Update 5/19/11. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton

Size: px
Start display at page:

Download "Update 5/19/11. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton"

Transcription

1 R100 Microphonics i Update 5/19/11 Andrew Hutton Reporting on work by Kirk Davis, Mike Drury, Leigh Harwood, John Hogan, Curt Hovater, Thomas Plawski, Mark Wiseman, etc.

2 The Problem Vibrations of the superconducting cavities (microphonics) change the frequency of the cavity Because the resonant frequency of the cavity is very narrow, the cavity can go off resonance This increases the fraction of RF power that is reflected back from the cavity More RF power is needed to provide the required gradient RF control module can lose lock Loses ability to control lthe cavity

3 R100, C100 cavities are nominally identical No stiffening rings Welded into helium vessel R100 cavities were made at JLab C100 00cavities were eemade by RI Anecdotal evidence that RI cavities arestifferthan than JLab cavities Work hardening? Hardware Description

4 Numbers Admiral cryomodule in the FEL 1 Hz Admiral is now installed in CEBAF at SL21 Renaissance in CMTF 0.5 Hz HTB with 2 C100 cavities in CMTF 2 Hz R100 in CMTF 7 20 Hz Spec for C100 in CEBAF ~ 5 Hz CMTF Cryo Module Test Facility in the Test Lab

5 Mechanical Description Tuning force Tune cavity in tension SST, Al and Ti construction Fulcrum bar (2) Warm drive components (not shown) Pivot-arm(2) Untuned Position Tuned Position Tension shaft Compression shaft Jack arms (4) Fulcrum bars Fulcrum bars Tuner Assy w/cavity Pivot-arms(4) How the Tuner Works Jack arms (4) Cryomodule Design Review 21 May, 2007

6 Design Changes Interface with helium vessel has been redesigned to fit available space Reduced hardware count/type No design change in tuner mechanism No design change in warm drive components SL21/FEL03 Pivot-Arm C100 Pivot-Arm Al casting Al Plate SST tab welded to helium vessel Cryomodule Design Review 21 May, 2007

7 Update: Tuner Stand We have a tuner test stand that will be used to measure vibration modes Cavity has been remeasured for field flatness Tests are about to start

8 Example of Data 13 Hz vibration prominent Variable during the day Likely noise in CMTF* 2 Resonances ~20 Hz 2 Resonances ~45 Hz Both likely to be cavity resonances * Breaking news: 13 Hz associated with heavy return gas load to Kinney pump Update identification still unclear Kirk Davis, Mike Drury

9 Two possible causes 1. Higher vibrations in the Test cave Priority 1 Why Historically ~twice as bad as the CEBAF tunnel Is it worse now due to TEDF or cryogenics changes? 2. Cryomodule more susceptible to vibrations Cavities floppier? Tuners, etc. not as well supported? First priority is to determine the leading cause

10 Background R100 in CMTF Most noise sources <60Hz except line harmonics Must avoid120hz

11 Background R100 in CMTF If we drive all lines below 1 Hz better, but not in spec Leigh Harwood Intermittent 13Hz is a problem but line is not a resonance

12 Frequency Shift 13 Hz noise masks effect of other driving terms 25 Hz

13 Comparison of Noise Terms Excitation Terms?

14 CEBAF Tunnel at SL21 Baseplate Vibration Measurement

15 CMTF at R100 Baseplate Vibration Measurement low frequency noise (<30 Hz) significantly worse at CMTF

16 Primary Cryogenic Return Measurement CEBAF tunnel at SL21 Noise level ~3 times stronger than baseplate

17 Primary Cryogenic Return Measurement CMTF at R Hz Noise level ~3 times stronger than baseplate Noise level ~3 times stronger than CEBAF Tunnel

18 R100 is currently in the CMTF Cryomodule vs Environment Installation planned in CEBAF Zone SL23 Admiral is currently in CEBAF zone SL21 Use a vibrator near both cryomodules to measure response to external vibrationsof of knownfrequency and amplitude If response is similar, problem is CMTF environment R100 should ldbe OK in CEBAF If response is different, the frequency can be correlated to knownmechanicaldifferences between the cryomodules Tells us where to look to fix R100 (and therefore C100) First tests in CMTF yesterday swing, more this evening When procedure is wrung out, will repeat in CEBAF

19 Hammer response at Baseplate R100 is ~100 times more responsive than the Admiral

20 Hammer response at Primary Cryo Return R100 is ~10 more responsive than the Admiral Admiral Response at Primary Cryo Return ~10 times Admiral response at Baseplate

21 Piezo Transfer Function

22 Piezo Transfer Function - Admiral

23 Piezo Transfer Function R100 Low Frequency plateau is ~8db higher Resonant Response

24 Priority 2 Develop Mechanical Solutions Some possible mechanical solutions can be tested now Increase lateral stabilization of tuner stack Add vibration damping pads under the cryomodule feet Both should be tested with the vibrator Develop ideas for mechanical fixes SNS cavities had spider support Can we retrofit? Canweuse wires under tension? Update Prototype spider support being built (takes two weeks) Mark Wiseman, Kirk Davis, Mike Drury

25 Priority 2 Develop Electronic Solutions Can new Digital RF Controller stabilize cavities Successful up to ~8 MV/m takes 2.8kW Can stabilize cavity at 15 MV/m but only for ~1 second Breaking news without 13 Hz can lock up to 19 MV/m Measure the response of the individual cavities to the piezo electric transducers (PZTs) installed on the tuners Also affects neighboring cavities (only ~5 db isolation) Use the PZTs to try and damp the microphonics Try and use Lorentz detuning (expansion of cavity as RF power increases) to feedback on microphonics Curt Hovater, Thomas Plawski

26 Priority 3 Gather Data A lot of data is being gathered to be evaluated later Every cavity has been characterized more than once Use PZTs as listening devices Are cavity oscillations in sync? Measure CMTF ground motion at regular intervals in a day Try and identify source Kinney? Mechanical vibration? Cryogen oscillations? Update: Will use Test Lab power outage to try and identify if source (Paul Powers)

27 12 GeV Project Status C100 1 and C100 2 assembly is proceeding On track for installation into CEBAF as planned String assembly of C100 3 is ready to begin On hold waiting for more information from R100 Welding of helium vessels onto cavities is on hold Pending decision on whether mechanicalsupport is required Pending decision on whether mechanical support is required ( spider )

28 Outlook (Andrew s opinion) Problem is serious, but not intractable Solution will most likely be a combination of several different fixes My preference is for passive fixes first, feedback second I do not see a reason to advance R100 installation I expect modified R100 to be installed in CEBAF as planned Commissioning i i order may change???? We will be judged by how well we address this problem not by the problem itself

29 As presented last week by John Hogan Install R100 in SL21 slot Measure microphonics Remove R100 Install C100 1 in SL21 slot Measure microphonics i Remove C100 1 Take to CMTF for standard commissioning Current Plan Install C100 1 as foreseen in original 6MSD planning

R100 Microphonics. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton

R100 Microphonics. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton R100 Microphonics Andrew Hutton Reporting on work by Kirk Davis, Mike Drury, Leigh Harwood, John Hogan, Kurt Hovater, Thomas Plawski, Mark Wiseman, etc. The Problem Vibrations of the superconducting cavities

More information

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

R.Bachimanchi, IPAC, May 2015, Richmond, VA

R.Bachimanchi, IPAC, May 2015, Richmond, VA 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

ABSTRACT 1 CEBAF UPGRADE CAVITY/CRYOMODULE

ABSTRACT 1 CEBAF UPGRADE CAVITY/CRYOMODULE Energy Content (Normalized) SC Cavity Resonance Control System for the 12 GeV Upgrade Cavity: Requirements and Performance T. Plawski, T. Allison, R. Bachimanchi, D. Hardy, C. Hovater, Thomas Jefferson

More information

SNS CRYOMODULE PERFORMANCE*

SNS CRYOMODULE PERFORMANCE* SNS CRYOMODULE PERFORMANCE* J. Preble*, I. E. Campisi, E. Daly, G. K. Davis, J. R. Delayen, M. Drury, C. Grenoble, J. Hogan, L. King, P. Kneisel, J. Mammosser, T. Powers, M. Stirbet, H. Wang, T. Whitlatch,

More information

Digital LLRF Test on the Renascence Cryomodule

Digital LLRF Test on the Renascence Cryomodule Digital LLRF Test on the Renascence Cryomodule Trent Allison, Rama Bachimanchi, Curt Hovater, John Musson and Tomasz Plawski Introduction The Renascence cryomodule was the first opportunity for testing

More information

Microphonics. T. Powers

Microphonics. T. Powers Microphonics T. Powers What is microphonics? Microphonics is the time domain variation in cavity frequency driven by external vibrational sources. A 1.5 GHz structure 0.5 m long will change in frequency

More information

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University Overview of ERL Projects: SRF Issues and Challenges Matthias Liepe Cornell University Overview of ERL projects: SRF issues and challenges Slide 1 Outline Introduction: SRF for ERLs What makes it special

More information

RENASCENCE * PERFORMANCE AND PROBLEMS ON FIRST TEST Feedthrough leaks sub 70 K. End group quenching

RENASCENCE * PERFORMANCE AND PROBLEMS ON FIRST TEST Feedthrough leaks sub 70 K. End group quenching Proceedings of SRF27, Peking Univ., Beijing, China PERFORMANCE OF THE CEBAF PROTOTYPE CRYOMODULE RENASCENCE * C. E. Reece, E. F. Daly, G. K. Davis, M. Drury, W. R. Hicks, J. Preble, H. Wang # Jefferson

More information

Tuning systems for superconducting cavities at Saclay

Tuning systems for superconducting cavities at Saclay Tuning systems for superconducting cavities at Saclay 1 MACSE: 1990: tuner in LHe bath at 1.8K TTF: 1995 tuner at 1.8K in the insulating vacuum SOLEIL: 1999 tuner at 4 K in the insulating vacuum Super-3HC:

More information

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY Low-Level RF S. Simrock, DESY Outline Scope of LLRF System Work Breakdown for XFEL LLRF Design for the VUV-FEL Cost, Personpower and Schedule RF Systems for XFEL RF Gun Injector 3rd harmonic cavity Main

More information

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT G. Olry, J-L. Biarrotte, S. Blivet, S. Bousson, C. Commeaux, C. Joly, T. Junquera, J. Lesrel, E. Roy,

More information

5.5 SNS Superconducting Linac

5.5 SNS Superconducting Linac JP0150514 ICANS - XV 15 th Meeting of the International Collaboration on Advanced Neutron Sources November 6-9, 2000 Tsukuba, Japan Ronald M. Sundelin Jefferson Lab* 5.5 SNS Superconducting Linac 12000

More information

SUPERCONDUCTING PROTOTYPE CAVITIES FOR THE SPALLATION NEUTRON SOURCE (SNS) PROJECT *

SUPERCONDUCTING PROTOTYPE CAVITIES FOR THE SPALLATION NEUTRON SOURCE (SNS) PROJECT * SUPERCONDUCTING PROTOTYPE CAVITIES FOR THE SPALLATION NEUTRON SOURCE (SNS) PROJECT * G. Ciovati, P. Kneisel, J. Brawley, R. Bundy, I. Campisi, K. Davis, K. Macha, D. Machie, J. Mammosser, S. Morgan, R.

More information

THE CRYOGENIC SYSTEM OF TESLA

THE CRYOGENIC SYSTEM OF TESLA THE CRYOGENIC SYSTEM OF TESLA S. Wolff, DESY, Notkestr. 85, 22607 Hamburg, Germany for the TESLA collaboration Abstract TESLA, a 33 km long 500 GeV centre-of-mass energy superconducting linear collider

More information

High Power Couplers for TTF - FEL

High Power Couplers for TTF - FEL High Power Couplers for TTF - FEL 1. Requirements for High Power Couplers on superconducting Cavities 2. Characteristics of pulsed couplers 3. Standing wave pattern in the coaxial coupler line 4. Advantages

More information

Direct Digital Down/Up Conversion for RF Control of Accelerating Cavities

Direct Digital Down/Up Conversion for RF Control of Accelerating Cavities Direct Digital Down/Up Conversion for RF Control of Accelerating Cavities C. Hovater, T. Allison, R. Bachimanchi, J. Musson and T. Plawski Introduction As digital receiver technology has matured, direct

More information

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM FOR THE EUROPEAN XFEL Julien Branlard, for the LLRF team TALK OVERVIEW 2 Introduction Brief reminder about the XFEL LLRF system Commissioning goals

More information

LORENTZ FORCE DETUNING ANALYSIS OF THE SPALLATION NEUTRON SOURCE (SNS) ACCELERATING CAVITIES *

LORENTZ FORCE DETUNING ANALYSIS OF THE SPALLATION NEUTRON SOURCE (SNS) ACCELERATING CAVITIES * LORENTZ FORCE DETUNING ANALYSIS OF THE SPALLATION NEUTRON SOURCE (SNS) ACCELERATING CAVITIES * R. Mitchell, K. Matsumoto, Los Alamos National Lab, Los Alamos, NM 87545, USA G. Ciovati, K. Davis, K. Macha,

More information

Waveguide Arc Restrike Test Results Abstract Background

Waveguide Arc Restrike Test Results Abstract Background Waveguide Arc Restrike Test Results Tom Powers, Doug Curry, Kirk Davis, Larry King, and Mike Tiefenback Thomas Jefferson National Accelerator Facility (Test dates July 6, 2004 through September 2, 2004)

More information

Vibration studies of a superconducting accelerating

Vibration studies of a superconducting accelerating Vibration studies of a superconducting accelerating module at room temperature and at 4.5 K Ramila Amirikas, Alessandro Bertolini, Wilhelm Bialowons Vibration studies on a Type III cryomodule at room temperature

More information

Digital Self Excited Loop Implementation and Experience. Trent Allison Curt Hovater John Musson Tomasz Plawski

Digital Self Excited Loop Implementation and Experience. Trent Allison Curt Hovater John Musson Tomasz Plawski Digital Self Excited Loop Implementation and Experience Trent Allison Curt Hovater John Musson Tomasz Plawski Overview Why Self Excited Loop? Algorithm Building Blocks Hardware and Sampling Digital Signal

More information

Examination of Microphonic Effects in SRF Cavities

Examination of Microphonic Effects in SRF Cavities Examination of Microphonic Effects in SRF Cavities Christina Leidel Department of Physics, Ohio Northern University, Ada, OH, 45810 (Dated: August 13, 2004) Superconducting RF cavities in Cornell s proposed

More information

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University ESS RF Development at Uppsala University Roger Ruber for the FREIA team Uppsala University ESS-UU Collaboration 2009 ESS and UU start discussion on 704 MHz RF development proposal for ESS dedicated test

More information

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension XFEL Cryo System Possible extension 1 st stage Project X Collaboration Meeting, FNAL September 8-9, 2010 (XFEL WP10 & WP13) Outline 2 XFEL accelerator structure TESLA technology Basic cryogenic parameters

More information

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute CEBAF waveguide absorbers R. Rimmer for JLab SRF Institute Outline Original CEBAF HOM absorbers Modified CEBAF loads for FEL New materials for replacement loads High power loads for next generation FELs

More information

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES LARGE SCALE TESTING OF SRF CAVITIES AND MODULES Jacek Swierblewski IFJ PAN Krakow IKC for the XFEL Introduction IFJ PAN 2 Institute of Nuclear Physics (IFJ) located in Kraków, Poland was founded in 1955

More information

RF System LSD Work. William Merz

RF System LSD Work. William Merz RF System LSD Work William Merz LSD Re-Baseline Review Jefferson Lab Thomas Jefferson National Accelerator Facility Page 1 Outline What I will talk about 12 GEV RF power system installation and commissioning

More information

SNS LLRF Design Experience and its Possible Adoption for the ILC

SNS LLRF Design Experience and its Possible Adoption for the ILC SNS LLRF Design Experience and its Possible Adoption for the ILC Brian Chase SNS - Mark Champion Fermilab International Linear Collider Workshop 11/28/2005 1 Why Consider the SNS System for ILC R&D at

More information

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF Y. Yamamoto #, H. Hayano, E. Kako, T. Matsumoto, S. Michizono, T. Miura, S. Noguchi, M. Satoh, T. Shishidio, K. Watanabe, KEK, Tsukuba,

More information

A 3 GHz SRF reduced-β Cavity for the S-DALINAC

A 3 GHz SRF reduced-β Cavity for the S-DALINAC A 3 GHz SRF reduced-β Cavity for the S-DALINAC D. Bazyl*, W.F.O. Müller, H. De Gersem Gefördert durch die DFG im Rahmen des GRK 2128 20.11.2018 M.Sc. Dmitry Bazyl TU Darmstadt TEMF Upgrade of the Capture

More information

LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC. Marc Ross 13 January 2014

LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC. Marc Ross 13 January 2014 LCLS-II SRF Linac Multi-lab partnership to build CW FEL based on SRF at SLAC Marc Ross 13 January 2014 What are the technical and practical limits for DF? 1st limit: Heat load at 2K for each cryomodule

More information

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY G. Devanz, D. Braud, M. Desmons, Y. Gasser, E. Jacques, O. Piquet, J. Plouin, J.- P. Poupeau, D. Roudier, P. Sahuquet, CEA-Saclay,

More information

The low level radio frequency control system for DC-SRF. photo-injector at Peking University *

The low level radio frequency control system for DC-SRF. photo-injector at Peking University * The low level radio frequency control system for DC-SRF photo-injector at Peking University * WANG Fang( 王芳 ) 1) FENG Li-Wen( 冯立文 ) LIN Lin( 林林 ) HAO Jian-Kui( 郝建奎 ) Quan Sheng-Wen( 全胜文 ) ZHANG Bao-Cheng(

More information

Cryogenics for Large Accelerators

Cryogenics for Large Accelerators Cryogenics for Large Accelerators Dr. Sergiy Putselyk Deutsches Elektronen-Synchrotron (DESY) MKS Division Notkestrasse 85 22607 Hamburg (Germany) Phone: +49 40 89983492 Fax: +49 40 89982858 E-Mail: Sergiy.Putselyk@desy.de

More information

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF Project X Cavity RF and mechanical design T. Khabiboulline, FNAL/TD/SRF TTC meeting on CW-SRF, 2013 Project X Cavity RF and mechanical design T 1 High ß Low ß 0.5 HWR SSR1 SSR2 0 1 10 100 1 10 3 1 10 4

More information

Design & Implementation of the LLRF System for LCLS-II. Andy Benwell (SLAC Spokesperson) LLRF 2017 October 16, 2017

Design & Implementation of the LLRF System for LCLS-II. Andy Benwell (SLAC Spokesperson) LLRF 2017 October 16, 2017 Design & Implementation of the LLRF System for LCLS-II Andy Benwell (SLAC Spokesperson) LLRF 2017 October 16, 2017 Outline LCLS II LCLS II LLRF Requirements/Parameters LLRF Team LLRF Design Testing efforts

More information

Amit Roy Director, IUAC

Amit Roy Director, IUAC SUPERCONDUCTING RF DEVELOPMENT AT INTER-UNIVERSITY ACCELERATOR CENTRE (IUAC) (JOINT PROPOSAL FROM IUAC & Delhi University (DU)) Amit Roy Director, IUAC to be presented by Kirti Ranjan (DU / Fermilab) Overview

More information

Frequency Tuning and RF Systems for the ATLAS Energy Upgrade. Gary P. Zinkann

Frequency Tuning and RF Systems for the ATLAS Energy Upgrade. Gary P. Zinkann Frequency Tuning and RF Systems for the ATLAS Energy Upgrade Outline Overview of the ATLAS Energy Upgrade Description of cavity Tuning method used during cavity construction Description and test results

More information

Review on Progress in RF Control Systems. Cornell University. Matthias Liepe. M. Liepe, Cornell U. SRF 2005, July 14

Review on Progress in RF Control Systems. Cornell University. Matthias Liepe. M. Liepe, Cornell U. SRF 2005, July 14 Review on Progress in RF Control Systems Matthias Liepe Cornell University 1 Why this Talk? As we all know, superconducting cavities have many nice features one of which is very high field stability. Why?

More information

SLHiPP-2, Catania, Italy. A cryogenic system for the MYRRHA linac. Nicolas Chevalier, Tomas Junquera

SLHiPP-2, Catania, Italy. A cryogenic system for the MYRRHA linac. Nicolas Chevalier, Tomas Junquera SLHiPP-2, Catania, Italy A cryogenic system for the MYRRHA linac Nicolas Chevalier, Tomas Junquera 04.05.2012 Outline 1 ) Cryogenic system requirements : heat loads 2 ) Temperature optimization, possible

More information

Piezoelectric multilayer triaxial accelerometer

Piezoelectric multilayer triaxial accelerometer Piezoelectric multilayer triaxial accelerometer C. Mangeot 1, B. Andersen 1, and M. Havránek 2 1 Noliac Motion, 2 Noliac Systems Hejreskovvej 18, Kvistgaard, 3470, Denmark Version: 200705 The accelerometer

More information

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE M. Liepe, S. Belomestnykh, E. Chojnacki, Z. Conway, V. Medjidzade, H. Padamsee, P. Quigley, J. Sears, V. Shemelin, V. Veshcherevich,

More information

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ERL 09 8 th 12 th June 2009 ALICE Accelerators and Lasers In Combined Experiments Brief Description ALICE Superconducting

More information

3.9 GHz work at Fermilab

3.9 GHz work at Fermilab 3.9 GHz work at Fermilab + CKM 13-cell cavity Engineering and designing W.-D. Moeller Desy, MHF-sl Protocol of the meeting about 3 rd harmonic cavities during the TESLA collaboration meeting at DESY on

More information

Packaging of Cryogenic Components

Packaging of Cryogenic Components Packaging of Cryogenic Components William J. Schneider Senior Mechanical Engineer Emeritus November 19-23 2007 1 Packaging of Cryogenic Components Day one Introduction and Overview 2 What is important?

More information

QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER*

QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER* QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER* P.N. Prakash and A.Roy Nuclear Science Centre, P.O.Box 10502, New Delhi 110 067, INDIA and K.W.Shepard Physics Division, Argonne National Laboratory,

More information

Phase Drift Budget Analysis for 12 GeV 1497 MHz LLRF System

Phase Drift Budget Analysis for 12 GeV 1497 MHz LLRF System Phase Drift Budget Analysis for 12 GeV 1497 MHz LLRF System John Musson 28-Sept-7 Introduction The 12 GeV upgrade effort included the creation of LLRF Requirements, directed at achieving.4% gradient regulation,.5

More information

LLRF Plans for SMTF. Ruben Carcagno (Fermilab) Nigel Lockyer (University of Pennsylvania) Thanks to DESY, PISA, KEK, Fermilab, SLAC Colleagues

LLRF Plans for SMTF. Ruben Carcagno (Fermilab) Nigel Lockyer (University of Pennsylvania) Thanks to DESY, PISA, KEK, Fermilab, SLAC Colleagues LLRF Plans for SMTF Ruben Carcagno (Fermilab) Nigel Lockyer (University of Pennsylvania) Thanks to DESY, PISA, KEK, Fermilab, SLAC Colleagues Outline Near-term (< 1.5 years) SMTF LLRF plan Long-term (>

More information

DESIGN OPTIONS FOR CEBAF ENERGY UPGRADE

DESIGN OPTIONS FOR CEBAF ENERGY UPGRADE b JLAB-ACT-97-09 DESGN OPTONS FOR CEBAF ENERGY UPGRADE L. Phillips, J. Mammosser, and V. Nguyen;Thomas Jefferson National Accelerator Facility, 12000 Jefferson Avenue, Newport News, VA 23606 USA Abstract

More information

Cavity Tuners. Outline. Tuner overview Concepts and examples. Focus: Fast piezo tuners for ERLs. Advanced piezo tuning.

Cavity Tuners. Outline. Tuner overview Concepts and examples. Focus: Fast piezo tuners for ERLs. Advanced piezo tuning. Cavity Tuners Oliver Kugeler Outline Tuner overview Concepts and examples Focus: Fast piezo tuners for ERLs Advanced piezo tuning ERL workshop 2009, Cornell Objectives for tuners Tune cavity resonance

More information

Third Harmonic Superconducting passive cavities in ELETTRA and SLS

Third Harmonic Superconducting passive cavities in ELETTRA and SLS RF superconductivity application to synchrotron radiation light sources Third Harmonic Superconducting passive cavities in ELETTRA and SLS 2 cryomodules (one per machine) with 2 Nb/Cu cavities at 1.5 GHz

More information

CAGE CAVITY: A LOW COST, HIGH PERFORMANCE SRF ACCELERATING STRUCTURE*

CAGE CAVITY: A LOW COST, HIGH PERFORMANCE SRF ACCELERATING STRUCTURE* CAGE CAVITY: A LOW COST, HIGH PERFORMANCE SRF ACCELERATING STRUCTURE* J. Noonan, T.L. Smith, M. Virgo, G.J. Waldsmidt, Argonne National Laboratory J.W. Lewellen, Los Alamos National Laboratory Abstract

More information

Energy Recovering Linac Issues

Energy Recovering Linac Issues Energy Recovering Linac Issues L. Merminga Jefferson Lab EIC Accelerator Workshop Brookhaven National Laboratory February 26-27, 2002 Outline Energy Recovery RF Stability in Recirculating, Energy Recovering

More information

Cavity development for TESLA

Cavity development for TESLA Cavity development for TESLA Lutz.Lilje@desy.de DESY -FDET- Cavity basics History: Limitations and solutions»material inclusions»weld defects»field emission»increased surface resistance at high field Performance

More information

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Overview ALICE (Accelerators and Lasers In Combined Experiments)

More information

S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members. Inter University Accelerator Centre New Delhi India

S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members. Inter University Accelerator Centre New Delhi India S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members Inter University Accelerator Centre New Delhi 110067 India Highlights of presentation 1. Introduction to Linear accelerator

More information

To produce more powerful and high-efficiency particle accelerator, efforts have

To produce more powerful and high-efficiency particle accelerator, efforts have Measuring Unloaded Quality Factor of Superconducting RF Cryomodule Jian Cong Zeng Department of Physics and Astronomy, State University of New York at Geneseo, Geneseo, NY 14454 Elvin Harms, Jr. Accelerator

More information

Advance on High Power Couplers for SC Accelerators

Advance on High Power Couplers for SC Accelerators Advance on High Power Couplers for SC Accelerators Eiji Kako (KEK, Japan) IAS conference at Hong Kong for High Energy Physics, 2017, January 23th Eiji KAKO (KEK, Japan) IAS at Hong Kong, 2017 Jan. 23 1

More information

TESLA Progress on R1 & R2 issues

TESLA Progress on R1 & R2 issues TESLA Progress on R1 & R2 issues Carlo Pagani Milano & DESY carlo.pagani@desy.de The TESLA Challenge for LC Physical limit at 50 MV/m > 25 MV/m could be obtained Common R&D effort for TESLA Higher conversion

More information

Niowave s Growth and the Role of STTR in its Development

Niowave s Growth and the Role of STTR in its Development Niowave s Growth and the Role of STTR in its Development Terry L. Grimm Niowave, Inc. Lansing MI Presented at National Academies STTR Workshop, Wash DC, May 2015 Outline Superconducting electron linacs

More information

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS J. Teichert, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A.

More information

Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS

Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS Patricia DUCHESNE, Guillaume OLRY Sylvain BRAULT, Sébastien BOUSSON, Patxi DUTHIL, Denis REYNET Institut de Physique Nucléaire d Orsay SRF

More information

Superstructures; First Cold Test and Future Applications

Superstructures; First Cold Test and Future Applications Superstructures; First Cold Test and Future Applications DESY: C. Albrecht, V. Ayvazyan, R. Bandelmann, T. Büttner, P. Castro, S. Choroba, J. Eschke, B. Faatz, A. Gössel, K. Honkavaara, B. Horst, J. Iversen,

More information

CEBAF Overview June 4, 2010

CEBAF Overview June 4, 2010 CEBAF Overview June 4, 2010 Yan Wang Deputy Group Leader of the Operations Group Outline CEBAF Timeline Machine Overview Injector Linear Accelerators Recirculation Arcs Extraction Systems Beam Specifications

More information

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY Abstract HIGH POWER COUPLER FOR THE TESLA TEST FACILITY W.-D. Moeller * for the TESLA Collaboration, Deutsches Elektronen-Synchrotron DESY, D-22603 Hamburg, Germany The TeV Energy Superconducting Linear

More information

2008 JINST 3 S The RF systems and beam feedback. Chapter Introduction

2008 JINST 3 S The RF systems and beam feedback. Chapter Introduction Chapter 4 The RF systems and beam feedback 4.1 Introduction The injected beam will be captured, accelerated and stored using a 400 MHz superconducting cavity system, and the longitudinal injection errors

More information

Snowmass WG5: Superconducting Cavities and Couplers (Draft August 12, 2005 Rong-Li Geng) Topic 1: Cavity Shape

Snowmass WG5: Superconducting Cavities and Couplers (Draft August 12, 2005 Rong-Li Geng) Topic 1: Cavity Shape Snowmass WG5: Superconducting Cavities and Couplers (Draft August 12, 2005 Rong-Li Geng) Topic 1: Cavity Shape Overview The cavity shape determines the fundamental mode as well as the higher order modes

More information

The European Spallation Source. Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013

The European Spallation Source. Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013 The European Spallation Source Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013 Overview The European Spallation Source (ESS) will house the most powerful proton linac ever built. The average

More information

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Approval: Originator: Tor Raubenheimer, Physics Support Lead Date Approved Approver: Marc Ross, Cryogenic System Manager Approver: Jose Chan,

More information

Lab 4. Crystal Oscillator

Lab 4. Crystal Oscillator Lab 4. Crystal Oscillator Modeling the Piezo Electric Quartz Crystal Most oscillators employed for RF and microwave applications use a resonator to set the frequency of oscillation. It is desirable to

More information

C100- Cryomodule Waveguide Temperature Profile and Heat Loads for Applied Heat Stations and RF Power

C100- Cryomodule Waveguide Temperature Profile and Heat Loads for Applied Heat Stations and RF Power JLAB-TN-9-1 March 5,29 C1- Cryomodule Waveguide Temperature Profile and Heat Loads for Applied Heat Stations and RF Power 1. INTRODUCTION Hrishikesh Phadke, Edward Daly A thermal analysis was performed

More information

Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay. Abstract

Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay. Abstract SRF Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay Abstract This report presents the piezo tuner developed at Saclay in the framework of CARE/SRF.

More information

two pairs of dipole steering windings that t inside the quadrupole yoke an RF beam position monitor (BPM) consisting of a pill box RF cavity,

two pairs of dipole steering windings that t inside the quadrupole yoke an RF beam position monitor (BPM) consisting of a pill box RF cavity, Chapter 6 Quadrupole Package The quadrupole package is shown in Fig. 6.1. It consists of a superferric quadrupole doublet powered in series enclosed in a stainless steel vessel and cooled by 4 K LHe; two

More information

Status of superconducting module development suitable for cw operation: ELBE cryostats

Status of superconducting module development suitable for cw operation: ELBE cryostats Status of superconducting module development suitable for cw operation: ELBE cryostats, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A. Winter Forschungszentrum

More information

SUPERCONDUCTING RESONATORS DEVELOPMENT FOR THE FRIB AND ReA LINACS AT MSU: RECENT ACHIEVEMENTS AND FUTURE GOALS

SUPERCONDUCTING RESONATORS DEVELOPMENT FOR THE FRIB AND ReA LINACS AT MSU: RECENT ACHIEVEMENTS AND FUTURE GOALS SUPERCONDUCTING RESONATORS DEVELOPMENT FOR THE FRIB AND ReA LINACS AT MSU: RECENT ACHIEVEMENTS AND FUTURE GOALS A. Facco #+, E. Bernard, J. Binkowski, J. Crisp, C. Compton, L. Dubbs, K. Elliott, L. Harle,

More information

High Order Modes Survey and Mitigation of the CEBAF C100 Cryomodules

High Order Modes Survey and Mitigation of the CEBAF C100 Cryomodules Available online at www.sciencedirect.com ScienceDirect Physics Procedia (2015) 000 000 www.elsevier.com/locate/procedia ICFA mini Workshop on High Order Modes in Superconducting Cavities, HOMSC14 High

More information

ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY

ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY P. A. McIntosh #, R. Bate, C. D. Beard, M. A. Cordwell, D. M. Dykes, S. M. Pattalwar and J. Strachan, STFC Daresbury Laboratory,

More information

PIP-II Superconducting RF Linac Status and Challenges" Leonardo Ristori! ICEC-ICMC Conference, New Delhi! 9 March 2016!!

PIP-II Superconducting RF Linac Status and Challenges Leonardo Ristori! ICEC-ICMC Conference, New Delhi! 9 March 2016!! PIP-II Superconducting RF Linac Status and Challenges" Leonardo Ristori! ICEC-ICMC Conference, New Delhi!! Outline" PIP-II Mission & Strategy! PIP-II SRF Linac Overview! Technical Risk & Mitigation! Indian

More information

Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala

Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala FREIA Report 2012/03 October 2012 DEPARTMENT OF PHYSICS AND ASTRONOMY UPPSALA UNIVERSITY Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala ESS TDR Contribution R. Ruber, T. Ekelöf, R.A. Yogi.

More information

A Comparison of Harmonic Tuning Methods for Load Pull Systems

A Comparison of Harmonic Tuning Methods for Load Pull Systems MAURY MICROWAVE CORPORATION A Comparison of Harmonic Tuning Methods for Load Pull Systems Author: Gary Simpson, MSEE Director of Technical Development in Engineering, Maury Microwave Corporation July 2009

More information

ESS RF Source and Spoke Cavity Test Plan

ESS RF Source and Spoke Cavity Test Plan FREIA Report 2015/01 26 February 2015 DEPARTMENT OF PHYSICS AND ASTRONOMY UPPSALA UNIVERSITY ESS RF Source and Spoke Cavity Test Plan R. Ruber (ed.), A. Bhattacharyya, D. Dancila, T. Ekelöf, J. Eriksson,

More information

THE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING CAVITY

THE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING CAVITY Presented at the 1999 Particle Accelerator Conference, New York City, NY, USA, March 29 April 2 CLNS 99/1614 / SRF 990407-03 THE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING

More information

International Technology Recommendation Panel. X-Band Linear Collider Path to the Future. RF System Overview. Chris Adolphsen

International Technology Recommendation Panel. X-Band Linear Collider Path to the Future. RF System Overview. Chris Adolphsen International Technology Recommendation Panel X-Band Linear Collider Path to the Future RF System Overview Chris Adolphsen Stanford Linear Accelerator Center April 26-27, 2004 Delivering the Beam Energy

More information

Laboratory Report INFN Milano LASA

Laboratory Report INFN Milano LASA Laboratory Report INFN Milano LASA Activities Underway Wire Position Monitor: new generation WPMs mounted on cryomodule and readout connected to control system Piezo Vibration Control: microphonic control

More information

Completion of the first SSR1 cavity for PXIE

Completion of the first SSR1 cavity for PXIE 2013 North American Particle Accelerator Conference Pasadena, CA Completion of the first SSR1 cavity for PXIE Design, Manufacturing and Qualification Leonardo Ristori on behalf of the Fermilab SRF Development

More information

Report of working group 5

Report of working group 5 Report of working group 5 Materials Cavity design Cavity Fabrication Preparatioin & Testing Power coupler HOM coupler Beam line absorber Tuner Fundamental R&D items Most important R&D items 500 GeV parameters

More information

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW*

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW* Presented at the 13th International Workshop on RF Superconductivity, Beijing, China, 2007 SRF 071120-04 OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW* S. Belomestnykh #, CLASSE, Cornell

More information

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team Engineering Challenges and Solutions for MeRHIC Andrew Burrill for the MeRHIC Team Key Components Photoinjector Design Photocathodes & Drive Laser Linac Cavities 703.75 MHz 5 cell cavities 3 rd Harmonic

More information

How Plant Rotating Equipment Resonance Issues Can Affect Reliability and Uptime

How Plant Rotating Equipment Resonance Issues Can Affect Reliability and Uptime How Plant Rotating Equipment Resonance Issues Can Affect Reliability and Uptime Eric Olson, Principal Engineer, Mechanical Solutions, Inc. Maki Onari, Principal Engineer, Mechanical Solutions, Inc. Chad

More information

SC5407A/SC5408A 100 khz to 6 GHz RF Upconverter. Datasheet. Rev SignalCore, Inc.

SC5407A/SC5408A 100 khz to 6 GHz RF Upconverter. Datasheet. Rev SignalCore, Inc. SC5407A/SC5408A 100 khz to 6 GHz RF Upconverter Datasheet Rev 1.2 2017 SignalCore, Inc. support@signalcore.com P R O D U C T S P E C I F I C A T I O N S Definition of Terms The following terms are used

More information

Status of berlinpro and BESSY II Installation of SSA. Helmholtz-Zentrum Berlin for materials and energy (HZB)

Status of berlinpro and BESSY II Installation of SSA. Helmholtz-Zentrum Berlin for materials and energy (HZB) Status of berlinpro and BESSY II Installation of SSA Wolfgang Anders, Helmholtz-Zentrum Berlin for materials and energy (HZB) 19th ESLS-RF Meeting 30.9.-1.10.2015 MaxLab outline BERLinPro Status building

More information

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium Performance of Superconducting Cavities for the European XFEL Detlef Reschke DESY for the EU-XFEL Accelerator Consortium Outline 2 European XFEL Linear Accelerator Cavity Production Vertical Acceptance

More information

Wavelength Control and Locking with Sub-MHz Precision

Wavelength Control and Locking with Sub-MHz Precision Wavelength Control and Locking with Sub-MHz Precision A PZT actuator on one of the resonator mirrors enables the Verdi output wavelength to be rapidly tuned over a range of several GHz or tightly locked

More information

Motivation: ERL based e linac for LHeC

Motivation: ERL based e linac for LHeC Erk Jensen, for the LHeC team and the RF group ERL 2013, BINP, Novosibirsk, 09 Sep 2013 09 Sep 2013 1 Motivation: ERL based e linac for LHeC ( O. Brünings presentation) NB.: This is a 09 Sep 2013 2 Some

More information

PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB

PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB D. Passarelli, J.P. Holzbauer, L. Ristori, FNAL, Batavia, IL 651, USA Abstract In the framework of the Proton

More information

State of the Art in RF Control

State of the Art in RF Control State of the Art in RF Control S. Simrock, DESY LINAC 2004, Lübeck Stefan Simrock DESY Outline RF System Architecture Requirements for RF Control RF Control Design Considerations Design Efforts Worldwide

More information

Varactor-Tuned Oscillators. Technical Data. VTO-8000 Series

Varactor-Tuned Oscillators. Technical Data. VTO-8000 Series Varactor-Tuned Oscillators Technical Data VTO-8000 Series Features 600 MHz to 10.5 GHz Coverage Fast Tuning +7 to +13 dbm Output Power ± 1.5 db Output Flatness Hermetic Thin-film Construction Description

More information

Status and Future Perspective of the HIE-ISOLDE Project

Status and Future Perspective of the HIE-ISOLDE Project Status and Future Perspective of the HIE-ISOLDE Project International Particle Accelerator Conference, IPAC 12 New Orleans, Louisiana, USA, May 20-25, 2012 Yacine.Kadi@cern.ch OUTLINE Scope of HIE-ISOLDE

More information

Current Industrial SRF Capabilities and Future Plans

Current Industrial SRF Capabilities and Future Plans and Future Plans Capabilities in view of Design Engineering Manufacturing Preparation Testing Assembly Taking into operation Future Plans Participate in and contribute to development issues, provide prototypes

More information