SUBJECT HEADING: Switching Programmes ISSUE: 18

Size: px
Start display at page:

Download "SUBJECT HEADING: Switching Programmes ISSUE: 18"

Transcription

1 SUBJECT: Switchgear/Switching PROCEDURE: S04 SUBJECT HEADING: Switching Programmes ISSUE: 18 DATE: Apr INTRODUCTION 1.1 A written programme of switching operations shall be prepared. This programme shall be endorsed by a Senior Authorised Person and shall be checked and agreed by another Senior Authorised Person. Copies of the programme shall be in the possession of the Authorised Person(s) carrying out the switching and the Control Engineer prior to the switching being carried out. (Switching by National Grid staff shall be control directed). 1.2 A written switching programme is not required for; routine switching; control directed switching (National Grid staff shall normally be control directed); fault restoration; National Grid controlled switching; emergency switching; telecontrol trip timing requests which do not require on site switching; R/C function testing carried out by Control which does not require on site switching; disabling, altering, resetting protection eg auto-reclose when there is no associated plant switching. 2. SWITCHING DEFINITIONS 2.1 Routine Routine switching shall only be undertaken if approved by System Operations. 2.2 Planned Switching carried out using a switching programme prepared and submitted to DSMC at least two working days before operations are to commence. Shorter timescales shall be allowed for emergencies or by prior arrangement with the Control Engineer involved. 2.3 Control Directed Switching authorised by the Control Engineer without the operational engineer being in possession of a switching programme. 2.4 Fault Restoration Control directed switching post fault to restore system supplies/security together with isolation, earthing and on occasions fault location of the faulty section *. NOTE * It is normally practicable to write a switching programme for the subsequent fault repair and re-commissioning together with the restoration to system normal. 2.5 Emergency Switching necessary to make dead a section of the system where life or plant are at risk. Such switching shall be reported to the Control Engineer as soon as practicable after the operation. S04.docx Issue 18 14/04/17 SJS CP606/610 Page 1 of 8

2 3. GENERAL 3.1 A switching programme(s) for a planned outage shall be submitted by only one party. The party responsible for the preparation and submission of a switching programme(s) shall be the party responsible for initiating the work. 3.2 Where planned work is to be initiated by more than one party, the responsibility for the preparation and submission of the switching programme shall be agreed between them. 3.3 All planned LV switching shall be the subject of a switching programme. If it is associated with an HV switching programme then the two programmes shall be cross referenced. 3.4 Switching programme operations shall normally be carried out in strict sequence unless a change in sequence is authorised by the Control Engineer. The Control Engineer may in appropriate cases instruct operations to be carried out simultaneously, by different operators, where such operations do not interact with other operations on the programme. 3.5 Switching programme requirements shall comply with those of the Distribution Safety Rules. 3.6 Where operations are to be carried out at a substation, all switching programmes shall include both the name and the number of the substation entered under the heading Location. 3.7 Once the LV or HV switching programme has been completed, it shall be signed off and field copies sent to System Management, DSMC, Linley House within 10 working days of programme completion. DSMC shall file all completed switching programmes and retain them for inspection for 2 years from the programme date. 4. SWITCHING PROGRAMME NUMBERS All switching programme numbers are issued by System Management at DSMC to the following procedure. 4.1 Staff requiring planned outages on the HV system shall obtain a combined outage/switching programme number from System Management. 4.2 At the start of requesting the outage the requesting engineer shall provide a start and end date, brief circuit/work information, a supply restoration time and an approximate start time. 4.3 Emergency supply interruptions and faults are not subject to this procedure although switching programme numbers for fault repairs shall be issued by DSMC. 5. PRELIMINARY ACTIONS The following are some of the factors which shall be taken into account as necessary, when preparing a switching programme. 5.1 Load flow and system security eg: Check circuit loads and ratings For 132kV outages the following may need to be considered: S04.docx Issue 18 14/04/17 SJS CP606/610 Page 2 of 8

3 (a) (b) (c) Circuits from supergrid substations with split 132kV busbar running arrangements, or Circuits which form part of multi circuit 132kV supplies to a 132kV substation, or A section of supergrid substation 132kV busbar Confirm with System Management, the required supergrid 132kV busbar running arrangements necessary to provide maximum security during the proposed outage. 5.2 System paralleling considerations - phase angle; tap change control arrangements. Refer to CP608 Section 9 for paralleling fault level control actions. 5.3 Fault level in relation to switchgear rating. 5.4 Protection settings - sensitive earth fault protection. 5.5 Parallel operation of private generation. 5.6 Availability and rating of LV backfeed. 5.7 Warning to consumers of temporary disconnection. 5.8 Type of switchgear involved Operational limitations Test bushings Earthing gear Actuators fitted? 5.9 Method of phasing out Number of control zones involved Number of operating engineers required - use of telecontrol switching Geographical location of switching points Automation Schemes or Remote Control of switchgear. The operating procedures for Switchgear Actuators are to be found in CP Private HV systems: Inform customer of proposed switching when security of supply is compromised Verify operational state of customers private switchgear, ie incomers and bus section closed. 6. HV SWITCHING PROGRAMMES 6.1 HV switching programmes shall be prepared using CRMS system, or the computerised paper equivalent, or paper forms ENW/657 and ENW/658. S04.docx Issue 18 14/04/17 SJS CP606/610 Page 3 of 8

4 6.2 Switching programmes can be printed and faxed to DSMC. The computerised paper equivalent can be digitally signed by endorser, ed to the approver, who will digitally sign the programme and then convert it to a pdf document and it to the DSMC Switching Programme inbox (DSMCSWPR@enwl.co.uk), to the endorser and all other operators Where practicable and necessary switching programmes shall be prepared to completely cover all stages of an outage ie: System rearrangement Safety switching to isolate and earth the section to be released for work. This includes switching between Electricity North West control boundaries Issue and cancellation of safety documents Switching to re-energise the outage section Switching to restore the system to normal. 6.4 Where, however, the duration of an outage is excessive or where due to practical consideration the progress of the outage is uncertain, separate switching programmes can be prepared to cover: Initial three stages in Final two stages in When the operation is to be carried out at a substation, both the name and the number of the substation shall be entered under the heading Location on the switching programme. 6.6 At the start of a planned outage, the first operation shall be to confirm planned supply interruption control sheet TMS number..approved and customers carded. 6.7 Each operation on a switching programme shall be separately itemised. Visual confirmation items such as checking the operational state of switchgear and EFIs shall be written as an operation on the switching programme, this requirement does not apply to routine planned substation inspections that are carried out as part of a pre-planned maintenance regime. The list below shows examples of approved switching programme text Open or Close CB Isolate CB Select CB earth position Open or Close isolator Open or Close earth switch Prove feeder spouts dead Withdraw or replace VT Apply or remove portable earth Render inoperative or restore tripping S04.docx Issue 18 14/04/17 SJS CP606/610 Page 4 of 8

5 LV paralleling Issue or cancellation of safety documents Remove/replace trip links Confirm open from earth Confirm oil switch open Confirm circuit breaker tripped Confirm EFI operated 6.8 The words "Apply Safety Lock and Post Caution Notice" or SL & CN shall be added to the above items where applicable. 6.9 Under a Sanction for Test (SFT) 7.2 of the safety rules permits the removal and replacement of CMEs as necessary However, it is recognised that when testing a circuit including switchgear at an intermediate substation or substations, that some switching is necessary during the testing: a) To ensure the whole system, within the specified points of isolation, is tested, and b). To change the state of some switches to enable a full test to be carried out eg opening of a transformer switchfuse or circuit breaker This limited switching may be carried out under the SFT, providing that no switching is done outside the circuit limits stated in the SFT. The circuit under test and hence under the SFT shall be the minimum consistent with the work being carried out It is important to remember that following the cancellation of the SFT, confirmation items detailing the state of all switches involved in the testing shall be listed before any further switching or work is carried out on the programme Testing, under a SFT, shall be carried out at the switchgear from where it is proposed to re-energise the circuit, except where it is impracticable (eg no available test bushings or test access) Where testing involves the primary conductors, the SFT shall include the following additional details under Brief description of testing to be carried out : a) The test bushing serial number (where test bushings are used) b) Integral test bushings (were test bushings are part of the switchgear) c) Direct connection (where testing is performed with direct connection to busbars or exposed conductors) 6.10 LV operations shall be written on a separately numbered LV programme sheet. Reference can then be made in the HV programme to the completion of a group of LV items. Alternatively, when the number of LV operations is small, they can be included on the HV programme. S04.docx Issue 18 14/04/17 SJS CP606/610 Page 5 of 8

6 6.11 If the HV system is to be amended or extended, then diagrams showing the existing and proposed arrangements, including intermediate stages if appropriate, shall be attached to the switching programme. Action shall also be taken to update operational diagrams Where the HV system is to be amended in such a way that existing circuit labelling is affected (e.g. new ground mounted substation, PMT or ABS) then the switchgear labels at remote ends will require replacing in line with CP615. Installation of labels on the new switchgear and replacement of labels on remote end switchgear shall be recorded as separate operations on the switching programme. In addition the wording of the labels shall be recorded on the System Amendment Diagram at both new and existing switchgear locations The degree of Authorisation of the Senior Authorised Persons responsible for the endorsement and approval of a switching programme shall be appropriate to the content of the switching programme Where provision exists to extend the entries on a switching programme, the range of numbers checked shall be entered against the endorsement and approval signatures When a programme is prepared to cover the first three stages mentioned in 6.2 above then: Separate switching programme sheets shall be used to contain a) Safety switching together with the initial safety document issue, and b) System re-arrangement switching If following either the issue of initial safety documentation or system arrangement switching the sequence of work is uncertain, blank sheets shall be appended to record any programme entries subsequently agreed. The blank sheet(s) shall be numbered in sequence and its (their) existence recorded in the statement of sheet numbers on the 'Programme of Switching Operations' front sheet Where provision is made to include additional items in the run of a programme, a significant gap shall be left in the numbering sequence to allow for subsequent item insertion If following the cancellation of the initial safety document(s) an unforeseen change in the work requirement is identified, when agreed, outstanding switching programme entries shall be cancelled and a new switching programme prepared. The new programme shall be cross referenced to the old programme When advantage is taken of the relaxation permitted in , the following conventions shall apply: Switching programme entries for both the issue and cancellation of additional safety documents shall be agreed and entered onto the programme at the time of request. NOTE: Switching programmes shall cater for the cancellation of all safety documents associated with points of isolation and earthing before such points are changed Additional programme entries shall be recorded on both the Control Engineer s 'Master' copy and the requesting Senior Authorised Persons and if appropriate Operational Engineer s copies. The entry numbers shall be the next available numbers, in sequence, on the Control Engineer s 'Master' copy. S04.docx Issue 18 14/04/17 SJS CP606/610 Page 6 of 8

7 6.17 When approved, the programme shall be adhered to unless circumstances change, in which case, if time permits, a revised programme shall be prepared. In all other cases, it is permissible to change the programme by alteration of individual items provided that two SAPs one of who shall be the Control Engineer (or Field Control Engineer if the changes are within the Field Control boundaries), agree the changes and initial the alterations on their copies of the programme. Consideration shall be given to suspending a switching programme where there are too many alterations as this could cause difficulty reading, misunderstanding and sequencing issues. It is important before the changes are agreed that a discussion takes place between the Control Engineer (or Field Control Engineer) and field engineers as to the reason for the changes and that all parties understand any changes. The field engineers shall write down the alterations and repeat them in full to the sender to ensure that the amendment has been accurately received. They shall ensure that all other copies of the programme are amended This procedure also applies if an error is found on a programme A copy of the initial switching programme or any continuation programme shall be available at DSMC at least two working days before the operations are to commence. Shorter timescales shall be allowed in emergency situations or where there is prior agreement with the Control Engineer involved Where switching programmes are used to control switching in more than one control boundary, operations under the control of each Control Engineer(s) shall be clearly indicated Confirmation of the operational state of HV customers private switchgear shall be written as items on the switching programme, ie incomers closed, bus section closed At 33kV and 132kV exposed conductor sites, following a sequence of application or removal of portable earths, confirmation items shall be added to the HV switching programme to confirm that portable earthing rod heads have been locked in an approved metal box. (See Procedure S41) 7. LV SWITCHING PROGRAMMES 7.1 LV switching programmes shall be prepared by a person who is authorised for LV switching, 7.2 When the operation is to be carried out at a substation both the name and the number of the substation shall be entered under the heading Location on the switching programme. 7.3 An LV switching programme register shall be maintained by System Management at DSMC. All LV switching programmes shall be entered in this register and given a unique number, which shall be sequential within the calendar year. 7.4 If the LV switching programme is associated with an HV switching programme, then the two programmes shall be cross-referenced. Alternatively, when the number of LV operations is small, they can form part of the HV programme. 8. DOCUMENTS REFERENCED Distribution Safety Rules CP608 - System Control CP630 - Operating Procedures for Switchgear Actuators S04.docx Issue 18 14/04/17 SJS CP606/610 Page 7 of 8

8 CP606 - Operations Manual Procedure S41 CP615-Substaion, Circuit and Plant Identification. 9. KEYWORDS Control; LV; Operation; Outage; Safety Rules. S04.docx Issue 18 14/04/17 SJS CP606/610 Page 8 of 8

SYNCHRONISING AND VOLTAGE SELECTION

SYNCHRONISING AND VOLTAGE SELECTION SYNCHRONISING AND VOLTAGE SELECTION This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for any

More information

Draft Kenya Standard for Balloting Not to be Cited as Kenya Standard

Draft Kenya Standard for Balloting Not to be Cited as Kenya Standard KENYA STANDARD KS 1859-5:2010 ICS 29.240.01 Electrical power transmission and distribution High-voltage operating regulations Part 5: Standard procedure and terminology for the issuing of operating instructions

More information

Field Instruction Switching Activities. Purpose. Scope. Objective. Safety

Field Instruction Switching Activities. Purpose. Scope. Objective. Safety 8.22 Switching Activities Purpose This instruction provides a safe system for switching on Horizon Powers Low Voltage, High Voltage and or Transmission electrical apparatus/network, where switching operations

More information

Earthing, HV Switching and Associated Operational Equipment. Approval: Chief Operating Officer

Earthing, HV Switching and Associated Operational Equipment. Approval: Chief Operating Officer ACCESS PRACTICE AP 24 Earthing, HV Switching and Associated Operational Equipment Process Authority: Manager Operations Improvement Approval: Chief Operating Officer Version Date: 27/08/2013 Revision:

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE EPN, LPN, SPN ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing

More information

Hamdy Faramawy Senior Application Specialist ABB Sweden

Hamdy Faramawy Senior Application Specialist ABB Sweden Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy

More information

Greenlining and Bluelining of Ergon Energy Substation Drawings

Greenlining and Bluelining of Ergon Energy Substation Drawings Greenlining and Bluelining of Ergon Energy Table of Contents Purpose and Scope... 1 Responsibilities... 1 Definitions, Abbreviations and Acronyms... 1 References... 1 General... 1 Requirements... 3 Testing

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: All ENGINEERING COMMISSIONING PROCEDURE ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing of new and

More information

EI HIGH VOLTAGE INSULATION TESTING POLICY

EI HIGH VOLTAGE INSULATION TESTING POLICY Network(s): Summary: ENGINEERING INSTRUCTION EI 09-0001 HIGH VOLTAGE INSULATION TESTING POLICY EPN, LPN, SPN This engineering instruction details the policy for the on-site insulation testing of new and

More information

EDS FAULT LEVELS

EDS FAULT LEVELS Document Number: EDS 08-1110 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-1110 FAULT LEVELS This standard provides guidance on the calculation, application and availability of

More information

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION and Guidance NSI 26 RAILWAY CONNECTION CIRCUITS Copyright National Grid plc 2016, all rights reserved. No part of this publication

More information

Title Operating Work - Low Voltage Distribution System. Reference Number POP 06 - (RIC Standard: EP SI)

Title Operating Work - Low Voltage Distribution System. Reference Number POP 06 - (RIC Standard: EP SI) Discipline Engineering Standard - NSW Category Electrical Title Operating Work - Low Voltage Distribution System Reference Number POP 06 - (RIC Standard: EP 95 30 00 03 SI) Document Control Status Date

More information

Guideline for Creating Disconnection Points and Establishing a Not Electrically Connected Area

Guideline for Creating Disconnection Points and Establishing a Not Electrically Connected Area Guideline for Creating Disconnection Points and Establishing a Not Document Number: Authorised by: Issue Date: 29 June 2012 Previous Document: 12 February 2010 Principal Authors: J Dohmen Powerlink D Brown

More information

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D Electricity Ten Year Statement November 2017 01 Electricity Ten Year Statement November 2017 001 Appendix D 1 Short-circuit currents 02 2 Short-circuit current terminology 04 3 Data requirements 07 4 Fault

More information

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1.1 INTRODUCTION 2 WFPS1.2 OBJECTIVE 2 WFPS1.3 SCOPE 3 WFPS1.4 FAULT RIDE THROUGH REQUIREMENTS 4 WFPS1.5 FREQUENCY REQUIREMENTS 5 WFPS1.6 VOLTAGE

More information

Appendix D Fault Levels

Appendix D Fault Levels Appendix D Fault Levels Page 1 Electricity Ten Year Statement November 2013 D.1 Short Circuit Currents Short Circuit Currents Three phase to earth and single phase to earth short circuit current analyses

More information

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007.

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007. Our Ref: Your Ref: Date: November 2007 To: All Recipients of the Serviced Grid Code Regulatory Frameworks Electricity Codes National Grid Electricity Transmission plc National Grid House Warwick Technology

More information

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations C&G 2395-01 Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations Phase rotation and verification of voltage drop 1 Outcomes of this Session describe how to assess

More information

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code) GC0102 EXTRACT OF EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 08/01/2018 Paragraph No/Title EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS (This contents page does not form part of the Grid Code) Page

More information

TS RES - OUTSTANDING ISSUES

TS RES - OUTSTANDING ISSUES TS RES - OUTSTANDING ISSUES This document has been officially issued as DRAFT until the following outstanding issues have been resolved. At that time the document will be officially reissued as the next

More information

RELEVANT ELECTRICAL STANDARDS

RELEVANT ELECTRICAL STANDARDS RELEVANT ELECTRICAL STANDARDS Issue 2 October 2014 Issue 2 September 2014 National Grid 2014 2014 Copyright owned by National Grid Electricity Transmission plc, all rights reserved. No part of this publication

More information

Busbars and lines are important elements

Busbars and lines are important elements CHAPTER CHAPTER 23 Protection of Busbars and Lines 23.1 Busbar Protection 23.2 Protection of Lines 23.3 Time-Graded Overcurrent Protection 23.4 Differential Pilot-Wire Protection 23.5 Distance Protection

More information

Table of Contents. Introduction... 1

Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...

More information

ACCESS TO HIGH VOLTAGE APPARATUS

ACCESS TO HIGH VOLTAGE APPARATUS CORPORATE PROCEDURE ACCESS TO HIGH VOLTAGE APPARATUS Approved By: Prepared By: Issue Date: 17/6/2011 Andrew Macrides Access to Apparatus Rules File No: Managing Director Committee QDOC2011/63 Status: Approved

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

RELEVANT ELECTRICAL STANDARDS

RELEVANT ELECTRICAL STANDARDS RELEVANT ELECTRICAL STANDARDS Issue 2 February 2014 National Grid 2014 No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means electronic,

More information

Single Line Diagram of Substations

Single Line Diagram of Substations Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission lines are

More information

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels

More information

PSSI 27 Work or Testing On or Near to High Voltage Direct Current (HVDC) Plant and Apparatus

PSSI 27 Work or Testing On or Near to High Voltage Direct Current (HVDC) Plant and Apparatus 1. SCOPE This Safety Instruction applies the principles established by the ScottishPower Safety Rules (Electrical and Mechanical) and the Company Safety Instructions to achieve Safety from the System for

More information

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event

More information

Power Frequency Withstand Voltage On-site testing of 400 kv GIS

Power Frequency Withstand Voltage On-site testing of 400 kv GIS Power Frequency Withstand Voltage On-site testing of 400 kv GIS D. Anaraki Ardakani, A. Omidkhoda, M. Solati High Voltage Engineering Center ACECR Tehran, Iran Da_ardakani@yahoo.com Paper Reference Number:

More information

Company Directive STANDARD TECHNIQUE: TP14C. Distribution Business Provided Metering Facilities

Company Directive STANDARD TECHNIQUE: TP14C. Distribution Business Provided Metering Facilities Company Directive STANDARD TECHNIQUE: TP14C Distribution Business Provided Metering Facilities Summary This standard technique document details the metering facilities to be provided by the distribution

More information

ECP GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE

ECP GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE Document Number: ECP 11-0511 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0511 GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE EPN, LPN, SPN This procedure details the testing and

More information

HIGH VOLTAGE RULES. Document Owner: HV Group. Authorised: Electrical Services Manager Liberty Primary Steel

HIGH VOLTAGE RULES. Document Owner: HV Group. Authorised: Electrical Services Manager Liberty Primary Steel HIGH VOLTAGE RULES Document Owner: HV Group Authorised: Electrical Services Manager Liberty Primary Steel HIGH VOLTAGE RULES Revision 10 INDEX 1.0 GENERAL 1.1 SCOPE 1.2 DUTIES 1.3 SUPPLY AND KNOWLEDGE

More information

DISTRIBUTION BUSINESS

DISTRIBUTION BUSINESS DISTRIBUTION BUSINESS DOCUMENT TITLE: MANUAL: DISTRIBUTION NETWORK OPERATION MANUAL DOCUMENT I.D. NUMBER: DS O SW 01 Copyright Aurora REVISIONS REV DATE REVISION DESCRIPTION APPROVAL NO. 1.0 1998 Interim

More information

ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE

ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0507 COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE EPN, LPN, SPN This procedure details the testing and commissioning procedures for

More information

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: ECP 11-0515 ENGINEERING COMMISSIONING PROCEDURE ECP 11-0515 HV METERING EQUIPMENT COMMISSIONING PROCEDURE

More information

Unit 2. Single Line Diagram of Substations

Unit 2. Single Line Diagram of Substations Unit 2 Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission

More information

Distribution Code. Approved by CER. Version: 5.0 Date: April Distribution System Operator ESB Networks Limited

Distribution Code. Approved by CER. Version: 5.0 Date: April Distribution System Operator ESB Networks Limited Distribution Code Approved by CER Version: 5.0 Date: April 2016 Issued by: Distribution System Operator ESB Networks Limited CONTENTS Page Preface... vii 1. INDUSTRY STRUCTURE... viii 2. USE OF THE DISTRIBUTION

More information

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES Issue 9: May 2013 National Grid National Grid Registered Office National Grid Electricity Transmission plc Registered Office: 1-3 Strand London

More information

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS ENGINEERING DESIGN STANDARD EDS 08-2109 LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS Network(s): Summary: EPN, LPN, SPN This standard provides guidance on the installation of

More information

UNCONTROLLED COPY. Queensland Electricity Entity Standard for Safe Access to High Voltage Electrical Apparatus. August 2015

UNCONTROLLED COPY. Queensland Electricity Entity Standard for Safe Access to High Voltage Electrical Apparatus. August 2015 Queensland Electricity Entity Standard for Safe Access to High Voltage Electrical Apparatus August 2015 August 2015 Queensland Electricity Entity Standard for Safe Access to HV Electrical Apparatus I This

More information

Protection of Electrical Networks. Christophe Prévé

Protection of Electrical Networks. Christophe Prévé Protection of Electrical Networks Christophe Prévé This Page Intentionally Left Blank Protection of Electrical Networks This Page Intentionally Left Blank Protection of Electrical Networks Christophe Prévé

More information

Absolute Block. Uncontrolled When Printed Document to be part superseded by GKRT0055 Iss 1 and GKRT0077 Iss 1 (published on 07/09/2013)

Absolute Block. Uncontrolled When Printed Document to be part superseded by GKRT0055 Iss 1 and GKRT0077 Iss 1 (published on 07/09/2013) Signatures removed from electronic version Submitted by... Richard Genner Nominated Responsible Manager Approved by... Philip Wiltshire Chairman, Train Control & Communications Subject Committee Approved

More information

Energy Networks Association

Energy Networks Association The Voice of the Networks Version 1 (ISSUED) Energy Networks Association Insert presentation title here ENA EREC P28 Issue 2 2018 Key Technical Modifications Grid Code and SQSS Mods Name Position Date

More information

Generation Interconnection Requirements at Voltages 34.5 kv and Below

Generation Interconnection Requirements at Voltages 34.5 kv and Below Generation Interconnection Requirements at Voltages 34.5 kv and Below 2005 March GENERATION INTERCONNECTION REQUIREMENTS AT 34.5 KV AND BELOW PAGE 1 OF 36 TABLE OF CONTENTS 1. INTRODUCTION 5 1.1. Intent

More information

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE ENGINEERING COMMISSIONING PROCEDURE ECP 11-0512 GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE Network(s): Summary: EPN, LPN, SPN This procedure details the testing and commissioning

More information

Electrical Procedure No E032. Procedure No: ELE 032

Electrical Procedure No E032. Procedure No: ELE 032 Procedure No: ELE 032 Procedure Title: Date of Procedure: Responsible Person(s) Safety Isolation of Low Voltage Networks and Systems for work to be carried out by third parties. i.e. Non University personnel.

More information

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes Company Directive STANDARD TECHNIQUE: SD1E/2 Technical Requirements for Customer Export Limiting Schemes Policy Summary This Standard Technique specifies the requirements for customer owned Export Limitation

More information

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS Ljubomir KOJOVIC Cooper Power Systems - U.S.A. Lkojovic@cooperpower.com INTRODUCTION In steel facilities that use Electric Arc Furnaces (EAFs) to manufacture

More information

Connection of Embedded Generating Plant up to 5MW

Connection of Embedded Generating Plant up to 5MW Engineering Recommendation No.3 of the Electricity Distribution Code Connection of Embedded Generating Plant up to 5MW Version 1.0 30th November 2005 Prepared by: Al Ain Distribution Company, Abu Dhabi

More information

each time the Frequency is above 51Hz. Continuous operation is required

each time the Frequency is above 51Hz. Continuous operation is required GC0101 EXTRACT OF EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 08/01/2018. ECC.6 ECC.6.1 ECC.6.1.1 ECC.6.1.2 ECC.6.1.2.1 ECC.6.1.2.1.1 ECC.6.1.2.1.2 ECC.6.1.2.1.3 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA

More information

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 Prepared by System Planning Division Transmission Planning Department PJM 2016 Table of Contents Table of Contents Approval...6

More information

SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY SPEC WRITER NOTE: Delete between // -- // if not applicable to project. Also, delete any other item or

More information

SWITCHING SAFETY & RELIABILITY CONFERENCE

SWITCHING SAFETY & RELIABILITY CONFERENCE SWITCHING SAFETY & RELIABILITY CONFERENCE JARGON WORKSHEET Energize (v) Energize is the process of applying rated voltage to circuit or equipment. Modified IEEE or OSHA from Adj. to verb. To make a piece

More information

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES Issue 11: February 2018 National Grid Registered Office National Grid Electricity Transmission plc Registered Office: 1-3 Strand London WC2N

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

Power Station Electrical Protection A 2 B 2 C 2 Neutral C.T E M L } a 2 b 2 c 2 M M M CT Restricted E/F Relay L L L TO TRIP CIRCUIT Contents 1 The Need for Protection 2 1.1 Types of Faults............................

More information

South African Distribution Code

South African Distribution Code South African Distribution Code Metering Code Version 6.0 July 2014 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact: Mr.

More information

LV/MV/HV CIRCUIT BREAKERS (SWITCH GEAR) DESIGN, INSPECTION, MAINTENANCE, REPAIR & TROUBLESHOOTING

LV/MV/HV CIRCUIT BREAKERS (SWITCH GEAR) DESIGN, INSPECTION, MAINTENANCE, REPAIR & TROUBLESHOOTING Training Title LV/MV/HV CIRCUIT BREAKERS (SWITCH GEAR) DESIGN, INSPECTION, MAINTENANCE, REPAIR & TROUBLESHOOTING Training Duration 5 days Training Venue and Dates LV/MV/HV Circuit Breakers (Switchgear):

More information

NEO TELE-TRONIX PVT. LTD. 6/7 Bijoygarh, Kolkata , Tel : ; Fax :

NEO TELE-TRONIX PVT. LTD. 6/7 Bijoygarh, Kolkata , Tel : ; Fax : NEO TELE-TRONIX PVT. LTD. 6/7 Bijoygarh, Kolkata - 700 032, Tel : 033 2477 3126; Fax : 033 2477 2403 www.ntplindia.com SPECIFICATION NTPL MAKE MICRO-CONTROLLER BASED AUTOMATIC 50KV/10A AC HIGH VOLTAGE

More information

Click to edit Master title style. Click to edit Master title style. Northern Powergrid Asset Recording Guidance

Click to edit Master title style. Click to edit Master title style. Northern Powergrid Asset Recording Guidance Click to edit Master title style Click to edit Master title style Northern Powergrid Asset Recording Guidance Rules for ICP & IDNO Version 1.0 April 2017 Introduction Accurate records for all assets are

More information

DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS

DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS Abdelrahman AKILA Ahmed HELAL Hussien ELDESOUKI SDEDCO Egypt AASTMT Egypt AASTMT Egypt Abdurrahman.akela@gmail.com ahmedanas@aast.edu hdesouki@aast.edu

More information

VI 3 - i TABLE OF CONTENTS

VI 3 - i TABLE OF CONTENTS VI 3 - i TABLE OF CONTENTS 3 PROJECT SPECIFIC DATA... 1 3.1 DEFINITIONS... 1 3.1.1 Design Data, High and Medium Voltage... 1 3.1.2 Design Data, Low Voltage Equipment... 2 3.1.3 Phase Relationship... 3

More information

Substation Testing and Commissioning: Power Transformer Through Fault Test

Substation Testing and Commissioning: Power Transformer Through Fault Test 1 Substation Testing and Commissioning: Power Transformer Through Fault Test M. Talebi, Member, IEEE, Power Grid Engineering Y. Unludag Electric Power System Abstract This paper reviews the advantage of

More information

TABLE OF CONTENT

TABLE OF CONTENT Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES

More information

Section 3. Test Procedures

Section 3. Test Procedures Section 3. Information contained within this section shall be read in conjunction with all sections of this manual Non - Compliant Test Results Where acceptable results are not attained in accordance with

More information

NSP/007/019 - Guidance on Substation Design: EHV Substation Drawing Policy

NSP/007/019 - Guidance on Substation Design: EHV Substation Drawing Policy Version:- 1.1 Date of Issue:- Feb 2015 Page 1 of 13 NSP/007/019 - Guidance on Substation Design: EHV Substation Drawing Policy 1. Purpose The purpose of this document is to outline the Northern Powergrid

More information

Module 9. Fault Type Form 4.X RELIABILITY ACCOUNTABILITY

Module 9. Fault Type Form 4.X RELIABILITY ACCOUNTABILITY Module 9 Fault Type Form 4.X 1 M9 Fault Type The descriptor of the fault, if any, associated with each Automatic Outage of an Element. 1. No fault 2. Phase-to-phase fault (P-P) 3. Single phase-to-ground

More information

No. SSIEC-PRC SHINSUNG. Polymer Recloser SIREC SERIES 15kV, 27kV, 38kV 400A, 630A, 800A

No. SSIEC-PRC SHINSUNG. Polymer Recloser SIREC SERIES 15kV, 27kV, 38kV 400A, 630A, 800A No. SSIEC-PRC-00803-1 SHINSUNG Polymer Recloser SIREC SERIES 15kV, 27kV, 38kV 400A, 630A, 800A Introduction SIREC(Solid Insulated Recloser) is designed for outdoor application with lightweight, longlife,

More information

ECP DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE

ECP DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE Document Number: ECP 11-0506 ENGINEERING COMMISSIONING PROCEDURE ECP 11-0506 DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE Network(s): Summary: EPN, LPN, SPN This procedure details the testing and commissioning

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

PME specialises in developing, implementing and maintaining solutions to the Mining industry.

PME specialises in developing, implementing and maintaining solutions to the Mining industry. +675 325 3533 PME specialises in developing, implementing and maintaining solutions to the industry. Our Services: Engineering & design EPC services High voltage design, installations and testing Installation

More information

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN Approval Amendment Record Approval Date Version Description 01/04/2014 1 Initial Issue under MTM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 7 Table of Contents

More information

Electrical Switchgear & Power Transformer Testing. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

Electrical Switchgear & Power Transformer Testing. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E Electrical Switchgear & Power Transformer Testing H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae ictd@ictd.ae Course Introduction: This will provide you with practical knowledge

More information

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 21 25 Sep $3,750 Dubai, UAE In any of the 5 star

More information

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS 1 B. RAMESH, 2 K. P. VITTAL Student Member, IEEE, EEE Department, National Institute of Technology Karnataka,

More information

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Applicability 1 Section 502.8 applies to: (a) the legal owner of a generating unit: (i) connected to the transmission facilities in the balancing authority area

More information

Reference Number PDS 07 (RIC Standard: EP SP)

Reference Number PDS 07 (RIC Standard: EP SP) Discipline Engineering Standard NSW Category Electrical Title Reference Number PDS 07 (RIC Standard: EP 12 10 00 20 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Jan 05 Standards

More information

Equipment Description Quantity as per drawings Actual quantity

Equipment Description Quantity as per drawings Actual quantity NOTE: SAFETY: Tests must be carried out after the installation, alteration or repair and before putting back to service. At all times maintain suitable clearance to all other electrical equipment and verify

More information

KENYA ELECTRICITY GENERATING COMPANY LTD

KENYA ELECTRICITY GENERATING COMPANY LTD KENYA ELECTRICITY GENERATING COMPANY LTD TENDER No. KGN-HYD-014-2016 TENDER FOR REHABILITATION OF PROTECTION EQUIPMENT FOR MASINGA HYDRO POWER STATION 20/06/2016 ADDENDUM NO. 1 In accordance with the tender

More information

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation Technical Requirements for Interconnection and Parallel Operation of Distributed Generation Single Phase

More information

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES C.E.T. Foote*, G.W. Ault*, J.R. McDonald*, A.J. Beddoes *University of Strathclyde, UK EA Technology Limited, UK c.foote@eee.strath.ac.uk

More information

Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design

Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design Company Directive POLICY DOCUMENT: SD4/7 Relating to 11kV and 6.6kV System Design Policy Summary This document describes the standard requirements for the design of the 11kV and 6.6kV systems. Reference

More information

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS S1. Standard Interconnection Methods with Typical Circuit Configuration for Single or Multiple Units Note: The protection requirements

More information

QUESTIONNAIRE for Wind Farm Power Stations only

QUESTIONNAIRE for Wind Farm Power Stations only TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21

More information

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it. 1. SCOPE The requirements of this document apply to all Plant, Equipment and Apparatus that are part of, or are Directly connected to, the Company network. Requirements contained herein may be modified

More information

Series NRX with PXR - Instructions for Neutral Current Sensor Type NF

Series NRX with PXR - Instructions for Neutral Current Sensor Type NF Supersedes March 2016 Series NR Series NR with PR - Instructions for Neutral Current Sensor Type NF Instructions apply to: UL1066/ANSI, UL489 series NR NF frame IEC IZM16 WARNING (1) ONLY QUALIFIED ELECTRICAL

More information

FAQ ON EARTHING STANDARDS 16/08/2018

FAQ ON EARTHING STANDARDS 16/08/2018 FAQ ON EARTHING STANDARDS 16/08/2018 This document has been updated to include changes made to substation earthing layouts that have been made necessary due to copper theft. The main changes to be aware

More information

One line and Three line diagrams Schematics Wiring Diagrams Logic ladders Ancillary prints Pictorial instructions

One line and Three line diagrams Schematics Wiring Diagrams Logic ladders Ancillary prints Pictorial instructions One line and Three line diagrams Schematics Wiring Diagrams Logic ladders Ancillary prints Pictorial instructions One line diagram (1) One line diagrams will typically show in a simple fashion an over

More information

IMP/007/011 - Code of Practice for the Application of Lightning Protection

IMP/007/011 - Code of Practice for the Application of Lightning Protection Version 1.1 of Issue Aug 2006 Page 1 of 11 IMP/007/011 - Code of Practice for the Application of Lightning Protection 1.0 Purpose The purpose of this document is to ensure the company achieves its requirements

More information

PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA

PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA Generally inspection of electrical installations is carried out under Regulation-30 (Periodical inspection & testing) & Regulation-43 (Approval

More information

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit Validation of a Power Transformer Model for Ferroresonance with System Tests on a 4 kv Circuit Charalambos Charalambous 1, Z.D. Wang 1, Jie Li 1, Mark Osborne 2 and Paul Jarman 2 Abstract-- National Grid

More information

OMICRON Seminar on Substation Testing and Diagnosis. October 23, 2017 Dubai, United Arab Emirates. October 24, 2017 Abu Dhabi, United Arab Emirates

OMICRON Seminar on Substation Testing and Diagnosis. October 23, 2017 Dubai, United Arab Emirates. October 24, 2017 Abu Dhabi, United Arab Emirates OMICRON Seminar on Substation Testing and Diagnosis October 23, 2017 Dubai, United Arab Emirates October 24, 2017 Abu Dhabi, United Arab Emirates Time Optimized Substation Asset Testing and Diagnosis Agenda

More information

How to maximize reliability using an alternative distribution system for critical loads

How to maximize reliability using an alternative distribution system for critical loads White Paper WP024001EN How to maximize reliability using an alternative distribution system for critical loads Executive summary The electric power industry has several different distribution topologies

More information

PROTECTION of electricity distribution networks

PROTECTION of electricity distribution networks PROTECTION of electricity distribution networks Juan M. Gers and Edward J. Holmes The Institution of Electrical Engineers Contents Preface and acknowledgments x 1 Introduction 1 1.1 Basic principles of

More information

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T-18

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T-18 BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T-18 LIVE LINE PERMITS, ASSURANCE OF NO RECLOSE PERMITS AND CAUTION TAGS Supersedes OO 1T-18 issued 13 October 2010 Review Year: 2019 Original signed by:

More information