1 Oil and Natural Gas Corporation Limited Eastern Offshore Asset 3rd Floor, Subhadra Arcade, Bhanugudi Junction Kakinada, Andhra Pradesh. Pin: Phone: Fax: NO. EOA/KG-DWN-98-2/OMC-PQC/2016 Date: 18 th Oct Expression of Interest (EOI) for Pre-Qualification ONGC, Eastern Offshore Asset, Kakinada invites potential reputed Management consultancy firms/ agencies having experience and expertise in the field of providing Management Consultancy services for execution of Offshore Oil & Gas Project(s) involving subsea completions / FPSOs/ Offshore Installation works - SURF(Subsea Umbilical, Risers & Flow lines). The Consultancy firms/ agencies are requested to submit their Pre-qualification documents; within 10 days i.e. before , as per the Pre-Qualification Criteria (PQC) enclosed at Annexure -2. The following Firms/ agencies were Pre-qualified based on Pre-qualification documents submitted by them against our earlier EOI: i. M/s. The Boston Consulting Group (BCG) ii. M/s. McKinsey & Company, Inc. iii. M/s. Ernst & Young With Technical collaboration of Upstream Adviser iv. Consortium of M/s. Turner & Townsend Private Limited and Price Waterhouse Coopers (PwC) Private Limited v. Consortium of M/s. GMC Limited, UK & KPMG, India vi. M/s. D Appolonia S.P.A., Italy The above Consultancy firms/ agencies who have already submitted their Pre-qualification documents against our earlier EOI need not submit their documents again. Page 1 of 15
2 Details of EOI for Pre-Qualification are as under: EOI No. EOA/KG-DWN-98-2/OMC-PQC/2016 Description of work Hiring of Owner s Management Consultant (OMC) for providing Management Consultancy Services for execution of KG-DWN-98/2 Offshore Oil & Gas Development Project involving subsea completions / FPSOs/ SURF (Subsea Umbilical, Risers & Flow lines). Brief of indicative scope of Work is enclosed at Annexure 1. Pre-Qualification Criteria (PQC) Please refer Annexure 2 (1) Mr. P.Lakshminarayana, GM(M) 3rd Floor, Subhadra Arcade, Bhanugudi Jn., Kakinada Tel ; Mob laxminarayan_p@ongc.co.in Contact Person from ONGC, regarding this EOI (2) Mr. M.V.R.Gopala Rao, DGM(E) 3rd Floor, Subhadra Arcade, Bhanugudi Jn., Kakinada Tel ; Mob rao_mvrg@ongc.co.in Last date for submission of documents Page 2 of 15
3 Annexure 1 KG-DWN-98/2 Project Hiring of Owner s Management Consultant (OMC) Indicative Scope of Work 1.0 Background 1.1 The KG-DWN-98/2 is a deep water NELP block of ONGC located on the East Coast of India. The Eastern Offshore Asset (EOA) of ONGC located at Kakinada, Andhra Pradesh is mandated with the responsibility of developing the offshore oil and gas fields in this block. The Block is broadly divided into two areas - the Northern Discovery Area (NDA) and the Southern Discovery Area (SDA). For ease of development & monetization, the NDA is further sub-divided into 2 Clusters viz. Cluster-I and Cluster-II. The present development relates to the development of Cluster-II area of the NDA. It is ONGC's first large deep-water field development project, with water depths ranging from 400 m to 1,300 m and is one of the most critical projects in current ONGC portfolio. ONGC is envisaging the following schedule for development of this project: Commencement of First Gas : June, 2019 Commencement of First Oil : March, 2020 Considering the magnitude & complexity of the Project with tight completion schedule, ONGC is looking for a Management Consulting Firm which will act as Owner's Management Consultant (OMC). Page 3 of 15
4 The OMC primarily shall be required to assist ONGC's Project / PMO Teams and work in close coordination with ONGC s Project Management Consultants (PMC) [being hired separately] for close monitoring, control and progress & exception reporting of the Project to senior ONGC Management. ONGC s Project Team is located at Kakinada, Andhra Pradesh while ONGC s PMO (Project Management Office), which is entrusted with the job of monitoring & control of high value projects through Stage-Gate Project Management Process, is located at New Delhi. The Project Management Consultants (PMC) for the Project, being hired separately by ONGC, shall be responsible for overall Project and Interface Management with micro-planning and coordination of all activities on a daily basis to deliver the Project. PMC role shall also consist of detailed design and engineering review of various contracts after award of work. 1.2 Facilities envisaged under the KG-DWN-98/2 Project: The Salient Features of the Field Development Plan (FDP) are given below, with the field layout for the selected Concept placed at Annexure-1: 1) Subsea Wells (35 nos.): Cluster 2A (Oil) Cluster 2B (Gas) : 15 Oil Producers + 12 Water Injectors : 8 deep water gas wells 2) Subsea Facilities: Subsea Production Systems (SPS) & associated facilities viz. Subsea Trees, flowlines, manifolds, umbilical & control systems. 3) Process Platform: One Process Platform with a LQ & Utility Platform in shallow water (100m water depth) both bridge connected to each other. Production capacity: MMSCMD (Cluster 2B free gas). 4) FPSO: 425m water depth, Turret mooring (permanent), Tandem offloading (stabilized oil). Production capacity: Oil 90,000 BOPD, Gas 3.8 MMSCMD, Water Injection 33,800 BWPD 5) Subsea Pipelines: i) Gas export pipeline: From Platform to Shore (cluster 2B free gas + cluster 2A associated gas). Page 4 of 15
5 ii) iii) iv) Subsea pipeline from FPSO to Platform (Cluster 2A associated gas) Rich & Lean MEG pipelines between onshore MEG plant & Platform Subsea pipe lines network connecting Cluster 2B gas fields to the platform including Spur lines v) Subsea Pipe lines network connecting Cluster 2A Oil fields to the FPSO including spur lines, Water injection lines and Gas lift lines. 6) Onshore MEG Plant: Located onshore at Odalarevu, Andhra Pradesh. MEG regeneration capacity: 2800 m 3 /day (17,500BPD) of Rich MEG 1.3 Project Implementation: ONGC has planned for development of Cluster-II through the following major, but not limited to, contract packages; tendering process for which have been initiated: 1) Marine Surveys: Geo-Physical Surveys : Completed Met Ocean Studies : Contract awarded Geo-Technical Investigations : Contract awarded Geo-Mechanical Study : Contract awarded 2) Drilling & Bundled Services: Hiring of Drilling Rigs, hiring of Bundled Services to support Rig Operations, Well Completion and Testing for Production & Activation. 3) Subsea Production Systems (SPS): Procurement of SPS, other long lead items viz. subsea trees, UTA, SDU topside control system, manifolds through finalization of Frame Work Agreement. 4) Subsea Umbilical, Risers & Flowlines (SURF): EPIC contract for subsea pipelines, Umbilical, Umbilical associated items (UTAs, etc.), Risers, Flow lines, tie-in between wells, control systems and tie-back facility. 5) FPSO: Charter Hiring of FPSO for processing & offloading via Shuttle tankers evacuation O&M contract for 12. 6) Offshore Platform: EPC Contract through ICB tendering for Offshore Process Platform including export Pipeline (in shallow water) to Onshore Terminal. Page 5 of 15
6 7) Onshore Gas Terminal Works and MEG plant: EPC contract through ICB tendering. 8) Hiring of MSV: Installation of Subsea Tree & subsequent IMR activities. 9) Owners Engineering Consultant (OEC): Systems engineering and operability by ONGC / Owner s Engineering Consultant (OEC) 10) Project Management Consultant (PMC): Overall Project & Interface management 2.0 Scope of Work of Owner s Management Consultant: 2.1 In order to meet the targets of First Gas and First Oil as brought out at para.1.1 above, it is required that all the Project activities are planned, monitored, controlled and reported in a way so that the project is implemented as per agreed schedules and costs. To achieve the above, ONGC intends to appoint an Owner s Management Consultant, referred henceforth as OMC, having proven competencies in the areas of Project Management of Offshore Oil & Gas Projects, as detailed in the Scope of Work defined in this section. The OMC shall be required to assist ONGC's Project / PMO Teams and work in close coordination with ONGC s Project Management Consultants (PMC) [being hired separately] for close monitoring, control and progress & exception reporting of the Project to senior ONGC Management. OMC personnel may be required to serve in various ONGC offices / vendor premises / other Meeting locations anywhere in India. The Project Management Consultants (PMC) for the Project, as brought out at Sl. No. 1.3 Point no. 10) above, are being hired separately by ONGC. The PMC shall be responsible for overall Project and Interface Management with microplanning and coordination of all activities of all work packages on a daily basis to deliver the entire Project. 2.2 OMC shall be required to provide Project Management and Capability Assessment / Capability Building Support to ONGC as per the following Scope of Work but not limited to: Page 6 of 15
7 (i) Project Management Support: a. Project Planning & Review b. Project Risk Management c. Stakeholder Management - Internal and External d. Project Monitoring & Control and Progress Reporting e. Web Portal for real time reporting (ii) Capability Assessment and Capability Building Support 3.0 Deliverables for Owner's Management Consultant: Following is the broad list of deliverables, which is indicative but not exhaustive: 3.1 Project Planning & Review: Comprehensive Project Management Plan Global benchmarks on relevant contracting strategies Overall Global Supply Landscapes for different project activities Multi-level project plan / schedule capturing key project activities and milestones. Project Management Tools and Systems for modeling of interdependencies across different work modules/ contracts with validity of licenses during the contract period. Critical path on an ongoing basis at periodic intervals. Project Review and Monitoring Process Detailed key activity/milestone level trackers of all modules/packages of the project Mid-course correction and mitigation measures to ensure timely delivery of the project as per requirement Project Update Meetings / Reviews of Project Progress Implementation of ONGC s Stage Gate Project Management Process Mobilization of Domain experts for need based peer review and expert guidance. 3.2 Risk Management: Risk & Opportunity Identification, Mitigation & Response Plans at key activity / Milestone level Risk Management Plan at key activity/milestone level. Review of Risk Management Plan at regular intervals as per project Management Plan. Timely reporting of imminent threats & opportunities. Page 7 of 15
8 3.3 Stakeholder Management: Stakeholder Management Plan Review of Stakeholder Management Plan at regular intervals Timely approvals through engagement with Executive Committee and top management Timely procurement and issue resolution through engagement with internal stakeholders such as Asset, Drilling / Well / Engineering Services, Institutes, MM and Finance etc. Platform/Provision for seamless interaction of Project team and PMO with contractors of various modules/packages of the project Facilitation of liaising with MoPNG and DGH for alignment and timely approvals 3.4 Project Monitoring & Control and Progress Reporting Tracking and monitoring of Tendering activities for early issue identification, mid-course corrections, and timely approvals. Forecasting of future performance with the use of software tools in order to effectively manage the project schedule and cost. Identification of the potential problems / setbacks w.r.t. cost, quality & schedules of overall project and suggestion of remedial actions. Project Update Meetings / Reviews of Project Progress at various levels Templates for Schedule & progress reporting / risk management / Stakeholder management and Interface & exceptions reporting. Communication Management Plan to facilitate real time flow of information to relevant offices. Generation, Communication and archiving of Reports and Alerts as per Communication Management Plan. 3.5 Web Based Project Management Portal: A new web portal to ensure real time progress / exception reporting with capability of issuing suitable alerts through / sms for timely intervention by the senior management.. Regular updation of the portal using the latest project management software tools by the OMC and other inputs from the Project Team / PMC. Relevant Project Management Tools / Software / hardware etc. and maintenance of the same at ONGC premises for the entire duration of this contract. A minimum of 6 licenses of the relevant Project management Tool / Software with validity for entire contract period Training to ONGC officers working on the project on relevant Project Management Tools. Page 8 of 15
9 3.6 Capability Assessment and Capability Building: Identification of Capability Gaps in the project organization Mobilization of Domain Experts to best address the identified capability gaps Platform for knowledge sharing/technology partnership with global E&P operators and other stakeholders to bridge the capability gap Trainings and exposures to the project organization for institutionalization of global best practices in project delivery and enhancing project management competency in ONGC Trainings and exposures to the project organization by global technical experts on various areas such as Deep Water development, sub-sea architecture, sub-sea installation, Advanced Project Management tools etc. Page 9 of 15
10 Annexure -2 Pre-Qualification Criteria 2.0 Eligibility and experience of the bidder:- 2.1.(a) Sl. No Criteria Technical weightag e/marks i (a) (b) Experience of the consultancy firms in past 10 The bidder should have experience of providing Management Consultancy services for a minimum period of 2 during last 10 (reckoned from the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria from different known service providers) in execution of Offshore Oil & Gas Project(s) involving subsea completions / FPSO / SURF through one or more contract(s) on cumulative basis. Experience of less than 6 months shallwill not be counted while arriving at total experience. Bidders to provide details as per Table-1 along with supporting documents. The bidder should have completed at least one Contract in last 10 (as on the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria from different known service providers) in providing Management Consultancy Services in execution of Offshore Oil & Gas Project(s) involving subsea completions / FPSO / SURF. Experience of less than 6 months in a single assignment will shall not be counted. Bidders to provide details as per Table-2 along with supporting documents. 60 Weightage 100% 80% 30 More than or more contracts 2-3 1contra ct Remarks Struck off portion deleted and bold letter portions added to keep uniformity with Evaluation of Quality Matrix for OMC approved by EC. Struck off portion deleted and bold letter portions added to keep uniformity with Evaluation of Quality Matrix for OMC approved by EC. Page 10 of 15
11 ii Experience of Key Personnel 25 a Global Project Management Expert: Minimum 15 Project Management Experience in Oil & Gas Project(s) out of which at least 10 (as on the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria from different known service providers) experience should be in Project Management of Offshore Oil & Gas Project(s) involving subsea completions/ FPSO / SURF. The expert should be minimum Engineering / Management graduate. Bidder to provide details as per Table-3 along with supporting documents. 17 Experience of more than 20 b c Project Lead: Minimum 7 Project Management Experience out of which atleast 03 (as on the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria from different known service providers) experience should be in Project Management of Offshore Oil & Gas Project(s)involving subsea completions/ FPSO / SURF. The Project Lead should be minimum Engineering / Management graduate. He should be familiar with Industry Standard Project Management Softwares viz. Primavera / Microsoft Project, etc. Bidder to provide details as per Table-4 along with supporting documents. Project Support Executives/Consultant executives : Minimum 02 of Project Management Consultancy Experience in Oil & Gas Project(s) (as on the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria 5 Experience of more than 10 3 Experience of more than 3 Experie nce of Experie nce of 7-10 Experie nce of 2-3 Struck off portion deleted and bold letter portions added to keep uniformity with Evaluation of Quality Matrix for OMC approved by EC. Struck off portion deleted and bold letter portions added to keep uniformity with Evaluation of Quality Matrix for OMC approved by EC. Page 11 of 15
12 from different known service providers). They should be minimum Engineering / Management graduate. They should have hands on experience of Industry Standard Project Management Softwares viz. Primavera / Microsoft Project etc. Bidder to provide details as per Table-5 along with supporting documents. iii Financial Strength of the 15 Consultant. a Net Worth of the Company 9.75 Positive for two F.Ys/ in last five /F.Y.s Positive for one year in last five / F.Y.s b Turnover for last two 5.25 >7 crore 5 crore to 7 crore Overall 100 Note: Overall more than 65 marks are to be obtained for pre-qualification to participate in tender. 1. For their experience as per clause 2.1.(a).(i).(a) and 2.1.(a).(i).(b) above, the service provider should submit either of the following: Completion certificate on letter head of the Client/ from clients covering the scope of work, duration of engagement, time period (From/to), and client s satisfaction with the execution of the work done by the service provider. Client reference who can be contacted of to verify service provider experience. 2. Existing contracts in operation for more than one (01) which are not yet completed on the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria from different known service providers, against which customers / bidder have certified satisfactory performance of such contracts, shall also be considered meeting requirement of clause no. 2.1.(a).(i).(a) above. Similarly, period of such contracts prior to the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria from different known service providers, shall be considered as part of their experience in relation to clause 2.1.(a).(i).(a) based on satisfactory performance certificate from clients/self- certification of bidder. 3. Contract(s) awarded prior to 10 as on the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria from different known service providers, which have run at least 1 in last 10, shall be considered meeting requirement of the clause 2.1.(a).i.(a) based on satisfactory performance certificate from the client(s)/self-certification by bidder. Similarly contracts awarded prior to 10 as on the date of issue of notice by ONGC seeking documents meeting the Pre-qualification criteria from different known service providers, but extending in portion of these 10, shall be considered as part of their experience towards requirement of clause 2.1.(a).(i).(a) on satisfactory performance certificate from their client(s)/selfcertification of the bidder. Page 12 of 15
13 Bidder to furnish the CVs of the personnel to be deployed duly certified by the CEO/Country Head of their company to be submitted along with the bid in the format given in Table-3,4 & 5 respectively. 2.1 (b) In case the bidder is an Indian company/ Indian Joint venture company, the Indian company/ Indian Joint venture company or its technical collaborator/ joint venture partner should meet the criteria laid down at 2.1.(a).(i). 2.2 Details of experience and past performance of the service provider and the collaborator (in case of collaboration) or of joint venture partner (in case of a joint venture), on works/ jobs done of similar in the past and details of current work in hand and other contractual commitments (along with personnel proposed to be deployed), indicating areas and clients are to be submitted in the table given at Annexure 3 along with their request for issue of Tender Document, in support of the experience laid down at para 2.1(a) and 2.1(b) above. 2.3 In case the service provider is a consortium of companies, the following requirement should be satisfied by the service provider: a. The leader of the consortium should satisfy the minimum experience requirement as per para 2.1.(a) above. b. The leader of the consortium should confirm unconditional acceptance of full responsibility of executing the Scope of work of this tender. This confirmation should be submitted along with the techno-commercial bid. c. All the members of the consortium must undertake in their MOU that each party shall be jointly and severally liable to ONGC for any and all obligations and responsibilities arising out of this contract. 2.4.(a) Indian companies/ Joint Venture companies :- Indian bidders whose proposal for technical collaboration/ Joint Venture involves foreign equity participation or payment of royalty and / or lumpsum for technical know-how and wherever Govt. approval is necessary, are required to submit copy of Govt. approval, on their application submitted to SIA, prior to the date price bid opening. 2.4.(b) Bidders should submit Memorandum of Understanding (MOU) / Agreement with their technical collaborator/joint venture partner (in case of Joint venture) clearly indicating their roles under the scope of work. 2.4.(c) MOU/ Agreement concluded by the bidder with technical collaborator/ joint venture partner (in case of joint venture), should also be addressed to ONGC, clearly stating that the MOU /Agreement is applicable to this tender and shall be binding on them for the contract period. Notwithstanding the MOU/Agreement, the responsibility of completion of job under this contract will be with the bidder The Bidders shall submit audited financial documents duly certified by the bidder in support of 2.1.(a).(iii).(a) & 2.1.(a).(iii).(b). Page 13 of 15
14 Details of experience and past performance of the service provider & personnel Annexure-3 Table-1 Experience of Service Provider in Management Consultancy Services in execution of Offshore Oil & Gas Project(s) with subsea completions / FPSO / SURF in last 10. Sl.No. Client name with address Description of Assignment / Contract & Brief on Scope of Work Contract /Assignment Start Date Completion Date Contact person of client along with contact no. & id Remarks Table-2 Experience of Service Provider in contract(s) completed for Management Consultancy services in execution of Offshore Oil & Gas Project(s) with subsea completions / FPSO / SURF in last 10. Sl.No. Client name with address Description of Assignment / Contract & Brief on Scope of Work Contract /Assignment Start Date Completion Date Contact person of client along with contact no. & id Remarks Table-3 Experience of Global Project Management Expert for the project Sl. Qualific N ation o. Name of the Global Project Management Expert Total Experience in Project Management in Oil & Gas Project(s) (Add Separate Sheets, if required) along with details of project, client, names along with , telephone no. of contact person of client) Project/ project Client/ client Start & completi on Dates Total experience in Project Management of Offshore Oil & Gas Project(s) involving subsea completions/ FPSO / SURF (Add Separate Sheets, if required) along with details of project, client, names along with , telephone no. of contact person of client ) Project/ project Client/ client Start & completio n Dates Remarks Page 14 of 15
15 Table-4 Experience of Project Lead for the project Sl. Qualificati No. on Name of the Proje ct Lead Total Experience in Project Management in Oil & Gas Project(s) (Add Separate Sheets, if required) along with details of project, client, names along with , telephone no. of contact person of client) Project/ project Client / client natur e Start date & comple tion Date Total experience in Project Management of Offshore Oil & Gas Project(s) involving subsea completions / FPSO / SURF (Add Separate Sheets, if required) along with details of project, client, names along with , telephone no. of contact person of client ) Project/ project Client / client natur e Start date & completi on Date Familiarizati on with Industry Standard Project Managemen t Software viz. Primavera / Microsoft Project etc. (Details & Certification s to be provided) Remar ks Table-5 Experience of Project Support Executives for the project Sl. Name of the Project Support Executive Qualification Total Experience in Project Management in Oil & Gas Project(s) (Add Separate Sheets, if required) along with details of project, client, names along with , telephone no. of contact person of client Project/ project Client/ client Start date & completion Date Hands on experience of Industry Standard Project Management Software viz. Primavera / Microsoft Project etc. (Details & Certifications to be provided) Remarks Note: Bidder should submit proof of work experience of previous client / employer of their personnel in accordance with the CV submitted for giving technical evaluation score for experience of personnel. Otherwise he / she shall be disqualified Page 15 of 15
NO. ONGC/EOA/KG-DWN-98/2 Cluster 2/ONSHORE/EOI/2016/ Date: EXPRESSION OF INTEREST (EOI)
Oil and Natural Gas Corporation Limited Eastern Offshore Asset Office of Project Manager, KG-DWN- 98/2 Project 3rd Floor, Subhadra Arcade, Near Bhanugudi Junction Kakinada - 533 003, Andhra Pradesh, India
More informationReliance Industries Limited
Reliance Industries Limited Notice Inviting Expression of Interest (RIL/E&P/EOI/2010/05) (Under International Competitive Bidding) For BLOCK NO : KG-DWN-98/3 (KG D6) Reliance Industries Limited (RIL),
More informationGLOBAL EXPRESSION OF INTEREST (EoI) FOR INTEGRATED DEVELOPMENT SERVICES FOR MANGALA, BHAGYAM & AISHWARIYA (MBA) FIELDS WITHIN THE RJ-ON-90/1 BLOCK
GLOBAL EXPRESSION OF INTEREST (EoI) FOR INTEGRATED DEVELOPMENT SERVICES FOR MANGALA, BHAGYAM & AISHWARIYA (MBA) FIELDS WITHIN THE RJ-ON-90/1 BLOCK Vedanta (erstwhile Cairn India Limited merged with Vedanta
More informationReliance Industries Limited. Notice Inviting Expression of Interest
Reliance Industries Limited Notice Inviting Expression of Interest (RIL/E&P/EOI/2010/02) (Under International Competitive Bidding) For Oil & Gas Field Developments A) Block ALL BLOCKS Reliance Industries
More informationRELIANCE INDUSTRIES LIMITED
RELIANCE INDUSTRIES LIMITED Petroleum Business (E&P) Notice Inviting Expression of Interest (RIL/E&P/EOI/2012/07) (Under International Competitive Bidding) A] For All Oil & Gas Fields Reliance Industries
More informationGlobal Energy Group s multi-client contract showcases UK-based engineering talent to achieve first oil for Catcher
News release 12 January 2018 Global Energy Group s multi-client contract showcases UK-based engineering talent to achieve first oil for Catcher Global Energy Group (GEG), a Scotland-headquartered energy
More informationA. BACKGROUND B. GENERAL TERMS OF REFERENCE
Page 1 of 7 A. BACKGROUND National Oil Corporation of Kenya (NOC) is a company wholly owned by the Government of Kenya which is charged with the mandate to participate in all aspects of petroleum business
More informationChiyoda Corporation and Ezra Holdings Limited enter into MOU to establish 50:50 Joint Venture, EMAS CHIYODA Subsea
Chiyoda Corporation and Ezra Holdings Limited enter into MOU to establish 50:50 Joint Venture, EMAS CHIYODA Subsea Chiyoda will invest in Ezra s Subsea Services business, EMAS AMC, to form EMAS CHIYODA
More informationReliance Industries Limited
Reliance Industries Limited Notice Inviting Expression of Interest (RIL/E&P/EOI/2010/06) (Under International Competitive Bidding) For Oil & Gas Fields Development A) Block ALL BLOCKS Reliance Industries
More informationFloating LNG facilities
Lessons learned from three of the industry s first FLNG contracts position TechnipFMC as the pioneer developer for the next generation of FLNG facilities facilities As one of the pioneers in the provision
More informationCertificate by the Architect: Certified that no addition and deletion has been made to the tender documents downloaded from the IIT Madras web site.
INDIAN INSTITUTE OF TECHNOLOGY MADRAS ENGINEERING UNIT CHENNAI 600 036 NOTICE INVITING TENDERS FOR APPOINTMENT OF ARCHITECTURAL CONSULTANT No: 35/ ARC / 2013 14 TECHNICAL BID COVER 2 NAME OF WORK: Providing
More informationOIL INDIA LIMITED DULIAJAN
Matter of Advertisement EXPRESSION OF INTEREST (EOI) No. EOI/PDNO/034/2016 Oil India Limited, a Government of India NAVARATNA Category Enterprise, engaged in the business of Exploration, Production & Transportation
More informationBharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli , TAMIL NADU, INDIA MATERIALS MANAGEMENT / CAPITAL EQUIPMENT
An ISO 9001 Company Bharat Heavy Electricals Limited (High Pressure Boiler Plant), TAMIL NADU, INDIA MATERIALS MANAGEMENT / CAPITAL EQUIPMENT ENQUIRY NOTICE INVITING TENDER Phone: +91 431 257 7653 Fax
More informationINDONESIA DEEPWATER INVESTMENT
INDONESIA DEEPWATER INVESTMENT SUBSEA ASIA 23-24 NOVEMBER 2015 @ DHARMAWANGSA HOTEL - JAKARTA PRESENTED BY DINAR INDRIANA KHOIRIAH HEAD PROJECT COMMUNICATIONS INPEX CORPORATION AGENDA Supply Chain Investment
More informationOffshore Construction Management Services. Capability & Experience
Offshore Construction Management Services Capability & Experience Capability Overview INTECSEA has a proven track record for providing solutions to problems faced when implementing frontier projects, by
More informationSUBSEA 7 AND GRANHERNE ALLIANCE. Engaging Early to Deliver Value
SUBSEA 7 AND GRANHERNE ALLIANCE Viable Solutions Operators are seeking novel and reliable concepts to overcome industry challenges such as complex reservoirs, cost, growth and schedule creep and to optimise
More informationDeep Panuke. 01U 27 Feb 08 Issued for Use C. Hewitt N. Coonan D. Riffe R. MacQueen Rev Date Reason for Issue Prepared Checked Checked Approved Title
01U 27 Feb 08 Issued for Use C. Hewitt N. Coonan D. Riffe R. MacQueen Rev Date Reason for Issue Prepared Checked Checked Approved Title Design of Subsea Wellhead Protection Structures Prequalification
More informationINTEGRATED SUBSEA PRODUCTION SYSTEMS Efficient Execution and Cost-Effective Technologies Deliver Project Success. Deepsea technologies
INTEGRATED SUBSEA PRODUCTION SYSTEMS Efficient Execution and Cost-Effective Technologies Deliver Project Success Deepsea technologies Streamlining Subsea Production Systems for Smaller Fields AFGlobal
More informationINTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE
INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE 4 What we do 6 Why choose us? 7 Service and product capabilities For more than 35 years, we have been providing clients with standalone and
More informationFacilitate. Collaborate. Innovate.
Cost Effective Subsea Processing Theme: Standardized Low Cost Separation System - Functional Specification and Market Study CALL FOR PROPOSALS SEPTEMBER 2014 Aim Facilitate. Collaborate. Innovate. Cost
More informationWHITE ROSE OILFIELD DEVELOPMENT APPLICATION
WHITE ROSE OILFIELD DEVELOPMENT APPLICATION VOLUME 1 CANADA-NEWFOUNDLAND BENEFITS PLAN SUBMITTED BY: HUSKY OIL OPERATIONS LIMITED AS OPERATOR SUITE 801, SCOTIA CENTRE 235 WATER STREET ST. JOHN S, NF, A1C
More informationBay du Nord Framework Agreement
Bay du Nord Framework Agreement Technical Briefing Department of Natural Resources July 2018 1 Outline Project Overview Fiscal and Equity Terms NL Benefits Next Steps 2 Project Overview Location Flemish
More informationSubsea Structural Engineering Services. Capability & Experience
Subsea Structural Engineering Services Capability & Experience Capability Overview INTECSEA s subsea structural engineering team has a proven track record for providing solutions to problems in the implementation
More informationTechnological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa
Technological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa 1 SAFER, SMARTER, GREENER Content Going Deeper Scale/Size of Deepwater Mega
More informationSECTION - II BID DATA SHEET
SECTION - II BID DATA SHEET Kenya Power and Lighting Company II - 1 Contract: A36 SECTION -II BID DATA SHEET The following bid-specific data for the plant and equipment to be procured shall amend and/or
More informationSubsea UK Neil Gordon Chief Executive Officer Championing the UK Subsea Sector Across the World
Subsea UK Neil Gordon Chief Executive Officer Championing the UK Subsea Sector Across the World 1 Overview About Subsea UK Facts and figures UK industry evolution Centre of Excellence Technology and Innovation
More informationOur projects Shell Prelude FLNG
Our projects A new landmark in the Offshore industry milestones Bolo bolo bolo bolo bolo bolo 2009 Master Agreement It all started in 2009 when Shell and the Technip-Samsung Heavy Industries Consortium
More informationSend your directly to
Welcome to Chess Subsea Production System Training - SPS Subsea production system (SPS) is associated with the overall process and all the equipment involved in drilling, field development, and field operation.
More information4 Briefing. Responsible investor
Issue Responsible investor 4 Briefing Wednesday 8 th February 2012 In 2010, we accepted all 26 recommendations made by the Bly Report our internal investigation into the Deepwater Horizon incident. BP
More informationThe Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250)
The Office of the Finance and Purchasing Manager Telephone : (250) 352-8204 Fax : (250) 352-6594 REQUEST FOR PREQUALIFICATIONS RADIO COMMUNICATIONS INFRASTRUCTURE UPGRADE CONTRACTOR SERVICES 2018-PRQ-01
More informationNEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017
NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP 697-16-016 July 28, 2017 Reference is made to the Request for Proposal (RFP) to Service Providers for Nevada Shared Radio Replacement Project, upon
More informationEngineering. Drafting & Design. Regulatory Interface. Project & Construction Management. Marine Operations Services
Engineering Drafting & Design Regulatory Interface Project & Construction Management Marine Operations Services Corporate Overview EXMAR Offshore is dedicated to the ownership and leasing of offshore assets
More informationCAPETANO OIL LIMITED (+233) (+233)
1 CAPETANO OIL LIMITED (+233) 202 027 485 (+233) 209 985 175 www.capetano.com info@capetano.com C90/24 Osu Badu Street, Airport Residential Area, Accra Ghana. 2017 Capetano Oil Limited. All rights reserved.
More informationNext Generation Training for Subsea & Marine Operations Engineers and Asset Managers
An Intensive 5 Day Training Course Next Generation Training for Subsea & Marine Operations Engineers and Asset Managers 16-20 Dec 2018, Dubai 09-13 Jun 2019, Dubai 15-19 Dec 2019, Dubai 20-NOV-18 This
More informationFPSO Design and Technology
An Intensive 5 Day Training Course FPSO Design and Technology 14-OCT-18 13-17 Oct 2019, Dubai www.petroknowledge.com FPSO Design and Technology WHY CHOOSE THIS TRAINING COURSE? This 5-day Design and Technology
More informationWHITE ROSE DEVELOPMENT PROJECT. Canada-Newfoundland and Labrador Benefits Report. For the Period April 1 June 30, 2004
WHITE ROSE DEVELOPMENT PROJECT Canada-Newfoundland and Labrador Benefits Report For the Period April 1 June 30, 2004 HDMS ID: 003839954 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 SUMMARY OF PROJECT ACTIVITIES...
More informationFIBRE FOR DEEP OFFSHORE OIL & GAS OPERATIONS
FIBRE FOR DEEP OFFSHORE OIL & GAS OPERATIONS Antoine Lecroart, Ronan Michel (Alcatel-Lucent Submarine Networks) Email: Alcatel-Lucent Submarine Networks, Route de
More informationOil & Gas Offshore. Industry challenges in deepwater discover
Oil & Gas Offshore Industry challenges in deepwater discover Galp Energia E&P portfolio spread over 4 continents, with main assets located in Portuguese speaking countries 2 Integrated position Enduring
More informationi-tech SERVICES DELIVERING INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE
i-tech SERVICES DELIVERING INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE 3 About us 4 What we do 6 Why choose us? 7 Service and product capabilities OUR VALUES Safety Integrity Innovation
More informationOffshore Pipelines. Capability & Experience
Offshore Pipelines Capability & Experience Capability Overview INTECSEA is a leading engineering and project delivery company in the offshore oil and gas sector. It operates across the full project cycle
More informationThe use of an integrated contract model (iepci) for Subsea developments
NH GRAND HOTEL KRASNAPOLSKY AMSTERDAM 3-5 APRIL 2017 The use of an integrated contract model (iepci) for Subsea developments Tim Crome 1991 1993 1995 1997 1999 2001 2003 2005 2007 2009 2011 MCE Deepwater
More informationENGINEERING SOLUTIONS FOR THE OIL & GAS INDUSTRY
ENGINEERING SOLUTIONS FOR THE OIL & GAS INDUSTRY BACK GROUND BASIS ENGINEERING IS A PROVIDER OF FACILITIES SOLUTION DESIGN TO THE OIL & GAS UPSTREAM MIDSTREAM MARKETS Founded in 1981, Basis Engineering
More informationLOCOMOTIVE ENGINEERING DEPTT.
SHEET 1 OF 9 SUBJECT: FOR DESIGN MANUFACTURING INSTALLATION OF FIXTURES FOR MANUFACTURING OF SHELL ASSEMBLY OF WAG7 LOCOMOTIVE Enclosures: Rev Date Prepared Rev Date Prepared Rev Date Prepared Approved
More informationQUARTERLY UPDATE. Summary
QUARTERLY UPDATE Q1 FY14 Summary Production levels consistent with designed plant capacity Current order backlog of US$86 million which will support full production until the beginning of Q4 FY14 Strong
More informationWorldwide Technip in Turkmenistan
Worldwide Technip in Turkmenistan Technip brings its worldwide expertise to the economic growth of Turkmenistan Technip at a glance Technip is a world leader in project management, engineering and construction
More informationBrae Area Pre Decommissioning MARATHON BRAE. Brae Area Decommissioning Programme. June Revision 1.0
Brae Area Pre Decommissioning MARATHON BRAE Brae Area Decommissioning Programme June 2017 Revision 1.0 Why is Marathon Oil decommissioning? Decommissioning is a natural step in the life cycle of an oil
More informationOpportunities and Challenges in Deepwater West Africa Projects
Opportunities and Challenges in Deepwater West Africa Projects Finding Petroleum - Finding African Oil Mark Jones - INTECSEA (UK) Royal Society of Chemistry, London 28th January 2015 Opportunities and
More informationENGINEERING SOLUTIONS AND CAPABILITIES. Capacity enhancement for deep water operations THE CHALLENGE THE SOLUTION
Capacity enhancement for deep water operations ENGINEERING SOLUTIONS AND CAPABILITIES THE CHALLENGE THE SOLUTION Operations are taking place in much deeper waters and in more diverse locations, Aquatic
More informationClick to edit Master title style APPEA AWIC UPDATE. Self Audit Checklist Source Control First Response
APPEA AWIC UPDATE Click to edit Mutual Master Aid subtitle style Self Audit Checklist Source Control First Response Presenter: Tom Nolan Perth 1st 4 th March, 2010 2012 WHAT IS APPEA? The Australian Petroleum
More informationSUB: EMPANELMENT OF CONSULTANCY AGENCIES FOR BUILDING PROJECTS/WORKS.
M/s ----------------------------------------- ----------------------------------------- ------------------------------------------- SUB: EMPANELMENT OF CONSULTANCY AGENCIES FOR BUILDING PROJECTS/WORKS.
More informationmarine, construction, drilling, floating production, decommissioning and renewables industries.
Maritime Assurance & Consulting Ltd (MAC), a Bureau Veritas Group Company, is a UK-based company with a global reach, offering a comprehensive range of support services to the Dynamic Positioning Assurance
More informationManager of Company Announcements ASX Limited Level 6, 20 Bridge Street SYDNEY NSW By E-Lodgement
2 April 2012 Manager of Company Announcements ASX Limited Level 6, 20 Bridge Street SYDNEY NSW 2000 By E-Lodgement Highlights: Galoc Oil Field recommences production Otto Energy Ltd (ASX:OEL) is pleased
More informationGALOC PHASE II DEVELOPMENT APPROVED AND RESERVES UPGRADED
11 September 2012 Manager of Company Announcements ASX Limited Level 6, 20 Bridge Street SYDNEY NSW 2000 By E-Lodgement GALOC PHASE II DEVELOPMENT APPROVED AND RESERVES UPGRADED Highlights: Final Investment
More informationCOLLABORATIVE R&D & IP ISSUES IN TECHNOLOGY TRANSFER IN UNIVERSITY SYSTEM
COLLABORATIVE R&D & IP ISSUES IN TECHNOLOGY TRANSFER IN UNIVERSITY SYSTEM Avinash Kumar Addl. Dir (IPR) DRDO HQ, DRDO Bhawan, Rajaji Marg New Delhi- 100 011 avinash@hqr.drdo.in IPR Group-DRDO Our Activities
More informationNATIONAL GAS DEVELOPMENT TASK FORCE ANNOUNCEMENT
NATIONAL GAS DEVELOPMENT TASK FORCE ANNOUNCEMENT It is announced for the of the General Public that the launched National Gas Development Task force will post all information on the Task Force, including
More informationVIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application
VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application 2 Virtus Subsea Connectors Delivering Long-Lasting Reliability at Each Subsea Connection Subsea production
More informationACTEON FLS - DECOMMISSIONING
ACTEON FLS - DECOMMISSIONING CLIENT VERSION 15 FEBRUARY 2016 INTRODUCTION TO ACTEON FLS ACTEON FLS Subsea services company Acteon has launched a new service. Acteon Field Life Service (FLS) offers a joined-up
More informationOnshore & Offshore Engineering and Management of Subsea Cables and Pipelines
Established in 1997, Primo Marine is an independent specialist with a wealth of experience in subsea cable engineering, from landfalls to subsea marine infrastructures. With an extensive track record,
More informationTo attract people and capital, industry must educate the public
CATEGORIZED 2011, January/February Posted on 28 January 2011 To attract people and capital, industry must educate the public Critical issues in drilling & completions with Naresh Kumar, Chairman, Deepwater
More informationSwiber Holdings Limited 1Q FY08 Results Briefing
Swiber Holdings Limited 1Q FY08 Results Briefing 15 May 2008 Page 1 Financial Highlights 1Q 2008 Page 2 Key highlights a record quarter Revenue (US$ m) Net Profit (US$ m) 160 1Q Y-O-Y: 266.9% 1Q Y-O-Y:
More informationOFFSHORE SPECIALIST ENGINEERING SERVICES. ZEE Engineering Consultants
OFFSHORE SPECIALIST ENGINEERING SERVICES ZEE Engineering Consultants With experienced engineers, with advanced knowledge in FEA modeling and backed by state of the art software, ZEE Engineering Consultants
More informationRisk Management of the First Deepwater Project in China Asia Offshore Energy Conference September 27, 2012
Risk Management of the First Deepwater Project in China Asia Offshore Energy Conference September 27, 2012 1 Advisories Forward-Looking Statements Certain statements in this presentation are forward-looking
More informationMINISTRY OF AGRICULTURE, LIVESTOCK & FISHERIES STATE DEPARTMENT OF FISHERIES AND BLUE ECONOMY
MINISTRY OF AGRICULTURE, LIVESTOCK & FISHERIES STATE DEPARTMENT OF FISHERIES AND BLUE ECONOMY KENYA MARINE FISHERIES AND SOCIO-ECONOMIC DEVELOPMENT PROJECT (KEMFSED) TERMS OF REFERENCE For an Individual
More informationAKER BP OG NORDOMRÅDET LANGSIKTIG VERDISKAPNING MED LOKALE RINGVIRKNINGER
AKER BP OG NORDOMRÅDET LANGSIKTIG VERDISKAPNING MED LOKALE RINGVIRKNINGER OLJE- OG GASSKONFERANSEN Bodø 8. november 2017 Kyrre Sørensen, Site Manager Area North, Aker BP ASA Aker BP Creating the leading
More informationPrelude FLNG Project. DOT conference presentation. November Jaap de Vries, Prelude FLNG Project Director FINAL
Prelude FLNG Project DOT conference presentation Jaap de Vries, Prelude FLNG Project Director FINAL Copyright of Royal Dutch Shell plc 1 Prelude FLNG: the largest offshore floating facility ever The Prelude
More informationMARISSUBSEA.com. Core Values. People. Integrity. Quality. Contents. 02/03 What we do. 04/05 Representatives. 06/07 ROV personnel
MARISSUBSEA.com Contents 02/03 What we do 04/05 Representatives 06/07 ROV personnel 08/09 Hydrographic personnel 10/11 Diving personnel 12/13 Additional disciplines Core Values People Our people make our
More informationSubsea 7 Norway. Monica Th. Bjørkmann Sales and Marketing Director
Subsea 7 Norway 28.06.2012 Monica Th. Bjørkmann Sales and Marketing Director Agenda Subsea 7 Norway What We Do Our Assets Market Going Forward Closing 27-Jun- 12 Page 2 Our new beginning A combination
More informationSubsea Positioning In deep water
Subsea Positioning In deep water PETRONAS - PETRAD - INTSOK CCOP DEEPWATER SUBSEA TIE-BACK Damai Puri Resort & Spa, Kuching, Sarawak, MALAYSIA 24TH - 26TH January, 2011 Supplier to the oil & gas industry
More informationThe petroleum industry, internationalisation, 11 and technology development. Industry development and internationalisation
The petroleum industry, internationalisation, employment 11 and technology development Industry development and internationalisation Employment in the petroleum sector The significance of technology development
More informationOIL INDIA LIMITED DULIAJAN
ADVERTISEMENT EXPRESSION OF INTEREST (EOI) NO. EOI/O/339/2017-2018 Oil India Limited, a Government of India NAVARATNA Category Enterprise, engaged in the business of Exploration, Production & Transportation
More informationSubsea and Export Systems. The world s leading independent provider of subsea and export systems, engineering and technology solutions.
Subsea and Export Systems The world s leading independent provider of subsea and export systems, engineering and technology solutions. Wood is a global leader in project delivery, engineering and technical
More informationOffshore Completion Systems
Offshore Completion Systems North Sea Experience Presented by: Hein Langaker Well Integrity and Control Convention #09 Completion crews often strive to create a challenging environment. We call our workplace
More informationFor personal use only
3D Oil Limited Level 5, 164 Flinders Lane Melbourne VIC 3000 Tel: +61 3 9650 9866 Fax: +61 3 9639 1960 www.3doil.com.au ASX Release 16 April 2013 West Seahorse Oil Field: Concept selected and FEED commenced
More informationTOURISM CORPORATION OF GUJARAT LIMITED
TOURISM CORPORATION OF GUJARAT LTD. Block No.16/17, 4th Floor, UdyogBhavan, Sector 11, Gandhinagar(Gujarat) Phone : (079) 23222645 / 23220002 Fax: (079) 23238908 TENDER NOTICE Offers are invited from reputed
More informationDiscipline. Technology TECHNOLOGY DEVELOPMENT. Technology WITHIN SBM OFFSHORE
Project Discipline Technology Product Line TECHNOLOGY DEVELOPMENT Technology WITHIN SBM OFFSHORE TECHNOLOGY CREATING VALUE 1959 1960 1972 1973 1977 1981 1985 1985 1986 CALM Buoy Drilling Jack-up DP Drillship
More informationQUARTERLY UPDATE. Summary
QUARTERLY UPDATE Q2 FY14 Summary Production levels returning to higher rates Higher production output anticipated for 2H FY14 to support compressed delivery times Current order book increased to US$88m
More informationTaking a broader view
Taking a broader view A brief introduction to DNV GL 1 SAFER, SMARTER, GREENER We are a global classification, certification, technical assurance and advisory company 2 In a challenging world we make businesses
More informationLocal Contribution to the Aasta Hansteen development
Local Contribution to the Aasta Hansteen development 05th June 20 Stian Sande Who are we Presentation overview What is our role on Aasta Hansteen Onshore activites and local contribution What do we expect
More informationMERMAID MARINE AUSTRALIA LTD INVESTOR BRIEFING DEVELOPMENT OF DAMPIER SUPPLY BASE
MERMAID MARINE AUSTRALIA LTD INVESTOR BRIEFING DEVELOPMENT OF DAMPIER SUPPLY BASE 1 May 2008 Agenda Overview Sector Highlights - Record Offshore Activity Levels - The Gorgon Project Mermaid s Strategy
More informationArctic and Cold Climate. Capability & Experience
Arctic and Cold Climate Capability & Experience Capability Overview WorleyParsons and INTECSEA are world leaders in design and construction of oil and gas production facilities located in remote, hostile
More informationSATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007
BR 94/2007 TELECOMMUNICATIONS ACT 1986 1986 : 35 SATELLITE NETWORK NOTIFICATION AND COORDINATION ARRANGEMENT OF REGULATIONS 1 Citation 2 Interpretation 3 Purpose 4 Requirement for licence 5 Submission
More informationIndustry collaboration to develop next generation subsea (well stream) compression system
PAU, FRANCE 5-7 APRIL 2016 Industry collaboration to develop next generation subsea (well stream) compression system Marco Gabelloni, Knut Nyborg, Anders Storstenvik Aker Solutions Alexandre de Rougemount
More informationJoint Industry Programme on E&P Sound and Marine Life - Phase III
Joint Industry Programme on E&P Sound and Marine Life - Phase III Request for Proposals Number: JIP III-15-03 Long Term Fixed Acoustic Monitoring of Marine Mammals throughout the Life Cycle of an Offshore
More informationSubsea Production Market and Industry Teaming. Presented by: Bruce Crager Executive Vice President: Expert Advisory Group Endeavor Management
Subsea Production Market and Industry Teaming Presented by: Bruce Crager Executive Vice President: Expert Advisory Group Endeavor Management February 28, 2017 Worldwide Progression of Water Depth Capabilities
More informationENGINEERING SERVICES CONSULTANCY
ENGINEERING SERVICES CONSULTANCY Managing complexity, unlocking value Petrofac Engineering & Production Services 02 03 Discover the difference Consultancy services Petrofac is an international service
More informationUniversity of Northampton. Graduate Leaders in Early Years Programme Audit Monitoring Report by the Quality Assurance Agency for Higher Education
Graduate Leaders in Early Years Programme Audit Monitoring Report by the Quality Assurance Agency for Higher Education November 2014 Contents Report of monitoring visit... 1 Section 1: Outcome of the monitoring
More informationSun Petrochemicals Private Limited
Sun Petrochemicals Private Limited Introduction Website : www.sunpetro.com/song/ Sun Oil & Natural Gas (SONG) (A Division of Sun Petrochemicals Private Limited) 17/B, Mahal Industrial Estate, Mahakali
More informationSUBSEA SYSTEM ARCHITECTURE FOR CORAL SOUTH FLNG
Introduction to Eni Our new mission: We are an energy company. We are working to build a future where everyone can access energy resources efficiently and sustainably. Our work is based on passion and
More informationBrief to the. Senate Standing Committee on Social Affairs, Science and Technology. Dr. Eliot A. Phillipson President and CEO
Brief to the Senate Standing Committee on Social Affairs, Science and Technology Dr. Eliot A. Phillipson President and CEO June 14, 2010 Table of Contents Role of the Canada Foundation for Innovation (CFI)...1
More information* Image courtesy of H-L-Andersen. Scanning in Explosive Environments Offshore
* Image courtesy of H-L-Andersen Scanning in Explosive Environments Offshore Ramboll Oil & Gas have been in partnership now since taking their first Z+F IMAGER in 2010. Ramboll Oil & Gas delivers engineering
More informationTotally Integrated Power (TIP) for the Oil and Gas Industry
Totally Integrated Power (TIP) for the Oil and Gas Industry Power for challenging environments Reliable. Safe. Efficient. Totally Integrated Power (TIP) Our comprehensive portfolio and extensive integration
More informationIndependent Communications Authority of South Africa Pinmill Farm, 164 Katherine Street, Sandton Private Bag X10002, Sandton, 2146
Independent Communications Authority of South Africa Pinmill Farm, 164 Katherine Street, Sandton Private Bag X10002, Sandton, 2146 ANNEXURE A TECHNICAL SPECIFICATIONS ICASA 09/2018 1. Purpose of the Request
More informationMarine Risers. Capability & Experience
Marine Risers Capability & Experience Capability Overview INTECSEA now offers, in a single company, industry leading capability for all marine riser systems including top-tensioned risers (TTRs) for direct
More informationUkrGasVydobuvannya Public invitation for Expression of Interest for participation in the project of gas production enhancement
UkrGasVydobuvannya Public invitation for Expression of Interest for participation in the project of gas production enhancement October 2018 Kyiv Summary and objectives One of the current UkrGasVydobuvannya
More informationOffshore Decommissioning Conference Fairmont Hotel, St Andrews 8 th October 2014
Offshore Decommissioning Conference Fairmont Hotel, St Andrews 8 th October 2014 Delivering the Future Together Delivering The Future Together: Nigel Jenkins CEO Decom North Sea Nigel Jenkins, Chief Executive
More information8(A) CONTRACTING, MENTOR-PROTÉGÉ PROGRAM, & JOINT VENTURES. March 9, 2010 William T. Welch
8(A) CONTRACTING, MENTOR-PROTÉGÉ PROGRAM, & JOINT VENTURES March 9, 2010 William T. Welch THE AUDIENCE How many individuals here represent companies that are now or have been in the 8(a) program? How many
More informationHusky Energy - Development Plan Amendment Application. White Rose Extension Project. Public Review. Noia s Submission
Husky Energy - Development Plan Amendment Application White Rose Extension Project Public Review Noia s Submission September 10, 2014 Table of Contents FOREWORD WREP PUBLIC REVIEW... 1. Background... 1.1
More informationMatrix Composites & Engineering Ltd
Matrix Composites & Engineering Ltd Euroz 2015 Industrials Tour 10 June 2015 Overview Introduction to Matrix Business Operations and Outlook Plant Tour 2 Introduction to Matrix WHO WE ARE AND WHAT WE DO
More informationINTELLIGENT ENGINEERING
INTELLIGENT ENGINEERING Leading marine design through innovation Compass Energy was established in 2004 to provide engineering services for the offshore oil and gas industry in Southeast Asia. We are an
More informationPROCUREMENT OF GOODS UNDER OPEN TENDER PROCEDURE
IFB NO. KGEC/DST-WB/EE /2018-19/995 PROCUREMENT OF GOODS UNDER OPEN TENDER PROCEDURE Kalyani Government Engineering College Kalyani 741 235; Nadia, West Bengal 1 Government of West Bengal Office of the
More information