ATTACHMENT Y STUDY REPORT

Size: px
Start display at page:

Download "ATTACHMENT Y STUDY REPORT"

Transcription

1 Dynegy Marketing and Trade, LLC Wood River Units 4 & 5: 473 MW Retirement: June 1, 2016 ATTACHMENT Y STUDY REPORT March 23, 2016 PUBLIC / REDACTED

2 PUBLIC VERSION EXECUTIVE SUMMARY An Attachment Y notification submitted by Dynegy Marketing and Trade, LLC was received by MISO on December 1, The request was for retirement of Wood River Units 4 & 5 beginning June 1, Ameren and MISO performed a transmission system reliability assessment of the impact of the retirement. Initial analysis determined that the retirement of Wood River Units 4 & 5 would result in thermal loading issues on the Transmission System unless mitigation plans are implemented prior to the retirement date. Analysis of area voltages indicated slightly degraded voltage conditions, but would not decline to a level that requires mitigation. In subsequent evaluation of alternative mitigation plans, solutions were identified that eliminated the need to retain the Wood River Units 4 & 5 as System Support Resource units. Transmission System upgrades needed to alleviate thermal overloads are planned to be completed by Ameren prior to the planned retirement date which includes the replacement of the Roxford 345/138kV transformer with a 700MVA rated bank and installation of a new 345kV circuit breaker to move the transformer to a new bus position. Additionally Ameren plans to complete the reconductor of the Madison State Street Madison Industrial line 1359 by end of 2016 and reconductor of the Belleville 17 th Street Centerville line 1586 by June Until these projects are completed, mitigation may include re dispatch of available generation or will require short term ratings to allow post contingent switching or load shedding as allowed by planning criteria. Other thermal overloads observed in the analysis are addressed available mitigation plans and future transmission upgrades that can be implemented prior to the need. Therefore, based on the expected completion of transmission upgrades and available mitigation plans, Wood River Units 4 & 5 will not be required as System Support Resource units and may Retire effective June 1,

3 PUBLIC VERSION Contents I. Introduction... 4 II. Study objectives... 4 III. Models and Assumptions... 5 a. Model Assumptions... 5 b. Table of Models... 6 c. Monitoring and Contingencies... 6 IV. Study Criteria and Methodology... 6 a. Steady State Thermal Criteria... 7 b. Steady State Voltage Criteria... 7 c. MISO Transmission Planning BPM SSR Criteria... 7 d. Contingencies... 7 e. Import Capability Assessment... 8 V. Study Results... 8 a Summer Peak Analysis... 8 b Shoulder Analysis... 9 c Summer Peak Analysis... 9 d Summer Peak Import Capability Analysis... 9 VI. SSR Agreement Cost Allocation VII. Alternatives Analysis a. New Generation or Generation Re dispatch b. System Reconfiguration and Operating Guides c. Demand Response or Load Curtailment d. Transmission Projects VIII. Conclusion IX. Appendices

4 PUBLIC VERSION I. INTRODUCTION The Market Participant Dynegy Marketing and Trade, LLC submitted an Attachment Y Notice to MISO dated November 24, 2015 for the retirement of the Wood River Units 4 & 5 effective June 1, The Wood River Units 4 & 5 are coal fired generators with a total capacity of 473 MW and are connected to the Ameren 138kV Transmission System. The plant is located near the city of Alton, Illinois. Figure 1.0: Location of Wood River Generating Plant in Alton, Illinois. II. STUDY OBJECTIVES Under Section of MISO s Tariff, SSR procedures maintain system reliability by providing a mechanism for MISO to enter into agreements with Market Participants (MP) that own or operate Generation Resources or Synchronous Condenser Units (SCUs) that have requested to either Retire or Suspend, but are required to maintain system reliability. 4

5 PUBLIC VERSION The principal objective of an Attachment Y study is to determine if the unit(s) for which a change in status is requested is necessary for system reliability based on the criteria set forth in the MISO Business Practices Manuals. The study work included monitoring and identifying the steady state branch/voltage violations on transmission facilities due to the unavailability of the Generation Resource or SCU. The relevant MISO Transmission Owner and/or regional reliability criteria are used for monitoring such violations. III. MODELS AND ASSUMPTIONS Corresponding to the anticipated retirement of [unit name][unit id], the following power system analysis models were used for the study: 2016 Summer Peak (MTEP Summer Peak Model) 2016 Shoulder (MTEP Shoulder Model) 2020 Summer Peak (MTEP Summer Peak Model) The Attachment Y study models were created in accordance with the MISO Transmission Planning Business Practice Manual (BPM 020 r12) Section This includes creating a set of Security Constrained Economic Dispatch (SCED) models from each source model in which the units being studied are taken out of service to represent the After retirement scenario. To create the Before retirement scenario, generation in MISO was scaled down in each model and then the to be retired unit was fully dispatched. a. Model Assumptions 1. Generation Approved Attachment Y Units are modelled offline 2. Transmission The following transmission projects in service prior to the change of status date are included models: MTEP Project 2996 Montgomery Hills 345kV clearance MTEP Project 1538 Pana Ramsey 138kV reconductor MTEP Project 3013 Turkey Hill Cahokia 345kV conversion MTEP Project 3339 Pana Taylorville 138kV reconductor MTEP Project 2472 Maple Ridge Fargo 345kV line addition The following transmission projects were excluded in the 2016SP and 2016SH models due to later in service date MTEP Project 2302 Madison Madison State St 138kV reconductor, ISD 12/1/2016 5

6 PUBLIC VERSION MTEP Project 4494 Galesburg 161/138kV transformer replacement at Sandburg, ISD 12/1/2016 MTEP Project 4471 Cahokia Dupo Ferry 138kV line reconductor, ISD 12/1/2017 MTEP Project 2237 Pana Faraday 345kV line addition, ISD 12/1/2016 MTEP Project 3017 Meredosia 345/138kV transformer, ISD 12/1/2016 MTEP Project 3022 Sandburg 345kV substation and line addition, ISD 12/1/2016 MTEP Project 3169 Pana Austin area work, ISD 12/1/2018 MTEP Project 3170 Zachary Maywood line addition, ISD 12/1/2018 MTEP Project 2248 Ottumwa Zachary 345kV line addition, 12/1/2018 b. Table of Models Table 1: Table of Models Topology Loads Source Model Wood River Contingencies Units 4 & Summer Peak MTEP SP On P1,P2,P4,P5,P7,select ed P3, P6 * Summer Peak MTEP SP Off P1,P2,P4,P5,P7,select ed P3, P6 * Shoulder MTEP SH On P1,P2,P4,P5,P7,select ed P3, P6 * Shoulder MTEP SH Off P1,P2,P4,P5,P7,select ed P3, P6 * Summer Peak MTEP SP On P1,P2,P4,P5,P7,select ed P3, P6 * Summer Peak MTEP SP Off P1,P2,P4,P5,P7,select ed P3, P6 * *NERC Category P4,P5 events simulated using Category P2 contingencies c. Monitoring and Contingencies Monitor: AMMO (356), AMIL (357) local balancing areas, kV bus voltages Contingencies: AMMO, AMIL NERC Category P1, P2, P4, P5, P7 and selected P3, P6 events for nearby 100 kv 345 kv facilities, CE selected single and bus double (P2) contingencies 345kV IV. STUDY CRITERIA AND METHODOLOGY PSS/E was used to perform AC contingency analysis. Cases were solved with automatic control of LTCs, phase shifters, DC taps, switched shunts enabled (regulating), and area interchange 6

7 PUBLIC VERSION disabled. Contingency analysis was performed on before and after cases. The results were compared to find if there were any criteria violations due to the unit(s) change of status. a. Steady State Thermal Criteria Ameren Transmission Planning Criteria applied for thermal analysis (effective 3/24/2015): For System Intact (NERC Category P0), all thermal loadings exceeding 100% of the normal rating. For NERC Category P1 P7 contingencies, all thermal loadings exceeding 100% of the emergency rating. b. Steady State Voltage Criteria Ameren Transmission Planning Criteria applied for voltage analysis (effective 3/24/2015): For System Intact (NERC Category P0), transmission bus voltages less than 95% or above 105% For NERC Category P1 P7 contingencies, transmission bus voltages less than 95% or above 105% c. MISO Transmission Planning BPM SSR Criteria As specified in the MISO BPM 020 r12, the System Support Resource criteria for determining if an identified facility is impacted by the generator change of status is: Under system intact and category P1 contingencies, branch thermal violations are only valid if the flow increase on the element in the after retirement scenario is equal to or greater than: a) 5% of the to be retired unit(s) MW amount (i.e. 5% PTDF) for a base violation compared with the before retirement scenario, or b) 3% of the to be retired unit(s) amount (i.e. 3% OTDF) for a contingency violation compared with the before retirement scenario. Under system intact and category P1 contingencies, high and low voltage violations are only valid if the change in voltage is greater than 1% as compared to the before retirement voltage calculation. Under category P1 P7 contingencies, for the valid thermal and voltage violations as specified above, generation re dispatch, system reconfiguration, and/or load shedding will be considered if applicable. d. Contingencies A subset of the MISO Transmission Expansion Plan (MTEP) contingencies in Ameren and neighboring ComEd system was used for AC contingency analysis. 7

8 PUBLIC VERSION The following NERC Categories of contingencies were evaluated: 1. Category P0 when the system is under normal conditions. 2. Category P1 contingencies resulting in the loss of a single element. 3. Category P2, P3, P4, P5, P6, P7 contingencies resulting in the loss of two or more (multiple) elements. 4. Maintenance outage condition with forced outage during shoulder load conditions. e. Import Capability Assessment A study of simultaneous import capability (FCITC) was performed. An import capability of 2000 MW, as limited by an Ameren transmission element, was used as a proxy to maintain transmission capability related to generation reserves in the Ameren Missouri or Ameren Illinois footprint, considering the 2020 summer peak model. Import capabilities for the AMMO and AMIL systems were developed considering the Wood River Plant retirement scenario as well as the Wood River Plant in service. Results were compared to determine if there is any significant change to import capability or if there are any criteria violations due to the proposed suspension of study units. V. STUDY RESULTS Appendix A to this report includes all constrained elements found to be affected by the retirement of Wood River Units 4 & 5. a Summer Peak Analysis Analysis of the 2016 summer peak conditions identified a number of NERC Category P2 contingency events which result in thermal overloads that would not be addressed with the SSR units. The study identified three NERC Category P3 events that result in thermal violations on two transmission facilities and nine NERC Category P6 events that cause thermal violations on four transmission facilities. The NERC Category P3 and Category P6 events are mitigated by proposed transmission upgrades or by redispatch following the first contingent event or post contingent load shedding where permitted. Analysis of the 2016 summer peak model indicated that NERC Category P1 and Category P3 events result in marginal voltage violations in the Wood River and significant voltage decline below 95% for NERC Category P2, Category P3 (Generator+Line) and Category P6 contingency events. To address concerns over the level of modeling details in the study models, additional voltage comparisons were performed using the Ameren 2020 summer peak model containing the more detailed representation of the Ameren subtransmission system. The MISO model used in the Wood River Attachment Y analysis includes an equivalent representation of these subtransmission facilities, while the Ameren model, which was used to support Ameren s compliance with NERC standard TPL 001 4, includes explicit representation of kv LTC bulk substation transformers and 34 kv capacitor banks, and equivalent representation of the 8

9 PUBLIC VERSION 34 kv lines between the kv bulk substations. The additional analysis confirmed that equivalent representation of the Ameren kv LTC transformers, 34 kv subtransmission lines, and 34 kv capacitor banks produced more conservative voltage results than the Ameren 2020 summer model with its explicit representation of kv transformers with LTC and 34 kv capacitor banks. Further, it is concluded that transmission level bus voltages that are identified as less than 95% in the MISO models used for the Wood River Attachment Y study are not true voltage concerns that require mitigation. b Shoulder Analysis In the 2016 shoulder study no thermal overloading issues were identified for base case or contingency conditions. Analysis of the 2016 shoulder model indicated several marginal voltage violations in the Wood River area as a result of NERC Category P2 and P3 events. Based on the comparison analysis of voltages in the equivalent and explicitly detailed models, it was determined that transmission level bus voltages that are identified as less than 95% in the MISO models used for the Wood River Attachment Y study are not true voltage concerns that require mitigation. c Summer Peak Analysis Analysis of the 2020 summer peak conditions identified four NERC Category P2 contingency events that cause thermal violations on four transmission facilities that would not be addressed by the SSR units. The study indicated that two NERC Category P3 contingency events cause thermal overloading of one transmission facility and six NERC Category P6 events cause thermal overloading on six transmission facilities. The NERC Category P3 and Category P6 events are mitigated by proposed transmission projects and by re dispatch following the first contingent event or post contingent load shedding where permitted. Analysis of the 2020 summer peak model indicated that NERC Category P1 contingency events result in marginal voltage violations in the Wood River area and significant voltage decline below 95% for NERC Category P2, Category P3 (Generator + Line) and Category P6 contingency events. Additional voltage comparisons were performed using the Ameren 2020 summer peak model containing the more detailed representation of the Ameren subtransmission system which confirmed that the equivalent models used for the Attachment Y study produce more conservative voltage results. Analysis of the more detailed model concluded that transmission level bus voltages that are identified as less than 95% in the MISO models used for the Wood River Attachment Y study are not true voltage concerns that require mitigation. d Summer Peak Import Capability Analysis The AmerenMO and AmerenIL transmission systems were tested for simultaneous incremental transfer (import) capability considering the MISO 2020 summer peak model with Wood River generating units 4 and 5 on 473 MW) and Wood River generating units 4 and 5 off (retired). Four simultaneous export subsystems were considered, with power coming from North, East, South, and West for each combination of generation deficiencies. The export 9

10 PUBLIC VERSION participation was varied over the four directions, with one direction assumed to provide 40% of the export, while each of the other three directions were assumed to provide 20% of the export. The analysis monitored only Ameren transmission facilities. Import subsystems considered were as follows: All on line AmerenIL generation All on line AmerenIL coal fired generation All on line AmerenIL generation in the Metro St. Louis East area All on line AmerenMO generation All on line AmerenMO coal fired generation All on line AmerenMO generation in the Metro St. Louis area The retirement of Wood River generating units 4 and 5 would not impact simultaneous import capability to AmerenIL generation as all calculated import FCITC from all test directions was MW with no limit found up to the test level. However, the retirement of the Wood River generators has a significant impact on the simultaneous import capability to AmerenMO generation as all calculated import FCITC from all test directions decreased by 585 MW to 1862 MW (33.5% to 46.5%) compared to the import FCITC with Wood River generation on. The retirement of the Wood River generation shifts the limit from the Cahokia 138 kv bus tie 3 4 for the outage of the [REDACTED] and [REDACTED] to the Roxford 345/138 kv transformer for the outage of the [REDACTED] and [REDACTED]. Although the import capabilities are above 2000 MW for two of the three import tests to AmerenMO generation, and the proxy would be maintained to ensure that there is transmission capability needed for generation reserves, please note that significant margin would be removed from the system to handle the unexpected transmission contingency and/or generation dispatch scenarios that could impact transmission operations on a daily basis. Therefore, upgrades would likely be pursued over time to assure that transmission capability needed for future generation reserve requirements would be available. VI. SSR AGREEMENT COST ALLOCATION MISO Cost Allocation Methodology utilizes bus distribution factors for the load buses to determine the impacted Elemental Pricing Nodes (EP Nodes) that are associated with the customers responsible for the costs of the SSR Unit. Using the quarterly MISO Network and Commercial model, the analysis determines the load buses that contribute to the constraints identified in the Attachment Y study using linear power flow techniques. The Commercial Model is used to allocate costs to the affected Load Serving Entities (LSE s) in each monthly settlement cycle based on the peak hour energy withdrawal. The SSR Cost allocation information was calculated for the constraints identified in the Attachment Y analysis based on the initial determination of need for the SSR Units. However, 10

11 PUBLIC VERSION with the subsequent resolution of reliability issues, the allocation of costs is no longer applicable and retained only for completeness. The initial cost allocation was calculated to include EP Nodes listed in Appendix B. VII. ALTERNATIVES ANALYSIS a. New Generation or Generation Re dispatch A review of the generation interconnection queue identified no new generation that has been proposed in the neighboring counties. Analysis of available generation re dispatch was performed for constraints caused by NERC Category P3 and P6 contingency events where load shedding is not allowed under Ameren local planning criteria. The results indicate that redispatch of nearby generation can effectively manage the constraints. Table 2 contains results of the generation re dispatch analysis. Table 2: Generation Re dispatch Estimates for Selected Contingencies Case Contingency Reliability Issue Madison State Street Tap-Madison Industrial 2016 Summer [REDACTED] section of Venice- Peak Madison Industrial 138 kv line Summer Peak 2020 Summer Peak [REDACTED] [REDACTED] Belleville 17th Street Jct-Centerville section of S Belleville-Centerville 138 kv line 1586 Cahokia 345/138 kv Xfmr #8 Generation Redispatch Venice: -150 MW Baldwin: -97 MW Baldwin: -137 MW b. System Reconfiguration and Operating Guides No existing operating guides are available to address the thermal issues. No new operating guides were developed to provide mitigation for constraints. c. Demand Response or Load Curtailment Evaluation of demand response was performed using load sensitivities to determine the amount of load that could alleviate the thermal overloading and voltage issues as a hypothetical solution. Although no customers have offered to provide demand response service, the analysis is intended to provide a general indication of the amount of load curtailment required to avoid the need for an SSR. Since the estimate is based on the most 11

12 PUBLIC VERSION effective locations for load shedding, the actual demand response will vary depending on the location of the customer load. The minimum amount of load shed is estimated to be 55 MW to fully mitigate the reliability issues resulting from NERC Category P3 and P6 contingent events that would otherwise be alleviated by the SSR generation. Table 3 contains results of the demand response analysis including the associated bus locations. Table 3: Demand Response Estimates for Selected Contingencies Case Contingency Reliability Issue Madison State Street Tap-Madison 2016 Summer Industrial section of [REDACTED] Peak Venice-Madison Industrial 138 kv line Summer Peak 2020 Summer Peak [REDACTED] [REDACTED] Belleville 17th Street Jct-Centerville section of S Belleville- Centerville 138 kv line 1586 Cahokia 345/138 kv Xfmr #8 Demand Response Bus Locations 30 MW 4MADSN INDUS MW 4CENTERVILLE MW 4CAHOK RUSL d. Transmission Projects Transmission projects already planned are expected to address many of the thermal issues identified in the analysis with three projects to be completed prior to summer Project Roxford 345/138kV Transformer & Breaker, ISD: 6/1/2016 Project 2302 Madison State St. Madison Industrial Reconductor, ISD: 12/1/2016 Project Belleville 17 th St. Centerville Reconductor, ISD: 6/1/2019 Project 9741 Porter Road Highland Upgrade, ISD: 6/1/2016 Project Cahokia Ridge 138kV Upgrade, ISD: 6/1/2018 Project 7801 Cahokia Ashley Upgrade, ISD: 6/1/2018 Reconductoring the Belleville 17th Street Junction Centerville section of South Belleville Centerville 138 kv line 1586 is needed to address the failure of [REDACTED] and other multiple outage conditions, and was earlier proposed for completion in This project will be advanced to 2019 to address the thermal loading concerns caused by the retirement of Wood River generation. A short term emergency rating would need to be developed for the nearterm to allow time for post contingency load shedding or switching in the Centerville area until the line reconductoring could be completed. 12

13 PUBLIC VERSION Rather than reconductor the Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line 1359, which was reconductored just a few years ago, it is proposed to install a new 345 kv breaker in the Roxford ring bus and connect the Roxford 345/138 kv transformer to its own ring bus position. This system connection modification would keep the Roxford 345/138 kv transformer in service for the outage of the [REDACTED] and eliminate the thermal loading concern on the Venice Madison State Street Tap line section for 345kV breaker failure conditions at the [REDACTED] Substation. This project is proposed for completion before summer Reconductoring the Madison State Street Tap Madison Industrial section of Venice Madison Industrial 138 kv line 1359 (MISO Project ID 2302) is planned for completion in late 2016, after the proposed retirement date of June 1, 2016 for the Wood River generators. This project is needed to address thermal loading concerns for 345 kv breaker failure events at the [REDACTED] Substation, which result in the outage of the [REDACTED]. The critical contingency loading on this line section would be reduced by maintaining the Roxford 345/138 kv transformer in service for these[redacted] breaker failure events, allowing for a short term emergency rating to be developed for the near term to allow time for post contingency load shedding or switching in the Madison Industrial/Granite City 23 rd Street area until the line reconductoring could be completed. Post contingency load shedding or subtransmission switching would also be required in the Granite City area for the coincident outage of [REDACTED] and the [REDACTED]. Assuming the completion of the project to reconnect the Roxford 345/138 kv transformer to the Roxford 345 kv ring bus, there is no need to replace the 477 kcmil ACSR bus conductor at the O Fallon Porter Road kv Substation to address the thermal loading concerns during circuit breaker failure events at the [REDACTED] Substation. The critical contingency loading on this line section would be eliminated by maintaining the Roxford 345/138 kv transformer in service for [REDACTED] breaker failure events. However, this project (MISO project ID 9741) will be completed by June, 2016 to address P6 outage events Replacement of the Roxford 345/138 kv 560 MVA transformer with a 700 MVA transformer is recommended to address thermal loading concerns with Wood River generation retired. The critical outage event is the coincident outage of [REDACTED] or [REDACTED] with the [REDACTED]. Work is underway to replace this transformer before summer The replacement of the Ridge and Cahokia 138 kv bus conductors in the Cahokia Ridge kv circuit would be needed to increase ratings on this facility as a result of the Wood River generation retirement. The critical contingency is the [REDACTED], or the coincident outage of the [REDACTED] and the [REDACTED]. Upgrade of the Cahokia 138 kv bus tie 3 4 is presently planned for The critical contingency is the failure of [REDACTED]. 13

14 PUBLIC VERSION VIII. CONCLUSION While analysis of the retirement of Wood River Units 4 & 5 indicates that a number of thermal loading issues will occur on the Transmission System without the units, mitigation options are available to alleviate the concerns. Area voltages slightly degrade as a result of the retirement, but would not decline to a level that requires mitigation. Evaluation of alternative mitigation plans identified solutions that eliminate the need to retain the Wood River Units 4 & 5 as System Support Resource units. Transmission System upgrades needed to alleviate thermal overloads are planned to be completed by Ameren prior to the planned retirement date which includes the replacement of the Roxford 345/138kV transformer with a 700MVA rated bank and installation of a new 345kV circuit breaker to move the transformer to a new bus position. Additionally Ameren plans to complete the reconductor of the Madison State Street Madison Industrial line 1359 by end of 2016 and reconductor of the Belleville 17 th Street Centerville line 1586 by June Until these projects are completed, mitigation may include re dispatch of available generation or will require short term ratings to allow post contingent switching or load shedding as allowed by planning criteria. Other thermal overloads observed in the analysis are addressed available mitigation plans and future transmission upgrades that can be implemented prior to the need. Therefore, based on the expected completion of transmission upgrades and available mitigation plans, Wood River Units 4 & 5 will not be required as System Support Resource units and may Retire effective June 1, IX. APPENDICES Appendix A: Table 1 Thermal Analysis Results Table 2 Voltage Analysis Results Appendix B: Table 1 SSR Cost Allocation 14

15 Appendix A Steady-State AC Contingency Analysis Results

16 Appendix A, Table 1 Thermal Analysis Results Wood River Attachment Y Study Compare Thermal Results Model Type Contingency Branch Rating B (MVA) % Loading with Wood River Off % Loading with Wood River On Comments 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] 2016SP P23 [REDACTED] Belleville 17th Street Jct Centerville section of S Belleville Centerville post contingent load shedding; MTEP App B Project 138 kv line , ISD: 6/1/2019 Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/2016 Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line MTEP App A Project 10884, ISD: 6/1/2016 Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv MTEP App A Project 10884, ISD 6/1/2016; MTEP line App A Project 9741, ISD 6/1/2016 Madison Industrial Granite City 23rd Street section of Madison Industrial Wood River 138 kv line confirmed corrected rating: 333MVA, not an issue Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/2016 Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line MTEP App A Project 10884, ISD: 6/1/2016 Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv MTEP App A Project 10884, ISD 6/1/2016; MTEP line App A Project 9741, ISD 6/1/2016 Madison Industrial Granite City 23rd Street section of Madison Industrial Wood River 138 kv line confirmed corrected rating: 333MVA, not an issue Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/ SP P3 [REDACTED] Roxford 345/138 kv Xfmr MTEP App A Project 10884, ISD 6/1/ SP P3 [REDACTED] Roxford 345/138 kv Xfmr MTEP App A Project 10884, ISD 6/1/ SP P3 [REDACTED] Roxford 345/138 kv Xfmr MTEP App A Project 10884, ISD 6/1/ SP P3 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] Madison State Street Tap Madison Industrial section of Venice redispatch or post contingent load shedding; MTEP Madison Industrial 138 kv line App A Project 2302, ISD: 12/1/2016 Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv MTEP App A Project 10884, ISD 6/1/2016; MTEP line App A Project 9741, ISD 6/1/2016 Madison Industrial Granite City 23rd Street section of Madison Industrial Wood River 138 kv line confirmed corrected rating: 333MVA, not an issue

17 Appendix A, Table 1 Thermal Analysis Results Wood River Attachment Y Study Compare Thermal Results Model Type Contingency Branch 2016SP P6 [REDACTED] Rating B (MVA) % Loading with Wood River Off % Loading with Wood River On Comments post contingent load shedding; MTEP App A Project Madison State Street Tap Madison Industrial section of Venice Madison Industrial 138 kv line , ISD: 6/1/2016, MTEP App A Project 2302, 85 ISD: 12/1/ SP P6 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line MTEP App A Project 10884, ISD: 6/1/2016 Belleville 17th Street Jct Centerville section of S Belleville Centerville redispatch or post contingent load shedding; MTEP 138 kv line App B Project 10886, ISD: 6/1/2019 Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv line MTEP App A Project 9741, ISD 6/1/ SP P6 [REDACTED] Cottage Hills Wanda section of Wood River Stallings 138 kv line confirmed corrected rating: 333MVA, not an issue 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] 2016SP P6 [REDACTED] 2020SP P23 [REDACTED] Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/2016 Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/2016 Madison Industrial Granite City 23rd Street section of Madison Industrial Wood River 138 kv line confirmed corrected rating: 333MVA, not an issue Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/2016 Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line post contingent load shedding; Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv MTEP App A Project 10884, ISD 6/1/2016; MTEP line App A Project 9741, ISD 6/1/2016 Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/2016 Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/2016 Madison State Street Tap Madison Industrial section of Venice post contingent load shedding; MTEP App A Project Madison Industrial 138 kv line , ISD: 12/1/2016 Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv line at limit, not an issue 2020SP P23 [REDACTED] Cahokia Ridge kv line post contingent load shedding; MTEP App B Project 10885, ISD 6/1/2018

18 Appendix A, Table 1 Thermal Analysis Results Wood River Attachment Y Study Compare Thermal Results Model Type Contingency Branch Rating B (MVA) % Loading with Wood River Off % Loading with Wood River On Comments 2020SP P23 [REDACTED] 2020SP P23 [REDACTED] 2020SP P23 [REDACTED] 2020SP P23 [REDACTED] 2020SP P23 [REDACTED] 2020SP P23 [REDACTED] 2020SP P23 [REDACTED] Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line < 85 MTEP App A Project 10884, ISD: 6/1/2016 Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv MTEP App A Project 10884, ISD 6/1/2016; MTEP line App A Project 9741, ISD 6/1/2016 Madison Industrial Granite City 23rd Street section of Madison Industrial Wood River 138 kv line < 85 confirmed corrected rating: 333MVA, not an issue Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line < 85 MTEP App A Project 10884, ISD: 6/1/2016 Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv MTEP App A Project 10884, ISD 6/1/2016; MTEP line App A Project 9741, ISD 6/1/2016 Madison Industrial Granite City 23rd Street section of Madison Industrial Wood River 138 kv line < 85 confirmed corrected rating: 333MVA, not an issue Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv line < 85 MTEP App A Project 9741, ISD 6/1/ SP P24 [REDACTED] Cahokia 138 kv Bus Tie at limit, not an issue 2020SP P32 [REDACTED] Roxford 345/138 kv Xfmr < 85 MTEP App A Project 10884, ISD 6/1/ SP P32 [REDACTED] Roxford 345/138 kv Xfmr < 85 MTEP App A Project 10884, ISD 6/1/ SP P32 [REDACTED] Cahokia Ashley kv line at limit, not an issue 2020SP P6 [REDACTED] Cottage Hills Wanda section of Wood River Stallings 138 kv line < 85 confirmed corrected rating: 333MVA, not an issue 2020SP P6 [REDACTED] Sioux Mississippi Tap section of Sioux Roxford kv line < 85 post contingent load shedding; 2020SP P6 [REDACTED] Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line < 85 post contingent load shedding; MTEP App A Project 10884, ISD: 6/1/ SP P6 [REDACTED] 2020SP P6 [REDACTED] Madison Industrial Granite City 23rd Street section of Madison Industrial Wood River 138 kv line < 85 confirmed corrected rating: 333MVA, not an issue Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv MTEP App A Project 10884, ISD 6/1/2016; MTEP line App A Project 9741, ISD 6/1/2016

19 Appendix A, Table 1 Thermal Analysis Results Wood River Attachment Y Study Compare Thermal Results Model Type Contingency Branch Rating B (MVA) % Loading with Wood River Off % Loading with Wood River On Comments 2020SP P6 [REDACTED] Cahokia Ashley kv line post contingent load shedding; MTEP App B Project 7801, ISD 6/1/ SP P6 [REDACTED] Cahokia 345/138 kv Xfmr # redispatch or post contingent load shedding 2020SP P6 [REDACTED] 2020SP P6 [REDACTED] 2020SP P6 [REDACTED] Madison Industrial Granite City 23rd Street section of Madison Industrial Wood River 138 kv line < 85 confirmed corrected rating: 333MVA, not an issue Venice Madison State Street Tap section of Venice Madison Industrial 138 kv line < 85 post contingent load shedding; Highland Tap East Collinsville section of Porter Rd East Collinsville 138 kv line < 85 at limit, not an issue 2020SP P6 [REDACTED] Turkey Hill East Belleville 138 kv line post contingent load shedding; 2020SP P6 [REDACTED] East Belleville Porter Rd 138 kv line post contingent load shedding; 2020SP P6 [REDACTED] Porter Road Highland Tap section of E Collinsville Porter Rd 138 kv line MTEP App A Project 9741, ISD 6/1/2016

20 Appendix A, Table 2 Voltage Analysis Results Wood River Attachment Y Study Compare Voltage Results Model Type Contingency Bus Voltage with Wood River On Voltage with Wood River Off Comments 2016SP P1 [REDACTED] Wood River 138 kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Laclede kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Laclede kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Conoco Phillips 138 kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Cottage Hills 138 kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Wood River 138 kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Laclede kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Laclede kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Conoco Phillips 138 kv marginally below limit, confirmed not an issue 2016SP P1 [REDACTED] Cottage Hills 138 kv marginally below limit, confirmed not an issue 2016SP P2 [REDACTED] Gillespie 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] North Staunton 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Litchfield 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Conoco Phillips 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Gillespie 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] North Staunton 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Gillespie 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Litchfield 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Wood River 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Laclede kv voltages are adequate, not an issue

21 Appendix A, Table 2 Voltage Analysis Results Wood River Attachment Y Study Compare Voltage Results Voltage with Wood River On Voltage with Wood River Off Model Type Contingency Bus Comments 2016SP P2 [REDACTED] Conoco Phillips 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Cottage Hills 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] BOC Gases 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Roxford 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Wood River 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Conoco Phillips 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Cottage Hills 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] BOC Gases 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Roxford 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Wanda 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Mississippi 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Wood River 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Conoco Phillips 138 kv voltages are adequate, not an issue 2016SP P2 [REDACTED] Cottage Hills 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Wood River 138 kv marginally below limit, confirmed not an issue 2016SP P3 [REDACTED] Laclede kv marginally below limit, confirmed not an issue 2016SP P3 [REDACTED] Laclede kv marginally below limit, confirmed not an issue 2016SP P3 [REDACTED] Conoco Phillips 138 kv marginally below limit, confirmed not an issue

22 Appendix A, Table 2 Voltage Analysis Results Wood River Attachment Y Study Compare Voltage Results Model Type Contingency Bus Voltage with Wood River On Voltage with Wood River Off Comments 2016SP P3 [REDACTED] Cottage Hills 138 kv marginally below limit, confirmed not an issue 2016SP P3 [REDACTED] Wanda 138 kv marginally below limit, confirmed not an issue 2016SP P3 [REDACTED] Wood River 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Conoco Phillips 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Cottage Hills 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Roxford 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Mississippi 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Wanda 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] BOC Gases 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Wood River 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Conoco Phillips 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Cottage Hills 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Roxford 138 kv voltages are adequate, not an issue 2016SP P3 [REDACTED] Mississippi 138 kv voltages are adequate, not an issue 2016SP P6 [REDACTED] Wood River 138 kv voltages are adequate, not an issue 2016SP P6 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P6 [REDACTED] Laclede kv voltages are adequate, not an issue 2016SP P6 [REDACTED] Conoco Phillips 138 kv voltages are adequate, not an issue

23 Appendix A, Table 2 Voltage Analysis Results Wood River Attachment Y Study Compare Voltage Results Model Type Contingency Bus Voltage with Wood River On Voltage with Wood River Off Comments 2016SP P6 [REDACTED] BOC Gases 138 kv voltages are adequate, not an issue 2020SP P1 [REDACTED] Wood River 138 kv marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Laclede kv > marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Laclede kv > marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Conoco Phillips 138 kv marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] BOC Gases 138 kv > marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Cottage Hills 138 kv marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Wood River 138 kv > marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Laclede kv > marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Laclede kv > marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Conoco Phillips 138 kv marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] BOC Gases 138 kv > marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Cottage Hills 138 kv marginally below limit, confirmed not an issue 2020SP P1 [REDACTED] Roxford 138 kv > marginally below limit, confirmed not an issue 2020SP P2 [REDACTED] Gillespie 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] North Staunton 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Litchfield 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Wood River 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Conoco Phillips 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] BOC Gases 138 kv > voltages are adequate, not an issue

24 Appendix A, Table 2 Voltage Analysis Results Wood River Attachment Y Study Compare Voltage Results Voltage with Wood River On Voltage with Wood River Off Model Type Contingency Bus Comments 2020SP P2 [REDACTED] Cottage Hills 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Roxford 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Gillespie 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] North Staunton 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Gillespie 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Litchfield 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Wood River 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Conoco Phillips 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Cottage Hills 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] BOC Gases 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Roxford 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Wood River 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Conoco Phillips 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Cottage Hills 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] BOC Gases 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Roxford 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Wanda 138 kv voltages are adequate, not an issue 2020SP P2 [REDACTED] Wood River 138 kv > voltages are adequate, not an issue

25 Appendix A, Table 2 Voltage Analysis Results Wood River Attachment Y Study Compare Voltage Results Voltage with Wood River On Voltage with Wood River Off Model Type Contingency Bus Comments 2020SP P2 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Conoco Phillips 138 kv > voltages are adequate, not an issue 2020SP P2 [REDACTED] Cottage Hills 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Cottage Hills 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Wanda 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Wood River 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Laclede kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Conoco Phillips 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Cottage Hills 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Roxford 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Mississippi 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Wanda 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] BOC Gases 138 kv > voltages are adequate, not an issue 2020SP P3 [REDACTED] Wood River 138 kv voltages are adequate, not an issue 2020SP P3 [REDACTED] Laclede kv voltages are adequate, not an issue 2020SP P3 [REDACTED] Laclede kv voltages are adequate, not an issue 2020SP P3 [REDACTED] Conoco Phillips 138 kv voltages are adequate, not an issue 2020SP P3 [REDACTED] Cottage Hills 138 kv voltages are adequate, not an issue 2020SP P3 [REDACTED] Roxford 138 kv voltages are adequate, not an issue 2020SP P3 [REDACTED] Mississippi 138 kv voltages are adequate, not an issue

AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Ameren Missouri, Ameren Illinois, and Ameren Transmission Company of Illinois)

AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Ameren Missouri, Ameren Illinois, and Ameren Transmission Company of Illinois) AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Missouri, Illinois, and Transmission Company of Illinois) TRANSMISSION PLANNING CRITERIA AND GUIDELINES March 28, 2003 Revised April

More information

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g 2011 SERTP Welcome SERTP 2011 First RPSG Meeting & Interactive Training Session 9:00 AM 3:00 PM 1 2011 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission

More information

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting Document C-29 Procedures for System Modeling: January 5 th, 2016 TFSS Revisions Clean Open Process Posting Prepared by the SS-37 Working Group on Base Case Development for the Task Force on System Studies.

More information

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/ ITC Holdings Planning Criteria Below 100 kv * Category: Planning Type: Policy Eff. Date/Rev. # 12/09/2015 000 Contents 1. Goal... 2 2. Steady State Voltage & Thermal Loading Criteria... 2 2.1. System Loading...

More information

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines Central Hudson Gas & Electric Corporation Transmission Planning Guidelines Version 4.0 March 16, 2016 Version 3.0 March 16, 2009 Version 2.0 August 01, 1988 Version 1.0 June 26, 1967 Table of Contents

More information

GridLiance Reliability Criteria

GridLiance Reliability Criteria GridLiance Reliability Criteria Planning Department March 1, 2018 FOREWORD The GridLiance system is planned, designed, constructed, and operated to assure continuity of service during system disturbances

More information

Voltage and Reactive Procedures CMP-VAR-01

Voltage and Reactive Procedures CMP-VAR-01 Voltage and Reactive Procedures CMP-VAR-01 NERC Standards: VAR-001-2 VAR-002-1.1b Effective Date: 07/31/2012 Document Information Current Revision 2.0 Review Cycle Annual Subject to External Audit? Yes

More information

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above March 13, 2018 Issued by: Dehn Stevens, Director System Planning and Services 1.0 SCOPE This document defines the criteria

More information

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES Transmission Planning TABLE OF CONTENTS I. SCOPE 1 II. TRANSMISSION PLANNING OBJECTIVES 2 III. PLANNING ASSUMPTIONS 3 A. Load Levels 3 B. Generation

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology For NERC Standard FAC-008 and FAC-009 Issued by: Dan Custer Reviewed by: Tom Mielnik Version 2.7 1 1.0 Scope: This document provides

More information

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line Vince Leung March 27, 2017 Reviewed by Johnny Nguyen Table of Contents Background 2 Objective 3 Base Case Assumptions

More information

MidAmerican Energy Company 69 kv Facility Ratings Methodology

MidAmerican Energy Company 69 kv Facility Ratings Methodology MidAmerican Energy Company 69 kv Facility Ratings Methodology Version 1.0 Issued by: Luke Erichsen Reviewed by: Tom Mielnik Last Reviewed: 8/29/2012 1 1.0 Scope: This document provides MidAmerican Energy

More information

System Ratings, Limits and Real-Time Monitoring. Presented to: Operating Committee April 21, 2016

System Ratings, Limits and Real-Time Monitoring. Presented to: Operating Committee April 21, 2016 System Ratings, Limits and Real-Time Monitoring Presented to: Operating Committee April 21, 2016 Thermal Facility Ratings In New England Summer ratings (April 1 to October 31) Winter ratings (November

More information

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology For NERC Standard FAC-008-3 Version 3.4 1 Contents 1. Scope... 3 2. Establishment and Communication of Facility Ratings:... 3 2.1.

More information

Planning Criteria. Revision 1.4 MAINTAINED BY: Transmission Working Group System Protection and Control Working Group Supply Adequacy Working Group

Planning Criteria. Revision 1.4 MAINTAINED BY: Transmission Working Group System Protection and Control Working Group Supply Adequacy Working Group Planning Criteria Revision 1.4 MAINTAINED BY: Transmission Working Group System Protection and Control Working Group Supply Adequacy Working Group PUBLISHED: 10/9/2017 LATEST REVISION: Effective 7/25/2017

More information

Central East Voltage and Stability Analysis for Marcy FACTS Project Phase I

Central East Voltage and Stability Analysis for Marcy FACTS Project Phase I Prepared by NYISO Operations Engineering 1. INTRODUCTION Central East Voltage and Stability Analysis for The Marcy Flexible AC Transmission System (FACTS) project is a joint technology partnership between

More information

Standard MOD Area Interchange Methodology

Standard MOD Area Interchange Methodology A. Introduction 1. Title: Area Interchange Methodology 2. Number: MOD-028-2 3. Purpose: To increase consistency and reliability in the development and documentation of Transfer Capability calculations

More information

FACILITY RATINGS METHOD TABLE OF CONTENTS

FACILITY RATINGS METHOD TABLE OF CONTENTS FACILITY RATINGS METHOD TABLE OF CONTENTS 1.0 PURPOSE... 2 2.0 SCOPE... 3 3.0 COMPLIANCE... 4 4.0 DEFINITIONS... 5 5.0 RESPONSIBILITIES... 7 6.0 PROCEDURE... 8 6.4 Generating Equipment Ratings... 9 6.5

More information

LONG-RANGE TRANSMISSION PLAN

LONG-RANGE TRANSMISSION PLAN LONG-RANGE TRANSMISSION PLAN 2011-2020 Transmission and Substation Engineering Department August 15, 2011 TABLE OF CONTENTS EXECUTIVE SUMMARY Page i I. OVERVIEW 1 A. Factors Affecting the Long Range Transmission

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Maine Public Service Reliability Solutions Update

Maine Public Service Reliability Solutions Update Maine Public Service Reliability Solutions Update Presentation at the Planning Advisory Group 9/17/13 MPS Reliability Solutions Study Review of Previous PAG Updates RLC completed assessment of existing

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

System Operating Limit Definition and Exceedance Clarification

System Operating Limit Definition and Exceedance Clarification System Operating Limit Definition and Exceedance Clarification The NERC-defined term System Operating Limit (SOL) is used extensively in the NERC Reliability Standards; however, there is much confusion

More information

AC Transmission Cases: Updated Powerflow Analysis

AC Transmission Cases: Updated Powerflow Analysis AC Transmission Cases: Updated Powerflow Analysis Zach Smith Director - Transmission Planning New York Independent System Operator New York State Public Service Commission AC Transmission Technical Conference

More information

FOUR TOTAL TRANSFER CAPABILITY. 4.1 Total transfer capability CHAPTER

FOUR TOTAL TRANSFER CAPABILITY. 4.1 Total transfer capability CHAPTER CHAPTER FOUR TOTAL TRANSFER CAPABILITY R structuring of power system aims at involving the private power producers in the system to supply power. The restructured electric power industry is characterized

More information

VAR Voltage and Reactive Control. A. Introduction

VAR Voltage and Reactive Control. A. Introduction VAR-001-5 Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-5 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are

More information

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION ATTACHMENT - AESO FUNCTIONAL SPECIFICATION Functional Specification Revision History Revision Description of Revision By Date D1 For internal Comments Yaoyu Huang January 8, 2018 D2 For external Comments

More information

CONSOLIDATED EDISON CO. OF NEW YORK, INC 4 IRVING PLACE NEW YORK, N.Y

CONSOLIDATED EDISON CO. OF NEW YORK, INC 4 IRVING PLACE NEW YORK, N.Y CONSOLIDATED EDISON CO. OF NEW YORK, INC 4 IRVING PLACE NEW YORK, N.Y. 10003 EP 7000 5 JULY 2009 VOLTAGE SCHEDULE, CONTROL, AND OPERATION OF THE TRANSMISSION SYSTEM PURPOSE This specification describes

More information

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE)

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE) COORDONNATEUR DE LA FIABILITÉ Direction Contrôle des mouvements d énergie Demande R-3944-2015 NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE) Original : 2016-10-14 HQCMÉ-10, Document 2 (En liasse) Standard

More information

Kansas City Power & Light Company. Transmission Facility Rating Methodology

Kansas City Power & Light Company. Transmission Facility Rating Methodology Company Prepared by: KCP&L Transmission Planning December 6, 2017 Table of Contents 1. Purpose...4 2. Generator Rating Methodology...4 3....4 3.1. Equipment Rating Methodology...4 3.2. Items considered

More information

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria ReliabilityFirst Regional Criteria 1 Disturbance Monitoring and Reporting Criteria 1 A ReliabilityFirst Board of Directors approved good utility practice document which are not reliability standards. ReliabilityFirst

More information

ROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT

ROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT ROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT Page 1 of 8 The document describes the current methodology used for developing facility ratings

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

VAR Voltage and Reactive Control

VAR Voltage and Reactive Control VAR-001-4 Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-4 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are

More information

A. Introduction. VAR Voltage and Reactive Control

A. Introduction. VAR Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-4.2 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are monitored, controlled, and maintained

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities at a level to prevent unnecessary tripping

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 PRC-025-1 Generator Relay Loadability A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities

More information

Available Transfer Capability (ATC) EE 521 Analysis of Power Systems Chen-Ching Liu Washington State University

Available Transfer Capability (ATC) EE 521 Analysis of Power Systems Chen-Ching Liu Washington State University Available Transfer Capability (ATC) EE 521 Analysis of Power Systems Chen-Ching Liu Washington State University i Available Transfer Capability (ATC) ATC measures the residual transfer capability in the

More information

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24 RC0120A - RC IRO-010 Data Specification NOTE: Changes from Peak's Attachment A are highlighted in red in columns C through G Section Category Number Responsible Pa Data Item Data Transfer Method 1.1 Transmission

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision By Date V1D1 For Comments Yaoyu Huang October 27, 2016 V1 For Issuance Yaoyu Huang November 21, 2016 Section 5.3 updated Transformer

More information

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements NPCC Regional Reliability Reference Directory # 12 Under frequency Load Shedding Program Requirements Task Force on System Studies Revision Review Record: June 26 th, 2009 March 3 rd, 2010 Adopted by the

More information

PRC Disturbance Monitoring and Reporting Requirements

PRC Disturbance Monitoring and Reporting Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

MCPS North/Central Need Identification

MCPS North/Central Need Identification MCPS North/Central Need Identification Economic Planning Users Group Meeting 12/11/2015 Transmission Need Identification Need Identification Congestion Analysis Identify Top Congested Flowgates Identified

More information

Dairyland Power Cooperative June Transmission to Transmission (T-T) Interconnection Guidelines

Dairyland Power Cooperative June Transmission to Transmission (T-T) Interconnection Guidelines Transmission to Transmission Interconnection Guidelines for the Dairyland Power Cooperative Transmission System (new interconnections or materially modified existing interconnections) Dairyland Power Cooperative

More information

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team. December 7 th, 2010 NPCC Full Member Committee; Please find attached a draft revised NPCC Regional Reliability Directory #12 Underfrequency Load Shedding Program Requirements and a draft revised NPCC UFLS

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the Board of Trustees. Description

More information

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Industry Webinar Reactive Power Planning NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Webinar Topics Reliability Guideline on Reactive Power Planning Webinar Topics Fundamentals of

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Applicability 1 Section 502.8 applies to: (a) the legal owner of a generating unit: (i) connected to the transmission facilities in the balancing authority area

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION North American Electric Reliability Corporation ) ) Docket No. PETITION OF THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION FOR

More information

Stability Issues of Smart Grid Transmission Line Switching

Stability Issues of Smart Grid Transmission Line Switching Preprints of the 19th World Congress The International Federation of Automatic Control Stability Issues of Smart Grid Transmission Line Switching Garng. M. Huang * W. Wang* Jun An** *Texas A&M University,

More information

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination Phase Distance (21) and Voltage-Controlled or Voltage-Restrained Overcurrent Protection (51V) NERC Protection Coordination Webinar Series June

More information

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

Northeast Power Coordinating Council, Inc. Glossary of Terms. Approved by the Reliability Standards Committee

Northeast Power Coordinating Council, Inc. Glossary of Terms. Approved by the Reliability Standards Committee Northeast Power Coordinating Council, Inc. Glossary of Terms Approved by the Reliability Standards Committee October 26, 2011 Revision History Version Date Action Change Tracking (New, Errata or Revisions)

More information

Transmission Availability Data System Phase II Final Report

Transmission Availability Data System Phase II Final Report Transmission Availability Data System Phase II Final Report Prepared by the Transmission Availability Data System Task Force for the NERC Planning Committee Approved by the Planning Committee on: Table

More information

Tampa Electric Company Facility Rating Methodology Approved 11/20/2018

Tampa Electric Company Facility Rating Methodology Approved 11/20/2018 Tampa Electric Company Facility Rating Methodology Approved 11/20/2018 Effective Date: 12/01/2018 Responsible Department: System Planning Review Cycle: 3 Years Last Date Reviewed: 11/16/2018 Next Planned

More information

Table 1 - Assignment of BA Obligations... 8

Table 1 - Assignment of BA Obligations... 8 Dynamic Transfer Reference Guidelines Version 2 June 2010 Table of Contents Table of Contents Chapter 1 Overview... 3 Purpose... 3 Terms... 3 Chapter 2 Dynamic Schedule Versus Pseudo-tie Fundamentals...

More information

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS S1. Standard Interconnection Methods with Typical Circuit Configuration for Single or Multiple Units Note: The protection requirements

More information

Transmission to Distribution/ End-User Interconnection Guidelines for the Dairyland Power Cooperative Transmission System

Transmission to Distribution/ End-User Interconnection Guidelines for the Dairyland Power Cooperative Transmission System Transmission to Distribution/ End-User Interconnection Guidelines for the Dairyland Power Cooperative Transmission System Dairyland Power Cooperative December 2014 Transmission to Distribution/ End-User

More information

COS MANUAL. March 24, Version 1.2. Outage Coordination Process. Peak Reliability. Version 1.0. NERC Reliability Standard IRO-017-1

COS MANUAL. March 24, Version 1.2. Outage Coordination Process. Peak Reliability. Version 1.0. NERC Reliability Standard IRO-017-1 Outage Coordination Process Version 1.0 NERC Reliability Standard IRO-017-1 COS MANUAL March 24, 2017 www.peakrc.com. Contents 1. Conventions... 2 2. Introduction... 2 3. Purpose... 2 4. Applicability...

More information

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document Bulk Electric System Definition Reference Document JanuaryVersion 2 April 2014 This technical reference was created by the Definition of Bulk Electric System drafting team to assist entities in applying

More information

Transmission Facilities Rating Methodology for Florida

Transmission Facilities Rating Methodology for Florida Document title Transmission Facilities Rating Methodology for Florida Document number EGR-TRMF-00001 Applies to: Transmission Engineering, Transmission System Operations, and Transmission Planning Duke

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System HOOSIER ENERGY REC, INC Requirements for Connection of Generation Facilities to the HE Transmission System January 2009 Table of Contents 1.0 INTRODUCTION...1 2.0 TYPES OF CONNECTED CIRCUIT CONFIGURATIONS...6

More information

Transmission System Phase Backup Protection

Transmission System Phase Backup Protection Reliability Guideline Transmission System Phase Backup Protection NERC System Protection and Control Subcommittee Draft for Planning Committee Approval June 2011 Table of Contents 1. Introduction and Need

More information

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels

More information

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document Bulk Electric System Definition Reference Document January, 2014 This draft reference document is posted for stakeholder comments prior to being finalized to support implementation of the Phase 2 Bulk

More information

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in A. Introduction 1. Title: Transmission Relay Loadability 2. Number: PRC-023-3 3. Purpose: Protective relay settings shall not limit transmission loadability; not interfere with system operators ability

More information

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4 MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS July 2016 Version 4 This page intentionally blank LEGISLATIVE AUTHORITY Section 15.0.3(1) of The Manitoba Hydro Act (C.C.S.M. c. H190) authorizes

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Requirements Applicability 1 Subject to subsections 2 and 3 below, section 502.8 applies to: (a) (c) (d) the legal owner of a generating unit or an aggregated

More information

August 25, 2017 VIA ELECTRONIC FILING

August 25, 2017 VIA ELECTRONIC FILING !! August 25, 2017 VIA ELECTRONIC FILING Kirsten Walli, Board Secretary Ontario Energy Board P.O Box 2319 2300 Yonge Street Toronto, Ontario, Canada M4P 1E4 Re: North American Electric Reliability Corporation

More information

Geoff Brown & Associates Ltd

Geoff Brown & Associates Ltd Geoff Brown & Associates Ltd REVIEW OF WESTERN POWER S APPLICATION FOR A TECHNICAL RULES EXEMPTION FOR NEWMONT MINING SERVICES Prepared for ECONOMIC REGULATION AUTHORITY Final 20 August 2015 Report prepared

More information

Artificial Island Proposal Window

Artificial Island Proposal Window Artificial Island Proposal Window PJM TEAC Artificial Island Recommendation 6/16/2014 Artificial Island Timeline Past Timeline 9/13/2012 PJM discusses the trending Artificial Island operational issues

More information

Brianna Swenson Alliant Energy Minnesota Power Systems Conference November 8, 2017

Brianna Swenson Alliant Energy Minnesota Power Systems Conference November 8, 2017 Brianna Swenson Alliant Energy Minnesota Power Systems Conference November 8, 2017 Topics Brief history of interties and regulations Who is involved? What exactly are we doing? Why is it important? Project

More information

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D Electricity Ten Year Statement November 2017 01 Electricity Ten Year Statement November 2017 001 Appendix D 1 Short-circuit currents 02 2 Short-circuit current terminology 04 3 Data requirements 07 4 Fault

More information

Final ballot January BOT adoption February 2015

Final ballot January BOT adoption February 2015 Standard PRC-024-21(X) Generator Frequency and Voltage Protective Relay Settings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

Effect of Topology Control on System Reliability: TVA Test Case

Effect of Topology Control on System Reliability: TVA Test Case 21, rue d Artois, F-758 PARIS CIGRE US National Committee http : //www.cigre.org 214 Grid of the Future Symposium Effect of Topology Control on System Reliability: TVA Test Case X. LI P. BALASUBRAMANIAN

More information

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics: A. Introduction 1. Title: Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions 2. Number: MOD-027-1 3. Purpose: To verify that the turbine/governor

More information

Cover Sheet. Technical Justification Retirement of WECC Regional Reliability Standard VAR-002-WECC-2 Automatic Voltage Regulators (AVR)

Cover Sheet. Technical Justification Retirement of WECC Regional Reliability Standard VAR-002-WECC-2 Automatic Voltage Regulators (AVR) Cover Sheet Attachment G (AVR) Retirement of WECC Regional Reliability Standard VAR-002-WECC-2 (AVR) Page 1 of 23 Request to Retire White Paper Retirement of WECC Regional Reliability Standard VAR-002-WECC-2

More information

Agenda Notes for 4 th Meeting of Sub Group in respect of Preparation of Reliability Standards for Protection System and Communication System

Agenda Notes for 4 th Meeting of Sub Group in respect of Preparation of Reliability Standards for Protection System and Communication System Agenda Notes for 4 th Meeting of Sub Group in respect of Preparation of Reliability Standards for Protection System and Communication System Meeting Date: 27.03.2017 Time: 1430 Hrs Venue: NRPC Conference

More information

CHAPTER ELECTRIC AND MAGNETIC FIELDS

CHAPTER ELECTRIC AND MAGNETIC FIELDS CHAPTER 62-814 ELECTRIC AND MAGNETIC FIELDS 62-814.100 Intent, Findings, Basis of Standards, and Research Needs 62-814.200 Electric and Magnetic Fields; Definitions 62-814.300 General Technical Requirements

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

System Impact Study PID MW Plant

System Impact Study PID MW Plant System Impact Study PID 233 150MW Plant Prepared by: Southwest Power Pool Independent Coordinator of Transmission 415 N. McKinley, Suite140 Little Rock, AR 72205 Rev Issue Date Description of Revision

More information

Generation Interconnection Guidelines for the Dairyland Power Cooperative Transmission System

Generation Interconnection Guidelines for the Dairyland Power Cooperative Transmission System Generation Interconnection Guidelines for the Dairyland Power Cooperative Transmission System December 2014 Dairyland Power Cooperative 3200 East Avenue South, P. O. Box 817 La Crosse, WI 54602-0817 DAIRYLAND

More information

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2 MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS April 2009 Version 2 LEGISLATIVE AUTHORITY Section 15(5) of The Manitoba Hydro Act authorizes Manitoba Hydro to set, coordinate and enforce

More information

August 25, Please contact the undersigned if you have any questions concerning this filing.

August 25, Please contact the undersigned if you have any questions concerning this filing. !! August 25, 2017 VIA ELECTRONIC FILING Ms. Erica Hamilton, Commission Secretary British Columbia Utilities Commission Box 250, 900 Howe Street Sixth Floor Vancouver, B.C. V6Z 2N3 Re: North American Electric

More information

Appendix D Fault Levels

Appendix D Fault Levels Appendix D Fault Levels Page 1 Electricity Ten Year Statement November 2013 D.1 Short Circuit Currents Short Circuit Currents Three phase to earth and single phase to earth short circuit current analyses

More information

Integration of Wind Generation into Weak Grids

Integration of Wind Generation into Weak Grids Integration of Wind Generation into Weak Grids Jason MacDowell GE Energy Consulting NERC ERSTF Atlanta, GA December 10-11, 2014 Outline Conventional and Power Electronic (PE) Sources Stability limitations

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events TPL-007-1 Transmission System Planned Performance for Geomagnetic Disturbance Events Stan Sliwa Transmission Planning RSCS Meeting May 18, 2017 www.pjm.com TPL-007-1 Purpose: Establish requirements for

More information

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document Bulk Electric System Definition Reference Document Version 2 April 2014 This technical reference was created by the Definition of Bulk Electric System drafting team to assist entities in applying the definition.

More information

Transmission Facilities Rating Methodology

Transmission Facilities Rating Methodology Document title Transmission Facilities Rating Methodology Document number EGR-TRMC-00009 Applies to: Transmission Engineering, Transmission System Operations, and Transmission Planning- Progress Energy

More information

Western New York Transmission Constraints

Western New York Transmission Constraints Western New York Transmission Constraints Wes Yeomans Vice President Operations Market Issues Working Group Rensselaer, NY August 4, 2016 2000-2016 New York Independent System Operator, Inc. All Rights

More information

A Comprehensive Approach for Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique

A Comprehensive Approach for Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique A Comprehensive Approach Sub-Synchronous Resonance Screening Analysis Using Frequency scanning Technique Mahmoud Elfayoumy 1, Member, IEEE, and Carlos Grande Moran 2, Senior Member, IEEE Abstract: The

More information

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Unit Auxiliary Transformer (UAT) Relay Loadability Report Background and Objective Reliability Standard, PRC 025 1 Generator Relay Loadability (standard), developed under NERC Project 2010 13.2 Phase 2 of Relay Loadability: Generation, was adopted by the NERC

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee March 9, 2017 2016/17 RTEP Long Term Proposal Window 2 2016/17 RTEP Long Term Proposal Window Timeline Window Opened: 11/1/2016 Window

More information