IFZONE PROJECT: IMPROVING CIRCULATION IN NEUTRAL SECTIONS. ADIF. Railway Technology Centre. Severo Ochoa, , Malaga, Spain.
|
|
- Kelley Blake
- 6 years ago
- Views:
Transcription
1 IFZONE PROJECT: IMPROVING CIRCULATION IN NEUTRAL SECTIONS José Conrado Martínez Acevedo 1) ( ), Carlos Tobajas Guerra 2) ( ), Luis Fernando Almenara 1) ( ), Jorge Iglesias Díaz 2), Juan Cabello Álvarez 2) ( Antonio Berrios Villalba 1) 1) ADIF. Railway Technology Centre. Severo Ochoa, , Malaga, Spain. 2) ADIF. Titan , Madrid, Spain. Txomin Nieva ( ), Mikel Aiarzaguena ( TRAINELEC. Industrial Park Katategi - Plot 3 bis , IRURA-Gipuzkoa, Spain. ABSTRACT Electrical phase separation Neutral Sections are installations that are necessary in High-Speed lines as they prevent electrical phase unbalance in the three phase grids that power them. The existence of neutral sections may entail some occasional operating problems and therefore an attempt is made to minimise how many of them there are and improve operation. In this sense, this paper proposes new technical approaches directed at this reduction and presenting and adopting new techniques that improve the operation of the trains when they run through them. All of these approaches are subject to the IFZONE Investigation Project. Although both aspects can be considered general, the paper is based on the experience and experimentation of the Administrador de Infraestructuras Ferroviarias (ADIF - Railway Infrastructure Administrator) in the neutral sections of the Spanish High-Speed network. 1. INTRODUCTION In the electrification of High-Speed railways (therefore, with single-phase alternating current), the power supply to the traction electrical substations is carried out via different electrical phases so that the balance produced on the three-phase transport lines is as low as possible 1. A standard substation with these characteristics is schematised in Figure 1. There are generally not more than two voltage transformers, which may be fed from the equal or different electrical phases. In the first situation, phase rotation would be carried out by substation while in the second it would be carried out by transformers. In any event, and according to the adopted rotation, the sections of catenary powered from each transformer will be in that electrical phase and therefore the transition between sections of a different phase will have to be foreseen in order not to connect them when the train passes. These sections are commonly called Electrical phase separation neutral sections (hereinafter they will only be called neutral sections). As can be deduced, in the case of adopting a rotation by substation, having a neutral section in it is not necessary, but rather only between collateral substations (Figure 1). If rotation is carried out by a transformer, a neutral section in the substation and between collateral substations will be required. It should be pointed out that the voltages that can be applied between the terminals of the primary winding of the transformers are the line-to-line voltages that can be obtained combining the three phase voltages of the transport three-phase grid. On their part, the voltages in the secondary winding are obtained applying the transformer transformation ratio to the primary voltages. As to be expected, the time rates of the secondary voltages do not vary as they are calculated multiplying the primary voltages by a scale. 1 The special characteristics of networks powered at 15 kv/1.67 Hz have not been considered.
2 Figure 1. Single-phase alternating current substation: a) Voltage transformers powered from the electrical phases themselves; b) Voltage transformers powered from four different electrical phases. (Source: ADIF). 2. TECHNICAL CHARACTERISTICS Considering the case of the Spanish High-Speed network, a neutral section is built with two insulated overlaps between which the de-energised catenary is installed (Figure 2). According to the indicated diagram, catenary 1 is powered from the electrical phase 2 (voltage V1) while catenary 2 is powered from phase 2 (voltage 2). The de-energised catenary is installed between the two (catenary 3). The train that is coming along catenary 1 enters into contact with catenary 3 via the first sectioning. Therefore, when the pantograph has lost contact with catenary 1, it only rubs catenary 3 until it reaches the second sectioning, when it starts to come into contact with catenary 3. It should be pointed out that the train enters the neutral section moving by mechanical inertia as its traction switch has been disconnected. It will reconnect when it leaves to be able to be powered from the new stretch again. V1 V2 Figure 2. Mechanical layout of a neutral section of catenary. (Source: ADIF). Logically, on passing from catenary 1 to catenary 3, the pantograph will connect to voltage V1. The same will happen with the V2 voltage on passing on the sectioning of catenary 2. The rest of the time,
3 the voltage of catenary 3 will vary depending on the difference of the electrical phases of the voltages of the ends and on the impedance of the de-energised section. It can be seen that if the time rates of the voltages of the collateral voltage transformers are consecutive (60º phase difference), the electric voltage between the ends of the neutral section is roughly the nominal voltage of the secondary of the transformers. If the rates are not consecutive (phase difference of 120º), the voltage between ends will be roughly 3 times the nominal voltage of the secondary. 3. OPERATING ASPECTS A neutral section may be announced with enough time for the train to be able to carry out the opening operation of the traction switch 2. As seen above, the opening requirement is due to the pantograph energising the de-energised catenary for a few seconds using the end sectionings, an action that may involve the electrical bypassing of both routes if the train has two pantographs that connect catenaries 1 and 2 via catenary 3 when passing over the sectionings. Furthermore, in short neutral sections, it has been seen that a very high speeds the arc extinction might not have occurred when the pantograph is already in the second sectioning. In any event, the greater the length of the deenergised section, the fewer problems will occur although the loss of speed the train suffers will generally be higher. The need for installing neutral sections in high-speed lines may entail the following problems: 1. Breakdowns on the catenary if a train enters with the traction switch closed. In the event of circulating under ATP this type of incidents will not occur. 2. Trains that stop in the section de-energised (for different reasons) and which cannot start up again on their own. Normally a train stopping affects the regularity of the rest of the trains circulating behind it, as some minutes are required for energising the de-energised section and being able to start to run again. 3. Generation of fatigue in the train s traction equipment due to continuous openings and closings of the circuit. It should be pointed out here that the train s lost speed when passing through the neutral section 3 is approximately 9 km/h with a total time passed since traction of roughly 22 s and having run roughly 1600 m. Even so, it has been seen that the existence of neutral sections on the line does not affect the total route time and the total amount of electric energy consumed. Even so, and as to be expected, the ideal situation for operation would be to have as few neutral sections as possible. 4. REDUCTION OF THE AMOUNT OF NEUTRAL SECTIONS As in the current situation it is not possible to get rid of the neutral section as an installation that prevents the unbalance of the network s phases, the objective would be reduce the amount of them. As seen above, they may be situated between collateral substations or in the electric substation itself if the phase rotation is carried out by the voltage transformer. It is important to highlight that the neutral section located in the substation is more critical than the one between collateral substations as in the case of an incorrect connection between adjacent routes, the short circuit produced would be more harmful for the installation. The main objective is therefore to do away this neutral section in substations. 2 Automatic process if circulating under ATP. 3 Data obtained after the tests carried out by ADIF on Madrid-Barcelona High-Speed Line and Madrid- Seville High-Speed Line (a mean circulation speed of 270 km/h is considered).
4 Electrical phase rotation in the substation or in the transformers, and therefore the amount of neutral sections that will finally exist is the outcome of the forecast of the demand of electric power from the supply grid. In this sense, it is easy to see that the unbalance entered in the supply point increases the higher the required power. Therefore, a rotation at transformer level would be associated to a demanding traffic scenario (high power and low frequency) that would possibly affect the balance of the network s phases in the event of only adopting a rotation on the substation level. It should be pointed out that in Spain the requirement imposed by the technical operator of the transport system 4, is for unbalance to not exceed 0.7% for a duration of minutes and 1% for a duration of seconds. If the most restrictive traffic scenario were not to be reached until a period of time has passed, with other prior scenarios existing, the temporary cancelling of the substation s neutral section may be viable from a technical point of view. In this situation, it would be useful to have an analysis to be able to assess the degree of unbalance in the network according to the frequency of trains that circulate on the line. Furthermore, and considering that the unbalance increases the lower the phase difference between adjacent transformers, it would also be useful to have a specific analysis for each of the phase difference configurations. All of these considerations should be born in mind from the moment the installation is designed, as a requirement would be for the three electrical phases of the grid to be laid out in the substation (consult diagram in Figure 1). In this way, a possible reconnection would be simpler from a construction point of view. As to be expected, all of these actions should be coordinated at the right time with the technical operator of the transport network. 5. INTRODUCTION OF A STATIC SWITCHING SYSTEM Currently some administrators 5 including ADIF 6 are starting to try static switching systems to allow the training making the transition between electrical phases directly, without being affected in any way and with the aim of improving the operating capacity of the exploitation. These type of systems use switches on each side of the neutral section, which are represented by semiconductor equipment that allow carrying out a switching in a very short space of time. A very important characteristic of this type of switching is that the exact position of the train should be born in mind. If the neutral section schematised in Figure 2 is considered, the operating principle of the system would be as follows: The train that is coming along catenary 1 is detected by a detection system that informs the switching system of the next entry of the train into the neutral section. At this moment, a close command is established to switch 1 so that the de-energised section is powered at voltage V1. The train does not receive the open command from the traction disconnector at any time. Again, the detection system should detect that the train is totally situated inside the deenergised section. When this condition occurs, an open command is issued on switch 1 and a close command on switch 2 so that the de-energised section is powered at voltage V2. This process is short enough for the train not to detect a lack of voltage in the catenary (which 4 Red Eléctrica de España (REE Spanish Electricity Grid). 5 It should be pointed out that Japanese high-speed lines already have these type of systems in service (for some years), although they are continuing to experiment and optimise the initial development. 6 The experimental system designed by ADIF together with other companies is called SCZN (Sistema de Conmutación de Zona Neutra Neutral Section Switching System) and is subject to a Research Project financed by the Ministry of Science and Innovation (IFZONE Project).
5 would involve opening the disconnector) and there is therefore no loss of traction. The train leaves the neutral section fed by electrical phase 2. In a given point of the exit of the neutral section, the detection system identifies the total passing of the train and starts to normalise the neutral section (opening of switch 2), and is ready for the next train to pass. It should be pointed out that the detection system may be represented by a track circuit specially designed for this function (as is the case of the Japanese system), or by a series of electromagnetic pedals that detect the position of the train wheel (system used by ADIF). Figure 4 represents the schematic form of the shunting sequence of the switching system when the train passes through the neutral section. Figure 4. Shunting sequence of the switching system. (Source: IZONE Project). As indicated above, the switching system should be designed to act in a given time that is determined by the characteristics of the material that circulates on the High-Speed line. Thus, if a detection system based on electromagnetic pedals is used (the case of ADIF), the main characteristic that determines the system s reaction time is the distance between the first wheel of the train and the nearest pantograph that it may carry in service.
6 The length of the de-energised catenary is also a fundamental parameter for analysing the viability of installing this type of systems. Specifically, it has been able to conclude that if this length is lower than established for an interoperable neutral section (402 m), installing switches will not be viable. The reason lies in considering the circulation in double composition of a 200 m train. In this case, if the distance existing between the train s first wheel and the farthest away pantograph from the second composition the train may carry in service (a small auxiliary distance derived from the coupling of the two trains should also be considered), it is concluded that this distance is the one that determines the maximum length of the de-energised section to be used. Therefore, the greater the de-energised section the simpler it will be to install a system with these characteristics 7. Considering the definitive situation of the pedal and the maximum train circulation speed, the time in which the system should react for carrying out the switching can be calculated. It has been concluded that in the case of ADIF the minimum reaction time should be around 0.3 s. 6. INTRODUCTION OF AN INDEPENDENT PROTECTION SYSTEM Another possible improvement for the operating capacity of the existing neutral sections on the High- Speed line is the introduction of a system ADIF has called SPZN (Sistema de Protección de Zona Neutra Neutral Section Protection System). It is an independent system to the neutral section control and is designed to prevent the train from entering the neutral section with the traction disconnector closed (a situation that could occur in the case of circulating without ATP, for example, due to a breakdown of the latter). The operating principle is based on measuring current using a sensor located in an area near to the rubbing area of the two catenaries in the sectioning. In normal operating conditions, circulation of current along this area should not exist, and if it is detected the sensor would emit a trigger command to the substation s switches. Analysing the type of sensor to be used is important to develop an easy to maintain and reliable system. 7. CONCLUSIONS The connection of voltage transformers in the same traction electric-power substation should be carried out between the same electrical phases so that the catenary neutral section in front of the substation can be eliminated. The adjacent transformers belonging to different traction substations are connected with a phase difference of 60º achieving in this way that the voltage existing between the ends of the catenary neutral section are roughly the same as the nominal voltage in the secondary of the transformers. An important improvement in the existing neutral sections would be represented by the introduction of a switching system (SCZN) that allows the train to make a transition between electrical phases without being affected in any whatsoever. Another system to be introduced would be the SPZN (protection system) preventing accidental connection between different electrical phases. 7 Thus, for example, in the Japanese railway network, a neutral section may be 1000 m long.
Grid Impact of Neutral Blocking for GIC Protection:
Report submitted to EMPRIMUS - Critical Infrastructure Protection Grid Impact of Neutral Blocking for GIC Protection: Impact of neutral grounding capacitors on network resonance Prepared By: Athula Rajapakse
More informationCatenary and autotransformer coupled optimization for 2x25kV systems planning
Power Supply System Analysis, Design and Planning 113 Catenary and autotransformer coupled optimization for 2x25kV systems planning E. Pilo, L. Rouco & A. Fernández Instituto de Investigación Tecnológica,
More informationERTMS/ETCS UNIT INTERFACES BETWEEN CONTROL-COMMAND AND SIGNALLING TRACKSIDE AND OTHER SUBSYSTEMS
EUROPEAN RAILWAY AGENCY ERTMS Unit ERTMS/ETCS UNIT Reference: ERA/ERTMS/033281 Document type: Version : 2.0 T Date : 12/05/2014 Edited by Quality review Approved by Name Angelo Chiappini Pio Guido Position
More informationTCR VERSUS VSC FOR RAILWAY LOAD BALANCING AND COMPENSATION. A CASE STUDY.
TCR VERSUS VSC FOR RAILWAY LOAD BALANCIN AND COMPENSATION. A CASE STUDY. Octavio M. Ruiz arcía Norcontrol. Soluziona. Spain. oruizg@soluziona.com Antonio ómez Expósito Dpt. of Electrical Eng. University
More informationWhen surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS
TRANSFORMER IN GRID When surge arres t ers are installed close to a power transformer, they provide protection against lightning overvoltage ABSTRACT The aim of this research article is to determine the
More informationP.O (November 2009) This is an unofficial translation of the latest draft of the Spanish grid code. Source: Jason MacDowell, GE Energy
INSTALLATIONS CONNECTED TO A POWER TRANSMISSION SYSTEM AND GENERATING EQUIPMENT: MINIMUM DESIGN REQUIREMENTS, EQUIPMENT, OPERATIONS, COMMISSIONING AND SAFETY. P.O. 12.2 (November 2009) This is an unofficial
More informationERTMS/ETCS UNIT INTERFACES BETWEEN CONTROL-COMMAND AND SIGNALLING TRACKSIDE AND OTHER SUBSYSTEMS EUROPEAN RAILWAY AGENCY.
EUROPEAN RAILWAY AGENCY ERTMS Unit ERTMS/ETCS UNIT Reference: ERA/ERTMS/033281 Document type: Version : 1.2 5 T Date : 15/11/201214/03/2013 Edited by Quality review Approved by Name Position Date & Signature
More informationEMC in the railway environment Hans Bängtsson
EMC in the railway environment 2018-05-17 Hans Bängtsson Aspects of EMC in the railway environment LEGAL radio-, TV- and tele communications must not be interfered SAFETY The railway signaling ( red and
More informationAbstract. 1 Introduction
Short circuit analysis for traction power supply system of new concept guided busway A. Del Naja, V. Galdi, L. Ippolito & A. Piccolo Diparimento diingegneria dell'informazione ed Ingegneria Elettrica -
More informationSERIES ACTIVE power filters have proved to be an interesting
928 IEEE TRANSACTIONS ON POWER ELECTRONICS, VOL. 14, NO. 5, SEPTEMBER 1999 A Fault Protection Scheme for Series Active Power Filters Luis A. Morán, Senior Member, IEEE, Ivar Pastorini, Juan Dixon, Senior
More informationCOMMISSION REGULATION (EU) No /.. of XXX
EUROPEAN COMMISSION Brussels, XXX [ ](2013) XXX draft COMMISSION REGULATION (EU) No /.. of XXX on implementing Directive 2009/125/EC of the European Parliament and of the Council with regard to small,
More informationHigh Voltage DC Transmission 2
High Voltage DC Transmission 2 1.0 Introduction Interconnecting HVDC within an AC system requires conversion from AC to DC and inversion from DC to AC. We refer to the circuits which provide conversion
More informationNational Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance
National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION and Guidance NSI 26 RAILWAY CONNECTION CIRCUITS Copyright National Grid plc 2016, all rights reserved. No part of this publication
More informationAn Audio Frequency Model of a 2x25 kv Traction Line for High Speed Railway Systems
An Audio Frequency Model of a 2x25 kv Traction Line for High Speed Railway Systems RICHARD BARTONI Railway Engineer Corso Italia, 83 00100 Rome ITALY bartoni@gtaroma1.191.it REGINA LAMEDICA Full Professor
More informationEarthing Guidance Notes
Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head
More informationThe Effect of Fault States of the Twelve-pulse Rectifier During the Recuperation
Transactions on Electrical Engineering, Vol. 3 (04), No. 8 The Effect of Fault States of the Twelve-pulse Rectifier During the Recuperation Ladislav Mlynařík ), Radovan Doleček ), ) University of Pardubice,
More informationFerroresonance Experience in UK: Simulations and Measurements
Ferroresonance Experience in UK: Simulations and Measurements Zia Emin BSc MSc PhD AMIEE zia.emin@uk.ngrid.com Yu Kwong Tong PhD CEng MIEE kwong.tong@uk.ngrid.com National Grid Company Kelvin Avenue, Surrey
More informationMitigation of Negative Sequence Currents and Effect of Magnetic Inrush Currents in Indian Railway Traction System
ISSN (Print) : 2347-671 (An ISO 3297: 27 Certified Organization) Vol. 4, Special Issue 6, May 215 Mitigation of Negative Sequence Currents and Effect of Magnetic Inrush Currents in Indian Railway Traction
More informationBreadboard Traffic Light System
1 Breadboard Traffic Light System Alex Sawicki & Geoff Yeung TEJ4M Mr. Bawa June20, 2013 2 Table of Contents Materials 3 Background Research 4 Experimental Procedure 7 Method One 8 Method Two 9 Conclusions
More informationRecent results on the Power Quality of Italian 2x25 kv 50 Hz railways
th IMEKO TC4 International Symposium and 18th International Workshop on ADC Modelling and Testing Research on Electric and Electronic Measurement for the Economic Upturn Benevento, Italy, September 15-17,
More informationDISCUSSION OF FUNDAMENTALS
Unit 4 AC s UNIT OBJECTIVE After completing this unit, you will be able to demonstrate and explain the operation of ac induction motors using the Squirrel-Cage module and the Capacitor-Start Motor module.
More informationVOLTAGE REGULATOR R 449. Installation and maintenance. This manual must be sent to the end user R 449 X2 Z1 X1 Z2 E+ E- (12V - 10A)
This manual must be sent to the end user X2 Z1 X1 Z2 E+ E- J1 t (12V - 10A) ~ 10 ohms Exciter field + - Isolated DC power supply Installation and maintenance WARNING TO AVOID HARM EITHER TO PEOPLE OR TO
More informationCoordination of surge arresters in DC 3 kv railway traction system field tests
Coordination of surge arresters in DC 3 kv railway traction system field tests Miroslaw Zielenkiewicz Tomasz Maksimowicz Center of Protection against Overvoltages and Electromagnetic Interferences RST
More informationBusbars and lines are important elements
CHAPTER CHAPTER 23 Protection of Busbars and Lines 23.1 Busbar Protection 23.2 Protection of Lines 23.3 Time-Graded Overcurrent Protection 23.4 Differential Pilot-Wire Protection 23.5 Distance Protection
More informationA NEW DIRECTIONAL OVER CURRENT RELAYING SCHEME FOR DISTRIBUTION FEEDERS IN THE PRESENCE OF DG
A NEW DIRECTIONAL OVER CURRENT RELAYING SCHEME FOR DISTRIBUTION FEEDERS IN THE PRESENCE OF DG CHAPTER 3 3.1 INTRODUCTION In plain radial feeders, the non-directional relays are used as they operate when
More informationAppendix D Fault Levels
Appendix D Fault Levels Page 1 Electricity Ten Year Statement November 2013 D.1 Short Circuit Currents Short Circuit Currents Three phase to earth and single phase to earth short circuit current analyses
More informationTable of Contents. Introduction... 1
Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...
More informationStatus Date Prepared Reviewed Endorsed Approved
Discipline Engineering Standard NSW Category Signalling Title Reference Number SDS 17 (RIC Standard: SC 00 13 01 17 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards
More informationSizing the neutral wire cross-section and minimization of neutral currents using microgeneration in low voltage networks
Sizing the neutral wire cross-section and minimization of neutral currents using microgeneration in low voltage networks André Braga Instituto Superior Técnico Av. Rovisco Pais, 1049-001 Lisbon, Portugal
More informationOPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES
OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES U AJMAL, GE Grid Solutions UK Ltd, usman.ajmal@ge.com S SUBRAMANIAN, GE Grid Solutions UK Ltd, sankara.subramanian@ge.com H Ha GE Grid Solutions
More informationOvervoltage Protection of Light Railway Transportation Systems
Overvoltage Protection of Light Railway Transportation Systems F. Delfino, R. Procopio, Student Member, IEEE, and M. Rossi, Student Member, IEEE Abstract In this paper the behavior of the power supply
More informationSicat Master. Engineering of overhead contact line systems. siemens.com/rail-electrification
Sicat Master Engineering of overhead contact line systems siemens.com/rail-electrification When engineering overhead contact lines for mass transit and main line railways, we combine the calculations of
More informationThe Confusion Surrounding Stray Voltage
The Confusion Surrounding Stray Voltage Jim Burke, InfraSource Inc., Fellow, IEEE Abstract While stray voltage has been a concern for farm livestock for many years, it is only within the past few years
More informationPower Frequency Withstand Voltage On-site testing of 400 kv GIS
Power Frequency Withstand Voltage On-site testing of 400 kv GIS D. Anaraki Ardakani, A. Omidkhoda, M. Solati High Voltage Engineering Center ACECR Tehran, Iran Da_ardakani@yahoo.com Paper Reference Number:
More informationGIS Disconnector Switching Operation VFTO Study
GIS Disconnector Switching Operation VFTO Study Mariusz Stosur, Marcin Szewczyk, Wojciech Piasecki, Marek Florkowski, Marek Fulczyk ABB Corporate Research Center in Krakow Starowislna 13A, 31-038 Krakow,
More informationElectricity Ten Year Statement November Electricity Ten Year Statement November Appendix D
Electricity Ten Year Statement November 2017 01 Electricity Ten Year Statement November 2017 001 Appendix D 1 Short-circuit currents 02 2 Short-circuit current terminology 04 3 Data requirements 07 4 Fault
More informationMODERN COMPUTATIONAL METHODS FOR THE DESIGN AND ANALYSIS OF POWER SYSTEM GROUNDING
MODERN COMPUTATIONAL METHODS FOR THE DESIGN AND ANALYSIS OF POWER SYSTEM GROUNDING J. Ma and F. P. Dawalibi Safe Engineering Services & technologies ltd. 1544 Viel, Montreal, Quebec, Canada, H3M 1G4 Tel.:
More information2 Grounding of power supply system neutral
2 Grounding of power supply system neutral 2.1 Introduction As we had seen in the previous chapter, grounding of supply system neutral fulfills two important functions. 1. It provides a reference for the
More informationAbstract. 1 Introduction
Invited Paper Modelling and simulation of electric railway traction, track signalling and power systems R.J. Hill School of Electronic and Electrical Engineering, University CWerZom Dotmz, BofA #^42 7,47,
More informationImproving Passive Filter Compensation Performance With Active Techniques
IEEE TRANSACTIONS ON INDUSTRIAL ELECTRONICS, VOL. 50, NO. 1, FEBRUARY 2003 161 Improving Passive Filter Compensation Performance With Active Techniques Darwin Rivas, Luis Morán, Senior Member, IEEE, Juan
More informationOptimization of power transformers based on operative service conditions for improved performance
21, rue d Artois, F-75008 PARIS A2-207 CIGRE 2012 http : //www.cigre.org SUMMARY Optimization of power transformers based on operative service conditions for improved performance A.Prieto, M.Cuesto, P.Pacheco,
More informationR Distribution Transformers. Mineral Oil-Immersed, Self-Cooled, 60 Hertz Voltages and Connections. Reference Data
Distribution Transformers Mineral Oil-Immersed, Self-Cooled, 60 Hertz Voltages and Connections R201-90-2 Reference Data CONTENTS POPULAR DlSTRIBUTlON TRANSFORMER AND CIRCUIT VOLTAGES... 1 2400-Volt Systems
More informationImproving High Voltage Power System Performance. Using Arc Suppression Coils
Improving High Voltage Power System Performance Using Arc Suppression Coils by Robert Thomas Burgess B Com MIEAust CPEng RPEQ A Dissertation Submitted in Fulfilment of the Requirements for the degree of
More informationCHAPTER 5 POWER QUALITY IMPROVEMENT BY USING POWER ACTIVE FILTERS
86 CHAPTER 5 POWER QUALITY IMPROVEMENT BY USING POWER ACTIVE FILTERS 5.1 POWER QUALITY IMPROVEMENT This chapter deals with the harmonic elimination in Power System by adopting various methods. Due to the
More informationDESIGN OF A 45 CIRCUIT DUCT BANK
DESIGN OF A 45 CIRCUIT DUCT BANK Mark COATES, ERA Technology Ltd, (UK), mark.coates@era.co.uk Liam G O SULLIVAN, EDF Energy Networks, (UK), liam.o sullivan@edfenergy.com ABSTRACT Bankside power station
More informationGSM-R Traffic Model for Radio-based Train Operation Wolfgang Hillenbrand / Holm Hofestädt
GSM-R Traffic Model for Radio-based Train Operation Wolfgang Hillenbrand / Holm Hofestädt Summary The article presents the GSR-R traffic model for FFB railway operation (FFB is the German abbreviation
More informationPhase earthing system - method for faulty phase selection with phase-to-earth faults. Ari Nikander Tampere University of Technology
Phase earthing system - method for faulty phase selection with phase-to-earth faults Ari Nikander Tampere University of Technology - 2 - Preface This report has been done as a part of the research work
More informationVoltage Sag Index Calculation Using an Electromagnetic Transients Program
International Conference on Power Systems Transients IPST 3 in New Orleans, USA Voltage Sag Index Calculation Using an Electromagnetic Transients Program Juan A. Martinez-Velasco, Jacinto Martin-Arnedo
More informationEI HIGH VOLTAGE INSULATION TESTING POLICY
Network(s): Summary: ENGINEERING INSTRUCTION EI 09-0001 HIGH VOLTAGE INSULATION TESTING POLICY EPN, LPN, SPN This engineering instruction details the policy for the on-site insulation testing of new and
More informationAbstract. 1 Introduction
Energy Production and Management in the 21st Century, Vol. 1 345 Investigation of the electrical strength of a contact gap of the high voltage live tank circuit breaker 126 kv class using an intelligent
More informationMAJOR ADVANCES IN MV/LV SUBSTATIONS. Th.Grima et JF.Faltermeier. Groupe CAHORS, France SUMMARY
MJOR DVNCES IN MV/LV SUSTTIONS Th.Grima et JF.Faltermeier Groupe CHORS, France SUMMRY Improvements on the reliability of the components of the network, combined with a well-considered policy of cost reduction
More informationFixed Series Compensation
Fixed Series Compensation High-reliable turnkey services for fixed series compensation NR Electric Corporation The Fixed Series Compensation (FSC) solution is composed of NR's PCS-9570 FSC control and
More informationPerformance of high voltage transducers for measurement of power quality disturbances modeling and simulation
Performance of high voltage transducers for measurement of power quality disturbances modeling and simulation HÉDIO TATIZAWA 1, ERASMO SILVEIRA NETO 2, GERALDO F. BURANI 1, ANTÔNIO A. C. ARRUDA 1, KLEIBER
More informationTest of rolling stock electromagnetic compatibility for cross-domain interoperability
IET Intelligent Transport Systems Research Article Test of rolling stock electromagnetic compatibility for cross-domain interoperability ISSN 1751-956X Received on 2nd March 2015 Revised on 17th July 2015
More information1. Introduction to Power Quality
1.1. Define the term Quality A Standard IEEE1100 defines power quality (PQ) as the concept of powering and grounding sensitive electronic equipment in a manner suitable for the equipment. A simpler and
More informationECP HV INSULATION TESTING
Document Number: ECP 11-0006 Network(s): Summary: All ENGINEERING COMMISSIONING PROCEDURE ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing of new and
More informationModeling and Validation of an Unbalanced LV Network Using Smart Meter and SCADA Inputs
Modeling and Validation of an Unbalanced LV Network Using Smart Meter and SCADA Inputs Derek C. Jayasuriya, Max Rankin, Terry Jones SP AusNet Melbourne, Australia Julian de Hoog, Doreen Thomas, Iven Mareels
More informationActive Power Filters: A Comparative Analysis of Current Control Techniques for Four-Leg Full-Bridge Voltage Source Inverters
Active Power Filters: A Comparative Analysis of Current Control Techniques for Four-Leg Full-Bridge Voltage Source Inverters Juan Rueda, Ernesto Pieruccini, María Mantilla, Member, IEEE and Johann Petit,
More informationElectromagnetic Compatibility of Train Detection Infrastructure with Rail Vehicles
Electromagnetic Compatibility of Train Detection Infrastructure with Rail Synopsis This document is a standard on immunity levels of infrastructure-based train detection systems, to provide electromagnetic
More informationP2 Power Solutions Pvt. Ltd.
P2 Power Solutions Pvt. Ltd. An ISO 9001:2008 Company Active Current Conditioners P2 Power Solutions Pvt. Ltd. P2 Power Solutions works to deliver Innovative Engineering solutions with specific focus on
More informationTransformer Protection
Transformer Protection Nature of transformer faults TXs, being static, totally enclosed and oil immersed develop faults only rarely but consequences large. Three main classes of faults. 1) Faults in Auxiliary
More informationGreenlining and Bluelining of Ergon Energy Substation Drawings
Greenlining and Bluelining of Ergon Energy Table of Contents Purpose and Scope... 1 Responsibilities... 1 Definitions, Abbreviations and Acronyms... 1 References... 1 General... 1 Requirements... 3 Testing
More informationQUESTIONNAIRE for Wind Farm Power Stations only
TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21
More informationTransformers TRANS FORM ERS
Transformers TRANS FORM ERS Meiden Transformers are standard design, standard quality. Our Factories on world-wide supply chain Since its founding in 1897 Meidensha Corporation has not only built up a
More informationModeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning
Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning M. PSALIDAS, D. AGORIS, E. PYRGIOTI, C. KARAGIAΝNOPOULOS High Voltage Laboratory,
More informationCapacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices
Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices M. Sanaye-Pasand, R. Aghazadeh Applied Electromagnetics Research Excellence Center, Electrical & Computer Engineering
More informationAC INTERFERENCE OF TRANSMISSION LINES ON RAILWAYS: INFLUENCE OF TRACK-CONNECTED EQUIPMENT I. ABSTRACT
AC INTERFERENCE OF TRANSMISSION LINES ON RAILWAYS: INFLUENCE OF TRACK-CONNECTED EQUIPMENT R. D. Southey, J. Liu, F. P. Dawalibi, Y. Li Safe Engineering Services & technologies ltd. 1544 Viel, Montreal,
More informationConsidering Power Losses of Switching Devices in Transient Simulations through a Simplified Circuit Model
Considering Power Losses of Switching Devices in Transient Simulations through a Simplified Circuit Model Juan M. Mauricio, José M. Maza-Ortega, Antonio Gómez-Expósito Abstract A simple model is proposed
More informationINVESTIGATION ON THE TECHNOLOGIES FOR DEFECT LOCALIZATION AND CHARACTERIZATION ON MEDIUM VOLTAGE UNDERGROUND LINES
INVESTIGATION ON THE TECHNOLOGIES FOR DEFECT LOCALIZATION AND CHARACTERIZATION ON MEDIUM VOLTAGE UNDERGROUND LINES Gonzalo MAIZ, Iberdrola Distribución, (Spain), gmaiz@iberdrola.es Armando RODRIGO, Instituto
More informationp. 1 p. 6 p. 22 p. 46 p. 58
Comparing power factor and displacement power factor corrections based on IEEE Std. 18-2002 Harmonic problems produced from the use of adjustable speed drives in industrial plants : case study Theory for
More informationPD132 Loop Detector Specification
PD132 Loop Detector Specification (Version 1.00) Content 1. Application... 3 2. Technical Data... 3 3 Wiring Diagram... 3 4 Use and operational... 4 4.1 Frequency adjust... 4 4.2 Sensitivity adjust...
More informationThe Advantages and Application of Three Winding Transformers
The Advantages and Application of Three Winding Transformers MSc, CEng, FIEE, FIMechE, FIPENZ Principal, Sinclair Knight Merz Abstract Although seldom used in Australia and New Zealand, three winding transformers
More informationESB National Grid Transmission Planning Criteria
ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and
More informationProtection against unacceptable voltages in railway systems
Bernhard Richter*, Alexander Bernhard*, Nick Milutinovic** SUMMERY Based on the system voltages for AC and DC railway systems the required voltage ratings for modern gapless MO surge arresters are given.
More informationJRC MODIFIED VOLTAGE CONTROL LAW FOR LOW FREQUENCY RAILWAY POWER SYSTEMS
Proceedings of the 27 IEEE/ASME Joint Rail Conference JRC27 April 4-7, 27, Philadelphia, PA, USA JRC27-2224 MODIFIED VOLTAGE CONTROL LAW FOR LOW FREQUENCY RAILWAY POWER SYSTEMS John Laury Electric Power
More informationDigital Fault Recorder Deployment at HVDC Converter Stations
Digital Fault Recorder Deployment at HVDC Converter Stations On line continuous monitoring at HVDC Converter Stations is an important asset in determining overall system performance and an essential diagnostic
More informationECP HV INSULATION TESTING
Document Number: ECP 11-0006 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE EPN, LPN, SPN ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing
More informationAGN 022 Conditions for Parallel Operation
Application Guidance Notes: Technical Information from Cummins Generator Technologies AGN 022 Conditions for Parallel Operation SYNCHRONISATION The parallel operation of Generating Sets is common, to share
More informationDIRECTIONAL PROTECTION
UNIVERSITY OF LJUBLJANA FACULTY OF ELECTRICAL ENGINEERING DIRECTIONAL PROTECTION Seminar work in the course Distribution and industrial networks Mentor: Prof. Grega Bizjak Author: Amar Zejnilović Ljubljana,
More informationMEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN
MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN Eugenio PEREA*, Eduardo ZABALA*, J. Emilio RODRÍGUEZ*, Asier GIL DE MURO*, Hugo GAGO * * * Fundación LABEIN,
More informationReduction of Peak Input Currents during Charge Pump Boosting in Monolithically Integrated High-Voltage Generators
Reduction of Peak Input Currents during Charge Pump Boosting in Monolithically Integrated High-Voltage Generators Jan Doutreloigne Abstract This paper describes two methods for the reduction of the peak
More informationRailway Wheels Flat Detector Using Doppler Effect
Available online at www.sciencedirect.com Physics Physics Procedia 3 (2010) 00 (2009) 811 817 000 000 www.elsevier.com/locate/procedia International Congress on Ultrasonics, Universidad de Santiago de
More informationFeeder Protection Challenges with High Penetration of Inverter Based Distributed Generation
Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Harag Margossian 1, Florin Capitanescu 2, Juergen Sachau 3 Interdisciplinary Centre for Security, Reliability
More informationFast Front Transients in Transformer Connected to Gas Insulated Substations: (White+Black) Box Models and TDSF Monitoring
Fast Front Transients in Transformer Connected to Gas Insulated Substations: (White+Black) Box Models and TDSF Monitoring Luis ROUCO 1, Xose M. LÓPEZ-FERNÁNDEZ 2, 3, Casimiro ALVAREZ-MARIÑO 3 and Hugo
More informationSEMICONDUCTOR LASER PROPERTY TO FORM INTERRUPTING RADIATION AT THE MOMENT OF SWITCHING ON AND SWITCHING OFF OF THE PUMPING ELECTRIC CURRENT
SEMICONDUCTOR LASER PROPERTY TO FORM INTERRUPTING RADIATION AT THE MOMENT OF SWITCHING ON AND SWITCHING OFF OF THE PUMPING ELECTRIC CURRENT Churakov Valery Lvovich IZHMASH, Chair of Theoretical Research
More informationInfluence of Wind Generators in Voltage Dips
Influence of Wind Generators in Voltage Dips E. Belenguer, N. Aparicio, J.L. Gandía, S. Añó 2 Department of Industrial Engineering and Design Universitat Jaume I Campus de Riu Sec, E-27 Castelló (Spain)
More informationAlternative Coupling Method for Immunity Testing of Power Grid Protection Equipment
Alternative Coupling Method for Immunity Testing of Power Grid Protection Equipment Christian Suttner*, Stefan Tenbohlen Institute of Power Transmission and High Voltage Technology (IEH), University of
More informationPSV3St _ Phase-Sequence Voltage Protection Stage1 (PSV3St1) Stage2 (PSV3St2)
1MRS752324-MUM Issued: 3/2000 Version: D/23.06.2005 Data subject to change without notice PSV3St _ Phase-Sequence Voltage Protection Stage1 (PSV3St1) Stage2 (PSV3St2) Contents 1. Introduction... 2 1.1
More informationELF ELECTRIC AND MAGNETIC FIELDS MEASUREMENTS IN GREECE
ELF ELECTRIC AND MAGNETIC FIELDS MEASUREMENTS IN GREECE E. Karabetsos, G. Filippopoulos, D. Koutounidis CH. Govari, N. Skamnakis Non ionizing radiation office, Greek atomic energy commission, P. O. BOX
More informationHARMONIC DISTURBANCE COMPENSATING AND MONITORING IN ELECTRIC TRACTION SYSTEM
HARMONIC DISTURBANCE COMPENSATING AND MONITORING IN ELECTRIC TRACTION SYSTEM A. J. Ghanizadeh, S. H. Hosseinian, G. B. Gharehpetian Electrical Engineering Department, Amirkabir University of Technology,
More informationValidation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit
Validation of a Power Transformer Model for Ferroresonance with System Tests on a 4 kv Circuit Charalambos Charalambous 1, Z.D. Wang 1, Jie Li 1, Mark Osborne 2 and Paul Jarman 2 Abstract-- National Grid
More informationSERVICING & METERING SERVICING AND METERING SECTION 5 SEC5:
SECTION SERVICING AND METERING SECTION 1. SERVICING.... NST IMPEDANCE TESTING.... METERING... General Requirements.... CT METERING... 8 CT Metering General Requirements... 8 Existing Installation Alterations
More informationVoltage Sags Evaluating Methods, Power Quality and Voltage Sags Assessment regarding Voltage Dip Immunity of Equipment
s Evaluating Methods, Power Quality and s Assessment regarding Voltage Dip Immunity of Equipment ANTON BELÁŇ, MARTIN LIŠKA, BORIS CINTULA, ŽANETA ELESCHOVÁ Institute of Power and Applied Electrical Engineering
More informationERTMS/ETCS UNIT INTERFACES BETWEEN CONTROL-COMMAND AND SIGNALLING TRACKSIDE AND OTHER SUBSYSTEMS
EUROPEAN RAILWAY AGENCY ERTMS Unit ERTMS/ETCS UNIT Reference: ERA/ERTMS/033281 Document type: Version : 4.0 T Date : 20/09/2018 Edited by Quality review Approved by Name Martin Schroeder Benoit Debuschere
More informationINTERACTION BETWEEN THE DISTRIBUTION NETWORK AND THE GENERATION DISTRIBUTED IN THE CASE OF SHORT-CIRCUIT IN THE MV NETWORK.
INTEACTION BETWEEN THE DISTIBUTION NETWOK AND THE ENEATION DISTIBUTED IN THE CASE OF SHOT-CICUIT IN THE MV NETWOK. Daniel CASTO, Eduardo BALMACEDA Energía San Juan S. A. - Argentina dcastro@energiasanjuan.com.ar;
More informationSYNCHRONISING AND VOLTAGE SELECTION
SYNCHRONISING AND VOLTAGE SELECTION This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for any
More informationSingle Earthed Neutral and Multi Earthed Neutral. Single Earthed Neutral and Multi Earthed Neutral: Multi Grounded Neutral System (MEN):
Single Earthed Neutral and Multi Earthed Neutral. SEPTEMBER 6, 2011 5 COMMENTS Single Earthed Neutral and Multi Earthed Neutral: In Distribution System Three Phase load is unbalance and non linear so The
More informationFACTORY AND FIELD VERIFICATION TESTS OF CONTROLLED SWITCHING SYSTEM
FACTORY AND FIELD VERIFICATION TESTS OF CONTROLLED SWITCHING SYSTEM by H. Ito, H. Tsutada, H. Kohyama, H. Yamamoto Mitsubishi Electric Corp. H. Wilson, S. Billings Mitsubishi Electric Power Products, Inc.
More informationSingle Line Diagram of Substations
Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission lines are
More informationModern Concepts of Energy Control Technology through VVVF Propulsion Drive
Modern Concepts of Energy Control Technology through VVVF Propulsion Drive Satoru OZAKI, Fuji Electric Systems Co., Ltd. Ken-ichi URUGA, Toyo Denki Seizo K.K. Dr. D.P. Bhatt, Autometers Alliance Ltd ABSTRACT
More information