1 THE ISRAEL ELECTRIC CORPORATION LTD. ENGINEERING PROJECTS GROUP SPECIFICATION No. 01-1E/S STANDARD SPECIFICATION FOR STANDARD SPECIFICATION FOR CONTRACTOR'S DRAWING AND DATA TRANSMITTAL CONTRACTOR S DRAWING AND DATA TRANSMITTAL TABLE OF CONTENTS SECTION PAGE No. 1. General 2 2. Quality Requirements 4 3. Graphic Scale Prepared Additional by: Requirements V. Tarif... Checked by: Z. Steg Approved by: 5 H. Brener 5. DECEMBER, Mailing of Drawing and Data 6-1-

2 STANDARD SPECIFICATION FOR CONTRACTOR S DRAWING AND DATA TRANSMITTAL TABLE OF CONTENTS SECTION PAGE No. 1. General 2 2. Quality Requirements 4 3. Graphic Scale Documents Transmittals Mailing of Drawing and Data 9 Attachment #1: Document Transmittal Notice. Attachment # 2: Instructions for AUTOCAD Drawings Submitted to IEC. -2-

3 STANDARD SPECIFICATION FOR CONTRACTOR S DRAWING AND DATA TRANSMITTAL (STANDARD 01-1E) 1. GENERAL In accordance with the provisions of the General Conditions and not derogating from the generalities thereof, Contractor s documents, such as: drawings, manuals and instructions (data, certificates, reports, calculations, Bill of Materials etc.), shall be submitted to the Purchaser in accordance with this Standard, except as supplemented in or modified by the Technical Specification (Annexure B ). 1.1 Transmittal Form A transmittal form (example is attached as Attachment # 1) must accompany The Contractor's documents as required in the Specification and shall include all information listed in para 4.2. All transmittals received without a transmittal form containing such information will be returned to the Contractor. The documents shall be transferred by electronic mail or magnetic media, as agreed with the Contractor and a note shall be made on the official document transmittal notice. In addition, hard copies may be submitted and sent by a special courier. 1.2 Documents Review and Approval After award of Contract, all engineering documents such as: drawings, manuals, and instructions (data, certificates, reports, calculations, Bill of Materials etc.) shall be submitted, as required in the Technical Specification, to the Purchaser for review and/or approval. -3-

4 1.2.1 Engineering documents will not be considered for review unless completed in all aspects and thoroughly checked by the Contractor The Purchaser will review the engineering documents for compliance with Contract Technical Specifications and will mark and stamp same to indicate changes or corrections, as required. If changes or corrections are necessary, engineering drawings, manuals, supporting data, Bill of Materials etc., with such changes or corrections noted, will be returned to the Contractor Submittals requiring Purchaser s approval will be returned to Contractor marked as follows: STATUS 1 - NO EXCEPTION TAKEN, THE CONTRACTOR MAY PROCEED WITH FABRICATION OR CONSTRUCTION STATUS 2 - THE CONTRACTOR MAY PROCEED, BASED ON MAKING REVISIONS AS NOTED AND RESUBMIT STATUS 3 - REVISE AS NOTED AND RESUBMIT - HOLD FABRICATION The review and approval of engineering documents by the Purchaser does not relieve the Contractor of any responsibility for errors or omissions in the work carried out. Faulty, incorrect, or incomplete work resulting from submittal errors shall be corrected by the Contractor, irrespective of any prior review by the Purchaser. 1.3 Design Information Design information shall be included on properly identified drawings (see para 4 for required identifying information). The fact that such design information may later be included in instruction and/or operating manuals does not relieve the Contractor from compliance with this requirement. -4-

5 1.4 Instructions and/or Operating Manuals Instructions and/or operating manuals shall be submitted in accordance with the requirements of Annexure "B" - Technical Specification. 1.5 Contractor s Exceptions Any exceptions to this Standard shall be clearly depicted in the Proposal submittal and specifically identified as an exception. 2. QUALITY REQUIREMENTS 2.1 General Documents (drawings, instructions and manuals), submitted to the Purchaser shall be of such quality and with such legibility that hard - copy reproductions may be prepared by the Purchaser with every line, character and letter clearly legible and usable for further reproduction Documents submitted to the Purchaser that do not conform to the requirements of this Specification, shall be subject to rejection by the Purchaser and, upon request, the Contractor shall resubmit conforming documents. If conforming submittals cannot be obtained from source documents, such source documents shall be retraced, redrawn or photographically restored, as may be necessary to meet such requirements. The Contractor s (or its Subcontractors') failure to initially satisfy the legibility quality requirements herein set forth, will not relieve the Contractor (or his Subcontractors) from meeting the required schedule for submittal of drawings and data. -5-

6 3. GRAPHIC SCALE All drawings drawn to scale shall have a graphic scale so that any proportional blowback from the original microfilm may be scaled. 4. DOCUMENT TRANSMITTALS Document Formats: Documents included in the "Documents Transmittal" list should be provided in a separate copy, in its original size and in one of the following formats: TIF, DOC, RTF, XLS, PDF Drawings having VECTOR parameters and included in the "Document Transmittal" list should be provided in a separate copy, in its original size and in AUTOCAD 2000 DWG format Instructions for AUTOCAD Drawings submitted to IEC, are attached as Attachment # Dimensional System: The dimensions in all submittals shall be in the metric system. The English equivalent of principal dimensions and tolerances may be indicated in adjacent brackets. -6-

7 4.3. Meta Data File: Each "Documents Transmittal" should be submitted to IEC, attached with a meta data file in EXCEL formats, including the following inputs: Description Type (Drawing, Instruction, Manual or Other) Doc./Draw. No. Version Title/Description Design Field (Mechanical, Civil, Electrical) Purpose of Sending (Approval, Information) File Name (Attachments Files) Original Size (A0, A1, A2, A3.) Drawing Scale (1:1, 1:5, 1:100 ) Manufacturer Manufacturer type (Main Contractor, Sub Contractor) System Sub project Content (Physical breakdown) Contract code IEC W.B.S (Work breakdown structure) Document Transmittal Number (DT/SI) UNID (Sequence Number Of Manufacturer) Transmittal No. Transmittal date Data Type string Date Size Values value=0 Drawing value=1 Instruction value=2 Manual value=3 Other value=m (Mechanical) value=c (Civil) value=e (Electrical) (Information, Approval) (A0,A1,A2,A3,A4) (1:1, 1:2, 1:5, 1:10, 1:25, 1:50, 1:100, etc ) value=m (Main contractor) value=s (Sub contractor) 4.4. Document Viewing: It should be possible to open each type of document using the suitable software programs running on Windows XP operating system and Office XP: IMAGINATION 7.1, ACROBAT 4.0, OFFICE 2000, AUTOCAD 2000, VOLOVIEW EXPRESS

8 4.5 Sending Documents "Documents Transmittal" should be sent by the following ways: - E - Mail using MS OUTLOOK. Each E - Mail should not exceed the size of 3 MB. - Compact Disk Technical Data Lists Technical data lists for Equipment, Instruments, Cables, etc., and Bill of Materials, included in the documents should be attached to the transmittal, using one of the following formats: EXCEL. All data should be compatible with IEC's information systems. The following fields are required: Item Identification: Each Drawing or Specification for a part, component, assembly, subassembly or any other item supplied in accordance with the Project Specification shall specify the location and methods for identifying the item. Identification shall include at least the following: - Drawing and Revision number - Part number - Serial number (if applicable) - Purchaser's name - Project name - Unit number - Purchaser's order - Contract number - Contractor's name -8-

9 4.8 Drawing Changes: Identification of changes on all drawings from the previous issue shall be shown on each drawing. 4.9 Drawing Number: Each separate drawing submitted to the Purchaser shall have a discrete drawing number for correct identification. Duplicate pieces of equipment such as valves, shall not be grouped on one drawing. They may utilize the same reference drawing but each valve shall have a discrete identification number Submittal Language: All submittals shall be in English or Hebrew (option of the Contractor) WBS code (if applicable) The Contractor shall add on the drawing/document title or on the approval stamp, IEC's WBS (Work Breakdown Structure) Code. IEC's WBS code is comprised of: Subproject number, Physical Breakdown (equipment content) Code and System Code. An example of how to indicate IEC's WBS Code is given below: 02 - S22 XX (subproject Content - system). -9-

10 5. MAILING OF DRAWINGS AND DATA 5.1 Shipment Method: All documents e.g. drawings, manuals, data, certifications, reports, calculations, Bill of Material in all forms as required by this Standard and this Technical Specification, originating outside Israel, shall be submitted by electronic mail or magnetic media, as agreed upon the Contractor. In addition, hard - copies may be submitted and sent by a special courier shipped via Air-Mail, Air-Express or Air-Freight, depending on the weight. For materials originating in Israel, the manner of shipment shall be coordinated with the Purchaser. 5.2 The documents should be provided to the Purchaser in the formats as indicated in paragraph 4.1 above. - F I N A L -10-

11 ATTCHMENT # 1 DOCUMENT TRANSMITTAL NOTICE -11-

12 ATTCHMENT # 2 INSTRUCTIONS FOR AUTOCAD DRAWINGS SUBMITTED TO IEC -12-

13 INSTRUCTIONS FOR AUTOCAD DRAWINGS SUBMITTED TO IEC 1. Do not use Unicode when indicating the measures on the drawing. 2. Do not change standard definitions of Dimension Style and Text Style. 3. The size of the sheet should not be less than the minimal size according to ISO (A4). 4. The sheet will be drawn using Decimal units, English equivalent of principal dimensions and tolerances may be indicated in adjacent brackets. 5. All types of dimensions used in the drawing should have a corresponding "Dimension Style". If the dimensions have been done by external application (not by AUTOCAD natively), take care to define correctly corresponding "Dimension Styles". If you can not to define the "Dimension Style", an "Explode" command should be done to this dimensions.. 6. Use only original AUTOCAD "Shape" files. 7. Do not use "True Type Fonts" in Hebrew. 8. Use only the original paths, of the AUTOCAD for the text fonts, when defining the "Font Styles". 9. Use only standard IEC Hebrew Text Fonts. IEC will provide the Hebrew Fonts for AUTOCAD to the Contractor. 10. Do not use "Mline" line types. 11. Use only AUTOCAD standard line types. 12. Purge the drawing from any irrelevant entities before submitting it to IEC. 13. The dimensions should not be indicted in the other "Blocks". 14. If "Binding" of "Xref" is performed, remove the sign "$" from all names (LayerNames, TextStyles, LineStyles, etc ) -13-

14 15. The following Files should be attached to each drawing: "Text Font" files, used in the drawing "Xref" files, if applicable. "Color Map" (*.pcp) files, compatible to HP printers. "Raster image" files, if applicable. 16. Save the name of the used "Color Map" in the drawing "Layout settings". 17. Unstead of paragraph 16, it's possible to use only the following seven basic colors and widths : Color Pen Number Width (mm) Red Yellow Green Cyan Blue Violet White (0.1) -14-

Section Meetings Section Material and Equipment. None Required

Section Meetings Section Material and Equipment. None Required January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.1 DESCRIPTION A. This specification defines the general requirements and procedures for submittals. A submittal is information

More information

Miami University. Physical Facilities Department. CAD Standards. April 2004

Miami University. Physical Facilities Department. CAD Standards. April 2004 Miami University Physical Facilities Department CAD Standards April 2004 1.0.0 OVERVIEW These standards pertain to the use, production and submittal of electronic CAD files at Miami University. They have

More information

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners

More information

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES DIVISION 1 GENERAL REQUIREMENTS SECTION 01 33 00 PART 1 - GENERAL 1.1 SUMMARY A. This section includes administrative and procedural requirements for submittals required for performance of the work, including

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA If project is not administered in PRISM, coordinate use of Exhibit 6 submittal schedule with this section. SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01334 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Submit to the ENGINEER for review, such working drawings, shop drawings, test reports and data on materials and equipment

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

CMW DELIVERABLES SPECIFICATION Version 1.0

CMW DELIVERABLES SPECIFICATION Version 1.0 CMW DELIVERABLES SPECIFICATION Version 1.0 Code: CMW-CADD-STD-06 June 2012 CONTENTS 1 INTRODUCTION... 3 2 GENERAL... 3 3 GRAPHIC FORMAT... 3 4 CADD STANDARDS... 3 5 DELIVERY MEDIA AND FORMAT... 4 6 DRAWING

More information

Working Drawing Manual

Working Drawing Manual Working Drawing Manual 2012 Table of Contents Section 1 Working Drawing Types... 1 1.1 General... 1 Section 2 Processing Steps... 1 2.1 Project Manager... 1 2.2 Engineering Document Unit... 2 2.3 Contractor...

More information

Engineering Drawing System

Engineering Drawing System LPR 7320.1 Effective Date: July 18, 2004 Expiration Date: July 18, 2008 Langley Research Center Engineering Drawing System National Aeronautics and Space Administration Responsible Office: Systems Engineering

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01 33 00 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes. 1. Submittal procedures. 2. Product data. 3. Shop drawings. 4. Samples. 5. Design data. 6. Test reports. 7. Certificates.

More information

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.

More information

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. SECTION 01300 - PART 1 - GENERAL 1.1 GENERAL A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. B. Unless otherwise noted, within 14 days after the date of commencement as stated in

More information

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

A. Action Submittals: Written and graphic information that requires Engineer's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES STANDARD SPECIFICATIONS SECTION 01330 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 DESCRIPTION A. Section includes general requirements and procedures related to preparation and transmittal of Submittals to

More information

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General

More information

East Central College

East Central College SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

A. Section includes administrative and procedural requirements for project record documents, including the following:

A. Section includes administrative and procedural requirements for project record documents, including the following: SECTION 017839 - PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01

More information

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES SECTION 01340 SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED A. Contractor shall submit to the Architect/Engineer for review and exception, if any, such working

More information

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals. SECTION 01300 PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Requirements B. Submittal Procedures C. Specific Submittal Requirements D. Action on Submittals E. Repetitive Review 1.2 DESCRIPTION

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 013300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply

More information

AutoCAD Standards University of California, Santa Cruz Physical Planning & Construction

AutoCAD Standards University of California, Santa Cruz Physical Planning & Construction University of California, Santa Cruz Physical Planning & Construction 1. General Requirements: 1.1 Format 1.2 Ownership 2. Required Data: 2.1 Area Tabulation 2.2 Drawing Files 2.3 External References 2.4

More information

Engineering Drawing System

Engineering Drawing System LPR 7320.1 Effective Date: February 2, 2010 Expiration Date: February 2, 2015 Langley Research Center Engineering Drawing System National Aeronautics and Space Administration Responsible Office: Systems

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide submittals in accordance with the General Conditions as modified by the Supplementary Conditions,

More information

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Shop drawings, manufacturer's catalog cuts, product data, samples, and attached Shop Drawing/ Catalog

More information

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal City of Winnipeg Brady Road Landfill Site Section 01300 New Entrance and Scale Facility Page 1 of 4 SUBMITTALS 1. SHOP DRAWINGS 1.1 General.1 Arrange for the preparation of clearly identified Shop Drawings

More information

00-General Drawings. Doc. no.: NA-00-STS002

00-General Drawings. Doc. no.: NA-00-STS002 Gæðaskjal (GSK) GSK-1773 Date of issue: 24.11.2016 Revision no.:2.0 Responsible: Einar Friðgeir Björnsson Editor: Rafn Magnús Jónsson 00-General Drawings Doc. no.: NA-00-STS002 This standard technical

More information

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS SECTION 01300 SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections,

More information

SUBMITTAL PROCEDURES

SUBMITTAL PROCEDURES SUBMITTAL PROCEDURES PART 1 GENERAL The ASPA Project Engineer (APE) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective

More information

Working Drawing Procedure

Working Drawing Procedure Working Drawing Procedure June 2007 Prepared by Structural Engineering & Construction Services 1.0 Working Drawing Procedure 1.1 General There are two primary types of working drawings, those requiring

More information

PROCEDURE FOR PROCESSING WORKING DRAWINGS

PROCEDURE FOR PROCESSING WORKING DRAWINGS PROCEDURE FOR PROCESSING WORKING DRAWINGS MAY 2005 Procedure for Processing Working Drawings GENERAL: The procedure for the review and processing of working drawings provide for two primary types of drawings,

More information

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

A. Action Submittals: Written and graphic information that requires Architect's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018 SECTION 01 7839 - PROJECT RECORD DOCUMENTS GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

CHAPTER A-10 DRAWINGS

CHAPTER A-10 DRAWINGS CHAPTER A-10 DRAWINGS INDEX Revised May 2018 10.1 GENERAL 10.1.1 Purpose and Scope 10.2 APPLICABLE PUBLICATIONS 10.3 COMPUTER AIDED DESIGN (CAD) 10.3.1 CAD Requirements 10.3.2 CAD Deliverables 10.3.3 CAD

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS DIVISION 1 - GENERAL REQUIREMENTS SECTION 01300 - SUBMITTALS PART 1 - GENERAL 1.1 STIPULATIONS A. The section "Special Requirements" forms a part of this section by this reference thereto and shall have

More information

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents. SECTION 01 3000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Submittals for review, information, and project closeout. D. Submittal procedures.

More information

The coordinate system and vertical datum shall be noted in the drawing in the metadata.

The coordinate system and vertical datum shall be noted in the drawing in the metadata. Purpose This document is provided for informational purposes and to assure data compatibility and compliance for as-built drawings or vector data formats specifically for the 354th Civil Engineer Squadron

More information

Vanderbilt University Standard Specification Revised 2/6/08

Vanderbilt University Standard Specification Revised 2/6/08 SECTION 01 78 23 OPERATION AND MAINTENANCE DATA PART 1 GENERAL 1.01 RELATED SECTIONS A. Section 01 77 00 Closeout Procedures B. Section 01 78 39 Project Record Documents 1.02 SUMMARY A. This section provides

More information

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS Page: 4-1 4.0 URD Process and Documentation Requirements 4.1 Process Steps The process of developing underground distribution facilities in a residential area consists of 10 major steps, which are summarized

More information

1. Land survey Work. 2. Civil and Structural engineering services.

1. Land survey Work. 2. Civil and Structural engineering services. SECTION 01050 FIELD ENGINEERING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification

More information

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum SECTION 013201 - SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum Pay Unit price breakdown) shall be developed and ultimately

More information

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Record Documents. B. Operation and Maintenance Manuals. C. Warranties and bonds. 1.02 RELATED REQUIREMENTS SECTION 01 78 00 A. Section 01 30 00 - Administrative

More information

11.0 INSTRUMENTATION LOOP DIAGRAMS

11.0 INSTRUMENTATION LOOP DIAGRAMS 11.0 INSTRUMENTATION LOOP DIAGRAMS Table of Contents 11.0 INSTRUMENTATION LOOP DIAGRAMS... 11-1 11.1 HISTORY OF CHANGE... 11-2 11.2 INSTRUMENT LOOP DIAGRAMS (ILD)... 11-4 11.2.1 Drawing Content... 11-4

More information

SECTION 2 GENERAL REQUIREMENTS

SECTION 2 GENERAL REQUIREMENTS SECTION 2 GENERAL REQUIREMENTS 2-1 ENGINEER REQUIRED: All plans and specifications for Improvements which are to be accepted for maintenance by the County and private, on-site drainage and grading shall

More information

Jacksonville District Master

Jacksonville District Master -01 33 00 (April 2006) From USACE / NAVFAC / AFCESA UFGS UNIFIED FACILITIES GUIDE SPECIFICATIONS Revised thoughout - changes not indicated by CHG tags SECTION TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS

More information

SECTION III SUBMITTALS AND APPROVALS

SECTION III SUBMITTALS AND APPROVALS SECTION III SUBMITTALS AND APPROVALS In order to expedite the approval process of new water distribution system and sanitary sewer collection system extensions, the Hilton Head No. 1 Public Service District

More information

Chapter 1 General Design Information

Chapter 1 General Design Information Chapter 1 General Information Introduction The primary aim in both designing and checking is to produce a structure that will safely carry the anticipated loads. The design team, consisting of the designers,

More information

DIGITAL DATA SUBMISSION STANDARDS Procedures and Guidelines

DIGITAL DATA SUBMISSION STANDARDS Procedures and Guidelines DIGITAL DATA SUBMISSION STANDARDS Procedures and Guidelines 2014 Citizens Wastewater of Westfield - GIS Digital Standards Table of Contents Introduction... 3 Definitions and Terms... 3 Reference Documents...

More information

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Progress meetings. D. Construction progress schedule. E. Coordination drawings. SECTION 013000

More information

Section 4: Ontario Realty Corporation CAD Standards and Guidelines

Section 4: Ontario Realty Corporation CAD Standards and Guidelines Section 4: Ontario Realty Corporation CAD Standards and Guidelines Ontario Realty Corporation 11 th Floor, Ferguson Block 77 Wellesley Street West Queen s Park Toronto, ON, M7A 2G3 August 10, 2007 Version

More information

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014) DRAFT UFGS- 01 XX XX (FEB 2014) ------------------------ Drafting Activity: USACE UNIFIED FACILITIES GUIDE SPECIFICATION SECTION TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION 01 XX XX (FEB

More information

Answer: Qualification statement should be provided with the bid.

Answer: Qualification statement should be provided with the bid. Little Diversified Architectural Consulting, Inc. 5815 Westpark Drive Charlotte, North Carolina 28217 Phone: 704-525-6350 Fax: 704-561-8700 Lincoln County Probation Renovation 208 N. Government Street

More information

Section XV - PER, Design, and Construction Submittal Requirements

Section XV - PER, Design, and Construction Submittal Requirements Section XV - PER, Design, and Construction Submittal Requirements A. Introduction - In an effort to reduce paper and to further implement the Oracle Unifier Project Management System, the Engineering Department

More information

Spec Section: Concrete Mix Design psi - Review Form Concrete Mix Design psi Data Sheets GCAN

Spec Section: Concrete Mix Design psi - Review Form Concrete Mix Design psi Data Sheets GCAN SUBMITTAL REVIEW Submittal: No. 013.00 Spec Section: 03 3000 2.11 Concrete Mix Design - 3500 psi - Review Form Reviewed By: Laura Landon, Comma-Q Architecture Date: May 10, 2012 Project: BPS Belgrade Elementary

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01 33 23 - SHOP DRAWINGS, PRODUCT DATA, AND PART 1 - GENERAL 1.1 SUMMARY A. Products include, but are not limited to, the following construction submittals: 1. Shop Drawings. 2. Product Data. 3.

More information

This specification describes the general requirements for Engineering Services provided to Vale.

This specification describes the general requirements for Engineering Services provided to Vale. 1/9 1.0 PURPOSE This specification describes the general requirements for Engineering Services provided to Vale. 2.0 GENERAL For the purposes of this document, the Engineering Consultant shall be referred

More information

Cloud Based Plan Review Process (Applicant)

Cloud Based Plan Review Process (Applicant) 1 Cloud Based Plan Review Process (Applicant) Organize Documentation Process Overview Upload Documents To Mercer Island FTP Site No Initial Submittal? Yes Intake Screening Approved? CST will inform you

More information

Brad Luke. Director Peddle Thorp Auckland

Brad Luke. Director Peddle Thorp Auckland Brad Luke Director Peddle Thorp Auckland Site Observation and Practical Completion Preparation PEDDLE THORP Introduction Architects Agreement for Services. Observation Work Plans. Auckland Council Quality

More information

Submittal Packages Detailed with Items and Reviewers

Submittal Packages Detailed with Items and Reviewers Submittal Packages Detailed with Items and Reviewers Tenochca Upgrades Project # 2351 San Diego State University 5500 Campanile Drive San Diego, CA 92182 Tel: 619-594-3740 Fax: 0054-096813-1 Tile Carpeting

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS PART 1 GENERAL 1.01 REQUIREMENTS INCLUDED SECTION 01 20 00 PROJECT MEETINGS A. Construction Manager shall schedule and administer pre-construction meeting, periodic progress meetings, and specially called

More information

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document.

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document. Enroll in GMFI Program Image Consultation Design Intent Document Preparation Preliminary Drawings Final Drawings Design Intent Document You are here. 1-2 Construction Documents Services performed by dealer

More information

It is expected that this standard will evolve over time; however the use of this standard should remain consistent within individual projects.

It is expected that this standard will evolve over time; however the use of this standard should remain consistent within individual projects. 1.0 Introduction A computer aided design (CAD) procedure is necessary to ensure that drawings produced by and for the University are readable, understandable, of a consistent standard, and, where necessary,

More information

SPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work

SPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work 2004 Specifications CSJ 0110-04-166 SPECIAL PROVISION 000--363 Description of Project, Scope of Contract and Sequence of Work 1. General. The work to be performed on this project consists of furnishing,

More information

SUBMITTAL REVIEW Steel Reinforcement - Slab and Masonry Shop Drawings GCAN. Notes: 1. See comments on submittal.

SUBMITTAL REVIEW Steel Reinforcement - Slab and Masonry Shop Drawings GCAN. Notes: 1. See comments on submittal. SUBMITTAL REVIEW Submittal: No. 010.00 Spec Section: 03 3000 2.3 Steel Reinforcement Shop Drawings - Slab and Masonry Reviewed By: Laura Landon, Comma-Q Architecture Date: June 13, 2012 Project: BPS Belgrade

More information

SECTION PROJECT MANAGEMENT AND COORDINATION

SECTION PROJECT MANAGEMENT AND COORDINATION SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Electronic Document Review (EDR)

Electronic Document Review (EDR) Electronic Document Review (EDR) Submittal Requirements Table of Contents Introduction... 3 Electronic Document Review Submittals:... 4 Plans... 4 Plat... 4 Forms... 4 Correspondence... 5 Plan Revisions...

More information

Building Standards Department. Markham eplan Submission Standards For Building Permits, Sign Permits and Zoning Preliminary Review

Building Standards Department. Markham eplan Submission Standards For Building Permits, Sign Permits and Zoning Preliminary Review Markham eplan Submission Standards For Building Permits, Sign Permits and Zoning Preliminary Review eplan Submission Standards Building Standards February 2018 SUBMISSION STANDARDS PREPARING YOUR ELECTRONIC

More information

SUBMITTAL REVIEW B Passenger Elevators Shop Drawings GCAN

SUBMITTAL REVIEW B Passenger Elevators Shop Drawings GCAN SUBMITTAL REVIEW Submittal: No. 008 Spec Section: 14 2010 Passenger Elevators Reviewed By: Tripp Lewton, Comma-Q Architecture Date: May 17, 2012 Project: BPS Belgrade Elementary School Location: Belgrade,

More information

Stanford University-Facilities Design Guideline SECTION Plans Review Submission Guidelines

Stanford University-Facilities Design Guideline SECTION Plans Review Submission Guidelines SECTION 01 33 00 Plans Review Submission Guidelines PART 1 GENERAL 1.01 OVERVIEW A. University Plans Review Process: 1. The process by which the Designer s schematic, design development, construction documents

More information

NEORSD. Cad Standards and Procedures Manual

NEORSD. Cad Standards and Procedures Manual NEORSD Cad Standards and Procedures Manual This Manual is being provided to you on loan from the NEOSRD and is the property of the NEOSRD. Periodic updates will be provided and you are responsible for

More information

BAE Systems Combat Vehicles Supplier Quality Assurance AS9102 Requirement

BAE Systems Combat Vehicles Supplier Quality Assurance AS9102 Requirement 1 BAE Systems Combat Vehicles Supplier Quality Assurance AS9102 Requirement February 27, 2019 2 Scope The intent of this document is to provide an understanding, and clarification as to what BAE Systems

More information

THE KENYA POWER AND LIGHTING CO. LTD. SPECIFICATIONS for IMPULSE VOLTAGE TEST EQUIPMENT

THE KENYA POWER AND LIGHTING CO. LTD. SPECIFICATIONS for IMPULSE VOLTAGE TEST EQUIPMENT THE KENYA POWER AND LIGHTING CO. LTD SPECIFICATIONS for IMPULSE VOLTAGE TEST EQUIPMENT NAME DESIGNATION SIGNATURE DATE Compiled by Ephantus Nyagah Ag. Senior Engineer Checked by Eng. Thagichu Kiiru Deputy

More information

PORTAGE COUNTY WATER RESOURCES DRAFTING STANDARDS. Date: January 26, 2001

PORTAGE COUNTY WATER RESOURCES DRAFTING STANDARDS. Date: January 26, 2001 PORTAGE COUNTY WATER RESOURCES DRAFTING STANDARDS Date: January 26, 2001 Portage County Water Resources Drafting Standards. AutoCad 2000/Land Development Desktop R2 Friday, January 26, 2001 Preface: Part

More information

Creating another Printed Circuit Board

Creating another Printed Circuit Board Appendix C Creating another Printed Circuit Board In this chapter, we will learn the following to World Class standards: Starting with a Finished Schematic Creating the Layers for the Printed Circuit Board

More information

submittals 1s e c t i o n

submittals 1s e c t i o n Architectural Woodwork Standards submittals 1s e c t i o n SECTION 1 introductory Information Introduction...25 What to Expect...25 Purpose...25 Level of Detail...25 Approvals...25 Scheduling...25 The

More information

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards] SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA PART I - GENERAL 1.1 SUMMARY A. Operation and Maintenance Data shall be submitted in appropriately-sized binders, with dividers, and organized by each

More information

PITKIN COUNTY STANDARDS for ELECTRONIC DRAWINGS and DOCUMENTS SUBMISSION

PITKIN COUNTY STANDARDS for ELECTRONIC DRAWINGS and DOCUMENTS SUBMISSION PITKIN COUNTY STANDARDS for ELECTRONIC DRAWINGS and DOCUMENTS SUBMISSION DOCUMENT SUBMISSION For Building Permit Submittal: Applicants bring Permit Application, Digital Drawings, and Supporting Documents

More information

DRAWING PROCESS EXTERNAL DRAWINGS

DRAWING PROCESS EXTERNAL DRAWINGS CERN CH-1211 Geneva 23 Switzerland LHC Project Document No. CERN Div./Group or Supplier/Contractor Document No. the Large Hadron Collider project EDMS Document No. 103559 Date:1998-06-25 Quality Assurance

More information

SECTION OPERATION AND MAINTENANCE DATA

SECTION OPERATION AND MAINTENANCE DATA SECTION 01787 OPERATION AND MAINTENANCE DATA PART 1 GENERAL 1.01 SUMMARY A. Compile product data and related information appropriate for OWNER's maintenance and operation of products furnished under Contract.

More information

1.0 INTRODUCTION DEFINITIONS DRAWING CONTROL PREPARATION OF SPECIFICATIONS AND DATASHEETS... 5

1.0 INTRODUCTION DEFINITIONS DRAWING CONTROL PREPARATION OF SPECIFICATIONS AND DATASHEETS... 5 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 DEFINITIONS... 4 3.0 DRAWING CONTROL... 4 4.0 PREPARATION OF SPECIFICATIONS AND DATASHEETS... 5 5.0 GUIDELINES FOR PREPARATION OF DRAWINGS... 5 6.0 CONTENTS

More information

11-SDMS-03 REV. 02 SPECIFICATIONS FOR

11-SDMS-03 REV. 02 SPECIFICATIONS FOR 11-SDMS-03 REV. 02 SPECIFICATIONS FOR XLPE INSULATED POWER CABLES FOR RATED VOLTAGES FROM 15 KV UP TO 36 KV (U m ) This specification is property of SEC and subject to change or modification without notice

More information

FAST TRACK WORKSHOP OBJECTIVES

FAST TRACK WORKSHOP OBJECTIVES 1 FAST TRACKING FAST TRACK WORKSHOP OBJECTIVES TO UNDERSTAND: 1. WHY ARE CRITICAL PATH ( FAST TRACK ) DESIGN SUBMITTAL PACKAGES ALLOWED 2. WHEN IS FAST TRACK ALLOWED 3. WHEN IS THE CONTRACTOR ALLOWED TO

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1073 PRECAST CONCRETE CERTIFICATION PROGRAM JULY 20, 2018

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1073 PRECAST CONCRETE CERTIFICATION PROGRAM JULY 20, 2018 STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1073 PRECAST CONCRETE CERTIFICATION PROGRAM JULY 20, 2018 1073.01 Program Overview 1073.02 Qualification 1073.03 Documentation Phase 1073.04 Documentation

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS USACE / NAVFAC / AFCEC / NASA UFGS-01 33 00 (May 2011) Change 9-08/17 ----------------------------- Preparing Activity: NASA Superseding UFGS-01 33 00 (February 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

RIT CAD Specifications

RIT CAD Specifications RIT CAD Specifications The design team shall provide RIT with Revit, AutoCAD, and PDF files that capture the construction conditions of the associated project. This document outlines requirements for submitting

More information

Report Number B0622. Requirements for Sellers of Special Tooling to the Boeing St. Louis Tooling Center

Report Number B0622. Requirements for Sellers of Special Tooling to the Boeing St. Louis Tooling Center Report Number B0622 Requirements for Sellers of Special Tooling to the Boeing St. Louis Tooling Center 1 Index Title Page....1 Index....2 Index of Page Changes.. 3 1.0 Scope....4 1.1 Relations to other

More information

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer Construction Documents 1.1 to 1.6 Create Submittal Log 1.1 Construction Docs Focus of this process is to transmit submittal

More information

REQUEST FOR QUOTATION INVITATION

REQUEST FOR QUOTATION INVITATION REQUEST FOR QUOTATION INVITATION DATE: July 15, 2010 DPS: REQUIREMENT: SUBJECT: Patricia Farina DPS Contract Administrator Email: Patricia.Farina@cityofchicago.org Telephone: 312-744-7660 Silver Halide

More information

APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN

APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN 209 S. Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN *** IMPORTANT INFORMATION ~ Please

More information

REMARKS: The A.F.F. dimension noted on the drawings to the bottom of the grid is 15 0, this dimension should be 16 0.

REMARKS: The A.F.F. dimension noted on the drawings to the bottom of the grid is 15 0, this dimension should be 16 0. SUBMITTAL REVIEW SENT VIA: REGULAR MAIL OVERNIGHT FAX HAND DELIVERY DIGITAL DELIVERY OTHER: TO: Rodrigo Gorgazzi / CannonDesign Steve Benesh / CannonDesign Tim Donlon / FROM: Steven Cooper CC: David Barnett

More information

(Non-legislative acts) DECISIONS

(Non-legislative acts) DECISIONS 4.12.2010 Official Journal of the European Union L 319/1 II (Non-legislative acts) DECISIONS COMMISSION DECISION of 9 November 2010 on modules for the procedures for assessment of conformity, suitability

More information

GENERAL REQUIREMENTS FOR THE MARKING OF ESCC COMPONENTS. ESCC Basic Specification No

GENERAL REQUIREMENTS FOR THE MARKING OF ESCC COMPONENTS. ESCC Basic Specification No Pages 1 to 14 GENERAL REQUIREMENTS FOR THE MARKING OF ESCC COMPONENTS ESCC Basic Specification No. 21700 Issue 2 Draft E November 2007 Document Custodian: European Space Agency - see https://escies.org

More information