MCset 17.5 kv. Installation instruction April Medium Voltage Distribution
|
|
- Piers McCormick
- 5 years ago
- Views:
Transcription
1 Medium Voltage Distribution MCset 17.5 kv Air insulated switchboard Withdrawable switchgear SF6 or vaccum technology Installation instruction April 2012
2
3 Contents General 2 Glossary 2 Earthing switch control symbols 2 Moving part control symbols 3 Recommendations 3 Standard tightening torques 4 List of bags and accessories 4 Packaging 5 Dimensions and weights 6 AD, CL-GL, VT cubicles 6 Cubicle fitted with IPX1/IPX2 roofs 9 DI2 cubicle 9 RHB, RHC cubicles 10 Transition enclosure MTP 11 Handling instructions 12 Land packaging 12 Ocean shipment packaging 12 Handling using a sling 12 Handling by rolling 13 Storage 13 Installation and operation recommendation 14 Floor finishing and cubicle fastening 15 Surface condition 15 Floor quality 15 Description of irons and accessories 15 Placing and adjusting on non earthquake resistant civil engineering works 15 Placing and adjusting on earthquake resistant civil engineering works Unpacking cubicles 19 Placing cubicles in a switchboard 19 Coupling of cubicles 22 Rack-in check 24 Removing the mobile part transport fixations 24 Installing the main earth connection 25 Installing the electric connections of the busbars and MV cables 27 Installing busbars 29 Installing busbars between MTP and the MOTORPACT cubicle 33 Placing MV cables on AD cubicle 36 Placing MV cables on RHC cubicle 42 MV cable screen earthing 46 LV cable routing and connection 47 Installing the tunnel 49 Installing the IPX1/IPX2 roofs or anti arc IPx1/IPx2 tunnels 52 Installing the tunnel end sheets 58 Installing the end sheets 60 Installing fans on versions 3600 A / 4000 A 63 Installation of a FU equipped with electromagnetic locking options 64 Earthing switch with electromagnetic locking 64 Rack-in prevention with electromagnetic locking 65 Prior to installing the front panels 65 Steps to be taken for tests and inspection 66 Power frequency dielectric test 66 Tests on site 67 Checking and setting up the internal arcing detector 67 Index EN.indd version 07 1
4 General Glossary UF Functionnal Unit (cubicle + mobile part + Sepam) Nota: this document is available for all the units ordered from April AD CL-GL TT RHB RHC MTP DI TT TC VPIS LV MV SMALT Incoming / feeder cubicle Withdrawable line coupling cubicle Measurement and busbar earthing cubicle Connection from the top by bar Connection from the top by cable Connection enclosure between an MCset cubicle and a MOTORPACT cubicle Fuse switch feeder cubicle Voltage transformer Current transformer or current sensor Voltage Presence Indicator System Low voltage Voltage class, including levels and 17.5 kv Earthing switch Mobile part LF Rollarc 400 EVOLIS CTV1 OED Extraction table SF6 withdrawable circuit breaker which is used in AD and CL cubicles SF6 breaking withdrawable contactor used in AD1 cubicle Vacuum circuit breaker which is used in AD and CL cubicles Vacuum breaking withdrawable contactor used in AD1 cubicle Tool to remove/insert the mobile part from the switchgear. The tool allows to place the mobile part on the floor. Tool to remove/insert the mobile part from the switchgear. The tool DOES NOT allow to place the mobile part on the floor. Earthing switch control symbols Rack-in prevention position. Locking possible. Rack-in or racked-out position. Operation position. Open earthing switch mechanical indicator. 2 version EN.indd
5 General Closed earthing switch mechanical indicator. Position can be locked using pad lock. Moving part control symbols Operation position. Racked-in position. Racked-out position. Insertion / extraction position. Recommendations Installation above the switchboard All type of equipment installation such as lamp or light are forbidden. Marking It is compulsory forbidden to walk on the parts with this label. It is compulsory forbidden to remove the parts with this label when the equipment is energised EN.indd version 07 3
6 General Standard tightening torques (Non greased screws and bolts) Screw Torque in Nm Ø 6 13 Ø 8 28 Ø Ø Ø Application methods: The elastic washers placed on the external sides of the connections and busbars ensure better distribution of stress induced by the screw torque. List of bags and accessories Switchboard packaging Package Switchboard end and fixing Switchboard Civil engineering Contenu - Switchboard end sheets - Fixation beams - Bag of screws and bolts - Top wireway and cover - 2 cubicle operation cranks - 10 mm2 wire - 1 earth fishplate and seal - Civil engineering guide - Installation manual - Operating manual - Cubicle fastening rails - Expansion screws - Bag of screws and bolts Package (Optional) Tests and inspection Spare parts Optional accessories Content - Manual earthing kit - Fuses - 1 busbar earthing truck - 1 phase balance testing device - 1 I and U test lead - 1 tunnel closure kit - 1 mobile part extraction tool (ERT or extraction table) 4 version EN.indd
7 General Packaging Content Cubicle packaging Separate packaging Screws and bolts for: - Busbar fastening (1) 2 - Busbar shims (1) 2 - Lock associated with the cubicle Lock unit Cubicle fastening on civil engineer. works 1 - Intercubicle fastening Coupling gaskets 2 1 Cable fastening (AD cubicle): - Flange supports 1 - Flanges 1 Cable floor: - Bottom plates 1 - Cable support sleeves 1 - Bag of screws and bolts Busbar 1250 A Cable connection brackets 1 - Busbar covers Zero frequence toroids Busbars 2500 A, 3150 A and more Cable compartment 1 - Fan compartment (FU 3600 A/ 4000 A) 1 (1) in general. (2) these parts can sometimes be dispatched in a separate package. The cable boxes installation drawings can be provided upon request: AD1 : AAV AD2 : AAV AD3 : BBV EN.indd version 07 5
8 Dimensions and weights AD, CL-GL, VT cubicles Cubicles with 1 CT per phase, internal arcing withstand and Gas Exhaust version (wall-mounted) or no internal arcing Boxes for 3600A / 4000A Dimensions AD1 AD2 AD3 CL1 CL2 CL3 TT1 TT2 (3600A) (3600A) (2500A) (3150A) (2500A) (3150A) (4000A) (4000A) Width (mm) L x x x x x Height** (mm) H Depth (mm) P Weight* (kg) x x x x x Weight (kg) of VT compartment * Maximum fully fitted weight. ** This dimension excludes cable flanges as well as any compartments placed under the cubicle. 6 version EN.indd
9 Dimensions and weights AD, CL-GL, VT cubicles Cubicles with 1 CT per phase, internal arcing withstand on 4 sides Boxes for 3600A / 4000A Dimensions AD1 AD2 AD3 CL1 CL2 CL3 TT1 TT2 (3600A) (3600A) (2500A) (3150A) (2500A) (3150A) (4000A) (4000A) Width (mm) L x x x x x Height** (mm) H Depth (mm) P Weight* (kg) x x x x x Weight (kg) of VT compartment * Maximum fully fitted weight. ** This dimension excludes cable flanges as well as any compartments placed under the cubicle EN.indd version 07 7
10 Dimensions and weights Cubicles with 2 CTs per phase, internal arcing withstand and Gas Exhaust version (wall-mounted) or no internal arcing Boxes for 3600A / 4000A Dimensions AD1 AD2 AD3 (2500A) (3150A) (3600A/4000A) Width (mm) L Height** (mm) H Depth (mm) P Weight* (kg) Weight (kg) of VT compartment * Maximum fully fitted weight. ** This dimension excludes cable flanges as well as any compartments placed under the cubicle. Cubicles with 2 CTs per phase, internal arcing withstand on 4 sides (installed in the middle of the room, no wall-mounting) Boxes for 3600A / 4000A Dimensions AD1 AD2 AD3 (2500A) (3150A) (3600A/4000A) Width (mm) L Height** (mm) H Depth (mm) P Weight* (kg) Weight (kg) of VT compartment * Maximum fully fitted weight. ** This dimension excludes cable flanges as well as any compartments placed under the cubicle. 8 version EN.indd
11 Dimensions and weights Cubicle fitted with IPX1/IPX2 roofs (e.g.: AD1 with internal arcing withstand on 4 sides) Dimensions AD1 IPX1 AD1 IPX2 Width (mm) L Height (mm) H Depth (mm) P tunnel DI2 cubicle Rear anti-arcing cubicle, internal arcing withstand on 3 or 4 sides (3 sides) (4 sides) Dimensions DI2 Internal arcing withstand on 3 sides and no internal arcing Internal arcing withstand on 4 sides Width (mm) L Height (mm) H Depth (mm) P Weight (kg) EN.indd version 07 9
12 Dimensions and weights RHB, RHC cubicles Cubicles with 1 CT per phase, internal arcing withstand on 4 sides (installation in the middle of the room, no wall-mounting) Boxes for 3600A / 4000A Dimensions RHB1 RHB2 RHB3 (2500A) RHB3 (3150A) RHB3 RHC1 RHC1 RHC2 RHC2 RHC3 (2500A) RHC3 RHC3 (3150A) 2 cables max. per phase 3 to 4 cables per phase 2 cables max. per phase 3 to 4 cables per phase 2 cables max. per phase 3 to 4 cables per phase 2 cables max. per phase (3600A) (4000A) Width (mm) L Height (mm) H Depth (mm) P (RHB3) 2275 (RHC3) 2000 Weight* (kg) Weight (kg) of VT compartment * Maximum fully fitted weight. Cubicles with 2 CTs per phase, internal arcing withstand on 4 sides (installation in the middle of the room, no wall-mounting) Boxes for 3600A / 4000A Dimensions RHB1 RHB2 RHB3 (2500A) RHB3 (3150A) RHB3 RHC1 RHC1 RHC2 RHC2 RHC3 (2500A) RHC3 RHC3 (3150A) 2 cables max. per phase 3 to 4 cables per phase 2 cables max. per phase 3 to 4 cables per phase 2 cables max. per phase 3 to 4 cables per phase 2 cables max. per phase (3600A) (4000A) Width (mm) L Height (mm) H Depth (mm) P (RHB3) 2275 (RHC3) 2000 Weight* (kg) Weight (kg) of VT compartment * Maximum fully fitted weight. 10 version EN.indd
13 Dimensions and weights Transition enclosure MTP (Motorpact transition enclosure) This enclosure is factory-mounted to the right or left of an MCset (depends on switchboard configuration). For more details see the MOTORPACT civil engineering guide: A. Dimensions MTP 1250 A 2500 A 3150 A Width (mm) L Height (mm) H Depth (mm) P Weight (kg) EN.indd version 07 11
14 Handling instructions Land packaging Functional Unit Ocean shipment packaging Functional unit Cubicles packed by threes Handling using a sling FU with circuit-breaker 12 version EN.indd
15 Handling instructions Handling by rolling Storage Store the devices in their original packaging, placed on dry ground or on a material insulating it from humidity. Long storage After long storage, clean insulating parts before operation EN.indd version 07 13
16 Installation and operation recommendation The switchgear s resistance to ageing in an MV substation depends on 3 main factors: 1/ The necessity of correct implementation of connections: New cold retractable or slip-on technology offers ease of installation that favours resistance over time. Their design allows them to used in polluted environments with harsh climatic conditions. 2/ Impact of the relative humidity factor: Installing a heating device is essential in climates with high relative humidity levels and major temperature differences. Ensure that draughts and / or thermal shocks are avoided in all cubicle compartments in order to avoid the creation of dew points (sources of partial discharges). The equipment must be installed in conformity with the relevant IEC standard. Outside of these normal usage conditions, we recommend contacting Schneider Electric to determine the operations to be carried out as well as their frequency according to the actual service conditions. 3/ Electrical room ventilation control: Grid size must be suited to the power dissipated in the substation. These grids must be placed exclusively in the vicinity of the transformer, in order to avoid air circulation on the LV switchboard. Operation and maintenance It is strongly advised to periodically carry out, (minimun every 2 years approximately), a few operation cycles on operating devices. Outside normal conditions of use, (between -5 C and 40 C, absence of dust, corrosive gas, etc.), it is recommended to examine, with our Schneider Electric services center, the steps to be taken, in order to ensure correct operation of the installation. After 6 to 12 month operations, we recommend you to check the busbars and MV cable connection torque. It should be done with a calibrated torque wrench, adjust to lower torque compare to values indicated in page 4. If no issues are detected and if the busbars and cable connections haven t been modified, it will not be necessary to do again this check. In case of disassembly, the elastic contact washers must be changed and replaced by new ones supplied by Schneider Electric. Our service centre is at your disposal at any time: b to diagnose the installation, b to offer, suitable maintenance operations, b to offer maintenance contracts, b to offer adaptations. An MCset 17.5 kv Maintenance and Services guide is available. It gives practical information on: b maintaining the equipment in good operation, b ensuring that the equipment is safe during all installation, repair and service operations. DEAI03EN/ART DEAI03FR/ART b Version 3600 A / 4000 A: We strongly recommend that you clean the ventilation grids A and B regularly (every 2 years): A: standard grids B: grids only on RHB version. b A fan monitoring system must be installed with the cubicle control and monitoring devices. Permanent operation of the following must be guaranteed: Cubicles types Fans quantity 3600 A 4000 A AD3, CL3 1 2 RHB version EN.indd
17 Floor finishing and cubicle fastening Surface condition Floor flatness is such that a 2 meter rule moved over all surfaces and in all directions, does not display a difference of more than 5 mm. Floor quality The floor must have a compression withstand u 33 MPa to roll the extraction tool on it without any damage. Description of irons and accessories Cubicle fastening Take this equipment from the civil engineering package of the switchboard packaging. Standard civil engineering: - 1 iron section A (length 2m) - 4 expansion pins B - 2 fastening shims C. Earthquake resistant civil engineering: - 2 iron sections A (length 2m) - 8 expansion pins B - 4 fastening shims C. Placing and adjusting on non earthquake resistant civil engineering works Preparation Drill a hole in the floor and irons. Placing the irons Place and fix the irons to the floor using the supplied expansion pins, screws and washers. Cut the last iron to the required length EN.indd version 07 15
18 Floor finishing and cubicle fastening Tightening irons Do not bend the iron on installation. Longitudinal adjustment: using a the water level and using shims before tightening the screws. Transversal adjustment: using a the spirit level and using shims before tightening the screws. For the correct installation of cubicles, it is advised to comply with a tolerance of ± 0.2 cm/m and a max. gap of ± 10 mm/10m on the length of the switchboard. 16 version EN.indd
19 Floor finishing and cubicle fastening Placing and adjusting on earthquake resistant civil engineering works Preparation Drill a hole in the floor and irons. This preparation remains an example of anchoring. For seismic applications, the anchorage must be designed and sized for the given installation taking into account the site loads, the floor material and dimensions and the anchorage type. Also, a slab space reserved at the FU is better than a slab space over all civil engineering. Placing the irons Place and fix the irons to the floor using the supplied expansion, screws and washers. Cut the last iron to the required length EN.indd version 07 17
20 Floor finishing and cubicle fastening Tightening irons Do not bend the iron on installation. Longitudinal adjustment: using a the water level and using shims before tightening the screws. The irons must be leveled very well because there is no level adjustement at the back in this case. Transversal adjustment: using a the spirit level and using shims before tightening the screws. For the correct installation of cubicles, it is advised to comply with a tolerance of ± 0.2 cm/m and a max. gap of ± 10 mm/10m on the length of the switchboard. 18 version EN.indd
21 Unpacking cubicles The preparation of cubicles must be carried out on the premises where they will be installed. Remove the 4 handling lugs (1 and 2). To avoid damaging the FU front panel components, leave the protection foam in place until the switchboard is in the operation phase. The circuit-breakers are delivered in cubicles in a racked-out position. Unpack the functional unit by removing the wooden columns (8 screws), then the plastic cover. Remove the cubicle packaging. Placing cubicles in a switchboard Assembling, adjusting and fastening Note: place switchboard cubicles according to front panel drawings and the single-line diagram. Start by placing the cubicle located in the middle of the switchboard (except in the case of an extension of the existing switchboard) then place the cubicles on either side of it, according to the Civil Engineering Guide indications. Depending on the type of civil engineering, take the following from the hardware bags. 1 bag of non earthquake resistant civil engineering screws and bolts n F0: Rear adjustment accessories: A: 4 x HM12 nuts B: 2 quick cage nuts C: 5 flat washers D: 4 x (HM12x70) screws E: 2 support irons. Front fastening accessories: F: 2 hook head bolts G: 2 fastening shims H: rubber anti-vibration plate. 1 bag of earthquake resistant civil engineering screws and bolts n F0: Cubicle «X» must not impede cubicle «X+1» and vis versa with respect to overall dimensions. Depending on the load, if a cubicle is found to be raised after the next one is installed, there is a risk of vibrations. Rear fastening accessories: H: 2 hook head bolts K: 2 fastening shims. Front fastening accessories: H: 2 hook head bolts J: 2 fastening shims EN.indd version 07 19
22 Placing above the maintenance space Do not remove any part of the cubicle. Note: placing can be carried out by lifting or rolling. Placement of the cubicle by rolling. Adjusting cubicles on standard civil engineering works The operations described here after, must only be carried out once the cubicle is positioned on civil engineering works. Position the support steel shim A and the rubber anti-vibration shim B at the rear of the cubicle from the maintenance space. Place the 2 quick cage nuts C at the rear of the cubicle, from underneath the cubicle. Cubicle «X» must not impede cubicle «X+1» and vis versa with respect to overall dimensions. Depending on the load, if a cubicle is found to be raised after the next one is installed, there is a risk of vibrations. Place the lock nut D on each screw E, place washer F, then screw the actuators in the quick cage nuts C. Lift the rear of the cubicle by screwing the 2 screws to level the cubicle. 20 version EN.indd
23 Fastening to the floor on standard civil engineering works Note: if the cubicle is provided with VT s, they must be removed, refer to the operating manual ( ), the chapter on Instructions for access to the interior of a cubicle. Pick from the hardware bag. Place the screws at the front of the cubicle and tighten them. Fastening to the floor one earthquake resistant civil engineering works Note: if the cubicle is provided with VT s, they must be removed, refer to the operating manual ( ), the chapter on Instructions for access to the interior of a cubicle. Pick from the two hardware bags. Place the screws at the rear of the cubicle and tighten them. Cubicle «X» must not impede cubicle «X+1» and vis versa with respect to overall dimensions. Depending on the load, if a cubicle is found to be raised after the next one is installed, there is a risk of vibrations. Pick from the two hardware bags. Place the screws at the front of the cubicle and tighten them EN.indd version 07 21
24 Coupling of cubicles Installing the inter cubicle gasket Note: for a first generation switchboard extension, consult the installation manual ( ) First generation switchboard extension. Place the self-adhesive inter cubicle gasket along the full height of the right side of the cubicle, except on the top wireway of the cubicle. This operation is not necessary for the cubicle at the right extremity of the switchboard. Install the second cubicle on the flloor as descrivbed before. Level the second cubicle if provided with leveling screws. Assemble the 2 cubicles together (11 fastening points). Access to the fastening points: - Refer to chapter on Instructions for access to the interior of a cubicle in the operating manual ( ). - See Removing the mobile part transportation devices. Assembling cubicles The lifting rings and its associated cage nuts must be removed. A: assembly of HM8 x 30 screws + M8 washers and HM8 nut. B: assembly of HM8 x 16 screws + M8 washers and M8 cage nuts. C: assembly of HM6 x 16 screws + M6 washers and HM6 nut + M6 washers. AFLR Internal Arc option: D: assembly of 6 screws H M8 + M8 washers + HM8 nuts + M8 washers. 22 version EN.indd
25 Assembling a MOTORPACT cubicle / MTP transition enclosure Left-hand assembly Right-hand assembly Implementation: 1: disassemble the transition enclosure E front and rear panel 2: open the top and bottom front doors of the Motorpact 3: remove the central front cover D of MOTORPACT by removing the 4 screws 4: remove the rear panels of the MOTORPACT compartments: see manual ( B), Installation guide 5: install screws A, nuts B and washers E as shown EN.indd version 07 23
26 Rack-in check Each time a cubicle is linked to another one, check that the mobile can be racked-in and locked in position properly. For the insertion and rack-in of the mobile part as well as to open the door, refer to the operating manual ( ) in the chapter on Operating instructions. Removing the mobile part transport fixations To extract the mobile part and to open the door, refer to operating manual in the chapter on Operating instructions. The operations described here after, must only be carried out once the cubicle has been placed and secured on the floor. Do not operate the mobile parts before removing the transport fixations. On LF circuit breaker 1: remove the 2 transport fixations (3 screws per fixation) 2: place the 4 screws and washers to fix the CB front cover. Tightening torque: 8.5 Nm. 3: remove the warning label: On a ROLLARC/ CTV1 contactor 1: remove the 2 transport fixations (3 screws per fixation) 2: place the 4 screws and washers to fix the CB front cover. Tightening torque: 8.5 Nm. 3: remove the warning label: On an EVOLIS circuit-breaker 1: remove the front panel screws 2: extract the circuit breaker (out of the cubicle) 3: remove the top fixation with access via the LV compartment 4: remove the fixation circuit breaker. Tightening torque: 8.5 Nm. 5: remove the warning label: 24 version EN.indd
27 On an EVOLIS HP circuit breaker 1: remove the 3 transport fixations (3 screws for the lower fixation and 3 screws for the upper fixation) 2: place the 6 scrwes and washers to fix the CB front cover. Tightening torque: 8.5 Nm. 3: remove the warning label: Installing the main earth connection From the switchboard to the building s earth Note: during the installation of the end sheets, punch the knock-outs from the sheets. For a switchboard with a MOTORPACT cubicle at the end, refer to MOTORPACT installation manual ref Connect the earth bar to the building s earth at the end of the switchboard, on the right and on the left, place the specific link with the oblong hole inside the cubicle. Tighten with a torque of 28 Nm EN.indd version 07 25
28 Inter-cubicles MCset - MCset and MCset - Transition Enclosure MTP Note: this connection can be done during the installation of each cubicle or at the end of switchboard assembly. The connection is located at the base of the cubicle Pick the self adhesive gasket from the hardware bag. Place this gasket around the link. Install the link by sliding it from cubicle 2 to cubicle 1. Place the bolt and tighten it. Use only screws HM8x Nm tightening torque. Stick the gasket onto the cubicle sheet as shown in A. Inter-cubicles Transition enclosure MTP - Motorpact The connection is located in the middle of the cubicle. The transition enclosure earth link is installed at the factory. When connecting it to the Motorpact, simply screw the transition enclosure earth link onto the earth bar inside the Motorpact. 26 version EN.indd
29 Installing the electric connections of the busbars and MV cables General information Assemblies with bolts for MV and LV internal equipment. Screws and bolts to be used: Class 8.8 according to standard NF E , i.e. an elastic limit, Re 630 MPa. Connection maintenance: During downtime, check the connection torque with a torque wrench. In the case of disassembly, change the elastic washers. Note: to carry out the following preliminary switchboard operations see chapter Instructions for access to the interior of a cubicle. Cubicle AD and CL without VT Preliminary operations to be carried out Extraction of the mobile part Placing busbars Placing MV cables (Optional) Close the earthing switch Remove the front panel protective cover plates Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment. (Optional) Remove the busbar access sheet Remove the manhole sheet Cubicle AD and CL with fixed VT Preliminary operations to be carried out Extraction of the mobile part Placing busbars Placing MV cables Close the earthing switch (Optional) Remove the front panel protective cover plates Remove the fixed VTs Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment. (Optional) Remove the busbar access sheet Remove the manhole sheet EN.indd version 07 27
30 Cubicle AD and CL with withdrawable VT Preliminary operations to be carried out Extraction of the mobile par Placing busbars Placing MV cables (Optional) Withdraw the VT fuses Close the earthing switch Remove the front panel protective cover plates Remove the withdrawable VTs Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment. (Optional) Remove the busbar access sheet Remove the manhole sheet TT cubicle with fixed VTs Preliminary operations to be carried out Remove the front panel protective cover plates Placing busbars Placing MV cables Remove the fixed VTs Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment. (Optional) Remove the busbar access sheet Remove the manhole sheet TT cubicle with withdrawable VT Preliminary operations to be carried out Withdraw VT fuses Placing busbars Placing MV cables Close the earthing switch Remove the front panel protective cover plates Remove withdrawable VTs Remove the separation plate from between the switchgear compartment (moving part) and the cable compartment. (Optional) Remove the busbar access sheet Remove the manhole sheet 28 version EN.indd
31 Installing busbars This connection is done during the installation of each cubicle. Access the busbars through the cubicle side. If this is not possible, access through the interior of the cubicle (refer to chapter on Instructions for access to the interior of a cubicle ). Retrieve; - The main busbar in the cubicle packaging - The busbar shims and hardware bag in the cubicle packaging. Place the busbar between the 2 previously assembled cubicles (refer to chapter on Principle of assembling busbars ). Tighten the fixation screws from the head side. 50 Nm tightening torque. Repeat these operations each time a switchboard cubicle is placed. Principle of assembling busbars 1250 A busbars Bag of 1250 A busbars: F0. A: top view of busbars B: 1 x (100 x 8) bar per phase C: nut D: conical contact washer E: flat washer F: M10 x 40 screws EN.indd version 07 29
32 2500 A busbars Bag of 2500 A busbars: F0. A: top view of busbarss B: 2 x (100 x 8) per phase C: nut D: conical contact washer E: flat washer F: M10 x 55 screws G: 3 holes shim H: 6 holes shim. Evolis HP 3150 A busbars Bag of 3150 A busbars: FA. A: top view of busbarss B: 4 riser busbars C: 3 x (100 x 8) per phase D: nut E: conical contact washer G: M10 x 85 screws. 30 version EN.indd
33 3150 A busbars Bag of 3150 A busbars: F0. A: top view of busbarss B: 3 x (100 x 8) per phase C: nut D: conical contact washer E: flat washer F: M10 x 70 screws G: 3 holes shim H: 6 holes shim. Evolis HP 4000 A busbars Bag of 4000 A busbars: FA. A: top view of busbarss B: 4 riser busbars C: 4 x (100 x 8) per phase D: nut E: conical contact washer F: flat washer G: M10 x 85 screws H: 3 holes shim EN.indd version 07 31
34 4000 A busbars Bag of 4000 A busbars: F0. A: top view of busbars B: 4 x (100 x 8) per phase C: nut D: conical contact washer E: flat washer F: M10 x 85 screws (special) G: 3 holes shim H: 6 holes shim. 32 version EN.indd
35 Cover assembly principle (depending on needs) Assembly the covers with clips Retrieve: from the cubicle packaging, the covers. Note: for mounting the covers with wire ties, see page 35. Place the half-covers on the main busbar connections. Close the covers on the bars. Installing busbars between MTP and the MOTORPACT cubicle 1250 A busbars MOTORPACT to the right A: nut B: contact washer C: flat washer D: M10 x 40 screws E: 1 x (76 x 9,5) per phase F: 2 holes shim G: M10 x 60 screws H: 1 hole shim. MOTORPACT to the left Note: for phase 3, the connection bar on the transition enclosure side is fastened to an insulator support EN.indd version 07 33
36 2500 A busbars A: nut B: contact washer C: flat washer D: M10 x 55 screws E: 2 x (76 x 9,5) per phase F: 1 hole shim G: M10 x 70 screws. MOTORPACT to the right MOTORPACT to the left Note: for phase 3, the connection bar on the transition enclosure side is fastened to an insulator support A busbars A: nut B: contact washer C: flat washer D: M10 x 70 screws E: 3 x (76 x 9,5) per phase F: 1 hole shim G: M10 x 80 screws. MOTORPACT to the right MOTORPACT to the left Note: for phase 3, the connection bar on the transition enclosure side is fastened to an insulator support. 34 version EN.indd
37 Optional insulated busbars MTP - Top views Assembling the covers: A: install a wire tie around the busbar, inside the cover (used to block the cover in position) B: close the cover with wire ties C: close the cover with the clips D: fit the entire cover assembly with clips. For cover assembly, refer to the chapter Cover mounting principle. Assembly of the covers with wire ties Position the half-covers on the busbar connection. Close the covers on the bars by tightening the wire ties through the notches EN.indd version 07 35
38 Placing MV cables on AD cubicle General information An explanation is given for all types of cables. Retrieve: from the cubicle packaging, floor plates, cable support and hardware bag. A: 3 single-pole cables B: 1 three-pole cable. To access the interior of a cubicle (refer to the operating manual chapter on Instructions for access to the interior of a cubicle ) Cut cable glands according to the number and diameter of cables. Install them around the cables. Refer to manufacturer instructions for cable termination. MV cable maintenance on AD cubicle Successively assemble, after having installed a row of cables: - Cable support - Flanges - Floor plates. Fix the flange support under the floor, after placing the cables vertical to their attachment bracket. Position the cable and its grommet correctly between the sheets (A). Fix and press the flange support against the cable under the cubicle floor. Only qualified personnel are to perform cable terminations and cable installation. Workers must be aware and understand the hazards involved in working with medium voltage circuits. Neglecting fundamental installation requirements may lead to personal injury, as well as damage to electrical equipment or other property. Block the cables with half-flanges. Make sure that the cable dielectric insulation does not contact any grounded metal parts or other phases. The grounded metallic support must be in contact with the external protective cable sheath. Reassemble bottom plates. Fill in the openings that have not been used with uncut cable glands. 36 version EN.indd
39 Cable termination height Type of cubicle Configuration H (mm) AD1 - AD2 630 A LV toroids set of 3 CTs sets of 3 CTs A LV toroids set of 3 CTs sets of 3 CTs 438 AD A 1 set of 3 CTs sets of 3 CTs A 1 set of 3 CTs sets of 3 CTs A 1 set of 3 CTs A/ 4000 A 1 set of 3 CTs 653 Surge arrester Removing In the case of an AD1 or AD2 cubicle fitted with a surge arrester, access to the cable compartment through the front requires removal of the surge arrester assembly. 1: remove the surge arrester connection 2: remove the insulator support. Installing Carry out the operations in the reverse order of removal. Tightening torque B: 50 Nm E: 20 Nm EN.indd version 07 37
40 Single-pole or three-pole cable without toroid TC AD1 and AD2, 1, 2 or 3 cables per phase Drill a hole in bracket A according to the cable head to be connected. Place and fix bracket A. An explanation is given for one phase. Do the same for the two other phases. Retrieve: in the cubicle packaging, the bracket and the hardware. Connect the cables. Apply standard tightening torque depending on the diameter of the bolt. The cable support is installed after the row of cable is installed (see chapter on MV cable maintenance on AD cubicle ). Dielectric tests must be carried out before connecting the surge arresters. B: 50 Nm tightening torque. Note: assembly sequence of the bolts for the bracket: 1: M10 x 30 screws 2: M10 washer 3: M10 nuts. For the connection of surge arresters, refer to chapter on Surge arresters. Place and fix brackets A, C and D. B: 50 Nm tightening torque. Connect the cables. Apply standard tightening torque depending on the diameter of the bolt. The cable support is installed after the row of cable is installed (see chapter on MV cable maintenance on AD cubicle ). Dielectric tests must be carried out before connecting the surge arresters. For the connection of surge arresters, refer to chapter on Surge arresters. AD3, 1 to 4 cables per phase Remove the bars. Drill a hole in the bars according to the cable heads to be connected. 38 version EN.indd
41 Put back the bars with new washers. Install the cable lugs inside the bars and place the screw head outside the bars. Apply standard tightening torque depending on the diameter of the bolt. A: screw B: washer C: nut D: lug. Dielectric tests must be carried out before connecting the surge arresters. For the connection of surge arresters, refer to chapter on Surge arresters. Tightening torque: B: 50 Nm E: 20 Nm. AD A/ 4000 A up to 8 cables per phase Remove the bars. Drill a hole in the bars according to the cable heads to be connected. Put back the bars with new washers. Install the cable lugs inside the bars and place the screw head outside the bars. Apply standard tightening torque depending on the diameter of the bolt. A: screw B: washer C: nut D: lug. Dielectric tests must be carried out before connecting the surge arresters. For the connection of surge arresters, refer to chapter on Surge arresters. Tightening torque: B: 50 Nm E: 20 Nm EN.indd version 07 39
42 Single-pole cable with toroid CT on cubicle AD1 and AD2 AD1 and AD2, 1 or 2 cables per phase The explanation is given for one phase. Do the same for the two other phases. Retrieve: in package of the cubicle packaging, links A and hardware. Drill a hole in link A according to the cable head to be connected. Place and fix link A. 50 Nm tightening torque. Note: assembly sequence of the bolts for the link: 1: M10 x 30 screws 2: M10 washers 3: M10 nuts. AD1 1 cable per phase Place phase 2 cable in the toroid. The explanation is given for one phase. Do the same for the two other phases. Note: assembly sequence of the bolts for the cable heads: 1: M10 x 30 screws 2: M10 washers 3: M10 nuts. Connect the cables on the link. Apply standard tightening torque depending on the diameter of the bolt. The cable support is installed after the row of cable is installed (see chapter on MV cable maintenance on AD cubicle ). AD2 1 cable per phase Place the cables through the toroids. 40 version EN.indd
43 Note: assembly sequence of the bolts for the cable heads: 1: M10 x 30 screws 2: M10 washer 3: M10 nuts. Connect the cables. Apply standard tightening torque depending on the diameter of the bolt. Dielectric tests must be carried out before connecting the surge arresters. After having installed a row of cables, then assemble the support flange (see chapter on MV cable maintenance on AD cubicle ). AD2 2 cables per phase AD3 2 cables per phase Place the cables through the toroids. Note: assembly sequence of the bolts for the cable heads: 1: M10 x 30 screws 2: M10 washer 3: M10 nuts. Connect the cables. Apply standard tightening torque depending on the diameter of the bolt. Dielectric tests must be carried out before connecting the surge arresters. After having installed a row of cables, then assemble the support flange (see chapter on MV cable maintenance on AD cubicle ) EN.indd version 07 41
44 Placing MV cables on RHC cubicle General information An explanation is given for all types of cables. Retrieve: from the cubicle packaging, floor plates, cable support and hardware bag. A: 3 single-pole cables B: 1 single-pole cable. To access the interior of a cubicle (refer to the operating manual chapter on Instructions for access to the interior of a cubicle ) Cut cable glands according to the number and diameter of cables. Install them through the cables. Refer to manufacturer instructions for cable termination. MV cable maintenance on RHC cubicle Successively assemble, after having installed a row of cables: - Cable support - Flanges - Cables glands plates. Fix the cable support to the roof after the cables are well placed vertically. See chapter on MV cable maintenance on AD cubicle ) for installation instructions. 42 version EN.indd
45 Single-pole or three-pole cable without toroid TC RHC A, RHC1 and RHC2 1, 2 or 3 cables per phase An explanation is given for one phase. Drill a hole in bracket A according to the cable head to be connected. Place and fix bracket A. Do the same for the two other phases. Retrieve: in the cubicle packaging, the bracket and the hardware bag. Place and fix brackets A and C. B: 50 Nm tightening torque. Connect the cables. Apply standard tightening torque depending on the diameter of the bolt. The cable support is installed after the row of cable is installed (see chapter on MV cable maintenance on RHC cubicle ). Note: assembly sequence of the bolts for the bracket fixation: 1: M10 x 30 screws 2: M10 washer 3: M10 nuts. Dielectric tests must be carried out before connecting the surge arresters. For the connection of surge arresters, refer to chapter on Surge arresters. RHC A and RHC2 4 cables per phase An explanation is given for one phase. Drill a hole in bracket A according to the cable head to be connected. Place and fix bracket A. Do the same for the two other phases. Retrieve: in the cubicle packaging, the bracket and the hardware bag. Place and fix brackets A. B: 50 Nm tightening torque. Connect the cables. Apply standard tightening torque depending on the diameter of the bolt. The cable support is installed after the row of cable is installed (see chapter on MV cable maintenance on RHC cubicle ). Note: assembly sequence of the bolts for the bracket fixation: 1: M10 x 30 screws 2: M10 washer 3: M10 nuts. Dielectric tests must be carried out before connecting the surge arresters. For the connection of surge arresters, refer to chapter on Surge arresters EN.indd version 07 43
46 RHC A 4 cables per phase Remove the bars. Drill a hole in the bars according to the cable heads to be connected. Put back the bars with new washers. Install the cable lugs inside the bars and place the screw heads outside the bars Apply standard tightening torque depending on the diameter of the bolt. A: screw B: washer C: nut D: lug. RHC A up to 8 cables per phase Remove the bars. Drill a hole in the bars according to the cable heads to be connected. Put back the bars with new washers. Install the cable lugs inside the bars and place the screw head outside the bars. Apply standard tightening torque depending on the diameter of the bolt. A: screw B: washer C: nut D: lug. 44 version EN.indd
47 Single-pole cable with toroid TC RHC1 1or 2 cables per phase An explanation is given for one phase. Do the same for the two other phases. Drill a hole in bracket A according to the cable head to be connected. Place and fix bracket A. Retrieve: in the cubicle packaging, the bracket and the screws and bolts. Place and fix brackets A. B: 50 Nm tightening torque. Connect the cables. Install the cable lugs inside the bars and place the screw head outside the bars. Note: assembly sequence of the bolts for the bracket fixation: 1: M10 x 30 screws 2: M10 washer 3: M10 nuts. The cable support is installed after the row of cable is installed.(see chapter on MV cable maintenance on RHC cubicle ). There are three ways of installing the toroids (according to the width of the cubicles): 1: 1 single-pole cable 2: 1 single-pole cable 3: 2 single-pole cables. Dielectric tests must be carried out before connecting the surge arresters. For the connection of surge arresters, refer to chapter on Surge arresters EN.indd version 07 45
48 MV cable screen earthing For single-pole or two-pole toroid CT The braid connection is done inside the cubicle. In all cases, the insulated MV cable screen braids must go through the toroids before connection to the switchboard main earth bar. For zero frequence toroid Example of cable installation: A: 1 three-pole cable 1 cable per phase 3 earthing braids B: 2 three-pole cables 2 cables per phase 6 earthing braids C: 3 single-pole cables 1 cable per phase 3 earthing braids D: 6 single-pole cables 2 cables per phase 6 earthing braids. In all cases, the MV cable screen braids must be insulated and go through the zero frequence toroid before connection to the switchboard s earth. The braid earth connection is done on the switchboard earth bars inside the maintenance space. Example: one cable per phase, 3 braids to be connected. Two cables per phase, 6 braids to be connected. 46 version EN.indd
49 LV cable routing and connection Incoming cables at the end of the switchboard Remove the roof on each cubicle (6 screws). Remove the cubicle cable troughs. Place the power supply lead cable inside the trough. Connect the wiring from the power supply lead cable for each cubicle through the cable glands. Place back the trough. Connect the wiring to the terminal blocks. Reassemble the roofing sheets (6 screws per sheet). Incoming cables through the top, each cubicle Remove the small cable sheet on the roof (4 screws) and the roof (6 screws). Cut the cable sheet taccording to the cables size to go through it. Install the cable glands on the sheet and the cables EN.indd version 07 47
50 Install the cable sheet on the roof (4 screws). Connect the wires to the terminal blocks. Install the roof (6 screws). Incoming cables from the floor, each cubicle Remove the cable trough. Cut according to the number and the diameter of the cables. (maximum 5 diameters 20 mm) at the base of the cable trough. Remove the roof and eventually the top cable sheet (6 and 4 screws). Pull the wiring and cable up to the cubicle top through the troughs. Install the cable trough. Connect the wires on the terminal blocks. Reassemble the roof (6 and 4 screws per sheet). 48 version EN.indd
51 Installing the tunnel Wall-mounted anti arc tunnel A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. 1/ First fix the angle bracket (2) on the wall using two screws. 2/ Fix the sheet (1) onto the cubicle using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3. 3/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 4/ Fix the roof (3) on the angle bracket (2) using two screws (C). 5/ Fix the tunnels of each cubicle together. Non wall mounted anti arc tunnel A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. 1/ First fix the sheets (1) onto the cubicle using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3. 2/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 3/ Fix the tunnels of each cubicle together EN.indd version 07 49
52 Wall-mounted anti arc tunnel for versions 3600 A / 4000 A Wall-mounted anti arc tunnel A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. 1/ First fix the angle bracket (2) on the wall using two screws. 2/ Fix the sheet (1) onto the ventilation box using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3. 3/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 4/ Fix the roof (3) on the angle bracket (2) using two screws (C). 5/ Fix the tunnels of each cubicle together. Non wall mounted anti arc tunnel for versions 3600 A / 4000 A A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. 1/ First fix the sheet (1) onto the ventilation box using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3. 2/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 3/ Fix the tunnels of each cubicle together. 50 version EN.indd
53 Installing a tunnel on a MTP transition enclosure The sheets are fixed by HM6 screws + M6 washers and HM6 nuts (A): 1/ Mount the support sheets (1) first. 2/ Mount the side panel (2). 3/ Fasten together the support sheets of each cubicle. 4/ Mount the roof (3). 5/ Mount the tunnel closing sheets in the front and rear (4). 6/ Fasten together the tunnel roofs of each cubicle EN.indd version 07 51
54 Installing the IPX1/IPX2 roofs or anti arc IPx1/IPx2 tunnels Wall-mounted IPX1 roof A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. D: HM6 screws + M6 sealing washers and HM6 nuts. 1/ First fix the angle bracket (2) on the wall using two screws. 2/ Fix the sheet (1) onto the cubicle using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3. 3/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 4/ Fix the roof (3) on the angle bracket (2) using two screws (C). 5/ Fix the tunnels of each cubicle together using 5 screws according to the vue (D). Non wall-mounted cubicle IPX1 roof A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. D: HM6 screws + M6 sealing washers and HM6 nuts. 1/ First fix the sheets (1) onto the cubicle using four screws (B) for MCset 1 and six screws (B) for MCset 2 and MCset 3 for each sheet. 2/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 3/ Fix the tunnels of each cubicle together using 5 screws according to the vue (D). 52 version EN.indd
55 Wall-mounted IPX1 roof for versions 3600 A / 4000 A A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. D: HM6 screws + M6 sealing washers and HM6 nuts. 1/ First fix the angle bracket (2) on the wall using two screws. 2/ Fix the sheet (1) onto the ventilation box using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3. 3/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 4/ Fix the roof (3) on the angle bracket (2) using two screws (C). 5/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D). Non wall-mounted IPX1 roof for versions 3600 A / 4000 A A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts D: HM6 screws + M6 sealing washers and HM6 nuts. 1/ First fix the sheets (1) onto the ventilation box using four screws (B) for MCset 1 and six screws (B) for MCset 2 and MCset 3 for each sheet. 2/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 3/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D) EN.indd version 07 53
56 IPX1 roof on a MTP transition enclosure The sheets are fixed with HM6 screws + M6 sealing washers and HM6 nuts (A): 1/ Mount the support sheets (1) first. 2/ Mount the side panel (2). 3/ Fasten the support sheets of each cubicle together. 4/ Mount the roof (3). 5/ Mount the tunnel closing sheets to the front and rear (4). 6/ Fasten the tunnel roof of each cubicle together. Wall-mounted IPX2 roof A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts D: HM6 screws + M6 sealing washers and HM6 nuts. 1/ First fix the angle bracket (2) on the wall using two screws. 2/ Fitxthe sheet (1) onto the cubicle using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3. 3/ Fix the feet (4) onto the cubicle using two screws (B). 4/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 5/ Fix the roof (3) on the feet (4) using two screws (C) and on the angle bracket (2) using two screws (C). 6/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D). 54 version EN.indd
57 Non wall-mounted IPX2 roof A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. D: HM6 screws + M6 sealing washers and HM6 nuts. 1/ First fix the sheets (1) onto the cubicle using four screws (B) for MCset 1 and six screws (B) for MCset 2 and MCset 3 for each sheet. 2/ Fix the feet (4) onto the cubicle using two screws (B). 3/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 4/ Fix the roof (2) on the feet (4) using two screws (C). 5/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D). Wall-mounted IPX2 roof for versions 3600 A / 4000 A A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. D: HM6 screws + M6 sealing washers and HM6 nuts. 1/ First fix the angle bracket (2) on the wall using two screws. 2/ Fix the sheet (1) onto the ventilation box using four screws (B) for MCset 1 and 6 screws (B) for MCset 2 and MCset 3. 3/ Fix the feet (4) onto the cubicle using two screws (B). 4/ Fix the roof (3) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 5/ Fix the roof (3) on the feet (4) using two screws (C) and on the angle bracket (2) using two screws (C). 6/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D) EN.indd version 07 55
58 Non wall-mounted IPX2 roof for versions 3600 A / 4000 A A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. D: HM6 screws + M6 sealing washers and HM6 nuts. 1/ First fix the sheets (1) onto the ventilation box using four screws (B) for MCset 1 and six screws (B) for MCset 2 and MCset 3 for each sheet. 2/ Fix the feet (3) onto the cubicle using two screws (B). 3/ Fix the roof (2) onto the sheet (1) using two screws (C) for MCset 1 and three screws (C) for MCset 2 and MCset 3. 4/ Fix the roof (2) on the feet (4) using two screws (C). 5/ Fix the tunnel of each cubicle together using 5 screws according to the vue (D). IPX2 roof on a MTP transition enclosure The sheets are fixed by HM6 screws + M6 sealing washers and HM6 nuts (A): 1/ Mount the support sheets (1) first and the feet (5). 2/ Mount the side panel (2). 3/ Fasten the support sheet of each cubicle together. 4/ Mount the roof (3). 5/ Mount the tunnel closing sheets at the front and rear (4). 6/ Fasten the tunnel roof of each cubicle together. 56 version EN.indd
59 Tunnel sheets or IPX1/IPX2 roofs for RHB cubicle 1/ Mount first the support sheets (1) at the rear first, then in the middle and the front feet (front feet are only used for IPx2 roofs) (3c). 2/ Mount the sheets (2) on the RHB duct part. 3/ Fasten the support sheet of each cubicle together. 4/ Mount the tunnel roof (3a) or the IPX1 roof (3b) or the IPX2 roof (3c). 5/ Fasten the tunnel roofs of each cubicle together. * Ventilation boxes for version 3600 A / 4000 A. Tunnel sheets or IPX1/IPX2 roofs for RHC cubicle 1/ Mount first the support sheets (1) at the rear first, then in the middle, and the front feet (front feet are only used for IPx2 roofs) (3c) 2/ Mount the access sheets (4). 3/ Fasten the support sheet of each cubilce together. 4/ Mount the tunnel roof (3a) or the IPX1 roof (3b) or the IPX2 roof (3c). 5/ Fasten the tunnel roofs of each cubicle together EN.indd version 07 57
60 Installing the tunnel end sheets For anti-arc tunnels or IPx1 roofs A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. 1/ First fix the sheet (1) onto the cubicle with the screws (C). 2/ Fix the sheet (1) onto the tunnel with the screws (C). For anti arc tunnel for version 3600 A/ 4000 A A: front of the cubicle B: HM6 screws C: HM6 screws + M6 washers and HM6 nuts. 1/ First fixthe sheet (1) onto the cubicle with the screws (C) 2/ Fix the sheet (1) onto the tunnel with the screws (C). 58 version EN.indd
61 For IPx2 roofs A: front of the cubicle B: rear of the cubicle The sheets are fixed with HM6 screws + M6 washers and HM6 nuts. 1/ Fix the sheet (1) onto the cubicle and onto the tunnel 2/ Fix the sheet (2) onto the tunnel feet at the front. 3/ Fix the sheet (3) onto the cubicle, the tunnel and the sheet (1). 4/ Fix the sheet (4) onto the sheet (1) EN.indd version 07 59
62 Installing the end sheets On the left end cubicle, place the cage nuts on the sides. For internal arc switchboards, stick the self adhesive gasket (A) along the front of the switchgear for both end sheets Note: operations are identical for the right or left ends of the switchboard. Make sure that the busbar end cover is assembled before mounting the switchboard s end covers. On the left and right end cubicles, place and screw (M8 screw) the 4 end sheet support beams. Assembling cover panels of cubicle ends Punch the knock-out at the panel bottom to let the earth bus to go through it (1 per panel). 60 version EN.indd
63 Note: operations are identical for the right or left ends of the switchboard. On the right end panel, place the cage nuts at the front line. Assemble the end cover panels 1 and 2 (right and left end of the switchboard). A: HM8 screws+ M8 washers B: HM6 screws+ M6 washers D: assembly of HM8 x 30 screws + M8 washers and HM8 nut + M8 washers EN.indd version 07 61
64 Wall-mounted switchboard D: assembly of HM8 x 30 screws + M8 washers and HM8 nut + M8 washers. Internal arc switchboard. D: assembly of HM8 x 30 screws + M8 washers + HM8 nut + M8 washers. E: assembly of HM8 x 6 screws + M8 washers + HM8 nuts + M8 washers. Place the top wireway closing sheet 4. Place the two screws to fix the top wireway closing sheet. 62 version EN.indd
65 Pop the 2 rivets to fix the operating handle support at the front of the end sheets. Store the operating handle in the front end panel. Installing fans on versions 3600 A / 4000 A Top view Fasten the box using 10 screws A. Connect the wiring in top wireway B of the cubicle. Maintenance procedures for ventilations and insulating parts are covered in the MCset 17.5 kv Maintenance and Services Guide DEAI03F/ART RHB EN.indd version 07 63
66 Installation of a FU equipped with electromagnetic locking options Earthing switch with electromagnetic locking FU delivered with the earthing switch closed To rack-in and rack-out the circuit breaker, the earthing switch must be operated. At the installation of the FU, the electromagnetic locking is not yet enegised, it must be manually released in order to operate the earthing switch. Initial status: - The earthing switch is closed, - Selector 4 is in the locked closed position. Opening the earthing switch without auxiliary supply Disassemble the VPIS without disconnecting the wiring. Insert a screwdriver via the box hole. Push back and hold in place the electromagnet (A) using the screwdriver, then pull towards you and turn the selector to the right in the operation position. Open the earthing switch, inserting the crank in reference 5 until the mechanical indicator light changes status. Position selector 4 in the locked open position. Put back the VPIS. 64 version EN.indd
67 Installation of a FU equipped with electromagnetic locking options Rack-in prevention with electromagnetic locking Initial status: - The circuit-breaker is in the racked-out position. - The earthing switch is closed. - The front panel is disassembled to access cable connections. To access the cable connection compartment, circuit-breaker rack-in must be prevented. At the installation of the FU, the electromagnetic lock is not energised, it must be manually released in order to place the front panel when the operations are complete. The locking system is accessible as per the arrow in the drawing opposite. Prior to installing the front panels If lever (A) is positioned as per figure 1, locking is active and prevents installation of the front panel. To desactivate the locking, insert a tool (screwdriver) into the hole placed under the box support and push the electromagnet rod (B). Push the lever (A) to position it as per figure 2. The system is released and the front panel can be placed back. Figure 1 Figure EN.indd version 07 65
68 Steps to be taken for tests and inspection Power frequency dielectric test This test must be performed by trained & authorized people. This test can be carried out in one single operation. All circuit-breakers must be racked-in, closed, with FU doors open. All the VT s and surge arresters must be disconnected during this test. More over, one of the FU feeder must have its lower panel open to connect the test cable. This procedure requires to defeat the interlocks. It is essential to follow the sequences here after. The insulation level of the switchgear can be tested on site. The test voltage shall be 80 % of the rated shortduration power-frequency withstand voltage of the switchgear as specified in clause of IEC Defeating Interlocks On FUs not connected to the generator Place the circuit-breaker in the test position, with the door open. Rack-in the circuit breaker (refer to the operating manual). Remove the shim. Raise and block the door lock rod using a 55 mm U shim. Press the pushbutton I to close the circuit-breaker Surge arrester connection This operation must only be carried out after dielectric tests, and before the connection of medium voltage cables to the FU. Place and fix the connection of each surge arrester. Refer to the chapter on MV cable connection. 66 version EN.indd
69 Tests on site Checking and setting up the internal arcing detector(1) This operation has to be made during assembly of the tunnels (option) or during operation on the roof of the cubicle. The internal arcing detector is located on the roof of the cubicle. To be operational, it must be in spring loaded position. (1) The internal arcing detector is mounted according to the internal arcing withstand characteristics of the cubicle. Setting up the internal arcing detector: - Push the metal rod (1) toward the back of the cubicle, - Hook the rod (1) on the support (2). 1: metal rod, 2: support EN.indd version 07 67
SM6. installation instructions. internal arc 16kA. 1s. addition to the standard cell user s instructions
SM6 Anglais MV distribution factory built assemblies at your service installation instructions internal arc 16kA. 1s addition to the standard cell user s instructions foreword... 3 symbols and conventions...
More informationPickup Box Utility Rack Package Installation (Instruction ID: )
017 Chevrolet Colorado Pickup - WD (VIN S) Canyon, Colorado Accessory Installation Manual N America Document ID: 3966961 Pickup Box Utility Rack Package Installation (Instruction ID:3144879) Installation
More informationMerloni Elettrodomestici. Technical Fitting Manual FRIDGE. Language Issue/Edition Page GB /
GB 99-11-03/01 1-38 Index 1 CONFORMITY OF APPLIANCE 3 2 MAIN ASSEMBLY TYPES 3 2.1 Under worktop 3 2.2 Double door 10 2.3 Combined 14 2.4 Single door Fridge or single door Freezer 19 2.5 Combined free-standing
More informationSTOP. V00029AC Rev. 04 READ ALL OF THE FOLLOWING INSTRUCTIONS BEFORE REMOVING CABINET FROM SKID TOOL LIST. NET-ACCESS S-Type Network Cabinets
Rev. 04 STOP READ ALL OF THE FOLLOWING INSTRUCTIONS BEFORE REMOVING CABINET FROM SKID NET-ACCESS S-Type Network Cabinets -Phillips screwdriver -Flatblade screwdriver -22mm socket wrench -15mm socket wrench
More information1 of 2 3/3/2017 4:49 PM
1 of 2 3/3/2017 4:49 PM Front Door Window, Assembly Overview 1 - Window guide - Inserted on flange 2 - Door 3 - Inner window recess seal - Inserted on flange 4 - Bolt - 20 Nm 5 - Carrier assembly - Window
More informationVersion: 1.0 Revised: 6/8/2011. CBU Assembly Instructions Manual
CBU Assembly Instructions Manual Contents 1 General... 3 2 Package... 4 2.1 Packing order... 4 2.2 Unpacking... 5 3 Assembly of the body... 6 3.1 General... 6 3.2 Mounting base drilling chart... 8 3.3
More information3.2.3 Rear Door Window and Quarter Window Carrier Assembly
Tighten all bolts. Tighten bolts marked -1- and -2- in specified sequence. Tightening torque: 8 Nm Remaining bolts can be tightened in any sequence. Insert door window -3- through window recess without
More information5/2 Introduction. Unequipped Distribution Boards 5/4 Modular distribution boards 5/5 Add-on parts
ALPHA AS Modular Distribution Boards /2 Introduction Unequipped Distribution Boards /4 Modular distribution boards / Add-on parts Assembly Kits for Unequipped Distribution Boards /6 8GK4 assembly kits
More informationInstallation Instructions Kit, Base Rail Bracket Part # 31413
Installation Instructions Kit, Base Rail Bracket Part # 31413 Dealer / Installer: Provide a copy of these Instructions to the end user of this product. These Instructions provide important operating and
More informationREC Series Rack Installation Guide
REC Series Rack Installation Guide 1 REC Series Rack Installation Guide TABLE OF CONTENTS SECTION SAFETY WARNINGS 1 600 WIDE EXPLODED VIEW 2 800 WIDE EXPLODED VIEW 3 SWITCHING DOOR HANDING 4 STABILIZING
More informationRAMPAGE P R O D U C T S. INSTALLATION INSTRUCTIONS BRONCO ZIPPER FASTRACK TOP PART #984xx BRONCO TOOLS REQUIRED
RAMPAGE P R O D U C T S 84 (+/- 1/4 ) INSTALLATION INSTRUCTIONS BRONCO ZIPPER FASTRACK TOP PART #984xx BRONCO 1966-1977 TOOLS REQUIRED 3/8 WRENCH 7/16 WRENCH ½ WRENCH #2 PHILLIPS SCREWDRIVER 1/8 DRILL
More informationMANUAL e130. Wallstation
MANUAL 07.29.13 e130 Wallstation The Enovate Medical e130 Wallstation was designed to set a new standard in quality. Enovate Medical s goal is to provide a wallstation that is ready for years of use,
More informationRepair manual. Fifth-wheel coupling JSK 38/50
Repair manual Fifth-wheel coupling JSK 38/5 ZDE 199 3 12 E 6/212 1 Foreword Table of contents Page Fifth wheel couplings are connecting parts that must comply with very high safety requirements and must
More informationJEEP JK ( 5 DOOR ) SLIMLINE II - FULL TRAY EXTREME RACK KIT
JEEP JK ( 5 DOOR ) SLIMLINE II - FULL TRAY EXTREME RACK KIT FAJK001 / KRJW014T INSTALL TIME: 2.5 Hours NOTE: Your Jeep JK (5 Door) Extreme Roof Rack Kit consists of four boxes. (1) the Tray, (2) the Roll
More informationArlink 7000 Workstation
Arlink 7000 Workstation Instructions for Assembly Basic Bench Assembly Undersurface Accessories Above Surface Accessories VSI Mounting Instructions Making Workspace Work is a trademark of Lista International
More informationAssembly Instructions
InTandem Table System November 20 InTandem Table System - Worksurface #4 x/" 4 wood screw power beam Tools Provided T-0 Extended Torx Driver T-25 Torx Driver Additional Tools Required Soft protective
More informationService installation of hardtop Installing hardtop
Service installation of hardtop Installing hardtop â Lower side windows as far as they will go. â Retract (if necessary unscrew) radio aerial. â Switch off ignition. â If necessary, remove wind deflector.
More informationInstallation Manual. Arc Chamber
Installation Manual Arc Chamber Installation Manual Introduction Administrative data Issue number: 6082940 G01 01 Date of issue: 25-03-2013 2 Arc Chamber Installation Manual 6082940 G01 01 March 25th 2013
More informationSuper Shot Adjustable Basketball System
Model: GP5A48 Installation, Operation and Maintenance Instructions Please read all instructions before attempting installation or operation of these units SAVE THESE INSTRUCTIONS FOR FUTURE USE PUBLICATION
More informationFront axle components, overview
j a t Front axle components, overview 40-1 General Information Load bearing components and parts of the suspension must not be welded or straightened. Vehicles without drive axle must not be moved, or
More informationConflicts Note: Drop-in Bed liner
Toyota Tundra 2015 LED Bed Lights Preparation Part Number: 00016-34089 Accessory Code: BU1000 Conflicts Note: Drop-in Bed liner Kit Contents Item # Quantity Reqd. Description 1 1 Hardware Kit 2 1 Driver
More informationModular equipment. Presentation, standards. Standard contactors TeSys GC
Presentation, standards Standard contactors TeSys GC Presentation TeSys GC contactors are designed for use in modular panels and enclosures. These contactors feature: b Easy installation v quick clip-on
More informationFifth-wheel coupling JSK 38/50
Repair manual Fifth-wheel coupling JSK 38/5 ZDE 199 3 12 E 6/25 1 LT SK38C-3 English RevA Foreword Table of contents Page Fifth wheel couplings are connecting parts that must comply with very high safety
More informationInstallation instructions, accessories. TV receiver, digital
Installation instructions, accessories Instruction No 30756561 Version 1.1 5 Part. No. 30756181, 30756569 TV receiver, digital Volvo Car Corporation TV receiver, digital- 30756561 - V1.1 Page 1 / 36 Equipment
More informationTOYOTA TACOMA LED BED LIGHTS Preparation
Preparation Part Number: PT948-35160 Kit Contents Item # Quantity Reqd. Description 1 1 Hardware Kit 2 1 Driver Side LED assembly 3 1 Passenger Side LED assembly 4 1 Main Wire Harness Hardware Bag Contents
More informationMOUNTING INSTRUCTIONS CONCRETE PURLIN BRACKET
CONCRETE PURLIN BRACKET VERSION MARCH 2015 GENERAL INSTRUCTIONS Safety: Systems may only be installed and operated by properly trained and technically suitable people (i.e. MCS accredited installers).
More informationElectrical Power Distribution Low-Voltage Systems SIVACON 8PS busbar trunking systems Installing with LI system
Introduction 1 Application planning 2 Electrical Power Distribution Low-Voltage Systems SIVACON 8PS busbar trunking systems Installation Manual Installation 3 Commissioning 4 Service and maintenance 5
More informationJEEP JK ( 3 DOOR ) SLIMLINE II - FULL TRAY EXTREME RACK KIT
JEEP JK ( 3 DOOR ) SLIMLINE II - FULL TRAY EXTREME RACK KIT FAJK004 / KRJW016T INSTALL TIME: 2 Hours NOTE: Your Jeep JK (3 Door) Extreme Roof Rack Kit consists of four boxes. (1) the Tray, (2) the Roll
More informationType XTSR71 Sizes
(Page 1 of 13) s 494-5258 Type XTSR71 s 494-5258 Figure 1 Thomas XTSR71 Coupling 1. General Information 1.1 Thomas Couplings are designed to provide a mechanical connection between the rotating shafts
More informationMedia Storage Systems Fixed Media Cabinets
Owner s Manual Media Storage Systems Fixed Media Cabinets Contents 1-Column Fixed Media Storage Cabinet Important User Information...........................2 Safety Precautions.................................3
More informationINSTALLATION INSTRUCTIONS FOR PLASCORE NARROW STILE DOORS
INSTALLATION INSTRUCTIONS FOR PLASCORE NARROW STILE DOORS The following information is provided by Plascore, Inc., as a general guideline for the installation of the Plascore Narrow Stile Door and Jamb
More informationJEEP JK ( 5 DOOR ) SLIMLINE II - FULL TRAY EXTREME RACK KIT
JEEP JK ( 5 DOOR ) SLIMLINE II - FULL TRAY EXTREME RACK KIT FAJK002 / KRJW014T INSTALL TIME: 5 Hours NOTE: Your Jeep JK (5 Door) Extreme Roof Rack Kit consists of four boxes. (1) the Tray, (2) the Roll
More informationINSTALLATION INSTRUCTIONS ATV WINCH MULTI-MOUNT Multi-Mount Mounting-Kit: PN Application: YAMAHA BIGBEAR 00+
INSTALLATION INSTRUCTIONS ATV WINCH MULTI-MOUNT Multi-Mount Mounting-Kit: PN 61025 Application: YAMAHA BIGBEAR 00+ Your safety, and the safety of others, is very important. To help you make informed decisions
More informationELECTRIC SLIP ROLL MACHINE. Model: ESR-1300X2.5/ESR-1300X4.5 ESR-1550X3.5/ESR-1580X2.0
ELECTRIC SLIP ROLL MACHINE Model: ESR-1300X2.5/ESR-1300X4.5 ESR-1550X3.5/ESR-1580X2.0 Operation Manual Table of contents I MAIN SPECIFICATION...2 II SAFETY INSTRUCTIONS.. 2 III OPERATION INSTRUCTIONS..4
More informationV Installation instructions, accessories. Auxiliary seat. Volvo Car Corporation Gothenburg, Sweden V70 (00-08) 2002
Installation instructions, accessories Instruction No 8624018 Version 1.3 Part. No. 30749269, 30749270, 30749271, 30749272, 30749273, 30749274 Auxiliary seat M8901699 Volvo Car Corporation Auxiliary seat-
More informationCentral Inverter SUNNY CENTRAL 200 / 250 / 250HE / 350
Central Inverter SUNNY CENTRAL 200 / 250 / 250HE / 350 Installation Guide SC20_25_35-IEN094521 98-4004821 Version 2.1 EN SMA Solar Technology AG Table of Contents Table of Contents 1 Notes on this Manual..............................
More informationGrowSpan Series 500 Roll-Up Ends
GrowSpan Series 500 Roll-Up Ends Photo may show a different but similar model. Doorframe materials are not included. 2016 Growers Supply All Rights Reserved. Reproduction is prohibited without permission.
More informationWARNING. Failure to observe these instructions could lead to severe injury or death.
INSTALLATION INSTRUCTIONS WINCH MOUNTING KIT Part Number: 80156, 80160 Application: 2008 Ford F150 Your safety, and the safety of others, is very important. To help you make informed decisions about safety,
More informationLAN Locker Adjustable Shelves
Adjustable Shelves LAN LOCKER ADJUSTABLE SHELVES * Adjustable Shelves are available for LAN LOCKER widths: 24, 30, 48, 60, and 72. * When installing more than one Adjustable Shelf, it is recommended that
More informationCW-Type Wall Mounted Cabinets Installation Instructions
Instruction Sheet 860446194 Issue 2, March 2013 CW-Type Wall Mounted Cabinets Installation Instructions General CommScope wall mount cabinets are available in 24-inch (610mm), 36-inch (914mm) and 48-inch
More information4/2 Introduction. Marshaling Boxes 4/8 8GK1 surface-mounting distribution boards
ALPHA 630 - DIN Floor- Mounted Distribution Boards /2 Introduction Unequipped Distribution Boards /5 8GK1 surface-mounting distribution boards, IP3 /6 8GK1 surface-mounting distribution boards, IP55 Marshaling
More informationINSTALLATION & OWNER S MANUAL
Rev. O p. 1 of 16 INSTALLATION & OWNER S MANUAL V4213 BALL CAGE KIT INSTALLATION & OWNER S MANUAL The contents of this envelope are the property of the owner. Be sure to leave with the owner when installation
More informationGared Pro-S Portable Backstop
Models: 9616 & 9618 Installation, Operation and Maintenance Instructions Please read all instructions before attempting installation or operation of these units SAVE THESE INSTRUCTIONS FOR FUTURE USE PUBLICATION
More informationINSTALLATION INSTRUCTIONS
Sheet 1 of 5 General: Upon receipt of fixture thoroughly inspect for any freight damage, which should be brought to the attention of the delivery carrier. Compare the catalog description listed on the
More informationGearBoss II High Density storage
Assembly/Owner s Manual GearBoss II High Density storage contents Safety...........................................2 General......................................2 Installation...................................2
More informationInstalling flat panels on the MPL15 wall mount
Installing flat panels on the MPL15 wall mount The MPL15 (DS-VW775) is a full-service video wall mount that can accommodate tiled LCD panels with up to a 400 x 400 mm VESA pattern in portrait and landscape
More informationRUBBISH CHUTE TECHNICAL NOTE
RUBBISH CHUTE TECHNICAL NOTE HAEMMERLIN - CDH GROUP 28 RUE DE STEINBOURG - BP 30045-67701 1 SAVERNE CEDEX - FRANCE Tel. + 33 (0)3 88 01 85 00 - Fax + 33 (0)3 88 01 85 39 welcome@haemmerlin.com - www.haemmerlin.com
More informationJEEP JK ( 3 DOOR ) SLIMLINE II - FULL TRAY EXTREME RACK KIT
JEEP JK ( 3 DOOR ) SLIMLINE II - FULL TRAY EXTREME RACK KIT FAJK005 / KRJW016T INSTALL TIME: 5 Hours NOTE: Your Jeep JK (3 Door) Extreme Roof Rack Kit consists of four boxes. (1) the Tray, (2) the Roll
More informationETX Powered Loudspeaker Accessories
ETX Powered Loudspeaker Accessories ETX-BRKT10, ETX-BRKT12, ETX-BRKT15, ETX-TCA-S, ETX-TCA-L, and ETX-BRKT35 en Installation Guide en 3 Table of contents 1 Safety 4 2 Installation 6 2.1 Wall mount bracket
More informationCSS Central Mount System
CSS-20 Installation Manual CSS-20 Safety Notifications Below are the installation instructions for the CSS-20-2 Long Span Beam Mounting System. Please read these safety notifications prior to beginning
More informationWHITE - Accessories. Series 500 Greenhouse Kit w/blackout System, Ventilation & Evaporative Cooling
Series 500 Greenhouse Kit w/blackout System, Ventilation & Evaporative Cooling WHITE - Accessories 2016 Growers Supply All Rights Reserved. Reproduction is prohibited without permission. Revision date:
More informationWATERFLUX 3000 Quick Start
WATERFLUX 3000 Quick Start Electromagnetic flowmeter The documentation is only complete when used in combination with the relevant documentation for the signal converter. KROHNE CONTENTS WATERFLUX 3000
More informationInstallation Instructions
Installation Instructions Ceiling Mount Bracket for DLP Based Projectors (for High Ceilings) Model No. ET-PKD100H Contents Important Safety Notice.................. 2 For DLP Based Projector: PT-D10000
More informationTOYOTA TACOMA TRAILER WIRE HARNESS Preparation
Preparation Part Number: PT725-35120 Kit Contents Item Quantity Reqd. Description # 1 1 Flasher Assembly (F/A) 2 1 Wire Harness 3 1 Sub Wire Harness 4 2 Plastic Tie (300mm) 5 4 Plastic Tie (200mm) 6 13
More information-- Gym Glide -- (Recreational Game Standard) Installation Instructions
-- Gym Glide -- (Recreational Game Standard) Installation Instructions Call Jaypro Sports Equipment at 1-800-243-0533 during regular business hours for technical support. www.jaypro.com Rev- Page 1 of
More informationTIRE RACK INSTALLATION INSTRUCTIONS Dodge Sprinter
Aluminess Products Inc 9402 Wheatlands Ct. #A Santee, CA 92071 619-449-9930 TIRE RACK INSTALLATION INSTRUCTIONS 07-11 Dodge Sprinter Please read before beginning Stainless steel hardware may bind together
More informationLOW-PROFILE WALLMOUNT CABINETS
USER MANUAL RMT35X SERIES LOW-PROFILE WALLMOUNT CABINETS 24/7 AT OR VISIT BLACKBOX.COM TABLE OF CONTENTS SAFETY INFORMATION... 3 Receiving, Unpacking, and Removing the Low-Profile Wallmount Cabinet from
More informationFloating Lake Truss Dock Instructions
Table of Contents Floating Lake Truss Dock Instructions 1. Dock Assembly and Set-Up 1.1 Installing Dock Floats 1.2 Positioning Quick Clips 1.3 Installing Anchor Posts 1.4 Installing Docks into the Water
More informationRear Mount Installation Instructions
Rear Mount Installation Instructions Ford Transit Low Roof 130 WB Frame Kit Part #: DTC 0809-011 V1.0.10.12.18 IMPORTANT INSTALLATION STEPS ARE DENOTED USING A STOP SIGN. THESE STEPS MUST BE PERFORMED
More informationTOYOTA TACOMA 2005 TRAILER WIRE HARNESS Preparation
Preparation Part Number: 08921 04960 NOTE: Part number of this accessory may not be the same as the part number shown. Kit Contents Item # Quantity Reqd. Description 1 1 Converter Assembl y 2 1 Wire Harness
More informationCast Resin Transformers
Cast Resin Transformers Installation, use and maintenance manual 07/13-01 PC 2 Cast Resin Transformers Table of contents 1 Safety guidelines 4 2 Reference standards 6 3 Rating plate 6 3.1 Conditions for
More informationArlink 7000 Workstation
Arlink 7000 Workstation Instructions for Assembly Basic Bench Assembly Undersurface Accessories Above Surface Accessories Making Workspace Work is a trademark of Lista International Corporation. Creation
More informationEquilibrium. Conference Table. Installation Instruction. Revision B 11/07/16
Equilibrium Conference Table Installation Instruction Revision B 11/07/16 Equilibrium End User Agreement Enwork Equilibrium table bases must be installed directly onto a four inch minimum thickness concrete
More informationFig. 2 DORMA-Glas Stand/Issue 02/03 Seite/Page 1/7
FSW Installation instructions Track rail 75 x 72 mm 1. Ceiling substructure and installation of the track rail (Fig. 1): The track rail must be bolted over its entire length (including the stacking track
More informationInstallation and Assembly - Universal Articulating Swivel Double-Arm for 42" - 60" Plasma Screens
Installation and Assembly - Universal Articulating Swivel Double-Arm for 42" - 60" Plasma Screens Models: PLAV 70-UNL, PLAV 70-UNL-S PLAV 70-UNLP, PLAV 70-UNLP-S R This product is UL Listed. It must be
More informationPowersafe Termination Guide
Powersafe Termination Guide Contents Index 1. Introduction 2. Overview 3. Termination Methods 3.1 Set screw termination 3.2. Recommended Assembly Procedure for Panel Mounted Connectors 3.3. Crimp Termination
More informationWATERFLUX 3000 Quick Start
WATERFLUX 3000 Quick Start Electromagnetic flow sensor The documentation is only complete when used in combination with the relevant documentation for the signal converter. KROHNE CONTENTS WATERFLUX 3000
More informationROBOT KR 350. Installation, Connection, Exchange. Ro/Me/03/ en. 1of 26
ROBOT KR 350 Installation, Connection, Exchange 1of 26 e Copyright KUKA Roboter GmbH This documentation or excerpts therefrom may not be reproduced or disclosed to third parties without the express permission
More informationCopyright Black Box Corporation. All rights reserved Park Drive Lawrence, PA Fax
Copyright 2003. Black Box Corporation. All rights reserved. 1000 Park Drive Lawrence, PA 15055-1018 724-746-5500 Fax 724-746-0746 JULY 2003 RM3010A RM315-R2 RM323-R2 RM329 RM451 RM457 RM3020A RM316 RM324-R2
More informationInstallation of the JD 900 Series Flex Grain Platform Auger Trough Liner Kit
www.polyskid.com P. O. Drawer 349, Monticello, GA. 31064 Phone: 800-542-7659 Fax: 706-468-2881 E-Mail: polytech@polyskid.com Installation of the JD 900 Series Flex Grain Platform Auger Trough Liner Kit
More informationCBT LW BATCHING SYSTEM 25, 50, 100 & 200 INSTALLATION GUIDE
CBT LW BATCHING SYSTEM 25, 50, 100 & 200 INSTALLATION GUIDE PICTOGRAMS Each Signifier displayed here is specific to this User Manual. Menu Previous Advance Note Tip Example Inspection Bowl & Frame Weigh
More informationTRAKFAST REPAIR MANUAL DANGER TOOL DISASSEMBLY ALWAYS TAKE THE FOLLOWING PRECAUTIONS BEFORE ANY SERVICE OR ROUTING MAINTENANCE IS PERFORMED:
DANGER ALWAYS TAKE THE FOLLOWING PRECAUTIONS BEFORE ANY SERVICE OR ROUTING MAINTENANCE IS PERFORMED: REMOVE FASTENERS REMOVE FUEL CELL REMOVE BATTERY REMOVE THE MAGAZINE ASSEMBLY Loosen and remove knob
More informationFactory Assistance: Phone: Fax: Page 1
CABLE RUNWAY ACCESSORIES Radius Drop / Stringer Drop Provides 3 bend radius Radius drop fits 6, 12 and 18 runway made from 1-1/2 x 3/8 tubing Steel construction Includes (3) cable spools, (1) bolt, (1)
More informationKawasaki Teryx 750 Cab Kit* Caution: Before using this product, read this manual and follow all Safety Instructions.
Owner s Manual Model: Kawasaki Teryx 750 Kawasaki Teryx 750 Cab Kit* Caution: Before using this product, read this manual and follow all Safety Instructions. Safety Instructions Cab Kit Contents Hardware
More informationInstallation Instructions
For Medium (15-18.5K) + Heavy duty (22-28.5K) Air Conditioner READ BEFORE INSTALLING UNIT To avoid risk of personal injury, property damage, or product damage due to the weight of this device and sharp
More informationVinyl Sliding Glass Door Assembly Instructions
Vinyl Sliding Glass Door Assembly Instructions SERIES SGD 5470/5570 Para instrucciones en español, visite: http://bit.ly/pgtassemblyinstructions Parts List ITEM 4 5 6 7 8 9 0 4 5 6 7 8 SGD 5470/5570 PARTS
More informationCAB END BEDTRAX (SIDE VIEW)
Supplied Hardware: (8-14) 1/4-20 Allen head bolts, (12-18) UHMW mount blocks, (4) D-ring tie downs Tools Needed: Allen head wrench GET TO IT. INSTALLATION INSTRUCTIONS STEP 1. INSERT (2) MOUNT BLOCKS INTO
More informationLow-Voltage Power Distribution and Electrical Installation Technology
Busbar trunking system Installation Manual 06/2011 Low-Voltage Power Distribution and Electrical Installation Technology Answers for infrastructure. SIVACON 8PS - Installation with LX system Low-voltage
More informationInstallation Instructions Kit, Base Rail Bracket Part # 31413
Installation Instructions Kit, Base Rail Bracket Part # 31413 Dealer / Installer: End User: Provide a copy of these Instructions to the end user of this product. These Instructions provide important operating
More informationCEILING-MOUNTED MONORAIL ANCHOR TRACK SYSTEM Assembly and Operation Instruction Manual
CEILING-MOUNTED MONORAIL ANCHOR TRACK SYSTEM Assembly and Operation Instruction Manual This manual is for various mounting types and plain and trussed track profiles. ISO 9001:2008 Registered Manual 103-0075
More informationRBP-1215B-RX DODGE RAM QUAD CAB RX3
RBP-1215B-RX3 2002-2017 DODGE RAM 15-3500 QUAD CAB RX3 Passenger side RX-3 Side Step Drill Template Passenger side rear Modular Bracket (6) L Support Brackets Driver side rear Modular Bracket Driver side
More informationINSTALLATION MANUAL FOR KINESIS STATIONS STEP MH67E EQUIPMENT REQUIRED FOR INSTALLATION
1 02/02/2012 INSTALLATION MANUAL FOR KINESIS STATIONS STEP MH67E EQUIPMENT REQUIRED FOR INSTALLATION Phillips screwdriver T wrenches size 5-6-8-10 Combination ratcheting wrench 17 and/or open-end wrench
More informationHOME GYM Owner s Manual
HOME GYM Owner s Manual Content Content-------------------------------------------------------------1 Safety precautions----------------------------------------------------2 Assembly instruction-------------------------------------------------3-12
More informationImportant Notice. caution: Use proper lifting equipment and correct procedures to avoid injury.
Integrity. Partnership. Quality. COMMERCIAL DOOR INSTALLATION INSTRUCTIONS SERIES 1900, 1950, 2000, 2250, 2500, 2750 Important Notice In the following text, the word: Warning: Indicates that serious injury
More informationTC ANT MOBILE... Mobile communication antennas and antenna cables. Data sheet _en_00. 1 Description
Mobile communication antennas and antenna cables Data sheet 106760_en_00 PHOENIX CONTACT 2015-08-11 1 Description This data sheet describes the accessories for mobile communication products. All mobile
More informationEKX Full-Range Loudspeaker Accessories
EKX Full-Range Loudspeaker Accessories EKX-BRKT12, EKX-BRKT15, and EKX-TCA en Installation Note en 3 Table of contents 1 Safety 4 1.1 Safety point 6 2 Installation 7 2.1 Wall mount bracket 7 2.2 Truss
More informationPMT-L31 (for Low Ceilings) PMT-H35 (for High Ceilings)
English Ceiling Mount Bracket PMT-L31 (for Low Ceilings) PMT-H35 (for High Ceilings) Installation Manual Be sure to read this manual thoroughly before using this bracket. After you have read this manual,
More informationSpring Loaded All Season Roll-Up Doors
Spring Loaded All Season Roll-Up Doors STAND-OFF MOUNTING METHOD INSTALLATION INSTRUCTIONS READ THIS FIRST Carefully examine the crate(s) for damage before opening. If the carton is damaged, immediately
More informationEaton Data Center Racks
Eaton Data Center Racks U 1. Product Overview In today's world, network equipment is one of the most important investments a business can make. How you store and protect this equipment is just as crucial.
More informationS6 User s Manual USER S MANUAL ver. 1.0
S6 User s Manual SKEETER - 1U LOW PROFILE SOLUTION Table of Contents Tabletop Configuration 2 Tabletop Configuration Accessories 4 Slide Configuration 5 slide configuration accessories 7 rack Mount configuration
More informationInstallation and Assembly - Universal Articulating Swivel Double-Arm for 42" - 60" Plasma Screens
Installation and Assembly - Universal Articulating Swivel Double-Arm for 42" - 60" Plasma Screens Models: PLAV 70-UNL, PLAV 70-UNL-S PLAV 70-UNLP, PLAV 70-UNLP-S R This product is UL Listed. It must be
More informationSILVERBACK INSTALLATION MANUAL
SILVERBACK INSTALLATION MANUAL R-SERIES SOLAR RACKS T OLL FREE 866-766-3727 WWW.ROOFSCREEN.COM Introduction... 2 The Silverback Solar Racking System... 2 This manual... 2 Application... 2 System Overview...
More informationInstallation Manual Porter Road, Sarasota FL fax
072015 Installation Manual BEFORE YOU BEGIN: Read these instructions completely and carefully. FOR YOUR SAFETY: Read and observe all CAUTIONS and WARNINGS shown throughout these instructions. Risk of injury.
More informationMaintenance and other important non-personal injury and non-material damage instructions or statements that should be observed.
VIGO INDUSTRIES INSTALLATION GUIDE FOR SHOWER ENCLOSURE ()! SAFETY PRECAUTIONS This Installation Guide uses the following symbols to indicate important information. Always observe the instructions indicated
More informationEF-Series EuroFrame Gen 2 Cabinet System User Manual
EF-Series EuroFrame Gen 2 Cabinet System User Manual www.chatsworth.com +44 1628 524-834 (UK) 2017 Chatsworth Products, Inc. All rights reserved. Chatsworth Products, Clik-Nut, CPI, CPI Passive Cooling,
More informationInstallation Instructions
For Medium (15-18.5K) + Heavy duty (-8.5K) Air Conditioner READ BEFORE INSTALLING UNIT To avoid risk of personal injury, property damage, or product damage due to the weight of this device and sharp edges
More informationINS A KSCR INSTALLATION INSTRUCTIONS STANDARD PROCEDURE. 1. Unpacking the KSCR Splicing the KSCR (If Required)...
INS-88.500-0A KSCR INSTALLATION INSTRUCTIONS STANDARD PROCEDURE 1. Unpacking the KSCR... 2 2. Splicing the KSCR (If Required)... 4 3. Assemble Curb and Rail Corners... 5 4. Install Cross Bracing (If Required)...
More informationInstruction Sheet RADIO FREQUENCY SYSTEMS. Install. Instr. for Microwave Parabolic Antennas 2.4 m (8 ft) No Rev.
Instruction Sheet No. 412764 Rev. B ECO 12469 Install. Instr. for Microwave Parabolic Antennas 2.4 m (8 ft) These Installation Instructions are valid for antennas in the following version: reflector 2.4
More information**MOUNTING YOUR MONITOR
FPP72V200 72 FREE STANDING DISPLAY CART Assembly Instructions Hardware List Ref. Qty. Part No. Description AA 4 030-1128 1/4-20 UNC, 1 3/4 Socket Hd Screws BB 1 030-1129 5/8-11 UNC 1 3/4 Socket Hd Screw
More informationSmall Above Fireplace Pull-Down Full-Motion TV Wall Mount
Small Above Fireplace Pull-Down Full-Motion TV Wall Mount P/N 33123 User's Manual CONTENTS SAFETY WARNINGS AND GUIDELINES... 3 INTRODUCTION... 4 FEATURES... 4 CUSTOMER SERVICE... 4 PACKAGE CONTENTS...
More information