Exhibit A SCOPE OF WORK AND DELIVERABLES T.H. 169 Mountain Iron to Hoover Road in Virginia

Size: px
Start display at page:

Download "Exhibit A SCOPE OF WORK AND DELIVERABLES T.H. 169 Mountain Iron to Hoover Road in Virginia"

Transcription

1 Exhibit A SCOPE OF WORK AND DELIVERABLES T.H. 169 Mountain Iron to Hoover Road in Virginia PROJECT OVERVIEW S.P is on T.H. 169 from 0.07 miles west of CR 109 in Mt. Iron to Hoover Road in Virginia Minnesota. Total project length is approximately 1.17 miles. Project elements include concrete pavement replacement and bituminous overlay, ADA improvements, new curb and gutter and sidewalk, signal replacements, lighting replacement, bridge repairs, widening of Co. Rd. 7 and reconstruction of Enterprise Drive. The project is currently scheduled for letting in May of The proposed project consists of the following work: TH 169 Design includes: ADA compliant Pedestrian ramps per State recommendations. Sidewalk and curb and gutter per the State approved Geometric Layout and ADA recommendation. Bituminous overlay on TH 169 from west project limits to just west of the new concrete pavement section approaching Bridge Replacement of concrete pavement from just west of Bridge to Hoover Road intersection. APS and traffic signal upgrades at 3 intersection Reconstruction of Enterprise Drive to accommodate new left turn lane per the State approved Geometric Layout. Widening of Co. Rd. 7 to accommodate new left turn lane per the approved State Geometric Layout. Replace the lighting system along the TH 53/TH 169 intersection and ramps; and at the TH 169/Enterprise Drive/Co. Rd. 7 intersection. Bridge (over the BNSF RR) and (T.H. 169 over T.H. 53) work: Bridge rehabilitation and repair plans to be completed by MnDOT s Bridge Office. Other report items will include the Design Memo, Utility Coordination, Intersection Control Evaluation (ICE), National Pollutant Discharge Elimination System (NPDES) Permit application, Storm Water Pollution Prevention Plan (SWPPP), signing, lighting, signal, striping, traffic control plans, Traffic Management Plans (TMP), coordination with MnDOT Bridge Office and ADA Office, cost estimates and cost splits for a cooperative agreement with the City of Mountain Iron and St. Louis County, and Special Provisions. Contractor deliverables will include Project Management, Utility Coordination, Design Memo, ICE reports, Detail Design Plans, Lighting Design Plans, Signal Design Plans, Striping Plans, Signing Plans Traffic Control Plans, SWPPP, NPDES permit application, TMP, Special Provisions, and Construction Cost Estimates. State will provide the staff approved geometric layout, survey data, Material Design and Pavement recommendations (MDR), geotechnical recommendation for Bridge approach, wetland delineation, hydraulic recommendations, and environmental documentation. 1.0 PROJECT MANAGEMENT (Source Code 1010) 1

2 Project Management will include work necessary for the effective communication and coordination of the project to ensure the project tasks are completed on time, within budget, and in accordance with State and Federal laws, rules, and regulations. See Tasks 3.0 and 4.0 for additional meetings. 1.1 Project Management and Administration Monthly Budget and Billing (Invoice and Status Report): Invoices will be accompanied by a cover letter explaining the general status of the project, including at a minimum the work completed to date, the anticipated remaining efforts and required schedule changes; progress report form Weekly Update to the State s Project Manager: On a weekly basis, the Contractor s Project Manager will update the State s Project Manager with a conference call with regards to the status of the project schedule, budget and general status/progress. 1.2 Work Plan and Schedule The Contractor s Project Manager will update and maintain a project schedule on a bi-weekly basis. The project schedule will be based upon the State s P6 Schedule. Biweekly schedule updates will be provided to the State s Project Manager. 1.3 Kick-off Meeting The Kick-off meeting will establish communications protocol and discuss the project schedule and will be held at the District Headquarters in Duluth. The Contractor will receive available existing information from the State. See other sections for additional meetings. 1.4 Quality Control Management A Contractor team member will be assigned the title of quality assurance/control manager and have the responsibility of reviewing submittals, prior to submittal, to ensure compliance with the MnDOT Quality Management Process (QMP). The basic format for quality certification will be checking, back checking, and verifying format in accordance with MnDOT s Design-Bid-Build Quality Management Process. Refer to for further information. 1.5 Deliverables State s Deliverables: 1. Review and respond to submittals. 2. Coordinate internal reviews. 3. Provide copies of project correspondences and project information. 4. Attend meetings. 5. Approve deliverables. 6. Monitor quality control. 7. P6 schedule and updating. 8. Early Notification Memo 9. Approved Scoping Document 10. Survey data 11. CATEX 12. File naming convention guidance and file directory structure guidance. 1. Schedule and attend meetings. 2. Weekly update meeting or conference call with State s Project Manager. 2

3 3. Prepare meeting agendas and minutes. 4. Prepare and submit monthly progress and status reports. 5. Maintain project schedule, and provide updates to the State s Project Manager. 6. Provide timely copies of critical correspondences and project issue data. 7. Provide Quality Assurance / Quality Control on project deliverables and submit project QA/QC certification. 8. Submit electronic project files on CD at the project completion (following file naming convention and file directory structure). 2.0 PROJECT DOCUMENTATION (Source Code 1071) Project Documentation will include all tasks necessary to prepare the project s Design Memo. Contractor will prepare Design Memorandum following the format found in MnDOT s Highway Project Development Process at for the project. 2.1 Deliverables 1. Draft Design memos for State s review. 2. Final Design Memos State s Deliverables: 1. Review and comment on documents 3.0 UTILITY COORDINATION (Source Code 1195) Utility coordination will include tasks necessary to be in compliance with MnDOT s 2013 Utilities Manual and applicable State Statutes. This includes but is not limited to Gopher State- One Call contacts and preparing and distributing letters and plans, meetings and individual utility contacts. 3.1 Step 1: Perform Gopher State One Call, receive utility data and survey data. Conduct field reviews if necessary. 3.2 Step 2: Prepare preliminary utility plans and tabulations showing inplace public and private utilities located within the proposed construction limits. Follow QC checks on utility file. The preliminary utility plans and tabulations will include the following: List of utility owners within the project. Plan view of inplace utilities showing location, size and type of facility (if known). Distinction between overhead and buried utility lines. Voltage of power lines greater than 15 kv. Tabulation of inplace utilities showing the location (indicated by station and offset from the roadway alignment used in the final construction plan), the utility facility owner, and the size and type of facility in the project area. 3.3 Step 3: Upon completion of the construction limits, submit a Utility Coordination Letter to each utility company of discovered utilities two to three (2-3) weeks prior to Utility Information Meeting; attached will be 20-45% plan set. Follow QC checks on letter and attached materials. Required plan sheets are listed below. Gather potential easement information from utility owners. Utility plans and tabulations should be back-checked. Utility Plan sheets will include the following: Title sheet 3

4 General layout Typical sections Preliminary utility tabulations Topography, construction plans, and removal plans showing preliminary construction limits and existing utility facilities 3.4 Step 4: Arrange and conduct a preliminary Utility Information Meeting for the purpose of informing utility owners about the project. Participants review and discuss the utility information plans. Distribute meeting minutes to all participants. 3.5 Step 5: Revise utility plans and tabulations based upon comments from the State and utility owners: Indicate the effect in the tabulation for each utility identified (leave as, adjust, relocate, or remove) based on project construction limits, grading changes, and project utility information. 3.6 Step 6: Submit a Utility Design Letter to each utility company of discovered utilities two to three (2-3) weeks prior to the Utility Design Meeting. Follow QC checks on let and attached materials. Include information to utility owners regarding project changes and major updates to utility information. Utility tabulations and plans (if major changes) will be back-checked. Utility plan sheets will include the following: Title sheet General layout Typical sections Updated utility tabulations with potential conflicts identified. Topography, construction plans, and removal plans showing construction limits and existing utility facilities Intersection details 3.7 Step 7: Arrange and conduct a Utility Design Meeting focusing on finding solutions to utility conflicts. MnDOT Utility Agreements and Permits Unit and the Construction Group should be involved. Meeting occurs at 60-75% construction plans. Distribute meeting minutes to all participants. 3.8 Step 8: Request utility owners to submit detailed plans, schedules and estimates using Request for Relocation Letter. Utilities are to submit relocation plans using the Red/Green/Brown Marking system. Red marks indicate facilities to be removed or put out of service; Green marked facilities will remain in place; and, Brown marks indicate proposed facilities. This step may require additional follow-up if utility owners are unresponsive/unfamiliar with the MnDOT process, or the project is very complicated. 3.9 Step 9: Arrange and conduct Utility Design Meetings to review major changes to the plan that affect the utilities Step 10: Conduct 90-Day GSOC prior to letting. Submit a Utility Verification and Information Letter to each identified utility owner, no more than 90 days prior to the submission of final plans to MnDOT Central Office, along with a final plan consisting of a title sheet, construction plan sheets, profiles, construction staging, utility tabulations, in place utility plan sheets, and cross sections. One copy will also be submitted to the State s Utility Agreements Office. Responses from utility companies will be copies to the State s Project Manager and the Utility Agreements Office. 4

5 3.11 Step 11: Review utility relocation plans and schedule to ensure they address all project conflicts and meet Utility Accommodation Policy. Coordinate review with construction. Assist permitting office with utility agreements and reimbursement. This will be the State s Utility Agreements and Permits Unit Step 12: Add proposed utility relocation locations to plans, profiles and cross sections for any proposed relocation information if the information is furnished prior to completion of the plans. Final QC check on utility plans and tabulations Add utility special provisions to the contract that will require mutual coordination between the utility owner and the Contractor including utility contact information Deliverables State s Deliverables: 1. Utility permitting process. 2. Send out notice and orders to utility companies (steps 13 and 14). 3. Available existing utility information. 4. Single set of consolidate plan comments 1. Gophers State One call documentation. 2. Coordination Letters and attachments. 3. Utility Plans and Tabulations. 4. Utility Coordination Meeting agendas, materials and minutes. 5. Phone log documentation. 6. Project Manager utility certification. 7. Meeting minutes 4.0 DETAIL DESIGN PLANS (SOURCE CODE 1250) This task includes development of final detailed design plan for the project. The State will provide an approved geometric layout, preliminary typical, horizontal alignments, vertical profiles, preliminary construction limits, and Corridor Modeling files used to generate preliminary cross sections. Contractor will be required to provide work using Mincrostation Corridor Modeler. The design will require realignment of approximately 600 feet of Enterprise Drive, widening of Co. Rd. 7 to accommodate a new left turn lane onto TH 169 and ADA improvements. Horizontal and vertical alignments for these roadways will be provided by the State. Bridge rehabilitation and repair plans for Bridge & will be prepared by MnDOT s Bridge Office. Coordination with MnDOT s Bridge Office will be required. Contractor tasks will include, storm water treatment plan, Storm Water Pollution Prevention Plan (SWPPP), design of intersection lighting along the TH 53/TH 169 ramps and TH 169 and Co. Rd. 7/Enterprise Drive intersection, rumble strips, and traffic barrier. The final road plans will also be consistent with any findings and recommendations identified in the Project Documentation and in accordance with Federal and State laws, rules, and regulations. 5

6 4.1 Construction Plans Each construction Plan set will consist of, but is not limited to, the following sheets, and not necessarily in the order listed below: a) Title Sheet Contains the location map, signature block, sheet index, project data, station equations, traffic data, and station-reference point comparison. b) General Layout (1 = 200 Ft) A layout of the project showing the plan sheet layout and sheet numbers for reference. c) Statement of Estimated Quantities (SEQ) Tabulation showing MnDOT s standard pay item numbers, item descriptions, and quantity of materials needed to complete the project. Columns will exist for referencing the individual item s tabulation. Notes will be included where necessary for clarification. The SEQ will require separation of quantities by funding source type. Contractor will ensure that pay items are consistent with the State s Trns*port pay item list. d) Soils and Construction Notes and Standard Plates Notes covering special requirements and critical information contained in the Materials Design Recommendation will be listed as well as any other special construction requirements and District-provided notes that have been identified. MnDOT Standard Plates used on this project will also be listed on this sheet. e) Typical Sections Typical sectional views of the existing and proposed roadway will be shown for the length of the project. The sections will be consistent with the Materials Design Recommendation and the CATEX. Surface type will be shown. f) Quantity Charts (Tabulations) Detailed quantity breakdown by station or station range of most items contained in the Statement of Estimate Quantities (SEQ). Tabulations will separate or note different funding sources. g) Public Utility Tabulations Detailed breakdown of existing utilities located within the project limits. This tabulation is required to have the following columns: Station, Location, Inplace Facility Description, Owner, Remarks, and Adjust, Relocate, or Leave As Is. h) Miscellaneous Details Any details necessary for the construction of unique or non-standard elements identified during detail design. i) Standard Plan Sheets MnDOT Standard Plan Sheets will be included as needed to supplement the construction details in the plan. The State will provide electronic copies of any District-Modified Standard Plan Sheets j) ADA Details a. The person who is responsible for leading the curb ramp, sidewalk and driveway design for the project must have attended MnDOT s Consultant ADA Training or have comparable experience approved by the State s Project Manager and must be directly involved with the design of the project. 6

7 b. Contractor will meet with State ADA staff after completion of the 30% and 60% plans. These meetings will be held in St. Paul. c. The designer will need to produce Level 2 detailed 1:20 scale intersection designs at all intersections. The designer will utilize sample plans from MnDOT s ADA design and construction tools website as a template for this design work. This intersection detail will show all surface utilities including signal poles, pedestal poles, cabinets, handholes, manholes and push button stations, in addition to the pedestrian facility work occurring at the intersection. d. For signalized intersections, the curb ramp designer will coordinate with the signal designer to determine appropriate locations for pedestrian crosswalks. The X,Y coordinates of the points where the proposed crosswalks intersect curb lines must be provided in the plan. See Section 6.0 for signal plans. e. All pay items including utility adjustments will be tabulated by quadrant and if radial domes are intended to be used at a quadrant the radius will be given in addition to quantity. Follow pay item guidance provided in MnDOT s ADA Project Design Guide when determining which pay items to use on the project. k) Road Connection and Entrance Details Detailed plan layouts and charts showing grades, radii, widths, cross slope and construction details. l) Construction Plan Sheets Detailed plans of the project providing information on the location of items such as roadways, shoulders, radii, turn lanes, acceleration lanes, driveways, curb and gutter, accessible sidewalks and curb ramps, tapers, right-of-way, railroad property, easements, obliterations, station equations, fencing, etc. Removal Sheets Detailed plans of the project providing information on the location of removal of pavement, sidewalk, drainage, etc. m) Drainage and Erosion Control / SWPPP Plans see Task 8.0 n) Traffic Control Plan see Task 5.0 o) Striping & Signing Plan see Task 5.0 p) Traffic Signal Plans see Task 6.0 q) Traffic Lighting Plans see Task 7.0 r) Cross-Section Sheets Cross-Section Sheets as needed for turn lanes, culverts and profile grade correction areas. Prepare cross-sections as needed to show drainage and special features. Cross sections will include existing ground line, proposed roadway template, grading grade, existing and proposed utilities, existing and proposed culverts, existing and proposed right-of-way, temporary easements, entrance slopes, subgrade corrections, unsuitable soil removal, rock lines and topsoil placement. 7

8 4.2 Plan Format The format of the Road/Construction Plans will comply with the State s current design concepts and practices. Sheets contained in the Road/Construction Plans and cross-sections will be submitted to MnDOT in MicroStation Version 8i or other version as approved by the State Project Manager. The Plan will be in compliance with the MnDOT CADD Standards Manual. Electronic Project design information will be in MicroStation and Geopak format. Upon completion of this Project or Termination of this contract, the electronic project files become the property of the State of Minnesota, Department of Transportation and will be submitted on a CD-ROM or portable USB device. Plans submitted for reviews will be delivered in a pdf format. The 95% and 100% design plan shall be submitted on 11 x17 bond and only the title sheets will be on an 11 x 17 sheet of vellum. Plan review meetings will be held at the MnDOT District One office in Duluth at the 60% and 90% plan reviews. 4.3 Plan Review and Approval The Road/Construction Plans will be submitted for review and approval at the following stages of development: a) Preliminary Design (30% Complete) Contractor will produce construction limits for the project showing proposed new right of way required for all project elements including ADA and drainage improvements. The 30% plan will also include the title sheets, typical sections, plan sheets and construction details. Prior to submittal of the construction limits, the Contractor will perform enhanced internal quality control review process (QA/QC review) of design components, including a Discipline Coordination Review meeting. Scan and electronically file documentation of quality control checks and resolutions. The State s District staff will complete review and comment on this submittal within 10 working days of the submittal date. The State will provide a single set of consolidated comments. If necessary, Contractor will revise and re-submit corrected construction limits. b) Intermediate Design (60% Complete) The Contractor will submit the 60% plan in a pdf format showing existing topography and utility plans, roadway plan sheets, drainage plans, typical sections, pavement marking and preliminary utility relocations. ADA plan review checklist #1 required for St. Paul 60% ADA plan review. Prior to submittal of the 60% plan, the Contractor will perform enhanced internal quality control review process (QA/QC review) of design components, including a Discipline Coordination Review meeting. Scan and electronically file documentation of quality control checks and resolutions. The State s District staff will complete review and comment on this submittal within 10 working days of the submittal date. The State will provide a single set of 8

9 consolidated comments. Resolved comments will be incorporated into the 90% plan submittal. Consultant will meet with State Project Manager and staff in the Duluth office to review the 60% comments. No more than 2 consultant staff will attend the meeting. c) Final Design (90% Complete) The Contractor will submit the 90% plan in a pdf format of the proposed Final Design Plans for State s Review and Comment. The 90% submittal by the Contractor is what the Contractor would consider final biddable plans. Selected sheets will be sent to Central Office for preparation of any necessary Agreements. ADA plan review checklist #2 required for St. Paul 90% ADA plan review. Prior to submittal of the 90% plan, the Contractor will perform enhanced internal quality control review process (QA/QC review) of design components, including a Discipline Coordination Review meeting. Scan and electronically file documentation of quality control checks and resolutions. The State s District staff will complete review and comment on this submittal within seven (7) working days of the submittal date. The State will provide a single set of consolidated comments. Resolved comments will be incorporated into the 95% plan submittal. Consultant will meet with State Project Manager and staff in the Duluth office to review the 90% comments. No more than 2 consultant staff will attend the meeting. d) Final Design (95% Complete) Upon making the revisions from the 90% District One submittal, the Contractor will submit two signed and certified set of bond prints with two copies of the vellum title sheet. The original signed and certified prints will be submitted to the State s Central Office Design Liaison Unit by the State s District Office for review and approval. Submit the SharePoint ADA Design Memo. Prior to submittal of the 95% plan, the Contractor will perform enhanced internal quality control review process (QA/QC review) of design components, including a Discipline Coordination Review meeting. Scan and electronically file documentation of quality control checks and resolutions. The State s District staff will complete review and comment on this submittal within three (3) working days of the submittal date. The State will provide a single set of consolidated comments. Resolved comments will be incorporated into the 100% plan submittal. The MnDOT Central Office Liaison Unit will make a final review and comment on the certified Construction Plan. The Contractor will resubmit the plans. Contractor should assume one meeting with State staff in St. Paul to review comments. e) Final Design (100% Complete) 9

10 Upon making the revisions requested by Central Office Design Liaison Unit, the Contractor will submit new signed and certified sheets, as necessary. An electronic copy of the project s Geopak design files (.gpk) and each sheet in Microstation format will be submitted. One copy of the design computations and quantity calculations will also be submitted. Prior to submittal of the 100% plan, the Contractor will perform enhanced internal quality control review process (QA/QC review) of design components, including a Discipline Coordination Review meeting. Scan and electronically file documentation of quality control checks and resolutions. An electronic copy of the project s Geopak design files (.gpk) and each sheet in Microstation format and PDF format will be submitted. One (1) copy of the design computations and quantity calculations will also be submitted. 4.4 Deliverables State s Deliverables 1. Approved geometric layout 2. Typical entrance and road connection detail sheet(s). 3. Pedestrian Curb Ramp Standard Plans 4. ADA recommendations. 5. Wetlands delineation 6. Example driveway design table 7. Final Materials Recommendation Report defining pavement reclamation, subgrade improvements, mainline pavement design, side road and entrances pavement design. 8. Geotechnical recommendation. 9. District-modified standard plan sheets. 10. ROW file in Microstation DGN format. 11. Traffic forecasts 12. Single set of consolidated plan comments 13. Meeting attendance 1. 30% plan submittal 2. 60% plan submittal % plan submittal % plan submittal % plan submittal. 6. ADA checklist #1 at 60% 7. ADA checklist #2 at 90% 8. ADA Design Memo. 9. Geopak design files (.GPK) 10. Microstation design files (.DGN) 11. Design computations and quantity computations. 12. QA/QC documentation. 13. Meeting attendance 5.0 TRAFFIC CONTROL, SIGNING & STRIPING PLANS ( see work item for Source Code) 10

11 5.1 Traffic Control plans and ramp detours (Source Code 1254) All work required for detailed plans, notes, and tabulations will be prepared showing the location of signs, barriers, and striping necessary to accommodate the construction within the project area. Plans and notes will be consistent with the Minnesota Manual of Uniform Traffic Control Devices (MMUTCD), Manual for Temporary Traffic Control Zone Layouts, and MnDOT District One practices. The plan sheets will contain tabulations showing the description and estimated quantity of traffic control devices by stage. Contractor will also prepare the Transportation Management Plan (TMP) for approval by the State. Provide internal coordination meetings, project coordination with the State s District staff, and communications as necessary. Submit temporary traffic control plans and tabulations at 60%, 90%, 95% and 100% completion with construction plans (Task 4.0). Perform internal quality control review of design components, including Discipline Coordination Review meeting, prior to each plan submittal for the State s review. Scan and electronically file documentation of quality control checks and resolutions. 5.2 Signing Plans (1 = 100Ft) (Source Code 1255) Contractor will prepare signing plans for the replacement of all permanent signing that would require changes based on the new design. Detailed plans, notes, and tabulations will be prepared showing the location of the inplace signs and the location of the permanent signs upon completion of the project. The plan will include necessary typicals found on the MnDOT Traffic Engineering website to construct the permanent signing as shown on the plan sheets. The plan will also include sign designs for new permanent signing. New signs must be designed according to the MnDOT Sign Design Manual and be completed using SignCAD software. Plans and notes will be consistent with the Minnesota Manual on Uniform Traffic Control Devices, Chapter 6 of the MnDOT Traffic Engineering Manual, the MnDOT Signing Plan Design Manual, and MnDOT District One practices. Submit signing and striping plans, at 60%, 90%, 95% and 100% completion with construction plans. (Task 4.0) 5.3 Striping Plans (1 = 100 Ft) Combined with Signing Plans (Source Code 1255) Detailed plans, notes, and tabulations will be prepared showing the permanent pavement markings. The plan will include the applicable MnDOT Pavement Marking Typicals found on the MnDOT Traffic Engineering website and plan sheets showing permanent pavement markings on the roadway alignment. Plans and notes will be consistent with the Minnesota Manual on Uniform Traffic Control Devices, Chapter 7 of the MnDOT Traffic Engineering Manual, and MnDOT District One practices. The State will provide the recommendation for the pavement marking materials. 11

12 5.4 Deliverables: State s Deliverables 1. Typical details 2. Pavement marking materials type 3. Single set of consolidated plan comments 4. Meeting attendance 1. 60% plan submittal % plan submittal % plan submittal % plan submittal. 5. Microstation design files (.DGN) 6. Design computations and quantity computations. 7. QA/QC documentation. 8. Meeting attendance 6.0 ICE REPORTS AND TRAFFIC CONTROL SIGNAL PLANS (Source Code 1251) 6.1 Intersection Control Evaluation Reports After review of the intersection, existing data, traffic counts and operations, two alternatives will be analyzed. Signal replacement with current geometrics Signal replacement with dual left for the T.H. 169 eastbound to northbound new geometrics This analysis will include but is not limited to the following: Traffic Signal Warrant check Crash analysis to determine impacts from the alternatives Operational analysis of alternatives using the SimTraffic software package Additional RODEL analysis of roundabout control for the intersection Oversized load considerations for roundabout design The operational analyses will include the existing and projected year 2038 volumes during the a.m. and p.m. peak hours. Once the analysis has been completed and recommendations developed and reviewed with the State, the ICE document will be prepared. The document will follow the Minnesota Manual on Uniform Traffic Control Devices, MnDOT Technical Memorandum No T-02 (Intersection Control Evaluation), and other pertinent guidance. A draft document will be submitted to State Project Manager for review and comment. Comments will be provided by the State within two weeks. State s comments will be incorporated into the final document. 12

13 6.2 Traffic Signal Plans Signal plans will be in State plan format (40 scale drawing), coordinate correct, and will contain all necessary design information including (but not limited to) the following: quantity tabulation, signature block, abbreviations, symbols, details (standard & special), intersection layout(s) and wiring diagram(s), ADA pedestrian curb ramp details (20 scale drawing), and For Information Only signal plans. All proposed signal plan sheets (and inplace system sheets, if not provided by State) will be drafted from new mapping data. The special provisions (Division SS) will be written to STATE standards and include State furnished materials references. 6.3 Deliverables State s Deliverables 1. In-place signal plans (hard copy or CADD file as available) 2. MnDOT s Traffic web site ( for checklists, sample plans, details, etc. 3. Plan sheet format 4. District-modified standard plan sheets 5. Plan/special provisions/estimate review comments Contractor s Deliverables 1. Traffic Counts needed for ICE reports 2. Draft and final Ice reports. 3. Field Walk with D1 staff and all required stakeholders (with underground utilities located) prior to 30% plan submittal contractor should plan for one additional field walk during design. 4. Submit signal plans and tabulations at 30% (PDF only) 60%, 90%, 95% and 100% completion with construction plans (Task 4.0) and in addition provide CADD design files and reference files at each submittal. 5. Cost estimates. 6. Special Provisions. 7. QA/QC documentation Perform internal quality control review of design components, including Discipline Coordination Review meeting, prior to each plan submittal for the State s review. Scan and electronically file documentation of quality control checks and resolutions. 7.0 LIGHTING PLANS (1 = 200 FT) (SOURCE CODE 1252) 7.1 Traffic Lighting Plans Lighting plans will be in State plan format, coordinate correct, and will contain all necessary design information including (but not limited to) the following: quantity tabulation, signature block, abbreviations, symbols, details (standard & special), 13

14 intersection layout(s) and wiring diagram(s), scale to be approved by D1 staff, appropriate to each area of interest (e.g. - 50, 100 or 200 scale drawing), and include Salvage and Removal Lighting plans as part of the lighting package, independent of the road design package. All proposed lighting plan sheets (and inplace system sheets, if not provided by State) will be drafted from new data. The special provisions (Division SL) will be written tostate standards and include state furnished materials. 7.2 Deliverables State s Deliverables: 1. In-place lighting plans (hard copy and if available CADD files) 2. MnDOT s Traffic web site ( ) for checklists, sample plans, details, etc. 3. Plan sheet format 4. District-modified standard plan sheets 5. State specific details for light service cabinet. 6. Plan/special provisions/estimate review comments 1. Field Walk with D1 staff and all required stakeholders (with underground utilities located) prior to 30% plan submittal and any follow up field reviews as the design process warrants. 2. Submit lighting plans and tabulations at 60%, 90%, 95% and 100% completion with construction plans (Task 4.0) and in addition provide CADD design files and reference files at each submittal. 3. Provide lighting plan sheets detailing design and quantities, including as part of the lighting design package lighting Removal and Salvage sheets using same layout and scale as proposed lighting sheets. Quantities for removals and salvages of in place lighting systems components will be shown and tabulated. 4. Cost estimates. 5. Special Provisions (Divisional). 6. QA/QC documentation Perform internal quality control review of design components, including Discipline Coordination Review meeting, prior to each plan submittal for the State s review. Scan and electronically file documentation of quality control checks and resolutions. 8.0 DRAINAGE, CULVERT, TEMPORARY EROSION/SEDIMENT CONTROL, PERMANENT TURF ESTABLISHMENT PLANS AND SWPPP PLAN SHEET (Source Code 1257) 8.1 Drainage Chart (Tabulation) Show the type, size, location, and proposed construction impact of inplace drainage culverts and structures within the project limits. The tabulation will show the removals, salvages, reinstalls, linings, extensions, etc. of pipes, culverts, 14

15 drainage structures. Also included in the tabulation will be new culverts and drainage structure information including type, size, lengths, class of pipe, excavation, and bedding. 8.2 Drainage Plan Sheets (1 = 50 Ft) to be combined with construction plans. Show proposed culverts, aprons, other drainage structure, labeling size, material type, and structure number if applicable. 8.3 Proposed Drainage Tabulation A list of the location, type, size, length, inlet and outlet elevations, grade, class, alternative pipe types, erosion control, excavation, and bedding for each proposed pipe and structure. The tabulations will also include quantities associated with box culvert/bridge construction. 8.4 For temporary erosion control items, show the location and type of temporary erosion control devices that will be used to control project runoff and sediment during construction. The Best Management Practices will be consistent with the CATEX and comply with Minnesota Pollution Control Agency (MPCA), Department of Natural Resources (DNR), Corp of Engineers (COE) and National Pollution Discharge Elimination System (NPDES) permit requirements. Erosion control will be developed in conjunction with District One construction personnel. 8.5 For permanent erosion control items, show the locations and types of permanent turf establishment in areas of construction disturbance and permanent erosion control devices that comply with MPCA Best Management Practices (BMP s). Erosion control will be developed in conjunction with District One construction personnel. 8.6 Drainage, Erosion Control and Turf Establishment Plan Sheets, estimates, and special provisions. Develop preliminary erosion control plan for the State s review and comment. 8.7 Meet with the State s District Construction staff to coordinate usage of BMPs, and identify pay item breakdowns, and necessary special provisions. Prepare drainage, erosion control and turn establishment plans and SWPPP. The plan will include notes, symbols and abbreviations of Best Management Practices being applied to control project runoff during construction. Prepare tabulations that summarize the drainage, erosion control and turf establishment items and their locations.\ Submit erosion control plans at 60%, 90%, 95% and 100% completion with construction plans (Task 4.0). Perform enhanced internal quality control review of design components, including Discipline Coordination Review meeting, prior to each plan submittal for the State s review. Scan and electronically file documentation of quality control checks and resolutions. 8.8 Deliverables State s Deliverables: 1. Standard district SWPPP template for consultant use. 2. Hydrinfa listing of drainage structures in the project 3. Hydraulic recommendations 15

16 4. Single set of consolidate plan comments %, 90%, 95% and 100% plan submittals. 2. Cost estimates. 3. QA/QC documentation. 9.0 WETLAND PERMITTING (SOURCE CODE 1071) 9.1 This task includes preparing a US Army Corps of Engineers wetland permit Contract s tasks will include: Attendance at pre-application TEP meeting with the USACE and members of the TEP and preparation meeting minutes. Will prepare and submit WCA/USACE Joint Permit Application (including all required exhibits) for S.P based on the provided wetland delineation. Assumes RGP-004-MN permit. Will respond to any USACE questions after permit submittal. Facilitate wetland permit coordination. Permit application dates will be established with the State s Project Manager to obtain the USACE permit for the May 19, 2017 letting date. State s Deliverables: 1. Wetland delineation report and wetland boundaries in CAD format. 2. Renew of Permit application 3. Meeting attendance 1. Meeting attendance and 2. WCA/USACE Joint Permit Application 10.0 SPECIAL PROVISIONS (Source Code 1297) The Contractor will prepare a draft Division S special provisions package for District review and a final package for the submittal to the Central Office. The Contractor will be responsible for producing the Special Provisions for unique items in this project not covered in the MnDOT Standard Specifications for Construction. Each provision will contain a description, materials, construction requirements, method of measurement, and basis of payment for each item. Deletions from, and additions to, Standard Specifications will be written and included as necessary. State will provide Special Provision sections 1404 (Maintenance of Traffic and Traffic Control), 1803 (Prosecution of Work), 1806 (Determination and Extension of Contract Time), 1807 (Failure to Complete Work on Time), and any District-specific edits of the Boiler Plate Provisions. An electronic draft copy will be submitted to State for review along with the 90%, 95% and 100% Final Design plans submittal Deliverables State s Deliverables: 1. Cost data information. 16

17 (Maintenance of Traffic and Traffic Control) (Prosecution of Work) (Determination and Extension of Contract Time) (Failure to Complete Work on Time) 6. District-special edits of boiler plate provisions. 1. Index of anticipated Special Provisions at 60% submittal. 2. Draft Special Provisions at 90% submittal. 3. Final Special Provisions at 95% submittal 11.0 CONSTRUCTION COST ESTIMATE (Source Code 1250) The Consultant will submit the Engineer s Construction Cost Estimate for each project based on quantities with the Intermediate Design (60% Complete), 90% and 95% submittal. The cost estimates will use the latest cost data available. The estimates must be submitted electronically in an Excel format. In addition to the required cost estimates in Excel format, the final design submittal (100%) will include an electronic file of estimated quantities and costs utilizing Geopak Quantities Manager (this uses Microsoft Access database). The 95% submittal will also include a separate file detailing costs of incidental and lump sum items. The electronic file will be submitted by the State directly to the Estimates Unit for loading into the Trns*port system Deliverables 12.0 PROJECT State s Deliverables: 1. Funding source information for cost estimate splits. 2. Cost information data (unit prices) 1. 60%, 90%, 95% and 100% cost estimates 2. Cost estimate splits for agreements. 30% Plan 60% Plan September 30, 2016 October 8, % Plan January 19, 2017 Plans, specifications, and cost estimate of completed plan for MnDOT District review. 95% Plan February 16, 2017 Plans, specifications, and cost estimate of completed plan for MnDOT Central Office review. 100% Plan Early April 2017 Signed plan complete and ready to be submitted to Central Office. Final cost estimate. Letting May 19,

SCOPE OF WORK AND DELIVERABLES T.H.

SCOPE OF WORK AND DELIVERABLES T.H. Exhibit A SCOPE OF WORK AND DELIVERABLES T.H. s 27, 73 and 289 in Moose Lake S.P. 8821-200 PROJECT OVERVIEW The project is located in Moose Lake, Carlton County s on TH 27, 73, and 289. TH 27 RP 245.044

More information

Exhibit A Scope of Services and Deliverables West Swan River Bridge Approaches

Exhibit A Scope of Services and Deliverables West Swan River Bridge Approaches Exhibit A Scope of Services and Deliverables West Swan River Bridge Approaches PROJECT OVERVIEW S.P. 6929-21 is on T.H. 73 in St. Louis County. The project includes replacement of existing Bridge #9262

More information

Detail Design For Pavement Rehabilitation on Trunk Highway 14 From Tracy to Revere

Detail Design For Pavement Rehabilitation on Trunk Highway 14 From Tracy to Revere Detail Design For Pavement Rehabilitation on Trunk Highway 14 From Tracy to Revere Section 1 Introduction and Intersection Information State Project (SP) 6401-37 on MN Highway 14 SP 6401-37 is a Bituminous

More information

MnDOT Contract Exhibit A - Scope of Services

MnDOT Contract Exhibit A - Scope of Services Introduction Information Introduction This Scope of Services represents work on two individual highway improvement projects as described below. The State intends to let two of the projects as separate

More information

MnDOT Contract Exhibit A- Scope of Services. Project Information -

MnDOT Contract Exhibit A- Scope of Services. Project Information - Detail Design For Pedestrian Improvements on Trunk Highways 23, 59, and 68 In the Marshall Area Introduction and Project Information Introduction The purpose of this contract is to provide the State with

More information

Detail Design for State Project

Detail Design for State Project Introduction and Project Information Detail Design for State Project 4210-49 Introduction This contract includes detailed design to letting for the shoulder widening of Trunk Highway (TH) 68 between the

More information

CHAPTER 1: TITLE SHEET and GENERAL LAYOUT

CHAPTER 1: TITLE SHEET and GENERAL LAYOUT CHAPTER 1: TITLE SHEET and GENERAL LAYOUT AREA OF ENVIRONMENTAL SENSITIVITY It is important to show the areas of environmental sensitivity in the plan to make sure these areas are not impacted. These locations

More information

Maintenance of Traffic sequence of operations including any phasing and detour maps;

Maintenance of Traffic sequence of operations including any phasing and detour maps; All Local-let projects are required to have a Stage 2 submittal to the LPA Manager for review. The only exceptions are 2-lane resurfacing, striping, guardrail, and raised pavement markers, unless otherwise

More information

Work Type Definition and Submittal Requirements 14.6 Signing Plan Design & Special Provisions. Work Type Definition

Work Type Definition and Submittal Requirements 14.6 Signing Plan Design & Special Provisions. Work Type Definition Work Type Definition Pages 1-3 detail the work type definition. In order to become pre-qualified for this work type, please see the Work Type Submittal Requirements on pages 4-6. I. Description Signing

More information

Florida's Turnpike Enterprise Roadway Phase III (90%) & Phase IV (100%) Check List Per FDM and TDH Part 3

Florida's Turnpike Enterprise Roadway Phase III (90%) & Phase IV (100%) Check List Per FDM and TDH Part 3 Notes to Reviewers Section 301 Design Exceptions, Variation, and Technical Memorandums Special directives date and source Key Sheet Section 302 Location Map w/ location of project on map All applicable

More information

Suggested Traffic Signal Design Procedures Indefinite Delivery (ID) Contract Locations and Conventional Signal Contract Locations

Suggested Traffic Signal Design Procedures Indefinite Delivery (ID) Contract Locations and Conventional Signal Contract Locations Suggested Traffic Signal Design Procedures Indefinite Delivery (ID) Contract Locations and Conventional Signal Contract Locations MDOT SUGGESTED TRAFFIC SIGNAL DESIGN PROCEDURE INDEFINITE DELIVERY INSTALLATION

More information

TABLE OF CONTENTS 1200 PLAN PREPARATION

TABLE OF CONTENTS 1200 PLAN PREPARATION 1200 PLAN PREPARATION TABLE OF CONTENTS PAGE 1201 General Plan Sheet Information... 12-1 1201.1 Introduction... 12-1 1201.2 Unit of Measure... 12-1 1201.3 Plan Sheet Materials and File Format... 12-1 1201.4

More information

CHAPTER 14: TRAFFIC SIGNAL STANDARDS Introduction and Goals Administration Standards Standard Attachments 14.

CHAPTER 14: TRAFFIC SIGNAL STANDARDS Introduction and Goals Administration Standards Standard Attachments 14. 14.00 Introduction and Goals 14.01 Administration 14.02 Standards 14.03 Standard Attachments 14.1 14.00 INTRODUCTION AND GOALS The purpose of this chapter is to outline the City s review process for traffic

More information

Washington County Road Engineering Plan Submittal/Review Checklist

Washington County Road Engineering Plan Submittal/Review Checklist Washington County Road Engineering Plan Submittal/Review Checklist Washington County Land Use Case File Number: Parcel(s): Developer/Owner Name(s): Developer/Owner E-mail(s): The following elements should

More information

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360)

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 Email: cdd@ci.tumwater.wa.us WATER-SEWER-STREET-STORM (IN CITY) Submittal Checklist TUM - RCVD BY DATE STAMP APPLICANT INFORMATION

More information

Update: July 20, 2012

Update: July 20, 2012 Location and Design Manual, Volume 3 ODOT Office of CADD and Mapping Services Update: July 20, 2012 ** NOTE: All metric references have been removed from this manual. ** PREFACE REVISIONS Glossary of Terms

More information

Revised BRIDGE REPORT AND LAYOUT PAVEMENT STRUCTURE DESIGN CHAPTER VII UTILITIES CHAPTER VIII TRAFFIC CONTROL DEVICES

Revised BRIDGE REPORT AND LAYOUT PAVEMENT STRUCTURE DESIGN CHAPTER VII UTILITIES CHAPTER VIII TRAFFIC CONTROL DEVICES CHAPTER I CHAPTER II CHAPTER III CHAPTER IV CHAPTER V CHAPTER VI GENERAL INFORMATION PRELIMINARY DESIGN SURVEYS DETAIL DESIGN BRIDGE REPORT AND LAYOUT PAVEMENT STRUCTURE DESIGN CHAPTER VII UTILITIES Revised

More information

City of Massillon Site Plan Checklist

City of Massillon Site Plan Checklist City of Massillon Site Plan Checklist The following information MUST be included with all Site Plans submitted for review and processing in order to constitute a complete Site Plan Package. Incomplete

More information

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST YES* GENERAL SUBMISSION ITEMS Does the submission include: 1. Thirteen (13) copies of completed Application Form? 2. Thirteen (13) copies of the Preliminary

More information

CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION:

CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION: CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION: LOG NO.: LEGEND REVIEW REVIEWED BY DATE / - Requirement satisfied 1 O Requirement not satisfied 2?

More information

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS All plans for sanitary sewer main extensions, improvements and modifications

More information

Work Type Definition and Submittal Requirements Work Type: Subsurface Utility Engineering (SUE)

Work Type Definition and Submittal Requirements Work Type: Subsurface Utility Engineering (SUE) MUST be qualified under Minnesota Department of Transportation Prequalification Program - Work Type 15.1 Subsurface Utility Engineering The first section, Work Type Definition, provides a detailed explanation

More information

LOWNDES COUNTY ENGINEERING PLAN REVIEW CHECKLIST. Design Professional: Phone: Developer: Phone: 2 nd Submittal (No Fee)

LOWNDES COUNTY ENGINEERING PLAN REVIEW CHECKLIST. Design Professional: Phone: Developer: Phone: 2 nd Submittal (No Fee) MEMORANDUM MICHAEL B. FLETCHER, P.E. COUNTY ENGINEER 327 N. Ashley Street Valdosta, GA 31601 Telephone: (229) 671-2424 Fax: (229) 245-5299 mfletcher@lowndescounty.com LOWNDES COUNTY ENGINEERING PLAN REVIEW

More information

Plan Preparation Checklist

Plan Preparation Checklist Appendix D Plan Preparation Checklist It is the responsibility of the Designer to complete and submit this checklist along with all required drawings for OUC (EFP) Review. All drawings submitted for OUC

More information

580 - NOISE BARRIERS OPSS 580 INDEX

580 - NOISE BARRIERS OPSS 580 INDEX 580 - OPSS 580 INDEX 580.1 GENERAL 580.1.1 Noise Barrier Design Elements 580.1.1.1 Wind-Load Designs 580.1.1.2 Sound-Absorptive Barriers 580.1.1.3 Noise Barrier Colour, Pattern and Texture 580.1.2 Grading

More information

CONCEPT REVIEW GUIDELINES

CONCEPT REVIEW GUIDELINES Department of Planning & Community Development @ Jefferson Station 1526 E. Forrest Avenue Suite 100 East Point, GA 30344 404.270.7212 (Phone) 404.765.2784 (Fax) www.eastpointcity.org CONCEPT REVIEW GUIDELINES

More information

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated

More information

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for preparation

More information

List of Figures. List of Forms

List of Figures. List of Forms City of Columbia Engineering Regulations PART 1: SUBMISSION OF PLANS Table of Contents Paragraph Description Page No. 1.1 General 1-1 1.2 Engineer s Report 1-1 1.3 Plans 1-3 1.4 Revisions to Approved Plan

More information

Survey Data and TOPO Checklist

Survey Data and TOPO Checklist Checklists Survey Data and TOPO Preliminary Plan Field Review Plans o Field Review Erosion Control Right-of-Way and Utility Meeting Plans Final Plan Field Review Plans Methods of Plan Markups Plan-in-Hand

More information

SITE PLAN Application Packet (Required For All Non-Residential Development Projects)

SITE PLAN Application Packet (Required For All Non-Residential Development Projects) SITE PLAN Application Packet (Required For All Non-Residential Development Projects) Community Development Department 90 North Main Street, Tooele, UT 84074 (435) 843-2130 Fax (435) 843-2139 Dear Applicant,

More information

CHAPTER 2C - PRELIMINARY DESIGN. General... 2C-1. Review of Work Load... 2C-2 Establishing Priorities... 2C-2

CHAPTER 2C - PRELIMINARY DESIGN. General... 2C-1. Review of Work Load... 2C-2 Establishing Priorities... 2C-2 SECTION 2C - 1 - PROJECT REVIEW CHAPTER 2C - PRELIMINARY DESIGN General... 2C-1 SECTION 2C - 2 - COORDINATING TIME SCHEDULES Review of Work Load... 2C-2 Establishing Priorities... 2C-2 SECTION 2C 3 - REVIEW

More information

CONVEYANCE PIPELINE AND PUMP STATION

CONVEYANCE PIPELINE AND PUMP STATION SCOPE OF WORK CONVEYANCE PIPELINE AND PUMP STATION The purpose of this scope of work is to provide engineering services to revise and complete the design of the RUWAP pipeline and 5th Avenue Pump Station

More information

Guidelines and Checklist For SAWS Sanitary Sewer. Developmental Engineering Division

Guidelines and Checklist For SAWS Sanitary Sewer. Developmental Engineering Division Guidelines and Checklist For SAWS Sanitary Sewer Developmental Engineering Division INITIAL CONSIDERATIONS UTILITY SERVICE AGREEMENT Utility Service Agreement A Utility Service Agreement (USA) will be

More information

Guidelines for the Preparation of ITS & Signal Plans by Private Engineering Firms

Guidelines for the Preparation of ITS & Signal Plans by Private Engineering Firms Guidelines for the Preparation of ITS & Signal Plans by Private Engineering Firms INTRODUCTION Use the following Guidelines in conjunction with the ITS & Signals Scope of work provided in the Project Scoping

More information

SECTION 6A ROADWAY PLAN PREPARATION

SECTION 6A ROADWAY PLAN PREPARATION SECTION 6A ROADWAY PLAN PREPARATION Table of Contents Page No 6A.1 GENERAL...1 6A.2 PRELIMINARY PLANS...3 6A.2.1 PRELIMINARY PLAN SHEETS...3 6A.2.2 PRELIMINARY PROFILE SHEETS...4 6A.3 PHASE A PLANS...4

More information

Porter County Plan Commission

Porter County Plan Commission Plan Type: Development Plan Administrative DRC PC Primary Plan Administrative DRC PC Secondary Plat/Replat Administrative DRC PC PUD Conceptual Detailed Final Project Information Project Name: Developer

More information

REQUIREMENTS. for ENGINEERING SERVICES PUBLIC CONSTRUCTION PROJECTS

REQUIREMENTS. for ENGINEERING SERVICES PUBLIC CONSTRUCTION PROJECTS REQUIREMENTS for ENGINEERING SERVICES on PUBLIC CONSTRUCTION PROJECTS April, 2007 David W. Johnson Senior Engineer Design & Construction Requirements for Engineering Services on Public Construction Projects

More information

PLANNING AND DEVELOPMENT

PLANNING AND DEVELOPMENT OVERVIEW Effective January 1, 1992 all applications for multi-family residential and all non-residential building permits require site plan approval before permit issuance. All new developments and existing

More information

Plan Submittal Checklist for Permit Projects Compliance Required Information. (Answer Yes or Not Applicable (NA)) Yes NA

Plan Submittal Checklist for Permit Projects Compliance Required Information. (Answer Yes or Not Applicable (NA)) Yes NA Note: This Checklist has been created to assist in and maintain a uniform review of Construction Design Documents for projects done under permit with the County. This document has been created by the Permit

More information

Automated Machine Guidance

Automated Machine Guidance Design Manual Chapter 5 - Roadway Design 5H - Automated Machine Guidance 5H-1 Automated Machine Guidance A. Concept Automated machine guidance (AMG) for grading is a process in which grading equipment,

More information

Authorized Agent: City of Manassas Check List Attached: Contact: Address: Phone Number: Fax Number: Developer s Name: Phone Number:

Authorized Agent: City of Manassas Check List Attached: Contact:   Address: Phone Number: Fax Number: Developer s Name: Phone Number: CITY OF MANASSAS DEPARTMENT OF COMMUNITY DEVELOPMENT DEVELOPMENT SERVICES DIVISION 9027 Center Street Room 201 Manassas, Virginia, 20110 Phone: 703-257-8278 Fax: 703-257-5831 Application Date: APPLICANT

More information

SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS

SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS 101 General 102 Submittal Requirements A. Initial Submittal B. Second Submittal 103 Plan Requirements A. Subdivisions B. Site Plans 104 Approval of

More information

City of Beaumont. Public Works Engineering. Street Improvement Plan Checklist REV 4/18/16

City of Beaumont. Public Works Engineering. Street Improvement Plan Checklist REV 4/18/16 City of Beaumont Public Works Engineering Project Name: TR: Project No.: Date: Street Improvement Plan Checklist Chk A. All Sheets 1. 24" x 36" 2. Signed by the engineer-of-work 3. Marked with the contact

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND DIRECTIVE 1C-12 Issue date: August 2012 1. General SURVEY, MAPPING AND UTILITY LOCATING This Directive has been developed as a general guide for the survey and mapping effort required for Fund projects.

More information

Chapter 23. Signing and Pavement Marking Plans

Chapter 23. Signing and Pavement Marking Plans Chapter 23 Signing and Pavement Marking Plans 23.1 General... 23-3 23.2 Key Sheet... 23-4 23.3 Signature Sheet... 23-4 23.4 Tabulation of Quantities and Pay Item Notes... 23-4 23.4.1 Standard Notes...

More information

PLAN RATINGS & COMMON ERRORS TO WATCH FOR IN PLANS

PLAN RATINGS & COMMON ERRORS TO WATCH FOR IN PLANS PLAN RATINGS & COMMON ERRORS TO WATCH FOR IN PLANS Project Design Services Unit June 2018 http://ihub/projectdelivery/design/index.html PROJECT RATING FORM This is filled out for ALL Process B projects.

More information

CITY OF LA MARQUE CHAPTER GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS

CITY OF LA MARQUE CHAPTER GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS CITY OF LA MARQUE CHAPTER 2 -------------------------------------------- GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS CHAPTER 2 ------------------------------------------------

More information

Subdivision Application Checklist

Subdivision Application Checklist City of Portsmouth, New Hampshire Subdivision Application Checklist This subdivision application checklist is a tool designed to assist the applicant in the planning process and for preparing the application

More information

CHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN

CHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN N/A Waiver (1) Four (4) copies of application form. (2) Fifteen (15) copies of plan (3) Subdivision/site plan application fee & professional review escrow deposit (4) Variance application fee & professional

More information

SECTION 2 GENERAL REQUIREMENTS

SECTION 2 GENERAL REQUIREMENTS SECTION 2 GENERAL REQUIREMENTS 2-1 ENGINEER REQUIRED: All plans and specifications for Improvements which are to be accepted for maintenance by the County and private, on-site drainage and grading shall

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL Engineering Design Services for the Preliminary Engineering of Lake Nepessing/Davison/Genesee Intersection Improvements Sections 1, 2, 11 and 12 of Elba Township Lapeer County, Michigan

More information

DEVELOPMENT PLAN CHECKLIST

DEVELOPMENT PLAN CHECKLIST Project Identification Information: DEVELOPMENT PLAN CHECKLIST 1.0 GENERAL 1.1 Additional information as required by specific Land Use 1.2 All sheets to include sheet number ( of ) 1.3 Seal and signature

More information

DEVELOPMENT REVIEW COMMENTS LAND DISTURBANCE PERMIT (LDP) CLEARING CLEARING & GRUBBING GRADING. Date Reviewed by. Project Name

DEVELOPMENT REVIEW COMMENTS LAND DISTURBANCE PERMIT (LDP) CLEARING CLEARING & GRUBBING GRADING. Date Reviewed by. Project Name GWINNETT COUNTY Department of Planning and Development One Justice Square 446 West Crogan Street Suite 150 1 st Floor Lawrenceville, GA 30046 Phone: 678.518.6000 Fax: 678.518.6240 www.gwinnettcounty.com

More information

Conceptual, Preliminary and Final Site Plan Review in Holladay City

Conceptual, Preliminary and Final Site Plan Review in Holladay City Conceptual, Preliminary and Final Site Plan Review in Holladay City The City of Holladay incorporated in December, 1999 and adopted its own zoning ordinance in May, 2000. All land use decisions are made

More information

Chapter 13 Plan Submittals

Chapter 13 Plan Submittals Chapter 13 Plan Submittals U30013.DOC 02/01/07 Chapter 13 Plan Submittals Section Topic Page 13.1 General 13.1 13.2 Subdivision Plans 13.1 13.3 Capital Improvement Project Plans 13.12 U30013.DOC 02/01/07

More information

Project Name: County File No.: Checked by: For: Date:

Project Name: County File No.: Checked by: For: Date: Project Name: County File No.: Checked by: For: Date: Print name Firm or agency Items noted in the checklist shall be considered the minimum amount of information necessary for submission of construction

More information

MICHIGAN DESIGN MANUAL ROAD DESIGN CHAPTER

MICHIGAN DESIGN MANUAL ROAD DESIGN CHAPTER 1.01 DEVELOPMENT METHODS 1.01.01 References 1.01.02 General 1.01.03 Survey and Mapping Methods 1.02 PLAN SHEETS MICHIGAN DESIGN MANUAL 1.02.01 Title Sheet A. Project Location B. Traffic Data C. Project

More information

1. Land survey Work. 2. Civil and Structural engineering services.

1. Land survey Work. 2. Civil and Structural engineering services. SECTION 01050 FIELD ENGINEERING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification

More information

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges 50.24 Culverts, Bridges and Culvert Bridges Type, Size and Location (T, S & L) Plans shall be required for all Bridges, Culvert Bridges and Culverts of eight-foot (8') clear span or greater as follows:

More information

SECTION 3 IMPROVEMENT PLAN REQUIREMENTS

SECTION 3 IMPROVEMENT PLAN REQUIREMENTS SECTION 3 IMPROVEMENT PLAN REQUIREMENTS CONTENTS Page 3-1 Digital Submittals 3-2 3-2 Paper Size and Scale 3-2 3-3 Drafting Standard 3-2 3-4 Title Sheet 3-2 3-5 Title Block 3-3 3-6 Drainage, Sewer, Water,

More information

KC Water Rules and Regulations For Water Main Extensions and Relocations

KC Water Rules and Regulations For Water Main Extensions and Relocations KC Water Rules and Regulations For Water Main Extensions and Relocations MAY 2017 NOTE: Changes from 2016 are highlighted in yellow and appear on Pages 5, 8, 10-11, 13, and 15. Additional changes made

More information

APPLICATION FOR SITE PREPARATION PERMIT

APPLICATION FOR SITE PREPARATION PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision/Plat Name: Location Description/ Nearest Intersection: Acreage: APPLICATION FOR SITE PREPARATION PERMIT No.

More information

SITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS

SITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS INCORPORATED VILLAGE OF ROCKVILLE CENTRE BUILDING DEPARTMENT SITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS Presubmission - Prior to a formal submission, the applicant should meet in person with

More information

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for preparation

More information

Minor Site Plan Application and Checklist Land Disturbing Activities

Minor Site Plan Application and Checklist Land Disturbing Activities Minor Site Plan Application and Checklist Land Disturbing Activities INSTRUCTIONS: Please provide the requested information below. The Development Services Department reviews each site plan submittal based

More information

CHAPTER 11. Plan Standards

CHAPTER 11. Plan Standards CHAPTER 11 Plan Standards A. Introduction The city requires uniform public improvement plans for ease of record keeping and understanding. The following standards govern most plan submittals to the city.

More information

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422 B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422 422.1 GENERAL The work under these tender items consists of the fabrication and installation in open cut of precast reinforced

More information

Anne Arundel County Dept. of Inspections and Permits Water Sewer Plan Checklist

Anne Arundel County Dept. of Inspections and Permits Water Sewer Plan Checklist Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated

More information

Site Plan Review Application. Interest in the Property (e.g. fee simple, land option, etc.)

Site Plan Review Application. Interest in the Property (e.g. fee simple, land option, etc.) 1. Identification CITY OF FENTON 301 South Leroy Street Fenton, Michigan 48430-2196 (810) 629-2261 FAX (810) 629-2004 Site Plan Review Application Project Name Applicant Name Address City/State/Zip Phone

More information

UTILITY AND STREET CONSTRUCTION PLAN REQUIREMENTS SECTION 1

UTILITY AND STREET CONSTRUCTION PLAN REQUIREMENTS SECTION 1 UTILITY AND STREET CONSTRUCTION PLAN REQUIREMENTS SECTION 1 ENGINEERING STANDARDS FOR UTILITY AND STREET CONSTRUCTION PLANS MARCH 2014 CONSTRUCTION PLAN SHEET FORMAT REQUIREMENTS REPRODUCIBLE MYLAR 1.

More information

INSTRUCTIONS: 1. Record the transmittal letter number, date, and subject on the transmittal record sheet located in the front of the manual.

INSTRUCTIONS: 1. Record the transmittal letter number, date, and subject on the transmittal record sheet located in the front of the manual. MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Technical Support Design Services Section TRANSMITTAL LETTER NO. (0-03) MANUAL: Standard Plates DATED: September

More information

B-PERMIT PLAN CHECK MANUAL

B-PERMIT PLAN CHECK MANUAL B-PERMIT PLAN CHECK MANUAL 5. SEWER PLANS Sewer Plans are usually submitted in conjunction with Street Plans to meet the requirements of conditions imposed on a Planning or Zoning action. In some cases

More information

SECTION 3 SUBMISSION REQUIREMENTS

SECTION 3 SUBMISSION REQUIREMENTS SECTION 3 SUBMISSION REQUIREMENTS Table of Contents Page No 3.1 GENERAL... 3 3.2 COORDINATION WITH OUTSIDE AGENCIES... 3 3.3 PRELIMINARY DESIGN... 4 3.4 FINAL DESIGN... 5 3.4.1 GENERAL... 5 3.4.2 PHASE

More information

BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006

BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006 Project Name: BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006 Phase: Unit: # Lots: Development Type (residential, commercial, industrial, etc.) Braselton Project No.

More information

DIVISION PAVEMENT MARKINGS AND MARKERS

DIVISION PAVEMENT MARKINGS AND MARKERS DIVISION 61 66 PAVEMENT MARKINGS AND MARKERS 66.01 SCOPE: The purpose of these specifications is to describe the minimum requirements of the City of Chesapeake for pavement markings and shall be in addition

More information

Guidelines for the Preparation of Traffic Signal & Intelligent Transportation System Plans on Design-Build Projects August 2007

Guidelines for the Preparation of Traffic Signal & Intelligent Transportation System Plans on Design-Build Projects August 2007 Guidelines for the Preparation of Traffic Signal & Intelligent Transportation System Plans on Design-Build Projects August 2007 INTRODUCTION Use the following Guidelines in conjunction with the Traffic

More information

CHAPTER 11 SURVEY CADD

CHAPTER 11 SURVEY CADD CHAPTER 11 SURVEY CADD Chapter Contents Sec. 11.01 Sec. 11.02 Sec. 11.03 Sec. 11.04 Sec. 11.05 Sec. 11.06 Sec. 11.07 Sec. 11.08 Sec. 11.09 Sec. 11.10 General Description of Survey File Contents of Survey

More information

LARAMIE COUNTY PLANNING & DEVELOPMENT OFFICE 3966 Archer Pkwy Cheyenne, WY Phone (307) Fax (307)

LARAMIE COUNTY PLANNING & DEVELOPMENT OFFICE 3966 Archer Pkwy Cheyenne, WY Phone (307) Fax (307) 3966 Archer Pkwy Cheyenne, WY 82009 planning@laramiecounty.com Phone (307) 633-4303 Fax (307) 633-4616 SITE PLAN REVIEW PROCESS 1. Pre-Application Meeting: The applicant shall meet with a Laramie County

More information

CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS

CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE E-10 ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS The City of Lompoc has determined that the Engineering Division should administer and issue Encroachment

More information

Essential Skills: Reading and Interpreting Maps and Plans

Essential Skills: Reading and Interpreting Maps and Plans Essential Skills: Reading and Interpreting Maps and Plans Prepared for: NEW YORK STATE PLANNING FEDERATION April 14, 2015 Prepared by: BME ASSOCIATES Peter G. Vars, P.E. Stages of Plan Review Concept /

More information

GCG ASSOCIATES, INC. February 8, Mr. Nathaniel Strosberg, Town Planner 101 Main Street Town of Ashland Ashland, MA 01721

GCG ASSOCIATES, INC. February 8, Mr. Nathaniel Strosberg, Town Planner 101 Main Street Town of Ashland Ashland, MA 01721 GCG ASSOCIATES, INC. CIVIL ENGINEERING AND LAND SURVEYING 84 Main Street Wilmington, Massachusetts 01887 Phone: (978) 657-9714 Fax: (978) 657-7915 February 8, 2016 Mr. Nathaniel Strosberg, Town Planner

More information

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS 11.01.00 Preliminary Site Plan Approval 11.01.01 Intent and Purpose 11.01.02 Review 11.01.03 Application 11.01.04 Development Site to be Unified 11.01.05

More information

CITY OF MUSKEGO DRAFTING STANDARDS

CITY OF MUSKEGO DRAFTING STANDARDS CITY OF MUSKEGO DRAFTING STANDARDS GENERAL - These standards apply to all plans. 1. Plans must be prepared on sheets measuring 36 inch across and 22 inch to 24 inch high unless otherwise specified under

More information

Appendix E-4. City of Fort Collins. Requirements for Utility Plans

Appendix E-4. City of Fort Collins. Requirements for Utility Plans Appendix E-4 City of Fort Collins Requirements for Utility Plans Project Name: Project Planner: Design Engineering Firm: Developer: All applications for final development plans must include final development

More information

CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 002 DRAFTING AND DRAWING STANDARDS

CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 002 DRAFTING AND DRAWING STANDARDS CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 002 DRAFTING AND DRAWING STANDARDS SECTION 2.1 INTRODUCTION... 1 (a) Objective...1 (b) Applicability...1 2.2 SUBMITTAL

More information

CITY OF REEDLEY NEW DEVELOPMENT PLAN REVIEW CHECK LIST

CITY OF REEDLEY NEW DEVELOPMENT PLAN REVIEW CHECK LIST CITY OF REEDLEY NEW DEVELOPMENT PLAN REVIEW CHECK LIST Tract Number and Subdivision Name: Engineering Firm: Contact Person: Address: City: State: Zip: Phone No. Fax No. Assessor s Parcel Number(s) Tentative

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 5 GEOTECHNICAL SUBMISSION GUIDELINES Geotechnical Bulletin GB5 was developed

More information

Application for Site Plan Review

Application for Site Plan Review Application for Site Plan Review 3275 Central Blvd., Hudsonville, Michigan 49426-1450, 616.669.0200 fax 616.669.2330 It is STRONGLY recommended that any application that must go before the Planning Commission

More information

DEPARTMENT OF COMMUNITY DEVELOPMENT SITE PLAN INFORMATION

DEPARTMENT OF COMMUNITY DEVELOPMENT SITE PLAN INFORMATION DEPARTMENT OF COMMUNITY DEVELOPMENT SITE PLAN INFORMATION 220 Clay Street Cedar Falls, Iowa 50613 General Information: Applications for developing a commercial, multi-family, or residential (in an overlay

More information

Please remove and replace the entire Table of Contents, Section A to Section J and all Appendices.

Please remove and replace the entire Table of Contents, Section A to Section J and all Appendices. Please remove and replace the entire Table of Contents, Section A to Section J and all Appendices. The following is a list of changes to the Design Criteria: 1. A2.01 General Note 4 Utility Coordination

More information

CITY OF OLIVETTE SITE PLAN AND COMMUNITY DESIGN REVIEW INFORMATION PACKET

CITY OF OLIVETTE SITE PLAN AND COMMUNITY DESIGN REVIEW INFORMATION PACKET CITY OF OLIVETTE SITE PLAN AND COMMUNITY DESIGN REVIEW INFORMATION PACKET THE FOLLOWING PACKET CONTAINS: PETITION FOR NONRESIDENTIAL DEVELOPMENT SITE PLAN AND COMMUNITY DESIGN REVIEW SCHEDULE OF DATES

More information

DEVELOPMENT SERVICES SITE PLAN SUBMITTAL 2.2.3

DEVELOPMENT SERVICES SITE PLAN SUBMITTAL 2.2.3 DEVELOPMENT SERVICES SITE PLAN SUBMITTAL 2.2.3 Unified Development Code (UDC) Article 2, Applications, Procedures and Criteria provides the steps for applying the Unified Development Code standards to

More information

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for

More information

Scope of Services. Project management tasks are estimated based upon anticipated project duration of 52 weeks.

Scope of Services. Project management tasks are estimated based upon anticipated project duration of 52 weeks. Scope of Services Project Understanding The City of Sparks (City) has also requested the HDR Engineering, Inc. (HDR) provided limited shop drawing review and periodic observation during construction and

More information

CHAPTER 29 PROJECT COMPLETION DOCUMENTS

CHAPTER 29 PROJECT COMPLETION DOCUMENTS CHAPTER 29 PROJECT COMPLETION DOCUMENTS PROJECT COMPLETION Upon completion of traffic control signal system and lighting projects, there are forms and checklists to ensure that the project is closed out

More information

DRAFTING STANDARDS 9.00 DRAFTING STANDARDS

DRAFTING STANDARDS 9.00 DRAFTING STANDARDS DRAFTING STANDARDS 9.00 DRAFTING STANDARDS Final plans shall conform in appearance, format, accuracy, and quality to the standards used in the Springfield Engineering Division. Additional standards shall

More information

PREPARATION GUIDELINES FOR UDFCD MAINTENANCE SITE PLAN

PREPARATION GUIDELINES FOR UDFCD MAINTENANCE SITE PLAN PREPARATION GUIDELINES FOR UDFCD MAINTENANCE SITE PLAN Overview The Urban Drainage and Flood Control District (District) is now requiring that a Maintenance Site Plan (Plan) be submitted for all pond projects

More information

CHAPTER 3 INFORMATION REQUIRED FOR PUBLIC IMPROVEMENT CONSTRUCTION PLANS TABLE OF CONTENTS

CHAPTER 3 INFORMATION REQUIRED FOR PUBLIC IMPROVEMENT CONSTRUCTION PLANS TABLE OF CONTENTS CHAPTER 3 INFORMATION REQUIRED FOR PUBLIC IMPROVEMENT CONSTRUCTION PLANS TABLE OF CONTENTS Section Title Page 3.1 General... 3-1 3.1.1 Plan Set...3-1 A. Loveland (City Limits Only)...3-1 3.1.2 Final Mylars...3-1

More information

Site Plan/Building Permit Review

Site Plan/Building Permit Review Part 6 Site Plan/Building Permit Review 1.6.01 When Site Plan Review Applies 1.6.02 Optional Pre- Application Site Plan/Building Permit Review (hereafter referred to as Site Plan Review) shall be required

More information