Parallel tap-changer controllers under varying load conditions (Part 1)

Size: px
Start display at page:

Download "Parallel tap-changer controllers under varying load conditions (Part 1)"

Transcription

1 Parallel tap-changer controllers under varying load conditions (Part 1) by Prof. B S Rigby, T Modisane, University of KwaZulu-Natal This paper investigates the performance of voltage regulating relays used to control on-load tap changing transformers in a meshed distribution system. Real-time digital simulation, together with hardware-in loop connection of relays, is used to investigate performance under practical conditions, in particular, the responses of the relays to changes in network operating conditions during the daily load cycle. This article covers an investigation into the use of a numerical voltage regulating relay [1, 2] in distribution networks in South Africa. The relay is used to regulate the output voltage of on-load tap changing transformers, and uses control algorithms that prevent circulating reactive currents from flowing between interconnected transformers at different points in a network. The advantage of this technology is that it allows operation in a meshed configuration, providing better back up and security of supply. The algorithm needs no dedicated communication channels, making it cost-effective where substations are tens of km or more apart. It is not possible to test the algorithm or its settings using standard relay injection techniques as it is effectively a distributed control technique applied simultaneously at several locations, with the controllers interacting via the network. In the study a real-time digital simulator [3] was used to predict the performance of relays with the algorithm enabled prior to commissioning. The study also focused on determination of algorithm settings suitable for conditions encountered in practical distribution networks. Fig. 1: Distribution network under study. Early work [4] focused on developing a detailed real-time simulator model of the distribution network while subsequent work [5] developed a detailed real-time simulation model of the main control algorithms, to better understand operation of the relay and allow engineers to study its performance without the need for a real-time simulator. More recent real-time simulation studies, that considered how the regulators respond to typical daily fluctuations in load throughout a distribution system [6,7], show that careful consideration needs to be given to settings for the relays under the varying load conditions encountered. Study system Distribution network Fig. 1 shows the system, part of a distribution network in the upper South Coast region of KwaZulu-Natal, comprising an 88 kv substation at N which feeds three separate Fig. 2: Phasor diagram showing the effects of circulating current. energize - April Page 16

2 loads (Fig. 2). This forms the basis of the socalled Δcosϕ algorithm used by the relays to regulate circulating current [1, 2]. The algorithm monitors voltage and current at the secondary terminals of the transformer and calculates the power factor cosϕ act of the network as seen by that transformer The difference between this measured power factor and the actual power factor of the network at that point (entered as a setting cosϕ set in the relay) is used as an indirect measurement of the presence of circulating reactive current in the transformer as follows: I CIRC = I T sinϕ act I T sinϕ set (1) Fig. 3: Simplified block diagram of the relay s voltage and circulating current control algorithms. Fig. 4: System response following reconnection of the transformer at S (Δcosϕ control disabled). substations U, S and W. Each of these substations has a 20 MVA, 88/22 kv on-load tap-changing transformer supplying local loads (L 1, L 2 and L 3 ). Substations U, S and W also supply switching station E and substation F via 22 kv feeders which supply local loads L 4 and L 5 respectively. The tap position on each transformer, T 1, T 2 and T 3, is controlled by its own relay. The circulating current problem If control of the secondary voltages at each transformer is carried out independently(by changing the tap position and hence turns ratio), when T 1 is at a higher tap position than T 2, it will have a higher internal voltage in its secondary winding than T 2, driving circulating current from T 1 to T 2 via the two closed paths between substations U and S. This will be almost entirely reactive in nature, since the impedance in the closed paths is predominantly reactive. The phasor diagram in Fig. 2 shows that circulating reactive current adds to load current supplied by transformer T 1, but is subtracted from load current supplied by transformer T 2, causing the internal volt drop in transformer T 1 to increase, and that in transformer T 2 to decrease. This distortion in the voltage regulation and loading of the two transformers can cause transformer T 1 to tap up even further (to overcome its increased internal volt drop) thereby increasing the circulating current and worsening the problem. The regulating relay and its settings A symptom of circulating current flow is a variation in the power factor at the transformer secondaries from the true power factor of the distribution system and The Δcosϕ algorithm then generates two error signals, Y U and Y P [1] : Y U = (U act U set ) ΔU perm (2) Y P = I CIRC /I CIRC perm (3) where U act and U set are actual and desired (setpoint) values of transformer secondary voltage, and I CIRC perm and ΔU perm are the permissible circulating current and transformer secondary voltage regulation respectively. Error signals for voltage and circulating current are combined into a single error signa, Y, as follows Y = Y U + Y P (4) U s e o f t h i s s i n g l e e r r o r s i g n a l, Y, t o t a p u p t h e t r a n s f o r m e r (when Y < 1,0) or tap down the transformer (when Y > - 1,0) allows both voltage regulation and circulating reactive current to be controlled independently within their permissible deviations determined by the user settings in the Δcosϕ control algorithm [1]. Fig. 3 shows a simplified block diagram of the relay s voltage and circulating current control algorithms illustrating the user-specified settings required. The user designed settings are those inputs shown enclosed in hexagonal polygons in the block diagram, whereas all other inputs represent measurements made (directly or indirectly) by the relay. When designing the settings for these regulators, the U set and ΔU perm values are chosen as for a conventional voltage regulator. In the distribution network being considered, the utility practice is to choose U set to be equal to 103% of the nominal transformer secondary voltage (to allow for line volt drop downstream in the medium voltage network) and to set ΔU perm at 1,1% of U set. When choosing settings for the circulating current control algorithms, there is no established local utility practice to rely on. The manufacturer s recommendation [2] is that the value for I CIRC perm at each transformer be set to a minimum of 60% of the circulating current measured when that transformer s tap setting differs from those of the other transformers by two positions. energize - April Page 17

3 The network power factor setting, cosϕ set, at each transformer should, theoretically, correspond to the correct power factor of the distribution system and its loads, when there is no circulating current flowing between transformers, because any measured changes in the network power factor away from cosϕ set setpoints is used by the relay to sense circulating current in its Δcosϕ algorithm [Eqn. 1]. Under practical conditions, these correct values of network power factor can be expected to change over time (even when there is no circulating current). The choice of cosϕ set therefore requires some care, as will be demonstrated in the results. The real-time simulator The real-time digital simulator (RTDS) [3] is a multiprocessor computing platform designed to allow detailed mathematical models of power systems to be analysed in real-time, as well as power system controller hardware to interact with, and control (in closed-loop) the power system plant represented in the real-time simulation model. In the first phase of the study, three separate regulating relays were used in a detailed, hardware-in-loop study of the system shown in Fig. 1. The distribution system was modelled on the RTDS simulator, while the three hardware relays performed the closed-loop control of the transformer tap positions of the simulated system in real-time. In the second phase, a software model of the regulating relay was incorporated (ie. the entire system and its relay control was modelled on the RTDS). This study was carried out to assess the feasibility of developing models of the relay for other simulation tools. Figs. 4 and 5 show the results of two hardware-in loop real-time simulator studies for a typical network event. In both, the transformer at substation S was initially disconnected (i.e. circuit breaker CBS in Fig. 1 was initially open). The regulators at the remaining two transformers were allowed to adjust their tap positions and reach a satisfactory steady-state condition. The tap changer at S was then manually set to its nominal setting (position 5), and the transformer was reconnected. This test was carried out both with and without Δcosϕ control enabled on all relays. Fig. 4 shows the response of the system following the r econnection of the transformer at S with Δcosϕ control disabled on all regulators. Fig. 5 shows the response to the same event with Δcosϕ control enabled. The figures show the response of voltage and reactive power output measured at the secondary terminals of the transformer, as well as the tap position of each transformer at substations U, S and W. The two transformers initially in service Fig. 5: System response following reconnection of the transformer at S (Δcosϕ control enabled). (U and W) start off at relatively high tap positions (12 to 13) since they are under heavy loading conditions due to the absence of the transformer at S. In both studies when the transformer at S is reconnected, its voltage initially decreases as it comes under load, and its tap position is increased over time by its regulating relay to return to within permissible range. However, comparison of Figs. 4 and 5 shows that the extent to which the tap position of transformer S is increased is quite different depending on whether or not the Δcosϕ control is enabled. With no Δcosϕ control (Fig. 4) the regulator at S only raises the tap setting to position 9, whereas with Δcosϕ control (Fig. 5) the tap setting is raised to position 12. The behaviour of the regulators at U and W is noticeably different with and without Fig. 6: Actual time varying loads: (a) at L 1 ; (b) at L 2. the Δcosϕ control enabled: with no Δcosϕ control (Fig. 4) there is no change in tap setting at W, and the tap setting at U is increased to position 14. With Δcosϕ control (Fig. 5) both U and W tap down. With Δcosϕ control employed, all three transformers adjust their tap settings to approximately the same positions following the reconnection of the transformer at S; however, without Δcosϕ control employed, the final tap positions of the three transformers are markedly different. With no Δcosϕ control, the loading on both transformers U and W increases, despite there being no change in the actual (customer) loads at L 1 to L 2. This is caused by the circulating reactive current supplied to transformer S, that enables it to reach its set point value of secondary voltage without having to move to a high energize - April Page 18

4 tap position, thereby reducing the share of the system load it carries. When Δcosϕ control is employed, each regulator acts to minimise transformer voltage regulation and circulating current. In Fig. 5 the regulators at U and W decrease the tap settings of their transformers at some time after the transformer at S is reconnected. These changes reduce the voltages at these transformers (i.e. move them away from their voltage set points), and also reduce the circulating reactive current flowing out of U and W into S. Reduction in circulating reactive current flowing into S means that the regulator at S has to carry out a greater number of increases in tap position to restore the voltage at S to its set point value. All three transformers still return to permissible voltage levels, with no significant circulating currents flowing between them; at nearly the same tap positions; carr ying approximately the same load. Variations in network loads Figs. 4 and 5 demonstrate how hardwarein-loop real-time simulator studies are able to predict the impact of regulating relays control actions following significant network changes. Within a time frame of several minutes, it is reasonable to assume that the loads at L 1 have fixed magnitude and power factor. Under such conditions, each relay correctly interprets the change in the power factor at its transformer s secondary terminals as being due to circulating current. However, over a longer time frame, the power factor measured at each transformer could also change with genuine variations in the load conditions at L 1. In such cases, the relays Δcosϕ algorithms may misinterpret real changes in power factor as the presence of circulating currents and respond inappropriately. To study the behaviour of the Δcosϕ algorithm under realistic network conditions, data was gathered on the behaviour of the loads, with the assistance of Eskom Distribution personnel. The behaviour of the lumped loads at L 1 was determined for two typical 24-hour periods, in midsummer and mid-winter. In addition, customised models and techniques were developed for the RTDS to allow the actual time-varying loads at L 1 to be replicated during the real-time simulation to study the response of the relays. Fig. 6 shows the active and reactive power variations and power factor at two of the five loads, L 1 and L 2, over a 24-hour period. During a typical daily load cycle, the active component of load varies considerably whilst there is much less variation in the reactive component, and consequently the power factors of loads L 1 Fig. 7: Real-time simulator study to investigate the response of hardware relays to the actual 24-hour load cycle in the distribution system; fixed cosϕ set values designed for conditions at t = 10 hours. and L 2 vary between 0,87 and 0,98 (loads L 3 show similar 24-hour trends). Relay response to time-varying loads Fixed network power factor settings The real-time model of the system was then run over an extended time frame to assess the performance of the relays under varying load conditions. Customwritten, time-varying load components were used at each lumped load (L 1 ) to reproduce the known variation in these loads in a 24-hour load cycle. Fig. 7 shows the results of one such study where there has been no disturbance to the topology of the network to initiate tap changes: the regulators each adjust their tap positions in response to the normal variation in daily load. The network power factor setting cosϕ set in each relay was set at a fixed value corresponding to the power factor seen by that regulator s transformer at time t = 10 hours. Choosing this fixed cosϕ set value results in a setting close to the actual time varying network power factor for the longest possible period during the daily load cycle: Fig. 6 shows that the individual load power factors remain at, or near to, their values at time t=10 hours for an approximately 10-hour period of the day. The results in Fig. 7 confirm that with fixed settings for cosϕ set, use of the Δcosϕ algorithm with time-varying loads could cause undesirable behaviour. During the period when the relays cosϕ set settings are sufficiently close to the conditions in the network (8 18 hours) the regulators maintain the transformer secondar y voltages within the permissible deviation (indicated by the dotted lines on the plots) and there is no circulating current (transformers at the same tap positions at all times). However, under very light load conditions (0 5 hours) the network power factor is much lower than the fixed settings, and the regulators at all three transformers misinterpret this low network power factor as being due to circulating current, resulting in a large negative value of YP. This (incorrect) negative error YP in circulating current is added to the genuine error Y U in secondary voltage at each transformer to give a combined error signal Y that incorrectly lies within the permissible deviation (±1) (the permissible deviations in Y are also shown by dotted lines on the plots). Consequently, each transformer s secondary voltage remains lower than the minimum permissible value during the period 0 5 hours because of the incorrectly determined error in circulating current. Similarly, during the peak-load period of the daily load cycle (18 21 hours) the network power factor is higher than the fixed cosϕ set values in each regulator. The regulators misinterpret this high network power factor as being due to circulating current, this time resulting in a large positive value of Y P ; this incorrect positive error Y P swamps the genuine negative error Y U in secondary voltage so that, although the combined error Y lies within its permissible energize - April Page 20

5 deviation, the transformer voltages remain higher than is permissible during this threehour period. It should be noted that the error Y P in circulating current is a result of the set-point network power factor value not being updated to track varying load conditions, and not as a result of actual circulating current flow (there are no differences in tap positions between transformers at any time during the day and hence no actual circulating currents). Contact Prof. Bruce Rigby, UKZN, Tel , brigby@ukzn.ac.za v energize - April Page 21

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods Proceedings of the th WSEAS International Conference on Power Systems, Beijing, China, September -, 200 Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

ENHANCING THE PERFORMANCE OF DISTANCE PROTECTION RELAYS UNDER PRACTICAL OPERATING CONDITIONS

ENHANCING THE PERFORMANCE OF DISTANCE PROTECTION RELAYS UNDER PRACTICAL OPERATING CONDITIONS ENHANCING THE PERFORMANCE OF DISTANCE PROTECTION RELAYS UNDER PRACTICAL OPERATING CONDITIONS by Kerrylynn Rochelle Pillay Submitted in fulfilment of the academic requirements for the Master of Science

More information

Relay-assisted commissioning

Relay-assisted commissioning Relay-assisted commissioning by Casper Labuschagne and Normann Fischer, Schweitzer Engineering Laboratories (SEL) Power transformer differential relays were among the first protection relays to use digital

More information

Voltage Sag and Swell Mitigation Using Dynamic Voltage Restore (DVR)

Voltage Sag and Swell Mitigation Using Dynamic Voltage Restore (DVR) Voltage Sag and Swell Mitigation Using Dynamic Voltage Restore (DVR) Mr. A. S. Patil Mr. S. K. Patil Department of Electrical Engg. Department of Electrical Engg. I. C. R. E. Gargoti I. C. R. E. Gargoti

More information

MODELLING AND ANALYSIS OF THE ENHANCED TAPP SCHEME FOR DISTRIBUTION NETWORKS

MODELLING AND ANALYSIS OF THE ENHANCED TAPP SCHEME FOR DISTRIBUTION NETWORKS MODELLIN AND ANALYSIS OF THE ENHANCED TAPP SCHEME FOR DISTRIBUTION NETWORKS Maciej Fila Brunel University/EDF Energy, UK maciej.fila@brunel.ac.uk areth A. Taylor Brunel Institute of Power Systems Brunel

More information

Hamdy Faramawy Senior Application Specialist ABB Sweden

Hamdy Faramawy Senior Application Specialist ABB Sweden Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

IMPLEMENTATION OF ADVANCED DISTRIBUTION AUTOMATION IN U.S.A. UTILITIES

IMPLEMENTATION OF ADVANCED DISTRIBUTION AUTOMATION IN U.S.A. UTILITIES IMPLEMENTATION OF ADVANCED DISTRIBUTION AUTOMATION IN U.S.A. UTILITIES (Summary) N S Markushevich and A P Berman, C J Jensen, J C Clemmer Utility Consulting International, JEA, OG&E Electric Services,

More information

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1)

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1) Dynamics and Control of Distributed Power Systems Fuel cell power system connection Ian A. Hiskens University of Wisconsin-Madison ACC Workshop June 12, 2006 This topology is fairly standard, though there

More information

Phase Shifting Transformers. Presented by

Phase Shifting Transformers. Presented by Phase Shifting Transformers Presented by Phase Shifting Transformers (PST s) (a.k.a. Phase Angle Regulators) VS φ S P V V S = X L L X L sin( φ φ ) L S VL φ L PST s are power flow control devices between

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller

Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer Anura Perera, Paul Keller System Operator - Eskom Transmission Introduction During the design phase of

More information

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1.1 INTRODUCTION 2 WFPS1.2 OBJECTIVE 2 WFPS1.3 SCOPE 3 WFPS1.4 FAULT RIDE THROUGH REQUIREMENTS 4 WFPS1.5 FREQUENCY REQUIREMENTS 5 WFPS1.6 VOLTAGE

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

CHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses

CHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses CHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses 8.1 Introduction The present level of Transmission and Distribution (T & D) losses in Indian power system is estimated

More information

Advanced Test Equipment Rentals ATEC (2832) CP RC. Resonance circuit for GIS testing

Advanced Test Equipment Rentals ATEC (2832) CP RC. Resonance circuit for GIS testing Established 1981 Advanced Test Equipment Rentals www.atecorp.com 800-404-ATEC (2832) CP RC Resonance circuit for GIS testing A new approach to testing gas-insulated switchgear Testing gas-insulated switchgear

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Differential Protection with REF 542plus Feeder Terminal

Differential Protection with REF 542plus Feeder Terminal Differential Protection with REF 542plus Application and Setting Guide kansikuva_bw 1MRS 756281 Issued: 09.01.2007 Version: A Differential Protection with REF 542plus Application and Setting Guide Contents:

More information

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Unit Auxiliary Transformer (UAT) Relay Loadability Report Background and Objective Reliability Standard, PRC 025 1 Generator Relay Loadability (standard), developed under NERC Project 2010 13.2 Phase 2 of Relay Loadability: Generation, was adopted by the NERC

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

Advanced Paralleling of LTC Transformers by VAR TM Method

Advanced Paralleling of LTC Transformers by VAR TM Method TAPCHANGER CONTROLS Application Note #24 Advanced Paralleling of LTC Transformers by VAR TM Method 1.0 ABSTRACT Beckwith Electric Company Application Note #11, Introduction of Paralleling of LTC Transformers

More information

Distance Relay Response to Transformer Energization: Problems and Solutions

Distance Relay Response to Transformer Energization: Problems and Solutions 1 Distance Relay Response to Transformer Energization: Problems and Solutions Joe Mooney, P.E. and Satish Samineni, Schweitzer Engineering Laboratories Abstract Modern distance relays use various filtering

More information

Impact of transient saturation of Current Transformer during cyclic operations Analysis and Diagnosis

Impact of transient saturation of Current Transformer during cyclic operations Analysis and Diagnosis 1 Impact of transient saturation of Current Transformer during cyclic operations Analysis and Diagnosis BK Pandey, DGM(OS-Elect) Venkateswara Rao Bitra, Manager (EMD Simhadri) 1.0 Introduction: Current

More information

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation Technical Requirements for Interconnection and Parallel Operation of Distributed Generation Single Phase

More information

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur Lecture - 10 Transmission Line Steady State Operation Voltage Control (Contd.) Welcome

More information

Accurate Synchrophasor Estimation to Support the Islanding Maneuver of Active Distribution Networks

Accurate Synchrophasor Estimation to Support the Islanding Maneuver of Active Distribution Networks Working Group Meeting June 5-6, 2012 Accurate Synchrophasor Estimation to Support the Islanding Maneuver of Active Distribution Networks Prof. Mario Paolone EPFL, Switzerland - Distributed Electrical Systems

More information

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Cork Institute of Technology Bachelor of Science (Honours) in Electrical Power Systems - Award Instructions Answer FIVE questions. (EELPS_8_Y4) Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Examiners:

More information

Substation Testing and Commissioning: Power Transformer Through Fault Test

Substation Testing and Commissioning: Power Transformer Through Fault Test 1 Substation Testing and Commissioning: Power Transformer Through Fault Test M. Talebi, Member, IEEE, Power Grid Engineering Y. Unludag Electric Power System Abstract This paper reviews the advantage of

More information

MV network design & devices selection EXERCISE BOOK

MV network design & devices selection EXERCISE BOOK MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester

More information

CHAPTER 4 PV-UPQC BASED HARMONICS REDUCTION IN POWER DISTRIBUTION SYSTEMS

CHAPTER 4 PV-UPQC BASED HARMONICS REDUCTION IN POWER DISTRIBUTION SYSTEMS 66 CHAPTER 4 PV-UPQC BASED HARMONICS REDUCTION IN POWER DISTRIBUTION SYSTEMS INTRODUCTION The use of electronic controllers in the electric power supply system has become very common. These electronic

More information

ECE 528 Understanding Power Quality

ECE 528 Understanding Power Quality ECE 528 Understanding Power Quality http://www.ece.uidaho.edu/ee/power/ece528/ Paul Ortmann portmann@uidaho.edu 208-733-7972 (voice) Lecture 22 1 Today Homework 5 questions Homework 6 discussion More on

More information

ADVANCED VECTOR SHIFT ALGORITHM FOR ISLANDING DETECTION

ADVANCED VECTOR SHIFT ALGORITHM FOR ISLANDING DETECTION 23 rd International Conference on Electricity Distribution Lyon, 5-8 June 25 Paper 48 ADVANCED VECT SHIFT ALGITHM F ISLANDING DETECTION Murali KANDAKATLA Hannu LAAKSONEN Sudheer BONELA ABB GISL India ABB

More information

Solution for Effect of Zero Sequence Currents on Y-Y Transformer Differential Protection

Solution for Effect of Zero Sequence Currents on Y-Y Transformer Differential Protection ABSTRACT National conference on Engineering Innovations and Solutions (NCEIS 2018) International Journal of Scientific Research in Computer Science, Engineering and Information Technology 2018 IJSRCSEIT

More information

Back to the Basics Current Transformer (CT) Testing

Back to the Basics Current Transformer (CT) Testing Back to the Basics Current Transformer (CT) Testing As test equipment becomes more sophisticated with better features and accuracy, we risk turning our field personnel into test set operators instead of

More information

SYNCHRONISING AND VOLTAGE SELECTION

SYNCHRONISING AND VOLTAGE SELECTION SYNCHRONISING AND VOLTAGE SELECTION This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for any

More information

MODELING THE EFFECTIVENESS OF POWER ELECTRONICS BASED VOLTAGE REGULATORS ON DISTRIBUTION VOLTAGE DISTURBANCES

MODELING THE EFFECTIVENESS OF POWER ELECTRONICS BASED VOLTAGE REGULATORS ON DISTRIBUTION VOLTAGE DISTURBANCES MODELING THE EFFECTIVENESS OF POWER ELECTRONICS BASED VOLTAGE REGULATORS ON DISTRIBUTION VOLTAGE DISTURBANCES James SIMONELLI Olivia LEITERMANN Jing HUANG Gridco Systems USA Gridco Systems USA Gridco Systems

More information

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections

More information

Experience with Connecting Offshore Wind Farms to the Grid

Experience with Connecting Offshore Wind Farms to the Grid Oct.26-28, 2011, Thailand PL-22 CIGRE-AORC 2011 www.cigre-aorc.com Experience with Connecting Offshore Wind Farms to the Grid J. FINN 1, A. SHAFIU 1,P. GLAUBITZ 2, J. LOTTES 2, P. RUDENKO 2, M: STEGER

More information

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels

More information

Discussion on the Deterministic Approaches for Evaluating the Voltage Deviation due to Distributed Generation

Discussion on the Deterministic Approaches for Evaluating the Voltage Deviation due to Distributed Generation Discussion on the Deterministic Approaches for Evaluating the Voltage Deviation due to Distributed Generation TSAI-HSIANG CHEN a NIEN-CHE YANG b Department of Electrical Engineering National Taiwan University

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

CP CU1. Coupling unit for line and ground testing

CP CU1. Coupling unit for line and ground testing CP CU1 Coupling unit for line and ground testing Line and ground test system CPC 100 The CPC 100 is a multifunctional test set for primary assets. When combined with the CP CU1 it covers the following

More information

How to maximize reliability using an alternative distribution system for critical loads

How to maximize reliability using an alternative distribution system for critical loads White Paper WP024001EN How to maximize reliability using an alternative distribution system for critical loads Executive summary The electric power industry has several different distribution topologies

More information

A U T O E S C M E N U

A U T O E S C M E N U QUICK GUIDE 4 - /,...!. ". #? = ) 7 6-5 + - 7 H A JA + Voltage Regulator REG-D /DA Short-Form Operating Manual Issue 09.11.2004 Copyright 2004 by A. Eberle GmbH & Co. KG. All rights reserved. Published

More information

Line protection with transformer in the protection zone

Line protection with transformer in the protection zone Line protection with transformer in the protection zone www.siemens.com/siprotec5 Three-end line protection with transformer in the protection range SIPROTEC 5 Application Three-end line protection with

More information

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014 Constant Terminal Voltage Working Group Meeting 4 19 th September 014 Overview Options summary System under investigation Options analysis Discussion Options Option 1 Constant Terminal Voltage controlled

More information

Fast Protection of Strong Power System With Fault Current Limiters and PLL - Aided Fault Detection

Fast Protection of Strong Power System With Fault Current Limiters and PLL - Aided Fault Detection Fast Protection of Strong Power System With Fault Current Limiters and PLL - Aided Fault Detection Shaik Abdul Razak P.G. Scholar, Dept. of EEE Ch Durga Prasad P.G.Scholar, Dept. of EEE UDJV Prasad Associate

More information

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström EH27401 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsn@ics.kth.se 1 Course map 2 Outline 1. Power System Topologies Transmission Grids vs Distribution grids Radial grids

More information

Keywords: Transformer, differential protection, fuzzy rules, inrush current. 1. Conventional Protection Scheme For Power Transformer

Keywords: Transformer, differential protection, fuzzy rules, inrush current. 1. Conventional Protection Scheme For Power Transformer Vol. 3 Issue 2, February-2014, pp: (69-75), Impact Factor: 1.252, Available online at: www.erpublications.com Modeling and Simulation of Modern Digital Differential Protection Scheme of Power Transformer

More information

FLC based AVC Relay with Newton Raphson Load Flow for Voltage Control in Distribution Network

FLC based AVC Relay with Newton Raphson Load Flow for Voltage Control in Distribution Network International Journal of Control Theory and Applications ISSN : 0974-5572 International Science Press Volume 10 Number 16 2017 FLC based AVC Relay with Newton Raphson Load Flow for Voltage Control in Distribution

More information

Fault Localization using Wavelet Transforms in 132kV Transmission Lines

Fault Localization using Wavelet Transforms in 132kV Transmission Lines ENGINEER - Vo). XXXXII, No. 04, pp. [95-104], 2009 The Institution of Engineers, Sri Lanka Fault Localization using Wavelet Transforms in 132kV Transmission Lines J.V.U.P. Jayatunga, P.S.N. De Silva and

More information

Non-detection zone of LOM protection for converter connected wind turbines

Non-detection zone of LOM protection for converter connected wind turbines - 1 - Non-detection zone of LOM protection for converter connected wind turbines Ontrei Raipala, Tampere University of Technology, Finland Table of contents Table of contents... 1 Introduction... 2 Loss

More information

Beyond the Knee Point: A Practical Guide to CT Saturation

Beyond the Knee Point: A Practical Guide to CT Saturation Beyond the Knee Point: A Practical Guide to CT Saturation Ariana Hargrave, Michael J. Thompson, and Brad Heilman, Schweitzer Engineering Laboratories, Inc. Abstract Current transformer (CT) saturation,

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

g GE POWER MANAGEMENT

g GE POWER MANAGEMENT 745 FREQUENTLY ASKED QUESTIONS 1 I get a communication error with the relay when I try to store a setpoint. This error can occur for several different reasons. First of all, verify that the address is

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Digital Simulation of Thyristor Controlled Interphase Power Control Technology (TC- IPC) to limit the fault currents

Digital Simulation of Thyristor Controlled Interphase Power Control Technology (TC- IPC) to limit the fault currents Digital Simulation of Thyristor Controlled Interphase Power Control Technology (TC- IPC) to limit the fault currents V.V.Satyanarayana Rao.R #1, S.Rama Reddy *2 # EEE Department,SCSVMV University Kanchipuram,India

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

Voltage Sag Index Calculation Using an Electromagnetic Transients Program

Voltage Sag Index Calculation Using an Electromagnetic Transients Program International Conference on Power Systems Transients IPST 3 in New Orleans, USA Voltage Sag Index Calculation Using an Electromagnetic Transients Program Juan A. Martinez-Velasco, Jacinto Martin-Arnedo

More information

ISSN: Page 298

ISSN: Page 298 Sizing Current Transformers Rating To Enhance Digital Relay Operations Using Advanced Saturation Voltage Model *J.O. Aibangbee 1 and S.O. Onohaebi 2 *Department of Electrical &Computer Engineering, Bells

More information

Z-SOURCE INVERTER BASED DVR FOR VOLTAGE SAG/SWELL MITIGATION

Z-SOURCE INVERTER BASED DVR FOR VOLTAGE SAG/SWELL MITIGATION Z-SOURCE INVERTER BASED DVR FOR VOLTAGE SAG/SWELL MITIGATION 1 Arsha.S.Chandran, 2 Priya Lenin 1 PG Scholar, 2 Assistant Professor 1 Electrical & Electronics Engineering 1 Mohandas College of Engineering

More information

SECTION LOW VOLTAGE ACTIVE HARMONIC FILTER SYSTEM NEMA 1 ENCLOSED

SECTION LOW VOLTAGE ACTIVE HARMONIC FILTER SYSTEM NEMA 1 ENCLOSED SECTION 16280 LOW VOLTAGE ACTIVE HARMONIC FILTER SYSTEM NEMA 1 ENCLOSED PART 1 - GENERAL 1.1 SUMMARY This specification defines the requirements for active harmonic filter systems in order to meet IEEE-519-2014

More information

Transformer energisation after network blackout

Transformer energisation after network blackout Transformer energisation after network blackout Impact on network restoration and improvement of its process ABSTRACT According to ENTSO-E Network policy 5, responsibility for system restoration after

More information

ABB Automation, Inc. Substation Automation & Protection Division Coral Springs, FL Allentown, PA

ABB Automation, Inc. Substation Automation & Protection Division Coral Springs, FL Allentown, PA ABB Automation, Inc. Substation Automation & Protection Division Coral Springs, FL Allentown, PA Instruction Leaflet 41-348.1H Effective: November 1997 Supersedes I.L. I.L. 41-348.1G, Dated January 1985

More information

ON-SITE TESTING OF SPECIAL TRANSFORMERS

ON-SITE TESTING OF SPECIAL TRANSFORMERS ON-SITE TESTING OF SPECIAL TRANSFORMERS Simanand GANDHI JEYARAJ, Megger Ltd, UK, Simanand.gandhi@megger.com, Robert MILNE, UK Power Networks, UK, robert.milne83@googlemail.com Grant MITCHELL, Transmag

More information

Investigation and Correction of Phase Shift Delays in Power Hardware in Loop Real-Time Digital Simulation Testing of Power Electronic Converters

Investigation and Correction of Phase Shift Delays in Power Hardware in Loop Real-Time Digital Simulation Testing of Power Electronic Converters 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2015 Grid of the Future Symposium Investigation and Correction of Phase Shift Delays in Power Hardware in Loop Real-Time

More information

INVESTIGATION INTO THE HARMONIC BEHAVIOUR OF MULTIPULSE CONVERTER SYSTEMS IN AN ALUMINIUM SMELTER

INVESTIGATION INTO THE HARMONIC BEHAVIOUR OF MULTIPULSE CONVERTER SYSTEMS IN AN ALUMINIUM SMELTER INVESTIGATION INTO THE HARMONIC BEHAVIOUR OF MULTIPULSE CONVERTER SYSTEMS IN AN ALUMINIUM SMELTER Abstract S Perera, V J Gosbell, D Mannix, Integral Energy Power Quality Centre School of Electrical, Computer

More information

Application Example Document ID: SA Rev. - September 24, 2004

Application Example Document ID: SA Rev. - September 24, 2004 Application Example Rev. - September 24, 2004 1 Summary Phasor based control of braking resistors A case study applied to large power oscillations experienced in the Swedish grid 1997 Phasor measurement,

More information

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE The following is PG&E's procedure for pre-energization inspections. For PG&E to provide the Load

More information

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP Kiran V. Natkar 1, Naveen Kumar 2 1 Student, M.E., Electrical Power System, MSS CET/ Dr. B.A.M. University, (India) 2 Electrical Power System,

More information

BED INTERCONNECTION TECHNICAL REQUIREMENTS

BED INTERCONNECTION TECHNICAL REQUIREMENTS BED INTERCONNECTION TECHNICAL REQUIREMENTS By Enis Šehović, P.E. 2/11/2016 Revised 5/19/2016 A. TABLE OF CONTENTS B. Interconnection Processes... 2 1. Vermont Public Service Board (PSB) Rule 5.500... 2

More information

6 Steps to Basic Voltage Regulation

6 Steps to Basic Voltage Regulation 6 Steps to Basic Voltage Regulation The following 6 settings are all that need to be made on the A.Eberle REG-D or REG-DA to enable basic voltage regulation. These settings can be made either by using

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 PRC-025-1 Generator Relay Loadability A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities

More information

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors May 11, 2010 Slide 1 Why phase-shifting transformers

More information

Phase Shifter Application Workshop. Siemens Energy, Inc.

Phase Shifter Application Workshop. Siemens Energy, Inc. Phase Shifter Application Workshop Siemens Energy, Inc. PJM Power Pool, March, 2015 siemens.com/energy Phase Shifter Application Workshop Phase Shifting Transformers Principles, Design Aspects and Operation

More information

APPLICATION NOTE - 018

APPLICATION NOTE - 018 APPLICATION NOTE - 018 Power Transformers Background Power Transformers are used within an AC power distribution systems to increase or decrease the operating voltage to achieve the optimum transmission

More information

INSTRUCTIONS FOR THE COMMISSIONING AND MAINTENANCE OF DIGITAL GENERATOR PROTECTION 3 I - PRINCIPLES AND APPLICATIONS 4 on 5 6 7 Figure 5 - Inverse time curve (N1) 8 9 1 0 1 1 1 2 1 3 All relays are delivered

More information

SIMULATION OF D-STATCOM AND DVR IN POWER SYSTEMS

SIMULATION OF D-STATCOM AND DVR IN POWER SYSTEMS SIMUATION OF D-STATCOM AND DVR IN POWER SYSTEMS S.V Ravi Kumar 1 and S. Siva Nagaraju 1 1 J.N.T.U. College of Engineering, KAKINADA, A.P, India E-mail: ravijntu@gmail.com ABSTRACT A Power quality problem

More information

Real-time Decentralized Voltage Stability Monitoring and Protection against Voltage Collapse

Real-time Decentralized Voltage Stability Monitoring and Protection against Voltage Collapse Real-time Decentralized Voltage Stability Monitoring and Protection against Voltage Collapse Costas Vournas National Technical University of Athens vournas@power.ece.ntua.gr 1 Outline Introduction to Voltage

More information

Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss

Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss Siemens AG, EV NP3 P.O. Box 3220 91050 Erlangen, Germany e-mail: Michael.Weinhold@erls04.siemens.de

More information

Transformer & Induction M/C

Transformer & Induction M/C UNIT- 2 SINGLE-PHASE TRANSFORMERS 1. Draw equivalent circuit of a single phase transformer referring the primary side quantities to secondary and explain? (July/Aug - 2012) (Dec 2012) (June/July 2014)

More information

Power Transformer Ratings' Calculation and Analysis - IEEE C

Power Transformer Ratings' Calculation and Analysis - IEEE C Power Transformer Ratings' Calculation and Analysis - IEEE C57.91-1995 Course No. E-3058 Credit: 3 PDH 2017 Decatur Professional Development, LLC. All rights reserved. Power Transformer Ratings Calculation

More information

Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices

Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices M. Sanaye-Pasand, R. Aghazadeh Applied Electromagnetics Research Excellence Center, Electrical & Computer Engineering

More information

Optimum dimensioning of a flicker compensator in three-phase electric-arc furnaces supply systems

Optimum dimensioning of a flicker compensator in three-phase electric-arc furnaces supply systems Optimum dimensioning of a flicker compensator in three-phase electric-arc furnaces supply systems Abstract Three-phase electric arc furnaces, the design power ratings of which are in many cases above 100

More information

Table of Contents. Introduction... 1

Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...

More information

Protection of Electrical Networks. Christophe Prévé

Protection of Electrical Networks. Christophe Prévé Protection of Electrical Networks Christophe Prévé This Page Intentionally Left Blank Protection of Electrical Networks This Page Intentionally Left Blank Protection of Electrical Networks Christophe Prévé

More information

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH Requirements for Offshore Grid Connections in the Grid of TenneT TSO GmbH Bernecker Straße 70, 95448 Bayreuth Updated: 5th October 2010 1/10 Requirements for Offshore Grid Connections in the Grid of TenneT

More information

Electrical Protection System Design and Operation

Electrical Protection System Design and Operation ELEC9713 Industrial and Commercial Power Systems Electrical Protection System Design and Operation 1. Function of Electrical Protection Systems The three primary aims of overcurrent electrical protection

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Applicability 1 Section 502.8 applies to: (a) the legal owner of a generating unit: (i) connected to the transmission facilities in the balancing authority area

More information

TABLE OF CONTENT

TABLE OF CONTENT Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES

More information

Low Frequency Demand Disconnection Summary

Low Frequency Demand Disconnection Summary Low Frequency Demand Disconnection Summary This article assesses the suitability of current low frequency protection on the network as more distributed generation is connected to WPD s network. DSOF June

More information

Distance Protection of Cross-Bonded Transmission Cable-Systems

Distance Protection of Cross-Bonded Transmission Cable-Systems Downloaded from vbn.aau.dk on: April 19, 2019 Aalborg Universitet Distance Protection of Cross-Bonded Transmission Cable-Systems Bak, Claus Leth; F. Jensen, Christian Published in: Proceedings of the 12th

More information

UNIT-4 POWER QUALITY MONITORING

UNIT-4 POWER QUALITY MONITORING UNIT-4 POWER QUALITY MONITORING Terms and Definitions Spectrum analyzer Swept heterodyne technique FFT (or) digital technique tracking generator harmonic analyzer An instrument used for the analysis and

More information

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 Charles J. Mozina, Consultant Beckwith Electric Co., Inc. www.beckwithelectric.com I. Introduction During the 2003 blackout,

More information

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES C.E.T. Foote*, G.W. Ault*, J.R. McDonald*, A.J. Beddoes *University of Strathclyde, UK EA Technology Limited, UK c.foote@eee.strath.ac.uk

More information

, ,54 A

, ,54 A AEB5EN2 Ground fault Example Power line 22 kv has the partial capacity to the ground 4,3.0 F/km. Decide whether ground fault currents compensation is required if the line length is 30 km. We calculate

More information

Power systems 2: Transformation

Power systems 2: Transformation Power systems 2: Transformation Introduction In this series of articles, we will be looking at each of the main stages of the electrical power system in turn. s you will recall from our Introduction to

More information

UPQC (Unified Power Quality Conditioner)

UPQC (Unified Power Quality Conditioner) A Unified Power Quality Conditioner (UPQC) is a device that is similar in construction to a Unified Power Flow Conditioner (UPFC). The UPQC, just as in a UPFC, employs two voltage source inverters (VSIs)

More information