6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room
|
|
- Benedict Wilkerson
- 5 years ago
- Views:
Transcription
1 6MSD Weekly Scheduling Meeting 1:30, MCC Conference Room October 12, ) Glance Back and 2-Week Look Ahead (F. Pilat) mins 2) PMI Report (P. Collins)... 5 mins 3) Critical Path Service Provider Reports mins (a) Alignment (Curtis) (b) SRF (Hogan) (c) EESIC (Garza) (d) Software (P. Kjeldsen) 4) Hall C Special Report: Qweak (G. Smith) mins 5) Safety Report: M. Logue... 5 mins 6) Meeting Recap and Action Items (All)... 5 mins
2 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting October 12, 2011
3 Progress Wed Oct 5 Wed Oct 12 Weeks: 22 down, 5 to go (30 days to Physics? November 11) Highlights: NE Stub: backfilling in progress NE Stub: utilities work progressed very fast NE Gate: installation started this morning! Work with beam started at the gun. PSS pre checks & certifications in progress C100 2 : cavity gradient > 20 MV/m in 7 out of 8 C100 1 : LLRF work, micro phonic measurements Hall C HKS Removal continues, Qweak mid term survey done Re aligned Primavera and SAD calendar, moved out some FEL and Hall A scope of work Areas of attention: Halls work appear to be late in the progress schedule real or reporting hiccups? No crisis at this moment in time, but monitor Ops start up, C100 and civil work schedules
4 2 weeks look ahead Civil construction work continues: NE Stub work (ramp) & Back fill to Grade Ongoing Hall D Buildings (Counting House, Tagger Area & Service Bldg) Finish temporary gate at NE stub tunnel start of injector operations RECO process officially started, daily meeting Injector PSS certifications & Injector Hot Checkout PSS Pre Checks & Certifications: NL and SL/BSY/End Stations Various Systems HCO C100 1 & 2 commissioning/testing in tunnel Restore 5.6 GeV machine (no C100) RF installation continues in the Linacs Hall A: G2P Beamline work & Target Repair Hall B: HDIce work Hall C: Qweak preps, removal HKS, final survey
5 6MSD Organization NO CRs & NTFs have been submitted, reviewed, and approved this week Transition 6MSD to operations PD rotation starts Monday October 17, 0745 and 0800 am meeting revert to the operations format Wednesday Progress/Resource Meeting will continue. Hall Physicists to tell us about preparation for beam (will start today with Hall C, then following with Hall B and Hall A) Weekly Thursday 6MSD Planning Team Meetings will be scheduled regularly for coordination and early discussions of lesson learned 6MSD team and organization in place until physics running and for lessons learned and 6MSD post mortem input to 12MSD organization
6 PM&IP 6MSD 10/12/11 Weekly Progress Meeting (10/07/11 Data) Report #22
7 PM&IP Schedule Issues: Hall D Phase 3 Tunnel Extension is ~23 Days behind schedule. (Nov. 10 th completion date) Hall A Septum and Target: 18 days behind scheduled completion of 01 Dec Hall C: Moller Polarimeter 1 day of float Compton Polarimeter 0 float LCW System Restoration Acid Flush? Ops Start Up Schedule in flux. FEL Activities have been removed from the schedule. Resource issues: Alignment Week of Oct 17th
8 PM&IP Other Schedule Information at Two Week Look Ahead - Shows all activities that have started that are not complete and any activities due to start in the next two weeks Critical Path Shows all MUST activities that have 2 days or less float. Schedule Variance - Shows all MUST activities that are not 100% complete and that the Start/Finish dates have slipped by at least 5 days.
9 Shutdown Work Summary Organization: Alignment Name: Chris Curtis Date: 12th Oct, 2011 Last Week Work That Went Better Than / As Expected: Hall A dump penetration survey completed. PEPPo solenoid aligned. Cryomodule spaceframe QC check completed. Hall D control survey completed Q Weak HKS mid stage teardown survey completed. North east accelerator quick check completed. Work That Went Slower Than Expected, Delays, and Issues: West arc stack 15 re checked and re aligned. Ongoing Shutdown Work Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns 12 GeV Arcs X Oct 21 Final alignment of NE arc Started today magnets G2p X TBD Harp & Dump fiducialization When available Hall C Q Weak X TBD Target alignment Scheduled for next week PEPPo X Oct 21 Alignment of PEPPo components Scheduled for next week 6MSD weekly mtg Align Oct 12 Page 1 of 3
10 Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns Hall D X October Solenoid alignment Second phase of solenoid alignment G2p X TBD Alignment of all downstream components and target Additional alignment for target repair Hall B X TBD Complete target /beamline alignment October Q Weak X TBD HKS monitoring; final alignment of detectors etc. End of October New Work Requests Requiring Schedule Changes: None Permits Not Already in Hand (hot work, lifting, blind penetrations): None Significant Problems Pending (delays, technical issues, resource issues, scheduling): Beginning to see light at the end of the accelerator tunnel. Staffing Outlook: OK 6MSD weekly mtg Align Oct 12 Page 2 of 3
11 Hall C Elevations 6MSD weekly mtg Align Oct 12 Page 3 of 3
12 Shutdown Work Summary Organization: SRF Name: John Hogan Date: 12 OCT 2011 Last Week Work That Went Better Than Expected: N/A Work That Went Slower Than Expected, Delays, and Issues: N/A Ongoing Shutdown Work Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns C Checkout X LLrf control; Microphonics Making good progress. damping investigation C Checkout X SRF commissioning. Making good progress. Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns C Checkout X LLrf control ongoing. Added HOM waveguide filters in preparation of beam tests. C Checkout Standard SRF performance Checkout on schedule for commissioning activities. LLrf will completion prior to hot checkout, confirm performance. 24 OCT Shutdown Work Summary_12OCT2011_JH Page 1 of 2
13 Project & Customer Status Completion Tasks Comments/Concerns New Work Requests Requiring Schedule Changes: N/A Permits Not Already in Hand (hot work, lifting, blind penetrations): N/A Significant Problems Pending (delays, technical issues, resource issues, scheduling): The time to install and checkout C is very tight; there is no float for unknown problems. Staffing Outlook: Ok. Shutdown Work Summary_12OCT2011_JH Page 2 of 2
14 Shutdown Work Summary Organization: EESIC Name: Omar Garza Date: Last Week Work That Went Better Than Expected: Work That Went Slower Than Expected, Delays, and Issues: Ongoing Shutdown Work Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns Hall C Qweak Cavity Electronics Hall A G2P Low Current BPM Electronics Hall A G2P Diagnostics Hall A G2P Motor Driver Chassis 12Gev SRF Vacuum Instrumentation X Ongoing Digital Section Testing Order DAC Brd. / Parts Building Chassis Near Completion DAC Brds and Components onhold due to acct. freeze $$ X Ongoing Complete PC Brds. <2wks Assemble Brds. In house Brd. Changes at 90% completion X Ongoing Cables completed Harp 1 installed, Harp 2 assembled, YAG assembled & tested Awaiting Driver Chassis X Ongoing Testing Unit delivered to Software X Ongoing SL23, 24, 25 Going Well Shutdown Work Summary Page 1 of 2
15 Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns Injector PePPo Ops AIPBSY (I to V) Module X Ongoing Beam Scrappers wiring Faraday Cup wiring Viewer wiring completed BPMs X On hold Brd Procurement, Assembly, Testing Software Waiting for beamline component installation Software Procure Brds Onhold $$ Accelerator Network Firewall Configuration Accelerator Maintenance X Ongoing Phase I Segment config. Phase II Failover config. Phase III Rules configuration Phase IV Network Implementation X Ongoing Diagnostics EA, SL Vacuum pumps Phase I completed Going Well Controls complete BPMs complete Diagnostics NL complete New Work Requests Requiring Schedule Changes: Permits Not Already in Hand (hot work, lifting, blind penetrations): Significant Problems Pending (delays, technical issues, resource issues, scheduling): Staffing Outlook: Shutdown Work Summary Page 2 of 2
16 Shutdown Work Summary Organization: Controls Software Name: Pam Kjeldsen Date: October 12, 2011 Last Week Work That Went Better Than/As Expected: Work That Went Slower Than Expected, Delays, and Issues: Ongoing Shutdown Work Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns PEPPo X 17 Oct 11 Viewers Ready to test with hardware PEPPo X 17 Oct 11 Dipole power supply controls Test stand operational; Software development underway PEPPo X 17 Oct 11 Discriminator/scaler for data acquisition Software installed in field; Waiting for hardware in order to test 12 GeV X 1 Oct 11 Low level RF Some progress; RF on sequence work continuing 12 GeV X 14 Oct 11 RF screens Some progress; Work continues G2P X 14 Nov 11 New harp controls Chassis received; Software Development progressing G2P X 15 Nov 11 New BPM controls Position and calibration algorithm to be developed; chassis in 2 weeks G2P X 21 Sep 11 Viewers Ready to test with hardware 6MSD Page 1 of 2
17 Project & Customer Status Completion Tasks Comments/Concerns G2P X 3 Oct 11 Septum magnet controls Waiting for information for last 5%; PSS/MPS X 15 Nov 11 CAEN power supply Good progress; Communications with power supply through Ethernet established Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns 12 GeV X 14 Nov 11 IOC boot management CASA X 1 Nov 11 MO monitor Hall A X 1 Nov 11 IOCs moved to accelerator network 6MSD Page 2 of 2 Implementation and 80% of testing done; testing remains for 20% Operations X LCW monitoring Acquisition plans ongoing Operations X 1 Nov 11 Control system write logging Wider installation Operations X 14 Nov 11 Digital image management Camera and network ready; computer to be installed Operations X 1 Nov 11 Confirm network changes do not impact accelerator or endstation operation New Work Requests Requiring Schedule Changes: None Permits Not Already in Hand (hot work, lifting, blind penetrations): None Significant Problems Pending (delays, technical issues, resource issues, scheduling): LCW monitoring requires a new server; Plant Engineering is pursuing its acquisition Staffing Outlook: OK Testing under way
18 Qweak Status & Plans for Beam (10 ) Status (Greg Smith) Qweak Run II not a new setup. A continuation Run I major down times predominantly: QTOR PS, DS beamline vacuum, Target pump 6MSD used to harden these systems And perform maintenance, make improvements to other systems Plans for Beam (Roger Carlini) Plans for 1 st week (11/11/11) Plans for remaining time
19 Upstream Status Compton: plan to finish work this week Doubled gain with new mirrors to ~1.6 kw Improved e-det effi (4 th plane, better cables, etc.) PbW photon detector gain stabilized Moller: unexpected large quad problem Q3 boneyard, Q2 Q3. Beamline reassembled. Pull vacuum & stack Pb after Moller tgt swap. Survey & alignment next week. Pivot halo target: Being re-designed for hor. offset beam Improved cavity BCMs: New electronics on track (Musson, Allison) 2 new cavities added to beamline 4 new cables pulled
20 Target Status Pump: replaced scored stator, replaced worn bearings Loop: replaced broken thermometry Heater: Installed higher power (3 4 kw) heater PS Cell: replaced both entrance & exit windows Coolant: replaced lossy 15K xfer line Solid tgts: improved heat xfer ( more I beam ), installed spare bkg tgts, replaced broken thermometry Replaced non-ss piping with SS Added more filters (magnetic & gas) Painting ballast/storage tanks, new inventory of H2 Performed 20K He cooldown test last week Test was successful: target is ready! Tgt survey & alignment scheduled for Oct. 18 th & 19 th
21 scoring gaps 2 mm exit window vacuum side 15 mm Φ, mm thick entrance window mm thick exit window vacuum side
22 Solid Targets Looking Downstream 2 axis motion system Looking Upstream
23 Downstream Status R1 GEMs: Replacing with pin diodes. Install lead flapper RII HDC s: Resolved an interference Replace 1 of 4 chambers with working spare (next week) Main Detectors: Compressed poor glue joint on 1 detector Installed new rail system to move bkg detector around Re-covering detector shield hut this week Downstream beamline at end of hall: New SS bellows (2 φ) leak tight New welded Al spool piece with viewer leak tight Waiting on quartz window & Ti bolts Install these parts this week or early next week, with new vacuum window, & pump out DS beamline Dump Tunnel: Leak in He dump line found & fixed Diffuser removed New ion chambers & rad hard cabling Repair dump tunnel dehumidifier
24 Upgrade to DS Viewer Region Problematic - Run 1 Design All Al (at small radius) - Run 2 Design H 2 O Cooled Window 24 H 2 O Cooled Window ~10 Φ SS Aluminum Stainless Steel Aluminum ~2 cm
25 Watching carefully : Dumpline dehumidifier Parts arrive only 10/31. Punt? Ballast tank painting Work order: by Friday DS beamline reassembly Within a week, to have time to deal with potential problems 4K flow re-certification
26 Thanks! Hall C/Qweak appear on track to be ready for beam well before the end of this month, thanks to the hard work and dedication of many people, including: Dave Hamlette & the radcon group, Neil Wilson & company, Rick Taylor & installation group, Greg Marble, Rick Gonzales & the vacuum group, survey & alignment group, Dave Meekins & the target group, Omar Garza, John Musson & Trent Allison, the magnet test group, Kelly Mahoney & Rich Wright, Joe Beaufait, and many others. And of course Andy Kenyon & our Hall C techs! Thanks to all of you who have helped & continue to help us be ready on time! THANK YOU!
27 Plan for Nov. 11 th 19 th Qweak indeed wants to take 1-pass beam between Nov if possible. The request is to receive (after initial tune-up beam) approximately 2 days of low intensity (200pA-10nA) running for our tracking measurements. We need to do this first before activation of the drift chamber region causes higher than ideal leakage currents in our wire chambers. We would then like a couple of days of transverse running with high current beam ~150uA's - using both horizontal and vertical transverse setups - say 1 day of each + mini-spin dance. After which we would like to go into a mode as close as possible to "production" - high current with 100% long. polarization. Some of this period would be used to allow Jay to briefly study the front end position corrector feedback system and the experiment to characterize how close we are setup to a "parity quality beam" condition.
28 Goals for Nov. 20 th. Production Running >50% of time at 150µA to 180µA on LH 2 >25% time: 2 shifts/week on Moller running (@ a few µa s) 1µA to 100µA on on Al 200pA to 100nA for tracking (~once a month) Some specialty configurations transverse, spin dance, <25% Exp + Acc down time
29 ΔA/A Projections (assumes 235 ppm MD, 87% pol) 25% Run 1 Run 2: 70% Goal Run 2: 50% Run 2: 30% 5.0% 4.5% 20% 4.0% 30% efficient ΔA/A (%) 15% 10% summer down ΔA/A (%) 3.5% 3.0% 2.5% 2.0% 70% 50% Calendar day of scheduled beam 5% 0% Calendar day of scheduled beam Statistical goal = 2.1%
30
31 Silica is an OSHA National Emphasis Program due to its hazards of long term lung diseases. Jack-hammering is known to release silica dust. The jack-hammering job was begun with some water on the operation but no respiratory protection (not ID d in AHA) & had some visible dust. Blowers supplied some air to the area. After the lack of a respirator was presented to the contractor, they assigned respirator qualified workers. Air samples the next day ultimately indicated potential overexposure due to inadequate level of respiratory protection. Contractor reassessed respirator used to better type for future work. This potential exposure became a reportable event.
6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room
6MSD Weekly Scheduling Meeting Wednesday @ 1:30, MCC Conference Room October 26, 2011 1) Glance Back and 2-Week Look Ahead (F. Pilat)... 10 mins 2) Operations Recovery Status (A. Freyberger)... 10 mins
More informationR.Bachimanchi, IPAC, May 2015, Richmond, VA
1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >
More informationC100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint
1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >
More informationInstallation! of! E (g 2p ) & E (G Ep /G Mp )! in Hall A! during the 6MSD!!"#$%&'(#
Installation! of! E08-027 (g 2p ) & E08-007 (G Ep /G Mp )! in Hall A! during the 6MSD!!"#$%&'(# E08-027 (g 2p )!! Measure the inelastic spin structure function g 2 of the proton in the low invariant momentum
More informationHall C Infrastructure Projects Update
Hall C Infrastructure Projects Update Outline Targets Input from tgt group Polarimetry Input from Dave G. Some Other Stuff Greg Smith JLab Jan. 2006 Target Upgrade- Basic Philosophy Need smaller SC for
More informationAlignment of the 12 GeV CEBAF Accelerator
Alignment of the 12 GeV CEBAF Accelerator Christopher Curtis Thomas Jefferson National Accelerator Facility, Newport News, Virginia, USA 1 Jefferson Lab Site c.2006 Jefferson Lab Site 2014 CEBAF 12 GeV
More informationRadiological Safety Analysis Document for the CLAS12 Engineering and the first physics run of Run Group A
Radiological Safety Analysis Document for the CLAS12 Engineering and the first physics run of Run Group A This Radiological Safety Analysis Document (RSAD) will identify the general conditions associated
More information3.9 GHz System (AH1) XFEL WP46
3.9 GHz System (AH1) XFEL WP46 14th European XFEL Machine Advisory Committee Meeting 02 May 2016 Paolo Pierini, INFN & DESY Elmar Vogel, DESY + INFN/DESY contributors PPT version 1 26/04/2016 Outline Status
More informationCommissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008
Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Overview ALICE (Accelerators and Lasers In Combined Experiments)
More informationRF System LSD Work. William Merz
RF System LSD Work William Merz LSD Re-Baseline Review Jefferson Lab Thomas Jefferson National Accelerator Facility Page 1 Outline What I will talk about 12 GEV RF power system installation and commissioning
More informationPhysics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7
Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Approval: Originator: Tor Raubenheimer, Physics Support Lead Date Approved Approver: Marc Ross, Cryogenic System Manager Approver: Jose Chan,
More information12 GeV Upgrade Project DESIGN SOLUTIONS DOCUMENT. Upgrade Hall A
12 GeV Upgrade Project DESIGN SOLUTIONS DOCUMENT Upgrade Hall A Version 1.2 July 28, 2010 DESIGN SOLUTIONS DOCUMENT Upgrade Hall A APPROVALS Approved by: 12 GeV Upgrade Control Account Manager, Hall A
More informationCEBAF Overview June 4, 2010
CEBAF Overview June 4, 2010 Yan Wang Deputy Group Leader of the Operations Group Outline CEBAF Timeline Machine Overview Injector Linear Accelerators Recirculation Arcs Extraction Systems Beam Specifications
More informationPREX- 2 Issues. April 11, Kent Paschke
PREX- 2 Issues April 11, 2014 Kent Paschke What We Learned in PREX-I What Worked: New Septum We now know how to tune it to optimize FOM A T false asymmetry A T is small (
More informationFLASH at DESY. FLASH. Free-Electron Laser in Hamburg. The first soft X-ray FEL operating two undulator beamlines simultaneously
FLASH at DESY The first soft X-ray FEL operating two undulator beamlines simultaneously Katja Honkavaara, DESY for the FLASH team FEL Conference 2014, Basel 25-29 August, 2014 First Lasing FLASH2 > First
More informationStatus of the PRad Experiment (E )
Status of the PRad Experiment (E12-11-106) NC A&T State University Outline Experimental apparatus, current status Installation plan Draft run plan Summary PRad Experimental Setup Main detectors and elements:
More informationALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory
ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ERL 09 8 th 12 th June 2009 ALICE Accelerators and Lasers In Combined Experiments Brief Description ALICE Superconducting
More informationLow-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY
Low-Level RF S. Simrock, DESY Outline Scope of LLRF System Work Breakdown for XFEL LLRF Design for the VUV-FEL Cost, Personpower and Schedule RF Systems for XFEL RF Gun Injector 3rd harmonic cavity Main
More informationSystem Integration of the TPS. J.R. Chen NSRRC, Hsinchu
System Integration of the TPS J.R. Chen NSRRC, Hsinchu OUTLINE I. Main features of the TPS II. Major concerns and intersystem effects of an advanced synchrotron light source III. Subsystems and intersystem
More informationINSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM
INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM FOR THE EUROPEAN XFEL Julien Branlard, for the LLRF team TALK OVERVIEW 2 Introduction Brief reminder about the XFEL LLRF system Commissioning goals
More informationActivities on Beam Orbit Stabilization at BESSY II
Activities on Beam Orbit Stabilization at BESSY II J. Feikes, K. Holldack, P. Kuske, R. Müller BESSY Berlin, Germany IWBS`02 December 2002 Spring 8 BESSY: Synchrotron Radiation User Facility BESSY II:
More informationHall C Polarimetry at 12 GeV Dave Gaskell Hall C Users Meeting January 14, 2012
Hall C Polarimetry at 12 GeV Dave Gaskell Hall C Users Meeting January 14, 2012 1. Møller Polarimeter 2. Compton Polarimeter Hall C 12 GeV Polarimetry Møller Polarimeter 6 GeV operation: uses 2 quads to
More informationFLASH: Status and upgrade
: Status and upgrade The User Facility Layout Performance and operational o a issues Upgrade Bart Faatz for the team DESY FEL 2009 Liverpool, UK August 23-28, 2009 at DESY > FEL user facility since summer
More informationStatus of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY
Status of the European XFEL Accelerator Construction Project Reinhard Brinkmann, DESY European XFEL Introduction Some specifications Photon energy 0.3-24 kev Pulse duration ~ 10-100 fs Pulse energy few
More informationRoman Pots. Marco Oriunno SLAC, PPA. M.Oriunno, SLAC
Roman Pots Marco Oriunno SLAC, PPA The Roman Pot technique 1. The Roman Pot, an historically successful technique for near beam physics: ISR, SPS, TEVATRON, RICH, DESY 2. A CERN in-house technology: ISR,
More informationRe-commissioning the Recycler Storage Ring at Fermilab
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on Accelerator Operations The Fermi National Accelerator
More informationEngineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team
Engineering Challenges and Solutions for MeRHIC Andrew Burrill for the MeRHIC Team Key Components Photoinjector Design Photocathodes & Drive Laser Linac Cavities 703.75 MHz 5 cell cavities 3 rd Harmonic
More informationA Facility for Accelerator Physics and Test Beam Experiments
A Facility for Accelerator Physics and Test Beam Experiments Experimental Program Advisory Committee Roger Erickson for the SABER Design Team December 4, 2006 The Problem: FFTB is gone! The Final Focus
More informationRF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS
RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS J. Teichert, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A.
More informationAccelerator Issues for PREX
Accelerator Issues for PREX Kent Paschke University of Virginia when name E b target, θ what s hard? Aug 2009 HAPPEX III 3.4 GeV 1 H, 12 o polarimetry Oct 2009 PV DIS 6 GeV 2 H, 12 o backgrounds Jan 2010
More informationSummer / Fall 2004 Downtime AEG Week 4 Summary
Summer / Fall 2004 Downtime AEG Week 4 Summary BaBar Monitoring - Monday August 23 o This survey is designed to check the detector after the installation of the brass plates in the lower part of the detector.
More informationFLASH 2. FEL seminar. Charge: 0.5 nc. Juliane Rönsch-Schulenburg Overview of FLASH 2 Hamburg,
FLASH 2 FEL seminar Juliane Rönsch-Schulenburg Overview of FLASH 2 Hamburg, 2016-03-22 Charge: 0.5 nc Overview 1. FLASH 2 Overview 1.Layout parameters 2. Operation FLASH2. 1.Lasing at wavelengths between
More informationEMMA the World's First Non-Scaling FFAG Accelerator
EMMA the World's First Non-Scaling FFAG Accelerator Susan Smith STFC Daresbury Laboratory CONTENTS Introduction Contents What are ns-ffags? and Why EMMA? The international collaboration EMMA goals and
More informationRESULTS ON FIELD MEASUREMENTS IN A FLAT POLE MAGNET WITH THE CURRENT CARING SHEETS
CBN 14-01 March 10, 2014 RESULTS ON FIELD MEASUREMENTS IN A FLAT POLE MAGNET WITH THE CURRENT CARING SHEETS Alexander Mikhailichenko Abstract. The results of measurements with a gradient magnet, arranged
More informationThe Qweak Experiment at Jefferson Lab
The Qweak Experiment at Jefferson Lab J. Birchall University of Manitoba for the Qweak Collaboration Elba XII, June 2012 1 Qweak: measurement of the weak charge of the proton Commissioning June - August,
More informationFLASH II: an Overview
FLASH II: an Overview 1. Layout. 2. Status 1. Civil Construction 2. E-beamline 3. Photon Beamline 3. Timeplan 4. Finances 5. Personnel Situation 6. Simultaneous Operation of FLASH1 and 2 FLASH II is a
More informationREVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES. S. Belomestnykh
REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES S. Belomestnykh HPC workshop JLAB, 30 October 2002 Introduction Many aspects of the high-power coupler design, fabrication, preparation, conditioning, integration
More informationJEDI. Status of the commissioning of the waveguide RF Wien Filter
COSY Beam Time Request For Lab. use Exp. No.: Session No. E 005.4 7 Collaboration: JEDI Status of the commissioning of the waveguide RF Wien Filter Spokespersons for the beam time: Ralf Gebel (Jülich)
More informationPackaging of Cryogenic Components
Packaging of Cryogenic Components William J. Schneider Senior Mechanical Engineer Emeritus November 19-23 2007 1 Packaging of Cryogenic Components Day one Introduction and Overview 2 What is important?
More informationVIBRATING WIRE SENSORS FOR BEAM INSTRUMENTATION Suren Arutunian
VIBRATING WIRE SENSORS FOR BEAM INSTRUMENTATION Suren Arutunian Yerevan Physics Institute Yerevan Physics Institute S.Arutunian, VIBRATING WIRE SENSORS FOR BEAM INSTRUMENTATION BIW 2008, Lake Tahoe, USA
More informationXFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension
XFEL Cryo System Possible extension 1 st stage Project X Collaboration Meeting, FNAL September 8-9, 2010 (XFEL WP10 & WP13) Outline 2 XFEL accelerator structure TESLA technology Basic cryogenic parameters
More informationStatus and Plans for the 805 MHz Box Cavity MuCool RF Workshop III 07/07/09 Al Moretti
Status and Plans for the 805 MHz Box Cavity MuCool RF Workshop III 07/07/09 Al Moretti 7/6/2009 1 Outline : Description of the Box cavity Concept. Box Cavity Summary Plans. HFSS Models of orthogonal and
More informationPreliminary Plan for a Hadron Production Facility at the SLAC A-Line and End Station A
Preliminary Plan for a Hadron Production Facility at the SLAC A-Line and End Station A R. Arnold, T. Fieguth, C. Hast, M. Woods, D. Walz ILC-SLACESA TN-2007-2 October 3, 2007 1. Overview A facility for
More informationCLAS12 First Experiment Workshop Report
CLAS12 First Experiment Workshop Report Latifa Elouadrhiri Jefferson Lab For more details about the workshop https://www.jlab.org/indico/event/201/ CLAS Collaboration Jefferson Lab March 28-31, 2017 1
More informationCEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute
CEBAF waveguide absorbers R. Rimmer for JLab SRF Institute Outline Original CEBAF HOM absorbers Modified CEBAF loads for FEL New materials for replacement loads High power loads for next generation FELs
More informationBeam Diagnostics, Low Level RF and Feedback for Room Temperature FELs. Josef Frisch Pohang, March 14, 2011
Beam Diagnostics, Low Level RF and Feedback for Room Temperature FELs Josef Frisch Pohang, March 14, 2011 Room Temperature / Superconducting Very different pulse structures RT: single bunch or short bursts
More informationSURVEY AND ALIGNMENT FOR THE SWISS LIGHT SOURCE
1 SURVEY AND ALIGNMENT FOR THE SWISS LIGHT SOURCE F.Q. Wei, K. Dreyer, U. Fehlmann, J.L. Pochon and A. Wrulich SLS / Paul Scherrer Institute CH5232 Villigen PSI Switzerland ABSTRACT The Swiss Light Source
More informationStrategy for the engineering integration of the ESS accelerator
Applications of Nuclear Techniques (CRETE15) International Journal of Modern Physics: Conference Series Vol. 44 (2016) 1660208 (7 pages) The Author(s) DOI: 10.1142/S2010194516602088 Nikolaos Gazis nick.gazis@esss.se
More informationFLASH. FLASH Training: RF Gun. FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously. Siegfried Schreiber, DESY
FLASH Training: RF Gun FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously Siegfried Schreiber, DESY FLASH Training DESY 17-Mar-2017 FLASH1 RF Gun History RF Guns operated
More informationUpdate 5/19/11. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton
R100 Microphonics i Update 5/19/11 Andrew Hutton Reporting on work by Kirk Davis, Mike Drury, Leigh Harwood, John Hogan, Curt Hovater, Thomas Plawski, Mark Wiseman, etc. The Problem Vibrations of the superconducting
More informationAcceleration of High-Intensity Protons in the J-PARC Synchrotrons. KEK/J-PARC M. Yoshii
Acceleration of High-Intensity Protons in the J-PARC Synchrotrons KEK/J-PARC M. Yoshii Introduction 1. J-PARC consists of 400 MeV Linac, 3 GeV Rapid Cycling Synchrotron (RCS) and 50 GeV Main synchrotron
More informationR. Assmann, CERN/AB. for the Collimation Project 7/12/2007 LHC MAC RWA, LHC MAC 12/07
Plan for Collimator Commissioning R. Assmann, CERN/AB 7/12/2007 for the Collimation Project LHC MAC RWA, LHC MAC 12/07 1) Installation Planning and Performance Reach Collimation is an performance-driven
More informationInitial Beam Phasing of the SRF Cavities in LCLS-II
Introduction Initial Beam Phasing of the SRF Cavities in LCLS-II P. Emma Nov. 28, 2016 One of the more challenging aspects of commissioning the LCLS-II accelerator is in the initial phasing of the SRF
More information(fb) Nevent/year for 50fb -1. s (GeV) ~ ~ qq q=t. ZZ cos <0.8 W + W tt 175GeV 500,00 5,000. Zh 120GeV. 230GeV. HA 400GeV 220GeV 410GeV
10 6 qq q=t (fb) 10 3 + ZZ cos
More informationTHE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING CAVITY
Presented at the 1999 Particle Accelerator Conference, New York City, NY, USA, March 29 April 2 CLNS 99/1614 / SRF 990407-03 THE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING
More informationTHE CRYOGENIC SYSTEM OF TESLA
THE CRYOGENIC SYSTEM OF TESLA S. Wolff, DESY, Notkestr. 85, 22607 Hamburg, Germany for the TESLA collaboration Abstract TESLA, a 33 km long 500 GeV centre-of-mass energy superconducting linear collider
More informationSlide Title. Bulleted Text
Slide Title 1 Slide Outline Title Brief view of the C-AD Complex Review of the RHIC LLRF Upgrade Platform Generic Implementation of a Feedback Loop RHIC Bunch by Bunch Longitudinal Damper Cavity Controller
More informationtwo pairs of dipole steering windings that t inside the quadrupole yoke an RF beam position monitor (BPM) consisting of a pill box RF cavity,
Chapter 6 Quadrupole Package The quadrupole package is shown in Fig. 6.1. It consists of a superferric quadrupole doublet powered in series enclosed in a stainless steel vessel and cooled by 4 K LHe; two
More informationDevelopment of C-Mod FIR Polarimeter*
Development of C-Mod FIR Polarimeter* P.XU, J.H.IRBY, J.BOSCO, A.KANOJIA, R.LECCACORVI, E.MARMAR, P.MICHAEL, R.MURRAY, R.VIEIRA, S.WOLFE (MIT) D.L.BROWER, W.X.DING (UCLA) D.K.MANSFIELD (PPPL) *Supported
More informationWinter Meeting January 14-15, Stephen Wood
Winter Meeting January 14-15, 2015 Stephen Wood Publications and Students Separated Response Functions in Exclusive, Forward Electroproduction on Deuterium Phys. Rev. C 91, 015202 (2015) (from Fpi data)
More informationNonintercepting Diagnostics for Transverse Beam Properties: from Rings to ERLs
Nonintercepting Diagnostics for Transverse Beam Properties: from Rings to ERLs Alex H. Lumpkin Accelerator Operations Division Advanced Photon Source Presented at Jefferson National Accelerator Laboratory
More informationBeam Loss Monitoring (BLM) System for ESS
Beam Loss Monitoring (BLM) System for ESS Lali Tchelidze European Spallation Source ESS AB lali.tchelidze@esss.se March 2, 2011 Outline 1. BLM Types; 2. BLM Positioning and Calibration; 3. BLMs as part
More informationVibration studies of a superconducting accelerating
Vibration studies of a superconducting accelerating module at room temperature and at 4.5 K Ramila Amirikas, Alessandro Bertolini, Wilhelm Bialowons Vibration studies on a Type III cryomodule at room temperature
More informationCircumference 187 m (bending radius = 8.66 m)
4. Specifications of the Accelerators Table 1. General parameters of the PF storage ring. Energy 2.5 GeV (max 3.0 GeV) Initial stored current multi-bunch 450 ma (max 500 ma at 2.5GeV) single bunch 70 ma
More informationDoes the short pulse mode need energy recovery?
Does the short pulse mode need energy recovery? Rep. rate Beam power @ 5GeV 1nC @ 100MHz 500MW Absolutely 1nC @ 10MHz 1nC @ 1MHz 50MW 5MW Maybe 1nC @ 100kHz 0.5MW No Most applications we have heard about
More informationRecent work on Hall A magnets Present and future Jay Benesch January 2018
Recent work on Hall A magnets Present and future Jay Benesch January 2018 1 Sources All of the information contained herein can be found in much more detail in the following Tech Notes: 16-043 (SoLID),
More informationRF Upgrade at DELTA. P. Hartmann DELTA, TU Dortmund
RF Upgrade at DELTA P. Hartmann DELTA, TU Dortmund DELTA parameters: Personnel: Beam energy: 550 MeV 1.5 GeV Beam current: 130mA @ 1.5GeV Beam lifetime: 12h @ 130 ma Availability: 95 % Operational: 3000
More informationStatus and Future Perspective of the HIE-ISOLDE Project
Status and Future Perspective of the HIE-ISOLDE Project International Particle Accelerator Conference, IPAC 12 New Orleans, Louisiana, USA, May 20-25, 2012 Yacine.Kadi@cern.ch OUTLINE Scope of HIE-ISOLDE
More informationElectron Beam Properties and Instrumentation MOLLER Director s Review, Jan. 14, 2010 Mark Pitt, Virginia Tech
Electron Beam Properties and Instrumentation MOLLER Director s Review, Jan. 14, 2010 Mark Pitt, Virginia Tech This talk will focus on the electron beam properties and beam instrumentation requirements
More informationLUCX - THZ PROGRAM: OVERVIEW AND PROSPECTS
LUCX - THZ PROGRAM: OVERVIEW AND PROSPECTS A. Aryshev On behalf of QB group and THz collaboration 14 Outline THz project overview LUCX activity LUCX Projects Overview THz program LUCX Laser system LUCX
More informationFLASH performance after the upgrade. Josef Feldhaus
FLASH performance after the upgrade Josef Feldhaus European XFEL / HASYLAB Users Meeting DESY, January 27, 2011 Upgrade 2009 / 2010 > Upgrade shutdown: September 2009 February 2010 exchanged RF stations
More information3 General layout of the XFEL Facility
3 General layout of the XFEL Facility 3.1 Introduction The present chapter provides an overview of the whole European X-Ray Free-Electron Laser (XFEL) Facility layout, enumerating its main components and
More informationDemonstration of exponential growth and saturation at VUV wavelengths at the TESLA Test Facility Free-Electron Laser. P. Castro for the TTF-FEL team
Demonstration of exponential growth and saturation at VUV wavelengths at the TESLA Test Facility Free-Electron Laser P. Castro for the TTF-FEL team 100 nm 1 Å FEL radiation TESLA Test Facility at DESY
More informationBeam Control: Timing, Protection, Database and Application Software
Beam Control: Timing, Protection, Database and Application Software C.M. Chu, J. Tang 储中明 / 唐渊卿 Spallation Neutron Source Oak Ridge National Laboratory Outline Control software overview Timing system Protection
More informationUpper limit of the electron beam energy at the CEBAF 2D injector spectrometer and its functionality
Upper limit of the electron beam energy at the CEBAF 2D injector spectrometer and its functionality Jonathan Dumas 1,2, Joe Grames 2, Eric Voutier 1 December 16, 28 JLAB-TN-8-86 1 Laboratoire de Physique
More informationFREIA Facility for Research Instrumentation and Accelerator Development Infrastructure and Control Architecture
FREIA Facility for Research Instrumentation and Accelerator Development Infrastructure and Control Architecture Konrad Gajewski 10 September 2013, Uppsala Why FREIA? Several circumstances test stand for
More informationESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University
ESS RF Development at Uppsala University Roger Ruber for the FREIA team Uppsala University ESS-UU Collaboration 2009 ESS and UU start discussion on 704 MHz RF development proposal for ESS dedicated test
More informationOverview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University
Overview of ERL Projects: SRF Issues and Challenges Matthias Liepe Cornell University Overview of ERL projects: SRF issues and challenges Slide 1 Outline Introduction: SRF for ERLs What makes it special
More informationAttosecond Diagnostics of Muti GeV Electron Beams Using W Band Deflectors
Attosecond Diagnostics of Muti GeV Electron Beams Using W Band Deflectors V.A. Dolgashev, P. Emma, M. Dal Forno, A. Novokhatski, S. Weathersby SLAC National Accelerator Laboratory FEIS 2: Femtosecond Electron
More informationLCLS-II SXR Undulator Line Photon Energy Scanning
LCLS-TN-18-4 LCLS-II SXR Undulator Line Photon Energy Scanning Heinz-Dieter Nuhn a a SLAC National Accelerator Laboratory, Stanford University, CA 94309-0210, USA ABSTRACT Operation of the LCLS-II undulator
More informationProgress in High Gradient Accelerator Research at MIT
Progress in High Gradient Accelerator Research at MIT Presented by Richard Temkin MIT Physics and Plasma Science and Fusion Center May 23, 2007 MIT Accelerator Research Collaborators MIT Plasma Science
More informationBEPCII-THE SECOND PHASE CONSTRUCTION OF BEIJING ELECTRON POSITRON COLLIDER
BEPCII-THE SECOND PHASE CONSTRUCTION OF BEIJING ELECTRON POSITRON COLLIDER C. Zhang, G.X. Pei for BEPCII Team IHEP, CAS, P.O. Box 918, Beijing 100039, P.R. China Abstract BEPCII, the second phase construction
More informationCommissioning of National Synchrotron Light Source-II (NSLS-II) Fast Orbit Feedback System
Commissioning of National Synchrotron Light Source-II (NSLS-II) Fast Orbit Feedback System 15 th ICALEPCS 2015, Melbourne, Australia K. Ha, Y. Tian, L. Yu, W. Cheng, L. Dalesio W. Levine, University of
More informationTuning systems for superconducting cavities at Saclay
Tuning systems for superconducting cavities at Saclay 1 MACSE: 1990: tuner in LHe bath at 1.8K TTF: 1995 tuner at 1.8K in the insulating vacuum SOLEIL: 1999 tuner at 4 K in the insulating vacuum Super-3HC:
More informationHardware Commissioning
Hardware Commissioning an update the status of the documentation the report on the resources the programme of the coming year Roberto Saban on behalf of the Hardware Commissioning Working Group status
More informationDesign of the magnets for the MAX IV project. Martin Johansson, Beam Dynamics meets Magnets-II workshop, Bad Zurzach, Dec.
Design of the magnets for the MAX IV project Martin Johansson, Beam Dynamics meets Magnets-II workshop, Bad Zurzach, 01-04 Dec. 2014 MAX IV 3 GeV ring magnets key aspects: Relatively small magnet aperture
More informationLight Source Diagnostics. Hywel Owen ASTEC Daresbury Laboratory
Light Source Diagnostics Hywel Owen ASTEC Daresbury Laboratory This Talk Not a review of light source diagnostics Good summaries at EPAC/PAC/DIPAC, etc. J.Safranek (ICALHEPS 99) J.Clarke (EPAC 94) R.Hettel
More informationDark current Monitor for the European XFEL D. Lipka, W. Kleen, J. Lund-Nielsen, D. Nölle, S. Vilcins, V. Vogel; DESY Hamburg
Dark current Monitor for the European XFEL D. Lipka, W. Kleen, J. Lund-Nielsen, D. Nölle, S. Vilcins, V. Vogel; DESY Hamburg Content 2 Dark current Principle of detecting weakly charged bunches with resonator
More informationElectron Cloud Studies in the Fermilab Main Injector using Microwave Transmission
Electron Cloud Studies in the Fermilab Main Injector using Microwave Transmission J. Charles Thangaraj on behalf of E-cloud team @ Fermilab (B. Zwaska, C. Tan, N. Eddy,..) p ω c ω ω Microwave measurement
More informationUsing Higher Order Modes in the Superconducting TESLA Cavities for Diagnostics at DESY
Using Higher Order Modes in the Superconducting TESLA Cavities for Diagnostics at FLASH @ DESY N. Baboi, DESY, Hamburg for the HOM team : S. Molloy 1, N. Baboi 2, N. Eddy 3, J. Frisch 1, L. Hendrickson
More informationTHz Pump Beam for LCLS. Henrik Loos. LCLS Hard X-Ray Upgrade Workshop July 29-31, 2009
Beam for LCLS Henrik Loos Workshop July 29-31, 29 1 1 Henrik Loos Overview Coherent Radiation Sources Timing THz Source Performance 2 2 Henrik Loos LCLS Layout 6 MeV 135 MeV 25 MeV 4.3 GeV 13.6 GeV σ z.83
More informationMOLLER/PREX Detector Development
MOLLER/PREX Detector Development Dustin McNulty Idaho State University mcnulty@jlab.org October 31, 2015 Introduction: Integrating detectors for PVeS PVES expts measure tiny asymmetries and require large
More informationLARGE SCALE TESTING OF SRF CAVITIES AND MODULES
LARGE SCALE TESTING OF SRF CAVITIES AND MODULES Jacek Swierblewski IFJ PAN Krakow IKC for the XFEL Introduction IFJ PAN 2 Institute of Nuclear Physics (IFJ) located in Kraków, Poland was founded in 1955
More information1 Status of the Hall A Møller Polarimeter
1 Status of the Hall A Møller Polarimeter 1 O. Glamazdin, 2 E. Chudakov, 2 J. Gomez, 1 R. Pomatsalyuk, 1 V. Vereshchaka, 2 J. Zhang 1 National Science Center Kharkov Institute of Physics and Technology,
More informationThe HOM measurement of a TESLA cavity (Z84) for HOM-BPM and cavity alignment
The HOM measurement of a TESLA cavity (Z84) for HOM-BPM and cavity alignment Ken.Watanabe:GUAS/AS (KEK) : presenter Hitoshi.Hayano, Shuichi.Noguchi, Eiji.Kako, Toshio.Shishido (KEK) Joint DESY and University
More informationTransverse Wakefields and Alignment of the LCLS-II Kicker and Septum Magnets
Transverse Wakefields and Alignment of the LCLS-II Kicker and Septum Magnets LCLS-II TN-16-13 12/12/2016 P. Emma, J. Amann,K. Bane, Y. Nosochkov, M. Woodley December 12, 2016 LCLSII-TN-XXXX 1 Introduction
More informationR100 Microphonics. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton
R100 Microphonics Andrew Hutton Reporting on work by Kirk Davis, Mike Drury, Leigh Harwood, John Hogan, Kurt Hovater, Thomas Plawski, Mark Wiseman, etc. The Problem Vibrations of the superconducting cavities
More informationBESSY VSR: SRF challenges and developments for a variable pulse-length next generation light source
BESSY VSR: SRF challenges and developments for a variable pulse-length next generation light source Institut SRF - Wissenschaft und Technologie (FG-ISRF) Adolfo Vélez et al. SRF17 Lanzhou, 17-21/7/2017
More informationStretched Wire Test Setup 1)
LCLS-TN-05-7 First Measurements and Results With a Stretched Wire Test Setup 1) Franz Peters, Georg Gassner, Robert Ruland February 2005 SLAC Abstract A stretched wire test setup 2) has been implemented
More informationSPS Crab Cavity Validation Run ( )
SPS Crab Cavity Validation Run (2017-2018) Alick Macpherson BE-RF-SRF Acknowledgments Marton Ady, Vincent Baglin, Philippe Baudrenghien, Krzyzstof Brodzinski, Rama Calaga, Ofelia Capatina, Frederic Galleazzi,
More information