, up 62.9%; Revenues up 18.1% 10/17/ PROVIDENCE, R.I.--(BUSINESS WIRE)-- Textron Inc. (NYSE: TXT) today reported third

More information

ESF 2. Communications

ESF 2. Communications ESF 2 Communications This page left blank intentionally. 1 Introduction: Purpose and Scope ESF 2 organizes, establishes, and maintains the communications capabilities among appropriate agencies/entities

More information

Wicomico County. RFP for new 700/800 hybrid P25 Phase II radio system

Wicomico County. RFP for new 700/800 hybrid P25 Phase II radio system Wicomico County RFP for new 700/800 hybrid P25 Phase II radio system 1 Wicomico County Proposal Team David G. Shipley Director of Emergency Services Rick Konrad Purchasing Agent Charles J. Ryan III, Esq.

More information

Attachment C to Modification # 6 to VA HSMM. Schedule of Fees

Attachment C to Modification # 6 to VA HSMM. Schedule of Fees Task A. Perform radio asset inventory, needs assessment, and project expected growth. B. Document existing radio frequency authorizations. Devise a frequency reuse strategy. Determine the capacity of the

More information

The Partnership Process- Issue Resolution in Action

The Partnership Process- Issue Resolution in Action The Partnership Process- Issue Resolution in Action AAPA- Quality Partnership Initiative rd Annual Project Managers Workshop December 5-6, 5 2007 3 rd Charles A. Towsley The Challenge: Environmental Conflict

More information

Textron Reports First Quarter 2016 Income from Continuing Operations of $0.55 per Share, up 19.6%; Reaffirms 2016 Financial Outlook

Textron Reports First Quarter 2016 Income from Continuing Operations of $0.55 per Share, up 19.6%; Reaffirms 2016 Financial Outlook Textron Reports First Quarter 2016 Income Continuing Operations of $0.55 per Share, up 19.6%; Reaffirms 2016 Financial Outlook April 20, 2016 06:30 AM Eastern Daylight Time PROVIDENCE, R.I.--(BUSINESS

More information

Public Safety Radio System Update September 9, 2013

Public Safety Radio System Update September 9, 2013 Public Safety Radio System Update September 9, 2013 Bill Greeves, CIO John Higgins, Deputy CIO 1 Timeline Beginning in 2016, Motorola will no longer support the current system. Also, future upgrades are

More information

800 MHz Trunked Radio. Management Briefing Number 2 ONE OF A SERIES OF NOTES ON TECHNOLOGY FROM ADCOMM

800 MHz Trunked Radio. Management Briefing Number 2 ONE OF A SERIES OF NOTES ON TECHNOLOGY FROM ADCOMM 800 MHz Trunked Radio Management Briefing Number 2 ONE OF A SERIES OF NOTES ON TECHNOLOGY FROM ADCOMM Copyright Adcomm Engineering 1991 This short paper offers discussion on trunked radio systems it is

More information

Narrow-banding What It Means to Public Safety Webinar

Narrow-banding What It Means to Public Safety Webinar Narrow-banding What It Means to Public Safety Webinar Rick Mulvihill Director Presenters Charlie Stephenson Director of Outreach and Technology Assistance Robert Rhoads Office of Emergency Communications,

More information

Butler County Department of Emergency Services. Butler County Radio Project Briefing

Butler County Department of Emergency Services. Butler County Radio Project Briefing Butler County Department of Emergency Services Butler County Radio Project Briefing Why are we here? Define : What is success = Establish long term solution for Public Safety Land-Mobile Radio FCC Mandate-

More information

The Eastern Shore of Virginia Radio Analysis

The Eastern Shore of Virginia Radio Analysis The Eastern Shore of Virginia Radio Analysis The Commonwealth of Virginia, Virginia Information Technologies Agency, by request of the Eastern Shore of Virginia 911 Commission 1, has analyzed communications

More information

Sanford Health F-M Ambulance. ARMER 800 MHz Radio System Participation Plan

Sanford Health F-M Ambulance. ARMER 800 MHz Radio System Participation Plan Sanford Health F-M Ambulance ARMER 800 MHz Radio System Participation Plan Sanford Medical Services (FM Ambulance), North Dakota 800 MHz ARMER Radio Participation Plan Contents 1. Introduction and ARMER

More information

Proposal May 17, 2016 Primary Election

Proposal May 17, 2016 Primary Election Proposal May 17, 2016 Primary Election 2 P age January 2016 Table of Contents Executive Summary 5 Background WCCCA History 1990 Bond Measure Population Growth and the Changing Demand for Service Technology

More information

Columbia Communications District Request for Information New Radio Communications System

Columbia Communications District Request for Information New Radio Communications System Columbia 9-1-1 Communications District Request for Information New Radio Communications System Submission Deadline January 2, 2018 1 1 Overview 1.1 Introduction The Columbia 911Communications District

More information

Orange County Sheriff s Department. Jo Ann Galisky Assistant Sheriff

Orange County Sheriff s Department. Jo Ann Galisky Assistant Sheriff Orange County Sheriff s Department Jo Ann Galisky Assistant Sheriff Orange County Demographics 798 Square Miles 34 cities 42 Miles of coastline Population- 2,978,800 2 nd largest county in California in

More information

ADDENDUM 1. Forsyth County. Request for Qualifications and Proposals. Consulting Services for Public Safety Radio Communications

ADDENDUM 1. Forsyth County. Request for Qualifications and Proposals. Consulting Services for Public Safety Radio Communications March 27, 2018 Forsyth County Request for Qualifications and Proposals Consulting Services for Public Safety Radio Communications Qualifications and Proposals Will Be Received Until **Date Change** 12:00

More information

Emergency Support Function 2. Communications. Iowa County Emergency Management Agency

Emergency Support Function 2. Communications. Iowa County Emergency Management Agency Emergency Support Function 2 Communications ESF Coordinator: Iowa County Emergency Management Agency Primary Agencies: Iowa County Communications E 9-1-1 Center Support Agencies: Iowa County Emergency

More information

101 Overview Presentation

101 Overview Presentation 101 Overview Presentation V1.00 30 minutes "Education is the most powerful weapon which you can use to change the world." - Nelson Mandela Contact support@omnitronics.com.au North America Contact support@omnitronicsworld.com

More information

UPGRADES TO 800 MHZ TRUNK RADIO SYSTEM TECHNOLOGY

UPGRADES TO 800 MHZ TRUNK RADIO SYSTEM TECHNOLOGY INFORMATION PAPER BUSINESS ADMINISTRATION COMMITTEE UPGRADES TO 800 MHZ TRUNK RADIO SYSTEM TECHNOLOGY December 2013 Purpose To provide information on the completed analysis for a phased technology upgrade

More information

Training that is standardized and supports the effective operations of NIIMS.

Training that is standardized and supports the effective operations of NIIMS. HISTORY OF THE INCIDENT COMMAND SYSTEM In the early 1970's, Southern California experienced several devastating wildland fires. The overall cost and loss associated with these fires totaled $18 million

More information

POSITION DESCRIPTION

POSITION DESCRIPTION State of Michigan Civil Service Commission Capitol Commons Center, P.O. Box 30002 Lansing, MI 48909 Position Code 1. RACCTCHE POSITIO DESCRIPTIO This position description serves as the official classification

More information