Snohomish County Courthouse Renovation + Addition COUNCIL PRESENTATION 6 MARCH 2017
|
|
- Ashlie Benson
- 5 years ago
- Views:
Transcription
1
2 Review the Process Building Assessment Prioritize into Tiered Matrix Develop Cost Estimate per Scope Items Schematic Design Renovation + Addition Schematic Drawings Interior + Exterior Perspectives Recommendations Scope of Work Additional Scope
3 Snohomish County Courthouse Project Building Assessment
4 Snohomish County Courthouse Project Building Assessment Tiered Matrix
5 Snohomish County Courthouse Project Campus Site Plan
6 Courthouse Renovation Plan Level B Floor Plan Level B Work Plan
7 Courthouse Renovation Plan Level 1 Floor Plan Level 1 Work Plan
8 Courthouse Renovation Plan Level 2 Floor Plan Level 2 Work Plan
9 Courthouse Renovation Plan Level 3 Floor Plan Level 3 Work Plan
10 Courthouse Renovation Plan Level 4 Floor Plan Level 4 Work Plan
11 Courthouse Renovation Plan Level 5 Floor Plan Level 5 Work Plan
12 Snohomish County Courthouse Project Schematic Massing Model
13 Schematic Courthouse Exterior Renderings
14 Schematic Courthouse Exterior Renderings
15 Schematic Public Lobby Renderings
16 Schematic Jury Assembly Renderings
17 Schematic Criminal Hearings Renderings
18 Scope of Base Renovation Work Public Entrance Lobby with Security Screening Public ADA Accessible Restrooms Improved Security Direct Inmate Delivery for 4 Courtrooms Dedicated Inmate Elevator Criminal Hearing on Level 1 Elevator and Stair Tower Courtroom Additions with full ADA Accessibility Jury Assembly with seating for 200 people Judicial Administration Offices Future Expansion capabilities Improved Sheriff Administration Offices Seismic Upgrade Extends the Life of the Building 50 years Cost = $ 62,899,826
19 Scope of Additional Renovation Work Mechanical & Plumbing Systems At End of Operational Life Cooling tower replacement (dual) Chiller replacement (1 of 2) Piping replacement (chilled and condenser) Pump replacement Replace existing heating and cooling coils on Main Building air handler Galvanized domestic water piping replacement allowance Boiler replacement (1 of 2) Heating water pumping replacement Per code, provide outside air to existing emergency generator diesel fuel system Extends the Life of the Building Systems 25 years Cost = $2,631,443
20 Scope of Additional Work Special Systems (Security Systems) Duress System Replacement Current system is obsolete Add help buttons as needed Interface between the help button and access control systems Upgrade access control system Replace and upgrade existing card readers and terminal controllers Add new card readers as required for Addition and Renovation Video surveillance system Upgrade video system Video recorder server Cost = $2,234,174
21 Scope of Additional Work Audio Visual Allowance for Selected Courtrooms AV Budget Allowance Assistive Listening Systems Addition of large-screen monitors New digital microphone system Software and hardware upgrades for HD monitors Video-conferencing capability for selected courtrooms Cost = $2,019,963
22 Scope of Additional Work Improvements to Selected Courtrooms District Court 1 & 2 1 courtroom ADA compliance enhancements for public accommodation Both courtrooms mechanical and lighting improvements Superior 1-4, 7, 8 & 10 Dept. 10 ADA compliance enhancements for public accommodation All interior finish updates, and mechanical and lighting renovations Superior Court 201 (ADA compliance enhancements for public accommodation) 1 Commissioner Courtroom (ADA compliance enhancements for public accommodation) Cost = $2,400,079
23 Design / Construction Schedule
24
Eastern Lebanon County School District Ad Hoc Committee: High School Renovation Project
Ad Hoc Committee: High School Renovation Project Wednesday, October 11, 2017 High School LGI Room, 6:00pm Instructional Focus for 2017-2018 Equitable Access to Rigorous Learning Results Focused Accountability
More informationState College of Florida, Manatee-Sarasota
State College of Florida, Manatee-Sarasota SCF Venice Chiller Plant Upgrade Project FAC2017-58 Project No. 7-17-2-11 and 3-17-2-12 ADDENDUM NUMBER #1 Date: December 4, 2017 NOTE: THIS ADDENDUM SHOULD BE
More informationOLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN
KBE APPROVAL DATE: APRIL 2013 including Finding #1 g g OLDHAM COUNTY SCHOOL'S DISTRICT FACILITIES PLAN PLAN OF SCHOOL ORGANIZATION 1. Current Plan PS, K-5, 6-8, 9-12 2. Long Range Plan PS, K-5, 6-8, 9-12
More informationPROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic
GENERAL SITE PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS Scope of work narrative Building code review Description of construction Documentation on drawings as List of applicable
More informationHuntington Beach City School District. M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y
Huntington Beach City School District M e a s u r e Q B o n d I m p l e m e n t a t i o n S i t e C o m m i t t e e M e e t i n g M a y 0 1 7 Agenda 1. Where are we in the process?. Measure Q Bond Program
More informationDesign Deliverables. Summary. A. Expectations for Design Deliverables:
Design Deliverables Summary A. Expectations for Design Deliverables: The Design Team is obligated to advance and deliver the project with a professional manner and standard of care that meets the expectations
More informationRufus M Hitch Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationIndex. 1 Introduction. 2 Executive Summary. 3 Long-Range Facility Master Plan
Index 1 Introduction 2 Executive Summary Existing Facility Inventory and Assessment Preliminary Space Needs Projections Master Plan Conclusions Project Recommendations 3 Long-Range Facility Master Plan
More informationThomas A Edison Regional Gifted Center ES 4929 N Sawyer Ave Chicago, IL Co-locating on this campus are EDISON and ALBANY PARK
Facility Assessment Report 4929 Sawyer Ave Chicago, IL 025 Co-locating on this campus are EDISO and ALBA PARK This report contains a summary of the results from the facility assessment completed on the
More informationCentral High School. 275 Lexington Parkway North. Project Summary: Issues Identified By School Community In 2015
275 Lexington Parkway North Project Summary: Central is the oldest high school in the state of Minnesota, beginning its 150th year. Its rich traditions, including academic excellence, are widely celebrated.
More informationPaul Cuffe Math-Science Technology Academy ES 8324 S Racine Ave Chicago, IL 60620
82 S Racine Ave Chicago, IL 020 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationAppendix A Existing Facilities Condition Audit. values culture relationships since 1909.
Appendix A Existing Facilities Condition Audit values culture relationships since 1909. Existing Facilities Condition Report Outagamie County Downtown Campus City of Appleton Outagamie County, Wisconsin
More informationCharles G Hammond Elementary School 2819 W 21st Pl Chicago, IL 60623
Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item
More informationTri-County Commercial Application Checklist
TRI-COUNTY SERVICE CENTER TRI-COUNTY SERVICE CENTER State of Oregon Clackamas Multnomah Washington C O U N T I E S Tri-County Commercial Application Checklist Department of Consumer & Business Services
More informationNathanael Greene Elementary School 3525 S Honore St Chicago, IL 60609
athanael Greene Elementary School 32 S Honore St Chicago, IL 009 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the
More information05BDB ADDENDUM 002. Thomas W. Wathen Business Division Building Renovation GENERAL ITEMS:
ADDENDUM 002 Addendum - 002 to the Drawings and Specifications dated, March, 2019, for Vincennes University, located at the Vincennes Campus in Vincennes, Indiana, as prepared by Andrew Young, Campus Architect,
More informationUniversity of Chicago Charter - NKO
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJosefa Ortiz De Dominguez Elementary School 3000 S Lawndale Ave Chicago, IL 60623
3000 S Lawndale Ave Chicago, IL 023 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This
More informationJohn F Kennedy High School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationArthur A Libby Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJames Shields Middle School 2611 W 48th St Chicago, IL 60632
2 W 48th St Chicago, IL 02 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationJohn Hancock College Preparatory High School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationUniversity of Houston Master Construction Specifications Insert Project Name SECTION MECHANICAL SCOPE OF WORK PART 1 - GENERAL
SECTION 23 00 10 - MECHANICAL SCOPE OF WORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements", and Section 23 01
More informationINTERIOR SIGNAGE MANUAL
INTERIOR SIGNAGE MANUAL ➊ Purpose ➋ Procedures ➌ ADA Requirements INTERIOR SIGNAGE MANUAL ➍ Text, Braille, Pictograms and Color ➎ Families of Interior Signage ➏ Mounting Guidelines ➐ Signage Diagrams ➑
More informationJohn Milton Gregory Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationArthur E Canty Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationAcademy for Global Citizenship Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationWilliam Penn Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationOCPS Submittal Register for Product Data and Shop Drawing Reviews
OCPS mittal Register for Product Data and Shop Drawing s Project ification Drawings - D Shop Drawings - Product Data - Test - TR Test Data - TD Calculations - Calc Certification - Cert 02 22 27 Pre-demolition
More informationCyrus H McCormick Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationRECORD GROUP NUMBER 156
DEPARTMENT OF MENTAL HEALTH AND MENTAL RETARDATION HOSPITAL AND SCHOOL FOR THE RETARDED ARLINGTON, TENN. BLUEPRINTS, 1965 RECORD GROUP NUMBER 156 Processed by: David R. Sowell Archival Technical Services
More informationJohn L Marsh Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationRequ est fo r sea led bids for an addition to Be ave r Lake Bathhouse
Requ est fo r sea led bids for an addition to Be ave r Lake house The lpena County Parks and Recreation commission will be accepting sealed bids for the following t rades: Concrete/Masonry, Electrical
More informationA.N. Pritzker School 2009 W Schiller St Chicago, IL 60622
A.. Pritzker School 2009 W Schiller St Chicago, IL 022 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document
More informationFranklin Elementary Fine Arts Center 225 W Evergreen Ave Chicago, IL 60610
22 W Evergreen Ave Chicago, IL 1 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationRobert Fulton Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMulticultural Academy of Scholarship
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationDaniel S Wentworth Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMarcus Moziah Garvey Elementary School S Morgan St Chicago, IL 60643
Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item
More informationThomas Chalmers Specialty Elementary School 2745 W Roosevelt Rd Chicago, IL 60608
W Roosevelt Rd Chicago, IL 8 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationFriedrich Ludwig Jahn Elementary School 3149 N Wolcott Ave Chicago, IL 60657
39 Wolcott Ave Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationArchitecture, Construction, and Engineering Technical Charter
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationGeorge Washington Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationUniversity of Chicago Charter - Carter G Woodson
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCharles P Caldwell Academy of Math & Science ES 8546 S Cregier Ave Chicago, IL 60617
S Cregier Ave Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationNDUS/UND IT Facility Office Building/Data Center
NDUS/UND IT Facility Building/Data Center Building Option 3 $9,133,128 Data Center $4,937,500 Tier 2 to Tier 3 (add on) $1,356,250 Total $15,426,878 Legislative Appropriation $12,500,000 Difference $2,926,878
More informationEPIC Academy High School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationDisney II Magnet School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationGeorge Washington Elementary School 3611 E 114th St Chicago, IL 60617
3 E th St Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up
More informationBUILDING PLAN REVIEW REQUIREMENTS
TOWNSHIP OF NORTH FAYETTE BUILDING DEPARTMENT COMMERCIAL PLAN REVIEW REQUIREMENTS BUILDING PLAN REVIEW REQUIREMENTS In order to perform a thorough Building Plan Review, the following specifications, drawings
More informationUniversity of Chicago - North Kenwood/Oakland 1119 E 46th St Chicago, IL Co-locating on this campus are U OF C - NKO and ARIEL
Facility Assessment Report 9 E 4th St Chicago, IL 03 This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationGeorge W Tilton Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJohn Hancock College Preparatory High School 4034 W 56th St Chicago, IL 60629
3 W th St Chicago, IL 09 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More information11/29/12. Des Moines Social Club Urban Design Review Project Narrative
11/9/1 Des Moines Social Club Urban Design Review Project Narrative Strategically located at 9th and Walnut, the Des Moines Social Club (DMSC) will become a critical link between the Court Avenue Entertainment
More informationWendell E Green Elementary School 1150 W 96th St Chicago, IL 60643
11 W 9th St Chicago, IL 3 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationAmos Alonzo Stagg Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationExhibit A Project Identification. Exhibit B Project Charter / Project Intent. Exhibit C Project Scope. Exhibit C Project Schedule
Exhibit A Project Identification Exhibit B Project Charter / Project Intent Exhibit C Project Scope Exhibit C Project Schedule Exhibit D Project Budget Exhibit E Owner Supplied Documents Exhibit F Sample
More informationCLARION COUNTY OFFICE DIRECTORY
CLARION COUNTY OFFICE DIRECTORY www.co.clarion.pa.us All phone numbers are area code 814 unless otherwise noted Adult Probation 500 Main Street, Clarion, PA 16214 Phone: 226-6020 Fax: 226-6027 Assessor
More informationTELEPHONE: (215) Addendum No Cooling Plant Replacement SDP Contracts No. B-080C, B-081C and B-082 of 2017/18
THE SCHOOL DISTRICT OF PHILADELPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, 3 rd Floor Suite 371 Philadelphia, PA 19130 TELEPHONE: (215) 400-4730 Addendum No. 001 Subject:
More informationJohn Harvard Elementary School of Excellence
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationSTEM Magnet Academy. Definitions EXTERIOR W Fillmore St Chicago, IL 60607
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMahalia Jackson Elementary School 917 W 88th St Chicago, IL 60620
W 88th St Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationRichard T Crane Medical Preparatory HS
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNorth Lawndale College Prep Charter - Collins
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationDisney II Magnet High School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMarcus Moziah Garvey Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationIdaho State Historical Museum Renovation and Addition
Idaho State Historical Museum Renovation and Addition History is essential to understanding America. Lessons from the past enhance historical literacy, create an informed citizenry, deepen our connections
More informationCAPITAL IMPROVEMENT PROGRAM
CAPITAL IMPROVEMENT PROGRAM Public Work Session No. 2 Project Narrative Submittal December 18, 2017 Prepared for: HALLSVILLE R-IV SCHOOL DISTRICT 421 East Highway 124 Hallsville, MO 65255 Prepared by:
More informationWilliam Howard Taft High School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationLangston Hughes Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationGeorge Washington High School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationPhilip Rogers Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationBrian Piccolo Elementary Specialty School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCharles N Holden Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMorton School of Excellence
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationRichard J Oglesby Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNorman A Bridge Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationU of I Facilities Standards Updates for 2017
U of I Facilities Standards Updates for 2017 Updates to the U of I Facilities Standards will occur on a periodic basis (typically all standards will be reviewed for accuracy & completeness every 3 years),
More informationJonathan Burr Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationUTSA Facilities Condition Assessment. Out Brief August XX, 2009
UTSA Facilities Condition Assessment Out Brief August XX, 2009 Agenda Opening Remarks FCA Results Summary by Category Example Deficiencies FCA Results Summary by Building Proposed Project List Potential
More informationAlexander Graham Bell Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationTheodore Roosevelt High School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJohn Spry Elementary Community School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationAndrew Carnegie Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More information2010 ADA Standards Courtroom Requirements
2010 ADA Standards Courtroom Requirements LIFT-U Division of Hogan Mfg., Inc. P.O. Box 398 Escalon, CA 95320 http://liftu.hogan.com Slide 1 of 50 2010 ADA Standards Courtroom Requirements LIFT-U Division
More informationRequired Documents for Commercial Permits Permit Types 1. New Structure 2. Addition 3. Remodel 4. Tenant Finish 5. Change of Tenant/Use 6.
Required Documents for Commercial Permits Permit Types 1. New Structure 2. Addition 3. Remodel 4. Tenant Finish 5. Change of Tenant/Use 6. Temporary Use 7. Decks over 30 inches 8. Re-Roof 9. Plumbing 10.
More informationJackie Robinson Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCTS-D Job Task Analysis
A Conducting a Needs Assessment 1 Identify decision-makers and stakeholders Contractual relationships Ability to ask probing questions RACi Chart Client organizational structure Ability to differentiate
More informationHenry H Nash Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationLegacy Charter Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJames Monroe Elementary School 3651 W Schubert Ave Chicago, IL 60647
W Schubert Ave Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationBetty Shabazz Intl Charter - DuSable Leadership
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS
ADDENDUM NO. TWO To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS Prepared By: ARCHITECT Bhide & Hall Architects, P.A. 1329-C Kingsley
More informationAddendum No. 1 page 1
Addendum No. 1 page 1 Project: Proj. No: 1634.02 Scottsburg High School HVAC Renovation 2017 Scott County School District 2 Scottsburg, Indiana Date: November 22, 2016 This addendum is a part of the bid
More informationWilliam Howard Taft High School 6530 W Bryn Mawr Ave Chicago, IL 60631
W Bryn Mawr Ave Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationJohann W von Goethe Elementary School 2236 N Rockwell St Chicago, IL 60647
3 Rockwell St Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationWilliam H Seward Communication Arts Academy ES 4600 S Hermitage Ave Chicago, IL 60609
S Hermitage Ave Chicago, IL 9 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationFrederic Chopin Elementary School 2450 W Rice St Chicago, IL 60622
2 W Rice St Chicago, IL 022 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationPhoenix Military Academy High School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMarch 1, Buildings for Our Future: 2016 Update
March 1, 2016 Buildings for Our Future: 2016 Update Buildings For Our Future: Project Objectives Transform five elementary schools in poor and worsening condition into 21st century centers of learning
More information