EXECUTIVE PEER EXCHANGE WORKSHOP

Size: px
Start display at page:

Download "EXECUTIVE PEER EXCHANGE WORKSHOP"

Transcription

1 MOTRACO PRESENTATION EXECUTIVE PEER EXCHANGE WORKSHOP June 2006, Johannesburg, South Africa

2 Politics and Historical Perspectives SADC treaty in August 1992 Peace in Mozambique in October 1992 and elections same year. Members of SADC sign in August 1995 the IGMOU that led to the establishment of the SAPP. In January 1997 GRM e GRSA signed an IGMOU for the development of hidro-electric potential and associated high voltage transmission lines in Moçambique. In March 1997 the GRM and Alusaf signed a Heads of fagreement tfor the establishment tof an aluminium i smelter in Mozambique. In June 1997 an electricity tariff for Mozal was agreed.

3 Creation of Motraco Problem: Eskom does not have a licence to sell electricity in Mozambique and EDM does not have sufficient transmission capacity to supply the smelter. Solution: Special Purpose Vehicle: Companhia de Transmissão de Moçambique, popularly known as Moçambique Transmission Company (MOTRACO), was registered in Moçambique in 1998.

4 Authorisations and Concessions In March 1998 GRM approved the Motraco project with certain fiscal benefits. Concession contracts t were entered into between Motraco and each of GRM, GRSA and GSW for: Contruction and ownership of transmission lines, Importation of energy for direct sales to Mozal Transportation of energy on behalf of EDM, SEB and ESKOM, Establishment of a fiber optic cable network on its transmission lines to ensure the reliability of electrical supplies to the aluminium smelter.

5 Concessions and Licences In Moçambique the Concession Contract between Motraco and GRM includes a transmission licence A transmission licence was issued to Motraco by SEB in April In RSA a transmission licence was issued by the National Energy Regulator. Concession fees are payable to GRM and GSW. A Joint Commission for Motraco (JCM) comprised of Dept. of Energy officials of GRM, GRSA and GSW exists.

6 ORGANISATION GRM, GRSA, GSW Eskom, 950MW + Eskom (O&M) Other EDM, ESKOM, SEB MOTRACO Equity, 39.5MUSD - SGM (6 Reps) + FC - 6 Board Members (NE) -7 employees, full time (Outsourcing strategy) Eskom, xmw (loop flow) SEB, 175MW EDM, 175MW + 250MW Mozal, 950MW +650MW 95% of total revenue Telecommunications Debt, 82MUSD EIB, JBIC, SBSA (Guaranteed by Eskom)

7 Motraco Head Office

8 MOTRACO Project Construction Trans Africa Projects managed all the contruction projects Principal contractors were ABB, Alstom, Siemens. The power transmission infrastructure comprises of: 2 x 400kV and 3 x 132kV power lines 2 x 100MVAr shunt reactors 1x 535MVAr & 1 x 344MVAr 400kV fixed series caps 2x 150MVAr, 400kV and 2 x 72MVAr, 275kV shunt caps 3 x 500MVA, 400/132kV power transformers 24 core OPGW fibre optic cables Maputo to Camden.

9 Cross-Border Transmission Network of Motraco Corumane PS Infulene 275kV 110kV Komatipoort 275kV MOZAMBIQUE Matola 275kV Arnot 400kV RSA SWAZILAND Maputo 400kV Mozal 132kV Camden 400kV Edwaleni 400kV LEGEND Transformer Capacitor Circuit Breaker Generating Station Transmission Line / Busbar

10 CROSS-BORDER TELECOMMUNICATIONS INFRASTRUCTURE KOMATIPOORT M RSA MOZAMBIQUE INFULENE M MAPUTO CITY ESKOM (JHB) M EDWALENI II M M M MOZAL CAMDEN MAPUTO SUBSTATION SEB RSA SWAZILAND (MBABANE) MOZAMBIQUE INTERNATIONAL BOUNDARY Eskom Digital Network FIBRE OPTIC CABLE M DIGITAL ADD-DROP MULTIPLEXER

11 400kV Transmission line Cross-Rope Tower

12 Transmission Line Access Road

13 400kV Transmission Line Servitude

14 400kV Line Tower Mast Down

15 400kV Series Capacitor Bank

16 400kV Tubular Busbars

17 400kV Switchgear

18 400kV Shunt Capacitor Bank

19 500MVA, 400/132kV Transformer

20 132kV Transmission lines (275kV Construction)

21 FINANCIAL PERFORMANCE: INCOME STATEMENT

22 FINANCIAL PERFORMANCE: ASSETS

23 FINANCIAL PERFORMANCE: LIABILITIES

24 CONCLUSION Motraco, as a creation resulting from workable partnerships between the public and private sectors is a unique, living and working role model for regional cooperation and integration. The End

IMPLICATIONS OF APPLYING DIFFERENT VAR SUPPORT TECHNOLOGIES IN THE ESKOM TRANSMISSION NETWORK WITH PARTICULAR EMPHASIS ON THE LIFECYCLE COST

IMPLICATIONS OF APPLYING DIFFERENT VAR SUPPORT TECHNOLOGIES IN THE ESKOM TRANSMISSION NETWORK WITH PARTICULAR EMPHASIS ON THE LIFECYCLE COST IMPLICATIONS OF APPLYING DIFFERENT VAR SUPPORT TECHNOLOGIES IN THE ESKOM TRANSMISSION NETWORK WITH PARTICULAR EMPHASIS ON THE LIFECYCLE COST Teboho Ken Ramorapeli A research report submitted to the Faculty

More information

General Technical Specifications of Frequency Converters for Tokyo-Chubu Interconnection Project

General Technical Specifications of Frequency Converters for Tokyo-Chubu Interconnection Project General Technical Specifications of Converters for Tokyo-Chubu Interconnection Project Note: It is possible that the contents of these specifications may be changed according to our detailed studies. Present

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision By Date V1D1 For Comments Yaoyu Huang October 27, 2016 V1 For Issuance Yaoyu Huang November 21, 2016 Section 5.3 updated Transformer

More information

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION ATTACHMENT - AESO FUNCTIONAL SPECIFICATION Functional Specification Revision History Revision Description of Revision By Date D1 For internal Comments Yaoyu Huang January 8, 2018 D2 For external Comments

More information

High voltage shunt capacitor banks HIGH VOLTAGE COMPENSATION AND HARMONIC FILTERING PRODUCTS

High voltage shunt capacitor banks HIGH VOLTAGE COMPENSATION AND HARMONIC FILTERING PRODUCTS High voltage shunt capacitor banks Alstom Grid high voltage shunt capacitor bank offering is divided in: By bank construction HV open rack capacitor banks HV enclosed capacitor banks By bank design HV

More information

ANNEXURE-I. Documents to be uploaded 1 Certificate of Registration with Industries 2 VAT Certificate 3 Service Tax Certificate

ANNEXURE-I. Documents to be uploaded 1 Certificate of Registration with Industries 2 VAT Certificate 3 Service Tax Certificate ANNEXURE-I Documents to be uploaded 1 Certificate of Registration with Industries 2 VAT Certificate 3 Service Tax Certificate 4 Excise Duty Registration Certificate 5 Pan Card 6 Approved Vendor Certificates

More information

Standard Prices for Generators 2010

Standard Prices for Generators 2010 Standard Prices for Generators 2010 Distribution System Operator ESB Networks Page 1 of 13 CONTENTS 1.0 Background...3 2.0 Standard Pricing Approach...3 Schedule of Charges for generators excluding VAT...6

More information

UTOPIA Historical Overview

UTOPIA Historical Overview UTOPIA Is a City-Owned Telecommunications Network In 2000 and 2001 multiple cities were receiving comments from their businesses and residents that internet services were too slow or inaccessible. Service

More information

INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H.

INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H. INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H. Aliche 1,2 nnamdi azikiwe university, awka, anambra state, nigeria.

More information

Analysis of a 405 km transmission line with series compensation

Analysis of a 405 km transmission line with series compensation Analysis of a 405 km transmission line with series compensation by Dr. Rupert Gouws, North-West University This paper presents an investigative case study and energy efficiency analysis of the 405 km,

More information

Blom ASA. Presentation at DnB NOR s SMB-seminar March 14th, CEO Dirk Blaauw

Blom ASA. Presentation at DnB NOR s SMB-seminar March 14th, CEO Dirk Blaauw Blom ASA Presentation at DnB NOR s SMB-seminar March 14th, 2007 CEO Dirk Blaauw Disclaimer Forward Looking Statements This presentation contains forward-looking statements that involve risks and uncertainties.

More information

RELEVANT ELECTRICAL STANDARDS

RELEVANT ELECTRICAL STANDARDS RELEVANT ELECTRICAL STANDARDS Issue 2 October 2014 Issue 2 September 2014 National Grid 2014 2014 Copyright owned by National Grid Electricity Transmission plc, all rights reserved. No part of this publication

More information

LLOYDS BANKING GROUP MATTERS RESERVED TO THE BOARDS (LLOYDS BANKING GROUP PLC, LLOYDS BANK PLC, BANK OF SCOTLAND PLC & HBOS PLC)

LLOYDS BANKING GROUP MATTERS RESERVED TO THE BOARDS (LLOYDS BANKING GROUP PLC, LLOYDS BANK PLC, BANK OF SCOTLAND PLC & HBOS PLC) LLOYDS BANKING GROUP MATTERS RESERVED TO THE BOARDS (LLOYDS BANKING GROUP PLC, LLOYDS BANK PLC, BANK OF SCOTLAND PLC & HBOS PLC) LLOYDS BANKING GROUP PLC, LLOYDS BANK PLC, BANK OF SCOTLAND PLC & HBOS PLC

More information

Afrosearch (Pty) Ltd P O Box Hatfield 0028 Tel (012) Fax (012)

Afrosearch (Pty) Ltd P O Box Hatfield 0028 Tel (012) Fax (012) Afrosearch (Pty) Ltd P O Box 13540 Hatfield 0028 Tel (012) 362 2908 Fax (012) 362 2463 Clr SP Mokoena 7 August 2007 Head: Community Services Greater Tubatse Municipality PO Box 206 BURGERSFORT 1150 Dear

More information

Action: Notice of an application for an order under sections 6(c), 12(d)(1)(J), and 57(c) of the

Action: Notice of an application for an order under sections 6(c), 12(d)(1)(J), and 57(c) of the This document is scheduled to be published in the Federal Register on 05/23/2014 and available online at http://federalregister.gov/a/2014-11965, and on FDsys.gov 8011-01p SECURITIES AND EXCHANGE COMMISSION

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee August 11, 2016 2016 RTEP Window #3 Anticipated Scope and Timeline Anticipated 2016 RTEP Window #3 Anticipated 2016 RTEP Window #3

More information

IMPROVING POWER QUALITY AND ENHANCING THE LIFE OF POWER EQUIPMENT, IN RAILWAY TSSs

IMPROVING POWER QUALITY AND ENHANCING THE LIFE OF POWER EQUIPMENT, IN RAILWAY TSSs IMPROVING POWER QUALITY AND ENHANCING THE LIFE OF POWER EQUIPMENT, IN RAILWAY TSSs Mr. P. Biswas, ABB ABSTRACT The Indian Railways employ single phase 25 kv Traction sub-station (TSS) for supplying power

More information

Power transformers. Shunt reactors Proven history for future success

Power transformers. Shunt reactors Proven history for future success Power transformers Shunt reactors Proven history for future success Shunt reactors an investment for today and for the future 2 Shunt reactors Improving power quality and reducing transmission costs Shunt

More information

POLICY PHILOSOPHY DEFINITIONS AC.2.11 INTELLECTUAL PROPERTY. Programs and Curriculum. APPROVED: Chair, on Behalf of SAIT s Board of Governors

POLICY PHILOSOPHY DEFINITIONS AC.2.11 INTELLECTUAL PROPERTY. Programs and Curriculum. APPROVED: Chair, on Behalf of SAIT s Board of Governors Section: Subject: Academic/Student (AC) Programs and Curriculum AC.2.11 INTELLECTUAL PROPERTY Legislation: Copyright Act (R.S.C., 1985, c.c-42); Patent Act (R.S.C., 1985, c.p-4); Trade-marks Act (R.S.C.

More information

European Charter for Access to Research Infrastructures - DRAFT

European Charter for Access to Research Infrastructures - DRAFT 13 May 2014 European Charter for Access to Research Infrastructures PREAMBLE - DRAFT Research Infrastructures are at the heart of the knowledge triangle of research, education and innovation and therefore

More information

RELEVANT ELECTRICAL STANDARDS

RELEVANT ELECTRICAL STANDARDS RELEVANT ELECTRICAL STANDARDS Issue 2 February 2014 National Grid 2014 No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means electronic,

More information

1. Please provide additional details about the radio replacement project and the Energy Management System (EMS).

1. Please provide additional details about the radio replacement project and the Energy Management System (EMS). 1. Please provide additional details about the radio replacement project and the Energy Management System (EMS). Radio replacement project SPS: Xcel Energy requires a replacement of its Two-Way Radio Voice

More information

Designing space policies in emerging countries: main challenges. 5 th September 2016

Designing space policies in emerging countries: main challenges. 5 th September 2016 Designing space policies in emerging countries: main challenges 5 th September 2016 1. Role of space for emerging countries 2. Main challenges in designing space policies 3. How to deal with the challenges

More information

Ruapehu Alpine Lifts. Whakapapa Electrical Network Strategy. Summary Consultation Document. 15 December 2016

Ruapehu Alpine Lifts. Whakapapa Electrical Network Strategy. Summary Consultation Document. 15 December 2016 Ruapehu Alpine Lifts Whakapapa Electrical Network Strategy Summary Consultation Document 15 December 2016 1. Introduction Local Networks are electricity distribution networks connected to Transpower s

More information

TRANSMISSION ASSETS. Filed: September 12, 2006 EB Exhibit D1 Tab 1 Schedule 2 Page 1 of INTRODUCTION

TRANSMISSION ASSETS. Filed: September 12, 2006 EB Exhibit D1 Tab 1 Schedule 2 Page 1 of INTRODUCTION Filed: September, 00 EB-00-00 Schedule Page of TRANSMISSION ASSETS.0 INTRODUCTION 0 Hydro One Networks Inc. is licensed by the Ontario Energy Board (OEB) to own, operate and maintain transmission facilities

More information

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS 101135-ELE-CMOS-E-2001 Electrical Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and has over 14 years hands-on experience, including 13 years working in operation, maintenance, construction

More information

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY Module 10 Initiation Code 1 M10 Initiation Code This is not the Initiating cause code The Outage Initiation Codes describe where an Automatic Outage was initiated on the power system. Element-Initiated

More information

Innovation Office. Intellectual Property at the Nelson Mandela University: A Brief Introduction. Creating value for tomorrow

Innovation Office. Intellectual Property at the Nelson Mandela University: A Brief Introduction. Creating value for tomorrow Innovation Office Creating value for tomorrow PO Box 77000 Nelson Mandela University Port Elizabeth 6031 South Africa www.mandela.ac.za Innovation Office Main Building Floor 12 041 504 4309 innovation@mandela.ac.za

More information

Continuous Monitoring on the SSE Networks Transmission System

Continuous Monitoring on the SSE Networks Transmission System 10 th Universities High Voltage Network Colloquium 18 th - 19 th January 2017, GCU, Glasgow, Scotland Continuous Monitoring on the SSE Networks Transmission System The Need for Standards, Specifications

More information

Globalisation increasingly affects how companies in OECD countries

Globalisation increasingly affects how companies in OECD countries ISBN 978-92-64-04767-9 Open Innovation in Global Networks OECD 2008 Executive Summary Globalisation increasingly affects how companies in OECD countries operate, compete and innovate, both at home and

More information

765 kv Series Capacitors for Increasing Power Transmission Capacity to the Cape Region

765 kv Series Capacitors for Increasing Power Transmission Capacity to the Cape Region IEEE PES PowerAfrica 2012 - Conference and Exposition Johannesburg, South Africa, 09-13 July 2012 765 kv Series Capacitors for Increasing Power Transmission Capacity to the Cape Region R. Grünbaum, Senior

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

Capability Statement

Capability Statement Capability Statement Who we are RCS Telecommunications (RCST) is a leading Australian telecommunications service provider for medium to large organisations. With over 35 years experience in communication

More information

WIPO-WASME Program on Practical Intellectual Property Rights Issues for Entrepreneurs, Economists, Bankers, Lawyers and Accountants

WIPO-WASME Program on Practical Intellectual Property Rights Issues for Entrepreneurs, Economists, Bankers, Lawyers and Accountants WIPO-WASME Program on Practical Intellectual Property Rights Issues for Entrepreneurs, Economists, Bankers, Lawyers and Accountants Topic 12 Managing IP in Public-Private Partnerships, Strategic Alliances,

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: All ENGINEERING COMMISSIONING PROCEDURE ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing of new and

More information

Experience with Connecting Offshore Wind Farms to the Grid

Experience with Connecting Offshore Wind Farms to the Grid Oct.26-28, 2011, Thailand PL-22 CIGRE-AORC 2011 www.cigre-aorc.com Experience with Connecting Offshore Wind Farms to the Grid J. FINN 1, A. SHAFIU 1,P. GLAUBITZ 2, J. LOTTES 2, P. RUDENKO 2, M: STEGER

More information

Clayton Taylor. ComRent International, LLC.

Clayton Taylor. ComRent International, LLC. Clayton Taylor CEO ComRent International, LLC. 24 Hour Tests Are Needed! New way of testing Ways to sell through testing Go after installed base Uptime and compliance 2 Eventually Generators Will Be Put

More information

Newmont Mining Corporation

Newmont Mining Corporation SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 FORM 8-K CURRENT REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 Date of Report (Date of earliest event reported):

More information

RRC POWER & ENERGY STATEMENT OF QUALIFICATIONS. experience matters

RRC POWER & ENERGY STATEMENT OF QUALIFICATIONS.  experience matters RRC POWER & ENERGY STATEMENT OF QUALIFICATIONS www.rrccompanies.com experience matters At the heart of a successful project lies a team of experts who can convert their knowledge to project results. Our

More information

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering DLC s Brady IIB Project Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering Project Need In 2007, PJM and Duquesne Light Company (DLC) transmission

More information

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors May 11, 2010 Slide 1 Why phase-shifting transformers

More information

NHS Greater Glasgow and Clyde Health Board. Policy on the Management of Intellectual Property

NHS Greater Glasgow and Clyde Health Board. Policy on the Management of Intellectual Property NHS Originated by: David Wyper and Lorna Kelly Title: Board Date: 6/05/2008 Authorised by: Date: 1 Introduction 1.1 NHS organisations are obliged to manage their Research & Development (R&D) to improve

More information

HVDC High Voltage Direct Current

HVDC High Voltage Direct Current HVDC High Voltage Direct Current Typical HVDC Station BACK TO BACK CONVERTER STATION MONO POLAR WITH GROUND RETURN PA Back to Back Converters indicates that the Rectifiers & Inverters are located in the

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE EPN, LPN, SPN ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing

More information

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE ENGINEERING COMMISSIONING PROCEDURE ECP 11-0512 GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE Network(s): Summary: EPN, LPN, SPN This procedure details the testing and commissioning

More information

SECTION VI SCOPE OF WORK

SECTION VI SCOPE OF WORK SECTION VI SCOPE OF WORK Overhead Lines and Underground cables VI 5.2 - i TABLE OF CONTENTS 5.2 SCOPE OF WORKS... 1 5.2.1 General... 1 5.2.2 Factory Acceptance Test... 2 5.2.3 33KV Lines and Cables...

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

Case No COMP/M KKR / BOSCH TELECOM PRIVATE NETWORKS. REGULATION (EEC) No 4064/89 MERGER PROCEDURE

Case No COMP/M KKR / BOSCH TELECOM PRIVATE NETWORKS. REGULATION (EEC) No 4064/89 MERGER PROCEDURE EN Case No COMP/M.1840 - KKR / BOSCH TELECOM PRIVATE NETWORKS Only the English text is available and authentic. REGULATION (EEC) No 4064/89 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 29/02/2000

More information

International Journal of Engineering & Computer Science IJECS-IJENS Vol:12 No:06 14 Smart Power Transmission System Using FACTS Device

International Journal of Engineering & Computer Science IJECS-IJENS Vol:12 No:06 14 Smart Power Transmission System Using FACTS Device International Journal of Engineering & Computer Science IJECS-IJENS Vol:12 No:06 14 Smart Power Transmission System Using FACTS Device Engr.Qazi Waqar Ali ¹, Prof.Dr.Azzam ul Asar ² 1. Sarhad University

More information

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document Bulk Electric System Definition Reference Document January, 2014 This draft reference document is posted for stakeholder comments prior to being finalized to support implementation of the Phase 2 Bulk

More information

ND1127:2000/09 TECHNICAL RECOMMENDATION. Part B. Issue 1. (Part B) DWDM Interconnect Between UK Licensed Operators

ND1127:2000/09 TECHNICAL RECOMMENDATION. Part B. Issue 1. (Part B) DWDM Interconnect Between UK Licensed Operators () DWDM Interconnect Between UK Licensed Operators TECHNICAL RECOMMENDATION Issue 1 Network Interoperability Consultative Committee Ofcom Riverside House, 2a Southwark Bridge Road, London SE1 9HA UK http://www.nicc.org.uk

More information

East-South HVDC Interconnector II, India : in commercial operation since 2003

East-South HVDC Interconnector II, India : in commercial operation since 2003 8006/0 5 HVDC / FACTS Highlights http://www.siemens.com/facts http://www.siemens.com/hvdc NEW! >>> Welcome to Siemens Highlights & Innovations in Transmission and Distribution East-South HVDC Interconnector

More information

Rosatom Approach to IPR Management in Collaborative Projects on Innovations

Rosatom Approach to IPR Management in Collaborative Projects on Innovations State Atomic Energy Corporation Rosatom Rosatom Approach to IPR Management in Collaborative Projects on Innovations Natalia Belenkaya Project Leader, Innovation Management ROSATOM Vienna, IAEA November

More information

Smart Power Transmission System Using FACTS Device

Smart Power Transmission System Using FACTS Device International Journal of Applied Power Engineering (IJAPE) Vol. 2, No. 2, August 2013, pp. 61~70 ISSN: 2252-8792 61 Smart Power Transmission System Using FACTS Device Qazi Waqar Ali 1, Azzam ul Asar 2

More information

P.O (November 2009) This is an unofficial translation of the latest draft of the Spanish grid code. Source: Jason MacDowell, GE Energy

P.O (November 2009) This is an unofficial translation of the latest draft of the Spanish grid code. Source: Jason MacDowell, GE Energy INSTALLATIONS CONNECTED TO A POWER TRANSMISSION SYSTEM AND GENERATING EQUIPMENT: MINIMUM DESIGN REQUIREMENTS, EQUIPMENT, OPERATIONS, COMMISSIONING AND SAFETY. P.O. 12.2 (November 2009) This is an unofficial

More information

CDP-EIF ITAtech Equity Platform

CDP-EIF ITAtech Equity Platform CDP-EIF ITAtech Equity Platform New financial instruments to support technology transfer in Italy TTO Circle Meeting, Oxford June 22nd 2017 June, 2017 ITAtech: the "agent for change" in TT landscape A

More information

Strategic Positioning of a NOC in the context of the new regulatory and the operating environment

Strategic Positioning of a NOC in the context of the new regulatory and the operating environment Strategic Positioning of a NOC in the context of the new regulatory and the operating environment Dr. Donald Mmari REPOA Prof. Sufian Bukurura Law Reform Commission of Tanzania Hyatt Kilimanjaro 28 th

More information

UGI Corporation (Exact name of Registrant as Specified in Its Charter)

UGI Corporation (Exact name of Registrant as Specified in Its Charter) UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 FORM 8-K CURRENT REPORT Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934 Date of Report (Date of earliest event

More information

FS INVESTMENTS & KKR FORM STRATEGIC PARTNERSHIP. Combining FSIC & CCT platforms to create stockholder value

FS INVESTMENTS & KKR FORM STRATEGIC PARTNERSHIP. Combining FSIC & CCT platforms to create stockholder value FS INVESTMENTS & KKR FORM STRATEGIC PARTNERSHIP Combining FSIC & CCT platforms to create stockholder value FS INVESTMENTS AND KKR TO ESTABLISH INDUSTRY-LEADING PARTNERSHIP FS Investments ( FS ) and KKR

More information

6 th December South West Scotland Forum

6 th December South West Scotland Forum 6 th December 2017 South West Scotland Forum SWS Developers Forum 6 www.spenergynetworks.co.uk th Dec 2017 1 Agenda Introduction Pearse Murray System Design Diyar Kadar Programme Update Bob McGuire, Colin

More information

KKR & Co. Inc. Goldman Sachs U.S. Financial Services Conference December 4, 2018

KKR & Co. Inc. Goldman Sachs U.S. Financial Services Conference December 4, 2018 KKR & Co. Inc. Goldman Sachs U.S. Financial Services Conference December 4, 2018 KKR Today Private Markets Public Markets Capital Markets Principal Activities $104bn AUM $91bn AUM Global Franchise $19bn

More information

Mubadala Development Company PJSC 2010 Full Year Results 24-March-2010

Mubadala Development Company PJSC 2010 Full Year Results 24-March-2010 Mubadala Development Company PJSC 2010 Full Year Results 24-March-2010 Speakers Today Waleed Al Mokarrab Al Muhairi Chief Operating Officer Carlos Obeid Chief Financial Officer Matthew Hurn Executive Director,

More information

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 % BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and

More information

SYSTEMS AND COMPONENTS FOR TRANSFORMER TESTING

SYSTEMS AND COMPONENTS FOR TRANSFORMER TESTING SYSTEMS AND COMPONENTS FOR TRANSFORMER TESTING 9.11/2 Transformer Testing n Type tests n Routine tests n Special tests n Applicable for tests on power and distribution transformers in factory and on-site

More information

Australia National Space Law and Space Policy

Australia National Space Law and Space Policy United Nations / CNSA / APSCO Workshop on Space Law Beijing 17-20 November 2014 Australia National Space Law and Space Policy Steven Freeland Professor of International Law, University of Western Sydney

More information

STATE OF NORTH CAROLINA OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA ALBEMARLE COMMISSION HERTFORD, NORTH CAROLINA

STATE OF NORTH CAROLINA OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA ALBEMARLE COMMISSION HERTFORD, NORTH CAROLINA STATE OF NORTH CAROLINA OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA ALBEMARLE COMMISSION HERTFORD, NORTH CAROLINA INVESTIGATIVE REPORT JANUARY 2019 1 EXECUTIVE SUMMARY PURPOSE The Office of the State

More information

Engaging Stakeholders

Engaging Stakeholders Engaging Stakeholders Users, providers and the climate science community JPI Climate WG2 Workshop: National Dialogues in Europe Thursday, 08 th May 2014 Roger B Street Module 2 Lessons Learned Users Needs

More information

Lecturer: Dr. J B E AL-ATRASH No. of Pages: 4

Lecturer: Dr. J B E AL-ATRASH No. of Pages: 4 Philadelphia University Faculty of Engineering Dept. of Electrical Engineering Student Name: Student Number: Final Exam Course Title: Design of T&D System Date: 15 th June 2016 Course No: 610 515/650511

More information

US GEOTHERMAL INC FORM 8-K. (Current report filing) Filed 09/15/11 for the Period Ending 09/15/11

US GEOTHERMAL INC FORM 8-K. (Current report filing) Filed 09/15/11 for the Period Ending 09/15/11 US GEOTHERMAL INC FORM 8-K (Current report filing) Filed 09/15/11 for the Period Ending 09/15/11 Address 390 E. PARK CENTER BLVD, SUITE 250 BOISE, ID 83706 Telephone 208-424-1027 CIK 0001172136 Symbol

More information

SPEECH by DG DEVCO Director Dr. Roberto Ridolfi D4D in Europe

SPEECH by DG DEVCO Director Dr. Roberto Ridolfi D4D in Europe SPEECH by DG DEVCO Director Dr. Roberto Ridolfi D4D in Europe Kickoff Digital for Development: Igniting partnerships Brussels, Monday 20 November 2017 BluePoint Conference Centre, Bd A. Reyers 80-1030

More information

Copyright 2012 IEEE. Paper presented at Power Africa, 9 July, Johannesburg, South Africa 2012.

Copyright 2012 IEEE. Paper presented at Power Africa, 9 July, Johannesburg, South Africa 2012. Copyright 2012 IEEE Paper presented at Power Africa, 9 July, Johannesburg, South Africa 2012. This material is posted here with the permission of the IEEE. Such permission of the IEEE does not in any way

More information

~ RG1 ~ RG2 ~ RG3 COORDINATION OF REGULATION SYSTEMS FOR GENERATORS AND TRANSFORMERS IN AN INDUSTRIAL COMBINED HEAT AND POWER PLANT 1.

~ RG1 ~ RG2 ~ RG3 COORDINATION OF REGULATION SYSTEMS FOR GENERATORS AND TRANSFORMERS IN AN INDUSTRIAL COMBINED HEAT AND POWER PLANT 1. 49 COORDINATION OF REGULATION SYSTEMS FOR GENERATORS AND TRANSFORMERS IN AN INDUSTRIAL COMBINED HEAT AND POWER PLANT 1. INTRODUCTION All the national combined heat and power plants work with the national

More information

Var Control. Adding a transformer and transformer voltage regulation. engineers loadflow program. The control system engineers loadflow.

Var Control. Adding a transformer and transformer voltage regulation. engineers loadflow program. The control system engineers loadflow. November 2012 Adding a transformer and transformer voltage regulation to the control system engineers loadflow program The control system engineers loadflow program The loadflow program used by this website

More information

Grid Impact of Neutral Blocking for GIC Protection:

Grid Impact of Neutral Blocking for GIC Protection: Report submitted to EMPRIMUS - Critical Infrastructure Protection Grid Impact of Neutral Blocking for GIC Protection: Impact of neutral grounding capacitors on network resonance Prepared By: Athula Rajapakse

More information

Power System Studies

Power System Studies Power System Studies Laois Ballyragget Cable Feasibility Study PE667-F4-R3-1-3 ESBI Engineering Solutions Stephen Court, 18/21 St Stephen s Green, Dublin 2, Ireland Telephone+353-1-73 8 Fax+353-1-661 66

More information

Wide Area Voltage Dispatch. - Case studies of ISO New England using NETSS AC XOPF program

Wide Area Voltage Dispatch. - Case studies of ISO New England using NETSS AC XOPF program Wide Area Voltage Dispatch - Case studies of ISO New England using NETSS AC XOPF program Xiaochuan Luo ISO New England Inc Marija Ilic, Jeff Lang NETSS Inc. EPRI AVC Workshop PJM, Norristown, PA May 19,

More information

Interim Report on the Heiligendamm Process at the G8 Summit in Hokkaido Toyako 7 to 9 July 2008

Interim Report on the Heiligendamm Process at the G8 Summit in Hokkaido Toyako 7 to 9 July 2008 Interim Report on the Heiligendamm Process at the G8 Summit in Hokkaido Toyako 7 to 9 July 2008 Prepared by the Steering Committee of the Heiligendamm Process consisting of the personal representatives

More information

Chapter 5. Forms of Business Ownership and Organization

Chapter 5. Forms of Business Ownership and Organization Chapter 5 Forms of Business Ownership and Organization Learning Objectives 1 2 Discuss why most businesses are small businesses. Determine the contributions of small businesses to the economy. 7 Outline

More information

Upstream Petroleum Contracts, Accounting & Auditing Policies and Procedures

Upstream Petroleum Contracts, Accounting & Auditing Policies and Procedures Upstream Petroleum Contracts, Accounting & Auditing Policies and Procedures 25 Nov - 06 Dec 2018, Dubai 02-13 Sep 2019, London 24 Nov - 05 Dec 2019, Dubai Upstream Petroleum Contracts, Accounting Introduction

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

Network Monitoring and Visibility Summary

Network Monitoring and Visibility Summary Network Monitoring and Visibility Summary This article reviews the shortfalls in legacy monitoring and what will be needed to manage the changing nature of the distribution network. This includes a particular

More information

AXALTA COATING SYSTEMS LTD.

AXALTA COATING SYSTEMS LTD. UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C. 20549 FORM 8-K CURRENT REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 Date of Report (Date of earliest event

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

NEWMONT MINING CORP /DE/

NEWMONT MINING CORP /DE/ NEWMONT MINING CORP /DE/ FORM 8-K (Current report filing) Filed 06/05/14 for the Period Ending 06/05/14 Address 6363 SOUTH FIDDLERS GREEN CIRCLE GREENWOOD VILLAGE, CO 80111 Telephone 303-863-7414 CIK 0001164727

More information

Siemens AG Österreich Transformers Weiz. Reference for Autotransformer. Autotransformer. Customer National Grid, UK

Siemens AG Österreich Transformers Weiz. Reference for Autotransformer. Autotransformer. Customer National Grid, UK Reference for Autotransformer National Grid, UK Tilbury SGT Delivery 2009 240 MVA, three-phase AUT 403/132/14 kv 100% first pass yield Autotransformer 45 units to several SGT of NG in the past 12 years

More information

12808/16 PG/cb 1 DG G 3 C

12808/16 PG/cb 1 DG G 3 C Council of the European Union Brussels, 30 September 2016 (OR. en) 12808/16 ESPACE 46 RECH 283 COMPET 515 TRANS 368 TELECOM 184 'I/A' ITEM NOTE From: To: Subject: General Secretariat of the Council Permanent

More information

QUESTIONNAIRE for Wind Farm Power Stations only

QUESTIONNAIRE for Wind Farm Power Stations only TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21

More information

NER300 Offshore Wind Park Nordsee One. Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH

NER300 Offshore Wind Park Nordsee One. Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH NER300 Offshore Wind Park Nordsee One Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH Brussels, 15 December 2017 1 Agenda General project overview & timeline

More information

GZ.:BMWF-8.105/5-II/1/2010

GZ.:BMWF-8.105/5-II/1/2010 Austrian Status Report on the implementation of the Recommendation from the European Commission on the management of Intellectual Property in knowledge transfer activities and a Code of Practice for universities

More information

OAH No , MPUC Dkt No. IP6701/WS STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS

OAH No , MPUC Dkt No. IP6701/WS STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS OAH No. -00--, MPUC Dkt No. IP0/WS-0- STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE MINNESOTA PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION BY AWA GOODHUE WIND, LLC FOR A

More information

2 nd Quarter Earnings Conference Call

2 nd Quarter Earnings Conference Call 2 nd Quarter Earnings Conference Call KKR & Co. Inc. Investor Update July 26, 2018 Recent Milestones K-1 $ Converted to a Corporation on July 1, 2018 Investor Day held on July 9, 2018 2 Key Metrics Assets

More information

Energy Delivery. Holland Bottom 500/161/115kV Substation. Delivering energy safely, reliably, efficiently and affordably.

Energy Delivery. Holland Bottom 500/161/115kV Substation. Delivering energy safely, reliably, efficiently and affordably. Holland Bottom 500/161/115kV Substation Delivering energy safely, reliably, efficiently and affordably. For the past two summers, several substations in the Little Rock area showed low voltages with no

More information

Arpeggio Acquisition Corporation (212) Devin Sullivan (212)

Arpeggio Acquisition Corporation (212) Devin Sullivan (212) CONTACT: -OR- INVESTOR RELATIONS COUNSEL: Eric Rosenfeld Maura Gedid Arpeggio Acquisition Corporation (212) 836-9605 212-316-7676 mgedid@equityny.com Devin Sullivan (212) 836-9608 dsullivan@equityny.com

More information

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document Bulk Electric System Definition Reference Document Version 2 April 2014 This technical reference was created by the Definition of Bulk Electric System drafting team to assist entities in applying the definition.

More information

SECTION VI SCOPE OF WORK

SECTION VI SCOPE OF WORK SECTION VI SCOPE OF WORK Overhead Lines and Underground cables VI 5.2 - i TABLE OF CONTENTS 5.2 SCOPE OF WORKS... 1 5.2.1 General... 1 5.2.2 Factory Acceptance Test... 2 5.2.3 33KV Lines and Cables...

More information

Landis+Gyr - a PE driven business transformation and successful buyout

Landis+Gyr - a PE driven business transformation and successful buyout Landis+Gyr - a PE driven business transformation and successful buyout Andreas Umbach, CEO Landis+Gyr 11. Private Equity & Corporate Finance Conference, Zürich, 4th July, 2012 1 Landis+Gyr Umbrella Presentation

More information

The Role of Governments and Policymakers in advancing Science Communication and PLUS in Africa.

The Role of Governments and Policymakers in advancing Science Communication and PLUS in Africa. República de Moçambique The Role of Governments and Policymakers in advancing Science Communication and PLUS in Africa. 3 rd African Conference on EID and Biosecurity Accra, August 18, 2017. Presentation

More information

TELECOMMUNICATIONS ACT, 1996 (ACT NO. 103 OF 1996): REGULATIONS

TELECOMMUNICATIONS ACT, 1996 (ACT NO. 103 OF 1996): REGULATIONS 1. Saved Record from Search: (kw: ((act n2 103) and (103 n2 1996))) and lg: (2001?) Database: Government Gazettes Gazette No: 22874 Notice No: 1255 Regulation No: 7217 Gazette: GOV Date: 20011128 No. R.

More information

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007 BR 94/2007 TELECOMMUNICATIONS ACT 1986 1986 : 35 SATELLITE NETWORK NOTIFICATION AND COORDINATION ARRANGEMENT OF REGULATIONS 1 Citation 2 Interpretation 3 Purpose 4 Requirement for licence 5 Submission

More information

ELECTRICAL POWER ENGINEERING

ELECTRICAL POWER ENGINEERING Introduction This trainer has been designed to provide students with a fully comprehensive knowledge in Electrical Power Engineering systems. The trainer is composed of a set of modules for the simulation

More information