INTERACTION BETWEEN THE DISTRIBUTION NETWORK AND THE GENERATION DISTRIBUTED IN THE CASE OF SHORT-CIRCUIT IN THE MV NETWORK.

Size: px
Start display at page:

Download "INTERACTION BETWEEN THE DISTRIBUTION NETWORK AND THE GENERATION DISTRIBUTED IN THE CASE OF SHORT-CIRCUIT IN THE MV NETWORK."

Transcription

1 INTEACTION BETWEEN THE DISTIBUTION NETWOK AND THE ENEATION DISTIBUTED IN THE CASE OF SHOT-CICUIT IN THE MV NETWOK. Daniel CASTO, Eduardo BALMACEDA Energía San Juan S. A. - Argentina dcastro@energiasanjuan.com.ar; ebalmaceda@energiasanjuan.com.ar, INTODUCTION The main purpose of an electric network is to transfer electricity from the electric power generators to the clients. The distribution networks make the connection to the final clients and must satisfy the electricity service with an agreed quality level on watch in the applicable norm. In the case of the province of San Juan Argentina, it is Energía San Juan S.A. The combined development of the generation of the heat and of energy and the interest for the renewable energies (biomass, aeolian, solar, etc.) they can lead in the present to a growth of the supply of energy in small modules. As these generators can be connected in any point of the network, we can say that this is the evolution of the network with the introduction of the dispersed sources of generation were 2500 KW. However, the maximum power that can contribute the generator is around 350 kw. The geographic location of the feeder is shown in the Figure Nº1. Estación Transformadora enerador Also, the introduction of a generator in any point of the network can cause some complications with the coordination of the protections. This means that when the fault appears, now exits several ways of contribution from current to the place of the fault, causing generally problems between the protection elements that are not directional. Figure Nº 1 I1 Sistema Equivalenrte The present work states a strategy to achieve the coordination of protections in the MV of 13,2 kv, where it was connected a synchronous generator with a hydraulic turbine that generates approximately 350 kw (the considered load of the distributor is of around 2500 kw). This generator belongs to a private company and this located in a point near the main source of the feeder. 2. DESCIPTION AND MODELLIN OF THE NETWOK The present study was make for a substation transformation from 33 to 13,2 kv call Parque Industrial. It located in the industrial area of San Juan's city. It includes circuit breakers, two transformer of 10 MVA (T1) and four feeders with different characteristic as for the consumption type and longitude. The synchronous generator is connected from the feeder called Bonduel Sur. It is installed on a watering canal located to 1.6 kilometers of the substation. The feeder has 3000 residential clients and it has a global length of 5,5 kilometers. The maximum load of the feeder in the year Subestación MT/BT econectador Fusible MT Figure Nº 2 T1 I2 ET P. Industrial I3 I4 I5 Distribuidor Bonduel Sur I6 Central El Candil In the case of the transformer (T1) of the substation of power, it protected with overcurrent time protection relay (in the primary and secondary side). Also, the feeders are protected with overcurrent time protection relay in the

2 beginning of the line. Then, there are recloser in the middle of the line and fuses in their derivations. The structure of the system is shown in the Figure Nº DESCIPTION OF THE HYDAULIC POWE STATION The next graph shows the power injected by the generator (since the first days of October of the year 2003). In this case, we can observe that the injected maximum power reached 320 kw, and then in the months of winter its contribution decays until stopping to work. This situation is presented in times of cleaning of the watering canal. The synchronous generator is hydraulic and it is installed on a watering canal located to 1.6 kilometers of the substation transformer Parque Industrial. This power substation is called El Candil and it is connected to the network through two transformers ( and ), to convert the voltage to the rest of the system. Next, is given the detail of data about these transformers and generator. The synchronous generator: Demanda Inyectada en kw por la Central El Candil Power = 450 kw Voltage = 3200 V Connection group: /09/03 17/09/03 26/09/03 4/10/03 13/10/03 21/10/03 30/10/03 7/11/03 16/11/03 24/11/03 3/12/03 11/12/03 20/12/03 28/12/03 5/01/04 14/01/04 22/01/04 31/01/04 8/02/04 17/02/04 25/02/04 6/05/04 14/05/04 23/05/04 31/05/04 9/06/04 17/06/04 26/06/04 4/07/04 13/07/04 21/07/04 30/07/04 7/08/04 16/08/04 24/08/04 1/09/04 10/09/04 18/09/04 27/09/04 5/10/04 Transforme 2: Power: 500 kva Voltage = 3,3/0,396 kv UCC = 5,1 % Connection group: / Transforme 3 Power: 700 kva Voltage = 0,380/13,86 kv UCC = 5,1 % Connection group: The structure of the power station El Candil is shown in the Figure Nº 3. CENTAL EL CANDIL 3200 V Figure Nº4: Power injected by the generator. 3. STUDY OF SHOT CICUIT To establish the strategy of coordination of the protection, we make the studies of short circuit currents in the mentioned electric system. For this, the sequence circuits were analyzed and the value of short circuit current was calculated for different kind of faults in different points of the network. With these data, the maximum and minima values were obtained in the network. Maximum short circuit current: For the case that contribute to a fault (three phases) the system and the generator. Minimum short circuit current: In case of fault (one phase) with impedance of ground through a 40 Ohms impedance. 3.1 CICUITS OF SEQUENCE. Transformador 0,5 MVA Positive Sequence Circuit. 380 V Transformador 0,7 MVA V V ELE de Sobrecorriente Figure Nº 3 Figure Nº 5

3 3.1.2 Negative Sequence Circuit. Figure Nº Zero Sequence Circuit. Figure Nº 7 4. STATEY OF POTECTION. The transformer of the power substation of 33/13,2 kv is protected against short circuit currents with overcurrent time protection relay (in the primary and secondary of the transformer). The normalised curves of adjustment are selected in function of the nominal current of the transformer. In the case of the feeders of 13,2 kv, they are protected by overcurrent time protection relay in the beginning of the line. The normalised curve of adjustment is selected in function of the nominal current according to the main section of the feeder. Also, each relay incorporates the function for instantaneous reclosing operation for different fault (one phase to ground or three phases). The main function, is the possibility to save the performance of fuses for transitory faults. Also, some feeders have reclosers due to the great problem of branches on the lines that we have in our city. 5. STUDY OF FAULTS IN DIFFEENT POINTS OF THE ELECTIC SYSTEM. We are going to analyse the most critical cases to establish and verify the selectivity of the protection. The graphic of the system study it shows in The Figure Nº 8, with the distribution of the short circuit currents for each fault in different points of the network. coordination between the switches of the feeder Bonduel Sur and the generator is not required. In that way, normalised temporised curves are selected to guarantee coordination between the switches (I5), (I2) and (I1). Also, as all the feeders have enabled the function of an instantaneous reclosing point for fault to one phase - earth or fault between phases, the relay of the generator is adjusted to send to the switch (I6) an instantaneous shot when its take a value above the threshold of overcurrent. This makes that every time that a fault appears in the point (1), they open in combined and instantaneous form the switches (I5) and (I6). After one second, the relay of the feeder sends a reclosing and it closes the switch (I5), without the contribution of the generator. In case of permanent fault, the feeder s relay sends a signal to open the switch (I5) according to the temporized curve. The Figure Nº 9, shows the adjustment of protection. It is necessary to clarify that the curves of the switches (I1) and (I2) are indexed at the level of 13,2 kv. Figures Nº 8 I Subestación MT/BT econectador Electrónico 5 T1 I1 Sistema Equivalenrte ET P. Industrial I3 I4 I5 4 I2 3 Fusibles MT 1 2 Distribuidor BonduelSur I6 CentralEl Candil 5.1 Fault in Point (1) In this case, the contribution to the faults is produced by the system and the generator. This makes that the value of the short circuit current is high reaching values of approximately 3,5 ka. Since the main function is highly commercial, we don t need that the generator operated in island. So the Fusible Figures Nº 9 Curva temp. I1 Curva temp. I2 Curva temp. I5 I6, I5 Instantánea t

4 5.2 Fault in Point (2) In this case, the short circuit current in this fault point is smaller than in point (1). According to the study, the maximum value of short circuit current (for faults between phases) is approximately (1,5 KA). Keeping in mind the strategy presented in the previous point (1) we maintain the coordination of the protection. Therefore, in the moment to appear a fault in the point (2), the instantaneous opening of the switches (I5) and (I6) take place. Then, the switch (I5) send the corresponding reclosing, having already disappeared the contribution of the generator. In case of permanent fault, the fuse of MV line burns. 5.3 Fault in Point (3) In this case, the contribution to the short circuit current in the point (3), is produced by the system and the generator. It is higher than the short circuit current in the previous points (1) and (2). According to the study, the short circuit current of three phase would be of approximately 4,5 ka. This is because the contribution of the system is higher than the contribution of the generator through the feeder Bonduel Sur. Keeping in mind the strategy presented in the previous points (1) and (2), we maintain the coordination of the protection. In this case, a fault in point (3) will cause the instantaneous opening of the switch (I6) or will open the switches (I5) and (I6), depending of the value of short circuit current. In that way, it will eliminate the contribution of the fault through the feeder Bonduel Sur. Then, the fault causes the opening of the switch (I2). After that, it is eliminated. It is important to mention that the instantaneous opening of the feeder's switch (I5) and of the generator (I6) reduce the possibility that the generator is works in island. This operation is not convenient because the minimum load of the feeder is bigger than the power able to inject the generator. a blockade sign to the feeder's relay Bonduel Sur in order to disable the instantaneous function for earth or between phases faults. 5.5 Fault in Point (5). In this case, the value of short circuit current contributed by the generator can be so small that it doesn't produce the open of the switches of the Bonduel Sur and generator. When we come closer to the power station, the short circuit current will be higher and the effect will be similar to the descriptions for point (4). It is important to mention that the are two recloser installed in series in this feeder. They have adjusted with two instantaneous tripping to stops the temporary faults and two time current curve timing to stop the permanent faults. In case of fault in the point (5), the recloser 2, send an instantaneous trip to stop the temporally faults. After two seconds, it sends a second instantaneous trip and it closes again. In the case of permanent fault, the fuse of the MV line eliminate it. 5.6 Adjustment of Protection System of 33/13,2 kv of the Power Station Parque Industrial. The Figure Nº 10, shows the real adjustment implemented in the studied system. This includes the temporized curves of the relay that protect the transformer of the power subtation and each feeder. Also, the curve of the fuse of MV (40 A) and the instantaneous and temporized adjustment of the two reclosers connected in series in one of the feeder. 5.4 Fault in Point (4) All the feeders have similar adjustments. When a fault appears in the point (4), the contribution of short circuit current takes place from the system and from the generator. Depending were the fault is located, the contribution of the generator can be very small. This fault produced the instantaneous opening of the switch (I3) or switches (I5) and (I6), depending of short circuit current. Then, the reclosing corresponding of the switch (I3) takes place without the contribution of the generator. In case of permanent fault, the switch (I3) will open. This situation causes an undesirable opening of the switches (I5) and (I6). To improve this situation, a system of blockades was implemented to cancel the instantaneous opening of the switch (I5). This way, when fault appears in anyone of the feeder (I3) or (I4), the protection relays sends Figure Nº10

5 6. CONCLUSIONS. The strategy of protection presented in this work allows to maintain the selectivity between the switches for almost all of the faults that can be presented in the studied system. Also, it maintained the instantaneous reclosing function for all of the feeders to different faults in order to save fuses in the network of MT for transitory fault. The only disadvantage in this strategy is when fault in point (3) appears, because it can cause not wanted openings of the switch of the generator. This situation can improve if we decided to adjust the curves of the protection relay of the feeder similar to the generator; for example, inverse time normalised curves. In this case, the fault in the point (3) will make an instantaneous reclosing in the feeder and then, in case of permanent fault, it will open definitive without cause the opens of the generator's switch. This is due to the difference of the contributions of short circuit current that will see each relay. In our case we decided to adjust the relay that protects to the generator with instantaneous trips for fault to one phase - earth or fault between phases. It was determined because in case of adjusting the relay with temporised curves, it will take a long time to open the switch. In that case, it will force to the generator to operate in island in a short time. Also, for any kind of fault, it could cause bigger mechanical demand in the generator and non-balance of voltage in the network of the system. It would affect the quality of service to the customers. We have to remember that the Bonduel Sur's minimum load is bigger than the capacity of power that can inject the generator. The study presented in this work allows you to achieve a good coordination of the protection to minimum cost. 7. EFEENCES 1] CIED 17ª International Conference on Electricity Distribution Barcelona [2] E. Orduña, Protección en Sistemas Eléctricos de Potencia Curso ama Estudiantil IEEE, UNSJ. San Juan Argentina, Octubre [3] SIEMENS Manual del elé de Sobrecorriente 7SJ

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS Juan Manuel Gers, PhD Protection coordination principles Relay coordination is the process of selecting settings that will assure that the relays

More information

Adaptive Relaying of Radial Distribution system with Distributed Generation

Adaptive Relaying of Radial Distribution system with Distributed Generation Adaptive Relaying of Radial Distribution system with Distributed Generation K.Vijetha M,Tech (Power Systems Engineering) National Institute of Technology-Warangal Warangal, INDIA. Email: vijetha258@gmail.com

More information

Distance Protection for Distribution Feeders. Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng.

Distance Protection for Distribution Feeders. Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng. Distance Protection for Distribution Feeders Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng. Why use distance protection for distribution feeders? Distance protection is mainly used for protecting

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS Juan Manuel Gers, PhD Example - Single Line Example 1 - Data Calculate the following: 1. The three phase short circuit levels on busbars

More information

Connection Impact Assessment Application

Connection Impact Assessment Application Connection Impact Assessment Application This form is for generators applying for Connection Impact Assessment (CIA) and for generators with a project size >10 kw. Please return the completed form by email,

More information

ARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS

ARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS The Electrical Power Engineers Qual-Tech Engineers, Inc. 201 Johnson Road Building #1 Suite 203 Houston, PA 15342-1300 Phone 724-873-9275 Fax 724-873-8910 www.qualtecheng.com ARC FLASH PPE GUIDELINES FOR

More information

Reducing the Effects of Short Circuit Faults on Sensitive Loads in Distribution Systems

Reducing the Effects of Short Circuit Faults on Sensitive Loads in Distribution Systems Reducing the Effects of Short Circuit Faults on Sensitive Loads in Distribution Systems Alexander Apostolov AREVA T&D Automation I. INTRODUCTION The electric utilities industry is going through significant

More information

POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE. Professor Akhtar Kalam Victoria University

POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE. Professor Akhtar Kalam Victoria University POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE Professor Akhtar Kalam Victoria University The Problem Calculate & sketch the ZPS, NPS & PPS impedance networks. Calculate feeder faults. Calculate

More information

NEW DESIGN OF GROUND FAULT PROTECTION

NEW DESIGN OF GROUND FAULT PROTECTION NEW DESIGN OF GROUND FAULT PROTECTION J. Blumschein*, Y. Yelgin* *SIEMENS AG, Germany, email: joerg.blumschein@siemens.com Keywords: Ground fault protection, directional element, faulted phase selection

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

Babak Enayati National Grid Thursday, April 17

Babak Enayati National Grid Thursday, April 17 2014 IEEE PES Transmission & Distribution Conference & Exposition Impacts of the Distribution System Renewable Energy Resources on the Power System Protection Babak Enayati National Grid Thursday, April

More information

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS 1 B. RAMESH, 2 K. P. VITTAL Student Member, IEEE, EEE Department, National Institute of Technology Karnataka,

More information

DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS

DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS Abdelrahman AKILA Ahmed HELAL Hussien ELDESOUKI SDEDCO Egypt AASTMT Egypt AASTMT Egypt Abdurrahman.akela@gmail.com ahmedanas@aast.edu hdesouki@aast.edu

More information

Relay Coordination in the Protection of Radially- Connected Power System Network

Relay Coordination in the Protection of Radially- Connected Power System Network Relay Coordination in the Protection of Radially- Connected Power System Network Zankhana Shah Electrical Department, Kalol institute of research centre, Ahemedabad-Mehshana Highway, kalol, India 1 zankhu.shah@gmail.com

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

BED INTERCONNECTION TECHNICAL REQUIREMENTS

BED INTERCONNECTION TECHNICAL REQUIREMENTS BED INTERCONNECTION TECHNICAL REQUIREMENTS By Enis Šehović, P.E. 2/11/2016 Revised 5/19/2016 A. TABLE OF CONTENTS B. Interconnection Processes... 2 1. Vermont Public Service Board (PSB) Rule 5.500... 2

More information

Time-current Coordination

Time-current Coordination 269 5.2.3.1 Time-current Coordination Time that is controlled by current magnitude permits discriminating faults at one location from another. There are three variables available to discriminate faults,

More information

Table of Contents. Introduction... 1

Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...

More information

Connection Impact Assessment Application Form

Connection Impact Assessment Application Form Connection Impact Assessment Application Form This Application Form is for Generators applying for a Connection Impact Assessment (CIA). In certain circumstances, London Hydro may require additional information

More information

A New Adaptive Method for Distribution System Protection Considering Distributed Generation Units Using Simulated Annealing Method

A New Adaptive Method for Distribution System Protection Considering Distributed Generation Units Using Simulated Annealing Method A New Adaptive Method for Distribution System Protection Considering Distributed Generation Units Using Simulated Annealing Method 3 Hamidreza Akhondi and Mostafa Saifali Sadra Institute of Higher Education

More information

T 1000 PLUS Secondary Injection Relay Test Set

T 1000 PLUS Secondary Injection Relay Test Set Secondary Injection Relay Test Set Designed for testing relays and transducers Microprocessor controlled With phase angle shifter Frequency generator Test results and settings are saved into local memory

More information

Protecting Feeders With Distributed Resource Scott Elling HDR Inc HDR, all rights reserved.

Protecting Feeders With Distributed Resource Scott Elling HDR Inc HDR, all rights reserved. Protecting Feeders With Distributed Resource Scott Elling HDR Inc. 2015 HDR, all rights reserved. Background Several Hundred Mega Watts of distributed PV Distribution Grid is no longer radial Protection

More information

T 1000 PLUS. Secondary Injection Relay Test Set. Designed for testing relays and transducers

T 1000 PLUS. Secondary Injection Relay Test Set. Designed for testing relays and transducers Secondary Injection Relay Test Set Designed for testing relays and transducers Microprocessor controlled With phase angle shifter Frequency generator High power outputs Large graphical display Compact

More information

THE NEED FOR ZERO SEQUENCE VOLTAGE PROTECTION IN MV NETWORKS WITH HIGH LEVELS OF DISTRIBUTED GENERATION

THE NEED FOR ZERO SEQUENCE VOLTAGE PROTECTION IN MV NETWORKS WITH HIGH LEVELS OF DISTRIBUTED GENERATION THE NEED FOR ZERO SEQUENCE VOLTAGE PROTECTION IN MV NETWORKS WITH HIGH LEVELS OF DISTRIBUTED GENERATION João MATEUS Andreia LEIRIA Marcelino FERREIRA AmberTREE Portugal LABELEC Portugal AmberTREE Portugal

More information

Impact Assessment Generator Form

Impact Assessment Generator Form Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project

More information

EE Lecture 14 Wed Feb 8, 2017

EE Lecture 14 Wed Feb 8, 2017 EE 5223 - Lecture 14 Wed Feb 8, 2017 Ongoing List of Topics: URL: http://www.ece.mtu.edu/faculty/bamork/ee5223/index.htm Labs - EE5224 Lab 3 - begins on Tues Feb 14th Term Project - details posted. Limit

More information

T/3000 T/3000. Substation Maintenance and Commissioning Test Equipment

T/3000 T/3000. Substation Maintenance and Commissioning Test Equipment T/3000 Substation Maintenance and Commissioning Test Equipment MULTI FUNCTION SYSTEM FOR TESTING SUBSTATION EQUIPMENT SUCH AS: CURRENT, VOLTAGE AND POWER TRANSFORMERS, ALL TYPE OF PROTECTION RELAYS, ENERGY

More information

Electrical Protection System Design and Operation

Electrical Protection System Design and Operation ELEC9713 Industrial and Commercial Power Systems Electrical Protection System Design and Operation 1. Function of Electrical Protection Systems The three primary aims of overcurrent electrical protection

More information

Simulation of voltage sag characteristics in power systems

Simulation of voltage sag characteristics in power systems Simulation of voltage sag characteristics in power systems Simulación de las características de los huecos de tensión en sistemas de potencia JOAQUÍN EDUARDO CAICEDO NAVARRO Student of electrical engineering

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

EMERGING distributed generation technologies make it

EMERGING distributed generation technologies make it IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 20, NO. 4, NOVEMBER 2005 1757 Fault Analysis on Distribution Feeders With Distributed Generators Mesut E. Baran, Member, IEEE, and Ismail El-Markaby, Student Member,

More information

N. TEST TEST DESCRIPTION

N. TEST TEST DESCRIPTION Multi function system for testing substation equipment such as: current, voltage and power transformers, all type of protection relays, energy meters and transducers Primary injection testing capabilities

More information

TABLE OF CONTENT

TABLE OF CONTENT Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES

More information

THE ROLE OF SYNCHROPHASORS IN THE INTEGRATION OF DISTRIBUTED ENERGY RESOURCES

THE ROLE OF SYNCHROPHASORS IN THE INTEGRATION OF DISTRIBUTED ENERGY RESOURCES THE OLE OF SYNCHOPHASOS IN THE INTEGATION OF DISTIBUTED ENEGY ESOUCES Alexander APOSTOLOV OMICON electronics - USA alex.apostolov@omicronusa.com ABSTACT The introduction of M and P class Synchrophasors

More information

Overcurrent and Overload Protection of AC Machines and Power Transformers

Overcurrent and Overload Protection of AC Machines and Power Transformers Exercise 2 Overcurrent and Overload Protection of AC Machines and Power Transformers EXERCISE OBJECTIVE When you have completed this exercise, you will understand the relationship between the power rating

More information

INSTRUCTIONS FOR THE COMMISSIONING AND MAINTENANCE OF DIGITAL GENERATOR PROTECTION 3 I - PRINCIPLES AND APPLICATIONS 4 on 5 6 7 Figure 5 - Inverse time curve (N1) 8 9 1 0 1 1 1 2 1 3 All relays are delivered

More information

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements

More information

Phase and neutral overcurrent protection

Phase and neutral overcurrent protection Phase and neutral overcurrent protection Page 1 ssued June 1999 Changed since July 1998 Data subject to change without notice (SE970165) Features Two-phase or three-phase time-overcurrent and earth fault

More information

Harmonic Distortion Levels Measured at The Enmax Substations

Harmonic Distortion Levels Measured at The Enmax Substations Harmonic Distortion Levels Measured at The Enmax Substations This report documents the findings on the harmonic voltage and current levels at ENMAX Power Corporation (EPC) substations. ENMAX is concerned

More information

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc. 770 565-1556 John@L-3.com 1 Protection Fundamentals By John Levine 2 Introductions Tools Outline Enervista Launchpad

More information

Unit 3 Magnetism...21 Introduction The Natural Magnet Magnetic Polarities Magnetic Compass...21

Unit 3 Magnetism...21 Introduction The Natural Magnet Magnetic Polarities Magnetic Compass...21 Chapter 1 Electrical Fundamentals Unit 1 Matter...3 Introduction...3 1.1 Matter...3 1.2 Atomic Theory...3 1.3 Law of Electrical Charges...4 1.4 Law of Atomic Charges...4 Negative Atomic Charge...4 Positive

More information

MV network design & devices selection EXERCISE BOOK

MV network design & devices selection EXERCISE BOOK MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

Preface...x Chapter 1 Electrical Fundamentals

Preface...x Chapter 1 Electrical Fundamentals Preface...x Chapter 1 Electrical Fundamentals Unit 1 Matter...3 Introduction...3 1.1 Matter...3 1.2 Atomic Theory...3 1.3 Law of Electrical Charges...4 1.4 Law of Atomic Charges...5 Negative Atomic Charge...5

More information

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 % BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and

More information

T 1000 PLUS. Secondary Injection Relay Test Set. Designed for testing relays and transducers

T 1000 PLUS. Secondary Injection Relay Test Set. Designed for testing relays and transducers Secondary Injection Relay Test Set Designed for testing relays and transducers Microprocessor controlled With phase angle shifter Frequency generator Test results and settings are saved into local memory

More information

Protective Relaying for DER

Protective Relaying for DER Protective Relaying for DER Rogerio Scharlach Schweitzer Engineering Laboratories, Inc. Basking Ridge, NJ Overview IEEE 1547 general requirements to be met at point of common coupling (PCC) Distributed

More information

QUESTIONNAIRE for Wind Farm Power Stations only

QUESTIONNAIRE for Wind Farm Power Stations only TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21

More information

Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering

Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering Expo - Nov. 3, 2014 Index Normal Distribution System

More information

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy Interconnection Coordinator 1945

More information

Distribution Feeder. Nazar Dhahir Sr. Transmission Engineer Tucson Electric Power Co. RMEL Distribution Conference March 11, 2010

Distribution Feeder. Nazar Dhahir Sr. Transmission Engineer Tucson Electric Power Co. RMEL Distribution Conference March 11, 2010 Distribution Feeder utomation ti Nazar Dhahir Sr. Transmission Engineer Tucson Electric Power Co. RMEL Distribution Conference March 11, 2010 IntelliTEM Team synchronization members share data Switches

More information

TD 1000 PLUS. Secondary Injection Relay Test Set. Designed for testing relays and transducers

TD 1000 PLUS. Secondary Injection Relay Test Set. Designed for testing relays and transducers Secondary Injection Relay Test Set Designed for testing relays and transducers Two current outputs to test differential relays Convertible current and voltage generator With phase angle shifter Frequency

More information

ECE 528 Understanding Power Quality

ECE 528 Understanding Power Quality ECE 528 Understanding Power Quality http://www.ece.uidaho.edu/ee/power/ece528/ Paul Ortmann portmann@uidaho.edu 208-733-7972 (voice) Lecture 22 1 Today Homework 5 questions Homework 6 discussion More on

More information

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length

More information

Power System Protection Manual

Power System Protection Manual Power System Protection Manual Note: This manual is in the formative stage. Not all the experiments have been covered here though they are operational in the laboratory. When the full manual is ready,

More information

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Harag Margossian 1, Florin Capitanescu 2, Juergen Sachau 3 Interdisciplinary Centre for Security, Reliability

More information

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP Kiran V. Natkar 1, Naveen Kumar 2 1 Student, M.E., Electrical Power System, MSS CET/ Dr. B.A.M. University, (India) 2 Electrical Power System,

More information

CHAPTER 5 POWER QUALITY IMPROVEMENT BY USING POWER ACTIVE FILTERS

CHAPTER 5 POWER QUALITY IMPROVEMENT BY USING POWER ACTIVE FILTERS 86 CHAPTER 5 POWER QUALITY IMPROVEMENT BY USING POWER ACTIVE FILTERS 5.1 POWER QUALITY IMPROVEMENT This chapter deals with the harmonic elimination in Power System by adopting various methods. Due to the

More information

INVESTIGATION INTO THE POWER QUALITY AND RELIABILITY OF SUPPLY IN THE INDUSTRIAL NETWORKS WITH DISTRIBUTED GENERATION

INVESTIGATION INTO THE POWER QUALITY AND RELIABILITY OF SUPPLY IN THE INDUSTRIAL NETWORKS WITH DISTRIBUTED GENERATION INVESTIGATION INTO THE POWER QUALITY AND RELIABILITY OF SUPPLY IN THE INDUSTRIAL NETWORKS WITH DISTRIBUTED GENERATION Rade M. CIRIC The Government of Autonomous Province of Vojvodina Secretariat for Science

More information

SECTION SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY

SECTION SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY SECTION 16075 - SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide a short-circuit, component protection, flash

More information

Protection of distributed generation interfaced networks

Protection of distributed generation interfaced networks Protection of distributed generation interfaced networks Manjula Dewadasa B.Sc (Hons) in Electrical Engineering A Thesis submitted in partial fulfilment of the requirements for the degree of Doctor of

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications

Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications FEATURED TOPIC Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications Sadayuki ISHIKURA*, Hideyuki NAKATANI, Junya TAKAGI, Tsutomu FUKADA, Shoji NISHIMURA

More information

Protection Scheme for Energy Storage Systems Operating in Island or Grid Connected Modes

Protection Scheme for Energy Storage Systems Operating in Island or Grid Connected Modes 24 th International Conference on Electricity Distribution Glasgow, 12-15 June 217 Paper 182 Protection Scheme for Energy Storage Systems Operating in Island or Grid Connected Modes Andre NEVES Bernardo

More information

Protection of Microgrids Using Differential Relays

Protection of Microgrids Using Differential Relays 1 Protection of Microgrids Using Differential Relays Manjula Dewadasa, Member, IEEE, Arindam Ghosh, Fellow, IEEE and Gerard Ledwich, Senior Member, IEEE Abstract A microgrid provides economical and reliable

More information

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION Andreas SUMPER sumper@citcea.upc.es Antoni SUDRIÀ sudria@citcea.upc.es Samuel GALCERAN galceran@citcea.upc.es Joan RULL rull@citcea.upc.es

More information

N. TEST TEST DESCRIPTION

N. TEST TEST DESCRIPTION Multi function system for testing substation equipment such as: current, voltage and power transformers, over-current protection relays, energy meters and transducers Primary injection testing capabilities

More information

Differential Protection for Microgrids with Embedded Generations

Differential Protection for Microgrids with Embedded Generations Differential Protection for Microgrids with Embedded Generations Paul Moroke Dept. of Electrical Engineering Tshwane University of Technology Pretoria, South Africa paulmoroke@gmail.com Abstract The permeation

More information

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination GSU Phase Overcurrent (51T), GSU Ground Overcurrent (51TG), and Breaker Failure (50BF) Protection NERC Protection Coordination Webinar Series

More information

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number:  Address: NORTH CAROLINA INTERCONNECTION REQUEST Utility: Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: An is considered complete when it provides all applicable and correct information

More information

U I. Time Overcurrent Relays. Basic equation. More or less approximates thermal fuse. » Allow coordination with fuses 9/24/2018 ECE525.

U I. Time Overcurrent Relays. Basic equation. More or less approximates thermal fuse. » Allow coordination with fuses 9/24/2018 ECE525. Time Overcurrent Relays More or less approximates thermal fuse» Allow coordination with fuses Direction of Current nduced Torque Restraining Spring Reset Position Time Dial Setting Disk Basic equation

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Coordination of protective relays in MV transformer stations using EasyPower Protector software

Coordination of protective relays in MV transformer stations using EasyPower Protector software Coordination of protective relays in MV transformer stations using EasyPower Protector software S. Nikolovski, Member, IEEE, I. Provci and D. Sljivac In this paper, the analysis of digital protection relays

More information

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS 101135-ELE-CMOS-E-2001 Electrical Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and has over 14 years hands-on experience, including 13 years working in operation, maintenance, construction

More information

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application General Application Information Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application Hydro One Remote Communities Inc. Lori.Rice@hydroone.com 1-807-474-2828 This Application

More information

, ,54 A

, ,54 A AEB5EN2 Ground fault Example Power line 22 kv has the partial capacity to the ground 4,3.0 F/km. Decide whether ground fault currents compensation is required if the line length is 30 km. We calculate

More information

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY WN U-60 Attachment C to Schedule 152, Page 1 SCHEDULE 152 APPLICATION FOR INTERCONNECTING A GENERATING FACILITY TIER 2 OR TIER 3 This Application is considered complete when it provides all applicable

More information

BUS2000 Busbar Differential Protection System

BUS2000 Busbar Differential Protection System BUS2000 Busbar Differential Protection System Differential overcurrent system with percentage restraint protection 1 Typical Busbar Arrangements Single Busbar Double Busbar with Coupler Breaker and a Half

More information

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 Prepared by System Planning Division Transmission Planning Department PJM 2016 Table of Contents Table of Contents Approval...6

More information

Anti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage

Anti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage POWERENG 2007, April 12-14, 2007, Setúbal, Portugal Anti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage Amin Helmzadeh, Javad Sadeh and Omid Alizadeh

More information

PROTECTION of electricity distribution networks

PROTECTION of electricity distribution networks PROTECTION of electricity distribution networks Juan M. Gers and Edward J. Holmes The Institution of Electrical Engineers Contents Preface and acknowledgments x 1 Introduction 1 1.1 Basic principles of

More information

Modelling Parameters. Affect on DER Impact Study Results

Modelling Parameters. Affect on DER Impact Study Results Modelling Parameters Affect on DER Impact Study Results Agenda Distributed Energy Resources (DER) Impact Studies DER Challenge Study Steps Lessons Learned Modeling Reverse Power Transformer Configuration

More information

CONTENTS. 1. Introduction Generating Stations 9 40

CONTENTS. 1. Introduction Generating Stations 9 40 CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific

More information

Solutions to Common Distribution Protection Challenges

Solutions to Common Distribution Protection Challenges Solutions to Common Distribution Protection Challenges Jeremy Blair, Greg Hataway, and Trevor Mattson Schweitzer Engineering Laboratories, Inc. Copyright SEL 2016 Common Distribution Protection Problems

More information

How to maximize reliability using an alternative distribution system for critical loads

How to maximize reliability using an alternative distribution system for critical loads White Paper WP024001EN How to maximize reliability using an alternative distribution system for critical loads Executive summary The electric power industry has several different distribution topologies

More information

Form B. Connection Impact Assessment Application Form Distribution System

Form B. Connection Impact Assessment Application Form Distribution System Form B Connection Impact Assessment Application Form Distribution System This Application Form is for Generators applying for Connection Impact Assessment ( CIA ). It is important that the Generator provides

More information

Voltage Sag Mitigation by Neutral Grounding Resistance Application in Distribution System of Provincial Electricity Authority

Voltage Sag Mitigation by Neutral Grounding Resistance Application in Distribution System of Provincial Electricity Authority Voltage Sag Mitigation by Neutral Grounding Resistance Application in Distribution System of Provincial Electricity Authority S. Songsiri * and S. Sirisumrannukul Abstract This paper presents an application

More information

An Example Distance Protection Application with Complicating Factors.

An Example Distance Protection Application with Complicating Factors. An Example Distance Protection Application with Complicating Factors. Presented to Western Protective Relay Conference 29 Spoane, Washington, USA Prepared by Yofre Jacome, COES PERU Charles F Henville,

More information

E N G I N E E R I N G M A N U A L

E N G I N E E R I N G M A N U A L 1 1 1.0 PURPOSE The purpose of this document is to define policy and provide engineering guidelines for the AP operating companies (Monongahela Power Company, The Potomac Edison Company, and West Penn

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

SAFETY ASPECTS AND NOVEL TECHNICAL SOLUTIONS FOR EARTH FAULT MANAGEMENT IN MV ELECTRICITY DISTRIBUTION NETWORKS

SAFETY ASPECTS AND NOVEL TECHNICAL SOLUTIONS FOR EARTH FAULT MANAGEMENT IN MV ELECTRICITY DISTRIBUTION NETWORKS SAFETY ASPECTS AND NOVEL TECHNICAL SOLUTIONS FOR EARTH FAULT MANAGEMENT IN MV ELECTRICITY DISTRIBUTION NETWORKS A. Nikander*, P. Järventausta* *Tampere University of Technology, Finland, ari.nikander@tut.fi,

More information

Orbital GFI Inverter Series

Orbital GFI Inverter Series Orbital GFI Inverter Series Datasheet Key Features One, split or three phases and up to 25 kva Superior efficiency of 95% CAN Bus control and DAQ Power quality and EMC compliance in accordance with European

More information

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D Electricity Ten Year Statement November 2017 01 Electricity Ten Year Statement November 2017 001 Appendix D 1 Short-circuit currents 02 2 Short-circuit current terminology 04 3 Data requirements 07 4 Fault

More information

PD300. Transformer, generator and motor protection Data sheet

PD300. Transformer, generator and motor protection Data sheet PD300 Transformer, generator and motor protection Data sheet DSE_PD300_eng_AO No part of this publication may be reproduced by whatever means without the prior written permission of Ingeteam T&D. One of

More information

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor. Basis of Design This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor. Background Information A Short Circuit and Coordination

More information

SYNCHRONISM RELAY SYNCRO-96. (Code ) INSTRUCTION MANUAL ( M / 99A ) (c) CIRCUTOR S.A.

SYNCHRONISM RELAY SYNCRO-96. (Code ) INSTRUCTION MANUAL ( M / 99A ) (c) CIRCUTOR S.A. SYNCHRONISM RELAY SYNCRO-96 (Code 2 28 913-2 28 914-2 28 915) INSTRUCTION MANUAL ( M 981 196 / 99A ) (c) CIRCUTOR S.A. ----- Synchronism relay SYNCRO-96 -------- M - 981 196 --- Page nº 1 Synchronism relay

More information

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION David TOPOLANEK Petr TOMAN Michal PTACEK Jaromir DVORAK Brno University of Technology - Czech

More information

Capacitor protection relay

Capacitor protection relay Capacitor Protection Relay FEATURES Capacitor unbalance protection Line current unbalance protection Overvoltage protection Overheating protection Ground fault protection Overcurrent protection Undercurrent

More information

International Journal of Advance Engineering and Research Development

International Journal of Advance Engineering and Research Development Scientific Journal of Impact Factor (SJIF): 3.134 International Journal of Advance Engineering and Research Development Volume 2,Issue 12,December -2015 E-ISSN (O): 2348-4470 P-ISSN (P): 2348-6406 Detection

More information

Predicting the Voltage Sag Performance of Electricity Distribution Networks

Predicting the Voltage Sag Performance of Electricity Distribution Networks Predicting the Voltage Sag Performance of Electricity Distribution Networks by Dr Robert Barr, Prof. Vic Gosbell, Mr Chris Halliday, Figure - Typical Rectangular Voltage Sag PU Supply Voltage..2 0.8 0.6

More information