Samuel Hudson BIM Support Specialist. Jeff Owens AIA, LEED AP
|
|
- Toby Perry
- 5 years ago
- Views:
Transcription
1 BIM Preparation for the USACE Lessons Learned in Conversion from REVIT to BENTLEY BIM Presenters: Samuel Hudson BIM Support Specialist Jeff Owens AIA, LEED AP L E ll Lee Ezell Consulting BIM Specialist
2 Oa BIM Support Services BIM Consultation / USACE Compliance Support for Attachment F Visualization Reporting for for Cost Estimation Bentley-based BIM Architectural Structural MEP 3D PDF Documentation 4D Construction Simulation Video
3 Presentation Outline Contract Deliverables / Attachment F * Workflow * Lessons Learned Relevant Projects Supporting Contractor-Lead Teams: COF Content from REVIT to Bentley, MEP WIT Content from REVIT to Bentley, All Disciplines WIT Content from REVIT to Bentley, All Disciplines
4 Contract Deliverables Attachment F 3 types in use - USACE determines which is to be used Type 1 - Project for Center of Standardization Design Contractor s BIM application of choice. Submittals Bentley BIM Applications, V8XM Workspace Type 2 - Non-COS Design Contractor s BIM application of choice. Submittals BIM Application specified in RFP Type 3 - Non-COS, BIM Neutral Design Contractor s BIM application of choice. Submittals Contractor s BIM Application of choice
5 Attachment F Minimum Requirements Model may vary in the level of detail for individual elements, but at a minimum must include all features that would be included on a quarter inch (1/4 =1-0 ) scaled drawing. all equipment piping & fittings fixtures including necessary intelligence to produce all equipment piping & fittings fixtures including necessary intelligence to produce accurate plans, elevations, building/wall sections, and schedules
6 Different Perspectives USACE There is no Spirit of the Contract There is no Conversion from REVIT to Bentley Contractors / AEs must demonstrate acceptable incorporation of objects from other platforms prior to project startup. Files must be editable / fully functional in specified application upon submittal.
7 Different Perspectives USACE There is no Spirit of the Contract There is no Conversion Contractor from REVIT / AE to Bentley Contractors / AEs must Provide demonstrate Optimum acceptable Design at tbest tcost incorporation of objects from other platforms prior to project startup. Take advantage of existing CAD/BIM systems Files must be editable Design / fully functional Solution may in specified include sources that don t application upon submittal. include or originate from Bentley applications. To satisfy Delivery of Submittals and As-Builts Choice between investing in and training for in-house Bentley BIM or using 3 rd Party BIM support services.
8 Different Perspectives USACE There is no Spirit of the Contract There is no Conversion Contractor from REVIT / AE to Bentley Contractors / AEs must Provide demonstrate Optimum acceptable Design at tbest tcost incorporation of objects from other platforms prior to project startup. Take advantage of existing BIM Support CAD/BIM Provider systems Files must be editable Design / fully functional Solution may in To specified include support sources the process that don t / path YOU have chosen to application upon submittal. include or originate from follow. Bentley applications. To satisfy Delivery of To Submittals advise you and on As-Builts potential pitfalls if they are seen Choice between investing coming. in and training for in-house Bentley BIM or using 3 rd Party BIM support services. To assist You to meet the terms of the required deliverables. Early start on any project makes it easier to integrate.
9 What will BIM Support Require? Project RFP with Attachment F for Overview & Deliverable Requirements. Team Contacts & Areas of Responsibility Milestones for Delivery 3D Geometry of all building systems in DWG for reference What level of Completion was the 3D taken to? Have Building Systems been checked for Interferences? 2D CAD Sheets in DWG and PDF for reference and incorporation. Were Documentation Symbols in REVIT setup for USACE standards for NCS? Manufacturer Cut Sheets as Basis of Design later for As-Builts.
10 Workflow Fidelity at import is not available by Conversion from REVIT. ReConstruction from Scratch is the Process that must be used. REVIT EXPORT to DGN EXPORT to DWG IFC to DGN ReCONSTRUCTION DGN
11 Process Overview Discipline Level 3D Composite Facility 3D Extracted 2D Views 2D CAD Models 2D CAD Sheets ARC INT STR MEC PLU BLDG 1 BLDG 2 Plans Elevs Bldg Sects Wall Sects Plans Elevs Bldg Sects Wall Sects Dtls G-001 to G-999 C-001 to C-999 L-001 to L-999 S-001 to S-999 Compose A-001 to A-999 References I-001 to I-999 & F-001 to F-999 P-001 to P-999 Annotate M-001 to M-999 E-001 to E-999 T-001 to T-999 FP Diag ELE BLDG 3 Schd Schd TEL 3D 2D from Models 2D from CAD
12 ReContructing 3D -Split Supplied DWG into Separate Models. -Split by Discipline i / Building Systems -USACE Naming Format for Model DGNs -Use DWGs as Point of Reference when constructing Bentley BIM -Location / Dimension / Quantity -Reconstruct over referenced DWG 3D and/or 2D Plans -Find Objects for Incorporation and copy forward. -Objects that will not need to be re-edited by Bentley -Drop to Elements then Select & Re-Group the Set -Apply USACE Parts to incorporated Object. -Attach Instance Data and Edit when Required.
13 ReContructing Views / Creating Extractions -Extraction Process well defined within Bentley. -Cut Lines in Con-Docs define where 3D is sliced. -Using Rules by Discipline to affect output. -Run extractions and compare to DWG equivalents from REVIT -USACE File Naming Format for Extractions -Add Missing Elements from Extraction into CAD Model file. -DWG reference may offer additional elements for incorporation. -USACE File Naming Format for CAD Models
14 ReContructing Schedules -Schedules are Excel Spreadsheets. -Populated by Instance Data from the models -Filled in Manually when not tied to the models (export from REVIT?) -Paste into CAD Sheets for inclusion -USACE Excel Schedules included with Workspace
15 ReContructing CAD Sheets -Create separate DGN Sheet for each Hardcopy Sheet. -Reference DWG CAD Sheets if available to match the composition. -Attach CAD Models & Extractions as references and Compose -Attach Excel Schedule Graphics and Compose -Copy forward annotations if graphically compliant -Remap colors and lines if required -OR Create new compliant annotations and symbols -USACE File Naming Format for CAD Sheets.
16 Strengths in Process Bentley from Conception through As-Built: Designers use CAD/BIM of choice use BIM Support as expanded capacity alongside Designers or Self-Perform. Bentley Model prepared for Interim Reviews and Submittals in full compliance with Attachment F., including checking for and resolving interferences. Material Quantities in support of Cost-Estimates provides cost reference for design. 4D Simulation to Resolve / Sell Difficult Construction Sequences Bentley from 65% through As-Built: Designers use their CAD/BIM platform of choice, keeping all efficiencies developed internally to those team members. BIM Support initiates after design is substantially resolved, preparing new BIM in Bentley format from scratch.
17 Weaknesses in Process Bentley from Conception through As-Built: If 3 rd Party Bentley Support, Higher Cost, as Bentley BIM is reworked through design iterations and interference resolution. More involvement in Design Process. Plan for some degree of lag with 3 rd Party Team to catch up state of in-house design. Bentley from 65% through As-Built: Not Compliant with Requirement for Interim Submittals BIM Support used as safety net when reworking the BIM around design already established. Discovery of Canned objects from other platforms that do not truly represent Equipment or Systems they are supposed to. Less effective use for Material Quantities in support of Cost- Estimates, a valuable Contractor Elective in Attachment F.
18 Moving Forward Software Development 2D becomes Live in V8i Plugin for REVIT being improved Imodel format offers collaboration Workflow Improvements Requirements for Support are Defined We have learned what to ask. Try to get On-Board much earlier Early Involvement results in better product Early Involvement satisfies the USACE.
19 Attachment F Contractor Electives Bentley BIM can support project scheduling: 6.3 Project Scheduling using the Model: Bentley BIM can support project scheduling through 4D Construction Simulation Bentley BIM can provide support for Cost Estimating: 6.4 >> for the Execution Plan >> for Interim Submittals >> Supporting Data for an MII Estimate at Interim Submittals and at project completion.
20 Communication
21 Questions / Discussion
22 Thank You For Your Time. Samuel Hudson BIM Support Specialist Jeff Owens AIA, LEED AP Lee Ezell Consulting Specialist Owens Architects Lawrenceburg, Kentucky Owens Architects is dedicated to designing buildings that create good function and inspiring beauty while demonstrating fiscal accountability and good earth stewardship. Our goal is to provide the highest level of professional service to institutional, commercial and residential clients that desire beautiful and durable buildings which can be built within the constraints of their construction budgets. Human needs design is the principle basis of our design philosophy
BIM Introduction. Building Information Management Definitions, Applications and general information. Betty Bezos
BIM Introduction Building Information Management Definitions, Applications and general information Betty Bezos betty@bezos.com 9/1/2017 1 9/1/2017 2 Innovations in BIM 3D Design: 3D visualizations allow
More informationNational BIM Standard - United States Version 3
National BIM Standard - United States Version 3 5 Practice Documents 5.5 Mechanical, Electrical, Plumbing, And Fire Protection Systems (MEP) Spatial Coordination Requirements for Construction Installation
More informationPiping Workflow for MEP AutoCAD Piping Phil Nower Hazen and Sawyer
Piping Workflow for MEP AutoCAD Piping Phil Nower Hazen and Sawyer MP3512-L: In this class we will harness the power of MEP Data in AutoCAD. We will review the workflow to fully utilize this Data throughout
More informationMEP Coordination. Ir. Dr. Sam C. M. Hui Faculty of Science and Technology
SBS5411 Building Information Modelling for BSE http://ibse.hk/sbs5411/ MEP Coordination Ir. Dr. Sam C. M. Hui Faculty of Science and Technology E-mail: cmhui@vtc.edu.hk Oct 2018 Contents Introduction Clash
More informationNEW YORK DISTRICT U.S. ARMY CORPS OF ENGINEERS OFFICIAL MANUAL FOR
NEW YORK DISTRICT U.S. ARMY CORPS OF ENGINEERS OFFICIAL MANUAL FOR BUILDING INFORMATION MODELING PROJECTS VERSION 1.0 MAY 2009 NEW YORK DISTRICT OFFICIAL MANUAL FOR BUILDING INFORMATION MODELING (BIM)
More informationDesign, Drawing and Sheet Composition
Design, Drawing and Sheet Composition Tools, Technologies and Concepts 1 WWW.BENTLEY.COM 2018 Bentley Systems, Incorporated 2018 Bentley Systems, Incorporated 2 WWW.BENTLEY.COM 2018 Bentley Systems, Incorporated
More informationSession 3 _ Part A Effective Coordination with Revit Models
Session 3 _ Part A Effective Coordination with Revit Models Class Description Effective coordination relies upon a measured strategic approach to using clash detection software. This class will share best
More informationBIM & Emerging Technologies. Disrupting Design process & Construction
BIM & Emerging Technologies Disrupting Design process & Construction Introduction Introduction - BIM Disrupting the Construction Introduction Design Major disruption already in various parts of the World
More informationi-models Kansas City Revit Users Group September, 2013
i-models Kansas City Revit Users Group September, 2013 Agenda i-model Definition Creation of i-models from Revit Reading an i-model Bentley Users collaborating with Revit Users Bentley View free Bentley
More informationCHAPTER A-10 DRAWINGS
CHAPTER A-10 DRAWINGS INDEX Revised May 2018 10.1 GENERAL 10.1.1 Purpose and Scope 10.2 APPLICABLE PUBLICATIONS 10.3 COMPUTER AIDED DESIGN (CAD) 10.3.1 CAD Requirements 10.3.2 CAD Deliverables 10.3.3 CAD
More informationIntegrating Design using BIM and IFC
Integrating Design using BIM and IFC Thomas Liebich AEC3, Munich, Germany tl@aec3.de www.aec3.com Company overview Founded 1997 7 employees established in 2 countries Main activities information modeling
More informationWhat is BIM and why should construction lawyers care about it? Dr. Carrie Sturts Dossick, P.E. Bita Astaneh Asl
What is BIM and why should construction lawyers care about it? Dr. Carrie Sturts Dossick, P.E. Bita Astaneh Asl Learning Objectives What is BIM? > BIM definition > BIM history > Common current uses (3D
More informationWhy Moving from AutoCAD to AutoCAD MEP Just Makes Sense!
AUTOCAD MEP Why Moving from AutoCAD to AutoCAD MEP Just Makes Sense! If you create building mechanical, electrical, or plumbing (MEP) construction documents and are currently working with AutoCAD software
More informationOptimizing Digital Drawing Files and BIM Models for Measurement and Estimating
Optimizing Digital Drawing Files and BIM Models for Measurement and Estimating Simon Lovegrove MRICS, AAIQS - Exactal CM4228 Drawing file formats issued for measurement and estimating purposes range from
More informationBIM. e Submission Guideline Structural. Annex 1a. Recommended Process Revit 2010
BIM e Submission Guideline Structural Annex 1a Recommended Process Revit 2010 Building and Construction Authority 5 Maxwell Road #16-00 Tower Block MND Complex Singapore 069110 www.bca.gov.sg Revision
More informationPlease comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at
Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf when using this file. Thank you. BIM & THE VALUE STREAM LCI:
More informationAddendum to Description of Services for Building and Planning, Digital Design. The Association of of Consulting Engineers
Addendum to Description of Services for Building and Planning, 2012 8.4 Digital Design 2016 The Association of of Consulting Engineers FRI and DANSKE ARK Addendum to Description of Services for Building
More informationAutodesk Revit MEP Learning Essentials Training Course Outline
Module 00 Revit in a Nutshell Interactive exercise on creating and documenting a basic building Module 01 Introduction to the Principles of BIM Simple Truths Behind the hype The benefits of BIM What will
More informationAutodesk Revit MEP Fundamentals
Autodesk Revit MEP Fundamentals Course Length: 4 days To take full advantage of Building Information Modeling, the Autodesk Revit MEP: Fundamentals training course has been designed to teach the concepts
More informationMoving to Model-Based Design
Infrastructure Solutions White Paper Moving to Model-Based Design Choosing Between 2D and 3D Do you really have to choose between 2D and 3D? The answer is no, but it is important to know why. Over the
More informationU.S.A.C.E. ALBUQUERQUE DISTRICT A/E/C CADD STANDARD SUPPLEMENTAL STANDARD
U.S.A.C.E. ALBUQUERQUE DISTRICT A/E/C CADD STANDARD SUPPLEMENTAL STANDARD (FOR USE WITH THE A/E/C CADD STANDARDS RELEASE 4.0) 24 March 2009 26 January 2012 PURPOSE AND SCOPE The purpose of this document
More informationHow technology is changing the way we deliver Structural Steelwork. Brenden Picton Phil Shanks
How technology is changing the way we deliver Structural Steelwork Brenden Picton Phil Shanks Presentation Outline Project Introduction & Process Description From the Engineers Perspective From the Detailers
More informationHow Digital Engineering Will Change The Way We Work Together To Design And Deliver Projects Adam Walmsley, BG&E, Australia.
How Digital Engineering Will Change The Way We Work Together To Design And Deliver Projects Adam Walmsley, BG&E, Australia. ABSTRACT Our industry is witnessing its biggest change since CAD was introduced
More informationFACILITIES CADD STANDARD
2015 Facilities Services Division of Design and Construction CADD Department FACILITIES CADD STANDARD CAD, BIM, & GIS Standards for the University of Alaska Fairbanks The University of Alaska Fairbanks
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 33 16.00 10 (May 2016) ------------------------------ Preparing Activity: USACE UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated
More information***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)
DRAFT UFGS- 01 XX XX (FEB 2014) ------------------------ Drafting Activity: USACE UNIFIED FACILITIES GUIDE SPECIFICATION SECTION TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION 01 XX XX (FEB
More informationBIM for FM: Helping Owners Realize the Benefits of BIM
Monday, June 13, 2016-4:00pm-5:15pm, Clark, Lower Level Presented by: Bert Jones, Associate Vice Chancellor for Facilities Management Services, Virginia Community College System Jeff Van Fleet, Account
More informationSECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationMP BIM at the Heart of the MEP Subcontractor Business
MP4229 - BIM at the Heart of the MEP Subcontractor Business Damien Legrand Sophie Montenot BIM Business Development Executive MEP BIM Manager 1 Class Summary Dive into the heart of an MEP subcontractor
More informationLA DOTD Electronic Plans Breaking New Ground
LA DOTD Electronic Plans Breaking New Ground Louisiana Transportation Engineering Conference Baton Rouge River Center February 13, 2007 Presented by Hollis Ward Electronic Plans - A Team Effort Bridge
More informationDesigning with BIM for Infrastructure on Large Transportation Projects
Designing with BIM for Infrastructure on Large Transportation Projects July 19, 2012, 10:00 a.m. Pacific Time Join civil designer Dave DeJong from Stantec as he discusses how BIM for Infrastructure has
More informationComputer-Aided Drafting and Design Technology, A.A.S.
Johnson County Community College 1 Computer-Aided Drafting and Design Technology, A.A.S. Drafting technicians are engineering communication specialists who apply mathematics, computer applications and
More informationProgramme TOC. CONNECT Platform CONNECTION Client MicroStation CONNECT Edition i-models what is comming
Bentley CONNECT CONNECT Platform MicroStation CONNECT Edition 1 WWW.BENTLEY.COM 2016 Bentley Systems, Incorporated 2016 Bentley Systems, Incorporated Programme TOC CONNECT Platform CONNECTION Client MicroStation
More informationBIM Technology Certificate Program
BIM Technology Certificate Program Program Description 216 Course Hours of Instruction Program Completion Time 9 Months Upon Completion VDCI Professional Technology Certificate Awarded BUILDING INFORMATION
More informationPlant & Process Electrical Design Introduction to I&W, promis e & BRCM
2014 Bentley Systems, Incorporated Plant & Process Electrical Design Introduction to I&W, promis e & BRCM Rick Black- Industry Sales Director - Electrical Group EMEA 3 WWW.BENTLEY.COM 2014 Bentley Systems,
More informationIssue Date: August 2018 Revision: 03
ENGINEERING CADD MANUAL Issue Date: August 2018 Revision: 03 Developed For: Metra Engineering Department 547 West Jackson Blvd. Chicago, Illinois 60661 Developed By: Chandra Mahalingam CADD System Administrator
More informationWhat is Meant by Level of Accuracy? As a service provider who. By John M. Russo, AIA. room width = 10'-0' building length = 100'-0' x = 1/4"
room width = 10'-0' x = 1/4" building length = 100'-0' x = 1/4" What is Meant by Level of Accuracy? As a service provider who documents buildings I often hear my clients say I need one quarter inch accuracy,
More information1 Introduction. M.Rajabi a, T.Bigga b and M.A.Bartl c.
Optimization of the quantity take-off (QTO) process for Mechanical, Electrical and plumbing (MEP) trades in tender estimation phase of the construction projects M.Rajabi a, T.Bigga b and M.A.Bartl c a
More informationOpenPlant. Hayley Brown Industry Consultant, Bentley Plant Bentley Systems, In
OpenPlant Hayley Brown Industry Consultant, Bentley Plant tley Systems, In co Introduction What is OpenPlant? OpenPlant is the branding for the next generation of applications and tools based on ISO 15926
More informationSection 4: Ontario Realty Corporation CAD Standards and Guidelines
Section 4: Ontario Realty Corporation CAD Standards and Guidelines Ontario Realty Corporation 11 th Floor, Ferguson Block 77 Wellesley Street West Queen s Park Toronto, ON, M7A 2G3 August 10, 2007 Version
More informationTHE ADVANCED MODELING SUBMITTAL REVIEW CHECKLIST (CHX)
THE ADVANCED MODELING SUBMITTAL REVIEW CHECKLIST (CHX) 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 1 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102
More informationCIFECENTER FOR INTEGRATED FACILITY ENGINEERING
CIFECENTER FOR INTEGRATED FACILITY ENGINEERING Industrial Case Study of Electronic Design, Cost, & Schedule Integration By Sheryl Staub-French Martin Fischer CIFE Technical Report #122 January, 2001 STANFORD
More informationBIM/VDC on TAA Projects:
2018 Logan International Airport BIM/VDC on TAA Projects: Direct Tenant TAA Projects Third Party Development Properties Massachusetts Port Authority Capital Programs & Environmental Affairs Preface Massport
More informationWhat s New in Bentley Civil SELECTseries 3
What s New in Bentley Civil SELECTseries 3 Introducing OpenRoads Technology Ian Rosam Product Manger, Bentley Civil 1 WWW.BENTLEY.COM 2013 2013 Bentley Bentley Systems, Incorporated Bentley Civil/Transportation
More informationAbout Hensel Phelps - Thai Nguyen About the project Rob Muellner BIM on the project Rob Muellner 3D Lift Drawing Production Rob Muellner MEP
BIM Case Study About Hensel Phelps - Thai Nguyen About the project Rob Muellner BIM on the project Rob Muellner 3D Lift Drawing Production Rob Muellner MEP Coordination Rob Muellner MEP Fabrication Chad
More informationMODEL SETUP FOR RENOVATION PROJECTS: INSTRUCTIONS AND TUTORIALS
MODEL SETUP FOR RENOVATION PROJECTS: INSTRUCTIONS AND TUTORIALS TABLE OF CONTENTS INTRODUCTION 1 PART ONE LAYERS AND CLASSES FOR RENOVATION PROJECT 2 OVERVIEW 2 SETTING UP LAYERS AND CLASSES 2 CREATING
More informationBIM Toolbox. User Guide. Version: Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES
BIM Toolbox User Guide Version: 2018.0 Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES Contents Introduction... 1 Create a new project... 2 Trace around a site
More informationFACADE: Future-proofing Architectural Computer-Aided DEsign
FACADE: Future-proofing Architectural Computer-Aided DEsign MacKenzie Smith Associate Director for Technology, MIT Libraries Principal Investigator, MIT FACADE Project MIT FACADE Project Develop Long-Term
More informationSECTION PROJECT COORDINATION VIA BIM
SECTION 01 31 13 PROJECT COORDINATION VIA BIM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationDesigner CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer
Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer Construction Documents 1.1 to 1.6 Create Submittal Log 1.1 Construction Docs Focus of this process is to transmit submittal
More informationEstates Development & Projects
Estates Development & Projects Production Guidelines for the Building Fabric Manual (incorporating Health & Safety File) Guidance for the Technical Author REVISION 10.2 Issue Date 09/2017 Contents Part
More informationMiami University. Physical Facilities Department. CAD Standards. April 2004
Miami University Physical Facilities Department CAD Standards April 2004 1.0.0 OVERVIEW These standards pertain to the use, production and submittal of electronic CAD files at Miami University. They have
More informationAgenda 1 Introduction 2 Navisworks Overview
Agenda 1 Introduction 2 Navisworks Overview BIM for Contractors: Autodesk Navisworks from Design to Construction to Facilities Management David Epps Manager Building Information Modeling Holder Construction
More informationBIM Design Services/ Introduction. T: E:
Introduction At Godfrey Syrett, Revit is now our default software, we have embraced its capabilities to enhance our design process and add value to it by utilising all its benefits. It is the integration
More informationRevit Revit A step by step guide. 11/14/2011 jimmy boone
Revit 2012 Revit A step by step guide 11/14/2011 jimmy boone Contents Environment settings... 4 Setting up a new MEP models... 5 Step 1, beginning from an architectural model... 5 Step 2 (if using a separate
More informationQuestions and Answers
AutoCAD MEP 2008 (Formerly known as Autodesk Building Systems) Questions and Answers AutoCAD MEP is the AutoCAD software-based design and construction documentation software solution for mechanical/ electrical/plumbing
More informationUDS OVERVIEW Uniform Drawing System
UDS OVERVIEW Uniform Drawing System The Construction Specifications Institute 601 Madison Street Alexandria, VA 1994 CSI began development of UDS Organization and presentation of drawing sets Organization
More informationENGINEERING DRAWINGS MANAGEMENT POLICY (IFC/AS BUILTS)
Approval Amendment Record Approval Date Version Description 15/10/2015 1 This policy takes precedence over L1-NAM-PRO-003 Infrastructure As Built Drawing Management due to business restructures. New Content
More informationCS21297 Visualizing Mars: Enabling STEM Learning Using Revit, Autodesk LIVE, and Stingray
CS21297 Visualizing Mars: Enabling STEM Learning Using Revit, Autodesk LIVE, and Stingray Fátima Olivieri, AIA KieranTimberlake folivieri@kierantimberlake.com Efrie Friedlander, AIA KieranTimberlake efriedlander@kierantimberlake.com
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationTitle. Author(s)YU-CHIH SU; YI-CHUAN HSIEH; MENG-CHUNG LEE; CHIH-YUA. Issue Date Doc URL. Type. Note. File Information CONSTRUCTION
Title DEVELOPING BIM-BASED SHOP DRAWING AUTOMATED SYSTEM I CONSTRUCTION Author(s)YU-CHIH SU; YI-CHUAN HSIEH; MENG-CHUNG LEE; CHIH-YUA Issue Date 2013-09-11 Doc URL http://hdl.handle.net/2115/54245 Type
More informationBIM Won t Work as a Deliverable, Will It? Dace A. Campbell, AIA, LEED AP (Moderator)
BIM Won t Work as a Deliverable, Spring BIMForum San Diego, CA Hilton San Diego Bayfront April 29-30, 2015 Will It? Dace A. Campbell, AIA, LEED AP (Moderator) @DaceCampbell Learning Objectives 1. Gain
More informationMODEL SETUP FOR RENOVATION PROJECTS INSTRUCTIONS AND TUTORIALS
MODEL SETUP FOR RENOVATION PROJECTS INSTRUCTIONS AND TUTORIALS WHAT S INSIDE INTRODUCTION 1 PART ONE LAYERS AND CLASSES FOR RENOVATION PROJECT 1 OVERVIEW 1 SETTING UP LAYERS AND CLASSES 1 CREATING OBJECT
More informationStanford University-Facilities Design Guideline SECTION Plans Review Submission Guidelines
SECTION 01 33 00 Plans Review Submission Guidelines PART 1 GENERAL 1.01 OVERVIEW A. University Plans Review Process: 1. The process by which the Designer s schematic, design development, construction documents
More informationRIT CAD Specifications
RIT CAD Specifications The design team shall provide RIT with Revit, AutoCAD, and PDF files that capture the construction conditions of the associated project. This document outlines requirements for submitting
More informationAn Introduction to SITEOPS
2015 Bentley Systems, Incorporated An Introduction to SITEOPS Bob Rolle, P.E Civil Application Engineer Today we ll cover how to: What our Clients want SITEOPS OPTIONEERING SITEOPS Workflow Blow your mind!
More informationREADING ARCHITECTURAL PLANS
READING ARCHITECTURAL PLANS ARCHITECTURAL DRAWINGS FOR A HOUSE Architectural drawings contain information about the size, shape, and location of all parts of the house ARCHITECTURAL DRAWINGS FOR A HOUSE
More informationAVEVA PDMS. Business Benefits. Accurate and clash-free 3D plant design
AVEVA PDMS Accurate and clash-free 3D plant design With ever increasing global demand for products from process and power plants, AVEVA PDMS enables companies to design, construct and maintain high quality
More informationDesign in Three Dimensions: Building Information Modeling and Design Visualization
ASID South Central Chapter Meeting September 7, 2007 Design in Three Dimensions: Building Information Modeling and Design Visualization Presented by Amy Crumpton, Assistant Professor, Mississippi State
More informationHouston Community College System
Drafting and design Engineering technology - AAS - General Computer-Aided Design Drafting ENGL 1301 Composition I PSYC 2301 Introduction to Psychology DFTG 1358 Electrical/ Electronics Drafting ENGL 2311
More informationA. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationJEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia
BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners
More informationServices Overview. Northeast Blueprint
Services Overview 2D CAD Conversions Paper to CAD 2D CAD Conversions Construction Engineering / CAD Services Construction Markups Consultant Drawings Coordinated Drawings As -Builts Steel Structural Detailing
More informationNo Export Licence Required - Not Protectively Marked
Discipline or report series #10 Technology/CASE Title #15 Summary and Completion Report for the Clean Sky CASE Project Date #40 15 November 25 Summary #60 This report summarises the work undertaken on
More informationAGENDA: BIM Introduction. Large-Scale Value. Value for Architects. Conceptual BIM / Small BIM. All-Out BIM. BIM Introduction
From Conceptual BIM to All-Out BIM Brent Mauti, Architect BARCH, OAA, MAA, SAA, AAA, MRAIC, NCARB, AIA, LEED-AP CH2M HILL CANADA ARCHITECTS INC. brent.mauti@ch2m.com Member of the Manitoba Association
More informationVanderbilt University Standard Specification Revised 2/6/08
SECTION 01 78 23 OPERATION AND MAINTENANCE DATA PART 1 GENERAL 1.01 RELATED SECTIONS A. Section 01 77 00 Closeout Procedures B. Section 01 78 39 Project Record Documents 1.02 SUMMARY A. This section provides
More informationAutodesk Navisworks: Using Autodesk Navisworks in a BIM Workflow
Autodesk Navisworks: Using Autodesk Navisworks in a BIM Workflow Course Length: 2 days The Autodesk Navisworks Using Autodesk Navisworks in a BIM Workflow learning guide teaches you how to better predict
More informationBIM Submission Reference Guide Book (Structural)
BIM Submission Reference Guide Book (Structural) This Document is currently under provisional status and is available for public review and comment. As the provisional status denotes, however, it will
More informationImplementing BIM for infrastructure: a guide to the essential steps
Implementing BIM for infrastructure: a guide to the essential steps See how your processes and approach to projects change as you adopt BIM 1 Executive summary As an ever higher percentage of infrastructure
More informationFixtures for Production of Modular Weld Tables
TSM 416 Technology Capstone Projects Undergraduate Theses and Capstone Projects 4-28-2017 Fixtures for Production of Modular Weld Tables Jeremy Andersen Iowa State University, jeremya@iastate.edu Cameron
More informationAutodesk Inventor LT. Easy as 1, 2, 3D.
Autodesk Inventor LT Easy as 1, 2, 3D. Model Your Part Designs in 3D With parametric 3D solid part modeling in Autodesk Inventor LT software, you can model your part designs in 3D instead of simply drawing
More informationTCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationWhite paper The Quality of Design Documents in Denmark
White paper The Quality of Design Documents in Denmark Vers. 2 May 2018 MT Højgaard A/S Knud Højgaards Vej 7 2860 Søborg Denmark +45 7012 2400 mth.com Reg. no. 12562233 Page 2/13 The Quality of Design
More informationDRAWING MANAGEMENT MISTAKES
5 DRAWING MANAGEMENT MISTAKES You re Making and How to Avoid Them Everything from the site plan, to punch lists and RFIs, to detailed call-outs are part of construction drawings the life blood of the AEC
More informationMicrostation V8 For Autocad Users By Jeanne Aarhus READ ONLINE
Microstation V8 For Autocad Users By Jeanne Aarhus READ ONLINE If you are looking for the ebook Microstation V8 for Autocad Users by Jeanne Aarhus in pdf form, in that case you come on to right site. We
More informationREinVenting an Interior design practice
Kelvin Tam NBBJ AB2535 Interior designers may think Autodesk Revit software is less useful to them than it is to architects, but this class will definitely change their minds. As the scope of interior
More informationUsing BIM to follow up milestones in a project plan during the design phase
Building Information Modelling (BIM) in Design, Construction and Operations 97 Using BIM to follow up milestones in a project plan during the design phase Ø. Mejlænder-Larsen Norwegian University of Science
More informationQUICKSTART COURSE - MODULE 7 PART 3
QUICKSTART COURSE - MODULE 7 PART 3 copyright 2011 by Eric Bobrow, all rights reserved For more information about the QuickStart Course, visit http://www.acbestpractices.com/quickstart Hello, this is Eric
More informationAutoCAD Architecture 2014
CADLearning for AutoCAD Architecture 2014 Course Details 19+ hours of training 325 video tutorials Exercise files included Instructor: Reid Addis Course Description CADLearning for AutoCAD Architecture
More informationAPPLYING 5D ON CONSTRUCTION PROJECTS Konstantinos Kessoudis, Ed. Züblin AG, Zentrale Technik
www.zueblin.de APPLYING 5D ON CONSTRUCTION PROJECTS Konstantinos Kessoudis, Ed. Züblin AG, Zentrale Technik 5D ZÜBLIN S DEFINITION Geometry Sequence Data / Processes 3D 4D 5D One continuously augmented
More informationUsing the ModelBuilder of ArcGIS 9 for Landscape Modeling
Using the ModelBuilder of ArcGIS 9 for Landscape Modeling Jochen MANEGOLD, ESRI-Germany Geoprocessing in GIS A geographic information system (GIS) provides a framework to support planning tasks and decisions,
More informationDrawing Management Brain Dump
Drawing Management Brain Dump Paul McArdle Autodesk, Inc. April 11, 2003 This brain dump is intended to shed some light on the high level design philosophy behind the Drawing Management feature and how
More informationAVEVA PDMS 12.0 The 3D plant design application for accurate and clash-free plant design
AVEVA PDMS 12.0 The 3D plant design application for accurate and clash-free plant design The process and power industries seek to commission high-quality plant earlier, and to bring it on line with minimum
More informationEND-TO-END BIM SOLUTIONS INTEGRATED PRODUCT DELIVERY SOLUTIONS BY ESCA INC.
END-TO-END BIM SOLUTIONS INTEGRATED PRODUCT DELIVERY SOLUTIONS BY ESCA INC. TRADITIONAL AEC PROCESS ISSUES The only industry that does not test a complete design before its implementation TRADITIONAL AEC
More informationThe Manufacturers Perspective
Making BIM work for product manufacturers The Manufacturers Perspective Chris Witte Thank you BIM has been the preserve of Architects and Main Contractors The Manufacturers BIM continuum Stakeholder Management
More informationMOVING TOWARD AN INTELLIGENT SHOP MODELING PROCESS
MOVING TOWARD AN INTELLIGENT SHOP MODELING PROCESS SUBMITTED: August 2007 REVISED: April 2008 PUBLISHED: June 2008 EDITORS: T. Olofsson, G. Lee & C. Eastman Robert Leicht, PhD Candidate, Department of
More informationOUR CLIENT BASE. Canada Norway. UAE Singapore. Germany. Netherlands USA. Hawaii. Australia. Qatar Oman. Belgium. New Zealand.
WHOWE ARE We help construction companies, general contractors, architects & engineers, integrate BIM into their projects seamlessly within their predefined timelines and budget, bridging the gap between
More informationA BIM Residential Workflow at NC Architects NC ARCHITECTS LTD
A BIM Residential Workflow at NC Architects NC ARCHITECTS LTD A BIM Residential Workflow at NC Architects By Derek Marshal NCA NC Architects Ltd Who we are NC Architects are committed to excellence in
More informationCOMPUTER AIDED DESIGN 40
COMPUTER AIDED DESIGN 40 Students can pursue an emphasis on any 1 of 3 disciplines: Architecture, Engineering Design, or Animation Description This course expands on the advanced skills learned in previous
More informationJanuary, 2014 Page 1 of 5
Part 1 General 1.1 General Instructions.1 These instructions add information to all articles of contracts with professionals..2 For each project, McGill University Facilities Operations and Development
More information