1 Document Number: ECP Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE EPN, LPN, SPN This procedure details the testing and commissioning procedures for groundmounted switchgear including ring main units and circuit breakers with time-limit fuses and switches. Author: John Mason Approver: Paul Williams Date: 10/09/2018 This document forms part of the Company s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue. Applicable To UK Power Networks External Asset Management G81 Website Capital Programme UK Power Networks Services Connections Contractors Health & Safety ICPs/IDNOs Legal Meter Operators Network Operations Procurement Strategy & Regulation Technical Training THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE

2 Revision Record Version 8.0 Review Date 04/12/2020 Date 18/07/2018 Author John Mason Reason for update: Updated to clarify the CT Loop Continuity test. What has changed: ECP i updated to instruct that the test link must remain in place during testing. ECP i updated to illustrate customer trip connections. ECP i Schematic diagram removed (can be found in Alfresco). ECP c updated to instruct that the test link must remain in place during testing. ECP c Schematic diagram removed (can be found in Alfresco). Version 7.0 Review Date 04/12/2020 Date 27/02/2018 Author John Mason Reason for update: Test form updates. What has changed: ECP a updated to illustrate customer trip connections. ECP e updated to illustrate customer trip connections. Version 6.0 Review Date 04/12/2020 Date 24/05/2017 Author Ian Marshall Reason for update: Updated following concerns raised by UK Power Networks field engineers around the overcurrent and earth fault release test values obtained. What has changed: Lucy VRN2a and VRE2a test form updated (ECP e). Lucy CN2a and VCE2a test form updated (ECP g). New test form ECP i created. Expected vales clarified in Sections 15.1 and Version 5.0 Review Date 04/12/2020 Date 09/09/2016 Author Ian Marshall Reason for update: Updated following introduction of new switchgear from Lucy. What has changed: Lucy VRN2a and VRE2a test form updated (ECP e). Lucy CN2a and VCE2a test form updated (ECP g). Version 4.0 Review Date 04/12/2020 Date 25/11/2015 Author Stephen Tucker Reason for update: Procedure and test forms updated to incorporate minor revisions following feedback from commissioning training course. What has changed: Test access continuity checks added (Section 10). HV insulation testing document reference updated (Section 9, 11and test forms). RN2/RN2c secondary injection values corrected on form ECP a and ECP c. FPI test connections updated on form ECP e and ECP f. Requirement to send copy of the test form to the ART added (Section 21). UK Power Networks 2018 All rights reserved 2 of 16

3 Version 3.0 Review Date 31/05/2018 Date 09/07/2013 Author Stephen Tucker General revision following field staff feedback. Shunt trip tests added. Secondary injection values in test forms a and c amended. Efacec test form h added. Reviewed for G81 website. Version 2.0 Review Date Date 26/03/2009 Author Stephen Tucker General revision and test forms for Lucy SSEa, VCN2a and VCE2a added. Version 1.0 Review Date Date 24/11/2006 Author Stephen Tucker Original. UK Power Networks 2018 All rights reserved 3 of 16

4 Contents 1 Introduction Scope References Abbreviations and Definitions Equipment Switchgear Designations Inspection Functional Checks Transformer Winding Insulation Resistance (Transformer-mounted Units Only) Switchgear Continuity Test High Voltage Insulation Test FPI CT Wiring Tests Protection CT Wiring Tests Time-Limit Fuses (TLF) Primary Injection Test (Free-standing Units Only) Secondary Injection Test (Transformer-mounted Units Only) Shunt Trip Coil and Emergency Trip (if fitted) Final Checks Test Equipment Certification Asset Data and Information UK Power Networks Independent Connection Provider (ICP) UK Power Networks 2018 All rights reserved 4 of 16

5 1 Introduction 1.1 This procedure details the testing and commissioning procedures for groundmounted switchgear, including ring main units and circuit breakers with time-limit fuses and switches, that shall be satisfied before the unit can be accepted as fit for service and energisation. 1.2 This procedure shall be carried out by the Commissioning Engineer or his appointed representative, who shall be an Authorised Person having appropriate training and/or experience. 1.3 This procedure shall be carried out in accordance with the requirements of the UK Power Networks Distribution Safety Rules. 1.4 This procedure shall be carried out having regard to the requirements and recommendations of the manufacturer. If conflict exists between the requirements of the manufacturer and those of UK Power Networks the matter shall be referred to Asset Management (or your UK Power Networks nominated contact). 1.5 This procedure assumes the following: When the switchgear is attached to a distribution transformer, it is not possible to carry out primary injection tests of the protection CTs. In all other applications full testing shall be carried out. The ring switch cable boxes are not connected. The substation earth conductor is connected to the low voltage/high voltage switchgear earth bar. 1.6 The results of all observations, tests, adjustments and all relevant remarks shall be recorded on the appropriate test form. 1.7 Where possible testing shall be carried without disconnecting or disturbing any wiring. UK Power Networks 2018 All rights reserved 5 of 16

6 2 Scope 2.1 This generic procedure applies to 11kV and 6.6kV ring main units and other switchgear with time-limit fuse (TLF) or time fuse-link (TFL) 1 protection which are either transformer-mounted or free-standing as detailed below. Merlin Gerin and Schneider RN2, RN2c and RE2c ring main units. Merlin Gerin and Schneider CN2 and CE2 circuit-breakers. Merlin Gerin and Schneider SE6 switch. Lucy SCRMU, VRN, VRN2, VRE, VRN2a and VRE2a ring main units. Lucy SSEa switch. Lucy VCN2a and VCE2a circuit-breakers. Efacec Fluofix GCT ring main unit. 2.2 The associated test forms, which should be read in conjunction with this procedure, include specific schematic diagrams, connections and trip levels for the items of switchgear listed above. 2.3 This procedure is written with reference to a ring main unit but it can also be applied to individual switches and circuit-breakers. 2.4 Switchgear with protection relays is covered in procedure ECP Air circuit-breakers are covered in procedure ECP The parasitic load trip unit (PLTU) is covered in procedure ECP Distribution transformer is covered in procedure ECP This procedure is intended for use by UK Power Networks field staff, contractors and external connection providers. 1 The term TLF is used throughout this procedure to refer to both TLF and TFL protection. UK Power Networks 2018 All rights reserved 6 of 16

7 3 References 3.1 This procedure should be read in conjunction with the following references: UK Power Networks Distribution Safety Rules. EDS Fuse Ratings at Distribution Substations (Internal document). ECS HV Insulation Testing. ECP Distribution Transformer Commissioning Procedure. ECP Ground Mounted Switchgear with Relays Commissioning Procedure. ECP ACB Commissioning Procedure. ECP PLTU Commissioning Procedure. Schneider Electric Ringmaster Range Installation, Operation and Maintenance Instructions, V5 December 1999 (RN2/RN6). Schneider Electric Ringmaster Range Installation, Operation and Maintenance Instructions, V10 July 2005 (RN2c/RN6c/RE2c). Lucy SCRMU Installation, Operation and Maintenance Manual. Lucy VRN Installation, Operation and Maintenance Manual. Lucy Sabre VRN2 Installation, Operation and Maintenance Manual. Lucy Sabre VRN2a Installation, Operation and Maintenance Manual. Efacec Fluofix GCT Installation, Operation and Maintenance Manual. 3.2 This procedure should be used with the following test forms: ECP a Schneider RN2, RN2c & RE2c. ECP b Schneider SE6. ECP c Schneider CN2 & CE2. ECP d Lucy SCRMU, VRN & VRN2. ECP e Lucy VRN2a & VRE2a. ECP f Lucy SSEa. ECP g Lucy VCN2a & VCE2a. ECP h Efacec Fluofix GCT. 4 Abbreviations and Definitions 4.1 The following abbreviations are used throughout this procedure. Term ART CT FPI RTU TFL TLF VT Definition UK Power Networks Asset Registration Team Current Transformer Fault Passage Indicator Remote Terminal Unit Time Fuse-link (same as TLF) Time-limit Fuse (same as TFL) Voltage Transformer UK Power Networks 2018 All rights reserved 7 of 16

8 5 Equipment 5.1 The following equipment is required to carry out the tests detailed in this procedure: 1kV insulation resistance tester (e.g. Megger). 5kV insulation resistance tester (e.g. Megger). Multimeter (or other continuity checker). Note: Fused leads should not be used for measuring resistance as false readings can be obtained. Ductor tester. Injection test set (suitable for primary/secondary injection). TLF shorting-links. 100A shorting-link or cable. RTU simulator (if required). 6 Switchgear Designations 6.1 The diagram below shows the switch/circuit-breaker and terminal designations referred to throughout this document. Circuit-breaker/ Tee-off (CB) L1 L2 L3 Ring Switch 1 (RSW1) L1 L2 L3 Ring Main Unit L1 L2 L3 Ring Switch 2 (RSW2) 7 Inspection 7.1 Record the substation, switchboard number, if applicable, transformer and current transformer (CT) details on the test form. 7.2 Carry out a visual inspection of the switchgear as detailed below. If possible the Commissioning Engineer shall rectify any non-conformances. However, all equipment defects shall be referred to UKPN Asset Management. Check that the switchgear is undamaged and is correctly mounted and secured to the plinth and to the transformer flange (if applicable). Check that the earth terminal(s) of the switchgear are securely connected directly to the substation earth electrodes. Check that all external surface finishes are undamaged. UK Power Networks 2018 All rights reserved 8 of 16

9 8 Functional Checks 8.1 Carry out the checks detailed below and record the results on the test form. In the event of non-conformance with the functional expectation the result shall be recorded on the test form and the equipment shall not be accepted into service. Check the opening and closing of door including the supporting struts if fitted. Check that the pointer of the SF 6 gas pressure indicator is in the healthy sector tap the site glass to overcome any stiction. 8.2 Check for correct operation of the circuit-breaker, ring switches, earth switches, test access covers and associated interlocks/switch position indicators are in accordance with the manufacturer's instructions. Open and close switches. Earth switches cannot be operated when service selected. Switch/circuit-breaker cannot be operated when earth selected. Open and close earth switches. Test access cannot be opened when switch/circuit-breaker in On and Off position. Test access can be opened when earth switch closed. Switch/circuit-breaker cannot be operated when test access open. 8.3 Carry out a functional check of each motorised actuator using an RTU simulator (LPN Remsdaq RTU only). 9 Transformer Winding Insulation Resistance (Transformer-mounted Units Only) 9.1 Carry out the transformer wining insulation test as detailed below using the test voltages from ECS and record the results on the test form. 9.2 Measure HV winding insulation resistance as follows: Connect the LV windings to earth via the neutral link and substation earth. Connect an insulation resistance tester between the transformer HV winding and earth. The test may be carried out from terminals L1 or L2 or L3 on either ring switch with ring switch closed and the circuit-breaker closed. The insulation resistance should be greater than 100M. 9.3 Measure LV winding insulation resistance as follows: If the transformer has a transformer-mounted LV fuse-cabinet it will be necessary to remove the neutral-earth link. Connect the HV windings to the substation earth via the circuit-breaker earthing switch. Connect an insulation resistance tester between the transformer LV winding and earth. The test may be carried out from terminals L1 or L2 or L3. The insulation resistance should be greater than 100M. Replace the neutral-earth link if removed above. 9.4 The tests for free-standing transformers are covered by the transformer commissioning procedure (ECP ). UK Power Networks 2018 All rights reserved 9 of 16

10 10 Switchgear Continuity Test 10.1 Carry out a switchgear continuity test using a multi-meter or a Ductor tester (for extensible switchgear with site assembled busbars) as detailed below and record the results on the test form. Note: Ensure the cable box connection studs are tight otherwise high resistance readings may be encountered On transformer-mounted units: Close both ring switches and open the circuit-breaker. Measure the continuity between each phase on ring switch 1 to each on phase ring switch 2. Close ring switch 1, open ring switch 2 and close the circuit-breaker. Measure the continuity between L1 to L2 and L2 to L3 on ring switch On free-standing units: Close both ring switches and close the circuit-breaker. Measure the continuity between each phase on ring switch 1 to each phase on ring switch 2 and each phase on the circuit-breaker Close ring switch 1 to earth and open ring switch 2. Measure the continuity from phase L1, L2 and L3 on ring switch 1 to earth Close ring switch 2 to earth and open ring switch 1. Measure the continuity from phase L1, L2 and L3 on ring switch 2 to earth. 11 High Voltage Insulation Test 11.1 Carry out high voltage insulation test as detailed below using the test voltages from ECS and record the results on the test form Close both ring switches and open the circuit-breaker for transformer-mounted units (close the circuit-breaker for free-standing units). Measure the insulation between each phase and earth with the other two phases earthed Open ring switch 1, close ring switch 2 and open the circuit-breaker for transformermounted units (close the circuit-breaker for free-standing units). Measure the insulation between L1, L2, L3 on ring switch 1 and earth with L1, L2, L3 on ring switch 2 earthed (L1, L2, L3 on the circuit-breaker should also be earthed for free-standing units) Close ring switch 1, open ring switch 2 and open the circuit-breaker. Measure the insulation between L1, L2, L3 on ring switch 1 and earth with L1, L2, L3 on ring switch 2 earthed (L1, L2, L3 on the circuit-breaker should also be earthed for free-standing units). UK Power Networks 2018 All rights reserved 10 of 16

11 12 FPI CT Wiring Tests 12.1 Carry out the FPI wiring tests as detailed below and record the results on the test form Disconnect the RTU/FPI if fitted. Note: This will ensure the RTU/FPI is not damaged during insulation testing and will ensure that the RTU/FPI wiring is eliminated when measuring CT loop continuity Measure the CT insulation resistance as follows: If applicable 2 remove the CT shorting-link. Temporarily disconnect the CT wiring, earth link or CT star point as detailed on the relevant test form. Measure the insulation resistance to earth of the CTs using a 1kV insulation resistance tester. The insulation resistance should be greater than 100M. Reconnect any wiring or links removed above on completion of the test Measure the CT loop continuity as follows: If applicable 2 remove the CT shorting-link. At the CT wiring terminal block identify the terminals for L1 CT and measure the resistance of the CT. The resistance should be in the region of 1-2. Repeat for L2 and L3 CT circuits Repeat for all switches with FPI CTs Reconnect FPI/RTU if applicable. 2 Some modern switchgear (e.g. Lucy VRN2a) uses an electronic shorting-block in place of a physical link that automatically shorts the CTs when the output wiring is disconnected. UK Power Networks 2018 All rights reserved 11 of 16

12 13 Protection CT Wiring Tests 13.1 Carry out the protection CT wiring tests as detailed below and record the results on the test form Measure the CT circuit insulation resistance as follows: Temporarily remove the CT wiring earth link. Measure the insulation resistance to earth of the CTs using a 1kV insulation resistance tester. The insulation resistance should be greater than 100M. Replace the earth link on completion of the test Measure the CT loop continuity using the method below. Remove each TLF, if fitted. Temporarily remove the CT ratio shorting-link. Measure the continuity of the L1 CT, trip coil and wiring from the CT ratio terminals. The resistance should be in the region of depending on the components in the circuit being measured. Replace the CT ratio shorting-link. Repeat for L2 and L3 CT circuits. Figure 13-1 Schneider RN2c CT Ratio Selection Figure 13-2 Lucy VRN2a CT Ratio Selection 14 Time-Limit Fuses (TLF) 14.1 Select the appropriate CT ratio and TLF rating in accordance with EDS Select the required CT ratio by moving the link to the required ratio (see Figure 13-1 and Figure 13-2) referring to the manufacturer's manual for more detailed instructions. Note: switchgear is generally supplied with the 100/5 ratio selected If fitted, set the CT ratio label to match the selected ratio and record the CT ratio on the test form Select two TLFs with the correct rating and check them for continuity. The TLFs should be fitted on completion of the testing. Note: TLFs are normally only fitted in the overcurrent circuits and not the earth fault circuit Record the TLF rating on the test form. UK Power Networks 2018 All rights reserved 12 of 16

13 15 Primary Injection Test (Free-standing Units Only) 15.1 For free-standing units carry out an earth fault and overcurrent release test on each phase of the circuit-breaker as described below and record the results on the test form. Note: The circuit-breaker trip coils are designed to operate in response to the instantaneous application of a current within the specified range. Therefore they may not operate successfully when the current is gradually applied, as in the first part of these tests. This shall not be regarded as a non-conformance, and the procedure shall be completed by instantaneous application of the trip current. Expected test values for CT ratio 50/5 or 100/5 should be <35A 15.2 Carry out the earth fault release test as follows: Remove the TLFs if fitted. Connect a shorting-link across the terminals of each pair of TLF connection studs. Close ring switch 1, open ring switch 2 and close the circuit-breaker. Connect the injection test set between L1 on ring switch 1 and L1 on the circuitbreaker. Slowly increase the primary injection current from zero until the circuit-breaker trips. If the circuit-breaker trips at any value of current within the specified range, record the value of the injection current. If the circuit-breaker does not trip within the specified range, repeat the test with the current preset to the maximum permissible value and apply instantaneously by switching the injection test set OFF and then ON. Repeat the test for L2 and L3. Remove shorting-link from TLF connection studs Carry out the overcurrent release test as follows: Close ring switch 1, open ring switch 2 and close the circuit-breaker. Connect a shorting-link across the L1, L2, L3 on the circuit-breaker. Connect the injection test set between L1 and L2 on ring switch 1. Slowly increase the primary injection current from zero until the circuit-breaker trips. If the circuit-breaker trips at any value of current within the specified range, record the value of the injection current. If the circuit-breaker does not trip within the specified range, repeat the test with the current preset to the maximum permissible value and apply instantaneously by switching the injection test set OFF and then ON. Repeat the test with the test set connected between L2 and L3 on the circuit-breaker. Remove the shorting-link from the circuit-breaker. Replace the TLFs. UK Power Networks 2018 All rights reserved 13 of 16

14 16 Secondary Injection Test (Transformer-mounted Units Only) 16.1 For transformer-mounted units carry out an earth fault and overcurrent release test on each phase of the circuit-breaker as described below and record the results on the test form. Note: The circuit-breaker trip coils are designed to operate in response to the instantaneous application of a current within the specified range. Therefore they may not operate successfully when the current is gradually applied, as in the first part of these tests. This shall not be regarded as a non-conformance, and the procedure shall be completed by instantaneous application of the trip current. Expected test values for the following CT ratio s: 50/5 = <3.5A, 100/5 = <7.0A 16.2 Carry out the earth fault release test as follows: Remove the TLFs if fitted. Connect a shorting-link across the terminals of each pair of OC TLF connection studs (L1 and L3). Close the circuit-breaker. Connect the injection test set across the earth fault trip coil i.e. between L2 phase CT and the CT earth link. Slowly increase the secondary injection current from zero to the maximum permissible value. If the circuit-breaker trips at any value of current within the specified range, record the value of the injection current. If the circuit-breaker does not trip within the specified range, repeat the test with the current preset to the maximum permissible value and apply instantaneously by switching the injection test set OFF and then ON. Remove shorting-link from TLF connection studs Carry out the overcurrent release test as follows: Close the circuit-breaker. Connect the injection test set across the L1 phase overcurrent trip coil i.e. between the L1 phase CT and the L2 phase CT. Slowly increase the secondary injection current from zero to the maximum permissible value. If the circuit-breaker trips at any value of current within the specified range, note the value of the injection current. If the circuit-breaker does not trip within the specified range, repeat the test with the current preset to the maximum permissible value and apply instantaneously by switching the injection test set OFF and then ON. Repeat the test with the injection test set connected across the L3 phase overcurrent trip coil i.e. between the L2 phase CT and the L3 phase CT. Replace the TLFs. UK Power Networks 2018 All rights reserved 14 of 16

15 17 Shunt Trip Coil and Emergency Trip (if fitted) 17.1 Check that the correct voltage has been selected on the shunt trip coil Locate the shunt trip coil terminals Using an appropriate test set apply either 70% (dc) or 85% (ac) of the rated voltage to the shunt trip coil and the circuit-breaker should trip Close the circuit-breaker Using an appropriate test set apply 100% of the rated voltage to the shunt trip coil and the circuit-breaker should trip Check that the emergency trip button correctly trips the circuit-breaker. 18 Final Checks 18.1 On completion of the commissioning tests check the following: Correct CT ratio selected. Correct TLF rating selected and fitted. All links are replaced and secure. Check FPI CT shorting-link(s) 3 are replaced if CTs are not used or not connected to FPI or RTU. Reconnect umbilical cable to RTU (if fitted). 19 Test Equipment 19.1 Record the make, type, serial or asset number and calibration date of all test equipment used during commissioning on the test form. 20 Certification 20.1 When all the tests have been satisfactorily completed, sign and date the test form. The test form should be left on-site in a plastic wallet and in a secure location. 21 Asset Data and Information 21.1 UK Power Networks Send a copy of the completed test form and the asset data form to the Asset Registration Team (ART) via the appropriate mailbox below. ART.EPN@ukpowernetworks.co.uk. ART.LPN@ukpowernetworks.co.uk. ART.SPN@ukpowernetworks.co.uk. 3 Some modern switchgear (e.g. Lucy VRN2a) uses an electronic shorting-block in place of a physical link that automatically shorts the CTs when the output wiring is disconnected. UK Power Networks 2018 All rights reserved 15 of 16

16 21.2 Independent Connection Provider (ICP) Send a copy of the completed test form and the asset data form to the Competitionin-Connections Delivery Project Manager. UK Power Networks 2018 All rights reserved 16 of 16

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE ENGINEERING COMMISSIONING PROCEDURE ECP 11-0512 GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE Network(s): Summary: EPN, LPN, SPN This procedure details the testing and commissioning

More information

ECP DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE

ECP DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE Document Number: ECP 11-0506 ENGINEERING COMMISSIONING PROCEDURE ECP 11-0506 DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE Network(s): Summary: EPN, LPN, SPN This procedure details the testing and commissioning

More information

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: ECP 11-0515 ENGINEERING COMMISSIONING PROCEDURE ECP 11-0515 HV METERING EQUIPMENT COMMISSIONING PROCEDURE

More information

ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE

ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0507 COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE EPN, LPN, SPN This procedure details the testing and commissioning procedures for

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: All ENGINEERING COMMISSIONING PROCEDURE ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing of new and

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE EPN, LPN, SPN ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing

More information

EDS LV ELECTRICAL SERVICE DRAWINGS

EDS LV ELECTRICAL SERVICE DRAWINGS Document Number: EDS 08-2110 Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-2110 LV ELECTRICAL SERVICE DRAWINGS EPN, LPN, SPN This standard details the drawings for service positions and connection

More information

EI HIGH VOLTAGE INSULATION TESTING POLICY

EI HIGH VOLTAGE INSULATION TESTING POLICY Network(s): Summary: ENGINEERING INSTRUCTION EI 09-0001 HIGH VOLTAGE INSULATION TESTING POLICY EPN, LPN, SPN This engineering instruction details the policy for the on-site insulation testing of new and

More information

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS ENGINEERING DESIGN STANDARD EDS 08-2109 LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS Network(s): Summary: EPN, LPN, SPN This standard provides guidance on the installation of

More information

EDS LV WAVEFORM MAINS CABLE RATINGS

EDS LV WAVEFORM MAINS CABLE RATINGS Document Number: EDS 02-0033 Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 02-0033 LV WAVEFORM MAINS CABLE RATINGS EPN, LPN, SPN This standard details the technical and practical information required

More information

UK Power Networks OPERATIONAL BULLETIN

UK Power Networks OPERATIONAL BULLETIN Document No: HSS 406 OB 160 Issue Date: 10 July 2018 Type: Operational Safety Subject: Changes to DSR procedures 2018/1 Applicable Areas: All Applicable Job Roles: All DSR holders Issued By: Dudley Sparks

More information

EDS GRID AND PRIMARY SUBSTATION CIVIL DESIGN STANDARDS

EDS GRID AND PRIMARY SUBSTATION CIVIL DESIGN STANDARDS Document Number: EDS 07-0105 ENGINEERING DESIGN STANDARD EDS 07-0105 GRID AND PRIMARY SUBSTATION CIVIL DESIGN STANDARDS Network(s): Summary: EPN, LPN, SPN This design standard details the current civil

More information

EDS FAULT LEVELS

EDS FAULT LEVELS Document Number: EDS 08-1110 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-1110 FAULT LEVELS This standard provides guidance on the calculation, application and availability of

More information

Electrical Switchgear & Power Transformer Testing. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

Electrical Switchgear & Power Transformer Testing. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E Electrical Switchgear & Power Transformer Testing H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae ictd@ictd.ae Course Introduction: This will provide you with practical knowledge

More information

Substation Preventive Maintenance

Substation Preventive Maintenance Substation Preventive Maintenance PROVINCIAL ELECTRICITY AUTHORITY 1 Presentation Contents 1) A kind of substation 2) Electrical equipment details of AIS substation 3) Electrical equipment details of GIS

More information

Greenlining and Bluelining of Ergon Energy Substation Drawings

Greenlining and Bluelining of Ergon Energy Substation Drawings Greenlining and Bluelining of Ergon Energy Table of Contents Purpose and Scope... 1 Responsibilities... 1 Definitions, Abbreviations and Acronyms... 1 References... 1 General... 1 Requirements... 3 Testing

More information

Sabre. Ring Main Unit

Sabre. Ring Main Unit Sabre Ring Main Unit Sabre catalogue Table of contents Introduction to Lucy Electric 3 Product panorama 4 Introduction to Sabre 5 Installation and operating conditions 6 Safety features 6 Application example

More information

Advanced Test Equipment Rentals ATEC (2832) CP RC. Resonance circuit for GIS testing

Advanced Test Equipment Rentals ATEC (2832) CP RC. Resonance circuit for GIS testing Established 1981 Advanced Test Equipment Rentals www.atecorp.com 800-404-ATEC (2832) CP RC Resonance circuit for GIS testing A new approach to testing gas-insulated switchgear Testing gas-insulated switchgear

More information

Module Title: Electrical Installation II Laboratory Sheet:

Module Title: Electrical Installation II Laboratory Sheet: Vocational Training Council Hong Kong Institute of Vocational Education Department of Engineering Module Title: Electrical Installation II Laboratory Sheet: Student name: Course / Year: Subject: Date:

More information

ECP TESTING AND COMMISSIONING GUIDANCE NOTES

ECP TESTING AND COMMISSIONING GUIDANCE NOTES Document Number: ECP 11-0003 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0003 TESTING AND COMMISSIONING GUIDANCE NOTES EPN, LPN, SPN This document provides guidelines and preferred

More information

Protection of Electrical Networks. Christophe Prévé

Protection of Electrical Networks. Christophe Prévé Protection of Electrical Networks Christophe Prévé This Page Intentionally Left Blank Protection of Electrical Networks This Page Intentionally Left Blank Protection of Electrical Networks Christophe Prévé

More information

SUBJECT HEADING: Switching Programmes ISSUE: 18

SUBJECT HEADING: Switching Programmes ISSUE: 18 SUBJECT: Switchgear/Switching PROCEDURE: S04 SUBJECT HEADING: Switching Programmes ISSUE: 18 DATE: Apr 2017 1. INTRODUCTION 1.1 A written programme of switching operations shall be prepared. This programme

More information

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS 101135-ELE-CMOS-E-2001 Electrical Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and has over 14 years hands-on experience, including 13 years working in operation, maintenance, construction

More information

EDS KV TRIPLEX CABLE RATING

EDS KV TRIPLEX CABLE RATING Document Number: EDS 02-0027 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 02-0027 11KV TRIPLEX CABLE RATING This engineering design standard provides the cable ratings and important

More information

NEO TELE-TRONIX PVT. LTD. 6/7 Bijoygarh, Kolkata , Tel : ; Fax :

NEO TELE-TRONIX PVT. LTD. 6/7 Bijoygarh, Kolkata , Tel : ; Fax : NEO TELE-TRONIX PVT. LTD. 6/7 Bijoygarh, Kolkata - 700 032, Tel : 033 2477 3126; Fax : 033 2477 2403 www.ntplindia.com SPECIFICATION NTPL MAKE MICRO-CONTROLLER BASED AUTOMATIC 50KV/10A AC HIGH VOLTAGE

More information

EDS KV SINGLE CORE XLPE CABLES

EDS KV SINGLE CORE XLPE CABLES THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS 02-0034 ENGINEERING DESIGN STANDARD EDS 02-0034 33KV SINGLE CORE XLPE CABLES Network(s): EPN, LPN,

More information

Connection of Embedded Generating Plant up to 5MW

Connection of Embedded Generating Plant up to 5MW Engineering Recommendation No.3 of the Electricity Distribution Code Connection of Embedded Generating Plant up to 5MW Version 1.0 30th November 2005 Prepared by: Al Ain Distribution Company, Abu Dhabi

More information

SERVICING & METERING SERVICING AND METERING SECTION 5 SEC5:

SERVICING & METERING SERVICING AND METERING SECTION 5 SEC5: SECTION SERVICING AND METERING SECTION 1. SERVICING.... NST IMPEDANCE TESTING.... METERING... General Requirements.... CT METERING... 8 CT Metering General Requirements... 8 Existing Installation Alterations

More information

VI 3 - i TABLE OF CONTENTS

VI 3 - i TABLE OF CONTENTS VI 3 - i TABLE OF CONTENTS 3 PROJECT SPECIFIC DATA... 1 3.1 DEFINITIONS... 1 3.1.1 Design Data, High and Medium Voltage... 1 3.1.2 Design Data, Low Voltage Equipment... 2 3.1.3 Phase Relationship... 3

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 21 25 Sep $3,750 Dubai, UAE In any of the 5 star

More information

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES COMPANY OVERVIEW EPS is a recognised company specialising in Electrical, Instrumentation, Structural, Mechanical and

More information

CP CU1. Coupling unit for line and ground testing

CP CU1. Coupling unit for line and ground testing CP CU1 Coupling unit for line and ground testing Line and ground test system CPC 100 The CPC 100 is a multifunctional test set for primary assets. When combined with the CP CU1 it covers the following

More information

Protection and control. Sepam range Sepam 100 LA Self-powering protection. Merlin Gerin Square D Telemecanique

Protection and control. Sepam range Sepam 100 LA Self-powering protection. Merlin Gerin Square D Telemecanique Protection and control Sepam range Sepam 0 LA Self-powering protection Merlin Gerin Square D Telemecanique presentation contents page presentation protection functional and connection schemes other connection

More information

Company Directive STANDARD TECHNIQUE: TP14C. Distribution Business Provided Metering Facilities

Company Directive STANDARD TECHNIQUE: TP14C. Distribution Business Provided Metering Facilities Company Directive STANDARD TECHNIQUE: TP14C Distribution Business Provided Metering Facilities Summary This standard technique document details the metering facilities to be provided by the distribution

More information

Company Directive STANDARD TECHNIQUE: TP6F/1. Power Measurement Conventions

Company Directive STANDARD TECHNIQUE: TP6F/1. Power Measurement Conventions Company Directive STANDARD TECHNIQUE: TP6F/1 Power Measurement Conventions Summary This document specifies the conventions that are used for the direction of Power Flow within Western Power Distribution

More information

Licensed Electricians Practical Assessment (LEP)

Licensed Electricians Practical Assessment (LEP) Licensed Electricians Practical Assessment (LEP) Surname: Date: Given Names: Time: Assessment Time (includes 10 minutes reading time): At the end of this time you will be asked to stop. 4 hours Have you

More information

TN, TT & IT Earthing Arrangements

TN, TT & IT Earthing Arrangements TN, TT & IT Earthing Arrangements In IT and TN-C networks, residual current devices are far less likely to detect an insulation fault. In a TN-C system, they would also be very vulnerable to unwanted triggering

More information

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS. IR Values are to be read on the megger by meggering the Power transformer

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS. IR Values are to be read on the megger by meggering the Power transformer PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS TESTS ON TRANSFORMERS 1. IR Values This is measured to measure the Insulation Resistance of the whole transformer. a) For 33/11 KV Power Transformer

More information

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer PART 1: GENERAL 1.01 Transformer A. This section includes liquid filled, pad mounted distribution transformers with primary voltage of 12kV or 4.16kV (The University will determine primary voltage), with

More information

CSEE UM71 AF Jointless Track Circuits Set-up, Test and Certification

CSEE UM71 AF Jointless Track Circuits Set-up, Test and Certification Discipline: Engineering (Signalling) Category: Standard CSEE UM71 AF Jointless Track Circuits Set-up, Test and Certification SES 06 Applicability New South Wales CRIA (NSW CRN) Primary Source RIC Standard

More information

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE The following is PG&E's procedure for pre-energization inspections. For PG&E to provide the Load

More information

Licensed Electricians Practical Assessment (LEP)

Licensed Electricians Practical Assessment (LEP) Licensed Electricians Practical Assessment (LEP) Surname: Given Names: Date: Time: Location: Assessment Time (includes reading and preparation time): At the end of this time you will be asked to stop.

More information

TECHNICAL DESCRIPTION TD-77A/3 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES

TECHNICAL DESCRIPTION TD-77A/3 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES INDEPENDENT POWER TRANSMISSION OPERATOR S.A. TNPRD/ SUBSTATION SPECIFICATION & EQUIPMENT SECTION October 2014 TECHNICAL DESCRIPTION 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES I. SCOPE This

More information

Specialists in HV and MV test and diagnostics. Testing in Substations

Specialists in HV and MV test and diagnostics. Testing in Substations Specialists in HV and MV test and diagnostics Testing in Substations Testing in Substations Testing in Substations At 4fores we specialize in the diagnosis and measurement of all types of existing technologies

More information

N. TEST TEST DESCRIPTION

N. TEST TEST DESCRIPTION Multi function system for testing substation equipment such as: current, voltage and power transformers, over-current protection relays, energy meters and transducers Primary injection testing capabilities

More information

ADVANCED CIRCUIT BREAKERS OPERATION AND MAINTENANCE SECTOR / ENGINEERING TECHNICAL & CERTIFICATE OF ATTENDANCE TRAINING COURSE

ADVANCED CIRCUIT BREAKERS OPERATION AND MAINTENANCE SECTOR / ENGINEERING TECHNICAL & CERTIFICATE OF ATTENDANCE TRAINING COURSE ADVANCED CIRCUIT BREAKERS OPERATION AND MAINTENANCE SECTOR / ENGINEERING TECHNICAL & CERTIFICATE OF ATTENDANCE TRAINING COURSE Circuit Breakers Play An Important Role In The Safe Distribution Of Electrical

More information

NSP/ 007 / 006 Guidance on Substation Design: Transformer Transport, Delivery and Installation

NSP/ 007 / 006 Guidance on Substation Design: Transformer Transport, Delivery and Installation Version:- 1.0 of Issue:- March 2016 Page 1 of 7 NSP/ 007 / 006 Guidance on Substation Design: Transformer Transport, Delivery and Installation 1. Purpose The purpose of this document is to provide guidance

More information

SYNCHRONISING AND VOLTAGE SELECTION

SYNCHRONISING AND VOLTAGE SELECTION SYNCHRONISING AND VOLTAGE SELECTION This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for any

More information

WB&S FS2500 AF Jointless Track Circuits Set-Up, Test and Certification

WB&S FS2500 AF Jointless Track Circuits Set-Up, Test and Certification Discipline: Engineering (Signalling) Category: Standard WB&S FS2500 AF Jointless Track Circuits Set-Up, Test and Certification SES 07 Applicability New South Wales CRIA (NSW CRN) Primary Source RIC Standard

More information

ELECTRIC NETWORK DESIGN APPROVAL APPLICATION

ELECTRIC NETWORK DESIGN APPROVAL APPLICATION Please complete all sections of the application form and return to newconnections@ukpowerdistribution.co.uk Section 1 Site Details UKPD Reference Number: Energisation Date: Site Name/Address/Postcode:

More information

TRAX Transformer and Substation Test System

TRAX Transformer and Substation Test System TRAX Replaces need for multiple test sets Saves time by eliminating need for multiple instruments learning User-friendly interface reduces training and testing time Portable and compact system components

More information

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application General Application Information Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application Hydro One Remote Communities Inc. Lori.Rice@hydroone.com 1-807-474-2828 This Application

More information

TRAX Transformer and Substation Test System

TRAX Transformer and Substation Test System Replaces need for multiple test sets Saves time by eliminating need for multiple instruments learning User-friendly interface reduces training and testing time Portable and compact system components for

More information

INTEGRATED TRANSMISSION PLAN Glossary

INTEGRATED TRANSMISSION PLAN Glossary INTEGRATED TRANSMISSION PLAN Glossary SEPTEMBER 2017 GLOSSARY Term AC ACM asset health and asset health index (AHI) automatic underfrequency load shedding (AUFLS) availability bus cable capacitor bank

More information

KENYA ELECTRICITY GENERATING COMPANY LTD

KENYA ELECTRICITY GENERATING COMPANY LTD KENYA ELECTRICITY GENERATING COMPANY LTD TENDER No. KGN-HYD-014-2016 TENDER FOR REHABILITATION OF PROTECTION EQUIPMENT FOR MASINGA HYDRO POWER STATION 20/06/2016 ADDENDUM NO. 1 In accordance with the tender

More information

Field Instruction Switching Activities. Purpose. Scope. Objective. Safety

Field Instruction Switching Activities. Purpose. Scope. Objective. Safety 8.22 Switching Activities Purpose This instruction provides a safe system for switching on Horizon Powers Low Voltage, High Voltage and or Transmission electrical apparatus/network, where switching operations

More information

N. TEST TEST DESCRIPTION

N. TEST TEST DESCRIPTION Multi function system for testing substation equipment such as: current, voltage and power transformers, all type of protection relays, energy meters and transducers Primary injection testing capabilities

More information

Busbars and lines are important elements

Busbars and lines are important elements CHAPTER CHAPTER 23 Protection of Busbars and Lines 23.1 Busbar Protection 23.2 Protection of Lines 23.3 Time-Graded Overcurrent Protection 23.4 Differential Pilot-Wire Protection 23.5 Distance Protection

More information

Types CDG 11 and CDG 16 Inverse Time Overcurrent and Earth Fault Relay

Types CDG 11 and CDG 16 Inverse Time Overcurrent and Earth Fault Relay Types CDG 11 and CDG 16 Inverse Time Overcurrent and Earth Fault Relay Types CDG 11 and CDG 16 Inverse Time Overcurrent and Earth Fault Relay Relay withdrawn from case Application The type CDG 11 relay

More information

Catalogue 1SFC en, Edition 3 November 2003 Supersedes Catalogue 1SFC en, Edition 2 November Arc Guard System TVOC

Catalogue 1SFC en, Edition 3 November 2003 Supersedes Catalogue 1SFC en, Edition 2 November Arc Guard System TVOC Catalogue 1SFC 266006-en, Edition 3 November 2003 Supersedes Catalogue 1SFC 266006-en, Edition 2 November 2000 Arc Guard System TVOC System units The two units of the are used as below: Approvals 1. with

More information

FAQ ON EARTHING STANDARDS 16/08/2018

FAQ ON EARTHING STANDARDS 16/08/2018 FAQ ON EARTHING STANDARDS 16/08/2018 This document has been updated to include changes made to substation earthing layouts that have been made necessary due to copper theft. The main changes to be aware

More information

Earthing, HV Switching and Associated Operational Equipment. Approval: Chief Operating Officer

Earthing, HV Switching and Associated Operational Equipment. Approval: Chief Operating Officer ACCESS PRACTICE AP 24 Earthing, HV Switching and Associated Operational Equipment Process Authority: Manager Operations Improvement Approval: Chief Operating Officer Version Date: 27/08/2013 Revision:

More information

Equipment Description Quantity as per drawings Actual quantity

Equipment Description Quantity as per drawings Actual quantity NOTE: SAFETY: Tests must be carried out after the installation, alteration or repair and before putting back to service. At all times maintain suitable clearance to all other electrical equipment and verify

More information

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY 9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor

More information

Transformer Trainer. Electrical Power Systems PSL20. Learning Outcomes. Key Features. Key Specifications

Transformer Trainer. Electrical Power Systems PSL20. Learning Outcomes. Key Features. Key Specifications Electrical Power Systems PSL2 Investigates the principles and operating characteristics of single-phase and three-phase power and distribution transformers Key Features Educational transformers with fully

More information

The Advantages and Application of Three Winding Transformers

The Advantages and Application of Three Winding Transformers The Advantages and Application of Three Winding Transformers MSc, CEng, FIEE, FIMechE, FIPENZ Principal, Sinclair Knight Merz Abstract Although seldom used in Australia and New Zealand, three winding transformers

More information

Distribution transformers Part 2 Ground mounted transformers not closecoupled

Distribution transformers Part 2 Ground mounted transformers not closecoupled PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Technical Specification 35-1 Distribution transformers Part 2 Ground mounted transformers not closecoupled www.energynetworks.org PUBLISHING

More information

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION and Guidance NSI 26 RAILWAY CONNECTION CIRCUITS Copyright National Grid plc 2016, all rights reserved. No part of this publication

More information

TABLE OF CONTENT

TABLE OF CONTENT Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES

More information

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations C&G 2395-01 Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations Phase rotation and verification of voltage drop 1 Outcomes of this Session describe how to assess

More information

UBC Technical Guidelines Section Edition Medium-Voltage Transformers Page 1 of 5

UBC Technical Guidelines Section Edition Medium-Voltage Transformers Page 1 of 5 Page 1 of 5 1.0 GENERAL 1.1 Coordination Requirements.1 UBC Energy & Water Services.2 UBC Building Operations 1.2 Description.1 UBC requirements for Substation Transformers. 2.0 MATERIAL AND DESIGN REQUIREMENTS

More information

CUSTOMER SUPPLIED HIGH VOLTAGE METERING UNIT SPECIFICATION FOR 11, 22 & 33 kv

CUSTOMER SUPPLIED HIGH VOLTAGE METERING UNIT SPECIFICATION FOR 11, 22 & 33 kv CUSTOMER SUPPLIED HIGH VOLTAGE METERING UNIT SPECIFICATION FOR 11, 22 & 33 kv June 2016 Issue 1 1. INTRODUCTION Introduction of contestability and the ability of all major customers to become contestable

More information

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER Engineering Specification TECHNICAL SPECIFICATION FOR AN ESSENTIAL Version: 3 Issued: 14 October 2016 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering - Electrical PRINTOUT MAY NOT

More information

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS Juan Manuel Gers, PhD Protection coordination principles Relay coordination is the process of selecting settings that will assure that the relays

More information

Chapter 7 Conclusion 7.1 General

Chapter 7 Conclusion 7.1 General Chapter 7 7.1 General The mechanical integrity of a transformer winding is challenged by several mechanisms. Many dielectric failures in transformers are direct results of reduced mechanical strength due

More information

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 Prepared by System Planning Division Transmission Planning Department PJM 2016 Table of Contents Table of Contents Approval...6

More information

Standard Prices for Generators 2010

Standard Prices for Generators 2010 Standard Prices for Generators 2010 Distribution System Operator ESB Networks Page 1 of 13 CONTENTS 1.0 Background...3 2.0 Standard Pricing Approach...3 Schedule of Charges for generators excluding VAT...6

More information

TRAX Transformer and Substation Test System

TRAX Transformer and Substation Test System TRAX Replaces need for multiple test sets Saves time by eliminating need for multiple instruments learning User-friendly interface reduces training and testing time Portable and compact system components

More information

ML TI21 AF Jointless Track Circuits Set Up, Test and Certification

ML TI21 AF Jointless Track Circuits Set Up, Test and Certification Discipline: Engineering (Signalling) Category: Standard ML TI21 AF Jointless Track Circuits Set Up, Test and Certification SES 08 Applicability New South Wales CRIA (NSW CRN) Primary Source RIC Standard

More information

Grounding Recommendations for On Site Power Systems

Grounding Recommendations for On Site Power Systems Grounding Recommendations for On Site Power Systems Revised: February 23, 2017 2017 Cummins All Rights Reserved Course Objectives Participants will be able to: Explain grounding best practices and code

More information

Hamdy Faramawy Senior Application Specialist ABB Sweden

Hamdy Faramawy Senior Application Specialist ABB Sweden Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy

More information

This document covers common questions concerning the design of an effectively grounded system.

This document covers common questions concerning the design of an effectively grounded system. This document covers common questions concerning the design of an effectively grounded system. To prevent against temporary overvoltage conditions when a line-to-ground fault occurs on the power grid.

More information

Company Directive STANDARD TECHNIQUE: SD5F. Relating to connecting multiple small low voltage connections with limited network analysis

Company Directive STANDARD TECHNIQUE: SD5F. Relating to connecting multiple small low voltage connections with limited network analysis Company Directive STANDARD TECHNIQUE: SD5F Relating to connecting multiple small low voltage connections with limited network analysis Policy Summary This document specifies the procedure for connecting

More information

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION! PREFACE This publication has been prepared as a guide for Architectural and Engineering (A&E) firms in the preparation of documents for the design and construction of new structures and the remodeling

More information

7. INSPECTION AND TEST PROCEDURES

7. INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies A. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. 2. Inspect physical and mechanical condition. 3. Inspect

More information

INDEX. Micro-ohmmeter MH-10 Page 3. MI (5, 10, 15, 20 kv) Page 4 Mega-ohmmeter MD (5 kv) Page 4

INDEX. Micro-ohmmeter MH-10 Page 3. MI (5, 10, 15, 20 kv) Page 4 Mega-ohmmeter MD (5 kv) Page 4 Micro-ohmmeter MH-10 Page 3 MI (5, 10, 15, 20 kv) Page 4 Mega-ohmmeter MD (5 kv) Page 4 Earth resistance meter TL-5 Page 5 Indirect earth contact simulator MPC (5, 20, 50 A) Page 6 Trip time tester CR

More information

SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY SPEC WRITER NOTE: Delete between // -- // if not applicable to project. Also, delete any other item or

More information

Testing of 400 kv GIS

Testing of 400 kv GIS Testing of 400 kv GIS Robert le Roux, Dermot Dorgan, Brian Perry ESB International - Ireland Paper 028 1 Introduction The 400 kv transmission is designed for critical periods of low loading. Due to critical

More information

PROTECTION of electricity distribution networks

PROTECTION of electricity distribution networks PROTECTION of electricity distribution networks Juan M. Gers and Edward J. Holmes The Institution of Electrical Engineers Contents Preface and acknowledgments x 1 Introduction 1 1.1 Basic principles of

More information

E N G I N E E R I N G M A N U A L

E N G I N E E R I N G M A N U A L 1 1 1.0 PURPOSE The purpose of this document is to define policy and provide engineering guidelines for the AP operating companies (Monongahela Power Company, The Potomac Edison Company, and West Penn

More information

PC IEEE Guide for Grounding of Instrument Transformer Secondary Circuits and Cases

PC IEEE Guide for Grounding of Instrument Transformer Secondary Circuits and Cases PC57.13.3 IEEE Guide for Grounding of Instrument Transformer Secondary Circuits and Cases OUTLINE Scope References Need for grounding; Warning Definition of Instrument transformers Grounding secondary

More information

Table of Contents. Introduction... 1

Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...

More information

NOTE: This paper relates to a closed book exam & therefore candidates should attempt this exam paper with no study-notes or text books.

NOTE: This paper relates to a closed book exam & therefore candidates should attempt this exam paper with no study-notes or text books. City & Guilds Fundamental Inspection & Testing 30 Question Test Sheet (2392-10 Paper No1.) NOTE: This paper relates to a closed book exam & therefore candidates should attempt this exam paper with no study-notes

More information

INSTALLATION AND MAINTENANCE MANUAL FOR GROUND MONITOR GM-250 COPYRIGHT 1983 AMERICAN MINE RESEARCH, INC.

INSTALLATION AND MAINTENANCE MANUAL FOR GROUND MONITOR GM-250 COPYRIGHT 1983 AMERICAN MINE RESEARCH, INC. INSTALLATION AND MAINTENANCE MANUAL FOR GROUND MONITOR GM-250 COPYRIGHT 1983 AMERICAN MINE RESEARCH, INC. MANUAL PART NUMBER 180-0036 ORIGINAL: 1-17-83 REVISION: B (8-26-86) NOT TO BE CHANGED WITHOUT MSHA

More information

7PG21 Solkor Rf Feeder Protection Energy Management

7PG21 Solkor Rf Feeder Protection Energy Management Reyrolle Protection Devices 7PG21 Solkor Rf Feeder Protection Energy Management 7PG21 Solkor Rf Contents Contents Technical Manual Chapters 1. Description of Operation 2. Performance Specification 3.

More information

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes Company Directive STANDARD TECHNIQUE: SD1E/2 Technical Requirements for Customer Export Limiting Schemes Policy Summary This Standard Technique specifies the requirements for customer owned Export Limitation

More information

Draft Kenya Standard for Balloting Not to be Cited as Kenya Standard

Draft Kenya Standard for Balloting Not to be Cited as Kenya Standard KENYA STANDARD KS 1859-5:2010 ICS 29.240.01 Electrical power transmission and distribution High-voltage operating regulations Part 5: Standard procedure and terminology for the issuing of operating instructions

More information

DEIF A/S. Insulation monitor. Type SIM-Q

DEIF A/S. Insulation monitor. Type SIM-Q Insulation monitor 4921232C Monitoring of insulation resistance on ungrounded AC networks (IT network) Working voltage up to 69V AC, withstands up to V DC Measuring range 1...Mohm or 1...Mohm Alarm on

More information